1 738 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 2, JUNE 2012 Utilizing a Smart Grid Monitoring System to Improve Voltage Quality of Customers Kerry D. McBee, Member, IEEE, and Marcelo G. Simões, Senior Member, IEEE Abstract The implementation of smart grids will fundamentally change the approach of assessing and mitigating system voltage deficiencies on an electric distribution system. Many distribution companies have historically identified customer level voltage deficiencies utilizing a reactive approach that relies upon customer complaints. The monitoring capabilities of a smart grid will allow utilities to proactively identify events that exceed the voltage threshold limitations set forth by ANSI Std. C84.1 before they become a concern to end-users. This proactive approach can reduce customer complaints and possibly operational costs. This paper describes an approach for determining voltage threshold limits as a function of duration for proactive voltage investigations utilizing smart grid monitoring equipment. The described approach was applied to a smart grid located in Boulder, Colorado. This paper also describes the results of this two-year study. Index Terms Customer complaints, operational costs, power quality, smart grid, smart meter, voltage quality. I. INTRODUCTION T HE Department of Energy (DOE) envisions a smart grid as a distribution system that consists of an extensive monitoring system [1]. Such a system allows for the monitoring of attributes such as voltage, current, kwh, and kva at substations transformers, distribution transformers, smart meters, distribution switching devices, and strategically installed power quality monitors. The number of system monitors on a smart grid is considerably more than the number found on existing distribution systems, which may only have several power quality monitors per feeder even if installed in accordance with the EPRI recommendations for monitoring feeder level power quality events [2]. Prior to the implementation of smart grids, EPRI recommended the installation of power quality monitors at the substation, middle of the feeder, end of the feeder, and near customers with sensitive loads. Unfortunately many electric distribution systems in use today fall short of even these EPRI recommendations by focusing most power quality efforts at the substation transformer. This lack of monitoring at the distribution level allows many voltage events that occur on distribution feeders or on the secondary side of distribution transformers Manuscript received May 30, 2011; revised October 08, 2011; accepted December 11, Date of publication April 27, 2012; date of current version May 21, Paper no. TSG K. D. McBee is with the Colorado School of Mines, Golden, CO USA, and also with Xcel Energy, Denver, CO USA ( kerry.d. mcbee@xcelenergy.com). M. G. Simões is with the Department of Engineering at Colorado School of Mines, Golden, CO ( msimoes@mined.edu). Color versions of one or more of the figures in this paper are available online at Digital Object Identifier /TSG to go unnoticed. In most cases the only notification the utility has of a voltage discrepancy comes from customers who are experiencing discomfort and/or equipment malfunction. The implementation of a smart grid monitoring system allows utility personnel to perform remote voltage investigations as soon as voltage events occur and before problems occur for customers. These investigations can be performed at the feeder level and at the customer s point of common coupling (PCC), which is important when investigating customer power quality issues [1], [3]. All devices that sense voltage, even if they do not possess power quality monitoring accuracy, are available to utilize for identifying voltage fluctuations that are damaging to customer equipment and/or reduce the quality of service for customers. A smart grid monitoring system consists of a main communication system that connects all devices with remote monitoring capabilities, utility and end-user owned, to a central data collection location which simplifies access to all data retrieved [4]. The aggregate number of these devices can account for hundreds of monitoring points per feeder depending upon design and customer penetration. Remote monitoring devices include: capacitor banks; distribution transformers; smart meters; power quality meters; phase monitoring units. Remote monitoring will allow for the identification of voltage deviations prior to equipment malfunction or misoperation that are noticeable to customers. Also, system deficiencies that have gone unnoticed by customers and utility personnel prior to the installation of a monitoring system will become evident. Four benefits to implementing a remote voltage investigation approach include the following: reduced number of customer voltage complaints; lowered operational costs associated with investigating customer voltage problems; reduced number of outages caused by failed connections; prevention of damage to utility or customer equipment. Historically customers have been the main source of identifying voltage discrepancies. The goal of a proactive approach is to identify problems before they become a concern to customers, therefore a new notification system is required. A smart grid can employ numerous software applications to interface with, interpret measurements from, and control distribution system devices. This type of software can provide automatic notification to utility personnel of voltage sags, swells, and other voltage events prior to them becoming a nuisance or problem to customers. Because many voltage events are temporary in nature, /$ IEEE

2 MCBEE AND SIMÕES: UTILIZING A SMART GRID MONITORING SYSTEM TO IMPROVE VOLTAGE QUALITY OF CUSTOMERS 739 anddonotwarrantfield investigations, threshold limits that include magnitude and time durations should be employed to insure the effectiveness of a proactive voltage investigation program. This paper examines how to establish threshold limits for the duration and magnitude of voltage events. Section II details both the existing reactive approach and the proposed proactive approach. Upper and lower threshold limits are detailed in this section along with an approach for determining duration threshold levels. To determine the effectiveness of the proactive approach and the methods described for determining thresholds limits, the methodology was applied to a smart grid located in Boulder, Colorado and operated by Xcel Energy. The Boulder smart grid, commonly referred to as SmartGridCity, consists of 26 feeders that serve approximately customers. At the time of this research, its smart grid monitoring system consisted of over smart meters and 5000 sensors installed on distribution transformers, both of which provide real time voltage readings. The results of applying the proactive approach to this smart grid along with an evaluation of the customer and economic benefits are detailed in Section IV. II. REACTIVE VERSUS PROACTIVE APPROACH TO INVESTIGATIONS A. Reactive Approach to Investigations In the past, most voltage quality investigations performed by distribution companies have been the result of customer complaints. This paper categorizes this approach of identifying and mitigating such problems as a reactive approach. The general reactive approach is described below. A utility company is notified by a customer that equipment is malfunctioning due to suspected voltage fluctuations, which are identified by customer equipment failure and dimming or flickering lights. Customers may also hire an engineering firm to investigate problems prior to notifying the utility. Although informative, a distribution company never wants to rely exclusively on a report provided by a customer s investigator due to the unknowns associated with their monitoring techniques, specifically in regards to the IEEE std [3]. Utility field personnel, many times in the form of a lineman, aredispatchedtoobtaininstantaneous readings and/or to identify the severity of the voltage fluctuations. If instantaneous readings do not suggest a problem, the utility company may choose to install power quality recording devices at the customer s PCC, within the customer s facility, and possibly at several locations along the circuit serving the customer in accordance with [3]. Voltage readings are recorded for a given time period, which is dictated by the frequency of the disturbances [3]. Many times the duration of recordings are limited by the small number of power quality recorders and the high volume of investigations. For events that are infrequent, this situation leads to investigations that are not thorough. This is rarely the case with a smart grid investigation since information is provided for days, weeks, and months. Power quality investigators analyze the recorded data to determine if the voltage fluctuations violate the threshold limitations set forth by ANSI Std. C84.1 and possibly a local regulatory agency [5]. If it is found that threshold limits are exceeded, the utility company will act to mitigate the problem. If it is found that the deviation is due to customer equipment, it is the customer s responsibility to mitigate the problem. The action taken by the distribution company is heavily dependent upon two things: 1) exceeding limits set by ANSI Std. C84.1 and/or tariffs set forth by local regulatory agencies; 2) a customer complaint regarding poor service. Utilizing both known standards and customer complaints has proven to be a very reliable approach for mitigating voltage quality problems in the past. However, a smart grid monitoring system can remove customers as the notification system and thereby improve customer service. B. Proactive Approach to Investigations The increased monitoring capabilities of a smart grid will allow for the identification of voltage quality problems at the same time as the customer, or before the customer experiences any significant equipment malfunctions or misoperations. This proactive approach will eliminate the customer as a means of identifying system deficiencies, which will leave the utility engineer with only the known standards and regulatory tariffs as a guide for determining system deficiencies. The authors have chosen to refer to voltage, current, and frequency fluctuations found through a smart grid monitoring system as deficiencies and not power quality events. Most definitions of power quality include the powering and grounding of equipment that is appropriate for normal operation [3], [6], [7]. Since customers are removed from the investigation, there is no evidence that equipment has malfunctioned or misoperated. Therefore the incentive of the utility company is not to improve power quality for customers, but to reduce and eliminate system deficiencies that are inefficient and may result in customer and/or utility equipment failure if not addressed. The elimination of customers as a means for voltage problem identification also presents a problem to the utility company. Which voltage deficiencies are investigated to minimize customer impact and optimize operational efficiency? Should a utility company investigate every voltage deficiency, even if its duration is only several cycles and only occurs once? The proactive approach to system monitoring should rely heavily upon voltage thresholds setforthbyansistd.c84.1 and local regulatory agencies. Std. C84.1 was developed for the purpose of protecting equipment from experiencing damaging voltages; therefore utilizing these thresholds provides protection for customer and utility equipment [5]. The standard defines two voltage ranges that are applicable for utility service and the utilization of end-user equipment above and below 600 V. Range A, which describes acceptable voltage ranges for steady state operations, provides the most conservative approach to investigations since these limits are the most stringent and will thereby identify more system deficiencies. For residential customers at 120 V the upper and lower limit is, which is more stringent than the minimum variation limits that define voltage sags and voltage swells [3]. Range B accounts for voltages that result from abnormal, but necessary operating conditions. Table I illustrates Range A of ANSI Std. C841 [5].

3 740 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 2, JUNE 2012 TABLE I ANSI STD. C RANGE AACCEPTABLE VOLTAGE LEVELS Voltage threshold limits are applied according to the location of the device that is being monitored. If the reading is taken at a smart meter, the service voltage limits should fall within the limits set by Range A of B. However, if the voltage is monitored at the distribution transformer, the lower limit should reflect at least a 2 3 V drop on the service conductors, which would result in a lower limit of V on systems below 600 V. Any violation of these limits, regardless of duration, is considered a voltage deficiency, which by definition includes more events than if only voltage sags and swells were considered. The smart grid monitoring system should interface with software that automatically notifies utility engineers when voltage deficiencies occur. Upon notification, the utility must determine if the event was temporary in nature or is the result of system deficiencies, with the latter type of events being investigated further. These system deficiencies are continuous in nature and will not remedy themselves. Evaluation of continuous events should include summing the duration of all voltage events that occur in a given time period. Temporary faults, which can be the cause of voltage events, can comprise as much as 76% 80% of all system faults on system [8] [10]. Most customer complaints are the result of long-term voltage problems, not those caused by temporary events. The aggregate time below or above the magnitude threshold is utilized to distinguish between temporary events and events that are consistent, but possibly infrequent. Any violation that deviates below or under the set magnitude threshold for an accumulated time of for a given period is investigated in further detail. The concept is illustrates mathematically in (1) and graphically in Fig. 1. where: total time duration above or below threshold limits for time period ; time duration of event in time period ; total number of different events where voltage thresholds are exceeded; investigation duration, typically a day, week, or month. (1) Fig. 1. Investigation envelope graph illustrating different investigation zones for events based on total time below or above threshold. Investigation zones are defined utilizing high and low threshold limits and. Voltage events that have aggregate time less than and fall into Zone 1 of Fig. 1 are considered temporary in nature and are not investigated any further. The time duration of this zone, which is defined by, should be based upon customer type. Customers more susceptible to voltage sags and swells, such hospitals and commercial or industrial facilities with critical processes could arrange an agreement with the Utility to have a that is satisfactory to capture repeated voltage sags and swells. Zone 2 consists of voltage levels that are acceptable. Therefore, the only voltages deficiencies investigated are those that fall into Zones 3 and 4, which are undervoltage and overvoltage zones. can range from a day, week, to a month, depending upon the desired level of investigation. III. APPLICATION OF PROACTIVE APPROACH The proactive investigation approach was applied to a smart grid located in Boulder, Colorado and operated by Xcel Energy, an electric utility company that generates, transmits, and distributes energy in eight states. At the time of the analysis, the smart grid consisted of 26 circuits served by 4 substations. The smart grid served over customers with its smart meters and 5000 voltage sensors installed on distribution transformers, both of which provided real time voltage and kwh readings. The system, which also utilizes self healing automation, went online in August of 2008, which coincided with the start of proactive investigations. The software utilized for interpreting smart meter and distribution transformer data was OpenGrid Distribution (OGD), which is manufactured by the Current Group. The authors utilized the software and the guidelines described in the previous section to proactively investigate voltage discrepancies that exceeded the voltage investigation envelope illustrated in Fig. 1. Upon the proactive identification of voltage problems, utility field personnel were dispatched to verify problems and to evaluate if mitigation actions were required. The magnitude threshold limits utilized for the study were based on Std. C84.1 Range A, but did not follow them exactly. A lower threshold limit of 117 V was utilized for sensors at distribution transformers, which can have a voltage that is 2 3 V higher than the voltage at the customers meter. The upper limit was not adjusted to account for secondary voltage drop so as

4 MCBEE AND SIMÕES: UTILIZING A SMART GRID MONITORING SYSTEM TO IMPROVE VOLTAGE QUALITY OF CUSTOMERS 741 Fig. 2. Voltage profile of 50 kva transformer with a loose neutral connection as provided by Open Grid Distribution software. not to exceed 126 V for situations where the secondary voltage drop is less than 2 V. The total duration for events was set at 30 min (0.5 h). The period of 96 h was utilized as. Investigations included researching any system event that fell into Zones 3 and 4. Problems found included: low voltage due to overloaded transformers; high and low continuous voltage due to loose neutral connections; intermittent high and low voltage due to loose conductor connectors; low voltage as a result of system reconfiguration due to outage restoration and new construction; high and low voltage due to failed distribution transformer windings. The software provided the authors with visual graphs of voltage events, which simplified the identification of violations of the voltage investigation envelope. A loose neutral connection was identified in Fig. 2, which illustrates the separation of voltage between the two transformer secondary conductors (LEG 1 and LEG2). A distribution transformer overload, which is illustrated in Fig. 3, was verified as being caused by a new customer connecting to the distribution transformer. Fig. 4 illustrates the identification of high voltage that was the result of a malfunctioning substation transformer load tap changer. Because the voltage problem found in Fig. 4 was caused by a substation device, the majority of the transformer sensors and smart meters recorded the same excessive voltage, which simplified the identification of the cause. Events such as overloaded transformers, loose connections, and failing transformers are not self-correcting over time; in fact they would most likely become progressively worse due to the nature of electrical equipment failures. Therefore, the utility company can pay for repairs before it affects customers or after. Waiting to mitigate problems can possibly be more expensive if the system deficiency results in utility or customer equipment damage, or a catastrophic failure occurs outside of normal business hours, thereby resulting in utility personnel working overtime and possibly requiring the emergency shipment of equipment. The results of the study revealed that investigation zones accurately captured problems that would eventually lead to cus- Fig. 3. Voltage profile of an overloaded 50 kva transformer as provided by Open Grid Distribution software. Fig. 4. Voltage profile of a 50 kva transformer with high primary side voltage, as provided by OpenGrid Distribution software. tomer complaints. A total of 45 voltage discrepancies were identified between August 2008 and December Fig. 5 illustrates the voltage problems identified, where they fell on the investigation envelope graph, and if the problems required equipment repair or upgrade (Action Required) or if they were due to abnormal operating conditions or were temporary in nature (No Action), which did not warrant mitigation. From these results, a more refined investigation envelope graph was developed, which is also illustrated in Fig. 5. Prior to implementation of the smart grid monitoring system, Xcel Energy regularly experienced voltage complaints in excess of 20 per year in the smart grid territory, with a peak of 50 complaints occurring in In 2009 and 2010, which were the first two complete years of implementation, 5 and 7 voltage complaints were recorded in the SmartGridCity territory. Fig. 6 illustrates the voltage complaints by year for the smart grid territory. It should be noted that the complaints recorded in 2009 and 2010 where not caused by voltage deficiencies. Customers requested investigations because of equipment misoperations; however, in each case the cause was determined to be due to customer owned equipment. Because of these types of

5 742 IEEE TRANSACTIONS ON SMART GRID, VOL. 3, NO. 2, JUNE 2012 TABLE II FIVE-YEAR SUMMARY OF VOLTAGE COMPLAINTS Fig. 5. period. Graph of all voltage deficiencies identified during 28-month analysis TABLE III COSTS AFFILIATED WITH VOLTAGE EVENTS 8/1/08 12/31/10 Fig. 6. Voltage complaints between 2004 and 2010 in SmartGridCity footprint. occurrences, voltage complaints may never go to zero in the SmartGridCity territory. Proactive investigations reduced the number of customer complaints, which are illustrated in Fig. 6, but did not reduce the number of voltage investigations. Complaints and proactive investigations were combined to determine the percentage of investigation performed within the SmartGridCity territory to those occurring outside of the smart grid territory. Between 2006 and 2010, the percentage of investigation performed in the smart grid territory, including both reactive and proactive investigations, ranged between 8.72% and 5.08%, with the latter occurring in Although the percentage decreased with time, as evident from Table II, the authors believe that the slight deviation is possibly the result of annual fluctuations in load, weather, and system constraints. Although the number of investigations did not decrease, the cost associated with investigating voltage deficiencies proactively did decrease. The total cost savings for 2009 and 2010 were calculated based on investigation costs. Specifically, the costs of remote investigations were compared to the costs of performing the same investigations utilizing the reactive approach to voltage investigations, which utilizes lineman and/or field visits by power quality investigators. Between 2006 and 2008, a lineman was initially dispatched for 36% of the investigations. The average cost of a lineman per investigation was $120, which included a single lineman, bucket extension truck, travel time, and investigation time. On-site power quality investigations were assumed to include a power quality investigator, recording equipment, recording equipment installation time, one week of data monitoring, and at least a day of data processing and analysis totaling an average operational cost of $520 per investigation. Smart grid investigations averaged no more than 2 h, which include office and field work. The authors, who are experienced in power quality investigations, performed the remote investigations; therefore the only requirement was 1 h of training on OGD, the software utilized to interpret smart meter and distribution transformer sensor measurements. The proactive investigations consisted of two actions. First, the authors identified a voltage problem with OGD, which took approximately 5 min with the automatic system notification. Once identified, the authors determined if field validation was required. A lineman was dispatched for 84% of the identified voltage events to validate and excess the problem. The average time spent on a remote investigation by the authors was 5 20 min, at an average cost of $14 per investigation. Based on the 45 problems identified during the 16-month period, the total cost of remote investigations was estimated to be approximately $5190. Applying the same 45 voltage problems to the reactive investigation costs described in the previous paragraph would result in a monetary

6 MCBEE AND SIMÕES: UTILIZING A SMART GRID MONITORING SYSTEM TO IMPROVE VOLTAGE QUALITY OF CUSTOMERS 743 impact of $25 320, an increase of $ or 487% from the cost of proactive investigations. Table III summaries the costs associated with both proactive and reactive investigations for the 45 voltage events identified. Even if the proactive approach resulted in more voltage event investigations than if the utility relied exclusively upon customer complaints, a success rate of 20% for proactive investigations would still be less costly than relying exclusive upon a reactive approach. The cost of implementation is not considered in the economic evaluation presented in this paper. Because of the many functionalities of the equipment utilized for proactive voltage investigations, comparing implementation costs to voltage investigation benefits would be inaccurate and misleading. Additional functions of the equipment utilized includes automated meter reading, feeder voltage and var optimization that reduces system losses, transformer loss management, outage notification, and the identification of nested outages during storm outages restoration efforts. IV. CONCLUSION The extensive monitoring system of a smart grid will allow distribution companies to proactively investigate system voltage deficiencies. Without customers acting as a notification system, distribution companies can rely upon ANSI Std. C84.1 and local tariffs in conjunction with predetermined duration thresholds to determine if a potential voltage problem exists. The case study presented in this paper illustrated that utilizing a 30-min duration for a 96-h window of monitoring is sufficient for reducing customer voltage complaints. Although complaints were reduced with a proactive approach to investigations, the total number of investigations or voltage events investigated did not decrease. However, the costs associated with voltage investigations were significantly reduced when compared to utilizing the existing reactive approach. REFERENCES [1] Title XIII, Department of Energy [Online]. Available: energy.gov/documentsandmedia/eisa_title_xiii_smart_grid.pdf [2] M. Baran and K. Scherrer, Extending power quality monitoring to feeder level, in Proc. IEEE Power Energy Soc. Gen. Meet. Convers. Del. Electr. Energy 21st Century, Jul [3] IEEE Recommended Practice for Monitoring Electric Power Quality, IEEE Standard [4] R. E. Brown, Impact of smart grid on distribution system design, in Proc. IEEE Power Energy Soc. Gen. Meet. Convers. Del. Electr. Energy 21st Century, Jul [5] American National Standard for Electric Power Systems and Equipment Voltage Ratings (60 Hertz), ANSI Standard C [6] IEEE Recommended Practice For Powering and Grounding Electronic Equipment, IEEE Standard [7] R. Dugan, M. McGranaghan, and H. Beaty, Electrical Power Systems Power Quality. New York: McGraw-Hill, 1996, p. 2. [8] S. F. Tan and S. K. Salman, Investigation into the implementation of auto reclosing scheme in distribution networks with high penetration of DGs, in Proc. 43rd Int. Univ. Power Eng. Conf., Sep [9] O. Jung-Hwan, Y. Sang-Yun, K. Jae-Chul, and K. Eung-Sang, Particular characteristics associated with temporary and permanent fault on the mult-shot reclosing scheme, in Proc. IEEE Power Eng. Soc. Summer Meet., Jul. 2010, vol. 1, pp [10] D. E. Parrish, Lightning-caused distribution circuit breaker operations, IEEE Trans. Power Del., no. 4, pp , Oct Kerry D. McBee (BS 99 MS 00) received the B.Sc. degree from the Colorado School of Mines, Golden, in 1999 and the M.Sc. degree in electric power engineering from Rensselaer Polytechnic Institute, Troy, NY, in He is currently working toward the Ph.D. degree in the Department of Engineering, Colorado School of Mines. During his career he has focused on power quality, reliability, forensic engineering, and distribution design for companies such as NEI Power Engineers, Peak Power Engineering, Knott Laboratory, and Xcel Energy. His field of interest is smart grid implementation effects upon distribution engineering and utility operations. Marcelo G. Simões (S 89 M 95 SM 98) received the Ph.D. degree from the University of Tennessee, Knoxville, in He is with Department of Electrical Engineering and Computer Science, Colorado School of Mines, Golden, where he is the Director of the Center for Advanced Control of Energy and Power Systems (ACEPS). He has been conducting research and education activities in the development of intelligent control for high-power-electronics applications in renewable- and distributed energy systems and smart-grid technology. Dr. Simões is currently Past Chair for the IEEE IAS IACC and Co-Chair for the IEEE IES Smart Grid Committee. He has been involved in activities related to the control and management of smart-grid applications since 2002 with his NSF CAREER award Intelligent Based Performance Enhancement Control of Micropower Energy Systems.

AMI information. for improved outage management

AMI information. for improved outage management Utilities the way we see it AMI information for improved outage management The information contained in this document is proprietary. 2013 Capgemini. All rights reserved. Rightshore is a trademark belonging

More information

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile Michael Coddington National Renewable Energy Laboratory Golden, Colorado, U.S.A.

More information

Automating LV Distribution networks using sensor technologies

Automating LV Distribution networks using sensor technologies Automating LV Distribution networks using sensor technologies Jayant Sinha Lead Consultant (Smart Networks) Enzen Global Ltd, UK 1 Managing the last mile Growing pressure on DNOs to improve LV network

More information

ELG4126 Distributed Generation and Renewables

ELG4126 Distributed Generation and Renewables ELG4126 Distributed Generation and Renewables Case Study of Renewable Energy and Smart Grid of Three Phases Phase One: Wind Farm Conduct a feasibility study for initiating a profitable wind energy farm

More information

Technical Requirements for Distributed Generation Connection

Technical Requirements for Distributed Generation Connection Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting

More information

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network Insu Kim, Ronald G. Harley, and Raeey Regassa Georgia Institute of Technology,

More information

Facility Interconnection Requirements

Facility Interconnection Requirements Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents

More information

Managing Power Outage with OpenWay

Managing Power Outage with OpenWay Managing Power Outage with OpenWay Dave Stensland Product Manager Katrina Hutchinson Sr. Product Manager 2010, Itron Inc. All rights reserved. 1 Executive Overview 3 Introduction to Outage Reliability

More information

Basic Reliability Analysis of Electrical Power Systems

Basic Reliability Analysis of Electrical Power Systems Basic Reliability Analysis of Electrical Power Systems Course No: E03-020 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Integration issues and simulation challenges of high penetration PV

Integration issues and simulation challenges of high penetration PV Integration issues and simulation challenges of high penetration PV March 6, 2014 EnerNex Capabilities Power Systems Modeling Transient Analysis Our preferred tools: EMTP RV, PSCAD Steady State & Quasi

More information

Fundamentals of Transmission Operations

Fundamentals of Transmission Operations Fundamentals of Transmission Operations Equipment Outages PJM State & Member Training Dept. Objectives At the end of this presentation the Learner will be able to: Identify how weather may influence outage

More information

What new capabilities

What new capabilities White Paper Emerging Trends in Analytics What new capabilities mean for distribution grid management Kent Hedrick Director of Grid Management Solutions at Landis+Gyr Future. Ready. SM July 2014 Analytics

More information

Wolverine Power Supply Cooperative, Inc. Senior Transmission System Operator

Wolverine Power Supply Cooperative, Inc. Senior Transmission System Operator I. OBJECTIVE Wolverine Power Supply Cooperative, Inc. Senior Transmission System Operator A. The Senior Transmission System Operator is responsible for the reliable and safe operation of Wolverine s transmission

More information

PPL Electric Utilities Summer Readiness Overview June 2018

PPL Electric Utilities Summer Readiness Overview June 2018 SUMMARY PPL Electric Utilities Summer Readiness Overview June 2018 For PPL Electric Utilities (PPL Electric), summer readiness means the company must respond effectively to summer storms as well as provide

More information

Integrated Volt/VAR Control

Integrated Volt/VAR Control Yukon energy automation software platform Integrated Volt/VAR Control For more efficient, higher quality and less costly power Integrated Volt/VAR Control enables smart grid power quality strategies 2

More information

(D2-01_28) ROLE OF ICT in Power System

(D2-01_28) ROLE OF ICT in Power System CONSEIL INTERNATIONAL DES GRANDS RESEAUX ELECTRIQUES INTERNATIONAL COUNCIL ON LARGE ELECTRIC SYSTEMS http:d2cigre.org STUDY COMMITTEE D2 INFORMATION SYSTEMS AND TELECOMMUNICATION 2013 Colloquium November

More information

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE CHENNAI INDIAN WIND GRID CODE Rajesh Katyal Unit Chief, R&D Centre for Wind Energy Technology OVERVIEW NEED FOR INDIAN WIND GRID CODE Wind energy constitutes 6% of the installed capacity in the power scenario

More information

8 th Annual Electric Power Industry Conference

8 th Annual Electric Power Industry Conference 8 th Annual Electric Power Industry Conference STATCOM Application to Address Grid Stability and Reliability: Part I November 11 th, 2013 Authors: Donald Shoup, P.E. and Dr. Gregory Reed Support: Nick

More information

Smart Grid Is it beneficial to all?

Smart Grid Is it beneficial to all? Smart Grid Is it beneficial to all? Dr. M. E. Farrag BEng, MSc, PhD, MIET, MIEEE, FHEA SL, Chair of the Electrical and Electronic Programmes Board 1 Contents 2 Is it needed or just a luxury? What is Smart

More information

Smart Distribution Applications and Technologies - Program 124

Smart Distribution Applications and Technologies - Program 124 Smart Distribution Applications and Technologies - Program 124 Program Description Program Overview New technologies will be critical to future smart grid operation. These technologies will include advanced

More information

Impacts of the Decentralized Wind Energy Resources on the Grid

Impacts of the Decentralized Wind Energy Resources on the Grid 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Impacts of the Decentralized Wind Energy Resources on the Grid Babak Enayati, PhD, Senior

More information

Smart Grid Demonstrations Cost and Benefit Analysis Methodology

Smart Grid Demonstrations Cost and Benefit Analysis Methodology Presentation Identifier (Title or Location), Month 00, 2008 Cost and Benefit Analysis Framework: Update EPRI Smart Grid Advisory Meeting October 14, 2009 Albuquerque, New Mexico Steve Bossart Director,

More information

Public Utility District Number 1 of Snohomish County

Public Utility District Number 1 of Snohomish County Public Utility District Number 1 of Snohomish County Facility Connection Requirements September 29, 2011 1 Revision History: Number Date Description Original Sept. 29, 2011 Document Origination Compilation

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

EDF and Integration of Distributed Energy Resources

EDF and Integration of Distributed Energy Resources IEEE Power Engineering Society Tuesday, June 20, 2006. Montreal EDF and Integration of Distributed Energy Resources Bruno Meyer (presenter) Director Power Systems Technology and Economics Yves Bamberger,

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

Member Service Electric Wiring Guidelines

Member Service Electric Wiring Guidelines Member Service Electric Wiring Guidelines Table of Contents A. Definitions... 2 B. Member Service Wiring Guidelines... 2 C: Meter located on the house from an underground source - pad transformer or j-box....

More information

Survey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST

Survey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST Survey and Summary of Best Practices for Distribution Reliability Improvement December 8, 2016 2 3 p.m. EST Webinar Overview Moderator: Speaker: Michele Suddleson DEED Program Director American Public

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Trico Electric Cooperative, Inc. Interconnection Requirements. For. Distributed Generation

Trico Electric Cooperative, Inc. Interconnection Requirements. For. Distributed Generation Version Dated May 5, 2017 Trico Electric Cooperative, Inc. Interconnection Requirements For Distributed Generation TRICO ELECTRIC COOPERATIVE, INC. INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION

More information

ASSESSMENT OF THE RELIABILITY OF A DYNAMIC SMART GRID SYSTEM

ASSESSMENT OF THE RELIABILITY OF A DYNAMIC SMART GRID SYSTEM International Journal of Power and Energy Systems, Vol. 3, No. 4, 20 ASSESSMENT OF THE RELIABILITY OF A DYNAMIC SMART GRID SYSTEM Arif Islam, Alex Domijan, and Aleksandar Damnjanovic Abstract One of the

More information

Analysis of distribution system reliability and outage rates

Analysis of distribution system reliability and outage rates Reclosers Technical Data TD280026EN Supersedes pril 2003 (R280-90-7) COOPER POWER SERIES nalysis of distribution system reliability and outage rates Recloser Technical Data TD280026EN nalysis of distribution

More information

School of Electrical Engineering and Computer Science. Expansion: Analysis, and Formulation. Washington State University

School of Electrical Engineering and Computer Science. Expansion: Analysis, and Formulation. Washington State University Distributed Generation Expansion: Analysis, Directions, Modeling, and Formulation Kevin Tomsovic Kevin Tomsovic Washington State University Importance of Distribution Systems Reliability under competition

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D. POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D. POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009 Effective Date: 26 August 2011 Expiry Year: 2015 Original signed by: APPROVED

More information

Virtual Power Plant Simulation

Virtual Power Plant Simulation AEP/EPRI Smart Grid Demo Virtual Power Plant Simulation Project Overview Smart Grid Advisory Meeting June 23, 2009 Tom Jones / Tom Walker Virtual Power Plant Simulation Project Virtual Power Plant (VPP)

More information

Tariffs January 1, 2017

Tariffs January 1, 2017 Tariffs January 1, 2017 Nova Scotia Power Inc. Tariffs & Regulations Approved by the Nova Scotia Utility and Review Board pursuant to The Public Utilities Act, R.S.N.S., 189,c.380 as amended Tariffs For

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

Energy Management System (EMS)

Energy Management System (EMS) Energy Management System (EMS) Comprehensive Power Quality Analysis Customer Billing and Invoicing at a Glance ExpertPower software solution provides comprehensive energy management, billing, demand response,

More information

Phasor measurement units gain credibility through improved test and calibration standards

Phasor measurement units gain credibility through improved test and calibration standards Phasor measurement units gain credibility through improved test and calibration standards Smart grid; PMU calibration position 1 The North American interconnection, or electric transmission grid, is a

More information

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I

More information

Understanding the Value of Uninterrupted Service

Understanding the Value of Uninterrupted Service Understanding the Value of Uninterrupted Service Paul Centolella, Vice President Analysis Group Mark McGranaghan, Vice President Power Delivery and Utilization Electric Power Research Institute CIGRE Grid

More information

Planned Islanding and Energy Storage at BC Hydro

Planned Islanding and Energy Storage at BC Hydro Planned Islanding and Energy Storage at BC Hydro Workshop: International Smartgrid projects review December 10, 2010 Jaime Peralta M.Sc., P.Eng. Distribution Planning T&D Asset Investment Management BC

More information

Bulk Power System Integration of Variable Generation - Program 173

Bulk Power System Integration of Variable Generation - Program 173 Program Description Program Overview Environmentally driven regulations such as state-mandated renewable energy standards and federal air and water standards, along with improved economic viability for

More information

Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks

Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks 1 Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks Linwei Chen, Haiyu Li, Steve Cox, and Kieran Bailey Presented by Dr Haiyu Li haiyu.li@manchester.ac.uk Senior

More information

Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events

Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events IWAIS XIV, China, May 0 Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events Asim Haldar, Ph.D, P.Eng. ahaldar@nalcorenergy.com

More information

Standard Development Roadmap

Standard Development Roadmap Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Smarter Business processes resulting from Smart Data

Smarter Business processes resulting from Smart Data 3 rd International Conference on Electricity Distribution Lyon, 15-1 June 15 Paper 5 Smarter Business processes resulting from Smart Data Goudarz POURSHARIF Andrew BRINT John HOLLIDAY University of Sheffield

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

ExISTING SubSTATION INfORmATIONON

ExISTING SubSTATION INfORmATIONON ExISTING SubSTATION INfORmATIONON drives equipment LIFe extension, modernization, and retrofitting david dolezilek and GeraLdo rocha, Schweitzer Engineering Laboratories, Inc. i. introduction Much of the

More information

Integrating Building Automation Systems with Microgrid Controls. Mingguo Hong, Associate Professor Case Western Reserve University Cleveland, OH

Integrating Building Automation Systems with Microgrid Controls. Mingguo Hong, Associate Professor Case Western Reserve University Cleveland, OH 1 Integrating Building Automation Systems with Microgrid Controls Mingguo Hong, Associate Professor Case Western Reserve University Cleveland, OH 2 The Typical Commercial Buildings Are aggregates of generation,

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

2014 Integral Analytics, Inc.

2014 Integral Analytics, Inc. 1 2 3 4 5 6 7 Company Overview Putting Advanced Analytics into Software to Manage Utility Costs & Risks Smart Grid Solutions T&D Planning Storage & Renewable Evaluation DSM Planning & Evaluation Marketing

More information

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013 CERTS Microgrids Tom Jahns Professor, University of Wisconsin-Madison LPPC Rates Roundtable May 21, 2013 Wisconsin Energy Institute WEI WEI provides linkage among all organizations associated with energy

More information

Partnering for reliable distribution

Partnering for reliable distribution Published by and copyright 013: Siemens AG Infrastructure & Cities Sector Smart Grid Division Humboldtstr. 59 90459 Nuremberg, Germany Further information is available from our Customer Support Center

More information

Microgrid Planning and Design MCAS Miramar, US Air Force Academy, and Fort Carson

Microgrid Planning and Design MCAS Miramar, US Air Force Academy, and Fort Carson Microgrid Planning and Design MCAS Miramar, US Air Force Academy, and Fort Carson Robert Butt, NREL Grid and Dispatchable Power Group E 2 S 2 - New Orleans May 13, 2011 NREL is a national laboratory of

More information

PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: February 11, 2015 REGULAR X CONSENT EFFECTIVE DATE N/A

PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: February 11, 2015 REGULAR X CONSENT EFFECTIVE DATE N/A PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: February 11, 2015 ITEM NO. 1 REGULAR X CONSENT EFFECTIVE DATE N/A DATE: TO: FROM: Public Utility Commission Brittany Andrus THROUGH:

More information

2012 Grid Strategy: Distribution Management System

2012 Grid Strategy: Distribution Management System 2012 Grid Strategy: Distribution Management System Advanced Applications for Distributed Energy Resources Jared Green Project Manager January 14, 2013 IEEE PES DMS Task Force Meeting 2012 Strategic Topic

More information

The Idaho Power Company

The Idaho Power Company Preventing Electrical Pollution Working with Customers to Control Electrical Pollution Idaho Power s Approach By Jon D Roholt For the IEEE PES T&D Conference & Exposition Chicago IL, April 23, 2008 The

More information

Medium voltage products. Technical Application Papers No. 17 Smart grids 1. Introduction

Medium voltage products. Technical Application Papers No. 17 Smart grids 1. Introduction Medium voltage products Technical Application Papers No. 17 Smart grids 1. Introduction Contents 2 1. Introduction 8 2 The different components and functions of a smart grid 8 2.1 Integration of distributed

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 No. 5310 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 1 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 2 3.1. Reporting Requirements/...

More information

DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE

DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE EB-0-0 Exhibit D Page of DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE 0 EXECUTIVE SUMMARY Background Over the past number of years, THESL has put considerable effort into its Asset Management

More information

DISTRIBUTION GRID PLANNING CONSIDERING SMART GRID TECHNOLOGIES

DISTRIBUTION GRID PLANNING CONSIDERING SMART GRID TECHNOLOGIES DISRIBUION GRID PLANNING CONSIDERING SMAR GRID ECHNOLOGIES Baktash NASIRI, Christian WAGNER, Ulf HÄGER and Christian REHANZ Institute of Energy Systems, Energy Efficiency and Energy Economics (ie³) U Dortmund

More information

DATA, BENCHMARKING AND RATIONALE BC Hydro Service Plan 2018/19 to 2020/21

DATA, BENCHMARKING AND RATIONALE BC Hydro Service Plan 2018/19 to 2020/21 DATA, BENCHMARKING AND RATIONALE BC Hydro Service Plan 2018/19 to 2020/21 BC Hydro relies on various data sources for relevant and accurate reporting of its Performance Measures. This includes, but is

More information

Standard PRC-002-NPCC-01 Disturbance Monitoring

Standard PRC-002-NPCC-01 Disturbance Monitoring A. Introduction 1. Title: Disturbance Monitoring 2. Number: PRC-002-NPCC-01 3. Purpose: Ensure that adequate disturbance data is available to facilitate Bulk Electric System event analyses. All references

More information

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018 Public Utility District Number 1 of Snohomish County Facility Connection Requirements February 9, 2018 1 Revision History: Number Date Description By Reviewed by Approved by: Original Sept. 29, 2011 Document

More information

Managing intelligent electronic devices

Managing intelligent electronic devices White Paper WP913001EN Managing intelligent electronic devices COOPER POWER SERIES As part of their Smart Grid initiatives, utilities have been deploying large numbers of Intelligent Electronic Devices

More information

Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1)

Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1) Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1) Date of Last Change to the Provided Information - September 1 st, 2017 Director, Transmission Operations The employee

More information

EE 741. Load Characteristics

EE 741. Load Characteristics EE 741 Load Characteristics Overview Some definitions Relation between load and loss factors Load models Load management Rate structure Metering Load forecasting Definitions Demand curve, maximum demand,

More information

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison Innovation & Grid Modernization at ComEd Laura García García Grid Strategy & Analytics Commonwealth Edison ComEd, An Exelon Company 2 Our Customers: 4 million electric customers in northern Illinois, including

More information

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY TARIFF FOR BASIC SERVICE

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY TARIFF FOR BASIC SERVICE Sheet 1 MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY TARIFF FOR BASIC SERVICE 1. General This Tariff may be revised, amended, supplemented or supplanted in whole or in part from time to time

More information

Using Software and Submeters to Manage Energy

Using Software and Submeters to Manage Energy Dan Ellis Product Manager Power Management Products Eaton s Cutler-Hammer business Introduction To be economically competitive in today s global marketplace, it is necessary to reduce the cost of production

More information

SMART GRID SCENARIO. Marina Egea,

SMART GRID SCENARIO. Marina Egea, SMART GRID SCENARIO Marina Egea, What is Smart Grid is an electricity network that can integrate in a costefficient manner the behaviour and actions of all users connected to it - generators, consumers

More information

Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation

Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation WEN-CHIH YANG Department of Electrical Engineering Technology and Science Institute of Northern Taiwan No.2, Syueyuan

More information

AEP Ohio gridsmart Phase 2 FAQs

AEP Ohio gridsmart Phase 2 FAQs AEP Ohio gridsmart Phase 2 FAQs External FAQs What is advanced metering infrastructure (AMI) and an automated meter reading (AMR)? What is the difference between them? AMI, also known as smart meters,

More information

Energy Industry Challenges

Energy Industry Challenges Energy Industry Challenges Global economic crisis; severe hurdles to capital-raising Extreme energy price volatility and uncertainty Backlash from energy consumers Urgent need to achieve energy independence

More information

Transmission Interconnection Requirements. Table of Contents

Transmission Interconnection Requirements. Table of Contents Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection Agreement III. Facility Requirements IV. Interconnection Initiation I. Introduction A. Purpose and Scope

More information

SETTING UP A LOAD-MANAGEMENT SYSTEM

SETTING UP A LOAD-MANAGEMENT SYSTEM POWER SYSTEMS TOPICS Power Up With a Load-Management System: SETTING UP A LOAD-MANAGEMENT SYSTEM AUTHOR ISAAC FRAMPTON Senior Staff Engineer Kohler Co. Power Systems Division Part of a -part series INTRODUCTION

More information

Smart Metering and the Need for Advanced Data Management

Smart Metering and the Need for Advanced Data Management Smart Metering and the Need for Advanced Data Management Brian Owenson Sr Director, Technology Strategy, Oracle Utilities Global Business Unit 1 Agenda A Little History Some Definitions Current State of

More information

DA concept for higherquality. supplies. 24 ABB Review 4/1996

DA concept for higherquality. supplies. 24 ABB Review 4/1996 DA concept for higherquality power supplies Low power network losses and an uninterrupted supply of electricity are no longer enough to satisfy today s consumers, who take a highquality power supply for

More information

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments GE Energy POWERING POTENTIA L Smart Grid Concept, Applications and Lessons Learned from Recent Deployments Gagan KAKKAR General Manager India Region GE Energy What is Smart Grid P O W E R I N G P O T E

More information

Mitigation of Voltage Fluctuations in Power System Using STATCOM

Mitigation of Voltage Fluctuations in Power System Using STATCOM RESEARCH ARTICLE OPEN ACCESS Mitigation of Voltage Fluctuations in Power System Using STATCOM M. Venkatesh & Ramakrishna Raghutu Assistant Professors, Dept. of Electrical & Electronics Engineering, GMRIT,

More information

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health

More information

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW

More information

John J. Simmins Senior Project Manager IntelliGrid Program October 5, 2012

John J. Simmins Senior Project Manager IntelliGrid Program October 5, 2012 A Monetization of Missing and Inaccurate GIS Data for the Purpose of Justifying Investment in GIS Data Improvement Initiatives Smart Grid Information Sharing Webcast GIS Interest Group John J. Simmins

More information

GE Digital Energy. Grid IQ Insight. Delivering Operational Insights for Utilities Globally. gimagination at work

GE Digital Energy. Grid IQ Insight. Delivering Operational Insights for Utilities Globally. gimagination at work GE Digital Energy Grid IQ Insight Delivering Operational Insights for Utilities Globally gimagination at work Putting Big Data into Action Data analytics present utilities with the powerful opportunity

More information

Power Management Solutions Exploring Hidden Cost Opportunities

Power Management Solutions Exploring Hidden Cost Opportunities Power Management Solutions Exploring Hidden Cost Opportunities Stephen Barker Head Of Energy Efficiency & Environmental Care Siemens plc, Industry Sector UK Siemens AG, 2010 All Rights Reserved Agenda

More information

Operational efficiency

Operational efficiency Operational efficiency OPERATIONAL EFFICIENCY G4-DMA Last year, the company invested BRL 791.5 million in services to consumers, expansion of the system, operational reliability, recovery of losses, information

More information

New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems

New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems WHITE PAPER Abstract Grid power demand peaks and increasing supply/ demand inbalances create management

More information

Energy Cost Reduction through Load Balancing & Load Shedding

Energy Cost Reduction through Load Balancing & Load Shedding white paper Energy Cost Reduction through Load Balancing & Load Shedding SCR controllers firing in phase angle degrade the power factor while increasing harmonics and electrical noise. A poor power factor

More information

Using Low Voltage Smart System (LVSS) Data for Intelligent Operations and Customer Support

Using Low Voltage Smart System (LVSS) Data for Intelligent Operations and Customer Support Using Low Voltage Smart System (LVSS) Data for Intelligent Operations and Customer Support Author & Presenter: Hartmut Bohmer- Engineering Projects Lead Co-author: Haneefa Motani- Marketing and Sales Administrator

More information

Distribution GIS & Grid Model Data Management

Distribution GIS & Grid Model Data Management Distribution GIS & Grid Data Management Pat Brown EPRI OGC Energy & Utilities Summit June 28, 2017 Pat Brown works in EPRI s Information and Communication Technology program. She is currently engaged in

More information

Integrated Capacity Analysis Working Group - Long Term Refinement Topics Scoping Document

Integrated Capacity Analysis Working Group - Long Term Refinement Topics Scoping Document Integrated Capacity Analysis Working Group - Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart Background: A June 7, 2017 Assigned Commissioner Ruling (ACR)

More information

RELIABILITY ASSESSMENT OF DISTRIBUTION NETWORS USING SEQUENTIAL MONTE CARLO SIMULATION

RELIABILITY ASSESSMENT OF DISTRIBUTION NETWORS USING SEQUENTIAL MONTE CARLO SIMULATION RELIABILITY ASSESSMENT OF DISTRIBUTION NETWORS USING SEQUENTIAL MONTE CARLO SIMULATION Srete Nikolovski *, Predrag Maric *, Ivan Mravak ** *Faculty of Electrical Engineering, K. Trpimira 2B, 31 Osijek,

More information

Benefit-Cost Analysis Summary Report

Benefit-Cost Analysis Summary Report Benefit-Cost Analysis Summary Report Site 74 City of Syracuse PROJECT OVERVIEW As part of NYSERDA s NY Prize community microgrid competition, the CNY RPDB has proposed development of a microgrid that would

More information

Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at

Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at Table of Contents Scope... 3 Definitions... 3 Application... 4 Uncontrolled Events... 5 Electromagnetic Compatibility (EMC)... 5 Electromagnetic Compatibility Levels... 5 Assessment of Low and Medium Voltage

More information

OUTAGE COORDINATION PROCESS

OUTAGE COORDINATION PROCESS OUTAGE COORDINATION PROCESS October 3, 2016 www.peakrc.com. Classification: Public Page 0 of 67 Effective Date: Apr 01, 2017 Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic

More information