1 Environmental Management System Integra Coal Operations Pty Ltd POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC) 2012 Doc No: Doc Owner: EMP_ Environmental Advisor Integra Coal Operations Approval: Manager Sustainability Integra Coal Operations Signed: Date: 31 August 2012 Revision Issue Date Originator Reviewed Approved 1 31/8/2012 J Trotter K Plasto K Plasto Environmental Advisor 01 31/08/ /08/ of 8
2 Table of Contents Page 1. PURPOSE SCOPE DEFINITION OF A POLLUTION INCIDENT DUTY TO REPORT WHO SHOULD REPORT WHAT INFORMATION SHOULD BE REPORTED INTEGRA CONTACT DETAILS EXTERNAL CONTACT DETAILS COMMUNICATING WITH NEIGHBOURS AND THE LOCAL COMMUNITY MINIMISING HARM TO PERSONS ON THE PREMISES DESCRIPTION AND LIKELIHOOD OF HAZARDS INVENTORY OF POLLUTANTS SAFETY EQUIPMENT INCIDENT RESPONSE ACTIONS STAFF TRAINING AND TESTING THE PIRP MAKING PLANS AVAILABLE... 8 List of Figures Figure 1 Pollution Incident Response Plan 9 Figure 2 Pollution Incident Response Plan 10 Figure 3 Pollution Incident Response Plan 11 Environmental Advisor 01 31/08/ /08/ of 8
3 1. P u r p o s e This Pollution Incident Response Management Plan (PIRMP) has been developed to satisfy pollution reporting obligations under the Protection of the Environment Operations Act 1997 (POEO Act) and the Protection of the Environment Operations (General) Regulation 2009 (POEO(G) Regulation). The plan outlines the classification, testing, reporting, and management requirements for an environmental pollution incident. The objectives of the plan are to ensure an environmental pollution incident is communicated to all relevant groups and individuals as well as prevent, minimise and control the risk of an environmental pollution incident. 2. S c o p e This plan covers the Integra Mine Complex operated by Integra Coal Operations Pty Ltd (Integra), a subsidiary of Vale. The Integra Mine Complex (the Complex) is located approximately 10 kilometres northwest of Singleton in the NSW Hunter Valley. This PIRMP is a sub-plan of the Integra Emergency Management System Operational Management Plan. 3. D e f i n i t i o n o f a P o l l u t i o n I n c i d e n t Pollution incident means an incident or set of circumstances during or as a consequence of which there is or is likely to be a leak, spill or other escape or deposit of a substance, as a result of which pollution has occurred, is occurring or is likely to occur. It includes an incident or set of circumstances in which a substance has been placed or disposed of on premises, but it does not include an incident or set of circumstances involving only the emission of any noise. 4. D u t y t o R e p o r t A pollution incident is required to be notified if there is a risk of material harm to the environment, which is defined in Section 147 of the Protection of the Environment Operations Act 1997 as: (a) harm to the environment is material if: it involves actual or potential harm to the health or safety of human beings or to ecosystems that is not trivial, or it results in actual or potential loss of property damage of an amount, or amounts in aggregate, exceeding $10,000 (or such other amount as is prescribed by the regulations), and (b) loss includes the reasonable costs and expenses that would be incurred in taking all reasonable and practicable measures to prevent, mitigate or make good harm to the environment. A pollution incident must be reported immediately to the EPA, NSW Health, Fire and Rescue NSW, WorkCover NSW and Singleton Shire Council. The NSW Department of Planning & Infrastructure and the Division of Resources & Energy of the Department of Trade & Investment, Regional Infrastructure & Services should also be informed. Environmental Advisor 01 31/08/ /08/ of 8
4 5. W h o S h o u l d R e p o r t When a person at site becomes aware of an actual or potential pollution incident, that person should advise his/her supervisor. The advised supervisor should advise the Integra Environmental Superintendent, Safety & Sustainability Manager or the General Manager. The Environmental Superintendent, Safety & Sustainability Manager or the General Manager will advise the bodies nominated in Section 4 (above) if the pollution incident meets the criteria for reporting. 6. W h a t I n f o r m a t i o n S h o u l d b e R e p o r t e d The following information (as a minimum and where known) should be reported: Location of the pollution incident. Type of pollutant. Quantity of the pollutant. Circumstances of the incident. Persons or environmental media impacted or at risk following the incident. Weather conditions (if relevant) such as wind speed, wind direction and whether it is raining. 7. I n t e g r a C o n t a c t D e t a i l s Title Various - Refer FRM_2003 Emergency Contact s General Manager Manager Safety & Sustainability Environmental Superintendent Various - Refer FRM_2003 Emergency Contact s Responsibility Activation of pollution incident response management plan. Notification of relevant authorities. Notification of relevant authorities. Notification of relevant authorities. Managing response to pollution incident. Environmental Advisor 01 31/08/ /08/ of 8
5 8. E x t e r n a l C o n t a c t D e t a i l s Service Additional Information Telephone Emergency Services (if dealing with an emergency) Police Fire Ambulance 000 EPA Environment Line Ministry of Health Population & Health Public Health Unit, Hunter New England Health, Newcastle Office (02) WorkCover Singleton Shire Council (02) (02) (a/h) Department of Planning & Infrastructure Singleton Compliance Branch (02) DTIRIS Division of Resources & Energy 9. C o m m u n i c a t i n g w i t h N e i g h b o u r s a n d t h e L o c a l C o m m u n i t y The Integra Complex operates a website available to members of the public ( A notification of a reportable incident meeting the criteria nominated in Section 4 of this Plan will be made on the Integra website. In addition, the Integra Complex operates a Community Hotline ( ). Practical utilisation of the Community Hotline to disseminate information will be investigated. Where a notifiable pollution incident has the potential to impact neighbouring properties, occupants of those potentially impacted properties will be telephoned or door knocked to advise of the situation. The nature and directional impact of the incident will determine the most appropriate properties to be notified. Integra operates a Community Consultative Committee (CCC) and all community representatives are contactable via . Community representatives on the CCC will be advised via of the reportable pollution incident. Where Integra are able to provide specific information to aid members of the local community to reduce their risk of harm, this information will be provided. An example of when neighbours and members of the local community would be informed would be a discharge (meeting criteria nominated in Section 4) of a diesel fuel into Glennies Creek. In this case, an avoidance of use of water from Glennies Creek below the fuel entry point would be recommended. Environmental Advisor 01 31/08/ /08/ of 8
6 10. M i n i m i s i n g H a r m t o P e r s o n s o n t h e P r e m i s e s At all times minimising harm to persons on the premises shall be a priority. Refer to the Integra Emergency Management System Operational Management Plan for specific actions. 11. D e s c r i p t i o n a n d L i k e l i h o o d o f H a z a r d s Principal hazards to human health or the environment associated with coal mining at the Integra Mine Complex are considered, in the first instance, to be those associated with underground mining (e.g. explosion, roof fall, water inrush, gas outburst, machinery interaction etc) and open cut mining (heavy plant accident, light vehicle accident, accidental detonation of explosives etc). These hazards are likely to affect Integra employees and contractors only. Such incidents occurring and having serious consequences, such as a fatality, are not likely but are possible. In addition, pollution incidents which could impact human health or the environment affecting either the Integra Mine Complex or beyond, include: Significant failure of hydrocarbon storage or supply lines causing substantial ground or groundwater contamination (low risk). Stormwater being impacted by sewage effluent (low risk). Blasting fume (low risk). [note blast initiation is staggered relative to nearby mine s blasting] Substantial sediment loss to neighbouring waterways (low risk). 12. I n v e n t o r y o f P o l l u t a n t s Potential pollutants stored, used or generated on the mine site include: diesel fuel oils dust mitigation fluids explosives potential blast fume sewage and sewage effluent sediment-contaminated stormwater 13. S a f e t y E q u i p m e n t Spill kits are to be found in the following locations: Open cut workshop Open cut fuel bay underground at diesel & oil tanks, store, hydrocarbon storage shed, BIS workshop and bench service bay Environmental Advisor 01 31/08/ /08/ of 8
7 Spill kits typically contain: spill absorbent chemical absorbent booms and pads plastic recovery bags personnel protective equipment Material safety data sheets are available at: open cut store open cut first aid room Coal Handling and Processing Plant underground control room via Chemwatch on the Integra intranet 14. I n c i d e n t R e s p o n s e Ac t i o n s Refer to the Integra Emergency Management System Operational Management Plan. Six steps to spill response are: raise the alarm secure the area approach with care identify the products assess the situation respond contain, cleanup, investigate, review Hydrocarbon contaminated soils should be remediated on site (where practical). Fugitive hydrocarbons retained in sumps etc should be recovered by the waste contractor with this capability. 15. S t a f f Tr a i n i n g a n d Te s t i n g t h e P I R P All employees will be made aware of the existence of the Pollution Incident Reporting Management Plan and their obligation to report a pollution incident to his or her supervisor. Training for Open Cut Examiners in the PIRP will be undertaken every two years and records maintained in the Integra training system files. A mock emergency will be conducted annually to test the adequacy of the Emergency Management System. This mock emergency will include use of the PIRP and involve desktop simulations and/or practical exercises or drills. Testing will cover all components of the PIRP, including the effectiveness of training. Dates for testing and staff members involved in the testing Environmental Advisor 01 31/08/ /08/ of 8
8 will be recorded. The Sustainability Department will provide a written report of the results of each such exercise along with recommendations relating to improvements. In addition, if a pollution incident covered by this plan occurs, then, within one month of that incident occurring, the PIRP will be tested. 16. M a k i n g P l a n s Av a i l a b l e A copy of this PRP will be made available at the Integra Mine Complex such that it is readily available to both Integra personnel to utilise and an authorised officer who may request. An abridged copy of the PIRP will be made available on the Integra website ( The abridged copy is to include the procedures for contacting the relevant authorities and procedures for communicating with the community. Environmental Advisor 01 31/08/ /08/ of 8
Pollution Incident Response Management Plan
Regain Spent Potliner Reprocessing Facility Kurri Kurri Aluminium Smelter Regain Document Code Objectives Comprehensive and timely communication about a pollution incident to all recognised stakeholders
More informationSOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)
SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) 1. PURPOSE Renewable Oil Services is licensed to conduct waste processing of hazardous and other wastes using non-thermal treatment and
More informationINCIDENT RESPONSE MANAGEMENT PLAN MAY 2016
INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016 DOCUMENT CONTROL Document Controller: Resilience Coordinator Date of last update: May 2016 Date of next update: May 2017 HPRM reference: HW2007-900/27/9.009 Version
More informationPollution Incident Response Management Plan. Newell Highway Trewilga Realignment
Pollution Incident Response Management Plan Newell Highway Trewilga Realignment Contents 1 Introduction... 2 1.1 Purpose and scope... 2 2 Statutory requirements... 3 2.1 Project approval... 3 2.2 Protection
More informationTasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS
Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS TASMAN EXTENSION PROJECT PRELIMINARY HAZARD ANALYSIS FEBRUARY 2012 Project No. DCL-09-01 Document No. PHA-C
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site
More informationHydrocarbon Management PROCEDURE
Hydrocarbon Management PROCEDURE Doc No: Approved: PRO-0380 Operations Manager Table of Contents 1. PURPOSE... 3 2. SCOPE... 3 3. REFERENCES... 3 3.1 LEGISLATION/STANDARDS... 3 4. DEFINITIONS... 3 5. HYDROCARBON
More informationPollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 20 th September Seven Hills Asphalt PIRMP_V8.
Pollution Incident Response Management Plan Seven Hills Asphalt Version Seven: 20 th September 2016 Seven Hills Asphalt PIRMP_V8 1 of 31 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a
More informationEnvironmental Management Plan Attachment 5 Environmental Incident Response Plan
Victorian Desalination Plant Response Plan Document No: ENV-000-PL-005 This Document is the property of Watersure and is protected by copyright. Other than for the purposes and subject to the conditions
More informationEnvironmental Conditions Laboratories (for commercial use) Group
GBR No. 20 Environmental Conditions Laboratories (for commercial use) Group ERA regulates the environmental impact of enterprises through two key mechanisms. Smaller scale activities are regulated through
More informationPollution Incident Response Management Plan
Pollution Incident Response Management Document 1 year Table of Contents 1 Introduction... 3 1.1 Background and Scope... 3 1.2 Regulatory Requirements... 3 2 Premise Details... 5 2.1 Site Details... 5
More informationEnvironmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group
Environmental Management System Integrated Pollution Control Document No. 5.2.1 Version no. 1 Origination Date 1 st February 2017 Area: The Group Approval: Group Services & Facilities Last Revision Date
More informationTABLE OF CONTENTS. Process Owner: ESR Verifiers: Jenna Marett; Andrew Raal Status: Approved Version: 1.3 Issue Date: 07/01/2014 Page: 1 of 21
PLN-08-004 TABLE OF CONTENTS 1. PURPOSE... 2 2. SCOPE... 2 3. RELATED DOCUMENTS... 2 4. Property Ownership... 3 5. DEFINITIONS... 3 5.1 Pollution Incident... 4 5.2 Major Pollution Incident... 4 5.3 Ranking
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 20593 20-December Licensee HI-QUALITY QUARRY (NSW) PTY LTD PO BOX 42 KEMPS CREEK NSW 2171 Premises HI QUALITY KEMPS CREEK CENTRAL 1503-1519 ELIZABETH DRIVE KEMPS
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 767 01-January Licensee METROPOLITAN COLLIERIES PTY. LTD. PO BOX 402 HELENSBURGH NSW 2508 Premises METROPOLITAN COLLIERY PARKES STREET HELENSBURGH NSW 2508 Scheduled
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 20850 24-November Licensee MACH ENERGY AUSTRALIA PTY LTD LEVEL 2, 179 GREY STREET SOUTH BANK QLD 4101 Premises MOUNT PLEASANT OPERATION 1100 WYBONG ROAD MUSWELLBROOK
More informationConstruction Environment Management Plan
Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated
More informationThe plan covers Girraween NSW site operated by Industrial Galvanizers Pty Ltd located at Amax Avenue, Girraween NSW 2145.
1. PURPOSE The purpose of this Pollution Incident Response Management (PIRMP) is to describe Industrial Galvanizers response to a potential pollution incident and to meet requirements of the Protection
More informationA positive, collaborative airport-wide approach is essential to minimise pollution. Heathrow Pollution Prevention Code of Practice
A positive, collaborative airport-wide approach is essential to minimise pollution. Heathrow Pollution Prevention Code of Practice Contents EXECUTIVE SUMMARY 03 INTRODUCTION _ 1.0 04 GENERAL REQUIREMENTS
More informationIncorporating an Air Quality Monitoring Protocol
UNDERGROUND OPERATION Incorporating an Air Quality Monitoring Protocol Issue 1: March 2007 Carbon Based Environmental Pty Limited 2007. This document was prepared solely for the original recipient and
More informationUpgrade of Schofields Road between Tallawong Road and Veron Road. Pollution Incident Spill Response Plan
Upgrade of Schofields Road between Tallawong Road and Veron Road For NSW Roads and Maritime Services Pollution Incident Spill Response Plan Document No: 428 PL004-10 Copy No. Revision Registered Holder
More informationGUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08
CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date
More informationSpill Response Procedures
Spill Response Procedures [your municipality] Purpose: The purpose of this Standard Operating Procedure (SOP) is to provide guidance for the proper response and corrective actions to be followed in the
More informationAnnex CC To Facilities Management Department. Routine Audit and Monitoring of Health and Safety management functions.
Annex CC To Facilities Management Department Routine Audit and Monitoring of Health and Safety management functions. The responsibilities and monitoring approaches contained within this guide are to be
More informationENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009
ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,
More informationPOLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Austral Masonry NSW Prospect (EPL# 4664)
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Austral Masonry NSW Prospect (EPL# 4664) Adapted from Horsley Park to suit Prospect PIRMP by M. Burns Reviewed 7/10/2016 Pollution Incident Response Management
More informationCentral NSW Regional Contaminated Land Policy Template
Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction
More informationSpills to the Environment and Reporting Policy
Applicable Legislation: Environmental Protection Act, R.S.O. 1990 O.Reg. 675/98, Classification and Exemption of Spills, Guelph By-Law Number (1996)-15202 to regulate the discharge of wastes into the sanitary
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 1552 01-June Licensee PORT WARATAH COAL SERVICES LTD PO BOX 57 CARRINGTON NSW 2294 Premises PWCS KOORAGANG COAL TERMINAL CURLEW STREET KOORAGANG NSW 2304 Scheduled
More informationTo reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.
Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems
More informationGuidance on the Standards for Storage and Treatment of End-of-life vehicles
Guidance on the Standards for Storage and Treatment of End-of-life vehicles Introduction This guidance has been prepared by the Environment Agency and the Scottish Environment Protection Agency (SEPA),
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 20076 12-June Licensee CLEANWAY ENVIRONMENTAL SERVICES PTY LTD PO BOX 5179 MINTO NSW 2566 Premises 12 SHAW ROAD 12 SHAW ROAD INGLEBURN NSW 2565 Scheduled Activity
More informationHazardous Waste Management
Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective
More informationEnvironmental Management Sub-Plan. Management Plan. Appendix I Pollution Incident Response. Bringelly Road Upgrade Stage 1
Environmental Management Sub-Plan Appendix I Pollution Incident Response Management Plan Bringelly Road Upgrade Stage 1 DETAILS OF REVISION AMMENDMENTS TO POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Plan
More informationNATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE
NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE Amended November 2014 PIPELINE PERFORMANCE MEASURES - OVERVIEW Introduction The National Energy Board (Board) took action in March
More informationCONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY
CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY File No. 0506-013-07 Contaminated Media Management Plan Midland
More informationThe EPA reasonably suspects that the Pollution Incident at the 4 separate application sites was caused by Wollongong Recycling (NSW) Pty Ltd.
WOLLONGONG RECYCLING (NSW) PTY LTD ABN 93 615 301 650 PO Box 7 ENFIELD NSW 2136 Attention: Ms Ros Dent Notice Number 1557160 File Number EF17/9001 Date of Issue 03-Oct-2017 To The Proper Officer LEGAL
More informationSITE SPECIFIC SPILL PLAN For use of this form, see the Installation Spill Contingency Plan; the proponent is DPW-ENRD
POST THIS PAGE PROMINENTLY AT EACH HAZARDOUS WASTE SATELLITE ACCUMULATION POINT, 90-DAY HW SITE, HAZARDOUS MATERIAL STORAGE AREA, AND SPCC CONTAINER STORAGE AREA Spill Response Call 911 for all spills
More informationBest Management Practices
Best Management Practices The following is a listing of all Best Management Practices (BMPs) that all tenants covered by this SWPPP should implement. These constitute the minimum requirements that each
More information5. Summary of pesticide regulation in South Australia
5. Summary of pesticide regulation in South Australia Understanding and complying with the laws that govern pesticides is an important first step towards achieving environmentally safe use. The regulation
More informationPREMIUM DISCOUNT SCHEME AUDIT TOOL
PREMIUM DISCOUNT SCHEME AUDIT TOOL 2003 WorkCover. Watching out for you. Disclaimer This publication contains information regarding occupational health, safety, injury management or workers compensation.
More informationAppendix B Noise and Blasting Impact Assessment
Appendix B Noise and Blasting Impact Assessment 19 August 2010 Ref: J0130-42-L4 Hansen Bailey Pty Ltd P.O. Box 473 SINGLETON NSW 2330 Attn: Ms. Melissa Walker Dear Mel, ABN: 73 254 053 305 78 Woodglen
More informationStormwater. Management Program. Port of Anacortes. Western Washington Phase II Municipal. Stormwater. Permit # WAR045711
Port of Anacortes Stormwater Management Program Western Washington Phase II Municipal Stormwater Permit # WAR045711 100 Commercial Ave Anacortes, WA 98221 360.293.3134 December 2016 Port of Anacortes Stormwater
More informationBUSINESS RESPONSE PLAN. Hastings Natural History Reserve E. Carmel Valley Road Carmel Valley, CA a field station of the:
Hastings Natural History Reserve 38601 E. Carmel Valley Road Carmel Valley, CA 93924 a field station of the: Museum of Vertebrate Zoology University of California, Berkeley Berkeley, CA 94720 EPA # CAR-000-120-873
More informationOil Spill Preparedness and Response
Oil Spill Preparedness and Response Purpose To plan and prepare for effective Oil Spill Response 1 that mitigates potential consequences of an Incident, including identification and fulfilment of requirements
More informationANNUAL ENVIRONMENTAL MANAGEMENT REPORT
ORICA KURRI KURRI ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2011 Revision Date Description Author Approver 0 25/07/2011 2011 Annual Environmental Report K Millard Environmental Advisor N Davies Project
More informationEnvironmental Management Plan (EMP)
SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit
More informationHazardous Materials Section. California Hazardous Material Spill/Release Notification Guidance To Report
California Hazardous Material Spill/Release Notification Guidance To Report all significant releases or threatened releases of hazardous materials, First Call 9-1-1 (or the local emergency response agency)
More informationFossil Fuels and the environment
Lecture -11: Fossil Fuels and the environment ENV 107: Introduction to Environmental Science Dr. A.K.M. Saiful Islam 16.1 Fossil Fuels Fossil fuels are all forms of stored solar energy. We say because
More informationAIRCRAFT MAINTENANCE PTY LTD
AIRCRAFT MAINTENANCE PTY LTD Operational Environmental Management Plan Prepared by Chief Engineer Date: 30 th December 2008 Version 1.0 INTRODUCTION is an aircraft engineering business that has been operating
More informationPOLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) RANGERS VALLEY FEEDLOT PREPARED FOR: RANGERS VALLEY CATTLE STATION PTY LTD PO BOX 63 GLEN INNES NSW 2370 TOOWOOMBA HEAD OFFICE PO Box 2175 (11 Clifford
More informationEnvironmental Compliance Report Liquid Chemical Storage, Handling and Spill Management Part B Review of Best Practice and Regulation The Liquid
Environmental Compliance Report Liquid Chemical Storage, Handling and Spill Management Part B Review of Best Practice and Regulation The Liquid Chemical Storage, Handling and Spill Management Environmental
More informationPollution prevention (land and water)
1 Purpose This document provides information on how to effectively manage pollutants for those working in Design, Construction and Maintenance activities. This guidance is to support the Level 2 Environment
More informationATTACHMENT J ACCIDENT PREVENTION & EMERGENCY RESPONSE
ATTACHMENT J ACCIDENT PREVENTION & EMERGENCY RESPONSE Attachment J Industrial Emissions Licence Application J.1 Accident Prevention This Accident Prevention information sets out the various measures at
More informationLoy Yang B Environment Improvement Plan
Loy Yang B Environment Improvement Plan 2017 Table of Contents 1 Endorsement 1 2 Environment Policy 2 3 Operating Arrangements 3 4 Site Management and Business Systems 4 5 Environmental Impacts and Risks
More informationTransport Sector Portfolio
Transport Sector Portfolio Rehabilitation of 4.476 Kms of Asphalt Road in Shindand District, Herat Province, Afghanistan. United Nations Office for Project Services ( UNOPS ) -and- Name of Contractor Site
More informationGovernment Decree on the Transport of Dangerous Goods by Air (210/1997; amendments up to 659/2009 included) Section 1 Scope of application (659/2009)
NB: Unofficial translation; legally binding only in Finnish and Swedish Government Decree on the Transport of Dangerous Goods by Air (210/1997; amendments up to 659/2009 included) Section 1 Scope of application
More informationAMENDMENT OF SOLICITATION
PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION PAGE 1 Metropolitan Washington Airports Authority 1A. AMENDMENT OF SOLICITATION NO. 1B. DATED Procurement and Contracts Dept., MA-29 November 13,
More informationMurra Warra Wind Farm Project Environmental Management Plan
1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human
More informationNSW DEPARTMENT OF PRIMARY INDUSTRIES MINERAL RESOURCES. New legislation & Major Hazard Management
New legislation & Major Hazard Management Since 1980, how many lives have been lost in NSW coal Mines? 108 Since 1900 More than 1500 Philosophy of NSW legislation The OH&S Act 1983 introduced the concept
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 12425 08-February Licensee WILPINJONG COAL PTY LTD LOCKED BAG 2005 MUDGEE NSW 2850 Premises WILPINJONG COAL MINE 1434 ULAN-WOLLAR ROAD WILPINJONG NSW 2850 Scheduled
More informationWHS Management Plans
WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the
More informationPollution & Environmental Harm
Pollution & Environmental Harm Fact Sheet 27 Updated December 2010 An introduction to Pollution and Environmental Harm There are a large range of activities that can lead to pollution or cause environmental
More informationACCIDENT PREVENTION & EMERGENCY RESPONSE
Attachment J ACCIDENT PREVENTION & EMERGENCY RESPONSE Cadbury Ireland Limited Project Ref: OES1061_01 Cadbury Ireland Limited February 2007 Attachment J J.1 Accidental Emissions Control Accidental emissions
More informationMonthly Environmental Monitoring Report
\ Monthly Environmental Monitoring Report Name of Operation Name of Licensee Environmental Protection Licence Reporting Period start date Reporting Period end date Version Author Approver Moolarben Coal
More informationWater Pollution Control for Work in Sensitive Areas
Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed
More informationPollution Prevention Technical Information note
Pollution Prevention Technical Information note Airfield management April 2011 This note gives you pollution prevention advice for the activities and processes that occur at airfields in England and Wales.
More informationSection 9A 9A Purpose of the Hazardous Substances Provisions
Section 9A 9A Purpose of the Hazardous Substances Provisions The Council has a function under section 31 of the RMA to control any actual or potential effects of the use, development or protection of land
More informationHealth & Safety Officer. Donegal County Council
CANDIDATES INFORMATION BOOKLET June 2016 Health & Safety Officer Donegal County Council ESSENTIAL REQUIREMENTS Department of the Environment, Heritage and Local Government An Roinn Comhshaoil, Oidhreachta
More informationEnvironment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance
South Australia s Environment Protection Authority Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance Clive Jenkins, Ruth Ward and Lara Settimio Outline
More informationSection 2 Environmental Considerations for Port Development and Operations
Environmental Considerations for Port Development and Operations The purpose of this section is to identify port development and operation activities that may affect environmental quality. For each activity,
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 529 01-January Licensee WAMBO COAL PTY LIMITED PMB 1 SINGLETON NSW 2330 Premises WAMBO COAL PTY LTD JERRYS PLAINS ROAD WARKWORTH NSW 2330 Scheduled Activity Coal
More informationEnsure your own actions reduce risks to health and safety
Ensure your own actions reduce risks to health and safety UNIT SM 1 Area of competence This unit is designed to demonstrate competence in following the health and safety duties required in the workplace
More informationProcedure: Safety Management System Procedure - My Safety
Procedure: Safety Management System Procedure - My Safety 1. Purpose Ensure a framework for managing OHS risks is implemented integrating the organisation's planning, management, reporting processes, communication,
More informationCONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK
CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK APPENDIX D Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project Description...
More informationPermit with introductory note
Permit with introductory note The Environmental Permitting (England & Wales) Regulations 2010 Glazewing Limited Saxon Pit Peterborough Road Whittlesey Peterborough Cambridgeshire PE7 1LQ Permit number
More informationTHE COMPLETE GUIDE TO ISO14001
THE COMPLETE GUIDE TO ISO14001 1. Introduction... 3 Plan Do Check Act... 5 2. Requirements... 7 Environmental Policy... 7 Environmental Aspects... 7 Legal and Other Requirements... 8 Objectives & Targets...
More informationPolicy Work Health and Safety (WHS) RCPA Introduction WHS legislation
Policy Subject: Work Health and Safety (WHS) Approval Date: July 2011, December 2014 Review Date: July 2018 Review By: Board of Directors Number: 1/2011 The Royal College of Pathologists of Australasia
More informationRelevant legislation (Administering Authority Commonwealth legislation
Commonwealth legislation Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) [Commonwealth Department of Sustainability, Environment, Water, Population and Communities (SEWPaC)] New
More informationPesticide Chemical Safety
Pesticide Chemical Safety This section discusses agricultural chemical safety for pesticides, including rodenticides, insecticides, herbicides, etc. Pesticides are chemicals that protect crops and livestock
More informationEnvironmental Guideline for Saskatchewan Asphalt Plants
Environmental Guideline for Saskatchewan Asphalt Plants Ministry of Environment July 2015 saskatchewan.ca/environment For enquiries or reporting, please contact: Government of Saskatchewan Environmental
More informationPesticide Use in Queensland
Pesticide Use in Queensland This Factsheet is for general information purposes and is not legal advice. Important legal details have been omitted to provide a brief overview of this area of the law. If
More informationWORK HEALTH AND SAFETY AUDIT STANDARD
WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...
More informationSTORM WATER PLAN (SWP) GUIDANCE TEMPLATE
STORM WATER PLAN (SWP) GUIDANCE TEMPLATE Name of Facility: Address: Phone Number: Date: INTRODUCTION This Storm Water Plan (SWP) is written in accordance with the State of Delaware Regulations Governing
More informationINTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol
INTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol For The International Cyanide Management Code www.cyanidecode.org December 2016 The International Cyanide Management
More informationStormwater Pollution Prevention Plan (SWPPP) For Single Family Residential Construction within a larger plan of development
COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Tel. (434) 296-5832 Fax (434) 972-4126 Stormwater Pollution Prevention Plan (SWPPP)
More informationFEEDLOT DESIGN AND CONSTRUCTION. 39. Agricultural and veterinary chemical storage. AUTHORS: Orla Keane and Peter Watts
39. Agricultural and veterinary chemical storage AUTHORS: Orla Keane and Peter Watts Introduction Agricultural and veterinary chemicals used in a feedlot must be stored in a way that maintains product
More informationSpills Reporting - A Guide to Reporting Spills and Discharges. As required by the. (Ontario) Environmental Protection Act (s.92 and s.
Spills Reporting - A Guide to Reporting Spills and Discharges As required by the (Ontario) Environmental Protection Act (s.92 and s.15) and Ontario Regulation 675/98 Classification and Exemption of Spills
More informationCalifornia Hazardous Materials Spill / Release Notification Guidance
California Hazardous Materials Spill / Release Notification Guidance To Report all significant releases or threatened releases of hazardous materials: First Call: 9-1-1 (or local emergency response agency)
More informationIN THE PROVINCIAL COURT OF ALBERTA CRIMINAL DIVISION HER MAJESTY THE QUEEN. -and- GAS PLUS INC. STATEMENT OF AGREED FACTS
IN THE PROVINCIAL COURT OF ALBERTA CRIMINAL DIVISION BETWEEN: HER MAJESTY THE QUEEN -and- GAS PLUS INC. STATEMENT OF AGREED FACTS Gas Plus Inc. stands charged that: Count1 On or between the 1st day of
More informationForms for Notifications of Independent Remediation and Migration. Version 3.0. Prepared pursuant to Section 64 of the Environmental Management Act
PROTOCOL 17 FOR CONTAMINATED SITES Forms for Notifications of Independent Remediation and Migration Version 3.0 Prepared pursuant to Section 64 of the Environmental Management Act Approved: Cameron Lewis
More informationEnvironmental Aspects, Impacts, and Risk ISO 14001:
1. PURPOSE: This document describes the procedure for identification of environmental risks, opportunities, aspects and impacts for the City of Dallas (City) Environmental Management System (EMS) and determining
More informationWhitewater River Region SWMP. APPENDIX L BMPs for Fire Fighting Agency Activities
Whitewater River Region SWMP APPENDIX L June 2009 INTENT The purpose of this plan is to identify Best Management Practices (BMPs) used by fire fighting agencies for management of Urban Runoff in the Whitewater
More informationSection 75J of the Environmental Planning and Assessment Act 1979
Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, approve the project referred to in Schedule 1, subject to the conditions in Schedule 2.
More informationUniversity of Birmingham
University of Birmingham Health and Safety Policy Manager responsible for review: Facilities Manager Date of last review and update: April 2015 Approved by: H&S committee 2015 Next scheduled review date:
More informationLivezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani DESCRIPTION OF
More informationCONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999
(No. JPBN. 1509/27 Vol. II CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999 In exercise of the powers conferred by section 5 of the Conservation
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 809 01-February Licensee YOLARNO PTY LTD PO BOX 405 INVERELL NSW 2360 Premises BINDAREE BEEF WARIALDA ROAD INVERELL NSW 2360 Scheduled Activity Livestock Processing