EE5721 FINAL EXAM MAY 11, 2011 NAME PLEASE DO NOT ENTER YOUR ID NUMBER

Size: px
Start display at page:

Download "EE5721 FINAL EXAM MAY 11, 2011 NAME PLEASE DO NOT ENTER YOUR ID NUMBER"

Transcription

1 Final Exam, EE5721, May 9, 2011 EE5721 FINAL EXAM MAY 11, 2011 NAME PLEASE DO NOT ENTER YOUR ID NUMBER Problem Max Points SCORE TOTAL 100

2 Final Exam, EE5721, May 9, 2011 Problem 1) 20 Points Power System Security Analysis Consider the six bus power system network below from the EE5721 textbook. Initially all loads are at 40 MW generators are each at 40 MW output. Bus 1 is the reference bus. The initial power flows are calculated with a DC Power Flow and result in the base flows below. The line flow limits are also shown with the percent loading. BASE TRANSMISSION LOADING Path From To Low Flow High Percent Loading

3 Final Exam, EE5721, May 9, 2011 The generator on bus 2 now agrees to sell an extra 50 MW to the load on bus 6. This requires adding 50 MW to the generation on bus 2 and adding an extra 50 MW to the load on bus 6. With this sale added to the original generation and load in operation, the power system must pass the (n-1) security test for line outages on lines 6-2, 6-3, and 6-5 a) In the base case there are no contingency outages which cause overloads. (You do not have to calculate this.) b) Do any of the line outages on lines 6-2, 6-3, and 6-5, taken one outage at a time, result in overloads when the additional 50 MW is being transferred? If so how much and what lines are overloaded. You only need to test for overloads on the same set of lines 6-2, 6-3, and 6-5. c) If there are overloads found, the generator at bus 2 will reduce its output and at the same time the load at bus 6 is going to reduce its load until there are no overloads due to the line outages found in part b above. How much should the generation on bus 2 and the load on bus 6 be reduced to eliminate all overloads. The PTDF factors, and the LODF factors for this system are on the next page.

4 POWER TRANSFER DISTRIBUTION FACTOR (PTDF) MATRIX Monitored Transaction Line From(Sell) - To(Buy) 1 to 4 1 to 5 1 to 6 2 to 4 2 to 5 2 to 6 3 to 4 3 to 5 3 to 6 1 to to to to to to to to to to to LINE OUTAGE DISTRIBUTION FACTOR (LODF) MATRIX Monitored Outage of one circuit Line From - To 1 to 2 1 to 4 1 to 5 2 to 3 2 to 4 2 to 5 2 to 6 3 to 5 3 to 6 4 to 5 5 to 6 1 to to to to to to to to to to to

5 Final Exam, EE5721, May 9, 2011 Problem 3 (30 points) Given the following power system: The network is to be modeled with a DC power flow with line reactances as follows: (assume 100 MVA base) x 12 = 0.1 pu x 23 = 0.05 pu The meters are all of the same type with a standard deviation of σ = 0.01 pu for each. The measured values are: m12 = 80 MW m21 = -75 MW m2 = 115 MW m23 = 150 MW m32 = -190 MW 1) Build the H matrix, label the rows and columns 2) Find the phase angles which result in a least squares fit to the measured values. 3) Do you suspect that any one of the measurements is a bad measurement? Just identify which you suspect is bad and say why.

6 Final Exam, EE5721, May 9, 2011 Problem 3) 20 Points Block Bidding of Generation in a Spot Price Auction You are to solve generation, load and pricing problems for a two bus power system. Each bus has a single generator and a single load as shown below: The generators are labeled G1 and G2 and the loads are labeled L1 and L2. The schedule of generation and load in this system is determined by an auction. The auction will consider the load to be variable in that the load shall submit a willingness to pay price to purchase blocks of energy. If the price of energy is below the load s willingness to pay price it is satisfied (assuming that there is sufficient transmission and generation capacity). If the price of energy from the generators is above the load s willingness to pay price - then the load is not satisfied (that is, the load block is not supplied). Draw the Supply Demand curves for this auction and show the clearing price. What is the flow on the line from 1 to 2 for each block sold, where flow from 1 to 2 is positive, from 2 to 1 is negative. The Generation and Load Prices are: Generator Blocks for sale: G1 Generator Blocks for sale: G2 Block Block Price Block Block Price Number MW $/MWh Number MW $/MWh G G G G Load bids to purchase: Load bids to purchase: L1 L2 Block Block Price Block Block Price Number MW $/MWh Number MW $/MWh L L L L

7 Final Exam, EE5721, May 9, 2011 Problem 4) 30 points You are asked to analyze the bilateral transaction versus a market auction for the three bus system below: Hydro Gen GEN 1 GEN 2 BUS 1 BUS MW max flow 700 MW max flow 600 MW max flow LOAD MW Green Load MW GEN 3 BUS 3 Green Load MW LOAD MW The Green Load Company owns loads at bus 2 and bus 3 and is trying to buy 300 MW at bus 2 from the Hydro Generator and 500 MW at bus 3 from the Hydro Generator. The Green Load Company s trading group calls up the Hydro Generator s trading group and asks for a price for 800 MW to be delivered 300 MW to bus 1 and 500 MW to bus 3. The Hydro Generator Trading Group has decided that it can get a high price from the Green Load and asks a price of 40 $/MWh. The traders at Green Load trading thinks that this price is much too high and says no thanks we will take our chances in the Market. Green Trading then puts in a bid to buy that is at $200/MWh so that they are assured of obtaining the 800 MW they need. We will solve this problem both ways and you will be asked to analyze the results. Bilateral Transaction Case: In this case the transactions are done completely outside the market and the MW transactions are superimposed onto the transmission system. The price for the MW sold by the hydro generator is 40 $/MWh. The generator has to pay any transmission charges determined by the results of the auction. You can treat this as two separate transactions 300 MW from the Hydro Generator on bus 1 to Green Load 1 on bus 2, and 500 MW from the same Hydro Generator on bus 1 to Green Load 2 on bus 3 with both transaction made at a price of 40 $/MWh. Next page

8 Final Exam, EE5721, May 9, 2011 Problem 4 continued: The results of the Bilateral calculations are: 700 MW max flow 700 MW 600 MW max flow ZERO MW FLOW Market case: Here the Hydro generator trading group places a bid to sell power into the market. This is done by giving a cost function to the auction operator of: C( P ) = P P 2 hydro hydro hydro The Green Loads both submit a bid to buy function of: C( P ) = 0 200P green _ load _1 green _ load _1 C( P ) = 0 200P green _ load _ 2 green _ load _ 2 Next page

9 Final Exam, EE5721, May 9, 2011 Problem 4 continued: The other generator cost functions and the cost functions of the loads are: Bid A B C Max (MW) Gen Gen Gen Load Load The market auction results with the hydro generator and the green loads as part of the market are: Hydro gen price = 40 $/MWh MARKET CASE 300 MW Hydro Gen GEN 1 Lambda= MW 1100 MW GEN 2 BUS 1 BUS MW max flow Lambda= MW Lambda= MW Green Load MW 700 MW max flow GEN MW LOAD MW BUS MW max flow ZERO MW FLOW LOAD MW Green Load MW MARKET CASE: No transactions Market participants are Gen 1, Gen 2, Gen 3 and Hydro Gen Load 2, Load 3, Green Load 1 and Green Load 2 Line 1-3 is at limit Note that the hydro generator only sells 300 MW and the Green Load Company still receives 300 MW at bus 2 and 500 MW at bus 3.

10 Final Exam, EE5721, May 9, 2011 Problem 4 continued: You are to find the following: 1) For the Bilateral case: The dollar income received by the Hydro generator, the transmission charges for each of the two bilateral transactions, and the net income of the Hydro Generator. 2) For the Bilateral case: The dollars paid by the Green Load Company for each of its loads. 3) For the Market Case: The dollar income received by the Hydro generator 4) For the Market Case: The dollars paid by the Green Load Company for each of its loads. 5) In this case we know that the Green Load had the opportunity to make direct transactions with the Hydro Generator and chose instead to go into the Market. Was this a good decision for the Green Load Company? 6) Was the Green Load s decision good or bad for the Hydro Generator? 7) If the Hydro Generating Company had purchased Financial Transmission Rights (FTRs) to insure against the transmission costs of the bilateral transactions: a. What are the FTRs it would need to have owned to pay off all transmission charges? Give details for all FTR contracts needed: i. From bus ii. To bus iii. MW amount b. What would be the Hydro Generation company s profits if it had owned the FTRs you specified in part a.

11 PROBLEM 1 Part b (n-1) Outage analysis Step 1: Calculate all flows with the 50MW added transaction fromula: Flow_ij_withtrans = flow_ij_start + PTDF_rs_ij * Mwtransaction_rs Line Flow_ii_withtrans flow_ij_start PTDF_rs_ij Mwtransaction_rs ij Step 2: Calculate all (n-1) contingency outage flows with the transaction of 50MW in place formula: Flow_ij_with_outage_nm = flow_ij_initial + LODF_ij_nm * flow_nm_initial Line flow_ij_with_outage_nm Flow_ii_withtrans outaged line nm LODF_ij_nm flow_nm_initial Limit ij initial flow OVERLOAD OVERLOAD OVERLOAD There are three overloads as shown above

12 PROBLEM 1 Part c) For this part it is best to reduce the transaction until the worst overload is eliminated, then check the remaining overloads. We will now use a formula that combines both the PTDF's and the LODF's so as to capture the transfer effect and the line outage effect in one place. formula: Flow_ij_withtrans_and_outage_nm = flow_ij_initial_withtrans + LODF_ij_nm * flow_nm_initial_withtrans = (flow_ij_start + PTDF_rs_ij * Mwtransaction_rs) + LODF_ij_nm * (flow_nm_start + PTDF_rs_nm * Mwtransaction_rs) = (flow_ij_start + LODF_ij_nm * flow_nm_start) + (PTDF_rs_ij + LODF_ij_nm * PTDF_rs_nm) * Mwtransaction_rs = flow_ij_with_outage_nm_notrans + adjusted_ptdf * Mwtransaction_rs where adjusted_ptdf = (PTDF_rs_ij + LODF_ij_nm * PTDF_rs_nm) line Flow_ij_withtrans_and_outage_nm flow_ij_start line LODF_ij_nm flow_nm_start flow_ij_with_outage_nm adjusted_ptdf wtransaction_rs ij nm _notrans OVERLOAD OVERLOAD OVERLOAD This obviously gives the same result, however, we can now solve for the amount to adjust the transaction to reduce any overloads. formula: for overloaded lines the needed change in flow is = flow_limit - flow with transaction and ourage then the formula for the required adjustment in transaction is: = ( (required adjustment in flow) - flow_ij_with_outage_nm)/adjusted_ptdf) line Flow_ij_withtrans_and_outage_nm Line Limits line required adjustment flow_ij_with_outage_nm adjusted_ptdf required adjustment ij nm in flow without transaction to transaction none none none Reduce the transaction by MW and all flows will be below limit and line 3-6 will be exactly at its limit of 45 MW when line 2-6 is opened.

13 Problem 2 solution H = θ2 θ 3 m m m m m R = H'*(R )*H = meas = Estimated values for bus phase angles in radians θ est 1 1 T 1 =(H'*(R )*H) *H *(R )*meas θ 2 = θ = Results Pflow 1-2 = Flow 2-3 = Pnet on bus 1 = Pnet on bus 2 = Pnet on bus 3 =

14 Problem 2 solution Errors: this is the error between measured value and calculated values using the estimated theta values: m12 error m21 error m2 error m23 error m32 error from this one would conclude that measurement m23 was in error because of the large MW error between m23 and its calculated value.

15

16

17

18 EE 5721 Final Exam Problem 4 solution BILATERAL TRANSACTION CASE Bus Bus LMP Values Hydro Generator to Green Load MW Transaction separate from Market Hydro Generator Green Load Price MW Sold Income Transmission Charge Net Profit Price MW Purchased Cost $12,000 0 $12, $12,000 Transmission Charge = (LMPreceive - LPMsend)*Mwtransacted = -$4,650 since negative, count as zero Hydro Generator to Green Load MW Transaction separate from Market Hydro Generator Green Load Price MW Sold Income Transmission Charge Net Profit Price MW Purchased Cost $20,000 $28,000 -$8, $20,000 Transmission Charge = (LMPreceive - LPMsend)*Mwtransacted = $28,000 SUMMARY FOR HYDRO GENERATOR COMPANY: net profit is $ $8000 = $4000 SUMMARY FOR GREEN LOAD COMPANY: net cost of the 800 MW of load = $ $20000 = $32000 MARKET CASE Bus Bus LMP Values Hydro and Green Load are part of the Market Hydro Generator Green Load Price MW Sold Income Transmission Charge Net Profit Price MW Purchased Cost Expense $12,180 0 $12, $18, $41,000 Net cost $59,390 SUMMARY FOR HYDRO GENERATOR COMPANY: net profit is $32,480 SUMMARY FOR GREEN LOAD COMPANY: net cost of the 800 MW of load = $18,390 + $41,000 = $59,390 CONCLUSIONS: Hydro gen actually sells less MW but makes more money in the market Green Load Co. pays more in the market and would have been better with the bilateral transactions of 300MW and 500MW FTR Analysis: This is the from to and MW necessary to cover the Hydro Gen Co. From - To MW Payoff Bus 1 to Bus No transmission charges so no payoff Bus 1 to Bus $28,000 This would change Hydro Gen Co profits to $32,000 income Hydro Gen Co. still makes more in the market

19 There was an error in writing the exam, the LMP value at bus 3 should have been 54 not 10.5 $/MWh in the Bilateral Transactions case. All students were graded on how they calculated the results using the incorrect value of I have also included the correct set of values just to show what it should have been and of course students were not expected to get these answers. Professor Wollenberg

20 EE 5721 Final Exam Problem 4 solution CORRECTED LMP AT BUS 2 BILATERAL TRANSACTION CASE Bus Bus LMP Values Hydro Generator to Green Load MW Transaction separate from Market Hydro Generator Green Load Price MW Sold Income Transmission Charge Net Profit Price MW Purchased Cost $12,000 $8,400 $3, $12,000 Transmission Charge = (LMPreceive - LPMsend)*Mwtransacted = $8,400 since negative, count as zero Hydro Generator to Green Load MW Transaction separate from Market Hydro Generator Green Load Price MW Sold Income Transmission Charge Net Profit Price MW Purchased Cost $20,000 $28,000 -$8, $20,000 Transmission Charge = (LMPreceive - LPMsend)*Mwtransacted = $28,000 SUMMARY FOR HYDRO GENERATOR COMPANY: net profit is $ $36,400 = $-4400 SUMMARY FOR GREEN LOAD COMPANY: net cost of the 800 MW of load = $ $20000 = $32000 MARKET CASE Bus Bus LMP Values Hydro and Green Load are part of the Market Hydro Generator Green Load Price MW Sold Income Transmission Charge Net Profit Price MW Purchased Cost Expense $12,180 0 $12, $18, $41,000 Net cost $59,390 SUMMARY FOR HYDRO GENERATOR COMPANY: net profit is $32,480 SUMMARY FOR GREEN LOAD COMPANY: net cost of the 800 MW of load = $18,390 + $41,000 = $59,390 CONCLUSIONS: Hydro gen actually sells less MW but makes more money in the market Green Load Co. pays more in the market and would have been better with the bilateral transactions of 300MW and 500MW FTR Analysis: This is the from to and MW necessary to cover the Hydro Gen Co. From - To MW Payoff Bus 1 to Bus $8,400 No transmission charges so no payoff Bus 1 to Bus $28,000 This would change Hydro Gen Co profits to $32,000 income Hydro Gen Co. still makes more in the market

Locational Marginal Pricing II: Unlocking the Mystery

Locational Marginal Pricing II: Unlocking the Mystery Locational Marginal Pricing II: Unlocking the Mystery Thomas D. Veselka Argonne National Laboratory Decision and Information Sciences Division Center for Energy, Environmental, and Economic Systems Analysis

More information

Power System Economics and Market Modeling

Power System Economics and Market Modeling Power System Economics and Market Modeling 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com PowerWorld Simulator OPF and Locational Marginal

More information

Two Settlement PJM /06/2016

Two Settlement PJM /06/2016 Two Settlement PJM 2016 Objectives Describe Two-Settlement process Day-Ahead Market Balancing Market Explain Virtual Transactions and their settlement Inc Offers Dec Bids Up-to Congestion Transactions

More information

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation MRTU Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation CRR Educational Class #2 CAISO Market Operations Why are LMPs important to the CRR Allocation & Settlement Process The CRR revenue

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

CHAPTER 5 SOCIAL WELFARE MAXIMIZATION FOR HYBRID MARKET

CHAPTER 5 SOCIAL WELFARE MAXIMIZATION FOR HYBRID MARKET 61 CHAPTER 5 SOCIAL WELFARE MAXIMIZATION FOR HYBRID MARKET 5.1 INTRODUCTION Electricity markets throughout the world continue to be opened to competitive forces. The underlying objective of introducing

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

PJM ARR and FTR Market

PJM ARR and FTR Market PJM ARR and FTR Market PJM State & Member Training Dept. PJM 2016 Objectives Explain the concepts and principles of Auction Revenue Rights and Financial Transmission Rights Describe how to participate

More information

Shift factors in ERCOT congestion pricing

Shift factors in ERCOT congestion pricing Shift factors in ERCOT congestion pricing Ross Baldick * March 5, 2003 1. Introduction In this paper, I discuss the ERCOT zonal and local congestion management scheme and analyze various economic and engineering

More information

LMP Implementation in New England

LMP Implementation in New England IEEE PES General Meeting, Montreal Eugene Litvinov June, 2006 2006 ISO New England Inc. 1 New England s Electric Power System 14 million people; 6.5 million households and businesses 350+ generators 8,000+

More information

Analysis of Electricity Markets. Lennart Söder

Analysis of Electricity Markets. Lennart Söder Analysis of Electricity Markets Lennart Söder Electric Power Systems Royal Institute of Technology March 2011 ii Contents 1 Basic electricity market modelling 1 1.1 Demand model...............................

More information

CUSTOMER GUIDE TO PJM BILLING

CUSTOMER GUIDE TO PJM BILLING CUSTOMER GUIDE TO PJM BILLING Billing Line Items include PJM Open Access Tariff (OATT) references, PJM Operating Agreement (OpAgr) references, and PJM Manual references. Reports are available for viewing,

More information

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

More information

Energy Markets - The Basics

Energy Markets - The Basics Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Fundamentals of Markets

Fundamentals of Markets Fundamentals of Markets Daniel Kirschen University of Manchester 2006 Daniel Kirschen 1 Let us go to the market... Opportunity for buyers and sellers to: compare prices estimate demand estimate supply

More information

ISO REVISED STAGING PLAN NO. 7

ISO REVISED STAGING PLAN NO. 7 ID Work Item Description 2 COMPLETE HIM Server An archival database is to be created for permanent historical storage of bidding, price and schedule data. HIM is defined in section 3.2.5 of the SI DSOW:

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at any bus is made up of three components:

More information

Generation Contingency Analysis

Generation Contingency Analysis Generation Contingency Analysis PJM 2016 Objectives Identify the procedure for redispatching generation to alleviate an overloaded monitored transmission line caused by a contingency PJM 2016 2 Agenda

More information

Proposal for a common set of requirements used for the continuous trading matching algorithm

Proposal for a common set of requirements used for the continuous trading matching algorithm Proposal for a common set of requirements used for the continuous trading matching algorithm 13 November 2017 1. Background 1. This document is a common proposal developed by all Transmission System Operators

More information

Implications of Cost and Bid Format on Electricity Market Studies: Linear Versus Quadratic Costs

Implications of Cost and Bid Format on Electricity Market Studies: Linear Versus Quadratic Costs Large Engineering Systems Conference on Power Engineering, July 2004, Halifax Canada. IEEE 2004 1 Implications of Cost and Bid Format on Electricity Market Studies: Linear Versus Quadratic Costs Mary B.

More information

LMP Calculation and Uplift

LMP Calculation and Uplift LMP Calculation and Uplift Anthony Giacomoni January 29, 2018 PJM 2017 Session Objectives Review fundamentals of locational marginal pricing (LMP) and uplift Review simple locational marginal pricing and

More information

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents

More information

. This function gives the supplier s behavior with respect to price and quantity.

. This function gives the supplier s behavior with respect to price and quantity. Demand and supply functions are used to describe the consumer and manufacturer behavior with respect to the price of a product or service and the quantity of a product or service. Different textbooks may

More information

Greater Than $1,000/MWh Cost Offer Revised Verification Procedure

Greater Than $1,000/MWh Cost Offer Revised Verification Procedure Greater Than $1,000/MWh Cost Offer Revised Verification Procedure Scott Benner Sr. Engineer, Market Analysis Market Implementation Committee May 3, 2017 FERC Order 831 & Offer Capping PJM is already compliant

More information

Tradable Pollution Permits

Tradable Pollution Permits Tradable Pollution Permits More Realistic Interventions to Solve Externality Problem Efficient Tax requires a lot of knowledge that government needs to have. Assigning property rights is not enough when

More information

Spring 06 Assignment 4: Game Theory and Auctions

Spring 06 Assignment 4: Game Theory and Auctions 15-381 Spring 06 Assignment 4: Game Theory and Auctions Questions to Vaibhav Mehta(vaibhav@cs.cmu.edu) Out: 3/08/06 Due: 3/30/06 Name: Andrew ID: Please turn in your answers on this assignment (extra copies

More information

Introduction to PowerWorld Simulator: Interface and Common Tools

Introduction to PowerWorld Simulator: Interface and Common Tools Introduction to PowerWorld Simulator: Interface and Common Tools through Interconnected System Operation 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com

More information

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012 PowrSym4 A Presentation by Operation Simulation Associates, Inc. February, 2012 1 Presentation Contents History of PowrSym Introduction to OSA The PowrSym3 Model PowrSym4 Enhancements 2 PowrSym Background

More information

Do not open this exam until told to do so. Solution

Do not open this exam until told to do so. Solution Do not open this exam until told to do so. Department of Economics College of Social and Applied Human Sciences K. Annen, Fall 003 Final (Version): Intermediate Microeconomics (ECON30) Solution Final (Version

More information

Standard Development Roadmap

Standard Development Roadmap Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect Parameter Tuning for Uneconomic Adjustments Lorenzo Kristov, Principal Market Architect Stakeholder Meeting May 13, 2008 Topics for Discussion Objectives of Current Parameter Tuning Effort Parameter Tuning

More information

Committed Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day.

Committed Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day. Proposed Tariff Revisions Attachment K-Appendix and Schedule 1 of the Operating Agreement Generator Offer Flexibility Senior Task Force Revisions Related To Make-Whole and Lost Opportunity Cost Payments

More information

Econ 101, section 3, F06 Schroeter Exam #2, Red. Choose the single best answer for each question.

Econ 101, section 3, F06 Schroeter Exam #2, Red. Choose the single best answer for each question. Econ 101, section 3, F06 Schroeter Exam #2, Red Choose the single best answer for each question. 1. Which of the following is consistent with elastic demand? a. A 10% increase in price results in a 5%

More information

Contingency Modeling Enhancements Issue Paper

Contingency Modeling Enhancements Issue Paper Contingency Modeling Enhancements Issue Paper March 11, 2013 California ISO Contingency Modeling Enhancements Issue Paper Table of Contents I. Executive Summary... 3 II. Plan for Stakeholder Engagement...

More information

New England States Committee on Electricity

New England States Committee on Electricity Renewable and Clean Mechanisms 2.0 Study Phase I: Scenario Analysis Winter 2017 New England States Committee on Electricity Overview Context Analytical Approach and Modeling Assumptions Scenario Analysis

More information

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff ConOp Internal NYISO HVDC Controllable Line Scheduling Concept of Operation Author: Scott Harvey, LECG Reviewers: ISO Staff LECG Staff Project Sponsor: Point of Contact: C. King B. Kranz Document Locator:

More information

Capacity Resource versus Energy Resource

Capacity Resource versus Energy Resource Capacity Resource versus Energy Resource Seasonal Capacity Resource Senior Task Force April 18, 2016 Capacity Resource or Energy Resource? When a new generator connects to PJM s system through the PJM

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING April 17, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

Evaluation of TCSC and DR Abilities for Congestion Management

Evaluation of TCSC and DR Abilities for Congestion Management Australian Journal of Basic and Applied Sciences, 5(6): 1011-1019, 2011 ISSN 1991-8178 Evaluation of TCSC and DR Abilities for Congestion Management 1 Y. Hoseynpoor, 2 T. PirzadehAshraf, 1 Sh. Sajedi,

More information

Market Settlements - Advanced

Market Settlements - Advanced Market Settlements - Advanced RPM Module PJM State & Member Training Dept. PJM 2017 Capacity vs. Energy Capacity A commitment of a resource to provide energy during PJM emergency under the capped energy

More information

Chapter 11. Decision Making and Relevant Information Linear Programming as a Decision Facilitating Tool

Chapter 11. Decision Making and Relevant Information Linear Programming as a Decision Facilitating Tool Chapter 11 Decision Making and Relevant Information Linear Programming as a Decision Facilitating Tool 1 Introduction This chapter explores cost accounting for decision facilitating purposes It focuses

More information

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator: ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

Economies of Scope and Value of Coordination in the Evolving Electric Power Systems

Economies of Scope and Value of Coordination in the Evolving Electric Power Systems Economies of Scope and Value of Coordination in the Evolving Electric Power Systems Mara Ilic, Marcelo Elizondo, Michael Patnik, Zayra Romo, Zhiyong Wu Abstract- In this paper we address the overwhelming

More information

2014 Integral Analytics, Inc.

2014 Integral Analytics, Inc. 1 2 3 4 5 6 7 Company Overview Putting Advanced Analytics into Software to Manage Utility Costs & Risks Smart Grid Solutions T&D Planning Storage & Renewable Evaluation DSM Planning & Evaluation Marketing

More information

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO Proposed Facility Study Report Project: A380_A383_A415_A414_A413 MISO # F088 Prepared for Midwest ISO January 15 th, 2010 Great River Energy Contact: Greg Schutte, Project Manager Great River Energy 1

More information

Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants *

Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants * Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants * R Naidoo and EJ Manning University of Pretoria, Pretoria, South Africa ABSTRACT:

More information

BILLING FORMULA FOR CUSTOMERS THAT SELL ELECTRICITY TO BC HYDRO PURSUANT TO AN ELECTRICITY PURCHASE AGREEMENT WITH A CONTRACTED GBL

BILLING FORMULA FOR CUSTOMERS THAT SELL ELECTRICITY TO BC HYDRO PURSUANT TO AN ELECTRICITY PURCHASE AGREEMENT WITH A CONTRACTED GBL Original of Page 1 BILLING FORMULA FOR CUSTOMERS THAT SELL ELECTRICITY TO BC HYDRO PURSUANT TO AN ELECTRICITY PURCHASE AGREEMENT WITH A CONTRACTED GBL 1.0 OVERVIEW AND APPLICABILITY This tariff supplement

More information

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright 2016 Ross Baldick www.ece.utexas.edu/~baldick/classes/394v/ee394v.html 1 7 Economic decision-making

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

Psychology and Economics Field Exam August 2015

Psychology and Economics Field Exam August 2015 Psychology and Economics Field Exam August 2015 There are 3 questions on the exam. Please answer the 3 questions to the best of your ability. Do not spend too much time on any one part of any problem (especially

More information

Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition

Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition Chris Mensah-Bonsu, Ph.D., Principal Consulting Advisor GRIDCo Bernard Modey, Director, System Operations - GRIDCo

More information

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to

More information

Section 7-3 Estimating a Population Mean: σ Known

Section 7-3 Estimating a Population Mean: σ Known Section 7-3 Estimating a Population Mean: σ Known Created by Erin Hodgess, Houston, Texas Revised to accompany 10 th Edition, Tom Wegleitner, Centreville, VA Slide 1 Key Concept Use sample data to find

More information

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS Reliability Coordinator Processes and Tools Objectives Describe how the FRCC Security Process addresses planning/coordination of the Bulk Electric System Describe

More information

ISO Course Outline. Market Transactions Class

ISO Course Outline. Market Transactions Class ISO Course Outline Purpose Market Transactions Class This two-day training class is intended to be one of the cornerstones of the market training program and is designed to review the market concepts and

More information

Price Discrimination: Exercises Part 2

Price Discrimination: Exercises Part 2 Price Discrimination: Exercises Part Sotiris Georganas Royal Holloway University of London Problem 1 An economics journal is considering offering a new service which will send articles to readers by email.

More information

Draft Whitepaper to Platte River Board of Directors

Draft Whitepaper to Platte River Board of Directors Draft Whitepaper to Platte River Board of Directors Report on Organized Power Markets RTOs and ISOs Presented for the October 2016 Board Meeting Overview This report on the potential formation of a regional

More information

Economics 101 Fall 2013 Answers to Homework #6 Due Tuesday, Dec 10, 2013

Economics 101 Fall 2013 Answers to Homework #6 Due Tuesday, Dec 10, 2013 Economics 101 Fall 2013 Answers to Homework #6 Due Tuesday, Dec 10, 2013 Directions: The homework will be collected in a box before the lecture. Please place your name, TA name and section number on top

More information

PJM Proposal for Incremental Auction Redesign

PJM Proposal for Incremental Auction Redesign PJM Proposal for Incremental Auction Redesign Jeff Bastian Manager, Capacity Market Operations Incremental Auction Senior Task Force May 31, 2017 www.pjm.com RPM Depends on Physical Resources RPM is designed

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

14.01 Principles of Microeconomics, Fall 2007 Chia-Hui Chen November 7, Lecture 22

14.01 Principles of Microeconomics, Fall 2007 Chia-Hui Chen November 7, Lecture 22 Monopoly. Principles of Microeconomics, Fall Chia-Hui Chen November, Lecture Monopoly Outline. Chap : Monopoly. Chap : Shift in Demand and Effect of Tax Monopoly The monopolist is the single supply-side

More information

Testing for Market Efficiency with Transactions Costs: An Application to Convergence Bidding in Wholesale Electricity Markets

Testing for Market Efficiency with Transactions Costs: An Application to Convergence Bidding in Wholesale Electricity Markets Testing for Market Efficiency with Transactions Costs: An Application to Convergence Bidding in Wholesale Electricity Markets Akshaya Jha and Frank A. Wolak April 9, 2013 Abstract With risk neutral traders

More information

MISO Initial Investigation Report on TLR Level 5 Event. For. FG 3706 Arnold-Hazleton 345 kv. July 02, 2003

MISO Initial Investigation Report on TLR Level 5 Event. For. FG 3706 Arnold-Hazleton 345 kv. July 02, 2003 MISO Initial Investigation Report on TLR Level 5 Event For FG 76 Arnold-Hazleton 5 kv July 2, 2 Page of 2 Contents of the Initial Investigation Report Description of purpose/cause of hold/curtailment...

More information

Schedule 9 and 10 PJM /23/2017

Schedule 9 and 10 PJM /23/2017 Schedule 9 and 10 PJM 2017 Schedule 9 PJM Scheduling, System Control and Dispatch Service How PJM pays its bills Unbundled Those who use the service, pay for it 6 categories plus FERC, NERC, RFC, OPSI,

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

Lecture 3 Mankiw chapters 4 and 5

Lecture 3 Mankiw chapters 4 and 5 In-Class Exam 1 1) Efficiency is not the same than equity. Why? Give an example in which an efficient allocation has been achieved but it creates significant inequalities. 2) Explain each of the following

More information

Benefits from Generation and Storage on the Distribution System

Benefits from Generation and Storage on the Distribution System Benefits from Generation and Storage on the Distribution System Andrew Levitt Senior Market Strategist Emerging Markets Special MRC Meeting DER Aug 24, 2016 Generation/Storage Resource Location and Types

More information

ConOp. Real-Time Scheduling Concept of Operation 1 MSWG. Document Locator: Revision History. Additions, deletions, modifications

ConOp. Real-Time Scheduling Concept of Operation 1 MSWG. Document Locator: Revision History. Additions, deletions, modifications ConOp Real-Time Scheduling Concept of Operation 1 Author: NYISO Staff Reviewers: NYISO Staff MSWG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

Green Certificate Document which proves that a quantity of 1 MWh of electricity was produces from renewable energy sources.

Green Certificate Document which proves that a quantity of 1 MWh of electricity was produces from renewable energy sources. Green Certificates Market Description OPCOM Green Certificates Market Operator legal person which assures Green Certificates trading and determines the prices on the Centralized Green Certificates Market,

More information

ENGG1811: Data Analysis using Excel 1

ENGG1811: Data Analysis using Excel 1 ENGG1811 Computing for Engineers Data Analysis using Excel (weeks 2 and 3) Data Analysis Histogram Descriptive Statistics Correlation Solving Equations Matrix Calculations Finding Optimum Solutions Financial

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

IMM Marginal Loss Allocation Methodology Recommendation

IMM Marginal Loss Allocation Methodology Recommendation IMM Marginal Loss Allocation Methodology Recommendation TITF October 26, 2010 Joseph Bowring John Dadourian History FERC Order (Docket EL08-14) required marginal loss surplus allocations for up to congestion

More information

Alternatives for Addressing the Interface Pricing Flaw

Alternatives for Addressing the Interface Pricing Flaw Alternatives for Addressing the Interface Pricing Flaw Presented to: Joint and Common Market Meeting David Patton President, Potomac Economics March 21, 2014 Introduction MISO and PJM s interface prices

More information

How to Use a Weird "Trade- In" Loophole to Bank $300 to $500 PER DAY

How to Use a Weird Trade- In Loophole to Bank $300 to $500 PER DAY How to Use a Weird "Trade- In" Loophole to Bank $300 to $500 PER DAY Presented by: Luke Sample Hosted by: John S. Rhodes Copyright 2016 WebWord, LLC. All Rights Reserved. This guide may not be reproduced

More information

Midterm 1 60 minutes Econ 1101: Principles of Microeconomics October 8, Exam Form A

Midterm 1 60 minutes Econ 1101: Principles of Microeconomics October 8, Exam Form A Midterm 1 60 minutes Econ 1101: Principles of Microeconomics October 8, 2012 Exam Form A Name Student ID number Signature Teaching Assistant Section The answer form (the bubble sheet) and this question

More information

Deregulation, Locational Marginal Pricing, and Critical Load Levels with Applications

Deregulation, Locational Marginal Pricing, and Critical Load Levels with Applications ECE 620 Lecture Nov. 2nd, 2016 Deregulation, Locational Marginal Pricing, and Critical Load Levels with Applications Fangxing (Fran) Li, Ph.D., P.E. Professor Dept. of EECS The University of Tennessee

More information

Flexible Transmission Decision Support

Flexible Transmission Decision Support Flexible Transmission Decision Support Kory W. Hedman Arizona State University PSERC Webinar April 21, 2015 1 Outline Key Takeaway Points, Project Overview, Industry Practices Flexible Transmission Decision

More information

Interconnection Training Program

Interconnection Training Program Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Methodology for Calculating Operating Limits for Generators

Methodology for Calculating Operating Limits for Generators Page 1 of 6 Methodology for Calculating Operating Limits for Generators I. Generator Operating Limit Definition The Generator Operating Limit (GOL) for a generator establishes a pathspecific, directional,

More information

External Proxy Bus for Northport/Norwalk Cable

External Proxy Bus for Northport/Norwalk Cable Market Structure Working Group June 2003 External Proxy Bus for Northport/Norwalk Cable Navigant Consulting, Inc. www.lipower.org Context The issue of when it is appropriate to have multiple external nodes

More information

Chapter 5: Variable pay or straight salary

Chapter 5: Variable pay or straight salary Chapter 5: Variable pay or straight salary University Professors get a straight salary which is not even based on age (may be considered high or low, depending on your point of view). Should we introduce

More information

Measurement and sampling

Measurement and sampling Name: Instructions: (1) Answer questions in your blue book. Number each response. (2) Write your name on the cover of your blue book (and only on the cover). (3) You are allowed to use your calculator

More information

Transmission Network Congestion in Deregulated Wholesale Electricity Market

Transmission Network Congestion in Deregulated Wholesale Electricity Market Transmission Network Congestion in Deregulated Wholesale Electricity Market N S Modi, Member IEEE, B R Parekh Abstract Electricity market plays an important role in improving the economics of electrical

More information

Reactive Power Support Services in Electricity Markets

Reactive Power Support Services in Electricity Markets PSERC Reactive Power Support Services in Electricity Markets Costing and Pricing of Ancillary Services Final Project Report Power Systems Engineering Research Center A National Science Foundation Industry/University

More information

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007 ISO-NE FCM Capacity Market Design Scott M. Harvey October 9, 2007 Summary The ISO-NE FCM capacity market design embodies many improvements over the prior ISO-NE capacity market. Five of these improvements

More information

Available Transfer Capability Implementation Document TP-OP-005-r15 Effective Date: AUG Purpose. 2 Scope. 3 Definitions

Available Transfer Capability Implementation Document TP-OP-005-r15 Effective Date: AUG Purpose. 2 Scope. 3 Definitions 001-1 R3.1 001-1 R1 R1.1 R1.2 001-1 R3.5 1 Purpose MISO has elected to utilize a flow-based approach for the evaluation of transmission service requests ( TSRs ). The Available Flowgate Capacity Methodology

More information

Practice Problems 2. State Price Elasticity Massachussets $ Ohio $ Utah $

Practice Problems 2. State Price Elasticity Massachussets $ Ohio $ Utah $ Firms and Markets Assignments and Problems Price Discrimination and Auctions Practice Problems 2 1. Many states sell vanity license plates (with personalized initials) to drivers, for extra fees. The cost

More information

Capacity Performance Training. June 24, 2015

Capacity Performance Training. June 24, 2015 Capacity Performance Training June 24, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

not to be republished NCERT Chapter 6 Non-competitive Markets 6.1 SIMPLE MONOPOLY IN THE COMMODITY MARKET

not to be republished NCERT Chapter 6 Non-competitive Markets 6.1 SIMPLE MONOPOLY IN THE COMMODITY MARKET Chapter 6 We recall that perfect competition was theorised as a market structure where both consumers and firms were price takers. The behaviour of the firm in such circumstances was described in the Chapter

More information

Available Transfer Capability Implementation Document TP-OP-005-r18 Effective Date: DEC Purpose. 2 Scope. 3 Definitions

Available Transfer Capability Implementation Document TP-OP-005-r18 Effective Date: DEC Purpose. 2 Scope. 3 Definitions 001-1a R3.1 001-1a R1 1 Purpose MISO has elected to utilize a flow-based approach for the evaluation of transmission service requests ( TSRs ). The Available Flowgate Capacity Methodology used requires

More information

Introduction to Analytics Tools Data Models Problem solving with analytics

Introduction to Analytics Tools Data Models Problem solving with analytics Introduction to Analytics Tools Data Models Problem solving with analytics Analytics is the use of: data, information technology, statistical analysis, quantitative methods, and mathematical or computer-based

More information

The Competitive Model in a More Realistic Setting

The Competitive Model in a More Realistic Setting CHAPTER 13 Monopolistic Competition: The Competitive Model in a More Realistic Setting Chapter Summary and Learning Objectives 13.1 Demand and Marginal Revenue for a Firm in a Monopolistically Competitive

More information

Question 2: How do we make decisions about inventory?

Question 2: How do we make decisions about inventory? uestion : How do we make decisions about inventory? Most businesses keep a stock of goods on hand, called inventory, which they intend to sell or use to produce other goods. Companies with a predictable

More information

Cost Development Guidelines

Cost Development Guidelines DRAFT Manual 15 Language Clean Version Approved by CDS on October 25, 2012 PJM Manual 15: Cost Development Guidelines Revision: 20 Effective Date: November 1, 2012 Prepared by Cost Development Subcommittee

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. PJM Update 4. MISO Update 5. Congestion Overlap Solution 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM

More information

Quadratic Regressions Group Acitivity 2 Business Project Week #4

Quadratic Regressions Group Acitivity 2 Business Project Week #4 Quadratic Regressions Group Acitivity 2 Business Project Week #4 In activity 1 we created a scatter plot on the calculator using a table of values that were given. Some of you were able to create a linear

More information

The Efficient Allocation of Individuals to Positions

The Efficient Allocation of Individuals to Positions The Efficient Allocation of Individuals to Positions by Aanund Hylland and Richard Zeckhauser Presented by Debreu Team: Justina Adamanti, Liz Malm, Yuqing Hu, Krish Ray Hylland and Zeckhauser consider

More information

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo

More information

Capacity Performance Training. March 16, 2015

Capacity Performance Training. March 16, 2015 Capacity Performance Training March 16, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information