SAWS WATER PROJECTS MODELING CRITERIA GUIDELINES

Size: px
Start display at page:

Download "SAWS WATER PROJECTS MODELING CRITERIA GUIDELINES"

Transcription

1 SAWS WATER PROJECTS MODELING CRITERIA GUIDELINES July U.S. Highway 281 North San Antonio, Texas 78212

2 Modeling Criteria Guidelines, July 2016 TABLE OF CONTENTS MODELING CRITERIA GUIDELINES FOR SAWS WATER PROJECTS... 3 HYDRAULIC GRADE LINE REQUEST FORM... 3 DEVELOPER PROCESS FOR SUBMITTING A HYDRAULIC MODEL... 3 APPENDIX A - HYDRAULIC GRADE LEVEL MAP APPENDIX B - EXAMPLE OF HYDRAULIC MODEL INPUTS... 6 APPENDIX C - EXAMPLE OF HYDRAULIC MODEL OUTPUTS

3 Modeling Criteria Guidelines for SAWS Water Projects Modeling Criteria Guidelines, July 2016 Hydraulic Grade Line Request Form Date Project Name Location Map - must include boundary of development tract and proposed connection point to existing water main Location of Development - if an address cannot be provided, then the closest street intersection and intersection corner will need to be provided Engineer s contact name, company, phone number, fax number, mailing address and address EDU s by Pressure Zone Fire Flow 25 psi Type of Development: Commercial/Industrial, Residential/Apartment Comments Developer Process for Submitting a Hydraulic Model Obtain the Pressure Zone static gradient for the development (Appendix A) Provide Development Master Plan reflecting roads, development densities, pressure zone limits, development units and contours with labels Provide development unit schedule by years with estimated service requirements (EDU s) by development unit per year Provide information on fire flow requirements for each development unit, per COSA adopted Fire Code and Local amendments, and SAWS Development criteria Submit hydraulic model using the criteria stated in Chapter 9 of the Utility Service Regulations and identify the software version used for the hydraulic model Submit the following to SAWS for review: a. Master Water Plan Exhibit to show the following: Water pipe layout of the development Unit or sub-development boundary limits Road alignments All anticipated water easements Pressure Zone boundary line(s) Contours with labels Pipe size(s) and location Fire hydrant locations state if existing or proposed Connection point(s) to existing SAWS/District Special Project (DSP) water main All proposed water infrastructure required to serve the proposed development including, but not limited to; tanks, wells, pumps, etc. b. Hydraulic Model Input Data (Appendix B) associated with the above map shall include the following: Establish scenarios by unit(s), when applicable. Scenarios should include domestic demands and fire flow evaluations for all areas within each scenario. One scenario shall reflect completed development of all units at full build-out. Pipe diameter, pipe length, C factor Fire hydrant existing and proposed with elevation and demand value 3

4 Modeling Criteria Guidelines, July 2016 Junction ground elevation and demand value Connection point(s) to SAWS/DSP water line ground elevation and hydraulic grade line Tanks hydraulic grade line, volume, ground surface elevation, configuration (ground storage or elevated storage) Pumps design point (flow and total dynamic head) or a pump curve, ground surface elevations, firm and ultimate capacities Wells sustainable yield c. Hydraulic Model Output (Appendix C) associated with the above map shall be legible and include the following: Provide data result tables and graphic exhibits for each scenario Data Result/Output Tables Pipe domestic flow velocity and head loss for each scenario Fire hydrant residual pressure under fire flow conditions Junction pressure for domestic Connection Point(s) to SAWS/DSP water line pressure/hydraulic grade line for domestic Tanks fill/drain rate Pumps flow from each pump Exhibits to be provided for each scenario Pipe size, show labels, domestic flow direction and velocities Node show labels, domestic condition pressures, estimated fire flow values, identify node(s) with minimum pressure that control fire flows throughout the development piping network. Junction locations must include the lowest and highest ground elevations where the proposed pipe will be located. If the proposed pipe has a dead-end, then the length from previous junction to the end of pipe along with pipe diameter must be stated. Pumps, tanks, wells show labels, provide graphs of flow rates, water levels, etc. as part of the scenario summary Fire hydrants show label, estimated fire flow values for mains at those locations Model ID s shall be labeled on the exhibit and legible. Summary of findings d. Engineering Report shall include the following: A brief summary of the development A brief description of development schedule reflecting service requirements by year and by units Summary of scenario descriptions Summary of scenario modeling results Available fire flow based on existing and proposed infrastructure Provide recommendations, if any, for potential oversizing of mains or facilities Exhibits printed on sizes that are easily readable and clearly illustrate required output data and results (tables, etc.) for hydraulic model A CD with appropriate dwg, dgn, shp files as noted above, with the complete Master Water Plan included. 4

5 Appendix A - Hydraulic Gradient Level Map HGL (ft) PZ Max Ground Elev (ft) Min Ground Elev (ft) B A C, 950E, 950W , 5A C A W B D D Y , C Z F L D , 10A, 10B N X D T , 11A, 11M CTI S B, 11O E E, 11K B, 12SSH C , 12A F C A ") ") µ Created: July 2016

6 Appendix B - Example of Hydraulic Model Inputs Note: The following examples should be used more as a reference due to varying hydraulic modeling software having different layout styles for model inputs. Pipe: Junction:

7 Modeling Criteria Guidelines, July 2016 Appendix B (continued) Note: The following examples should be used more as a reference due to varying hydraulic modeling software having different layout styles for model inputs. Tank: Pump: Well: 7

8 Modeling Criteria Guidelines, July 2016 Appendix C - Example of Hydraulic Model Outputs Note: The following examples should be used more as a reference due to varying hydraulic modeling software having different layout styles for model outputs. Pipes: Junctions: 8

San Antonio Water System Infrastructure Planning Application for Subdivision Plat Review

San Antonio Water System Infrastructure Planning Application for Subdivision Plat Review FN001-4 REV A 6/09 Applicant / Developer / Owner San Antonio Water System Infrastructure Planning Application for Subdivision Plat Review Plat I.D. # Name Contact Person Address Phone / Fax Number Applicant

More information

CHAPTER 4 HYDRAULIC ANALYSIS

CHAPTER 4 HYDRAULIC ANALYSIS CHAPTER 4 HYDRAULIC ANALYSIS This chapter presents information on the computer hydraulic model of the City s water system and the results of hydraulic analyses. The purpose of the hydraulic analysis is

More information

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards 2.9. WATER SYSTEM DESIGN Ivins City Standard Specifications for Design and Construction All culinary water mains and appurtenances shall be designed to provide for adequate future service for all contiguous

More information

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS DESIGN STANDARDS SECTION 2 INDEX ITEM DESCRIPTION 2.00 GENERAL STATEMENT 2.01 WATER DISTRIBUTION

More information

ENGINEERING REPORT WATER SUPPLY

ENGINEERING REPORT WATER SUPPLY PROPOSED RESIDENTIAL DEVELOPMENT, CORAL SPRINGS TRELAWNY FCS #: 1124/76/C ENGINEERING REPORT WATER SUPPLY PREPARED FOR Gore Developments Limited 2c Braemar Ave, Kingston 10 FEBRUARY 2012 1 TABLE OF CONTENTS

More information

CITY OF SASKATOON DESIGN AND DEVELOPMENT STANDARDS MANUAL SECTION FOUR WATER DISTRIBUTION SYSTEM

CITY OF SASKATOON DESIGN AND DEVELOPMENT STANDARDS MANUAL SECTION FOUR WATER DISTRIBUTION SYSTEM CITY OF SASKATOON DESIGN AND DEVELOPMENT STANDARDS MANUAL SECTION FOUR WATER DISTRIBUTION SYSTEM 2018 TABLE OF CONTENTS Section Four Water Distribution System SECTION PAGE NUMBER 1. Objective...1 2. Submissions

More information

Section 7 Hydraulic Model Development and Evaluation Criteria

Section 7 Hydraulic Model Development and Evaluation Criteria Section 7 Hydraulic Model Development and Evaluation Criteria The hydraulic evaluation conducted to develop this master plan was performed using a computer model of the reclaimed water distribution system.

More information

Agua Consulting Inc. Engineered Water Solutions

Agua Consulting Inc. Engineered Water Solutions Agua file: 023-01.340 District of Summerland 9215 Cedar Avenue Box 159 Summerland, BC V0H 1Z0 Attention: Mr. Devon van der Meulen, Manager of Utilities Dear Devon: RE: Banks Crescent Proposed 346 Unit

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

FREELAND WATER & SEWER DISTRICT BERCOT ROAD INTERTIE STUDY

FREELAND WATER & SEWER DISTRICT BERCOT ROAD INTERTIE STUDY FREELAND WATER & SEWER DISTRICT ISLAND COUNTY WASHINGTON BERCOT ROAD INTERTIE STUDY G&O #13507 NOVEMBER 2013 FREELAND WATER & SEWER DISTRICT ISLAND COUNTY WASHINGTON BERCOT ROAD INTERTIE STUDY G&O #13507

More information

APPENDIX M VANDEN MEADOWS PROJECT WATER MODELING STUDY AND TECHNICAL MEMORANDUM

APPENDIX M VANDEN MEADOWS PROJECT WATER MODELING STUDY AND TECHNICAL MEMORANDUM APPENDIX M VANDEN MEADOWS PROJECT WATER MODELING STUDY AND TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Date: March 16, 2011 FROM: Victor M. Alaniz, P.E. Nolte Associates, Inc. 2495 Natomas Park Drive, Fourth

More information

WATER MAIN EXTENSION DESIGN REQUIREMENTS

WATER MAIN EXTENSION DESIGN REQUIREMENTS This guideline provides minimum requirements for the design of new water main extensions. This guide is not to be used as a substitution for the detailed design of the water system. The Developer s Engineer

More information

KUM & GO 300 SUBDIVISION THORNTON, COLORADO

KUM & GO 300 SUBDIVISION THORNTON, COLORADO FINAL UTILITY STUDY KUM & GO 300 SUBDIVISION THORNTON, COLORADO PREPARED FOR: KUM & GO, L.C. 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266 PH: (515) 457-6232 CONTACT: RYAN J. HALDER PREPARED BY: OLSSON

More information

PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS

PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS 39 AUGUST 2005 TABLE OF CONTENTS PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS PAGE SECTION 1 DESIGN CRITERIA 41 SECTION 2 SUBMITTAL 44 SECTION 3 STRUCTURES

More information

TxDOT Houston District Permit Requirements (Information contained herein is subject to change)

TxDOT Houston District Permit Requirements (Information contained herein is subject to change) Houston District Permit Requirements (Information contained herein is subject to change) Access Driveway for Commercial / Industrial Developments; or Street Tie-In / Drainage-Only 1) Complete the three

More information

Section 5 - Planning Criteria. Section 5

Section 5 - Planning Criteria. Section 5 Section 5 - Planning Criteria Section 5 SECTION 5 PLANNING CRITERIA This section presents the design criteria and methodologies for analysis used to evaluate the existing distribution system and its facilities

More information

ADVANCED WATER DISTRIBUTION MODELING AND MANAGEMENT

ADVANCED WATER DISTRIBUTION MODELING AND MANAGEMENT H A E S T A D M E T H O D S ADVANCED WATER DISTRIBUTION MODELING AND MANAGEMENT F i r s t E d i t i o n Table of Contents Preface Continuing Education Units About the Software xv xix xxi Chapter 1 Introduction

More information

255 NORTHFIELD DRIVE EAST

255 NORTHFIELD DRIVE EAST 255 NORTHFIELD DRIVE EAST Fire Flow/Water Demand Analysis Project Location: 255 Northfield Drive East Waterloo, Ontario Prepared for: Abbey Ridge Developments Inc. 22 King Street South, Suite 300 Waterloo,

More information

APPENDIX B. WSSC Design Criteria for Water Distribution Systems

APPENDIX B. WSSC Design Criteria for Water Distribution Systems a. System Requirements ) Pressure Requirements APPENDIX B WSSC Design Criteria for Water Distribution Systems a) The water distribution system shall have adequate capacity to supply domestic demand to

More information

El Margarita Development Analysis

El Margarita Development Analysis 303 Second Street, Suite 300 South San Francisco, California 94107 415-243-2150 FAX: 415-896-0999 El Margarita Development Analysis 28 January 2015 Prepared for City of Yuba City 1201 Civic Center Boulevard

More information

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations.

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations. COACHELLA VALLEY WATER DISTRICT DOMESTIC WATER CHECKLIST Tract/Parcel No: Project Common Name: Developer: Engineer: Engineer Signature: Date: Phone: Phone: Print: This is only a general checklist; please

More information

WATER AND SANITARY SEWER

WATER AND SANITARY SEWER RUBIDOUX COMMUNITY SERVICES DISTRICT WATER AND SANITARY SEWER DESIGN & CONSTRUCTION MANUAL THIS PAGE INTENTIONALLY BLANK RUBIDOUX COMMUNITY SERVICES DISTRICT WATER AND SANITARY SEWER SYSTEM DESIGN AND

More information

Presentation Summary. What, Why, and How. Building the Model. Facility Data Acquisition. Model Calibration. Real World Applications/Case Studies

Presentation Summary. What, Why, and How. Building the Model. Facility Data Acquisition. Model Calibration. Real World Applications/Case Studies Uday Khambhammettu Randolph Rostas VA AWWA Presentation Summary What, Why, and How Building the Model Facility Data Acquisition Model Calibration Real World Applications/Case Studies Model Maintenance

More information

EXISTING SYSTEM ANALYSIS

EXISTING SYSTEM ANALYSIS Chapter 6 EXISTING SYSTEM ANALYSIS This chapter describes the evaluation of the existing water distribution system, using the calibrated hydraulic model and the 2006 water demands. The system evaluations

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System INSTRUCTIONS: This form shall be completed and submitted (in duplicate)

More information

ENGINEERING REVIEW CHECKLIST City of Mount Clemens

ENGINEERING REVIEW CHECKLIST City of Mount Clemens (To be completed by the Developer s & Submitted with ing Plans) DATE: PROJECT NAME: Site Plan Approved: Date DESIGN ENGINEERING COMPANY: ing Company Contact Information: Name: Phone: Email: Owner Contact

More information

NZQA registered unit standard version 4 Page 1 of 5

NZQA registered unit standard version 4 Page 1 of 5 Page 1 of 5 Title Describe drinking-water supply reticulation systems Level 5 Credits 8 Purpose People credited with this unit standard are able to describe: the reticulated services found on public and

More information

SYSTEM ID: KY 10 NARRATIVE DESCRIPTION

SYSTEM ID: KY 10 NARRATIVE DESCRIPTION SYSTEM ID: KY 10 NARRATIVE DESCRIPTION KY 10 is primarily a branched system in Kentucky with the following assets: 13 Tanks, 13 Pumps, 1 Water Treatment Plant, and approximately 1353879 feet of pipe. KY

More information

SYSTEM ID: KY 3 NARRATIVE DESCRIPTION

SYSTEM ID: KY 3 NARRATIVE DESCRIPTION SYSTEM ID: KY 3 NARRATIVE DESCRIPTION KY 3 is primarily a grid system in Kentucky with the following assets: 3 Tanks, 5 Pumps, 1 Water Treatment Plant, and approximately 277,022 feet of pipe. KY 3 provides

More information

Storage and pumping capacity analysis using hydraulic modeling

Storage and pumping capacity analysis using hydraulic modeling Storage and pumping capacity analysis using hydraulic modeling G. MacPherson City of Chilliwack, B.C., Canada W. de Schaetzen & S. Cripps GeoAdvice Inc., Vancouver, B.C., Canada ABSTRACT: This paper summarizes

More information

SUBDIVISION IMPROVEMENT PLANS FORM

SUBDIVISION IMPROVEMENT PLANS FORM Page 1 of 9 CITY OF CONROE SUBDIVISION IMPROVEMENT PLANS CHECKLIST SUBMIT THREE FINAL SETS OF PLANS (maximum size 24 X36 ), OTHER ITEMS LISTED, AND THIS COMPLETED, CERTIFIED CHECKLIST TO THE ENGINEERING

More information

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:

More information

CITY OF BENICIA IMPROVEMENT PLAN REVIEW CHECKLIST

CITY OF BENICIA IMPROVEMENT PLAN REVIEW CHECKLIST CITY OF BENICIA DEPARTMENT OF PUBLIC WORKS ENGINEERING DIVISION 250 EAST L STREET, BENICIA, CA 94510 Phone: (707) 746-4240 CITY OF BENICIA IMPROVEMENT PLAN REVIEW CHECKLIST Tract Map # This checklist is

More information

Silver Seven Corporate Centre Phase 1

Silver Seven Corporate Centre Phase 1 SERVICING BRIEF Silver Seven Corporate Centre Phase 1 15 & 19 Frank Nighbor Place and 737 & 777 Silver Seven Road Kanata, Ontario Report No. 12022-SB May 31, 2012 Revised October 23, 2012 D. B. G R A Y

More information

Woodbury - Aurora Metro Station

Woodbury - Aurora Metro Station Woodbury - Aurora Metro Station Master Utility Report Aurora, Colorado E. Centrepoint Dr. and E. Alameda Dr. Prepared By: Galloway 6162 S. Willow Drive, Suite 32 Greenwood Village, CO 8111 33.77.8884 POC:

More information

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###)

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###) CITY OF OXNARD ENGINEERING DIVISION REQUIRED FORMAT AND CONTENTS HYDROLOGIC AND HYDRAULIC DRAINAGE REPORTS This report will provide a basis for design of the drainage system for the subject project. The

More information

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413 Page: 1 of 5 CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413 COMMERCIAL/RESIDENTIAL UTILITY PLAN COMPLETENESS CHECK LIST Updated

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

Riverside South Block 3/4, Richcraft Group of Companies Inc., City of Ottawa SERVICING REPORT

Riverside South Block 3/4, Richcraft Group of Companies Inc., City of Ottawa SERVICING REPORT Riverside South Block 3/4, Richcraft Group of Companies Inc., City of Ottawa SERVICING REPORT Prepared by: Stantec Consulting Ltd. 1505 Laperriere Avenue Ottawa, ON K1Z 7T1 File: 160401004/83 January 17,

More information

Project: Developer/Designer: Reviewer:

Project: Developer/Designer: Reviewer: City of Charlottesville, Virginia Engineering Plan Review Checklist (Site Plans, Site Plan Amendments, and Major Subdivisions) 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182;

More information

CITY OF ANAHEIM SEWER DESIGN MANUAL

CITY OF ANAHEIM SEWER DESIGN MANUAL CITY OF ANAHEIM CITY OF ANAHEIM DEPARTMENT OF PUBLIC WORKS SUBDIVISION SECTION SEWER DESIGN MANUAL TABLE OF CONTENTS 1. SIZING... 2 Design flows:... 2 Roughness coefficient (n):... 2 Velocity (Average

More information

CHAPTER 4 Hydraulic Model Management and Documentation Protocols

CHAPTER 4 Hydraulic Model Management and Documentation Protocols CHAPTER 4 Hydraulic Model Management and Documentation Protocols It is important for the City s hydraulic model to be updated regularly to reflect newly installed/modified water system pipelines and facility

More information

Draft Report. Prepared for: City of Ottawa. Prepared by: Stantec Consulting Ltd Clyde Avenue Ottawa, ON, K2C 3G4. Insert revision record

Draft Report. Prepared for: City of Ottawa. Prepared by: Stantec Consulting Ltd Clyde Avenue Ottawa, ON, K2C 3G4. Insert revision record Feasibility Study - Extension of Carlsbad Springs Trickle Feed Water System Area East of Carlsbad Springs (Russell Road, Carlsbad Lane, Sabourin Road & Boundary Road Industrial Park Draft Report Prepared

More information

PLANNING AND ZONING COMMISSION APPLICATION FOR IMPROVEMENT PLAT APPROVAL

PLANNING AND ZONING COMMISSION APPLICATION FOR IMPROVEMENT PLAT APPROVAL PLANNING AND ZONING COMMISSION APPLICATION FOR IMPROVEMENT PLAT APPROVAL Date Submitted: Project Number: CITY OF ALEXANDRIA 8236 WEST MAIN STREET ALEXANDRIA, KY 41001 (859) 635-4125 FAX (859) 635-4127

More information

Table of Contents. 3.1 Source Capacity Analysis

Table of Contents. 3.1 Source Capacity Analysis Table of Contents 3.1 Source Capacity Analysis... 3-1 3.1.1. Design Criteria... 3-1 3.1.2. Source Capacity Evaluation... 3-1 3.1.2.1 Plateau Zone... 3-1 3.1.2.2 Cascade View Zone... 3-4 3.2 Storage Capacity

More information

About Me. Overview. Seattle Regional Water System. Seattle Regional Water System. Water System Analysis and Design at Seattle Public Utilities

About Me. Overview. Seattle Regional Water System. Seattle Regional Water System. Water System Analysis and Design at Seattle Public Utilities About Me Water System Analysis and Design at Seattle Public Utilities Jon C. Ford, P.E. CEE 481 October 1, 8 Senior Civil Engineer, Seattle Public Utilities BSCE, Seattle University MSCE, University of

More information

MASTER WATER SYSTEM DESIGN REPORT DESERT TRAILS

MASTER WATER SYSTEM DESIGN REPORT DESERT TRAILS MASTER WATER SYSTEM DESIGN REPORT FOR DESERT TRAILS SURPRISE, ARIZONA Prepared for: HE Capital Fox Trails, LLC 2850 E. Camelback Road Suite 110 Phoenix, Arizona 85016 1 st Submittal February, 2009 2 ND

More information

Report. Lake Water Supply Hydraulic Modeling. Village of. Lindenhurst, IL. April 2012

Report. Lake Water Supply Hydraulic Modeling. Village of. Lindenhurst, IL. April 2012 Lake Water Supply Hydraulic Modeling Report Village of Lindenhurst, IL April 2012 R:\MAD\Documents\Reports\Archive\2012\Lindenhurst, IL\Lake Water Supply.HM.1290.039.mjf.jan\Report\!Front Cover (Blue=Water)

More information

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS 2.1. General Requirements Sanitary sewers are to be provided solely for the removal of sanitary waste. Under no circumstances shall any roof drains,

More information

South Coast Water District 2017 Master Plan Updates

South Coast Water District 2017 Master Plan Updates South Coast Water District 2017 Master Plan Updates SCWD Sara Mathis, PE AECOM Henry Liang, PE Kelly McEnerney, EIT June 22, 2017 2017 Master Plan Update Presentation Outline Approach Potable Water System

More information

CHAPTER 5 WATER SYSTEM DESIGN STANDARDS

CHAPTER 5 WATER SYSTEM DESIGN STANDARDS CHAPTER 5 WATER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 5 WATER SYSTEM DESIGN STANDARDS 5.00 Objective Page 1 5.01 Additional Referenced Standards Page 1 5.02 Special Design Problems Page 2 5.03

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

Eastern Sewershed Package IV Project Solicitation Number: CO Job No.: ADDENDUM 1 April 20, 2018

Eastern Sewershed Package IV Project Solicitation Number: CO Job No.: ADDENDUM 1 April 20, 2018 Eastern Sewershed Package IV Project Solicitation Number: CO-00149 Job No.: 17-4527 ADDENDUM 1 April 20, 2018 To Bidder of Record: This addendum, applicable to work referenced above, is an amendment to

More information

Leveraging Hydraulic Models

Leveraging Hydraulic Models Leveraging Hydraulic Models presented by Melissa Brunger, P.E. GAWP Fall Conference November 14, 2017 Hydraulic Modeling Applications Case Studies Conclusions/Lessons Learned AGENDA System curves for pump

More information

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CHAPTER 3 WATER SYSTEM DESIGN 3.1 WATER SYSTEM DESIGN GENERAL 3.1.1 Criteria for the design of water service and water distribution lines

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

PRELIMINARY MUNICIPAL SERVICING REPORT NORTHWOODS SUBDIVISION. Prepared for: North Grassie Properties Inc.

PRELIMINARY MUNICIPAL SERVICING REPORT NORTHWOODS SUBDIVISION. Prepared for: North Grassie Properties Inc. PRELIMINARY MUNICIPAL SERVICING REPORT SUBDIVISION Prepared for: North Grassie Properties Inc. Prepared by: Stantec Consulting Ltd. 905 Waverley St. Winnipeg, MB R3T 5P4 July 2012 File: 116808030 SUBDIVISION

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

J. PAUL GUYER, P.E., R.A.

J. PAUL GUYER, P.E., R.A. J. PAUL GUYER, P.E., R.A. Paul Guyer is a registered civil engineer, mechanical engineer, fire protection engineer and architect with over 35 years experience designing all types of buildings and related

More information

PART VII - WATER SYSTEM DESIGN CRITERIA

PART VII - WATER SYSTEM DESIGN CRITERIA PART VII - WATER SYSTEM DESIGN CRITERIA A. Water Distribution, General 1. The water system layout shall be approved by the City Engineer. The fire hydrant layout shall be approved by the Redwood City Fire

More information

Final - Preliminary Design Report Interstate 10 and Indian Avenue Area Sewer System. Prepared for

Final - Preliminary Design Report Interstate 10 and Indian Avenue Area Sewer System. Prepared for Final - reliminary Design Report Interstate 10 and Indian Avenue Area Sewer System repared for Mission Springs Water District July 2012 Mission Springs Water District I-10 & Indian Area Sewer System DR

More information

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable

More information

DRAFT TECHNICAL MEMORANDUM

DRAFT TECHNICAL MEMORANDUM Stetson Engineers, Inc. Technical Memorandum - New City of Solvang Well Field, May 14, 2010 DRAFT TECHNICAL MEMORANDUM 2171 E. Francisco Blvd., Suite K San Rafael, California 94901 TEL: (415) 457-0701

More information

Wastewater Collection. (Sewer Alternatives)

Wastewater Collection. (Sewer Alternatives) Wastewater Collection (Sewer Alternatives) Sewer Basics Collection and transport of wastewater from each home/building to the point where treatment occurs. Wastewater Characterization Solids Liquids Pipe

More information

Functional Servicing Report. Winston Park West Proposed Business Park Development Project. Infrastructure Ontario (IO) September MU1

Functional Servicing Report. Winston Park West Proposed Business Park Development Project. Infrastructure Ontario (IO) September MU1 Functional Servicing Report Winston Park West Proposed Business Park Development Project (IO) September 2011 14-11208-001-MU1 Winston Park West 2 TABLE OF CONTENTS Page 1.0 INTRODUCTION... 3 1.1 SITE DESCRIPTION...

More information

Land Use Assumptions Technical Memorandum

Land Use Assumptions Technical Memorandum San Antonio Water System Water and Wastewater Facilities Land Use Assumptions Plan, Capital Improvements Plan, and Maximum Impact Fees Study Land Use Assumptions Technical Memorandum November 2018 Contents

More information

Sewer Modeling of Near- Term Development Technical Memorandum

Sewer Modeling of Near- Term Development Technical Memorandum Sewer Modeling of Near- Term Development City of Reedley, CA March 8, 2018 Page Intentionally Blank The City of Reedley (City) is anticipating near-term developments to the north of the City s currently

More information

CITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES

CITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES CITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES SECTION A NOTES TO ENGINEERS This manual is intended to aid and assist private engineers in the layout and design of sanitary sewers

More information

CEE 371 Fall 2009 Design Problem 1 (work in teams of 3) DESIGN OF AMHERST TRANSMISSION MAIN

CEE 371 Fall 2009 Design Problem 1 (work in teams of 3) DESIGN OF AMHERST TRANSMISSION MAIN CEE 371 Fall 2009 Design Problem 1 (work in teams of 3) DESIGN OF AMHERST TRANSMISSION MAIN Background The drinking water sources for the Town of Amherst include two surface water (reservoir) supplies

More information

TABLE OF CONTENTS. 5 WATER SUPPLY 5-1 Sources of Supply TOC-1 City of Ontario Water Master Plan. R:Reports\Ontario\Water Master Plan

TABLE OF CONTENTS. 5 WATER SUPPLY 5-1 Sources of Supply TOC-1 City of Ontario Water Master Plan. R:Reports\Ontario\Water Master Plan Section Page 1 EXECUTIVE SUMMARY 1-1 Purpose... 1-1 1-2 Study Area... 1-1 1-3 Water Use... 1-2 1-4 Water Supply... 1-9 1-5 Existing System... 1-11 1-6 Service Criteria... 1-16 1-7 Hydraulic Model... 1-18

More information

Yorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report

Yorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report Yorkton Rona Commercial and Industrial development Concept Plan and Serviceability Report Prepared for: 101242326 Sask Ltd. Box Ft Quappelle, SK Canada S0G 1S0 Prepared by: Stantec Consulting Ltd. 302-1345

More information

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves

More information

CITY OF MERIDIAN LAND DEVELOPMENT SERVICES SUBDIVISION PLAN REVIEW CHECK LIST

CITY OF MERIDIAN LAND DEVELOPMENT SERVICES SUBDIVISION PLAN REVIEW CHECK LIST Project Name: Hearing Date: Reviewer: Date of Review: # OK NEED N/A General Plan Design All documents, design standards, specifications, and forms should be taken from the website each time they are used

More information

Proposed Residential Development Snow Valley Uplands Cameron Estates Township of Springwater Functional Servicing Report

Proposed Residential Development Snow Valley Uplands Cameron Estates Township of Springwater Functional Servicing Report 453211 Ontario Ltd. Proposed Residential Development Snow Valley Uplands Cameron Estates Township of Springwater Functional Servicing Report Prepared by: AECOM 55 Cedar Pointe Drive, Suite 620 705 721

More information

Hydraulic Modeling and System Optimization

Hydraulic Modeling and System Optimization DRINKING WATER ENERGY MANAGEMENT WORKSHOP SERIES TAKING ENERGY IMPROVEMENTS TO THE NEXT LEVEL: Hydraulic Modeling and System Optimization Steven Jones, M.S., P.E. September 4, 2013 What is a Water System

More information

Index. Composition and Order of Plan Set. Utility Plan... 5

Index. Composition and Order of Plan Set. Utility Plan... 5 City of Des Plaines Public Works and Engineering Department Revised-October 5, 2012 Index Composition and Order of Plan Set Title Page Number Cover Sheet... 1 Requirements for Site Development... 2 Grading

More information

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA This report was prepared to present development information (Utility availability, Development Regulations, Flood Plain information,

More information

OVERALL UTILITY PLANS 1. Provide a typical section depicting the roadway (proposed/future), utility locations, and separation for

OVERALL UTILITY PLANS 1. Provide a typical section depicting the roadway (proposed/future), utility locations, and separation for OVERALL UTILITY PLANS 1. Provide a typical section depicting the roadway (proposed/future), utility locations, and separation for all roadways. Identify utility locations/separations from gutter lip and

More information

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements 4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for

More information

A Balancing Act: Complex Distribution System Planning in the Western North Carolina Foothills Tina Whitfield - HDR

A Balancing Act: Complex Distribution System Planning in the Western North Carolina Foothills Tina Whitfield - HDR A Balancing Act: Complex Distribution System Planning in the Western North Carolina Foothills Tina Whitfield - HDR 2017 HDR, Inc., all rights reserved. Agenda 01 Overview 02 Approach 03 Findings 04 Alternatives

More information

[] Brochure, picture, drawing, etc., of the use to be conducted (if applicable).

[] Brochure, picture, drawing, etc., of the use to be conducted (if applicable). TEMPORARY USE PERMIT APPLICATION ACCOUNT # 4232 Temporary Use Permit procedures are contained in Section 83.030705 of the Yucaipa Development Code. Temporary Use Permits shall be first issued for a period

More information

Hydraulic Analysis Comparing Efficiency of One and Two Zone Pressure Water Systems

Hydraulic Analysis Comparing Efficiency of One and Two Zone Pressure Water Systems Hydraulic Analysis Comparing Efficiency of One and Two Zone Pressure Water Systems 1 Agenda: - Background - Objectives - Water Distribution System Overview - GIS and Hydraulic Modeling Relationship - Hydraulic

More information

Environmental Engineering-I

Environmental Engineering-I Environmental Engineering-I Prof. Dr. Muhammad Zulfiqar Ali Khan Engr. Muhammad Aboubakar Farooq Water Distribution Systems & Analysis 1 Water Distribution Systems & Analysis References Water Supply &

More information

TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115.

TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115. TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM SECTION TITLE PAGE 115.1 GENERAL 115.1 115.2 SIZING LINES 115.1 115.3 DISTRIBUTION SYSTEM 115.2 115.3.1 Layout

More information

SECTION 4 STORM DRAINAGE

SECTION 4 STORM DRAINAGE 4.01 GENERAL SECTION 4 STORM DRAINAGE These standards shall provide minimum requirements for the design of Storm Drainage and related appurtenances within the City of West Sacramento rights of way and

More information

PRELIMINARY WASTEWATER CAPACITY STUDY

PRELIMINARY WASTEWATER CAPACITY STUDY PRELIMINARY WASTEWATER CAPACITY STUDY Tentative Tract Map No. 18955 CITY OF HESPERIA Prepared for: HESPERIA VENTURES I, LLC 10410 Roberts Road Calimesa, CA 92320 Tel (714) 785 2381 Mr. John Ohanian Prepared

More information

By Kimbal A. Hall, PE. Submitted to: WESTFALL MANUFACTURING COMPANY. May ALDEN RESEARCH LABORATORY, INC. 30 Shrewsbury Street Holden, MA 01520

By Kimbal A. Hall, PE. Submitted to: WESTFALL MANUFACTURING COMPANY. May ALDEN RESEARCH LABORATORY, INC. 30 Shrewsbury Street Holden, MA 01520 COMPUTATIONAL FLOW MODEL OF WESTFALL'S 36 3050 THREE STAGE MIXER TO BE INSTALLED IN THE PERCHLORATE BLENDING STATION FOR THE CITY OF REDLANDS, CALIFORNIA GFS-411507-1R2 By Kimbal A. Hall, PE Submitted

More information

Special Land Use Permit Application Planning Division

Special Land Use Permit Application Planning Division Special Land Use Permit Application Planning Division Form will not be processed until it is completely filled out. 1. Applicant Name:_ Address: Phone Number: Fax Number: Email address: 3. Applicant s

More information

PENNSYLVANIA STANDARDS FOR RESIDENTIAL SITE DEVELOPMENT: APRIL 2007 CHAPTER 8: OTHER UTILITIES

PENNSYLVANIA STANDARDS FOR RESIDENTIAL SITE DEVELOPMENT: APRIL 2007 CHAPTER 8: OTHER UTILITIES CHAPTER 8: OTHER UTILITIES Sections Page # 8.0 INTRODUCTION 4 8.1 GENERAL 4 8.1.1 Act 287: PA OneCall 4 8.2 LOCATION 4 8.3 TRENCHING AND BACKFILL STANDARDS 4 8.4 EASEMENTS 6 8.5 PETROLEUM AND NATURAL GAS

More information

Sanitary Sewer Design. Sanitary Sewers, Page 1

Sanitary Sewer Design. Sanitary Sewers, Page 1 Sanitary Sewer Design Sanitary Sewers, Page 1 Sanitary Sewers, Page 2 Sanitary Sewer Design sanitary sewers collect and transport domestic and industrial wastes via gravity flow the ultimate destination

More information

DRAINAGE SUBMITTAL CHECKLIST

DRAINAGE SUBMITTAL CHECKLIST Project Name: Firm Name: Map ID: Engineer: Address: City: State: Zip: Phone Number: Fax Number: Property Owner: Address: City: State: Zip: Reviewed By: Date Received: Date Accepted for Review: The following

More information

Water Utility Science Water Math and Hydraulics 050. Name: Date:

Water Utility Science Water Math and Hydraulics 050. Name: Date: Water Utility Science Water Math and Hydraulics 050 Name: Date: Note: Please show all of your calculations for each problem no matter how simple the problem may seem. Please use the accompanying pieces

More information

Special Land Use Permit Application Planning Division Form will not be processed until it is completely filled out.

Special Land Use Permit Application Planning Division Form will not be processed until it is completely filled out. Special Land Use Permit Application Planning Division Form will not be processed until it is completely filled out. 1. Applicant Name:_ Address: Phone Number: Fax Number: Email address: 3. Applicants Attorney/Contact

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Marianneville Developments Ltd.

Marianneville Developments Ltd. Estates of Glenway Project No. L09-301 March 2012 Executive Summary Cole Engineering Group was retained by Marianneville Developments Limited to undertake a Functional Servicing Report in support of the

More information

WATER SUPPLY CHALLENGES FOR AN ISLAND COMMUNITY

WATER SUPPLY CHALLENGES FOR AN ISLAND COMMUNITY WATER SUPPLY CHALLENGES FOR AN ISLAND COMMUNITY Britton Corbin, P.E. Janet McSwain, P.E. AUTHORS: Britton Corbin, Project Engineer, Earth Tech AECOM 2456 Remount Rd. Charleston, SC 29406 Janet McSwain,

More information

Design Checklist for Water and Sewer for Extensions and Subdivisions

Design Checklist for Water and Sewer for Extensions and Subdivisions Design Checklist for Water and Sewer for Extensions and Subdivisions The proponent s hydraulic engineer/designer is required to complete this checklist and submit to Services Development, when submitting

More information

Tank Name: Cornwell 0.5MG Reservoir

Tank Name: Cornwell 0.5MG Reservoir TIDEFLEX MIXING SYSTEM (TMS) PRELIMINARY DESIGN REPORT Tank Name: Cornwell 0.5MG Reservoir Water Utility/Owner: Soquel Creek Water District, CA Consultant: CONTENTS TMS - GENERAL ARRANGEMENT DRAWING CFD

More information