3.11. Hazardous Materials

Size: px
Start display at page:

Download "3.11. Hazardous Materials"

Transcription

1 3.11 Hazardous Materials

2 3.11 Hazardous Materials Introduction to Analysis Summary of Results Hazardous materials sites may be encountered during the construction of the stations and the alignment associated with the Preferred Alternative. There are an estimated 4 sites within the trackway and up to 14 sites are found at the stations sites, depending on the design option selected. In general, there is a greater potential to encounter hazardous material sites in the Denver and Adams Sections as compared to the Arvada and Wheat Ridge Sections. The greatest potential for conflicts with hazardous materials would be during construction of the section of alignment from DUS to Pecos Street that is constructed for the Northwest Rail project under the No Action Alternative, and shared with the Gold Line project (Preferred Alternative). When contaminated soils or groundwater are encountered, they would be characterized and properly disposed under the guidance of RTD's Materials Management Plan, which would be prepared prior to construction Purpose The presence or release of hazardous materials on construction sites can expose workers, residents, and other ecosystems to contaminants that may compromise their health. As a result, evaluation of the potential for rail projects to impact or be impacted by hazardous material sites is required by regulation. 1 Encountering hazardous waste during construction is costly and can affect the cost-effectiveness of the project Affected Environment A Modified Phase I Environmental Site Assessment (MESA) was prepared for the Gold Line study area and evaluated known spills of hazardous substances or petroleum products along the proposed alignment (Walsh, 2006). Walsh completed an additional review of hazardous material sites for the East Direct Design Option in April 2008 (Robinson, 2008). The MESA was compared to a similar document produced for the Northwest Rail project for the section of the alignment from DUS to Utah Junction (Goodbee, 2005). More than 900 individual listings were identified along the proposed 11.2 mile alignment 2. Of these, 128 listings were ranked as having a high potential for environmental contamination and 139 listings were ranked as having a moderate level of potential concern. The facilities are counted as listings at this stage because there was no reconciliation of sites with multiple listings, and the same facility might have been counted several times. The remaining listings were ranked as low or negligible. The Walsh MESA included a summary of the number of ranked sites by municipal area. Using the available information, numbers of sites within 1,000 feet of the proposed alignment are shown by section in Table Comprehensive Environmental Response, Compensation and Liability Act 2 This includes 3.5 miles of shared alignment for the Northwest Rail and Gold Line projects and the remaining 7.7 miles west of Pecos Street used only by the Gold Line project

3 TABLE Site Ranking Summary (Sites within 1,000 feet of the Proposed Alignment) 1 Moderate Section Sites Sites Low Sites Denver Adams Arvada Wheat Ridge Total Total Sites Source: Walsh, Some listings did not have a city reported or were located in an unincorporated area. There was not sufficient information to determine if the listing was in unincorporated Jefferson or Adams County Impact Evaluation Methodology The sites that were ranked as high and moderate were mapped onto the proposed footprint of the Preferred Alternative, as well as the section of track shared with Northwest Rail. The footprint included areas of construction along the proposed alignment, as well as properties needed for proposed stations. This information was used to identify potential areas of concern for either construction or land acquisition. The use of the anticipated construction footprint eliminated many of the original sites identified in the Walsh MESA because they would not have an impact on construction activities and would not be part of a parcel purchased for ROW Results The potential for encountering hazardous materials in the Gold Line study area is closely correlated with land use. Commercial and industrial land uses generally present the greatest risk for encountering hazardous materials. The presence and character of hazardous materials are expected to be typical of most urban and urbanizing areas, including groundwater contamination from Leaking Underground Storage Tanks (LUST), asbestos and lead paint from older buildings and bridges, contaminated soils along the railroad ROW, and residual pesticides from agricultural activities. No Action Alternative The No Action Alternative assumes that existing and committed improvements, as defined in Chapter 2, Alternatives Considered, would be implemented by others as planned. Direct Impacts Roadway Projects Implementation of the Sheridan Boulevard project would be through a heavily commercial section. Although there are no design details available for this project, it appears that the construction may affect hazardous waste sources or underground storage tanks (USTs) because of the commercial nature of both sides of the roadway. Potential contaminants include petroleum-based fuels, other hydrocarbon compounds, and solvents. Implementation of the I-70 and Kipling Interchange project would be within an existing commercial area. It is probable that construction would not directly affect hazardous materials because the interchange is somewhat isolated from the commercial properties and is therefore not likely to sit on any abandoned USTs

4 Implementation of the Wadsworth Boulevard project is also located within an existing commercial area. Although there are no design details available for this project, it appears that the construction may affect hazardous waste sources or USTs because of the commercial nature of both sides of the roadway. Potential contaminants include petroleum-based fuels, other hydrocarbon compounds, and solvents. Northwest Rail Project The risk of encountering hazardous materials from DUS to Pecos Street is about the same for the Railroad Alignment and the East Direct Design Option. Using the Railroad Alignment, construction of the Northwest Rail project in this section would involve the risk of encountering approximately 500 hazardous waste sites as the alignment passes through the freight rail corridor. Figure presents the sites within the construction footprint of the project that are ranked moderate or high risk. Construction-related activities that may encounter hazardous materials include the removal or replacement of contaminated track ballast or railroad ties, excavation and drilling during construction of bridge abutments and piers, and excavation during construction of stations. The removal or replacement of existing, contaminated track ballast or railroad ties would be an issue throughout the freight railroad ROW. Potential hazardous waste sites associated with the East Direct Design Option are generally associated with private commercial or industrial businesses (Table ). In addition, the East Direct Design Option would require the demolition of more buildings, as compared to the Railroad Alignment; therefore, there is a greater potential to encounter asbestos or lead based paint. The risks of hazardous materials north of Pecos Street to near Lowell Boulevard, where the Northwest Rail alignment exits the Gold Line study area are unknown. Contaminated soils or groundwater would be characterized and properly disposed of in conformance with RTD s Materials Management Plan, which would be prepared prior to construction of the Northwest Rail project. Indirect Impacts Construction of the above-referenced projects would not likely involve indirect impacts to hazardous materials. Future design refinements would provide additional information on the potential indirect impacts to hazardous materials. Temporary Construction Impacts All direct impacts would occur during the construction phase and are not repeated here. Cumulative Impacts The construction of the No Action Alternative would encounter hazardous materials. These materials would be removed from the site and properly disposed. The construction of all other infrastructure required to accommodate the 2030 population, including all the remaining FasTracks projects, would result in the exposure and remediation of unknown quantities of hazardous waste. Therefore, these materials would no longer represent a potential threat to human health and the environment. The operational effects of future projects on hazardous waste generation are well controlled by state and federal regulation, thereby avoiding the impacts of the past

5 GOLD LINE DRAFT ENVIRONMENTAL IMPACT STATEMENT FIGURE All Sites Ranked as Moderate or within the Proposed Project Construction Footprint

6 TABLE Private Commercial and Industrial Sites Ranked as Moderate or : East Direct Design Option ID # Name of Site Address Ranking 1 Comments East Direct Design Option (Northwest Rail) 2 Power Rental Equipment 10 Brannan Sand and Gravel 11 Westric Battery Company 12 AAA Waterproofing 13 Rocla Concrete Tie Inc. 725 West 39th Avenue 730 West 42nd Avenue/4100 Fox Street West of Galago Street/South of 43rd Avenue 750 West 48th Avenue 701 West 48th Avenue 14 Qwest Communications 5151 Fox Street 15 Owens-Corning Fiberglass Roofing Products 5201 Fox Street Moderate UST within footprint and current site activity UST within footprint, LUST within footprint and source activity Acid plant noted on historical documents in the 1920s UST within footprint and current source activity Source in the footprint UST within footprint and current source activity UST within footprint, current source activity, and possible spill of hazardous materials 16 B&B Blending 5285 Fox Street Moderate Former source activity 17 Bioenergy of Colorado 801 West 56th Avenue Landfill and source activity 18 Intersection Parking Lot 53rd Place/Fox Street Moderate Spill of hazardous materials on property adjacent to footprint Source: Gold Line Team, Rankings are based on professional judgment and the distance from the centerline of the alignment or station boundary, for each information source (for example, Federal National Priority List or UST) Preferred Alternative Direct Impacts As with the No Action Alternative, the majority of direct impacts to hazardous materials associated with the Preferred Alternative would occur during construction. Denver Section The only property acquisitions in this section are related to the construction of the Denver Section station options and the electric substation. Table and Figure show the sites that are potentially within the station footprint and would affect construction. The 38th Avenue, 39th Avenue East, and the 41st Avenue East stations are estimated to affect seven, five and three moderate to high risk hazardous waste sites, respectively

7 TABLE Sites Ranked as Moderate or within the Proposed Station Construction Footprints in the Denver Section ID # Name of Site Address Ranking 1 Comments 38th Avenue Station 1 The Texas Company Oil Distribution Station 2 Power Rental Equipment 4 Vasquez Boulevard and I-70 North of 38th Avenue between Galapago Street and the railroad tracks 725 West 39th Avenue Vasquez Boulevard and I-70 5 Fox Street Service 3901 Fox Street 6 Stained soil West of tracks between 39th Avenue and 43rd Avenue Moderate Lubricating oil in tanks observed on historical documentation of property use. UST within footprint and current source activity. Contamination of surficial soils from historic metal smelters in area. UST operated at facility; LUST reported; operations could include use of hazardous substances and petroleum products. Discolored soil observed during aerial photograph review. 7 Zens Tire Inc Fox Street Moderate LUST reported. 8 RTD 3997 Fox Street Moderate Operations could include use of hazardous materials or petroleum products. 39th Avenue East Station 1 The Texas Company Oil Distribution Station 2 Power Rental Equipment 3 Wagner Rents Downtown Branch 4 Vasquez Boulevard and I-70 North of 38th Avenue between Galapago Street and the railroad tracks 725 West 39th Avenue 805 West 39th Avenue Vasquez Boulevard and I-70 8 RTD 3997 Fox Street Moderate Lubricating oil in tanks observed on historical documentation of property use. UST within footprint and current source activity. UST operated at facility. Contamination of surficial soils from historic metal smelters in area. Operations could include use of hazardous materials or petroleum products. 41st Avenue East Station 9 L Northhaft & Son Inc Fox Street UST within footprint. 4 Vasquez Boulevard and I-70 Vasquez Boulevard and I-70 8 RTD 3997 Fox Street Moderate Contamination of surficial soils from historic metal smelters in area. Operations could include use of hazardous materials or petroleum products. Source: Gold Line Team, Rankings are based on professional judgment and the distance from the centerline of the alignment or station boundary, for each information source (for example, Federal National Priority List or UST)

8 Adams Section Property acquisitions in this section would be related to the construction of the stations at Pecos Street and Federal Boulevard. The proposed footprint for the station was compared with the identified sites of concern at both station locations (Table and Figure ). One site would be encountered with the Pecos East Station option as compared with five sites at the Pecos West Station option. Two sites would be encountered with the Federal Station option. TABLE Sites Ranked as Moderate or within the Proposed Station Construction Footprint in the Adams Section ID # Name of Site Address Ranking 1 Comments Pecos East Station 19 Adams County Landfill 20 Adams County Dump 21 City and County Of Denver 22 No Name Reported East of Pecos Street and South of 62nd Avenue Pecos West Station South of 60th Avenue at Wyandot 60th Avenue and Shoshone Street West 60th Avenue 23 Western Paving 5959 Pecos Street 24 No Name Reported West of Pecos at 60th Avenue Federal Station 25 No Name Reported 2700 West 60th Avenue 26 No Name Reported 60th Avenue and Federal Boulevard (West Side) Landfill within the footprint of the Pecos East Station, Phases 1 and 2. Landfill within the footprint of the Pecos West Station, Phase 2. Landfill within the footprint of the Pecos West Station, Phase 2. Landfill within the footprint of the Pecos West Station, Phases 1 and 2. Landfill within the footprint of the Pecos West Station, Phases 1 and 2. Landfill within the footprint of the Pecos West Station, Phase 1. Landfill within the footprint of the Federal Station, Phase 2. Landfill within the footprint of the Federal Station, Phase 2. Source: Gold Line Team, Rankings are based on professional judgment and the distance from the centerline of the alignment or station boundary, for each information source (for example, Federal National Priority List or UST) In addition to these impacts, landfills in the vicinity of 60th Avenue and Pecos Street are shown as extending to the trackway footprint. Two non-landfill properties are mapped within or immediately adjacent to the trackway footprint in this section (Table ). TABLE Sites Ranked as Moderate or within the Proposed Trackway Footprint in the Adams Section ID # Name of Site Address Ranking 1 Comments 27 Lloyd Cunningham 5901 North Federal Boulevard Registered UST. 28 Cunningham Property 5900 North Federal Boulevard Moderate Operations could include use of hazardous materials or petroleum products. Source: Gold Line Team, Rankings are based on professional judgment and the distance from the centerline of the alignment or station boundary, for each information source (for example, Federal National Priority List or UST)

9 Arvada Section No sites are located within the station footprints in the Arvada Section. Two sites are mapped within the trackway footprint or are listed as businesses that would have to be relocated (Table ). TABLE Sites Ranked as Moderate or within the Proposed Trackway Footprint in the Arvada Section ID # Name of Site Address Ranking 1 Comments 29 Lamar Automotive 5690 Lamar Street Tank leak and operations could include use of hazardous materials or petroleum products. Mapped within the track footprint. 30 Wheat Ridge Regional Center Ridge Road Tank leak and operations could include use of hazardous materials or petroleum products. Property identified for relocation of operations. Source: Gold Line Team, Rankings are based on professional judgment and the distance from the centerline of the alignment or station boundary, for each information source (for example, Federal National Priority List or UST) In addition to these sites, there is an area of excavation proposed for construction of a retaining wall to the west of Wadsworth Boulevard. A LUST immediately adjacent to this area (Lucky Mart at 7201 Grandview Avenue) has not received a required No Further Action letter from the State of Colorado. Prior to construction activities, information regarding the extent of contamination should be reviewed and considered during development of a Materials Management Plan. It is possible that remediation will be completed before construction begins. Wheat Ridge Section No sites of concern were identified within the project footprint in the Wheat Ridge Section. Indirect Impacts The Preferred Alternative is not anticipated to have indirect impacts on hazardous materials. Future design refinements would provide additional information on the potential indirect impacts to hazardous materials. Temporary Construction Impacts All direct impacts would occur during the construction phase and are not repeated here. Cumulative Impacts The cumulative impacts discussed above for the No Action Alternative are analogous to those anticipated for the Preferred Alternative Mitigation Measures Mitigation techniques to reduce identified impacts to hazardous materials are described in Table

10 TABLE Mitigation Measures for Hazardous Materials under the Preferred Alternative Mitigation Measure for the Impact Impact Type Preferred Alternative Existing hazardous material sites within or adjacent to areas of proposed excavation and acquisition of property Water quality protection Protection of construction workers Source: Gold Line Team, 2007 Construction Evaluate ballast and railroad ties to be removed and disposed of with the proper waste classification. Disposal must be appropriate for the resulting classification. Complete site specific Phase II Environmental Site Assessments (ESA) with subsurface investigation (soil and groundwater) for sites that may have been contaminated or affect final design, as documented by the Phase I ESA, where appropriate. Prepare a Health and Safety Plan and a Materials Handling Plan to address contaminated soil and groundwater. Determine engineering controls to minimize quantity of contaminated materials. Determine cost recovery of hazardous material sites where removal actions and long-term maintenance is required. Conduct an individual site-specific Phase I ESA of properties before acquisition. Prepare an asbestos survey for any building acquisition or demolition. Construction Implement construction BMPs in accordance with a Stormwater Pollution Prevention Plan. BMPs may include secondary containment areas for refueling construction equipment, berms or ponds to control runoff, and a monitoring program to test stormwater for contaminants prior to discharge from the construction site. Construction Compliance with Occupational Safety and Health Administration requirements for construction workers who may be exposed to hazardous materials, including preparation of Health and Safety and Emergency Response Plans, air monitoring (if necessary), and provision of personal protective equipment

11 3.12 Safety and Security

12 3.12 Safety and Security Introduction to Analysis Summary of Results Since the implementation of RTD s LRT system, crime on board vehicles and at stations has been statistically insignificant. The majority of offenses are non-violent crimes, such as trespassing and disorderly conduct on vehicles and theft and vandalism of automobiles at stations. Based on historic experience, the Preferred Alternative would have no affect on crime in the study area. Crime at the transit stations or on the EMU vehicles is expected to reflect the crime activity of the surrounding communities, which would be similar to the No Action Alternative. The proposed stations of the Preferred Alternative would not increase the local rate of crime but would be representative of the surrounding neighborhood crime rates. Therefore, neighborhoods with high crime rates would continue to experience higher-thanaverage crime rates with or without the proposed stations. As a result, crime rates higher than average are predicted at any of the 38th Avenue Station options in Denver and the Ward Road Station in Wheat Ridge. These stations would be monitored upon implementation and more aggressive security measures may be needed at these locations Purpose Increased criminal activity and impeded emergency vehicle access are concerns of communities within the Gold Line study area. Because of these concerns, existing and future safety and security issues in the Gold Line study area have been analyzed as they relate to passengers and the surrounding community. In particular, the likelihood of change to crime rates and the effects of the project on emergency response times in the Gold Line study area have been evaluated Affected Environment The RTD Safety and Security Manual defines measures the agency takes to ensure the safety and security of its rail transit patrons and those indirectly impacted by their operations. The measures include a Safety and Security department that provides vehicle on-board security staff during hours of rail operation and station area security staff. Emergency telephones are located in station areas and closed circuit television coverage is provided at designated stations, parking structures and lots, and in vehicles. The RTD security force works with the local police to control crime on-board vehicles, along the corridor, at station areas, and in parking facilities. For implementation of the Gold Line project, RTD would convene a Fire and Life Safety Committee comprised of representatives from local law enforcement and emergency services. This committee would assist in the development of an emergency plan for the Gold Line study area and coordinate responses to various emergency situations. Design criteria contain guidelines for station areas to reduce crime at stations and parking facilities. These guidelines are to be followed unless a waiver is obtained from the RTD Safety and Security Committee. The Gold Line project would include security cameras and emergency telephones that would be connected with the RTD security command center and monitored by security personnel

13 Station Area and On-board Crime To determine the existing station area and on-board crime rates, crime statistics were gathered for each of the communities in the Gold Line study area for 2005 as listed in Table TABLE Existing Annual Crime Statistics by Section 2005 Section Agency Homicide Rape Robbery Burglary Auto Theft Denver City and County of Denver ,424 7,318 7,769 Police Department Adams Adams County Sheriff s ,438 0 Department Arvada City of Arvada Police Department Wheat Ridge City of Wheat Ridge Police Department Source: US Department of Justice, 2005 The figures shown in these tables are categorized according to standards used by the Federal Bureau of Investigation s Uniform Crime Reporting Program, a program that is used to standardize and track the reporting of crime. In general, areas of more intense urban uses experience higher crime rates. Table shows crime rates relative to population. TABLE Summary of Crime Rates Relative to Population Section Agency Total Serious Crimes Population Crimes Per 1,000 People Denver City and County of 16, , Denver Police Department Adams Adams County 1, ,257 4 Sheriff s Department Arvada City of Arvada Police 1, , Department Wheat Ridge City of Wheat Ridge Police Department , Source: Colorado Department of Local Affairs, Serious crimes consist of murder, rape, robbery, burglary, and auto theft. Evaluating the change in crime is important because the crime occurring in and around transit stations is similar to the crime of the surrounding area, and more intense security measures may need to be implemented if necessary. Armed and uniformed officers patrol transit vehicles, pnrs, and stations. This service increases proportionately with increased transit service. Crime records for existing pnr locations in the Gold Line study area and current transit stations system-wide were examined to assess the safety and security of patrons under current conditions. The existing Olde Town Station in Arvada and the Ward Road Station in Wheat Ridge are the only pnrs near the proposed alignment. The facilities have a total of 711 parking spaces. In general, theft and vandalism are negligible and difficult to isolate to these locations. System-wide, there was only one vandalism incident and 51 theft incidents in 2005, according to RTD statistics (RTD, 2007). According to RTD statistics, crimes for bus operations in 2005 were negligible. Crime potential for the proposed new stations is anticipated to be similar. Crime on-board RTD s existing light rail vehicles for 2004 and 2005 is displayed in Table Disorderly conduct

14 was the most common offense on vehicles. Threats were the second most recorded offense in these 2 years. TABLE Crime On-Board RTD Light Rail Vehicles Incidents On-board Light Rail Vehicles Alcohol offense 2 0 Arson 0 1 Assault 2 5 Disorderly conduct 11 5 Drug offense 3 0 Forgery/Counterfeit 0 0 Fraud 0 0 Sex offense 0 1 Theft 0 2 Transit-specific crime 2 1 Trespassing 1 0 Threats 7 5 Weapons offense 2 0 Vandalism 0 1 Total Crime Incidents Source: RTD, 2006b Public Services Police, Fire, and Emergency Police, fire, and emergency services information was provided from various agencies and companies throughout the Gold Line study area. A summary of the existing public safety services by location is presented in Table TABLE Police, Fire, and Emergency Service Locations by Section Section Police Location Fire Location Emergency Location Denver Adams 1311 West 46th Avenue 1566 North Washington Street 1331 Cherokee Street 332 North 19th Avenue 5291 East 60th Avenue 745 West Colfax Avenue 2575 North Federal Boulevard 2500 North Washington Street 1890 Lawrence Street 1300 Blake Street 2195 West 38th Avenue 1616 Park Avenue West No fire stations were identified in this section Arvada 8101 Ralston Road 7900 West 57th Avenue West 52nd Avenue 7300 Kipling Street 6845 West 68th Avenue 8100 Vance Drive 6503 Simms Street 6651 Indiana Street Wheat Ridge 7500 West 29th Avenue 7300 Kipling Street (Fire Stations in Arvada also respond in Wheat Ridge, depending on location) Source: Gold Line Team, 2007 Denver Health Medical Center Saint Joseph s Hospital Saint Luke s Medical Center No hospitals were identified in this section No hospitals were identified in this section Exempla Healthcare Family Institute of Colorado

15 Impact Evaluation Impacts to public safety and security are discussed below Methodology Security and safety concerns can be grouped into station area and on-board safety and police, fire, and emergency response. Station Area and On-Board Safety Studies in areas before and after the introduction of a transit system suggest that stations are as safe as the surrounding commercial activity centers or places that people congregate. The observed frequency of crime at stations tends to mirror the crime of the surrounding area. The majority of these crimes are non-violent acts, such as vandalism and theft. Statistics for RTD s existing LRT transit system identify similar patterns of crime on-board vehicles, with crime on-board reflecting crime rates in the surrounding area (RTD, 2007). For purposes of this analysis, the station area and on-board safety category was evaluated by comparing the weighted average of crimes based on the total number of proposed parking spaces at each station. This was accomplished by calculating a crime index for each of the stations based on the number of parking spaces and crime rates of the surrounding areas. A station with a crime index above 1 would be considered higher than the Gold Line study area average, and a crime index less than 1 would indicate a station below the Gold Line study area average. A composite crime index was then developed by adding the individual crime indices for each station. Because similar types of crime at stations and on-board vehicles can be anticipated with new transit service, evaluating crime by using parking spaces as a surrogate for the potential exposure to crime allowed comparison of the different stations. For example, a station with fewer spaces but in a higher crime area would reflect a higher potential exposure to crime (composite crime index) than a station with more spaces in a lower crime area. By identifying those proposed stations in higher crime areas, the stations can be compared and more aggressive crime prevention measures can be considered. Police, Fire, and Emergency Response Impacts to police, fire, and emergency services can result during construction of a rail transit system if major roadways are closed due to bridge or other facility construction or if extensive detours require significant out-of-direction travel and increased response times. Increased train frequency at at-grade crossings may affect both short- and long-term response times Results No Action Alternative The No Action Alternative assumes that existing and committed improvements, as defined in Chapter 2, Alternatives Considered, would be implemented by others as planned. Direct Impacts Station and On-Board Safety Impacts Increases in station area crime and on-board crime are not anticipated for the No Action Alternative because no additional stations would be added in the Gold Line study area. Police, Fire, and Emergency Response Time Impacts Police, fire, and emergency services may be slightly affected by increased response times during peak hours due to increased congestion and at-grade crossings at West 48th Avenue

16 and Pecos Street 1 in the Gold Line study area, as well as increased demands for emergency services due to additional traffic accidents associated with the planned 2030 growth. Indirect Impacts Implementation of the No Action Alternative would have no indirect impacts to safety and security. Temporary Construction Impacts The construction of the three No Action Alternative roadway projects may represent an element of driver risk during construction as lane closures and detours present an added challenge to drivers. This would be due to possible lane closures and the movement of construction-related vehicular traffic. Police, fire, and emergency services may be adversely affected in the immediate project areas by increased response times due to these construction activities. Traffic control plans would be developed by the construction contractors selected to perform the work. Construction of the Northwest Rail project would involve construction at the following at-grade crossings: West 48th Avenue, Pecos Street, West 64th Avenue, Lowell Boulevard, and West 72nd Avenue where the alignment leaves the Gold Line study area. Similar elements of driver risk, as described above for the No Action roadway projects, would also be experienced at these locations during construction. Cumulative Impacts Future safety and security statistics by neighborhood would remain comparable to existing trends with the implementation of the No Action Alternative. Preferred Alternative Direct Impacts Station and On-Board Safety Impacts For the Preferred Alternative, on-board crime is expected to be similar to existing operating transit crime statistics and proportionate to increases in transit service in all sections. Using the crime rate per thousand persons and the anticipated number of parking spaces at each station, the crime index or potential exposure to crime was determined. This information is presented in Table TABLE Station Crime Indices for 2030 Section Station Number of Parking Spaces Crime Index 38th Avenue 1, Denver 39th Avenue East 1, st Avenue East Pecos Station (East or West) Adams Federal Sheridan Arvada Olde Town Arvada Ridge Wheat Ridge Ward Road Source: Gold Line Team, The impact would not occur if Adams County constructs a planned grade separation project at Pecos Street. The funding for this project has not been finalized

17 Table shows that the two areas with the highest potential exposure to crime are the Denver Section stations and the Ward Road Station. The stations with the lowest potential exposure to crime are those in Arvada and Adams County. The crime conditions at any of the Denver Section stations options would be the same since the station locations are within two blocks of one another. Police, Fire, and Emergency Response Time Impacts Police, fire, and emergency services may be slightly affected by increased response times during peak hours due to increased congestion at the 17 2 at-grade crossings required for the Preferred Alternative. Because RTD would provide a high degree of safety improvements at each grade crossing, including gates and signal improvements, the potential for collisions with emergency vehicles is small. However, it is possible that some additional congestion at these locations would be experienced by emergency vehicles. Indirect Impacts Implementation of the Preferred Alternative is not anticipated to indirectly affect crime rates any differently than the No Action Alternative. Future neighborhood crime would be representative of the surrounding area, with or without the implementation of the Preferred Alternative. Temporary Construction Impacts The impact on emergency response times during construction of the 17 2 required at-grade crossings is a potential concern with the Preferred Alternative. It is possible that there would be some reduction in traffic capacity at some point during construction. Flaggers would be available to direct traffic during the construction across traveled roadways. Cumulative Impacts Future safety and security statistics by neighborhood would remain comparable to existing trends with the implementation of the Preferred Alternative Avoidance and Minimization The RTD design, construction, and operations standards for new transit systems, including the Preferred Alternative, incorporate several components and actions to make the systems safe and secure for transit patrons and the general public. A hazard identification, analysis, and resolution process is required for all transit engineering projects. Hazards are identified through a Preliminary Hazard Analysis to define hazards and their effects. In addition, a safety certification process is required to verify that system elements comply with a formal list of safety requirements for the transit mode. RTD would work with police, fire, and transportation agencies during project design to ensure reliable emergency access is maintained. To minimize the impact on emergency response times, RTD would commit to maintain at least one open lane of traffic on affected north-south arterials during construction. Alternative plans or routes would be developed if needed to avoid delays in emergency response times. Fencing or barriers would be provided along the proposed alignment and surrounding station areas. These would be designed to be a safety barrier to prevent trespassers, vehicles, trucks, and other roadway users from entering the trackway. These would also be designed to prevent road debris or plowed snow, slush, and ice from entering the trackway or station areas. Safety measures would be incorporated on elevated sections to provide fall protection as well as adequate space for maintenance workers. 2 There are 19 at-grade crossings in the Gold Line study area; two are part of the Northwest Rail project under the No Action Alternative

18 All stations would be designed with a minimum of two access and egress points. These points would facilitate safe and efficient evacuation of a station in 4 minutes or less. Surveillance would include both personal and video surveillance. Video surveillance systems would be capable of transmitting real-time video to RTD via a fiber optic transmission backbone or other suitable transmission network. Personal surveillance would include uniformed officers who inspect transit stations on a recurring basis. Emergency telephones would be installed onsite. Emergency telephones would be consistent with existing RTD units and would meet performance requirements of RTD s existing emergency telephone network. Emergency telephones would cover station platforms, elevator waiting areas, stairwell entries, parking structures, pedestrian tunnels, and pedestrian bridges. Crime Prevention through Environmental Design (CPTED) would be incorporated in the entire design. The purpose of CPTED is to minimize potential threats and vulnerabilities to the transit system, facilities, and patrons and maximize safety and security through engineering and design. Some CPTED strategies would include: Maximizing the visibility of people, parking areas, patron flow areas, and building/ structure areas. Providing adequate lighting to minimize shadows. Installing graffiti guards and removing graffiti when discovered. Installing Mylar shatter guard protection for glass windows. Installing landscaping that maximizes visibility. Providing gateway treatments, decorative fencing, perimeter control, and a minimum number of parking structure access points. Coordinating and cooperating with municipalities to promote transit-friendly land uses (avoiding land uses that have links to crime). Establishing maintenance programs that repair broken windows, pick-up litter, and manage streetscapes and public spaces. Design elements and electronic technology would be used to ensure the transit platform area is safe and free of hazards. Representative measures include: Active and passive warning devices that alert persons of risks and hazards. Light Emitting Diode flashing pedestrian warning signs that warn of an approaching train. Pavement coloring and texturing to notify pedestrians of hazards and/or risk areas. Pedestrian bafflers such as swing gates, automatic pedestrian gates, or Z-crossings on platforms with poor sight distance to prevent pedestrians from entering the railway. An internet-based local information network would be created to serve a variety of needs. It would provide promotional opportunities; real-time transit information; updates on construction, route closures, and alternative route information; and other transportation information and services. The network would be coordinated with state and regional Intelligent Transportation Systems projects

19 RTD would work with local police and sheriff s departments to plan for appropriate security forces and would increase the number of private security guards on patrol within the corridor proportionate to the increase in service. Additional safety and security measures would be undertaken during construction to reduce the impact on the public, including: Producing Traffic Management Safety Reports and Traffic Control Plans for each phase of construction. Accounting for the poor air quality season (November 1 to March 1). Keeping transit operating at existing stops where possible. Keeping bike and pedestrian facilities continuous. Ensuring the contractor obtains permits and approvals by local governments for all detours. Providing signing plans (sign continuity must be maintained and advance warning of any closure provided at least 7 days in advance). Providing pavement marking plans to maintain access and circulation in construction areas. Providing temporary signalization plans in coordination with RTD, local agencies, and utility providers Mitigation Measures No mitigation is required beyond adherence to RTD Safety and Security design standards. RTD will convene a Fire and Life Safety Committee that will assist in preparing an emergency plan and coordinate response to emergency situations

20 3.13 Utilities

21 3.13 0BUtilities BIntroduction to Analysis BSummary of Results The analysis shows that implementation of the Preferred Alternative would require as many as 26 major utility relocations for the construction of the trackway and up to an additional 52 major utility relocations for construction of the stations. By comparison, the extent of utility relocations for the three roadway projects under the No Action Alternative cannot be estimated at this time because no engineering has been done for these projects. The construction of the Northwest Rail project under the No Action Alternative would require as many as 18 major utility relocations BPurpose Utility relocation analysis is important for three reasons: The construction of a project across utilities could result in the release of sewage, natural gas, or other contaminants to the environment, as well as loss of service to local customers. Preliminary design has been based on this analysis to identify potential conflicts and recommend areas for further investigation and coordination with utility companies during later stages of the project. Utility relocation can be a significant cost to the proposed project, so it is important to identify opportunities to avoid these relocations BAffected Environment The major utilities identified in the Gold Line study area include fiber, telephone, low voltage electric lines, high voltage electric transmission (ELT) lines, buried water and gas lines, sanitary and storm sewers, and irrigation ditches. The following provides general information for each type of major utility. 9BDenver Section The Denver Section contains the Railroad Alignment and East Direct Design Option. These two alignments are within about 300 feet of each other in a north-south direction. This area has a long history of industrial and commercial development, and as a result, has many old utility crossings as well as more recent utilities. These utilities include storm sewers ranging from 66 inches to 72 inches in diameter, two Metro Wastewater sanitary sewers from 70 to 78 inches in diameter, a 20-inch raw water line, the Farmers and Gardeners Ditch, several buried fiber optic lines, a high-pressure gas line, the Xcel Argo substation, Xcel overhead and underground electric lines, overhead and underground communication lines, and underground low- and intermediate-pressure gas lines. There are three station options in the Denver Section depending on the alignment selected. There are more utilities at the 38th Avenue Station and 39th Avenue East Station locations than found at the 41st Avenue East Station location. These include: Denver Wastewater 42- inch and 66-inch storm sewers, an 18-inch sanitary sewer, Level 3 fiber optic line, Xcel lowand intermediate-pressure lines, Qwest overhead and underground communication lines, and Xcel overhead and underground electric lines. At the 41st Avenue East Station there

22 are two Denver Wastewater 8-inch sewers, Level 3 fiber optic line, Qwest overhead and underground communication lines, and Xcel overhead and underground electric lines. 10BAdams Section In the Adams Section, the Railroad Alignment and East Direct Design Option have similar utility issues. The Railroad Alignment runs through the Utah Junction rail yard and the East Direct Design Option is located adjacent to the rail yard through commercial and industrial land uses. The Suncor high pressure gas line, Denver Water 66-inch water line and the Fisher Ditch are located in this area. Just east of Sheridan Boulevard, the BNSF/UP alignment separates and the Preferred Alternative follows the BNSF Railway Company ROW to the west. The major utilities that cross or run parallel to the proposed alignment in the Adams Section include numerous storm sewers ranging from 36 inches to 68 inches in diameter, two drainage culverts, raw water lines, Manhart Ditch, Jim Baker Outlet Ditch, Fisher Ditch, Kershaw Ditch, a communications fiber trench, overhead and underground communications lines, Qwest overhead and buried fiber optic lines, Xcel overhead and underground electric lines, and Xcel underground low-and intermediate-pressure gas lines. Two stations would be located in the Adams Section at Pecos Street and Federal Boulevard. The Pecos Station has two options: Pecos East and Pecos West. While both stations include utilities, neither offers an advantage over the other. Utilities at the Federal Station are limited to on Xcel overhead electric line and one Qwest overhead communication line. 1BArvada Section In the Arvada Section, the Preferred Alternative continues to follow the BNSF Railway Company ROW through many residential and commercial developments. The major utilities in the Arvada Section include numerous storm sewers ranging from 30 to 60 inches in diameter, many sanitary sewers ranging from 8 to 10 inches in diameter, Pachello Lateral Ditch, Wadsworth Ditch, Wadsworth Lateral Ditch, Swadley Ditch, Allen Rend Ditch, fiber optic lines, overhead and underground low-voltage electric lines, overhead and underground communication lines, and underground low- and intermediate-pressure gas lines. Three stations are proposed in the Arvada Section: Sheridan, Olde Town, and Arvada Ridge. Utilities in the Olde Town Station footprint include 10-inch vitreous clay pipe (VCP) sanitary sewers, a 36-inch storm sewer, Swadley Ditch, buried and overhead communication lines, low-pressure gas lines, overhead and buried electric lines, and Manhart Ditch. 12BWheat Ridge Section In the Wheat Ridge Section, residential neighborhoods and commercial developments border the BNSF Railway Company ROW. The major utilities in the Wheat Ridge Section include numerous 8- to 10-inch sanitary sewers, Juchem/Reno Ditch, a high-pressure gas line, fiber optic lines, Ridge substation ELT lines, overhead and underground low-voltage electric lines, overhead and underground communication, and underground low- and intermediate-pressure gas lines. The Ward Road Station is the only station within the Wheat Ridge Section of the Gold Line study area. Utilities in the Ward Road Station footprint include an 8-inch sanitary sewer and a storm sewer

23 BImpact Evaluation BMethodology The utility impact evaluation included: Contacting the Utility Notification Center of Colorado for initial identification of private utility companies and municipalities with facilities in the Gold Line study area. Contacting the identified companies and departments to obtain maps or verbal descriptions of the facilities. Follow-up field reconnaissance and review of US Geological Survey topographic maps confirmed the findings and provided additional information that was compiled into a contact list, utility tables organized by section and ownership, impact and mitigation tables organized by section and ownership, and utility maps. Identifying major utilities based on their critical nature or potential high cost and complexity of relocation. Utilities identified included: telecommunications networks (buried telephone and fiber optic lines), overhead electric and telephone, cell phone towers, irrigation ditches, water lines 24 inches or larger in diameter, sanitary sewer lines 18 inches or larger in diameter or any size if constructed of brick/clay, storm sewers or culverts 36 inches or larger in diameter, gas transmission lines, natural gas pipelines, petroleum lines, pump or meter stations, electric substations, and high-voltage lines (ELT lines). Identifying potential utility conflicts and comparing them to the Gold Line footprint with the locations of utilities as plotted on the utility map. The maximum excavation depth required to construct tracks at grade was assumed to be 4 feet. Utilities were assumed to be impacted if they crossed the proposed alignment footprint; ran parallel to and inside of the proposed alignment footprint; were located within a station footprint; were unable to function normally; were inaccessible; were not able to maintain sufficient clearance; or could have ruptured or disrupted service. Evaluating both relocations and adjustments in terms of possible disruptions in service or endangerment to human health and the environment from rupture that could result during either action. It is expected that all utility impacts would be short term, these would be addressed prior to or during construction by relocation or adjustment, and there would be no rupturing of gas, sanitary, sewer, or water lines BResults 13BNo Action Alternative The No Action Alternative assumes that existing and committed improvements, as defined in Chapter 2, Alternatives Considered, would be implemented by others as planned. 15BUDirect Impacts Roadway Projects Implementation of the two roadway projects and the reconstruction of the I-70/Kipling interchange would require the proportionate expansion of existing storm sewer systems to accommodate increased storm flows. Other than construction effects discussed below, utilities such as water and wastewater, communications systems, and electric power would be unaffected

3.11. Hazardous Materials

3.11. Hazardous Materials 3.11 Hazardous Materials 3.11 Hazardous Materials 3.11.1 Introduction to Analysis 3.11.1.1 Summary of Results Hazardous materials sites may be encountered during the construction of the stations, electric

More information

Section 3.11: Hazardous Materials

Section 3.11: Hazardous Materials Section 3.11: Hazardous Materials Section 3.11 Hazardous Materials 3.11 HAZARDOUS MATERIALS 3.11.1 Introduction to Analysis This section provides information regarding known contaminated sites and general

More information

3.11 HAZARDOUS MATERIALS

3.11 HAZARDOUS MATERIALS 3.11 HAZARDOUS MATERIALS 3.11.1 Introduction to Analysis This section provides information regarding known contaminated sites and general areas of potentially contaminated properties along the proposed

More information

TABLE SUMMARY OF POTENTIAL CONFLICTS WITH MAJOR UTILITIES DUS ACCESS TO 162 ND AVENUE AREA

TABLE SUMMARY OF POTENTIAL CONFLICTS WITH MAJOR UTILITIES DUS ACCESS TO 162 ND AVENUE AREA 3.13 UTILITIES 3.13.1 Introduction to Analysis Impacts to existing utilities by transportation projects have the potential to adversely affect the cost and schedule of a project as well as neighboring

More information

Hazardous Materials Technical Memorandum

Hazardous Materials Technical Memorandum Hazardous Materials Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District

More information

4.12 Public and Emergency Services

4.12 Public and Emergency Services 4.12 Public and Emergency Services Public services include schools, community centers, cemeteries, and social service providers. Emergency services include fire and police stations and services, hospitals,

More information

Wetlands and Other Waters of the United States

Wetlands and Other Waters of the United States 3.10.3 Wetlands and Other Waters of the United States 3.10.3.1 Introduction to Analysis Summary of Results The Preferred Alternative would result in the direct, permanent impact of 1.17 acres of wetlands

More information

3.10. Natural Resources

3.10. Natural Resources 3.10 Natural Resources 3.10 Natural Resources Section 3.10.1 discusses mineral resources and geologic impacts, Section 3.10.2 discusses water resources impacts, Section 3.10.3 discusses wetlands and wetland

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Transportation and Utilities

Transportation and Utilities 4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

Chapter 14 Public Services and Utilities

Chapter 14 Public Services and Utilities Chapter 14 Public Services and Utilities 1 What are the existing public services and facilities in the region? This chapter discusses existing public services and facilities in the central Puget Sound

More information

GENERAL NOTES REQUIRED NOTES ON ALL PLANS

GENERAL NOTES REQUIRED NOTES ON ALL PLANS GENERAL NOTES REQUIRED NOTES ON ALL PLANS ALL MATERIALS, WORKMANSHIP AND CONSTRUCTION SHALL CONFORM TO THE CURRENT CITY OF SANTA ROSA DESIGN AND CONSTRICTIOIN STANDARDS AND CONSTRUCTION SPECIFICATIONS

More information

Chapter 10. Intelligent Transportation Systems. Ohio Kentucky Indiana Regional Council of Governments Regional Transportation Plan

Chapter 10. Intelligent Transportation Systems. Ohio Kentucky Indiana Regional Council of Governments Regional Transportation Plan Chapter 10 Intelligent Transportation Systems Ohio Kentucky Indiana Regional Council of Governments 2030 Regional Transportation Plan Chapter 10 Intelligent Transportation Systems INTRODUCTION Intelligent

More information

Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011

Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011 Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011 General Provisions and Specifications - These provisions and specifications shall

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 Table 4.17-3. Summary of Adverse Environmental Justice Impacts Topic No Build TSM At-Grade Emphasis LRT Underground Emphasis LRT Locally Preferred Alternative Transit

More information

SECTION 9000 MAINTENANCE SERVICES

SECTION 9000 MAINTENANCE SERVICES SECTION 9000 MAINTENANCE SERVICES 9000 MAINTENANCE SERVICES... 1 9001 LEGISLATIVE AUTHORITY... 1 9002 GENERAL MAINTENANCE... 1 9003 PEDESTRIAN OVERPASSES... 1 9003.1 GENERAL MAINTENANCE... 1 9003.2 WINTER

More information

CHAPTER 3 SCOPE SUMMARY

CHAPTER 3 SCOPE SUMMARY CHAPTER 3 SCOPE SUMMARY GENERAL The SDDOT is an active member of AASHTO to share common national design standards for the state highway system. The AASHTO Task Force on Geometric Design has completed the

More information

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014 New Stadium Project Construction Activity Mitigation Program January 22, 2014 Construction Mitigation Plan Introduction It is the primary goal of HHRM, JV to minimize negative effects on traffic and the

More information

Sediment control measures, including straw bales, silt fences, sediment traps and/or sediment basins

Sediment control measures, including straw bales, silt fences, sediment traps and/or sediment basins During final design, additional efforts will be taken to minimize wetland impacts, such as minimizing culvert lengths and the use of riprap for bridge abutment protection and stormwater outfalls. Wetland

More information

Chapter 11: Hazardous Materials A. INTRODUCTION

Chapter 11: Hazardous Materials A. INTRODUCTION Chapter 11: Hazardous Materials A. INTRODUCTION This chapter relies on the analysis from the Fresh Kills Park Final Generic Environmental Impact Statement (FGEIS) and summarizes the conclusions drawn from

More information

SOIL MANAGEMENT PLAN

SOIL MANAGEMENT PLAN SOIL MANAGEMENT PLAN BELFAST BOATYARD 39 & 41 FRONT STREET BELFAST, MAINE Prepared by: Ransom Consulting, Inc. 400 Commercial Street, Suite 404 Portland, Maine 04101 (207) 772-2891 March 22, 2013 1.0 INTRODUCTION

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED METROPOLITAN COUNCIL ENVIRONMENTAL SERVICES ST. LOUIS

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

19. Hazardous Materials

19. Hazardous Materials Northern Branch Corridor SDEIS March 207 9. Materials 9.. Chapter Overview 9... Introduction The following analysis was conducted to determine whether the new or relocated SDEIS elements that were proposed

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

Appendix C Chapter 1 Initial Site Assessment Worksheet

Appendix C Chapter 1 Initial Site Assessment Worksheet Appendix C Chapter 1 Initial Site Assessment Worksheet Contents Section 1 Overview...1-2...1-3 C-1-1 Section 1 Overview Section 1 Overview Disclaimer The following worksheet is an example and provides

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

Appendix H Mitigation Monitoring Plan

Appendix H Mitigation Monitoring Plan Appendix H Mitigation Monitoring Plan Appendix H No. Impact/Mitigation Measure Implementation & Monitoring 1. Traffic and Transportation Impacts All traffic control plans and mitigation measures, prepared

More information

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location Maryland Department of the Environment Site Location FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) This 2.4581-acres site (Site) consists of four parcels of

More information

REPORT ON PHASE I ENVIRONMENTAL SITE ASSESSMENT 1358 COKER STREET OSGOODE WARD, GREELY CITY OF OTTAWA, ONTARIO. Submitted to:

REPORT ON PHASE I ENVIRONMENTAL SITE ASSESSMENT 1358 COKER STREET OSGOODE WARD, GREELY CITY OF OTTAWA, ONTARIO. Submitted to: Civil Geotechnical Structural Environmental Industrial Health & Safety 215 Sanders Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 REPORT ON PHASE I ENVIRONMENTAL

More information

Project Initiation Form

Project Initiation Form Meeting Date: The Project Initiation Form should be completed in conjunction with the Level 2 Screening Form. Process Leads and/or Planners should complete the Project Initiation Form to document coordination

More information

SECTION MAINTENANCE OF EXISTING CONDITIONS

SECTION MAINTENANCE OF EXISTING CONDITIONS SECTION 02 01 00 MAINTENANCE OF EXISTING CONDITIONS PART 1 GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged

More information

4.14 HAZARDOUS MATERIALS

4.14 HAZARDOUS MATERIALS 4.14 HAZARDOUS MATERIALS INTRODUCTION The presence of hazardous materials is a part of everyday life that could affect residents, workers, and visitors within the County. Certain activities can pose a

More information

Environmental Assessment. Appendix G Hazardous Materials Technical Report

Environmental Assessment. Appendix G Hazardous Materials Technical Report Environmental Assessment Appendix G Hazardous Materials Technical Report Hazardous Materials and Waste Sites Summary Technical Memorandum Kansas City Streetcar Main Street Extension December 20, 2018 DRAFT

More information

12.0 Contaminated Materials

12.0 Contaminated Materials 12.0 Contaminated Materials 12.1 Introduction An investigation was performed to identify hazardous waste and contaminated material sites in the study area of the Columbia Pike Transit Initiative ( the

More information

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX Southern California Association of Governments ADOPTED APRIL 2012 INTELLIGENT TRANSPORTATION SYSTEMS Introduction 1 Existing System Description 1 Existing System

More information

I-275 (State Road 93) Project Development & Environment Study

I-275 (State Road 93) Project Development & Environment Study DRAFT CONTAMINATION SCREENING EVALUATION REPORT (POND SITES) I-275 (State Road 93) Project Development & Environment Study From north of Dr. Martin Luther King Jr Boulevard (SR 574) to north of Bearss

More information

Evaluation of Alternatives

Evaluation of Alternatives Chapter 9.0 Evaluation of Alternatives Chapter 9.0 provides a summary evaluation of the No Build Alternative and the Preferred Alternative. The evaluation contained within this chapter is an assessment

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 9 General Infrastructure

FLORIDA STATE UNIVERSITY MASTER PLAN 9 General Infrastructure GENERAL INFRASTRUCTURE ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee

More information

Chapter 6 Freight Plan

Chapter 6 Freight Plan Chapter 6 Freight Plan Overview This chapter presents a review and assessment of needs, deficiencies, policies and improvement options affecting the freight transportation system within the Medford Urban

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

MEMO. Please submit written comments by US Mail to: North Coast Railroad Authority Attn: Heather Lindsteadt 419 Talmage Road, Suite M Ukiah, Ca 95482

MEMO. Please submit written comments by US Mail to: North Coast Railroad Authority Attn: Heather Lindsteadt 419 Talmage Road, Suite M Ukiah, Ca 95482 MEMO The primary purpose of these proposed guidelines is to establish safety and operational standards for any trail proposed on NCRA right-of-way. On August 13, 2008 the North Coast Railroad Authority

More information

STATEMENT OF PRINCIPLE

STATEMENT OF PRINCIPLE 2011 STATEMENT OF PRINCIPLE It is important to understand that this Guide is a "baseline". Each organization should develop and utilize its own approach to the "baseline". The success of the Guide is predicated

More information

DESIGN OF ROAD OVERBRIDGES

DESIGN OF ROAD OVERBRIDGES Civil Engineering Technical Requirement CIVIL-SR-001 DESIGN OF ROAD OVERBRIDGES Revision: G Updated: 30 May 2011 Queensland Rail 2011 Reproduction by any means (including electronic, mechanical, photocopying,

More information

Oklahoma Underground Facilities Damage Prevention Act

Oklahoma Underground Facilities Damage Prevention Act Oklahoma Underground Facilities Damage Prevention Act For your reference a copy of the act has been included in this guide. The act may be changed at any time and you should contact Oklahoma One-Call System,

More information

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

Application For Waste Regulation (Check all that apply)

Application For Waste Regulation (Check all that apply) Environmental Protection and Growth Management Department ENVIRONMENTAL ENGINEERING AND PERMITTING DIVISION 1 North University Drive, Mailbox #201 Plantation, Florida 33324 954-519-1483 FAX 954-519-1412

More information

SECTION TRAFFIC REGULATIONS

SECTION TRAFFIC REGULATIONS PART 1 GENERAL 1.1 DESCRIPTION A. Traffic Control permits, notifications, mobilization, temporary signs, barriers, lights, flagging personnel, striping, markings, and demobilization and removal. 1.2 RELATED

More information

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required.

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required. Overview of Section 9 9.0 The GESC Permit Section provides a description of the Small Utility GESC Permit Program. Step 1. Determine if a GESC Permit is Applicable and if a Project Specific GESC Plan is

More information

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc. 2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction

More information

11 Joint Development Regulatory Context and Methodology

11 Joint Development Regulatory Context and Methodology 11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit

More information

COUNTY OF SUTTER ENCROACHMENT PERMIT

COUNTY OF SUTTER ENCROACHMENT PERMIT COUNTY OF SUTTER ENCROACHMENT PERMIT PERMIT No. Development Services Dept. Engineering Division 1130 Civic Center Blvd Yuba City, CA 95993 (530) 822-7400 Hours: 8 AM - 5 PM Upon completion, submit application

More information

Mendocino Forest Products Grading For Industrial Land Improvements

Mendocino Forest Products Grading For Industrial Land Improvements Mendocino Forest Products Grading For Industrial Land Improvements Technical Memorandum #10 CEQA Evaluation of Environmental Impacts Prepared for: Mendocino Forest Products Company, LLC Consulting Engineers

More information

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas.

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas. Affected Environment, Environmental 2.1.4 Utilities and Service Systems This section addresses the potential impacts to public utilities and service systems within the project area as a result of project

More information

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS Section Title Page 12.1 General... 12-1 12.2 Design Standards... 12-1 12.2.1 General Requirements...12-1 12.2.2 Minimum Depth...12-1

More information

Infrastructure Element

Infrastructure Element Infrastructure Element 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 INFRASTRUCTURE ELEMENT GOAL 1: To provide for environmentally

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

EMU: BN/UP ALTERNATIVE ARVADA RIDGE STATION OPTION A

EMU: BN/UP ALTERNATIVE ARVADA RIDGE STATION OPTION A OPTION A OPTION A: GOLD LINE TEAM ANALYSIS Option A Parking on the Southwest corner of Ridge & Kipling Operational Community Environmental ADVANTAGES Good access off of Kipling at 51 st Place Good community

More information

VALLEY LATERAL PROJECT. RESOURCE REPORT 11 Reliability and Safety. FERC Docket No. CP

VALLEY LATERAL PROJECT. RESOURCE REPORT 11 Reliability and Safety. FERC Docket No. CP VALLEY LATERAL PROJECT RESOURCE REPORT 11 Reliability and Safety FERC Docket No. CP16- -000 November 2015 Section TABLE OF CONTENTS Page 11.0 RELIABILITY AND SAFETY... 11-1 11.1 NATURAL GAS PIPELINE INDUSTRY

More information

Highway / Utility Guide

Highway / Utility Guide Oregon Department of Transportation Highway Division Right of Way Section Highway / Utility Guide Railroad & Utilities Unit Right of Way Section STATEMENT OF PURPOSE It is important to understand that

More information

Traffic Impact Study Requirements

Traffic Impact Study Requirements [TYPE THE COMPANY NAME] Traffic Impact Study Requirements County of San Mateo Department of Public Works Roadway Services 9/1/2013 I. Introduction The County of San Mateo (County), Department of Public

More information

City of Reno Public Works

City of Reno Public Works City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE11-00XXX Applicant: Job Description:

More information

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. Contact the Planning Department at 970-429-2799 with any questions. November 2017

More information

Canadian National Contractor Safety Orientation Canadian Based Operating Companies Course Exam

Canadian National Contractor Safety Orientation Canadian Based Operating Companies Course Exam Canadian National Contractor Safety Orientation Canadian Based Operating Companies Course Exam Question 1: Before working on CN property, the contractor must: A. Have a valid right of entry agreement.

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

Review Zone Application for D&R Canal Commission Decision

Review Zone Application for D&R Canal Commission Decision Review Zone Application for D&R Canal Commission Decision MEETING DATE: December 21, 2016 DRCC #: 16-4345 Latest Submission Received: December 7, 2016 Applicant: Robert McCarthy, PE PSE&G 4000 Hadley Road,

More information

CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application

CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application Good for 90 days from the Date Issued This permit is only required if the work location is owned or controlled by the City of Homestead and

More information

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows: SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities

More information

STAFF REPORT. To: Planning Commission Meeting date: December 14, 2016 Item: UN Prepared by: Robert Eastman. To allow a vehicle impound yard

STAFF REPORT. To: Planning Commission Meeting date: December 14, 2016 Item: UN Prepared by: Robert Eastman. To allow a vehicle impound yard # 6 ) UN-79-16 ABC TOWING, TITAN TOWING, AND TOW GUY TOWING SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: December 14, 2016 Item: UN-79-16 Prepared by: Robert Eastman

More information

6.1 Introduction to Wastewater Issues

6.1 Introduction to Wastewater Issues Section 6: Water Pollution This Section will help you: Understand if you generate industrial wastewater; Understand where your wastewater goes; Make sure you meet requirements for floor drains; Properly

More information

BNSF North SIG Intermodal Improvement Project. Seattle, Washington

BNSF North SIG Intermodal Improvement Project. Seattle, Washington BNSF North SIG Intermodal Improvement Project Seattle, Washington By Charles E. Burnham, P.E. David Evans and Associates, Inc. Trans-Pacific Trade Center Building 3700 Pacific Highway East, Suite 311 Tacoma,

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Article 16 Traffic Impact Analysis

Article 16 Traffic Impact Analysis Article 16 Traffic Impact Analysis Table of Contents... 16-1 Chapter 16.1 Purpose and Intent... 16-2 Chapter 16.2 Applicability... 16-2 Chapter 16.3 Exemptions... 16-2 Chapter 16.4 Trip Generation Data...

More information

Chapter 9 UTILITIES ELEMENT

Chapter 9 UTILITIES ELEMENT Chapter 9 UTILITIES ELEMENT Introduction The state of Washington Growth Management requires that local governments developing or updating Comprehensive Plans under the Act to include an element within

More information

Federal Way Transit Center to Tacoma Dome Light Rail

Federal Way Transit Center to Tacoma Dome Light Rail Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 9.7 miles Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project

More information

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) 8 Evaluation of Alternatives This chapter evaluates the effectiveness of the No Build Alternative and the Southwest Light Rail Transit (LRT) Project (the Project) based on the information contained in

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1300 CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1301 SECTION 13.01 STATEMENT OF PURPOSE To provide for manufactured home park development, of long-term duration of stay, in

More information

OTHER CEQA CONSIDERATIONS

OTHER CEQA CONSIDERATIONS Chapter 5 OTHER CEQA CONSIDERATIONS CEQA Guidelines Section 15128 requires that an EIR disclose the reasons why various possible environmental effects of a proposed project are found not to be significant

More information

Rte. 66/29 Interchange Reconstruction Project: ,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track

Rte. 66/29 Interchange Reconstruction Project: ,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track Rte. 66/29 Interchange Reconstruction Project: 0066-076-113,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track Mileposts B-8.1 thru B-8.8 DOT 714-363S, 714-364Y Gainesville,

More information

SECTION 10 UTILITIES

SECTION 10 UTILITIES SECTION 10 UTILITIES Virtually every highway construction project in the State of New Jersey impacts utility facilities. The Designer shall examine and seek alternatives to minimize or eliminate the impact

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

ATTACHMENT A: FINDINGS

ATTACHMENT A: FINDINGS ATTACHMENT A: FINDINGS 1.0 CEQA FINDINGS 1.1 CEQA Exemption The County Planning Commission finds that the proposed project is exempt from environmental review under the California Environmental Quality

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES The District of West Vancouver requires a Traffic Management Plan (TMP) to be submitted for acceptance by the Land Development

More information

Peterborough County Road Safety Audit Guideline Pilot

Peterborough County Road Safety Audit Guideline Pilot Peterborough County Pilot Table of Contents 1.0 Purpose... 3 2.0 Road Safety Audit Objectives... 3 3.0 Legal Issues... 3 4.0 Road Safety Audit Procedures... 4 4.1 Project Selection Criteria... 5 4.2 Scope...

More information

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed

More information

Sheriff Protection Services

Sheriff Protection Services 3.11.2 Sheriff Protection Services ENVIRONMENTAL SETTING Existing Conditions Police protection, enforcement, and emergency services in the City of Malibu are provided by the Los Angeles County Sheriff

More information

Woodlake General Plan Draft Environmental Impact Report

Woodlake General Plan Draft Environmental Impact Report 5.0 UNAVOIDABLE ADVERSE ENVIRONMENTAL EFFECTS The following potential adverse environmental effects appear to be unavoidable if the Woodlake General Plan is implemented, even if certain mitigation measures

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: NOVEMBER 13 THROUGH NOVEMBER

More information

City of Tacoma Surface Water Management Manual

City of Tacoma Surface Water Management Manual City of Tacoma Surface Water Management Manual Volume IV Source Control BMPs Prepared by: Tacoma Public Works Environmental Services January 2003 Table of Contents Chapter 1 Introduction to Volume IV...

More information

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System INSTRUCTIONS: This form shall be completed and submitted (in duplicate)

More information

G. HYDROLOGY Existing Conditions

G. HYDROLOGY Existing Conditions G. HYDROLOGY Existing Conditions Surface Water Runoff This section is based on the hydrology and drainage analysis for the proposed Project, which was prepared by KPFF Consulting Engineers and is attached

More information

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA) DRAFT Analysis of Brownfields Cleanup Alternatives (ABCA) Preliminary Evaluation Ball Square Station Site Boston Avenue and Broadway Somerville and Medford, Massachusetts Massachusetts DEP Release Tracking

More information

KALIA-FORT DERUSSY WASTEWATER SYSTEM IMPROVEMENTS FINAL ENVIRONMENTAL ASSESSMENT EXECUTIVE SUMMARY

KALIA-FORT DERUSSY WASTEWATER SYSTEM IMPROVEMENTS FINAL ENVIRONMENTAL ASSESSMENT EXECUTIVE SUMMARY EXECUTIVE SUMMARY This Environmental Assessment (EA) addresses the environmental impacts of the Proposed Action to construct certain improvements to the City and County of Honolulu (City) wastewater collection

More information