The data contained several inconsistencies and the following procedure was used to identify and rectify readings that appeared erroneous:

Size: px
Start display at page:

Download "The data contained several inconsistencies and the following procedure was used to identify and rectify readings that appeared erroneous:"

Transcription

1 4.0 LAO POWER MARKET 4.1 Load Analysis Analysis of System Load Data Load data from EdL substations was collected analyzed and, after some adjustments, used as a basis for the development of dimensionless load duration curves needed by Lahmeyer s generation planning model, SEXSI. The load analysis was carried out for the calendar year 2002 and used data from EdL s existing grids but not from its isolated load centers. Hourly substation load data was keyed into data files and converted to the Lahmeyer time series database. Hourly values of power sent out were processed for most of the main 22 kv substations covering more than 90% of the total power demand. This figure was brought to 100% by proportioning the predicted year 2002 values of all substations given in Tables and of the report, Study on Master Plan of Transmission Line and Substation System in Lao PDR (the JICA Report ) 3 against those from the substations for which data was available. The data contained several inconsistencies and the following procedure was used to identify and rectify readings that appeared erroneous: All readings with a rise or fall exceeding 70% compared with the previous hour were marked and checked, and those showing subsequent rebound of the same magnitude were specially marked as being highly suspicious. The time series were then inspected for the occasions marked and adjustments made where plausible. Program HCHEK was used to automatically suggest more reasonable values based on readings for the same hour in the previous and following week. All days that showed a total drop in generation of 30% compared with the previous week were also inspected (program HCHEC), and adjustments made as described above. The losses for the 115 kv system were taken as 4% at peak load and quadratically less for periods of lighter loads; i.e. the corresponding energy loss during any hour at half of peak load would be calculated as 4% x = 1.0%. The results of the load analysis are given in Table 4.1 and a summary of peak load and energy requirements is provided in Table 4.2. The values in Table 4.1 are for stations connected to the grid by the beginning of A small percentage of national electricity demand occurs in small EdL grids, provincial isolated systems and through off-grid generation in remote locations. The estimation of peak load takes load diversity into account using the diversity 3 Study on Master Plan of Transmission Line and Substation System in Lao PDR, Final Report, Nippon Koei, JICA, September 2002 Final Report Vol A: Main Report 36

2 found in the 2002 load data. The estimated peak for an interconnected system is therefore less than the aggregate of peak loads of the component systems. Table 4.1: Load Analysis Summary Comparison with EdL PDP 2003 PSDP Load Analysis Isolated Grids Code Peak Energy Load Factor Diversity Facor (MW) (GWh/a) (%) (%) Central 1 C Central 2.1 C Central 2.2 C South S Sum CS Aggregate Values Central 1 + Central 2.1 C Central 1 + Central C Central + South S Comparison with EdL PDP 2003 Isolated Grids Code Peak Energy Difference in Peak Difference in Energy (MW) (GWh/a) (MW) (GWh/a) Central 1 C % 1% Central 2 C21+C % -2% South S % 30% Sum CS % 3% Aggregate Values Central 1 + Central C % 0% Central + South S % 3% Table 4.2: Peak Load and Energy Requirements Grid Code Peak Load (MW) Energy Requirement (GWh) Annual System Load Factor Central 1 + Central 2.1 C Central 1 + Central 2.1 and 2.2 C Central 1 + Central 2 + South CS Central 2.2 C South S It can be seen from Table 4.2 that EdL estimates of peak demand (MW) for combined systems (assuming interconnection) appears to be about 10% higher than the values derived from the load analysis. This is largely because load diversity was not considered by EdL. EdL s estimate of overall energy requirement (GWh) is also higher, by about 3%. (%) Final Report Vol A: Main Report 37

3 4.1.2 Load Profiles Information on the average weekly load profile and seasonal distribution of peak loads for each of the grids were also generated (example of Grids C1/C2.1 provided as Figures 4.1 and 4.2). Final Report Vol A: Main Report 38

4 Figure 4.1: 2002 Average Weekly Load Profile Central 1 and 2.1 Final Report Vol A: Main Report 39

5 Figure 4.2: 2002 Annual Peak Load Profile Central 1 and 2.1 A number of features of the load profiles in Lao PDR are evident: Three distinct peaks occur within the daily load curve in the morning, afternoon and evening. The prominent evening peak extends from 6:00pm to 9:00pm and defines the system s installed capacity requirements the morning and afternoon peaks are only 80% of the evening peak. The EGAT system peak is in the afternoon and the lack of coincidence with the Lao peak may provide opportunities for mutual gain in power trading arrangements. The morning and afternoon peaks are attenuated on Saturdays and Sundays and the evening peak is about 10% less than the weekday peaks. The shape of the daily load curve does not vary between seasons but the capacity does. Loads during the cooler months of December and January are about 80% of the equivalent loads dung the hottest months. The system load factor 4 is relatively constant over the year (refer Figure 4.2) Load Duration Curves The load analysis of hourly loads produced dimensionless load duration curves (LDC) for each month of 2002 for use in the SEXSI power system expansion modeling. The SEXSI model employs the dimensionless curves to provide load duration patterns for future years by scaling them up to the predicted peak power and generation requirements of a given year. As an example, monthly load duration curves for C1/C2.1 are provided as Figure 4.3). The uniformity in their shape emphasizes the lack of variation in load patterns between months. 4 System load factor is defined as the ratio of energy (continuous power) to peak demand. Final Report Vol A: Main Report 40

6 The 2002 annual load duration, formed by aggregating the monthly figures for individual substations, is provided as Figure 4.4). Figure 4.3: 2002 Monthly Dimensionless Load Duration Curves Central 1 and 2.1 Figure 4.4: 2002 Annual Dimensionless Load Duration Curves Central 1 and 2.1 Final Report Vol A: Main Report 41

7 4.2 Demand Forecast for Lao PDR Basis of Forecast The reference point for the preparation of the demand forecast is the Government s goal to increase the national electrification ratio from the current level of 41% to 90% by This goal will be achieved by: (i) (ii) Off-grid development a successful but embryonic program of off-grid electrification employing state, donor and private resources is in place in Lao PDR. Villages chosen for off-grid electrification are currently beyond the reach of the EdL grids and are expected to remain so for the next 10 years (the time assumed for amortization of off-grid loans). Grid extension programs involving sub-transmission and distribution development. These programs will be scoped to achieve the 90% target after taking into account the contribution of off-grid household electrification. The basis of the demand forecast is the growth in demand in EdL s grids due to increasing demand of existing custiomers plus load associated with new connections. To the extent practicable, the PSDP demand forecast is based on the EdL forecast which was reviewed and adapted for the purpose. EdL s current forecast is described in EdL s recently updated Power Development Plan (the EdL PDP ). 5 EdL based its forecast on the methodology adopted in the JICA Report. The methodologies used in the JICA Report and EdL PDP have been reviewed and a summary of the reviews is contained in Annex Assumptions The key assumptions used in deriving the EdL demand forecast are described in Annex 8. These have been modified for the PSDP in the following areas. (i) Forecast of Electrification Ratio The planned household and village electrification ratios are a key input into the EdL and JICA demand forecast models. Accordingly the planned electrification ratios have been reviewed and the EdL targets modified as noted in Table 4.3 with the objective of electricity being introduced into of 90% of households by 2020 either through grid connections or off-grid supplies. The EdL electrification rates have been modified for PSDP forecasting purposes as indicated in Table 4.3. The modified EdL rates represent achievable interim targets. 5 Power Development Plan PDP (Updated Schedule of Committed Projects), System Planning Office, Development Division, Electricité du Laos, July Final Report Vol A: Main Report 42

8 Table 4.3: Electrification Targets Forecast Scenario PDP Low (%) PDP Medium (%) PDP High (%) Modified PDP (%) Pre-Grid (%) Grid Conversion (%) Off-Grid (%) Modified EdL (%) Total Households ( ) 915, ,449 1,071,383 1,183,863 1,295,799 Pre-Grid Households ( ) 310 1,325 50,000 86, ,000 The assumptions and sources of data behind the PSDP electrification targets in Table 4.3 are outlined: a) EdL PDP low, medium and high scenario - the source of this data is the EdL Power Development Plan for the period , July Although it is not explicitly stated, EdL s power development plan has been predicated on the high growth forecast scenario. This is the scenario that achieves GOL s intermediate and long-term electrification targets. b) Modifications to EdL PDP The EdL PDP s 2010, 2015 and 2020 targets may be achievable if funds for the necessary capital works are available. The 2005 PDP target, though, is ambitious from two perspectives; firstly, availability of funds for capital works and, secondly, capacity constraints within the Lao power transmission and distribution system. Consequently, the 2005 target was reviewed downwards from the EdL PDP high and medium case values. A 2005 household electrification target of 45% was adopted by interpolating between the EdL PDP s 2003 and 2010 PDP household electrification targets. c) Pre-Grid The EdL PDP does not take into account off-grid technologies (pre-grid) for electrifying households. There is currently a successful off-grid program in Lao PDR and the pre-grid household electrification targets have been deducted from the overall household electrification targets for the PSDP forecast. Targets of 50,000 households by 2010 and 150,000 households by 2020 were established for the pre-grid program in consultation with the off-grid unit of DOE and the World Bank. Though the contribution of the off-grid program to GOL s household electrification targets is significant, the effect on forecast demand for capacity and energy is slight. Final Report Vol A: Main Report 43

9 d) Grid Conversion - In combination with pre-grid targets, a rate at which off-grid villages convert to grid supplies was also estimated. This target takes into the account pre-grid households that change to grid-connected services as the grid extends further into rural areas. The grid conversion target was established in consultation with the off-grid unit of DOE. e) Off-Grid The off-grid scenario represents the households that will use off-grid technologies for the foreseeable future and is calculated by deducting the grid conversion target from the pre-grid target. f) Modified EdL The modified EdL scenario is calculated by deducting the off-grid households from the modified EdL PDP scenario. This is the demand forecast scenario that the PSDP study will use as a Base Case going forward. The household electrification rates from which the EdL PDP and modified EdL demand forecast scenarios are derived are shown in Figure 4.5. The modified EdL demand forecast scenario, together with the underlying assumptions, were discussed with the World Bank. Figure 4.5: Household Electrification Rates (ii) Non-Residential Demand Growth Non-residential demand growth is based in part on GDP growth targets. Should actual GDP growth be less than the GOL s targets, there will be lower than planned demand growth. The GDP growth targets assumed are the same for all scenarios and are based on the Socio-Economic Strategy of the GOL, repeated in Table 4.4. Final Report Vol A: Main Report 44

10 Table 4.4: GDP Growth Targets 2000 to to to 2020 GDP Total GDP Industry Sector GDP Service Sector The above GDP growth figures have been adopted; however, demand forecast should be reviewed in subsequent years and adjusted to reflect any changes in actual and forecast GDP figures. (iii) Household Electrification Rate Household electrification rates (number of electrified houses divided by the total number of houses in each village) are not specifically taken into account in the demand forecast. The implication of a low household electrification rate is that the grid must extend further to electrify the target number of households and this increases the cost per electrified household in newly electrified villages. Though household electrification rates may be low initially, household electrification rates are expected to increase rapidly to close to 100% within within 5 years of the grid arriving at a village. We therefore have not taken the household electrification rate into account in the demand forecast. (iv) Coincidence The following coincidence factors were allowed for when interconnecting EdL s grids: Central 1 + C 2.1 Grid 0.97 Central 1 + C2.1 + C2.2 Grid 0.94 Central 1 + C2.1 + C2.2 + S Grid 0.94 v) Industry Load in Central 2.1 Grid There is evidence of increasing economic activity in Lao PDR and the GMS region. A number of developments within the Central C2 supply area, in particular, is seeing a significant increase in demand. The improvement of the north-south and east-west (Thailand-Vietnam) road system will contribute to the general development of the area but, more significantly in the short term, a number of industrial point loads are being added in the Central 2.1 area including the following: Cement factory 20 MW 2005 Quarry 5 MW 2008 Gypsum & lead mine 5 MW 2006 Copper/Gold Mine 40 MW 2005 Final Report Vol A: Main Report 45

11 Nam Theun 2 construction 4-8 MW Irrigation 10 MW vi) Actual Energy Demand Data The 2002 value of demand was determined using load data obtained from EdL substations and processed using Lahmeyer s HCHEC and HDURM programs. The value so derived did not correspond to the EdL figure for the same year and the EdL forecast was therefore adjusted for PSDP purposes by anchoring the EdL growth forecasts to this known 2002 starting value PSDP Base Case Scenario Assumptions In summary, the PSDP base case demand forecast for grid-supplied electricity (domestic consumption) is formulated on the EdL PDP forecast with the following adjustments: (i) (ii) (iii) (iv) (v) The household electrification target (inclusive of off-grid households) for 2005 is reviewed downward to 45%; Pre-grid and off-grid households are taken into account in the projections of total households electrified; Coincidence has been allowed for when interconnecting isolated grids; Additional industrial load has been allowed for in the Central 2.1 grid (Khamouanne Province); The forecast has been adjusted to reflect actual 2002 energy demand data Comparison of PSDP and EdL Forecasts The aggregate EdL demand forecast is summarized in Table 4.5. The PSDP demand forecast, determined by making the adjustments to the EdL forecast described in the preceding section, is summarized in Table 4.6. The apparent anomaly between years 2002 and 2005 is caused by the copper/gold mine electro winning process in Central 2.1. This will be a load of about 40 MW with a load factor of 0.8. The electro winning plant is presently under construction, as is the 115 kv transmission line to feed the plant, with a planned commissioning date of December A graphical comparison of recent demand forecasts is provided in Figure 4.6. Final Report Vol A: Main Report 46

12 Table 4.5: Aggregate EdL Forecast Item Unit Energy Consumption GWh , , , ,834.2 Av. annual Growth Rate % 24% 9% 6% 5% Peak Load MW Av. annual Growth Rate % 22% 8% 6% 5% Load Factor % 55.3% 55.6% 60.0% 60.0% 60.0% (Source: Summary of Electricity Demand Forecast (High Case), EdL PDP Plan, EdL Power Development Plan PDP , July 2003) Table 4.6: PSDP Demand Forecast Item Unit Energy Consumption GWh , , , ,664.2 Av. annual Growth Rate % 23% 9% 6% 6% Peak Load MW Av. annual Growth Rate % 20% 7% 6% 5% Load Factor % 54% 58% 63% 63% 64% Final Report Vol A: Main Report 47

13 Figure 4.6: Comparison of Recent Demand Forecasts 1200 MAXIMUM DEMAND (MW) PSDP Demand Forecast (June 2004) EdL PDP (High Scenario, July 2003) JICA Study, (High Scenario, Sept 2002) JICA Study, (Low Scenario, Sept 2002) PSSS Study (High Scenario, March 2001) PSSS Study (Base Scenario,March 2001) HDSS Study (Base Scenario, Jan 2000) YEAR 6000 DEMAND (GWh) PSDP Demand Forecast (June 2004) EdL PDP (High Scenario, July 2003) JICA Study, (High Scenario, Sept 2002) JICA Study, (Low Scenario, Sept 2002) PSSS Study (High Scenario, March 2001) PSSS Study (Base Scenario,March 2001) HDSS Study (Base Scenario, Jan 2000) YEAR Final Report Vol A: Main Report 48

Energy Policy in Lao PDR

Energy Policy in Lao PDR Energy Policy in Lao PDR Phonepasong SITHIDETH. Technical staff Ministry of Energy and Mines. (MEM) Department of Electricity. (DOE) IEEJ, May 2011 Tokyo Japan Content Background Current energy policy

More information

Rural Electrification Situation in Lao PDR

Rural Electrification Situation in Lao PDR Rural Electrification Situation in Lao PDR CAP-REDEO MEETING 4 th April 2007. Vientiane, LAO PDR Department of Electricity, Ministry of Energy and Mines LAO PDR Tel: 856-21 21-415714 Fax; 856-21 21-415388

More information

Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic, Social and Environment Blueprint Perspective

Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic, Social and Environment Blueprint Perspective Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic, Social and Environment Blueprint Perspective Akhomdeth Vongsay and Xayphone Bounsou National University of Laos

More information

REFERENCES. 1. Acres International, RSW and Hydro Quebec, Nam Tha 1 Hydropower Project, Report to SPB Hydro-Power Co. Ltd., November 1997.

REFERENCES. 1. Acres International, RSW and Hydro Quebec, Nam Tha 1 Hydropower Project, Report to SPB Hydro-Power Co. Ltd., November 1997. REFERENCES ANNEX 3 ANNEX 3 REFERENCES 1. Acres International, RSW and Hydro Quebec, Nam Tha 1 Hydropower Project, Report to SPB Hydro-Power Co. Ltd., November 1997. 2. ADB Developing Best Practices for

More information

AEC + BIMSTEC EC : ASEAN Economic Community + Bay of Bengal Initiative for Multi-sectoral Technical and Economic Cooperation

AEC + BIMSTEC EC : ASEAN Economic Community + Bay of Bengal Initiative for Multi-sectoral Technical and Economic Cooperation AEC + BIMSTEC EC : ASEAN Economic Community + Bay of Bengal Initiative for Multi-sectoral Technical and Economic Cooperation 11 2556 2 (GDP) 3 - - 7 - - 4 Low Carbon Economy: 450 ppm scenario 5 2,000 1,800

More information

Thailand Power Development Plan (PDP 2007)

Thailand Power Development Plan (PDP 2007) Thailand Power Development Plan (PDP 2007) By Mr. Prutichai Chonglertvanichkul Assistant Governor - Planning Electricity Generating Authority of Thailand (EGAT) Presented to High Level Forum on Lao-Thai

More information

POLICY REVIEW AND INSTITUTIONAL ANALYSIS OF THE HYDROPOWER SECTOR IN LAO PDR, CAMBODIA, AND VIETNAM

POLICY REVIEW AND INSTITUTIONAL ANALYSIS OF THE HYDROPOWER SECTOR IN LAO PDR, CAMBODIA, AND VIETNAM Mekong (MK1) project on optimizing reservoir management for livelihoods, Challenge Program for Water and Food POLICY REVIEW AND INSTITUTIONAL ANALYSIS OF THE HYDROPOWER SECTOR IN LAO PDR, CAMBODIA, AND

More information

Renewable Energy Development in Cambodia. Institute of Technology of Cambodia

Renewable Energy Development in Cambodia. Institute of Technology of Cambodia Renewable Energy Development in Cambodia Institute of Technology of Cambodia 1 BACKGROUND Cambodia, situated in Southeast Asia, shares borders with Vietnam, Laos and Thailand. Land area : 181 035 sq. km

More information

FP_C.3_EGAT_ Thai-Laos Cross Border Energy and Environment: Case study on Hong Sa Lignite Power Plants in Lao PDR.

FP_C.3_EGAT_ Thai-Laos Cross Border Energy and Environment: Case study on Hong Sa Lignite Power Plants in Lao PDR. FP_C.3_EGAT_ Thai-Laos Cross Border Energy and Environment: Case study on Hong Sa Lignite Power Plants in Lao PDR. Cherid Kalayanamitr, Project Environment Division Electricity Generating Authority of

More information

ECONOMIC ANALYSIS. A. Methodology and Major Assumptions

ECONOMIC ANALYSIS. A. Methodology and Major Assumptions Second Green Power Development Project (RRP BHU 44444) ECONOMIC ANALYSIS 1. Bhutan has one of the fastest growing economies in Asia. Its annual growth rate averaged 8.7% of gross domestic product (GDP)

More information

Sustainable Power Sector Development in the GMS

Sustainable Power Sector Development in the GMS Sustainable Power Sector Development in the GMS - Update on RETA 9003-20 June 2018 Hyunjung Lee, ADB & Nikolay Nikolov, Ricardo, TA team leader Project Overview TA background: GMS economic growth has been

More information

2.6 NAM FA HYROPOWER PROJECT

2.6 NAM FA HYROPOWER PROJECT 2.6 NAM FA HYROPOWER PROJECT The Nam Fa Project is located in Bokeo Province on the Nam Fa (Nam Pha). The layout of the Project is shown in the attached plan. The project configuration developed for the

More information

LAO PEOPLE S DEMOCRATIC REPUBLIC STUDY ON POWER SUPPLY AND DEMAND IN CENTRAL REGION IN LAO PEOPLE S DEMOCRATIC REPUBLIC

LAO PEOPLE S DEMOCRATIC REPUBLIC STUDY ON POWER SUPPLY AND DEMAND IN CENTRAL REGION IN LAO PEOPLE S DEMOCRATIC REPUBLIC No. Ministry of Energy and Mines Electricite du Laos EDL-Generation Public Company Lao People's Democratic Republic LAO PEOPLE S DEMOCRATIC REPUBLIC STUDY ON POWER SUPPLY AND DEMAND IN CENTRAL REGION IN

More information

Chapter 10. Lao PDR Country Report. September 2016

Chapter 10. Lao PDR Country Report. September 2016 Chapter 10 Lao PDR Country Report September 2016 This chapter should be cited as Kouphokham, K. (2016), Lao PDR Country Report in Kimura, S. and P. Han (eds.) in Energy Outlook and Energy Saving Potential

More information

Towards a viable renewable energy sector for the Lao PDR

Towards a viable renewable energy sector for the Lao PDR Towards a viable renewable energy sector for the Lao PDR 1 Using Green Technology to solve problems Edward Allen The largest Renewable Energy and Resources institute in Lao PDR with the largest Bio-energy

More information

Chapter 1 Primary Energy Data

Chapter 1 Primary Energy Data Chapter 1 Primary Energy Data The primary energy sources of the Lao People s Democratic Republic (Lao PDR) consist of coal, oil, hydro, and biomass. The country imports oil products to meet its domestic

More information

INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID

INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID CEYLON ELECTRICITY BOARD INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID 2018-2028 Dr. H.M Wijekoon Chief Engineer (Transmission Planning) Randika Wijekoon Electrical Engineer (Generation

More information

The Lao People s Democratic Republic THE MASTER PLAN STUDY ON SMALL-HYDRO IN NORTHERN LAOS. Final Report : Volume 4 SMALL-HYDRO VISUAL GUIDE

The Lao People s Democratic Republic THE MASTER PLAN STUDY ON SMALL-HYDRO IN NORTHERN LAOS. Final Report : Volume 4 SMALL-HYDRO VISUAL GUIDE No. The Lao People s Democratic Republic THE MASTER PLAN STUDY ON SMALL-HYDRO IN NORTHERN LAOS Final Report : Volume 4 SMALL-HYDRO VISUAL GUIDE December 2005 Japan International Cooperation Agency Economic

More information

Key Statistical Data

Key Statistical Data Key Statistical Data System Installed Generating Capacity Type of Power Plant 2012 2011 Increase MW Percentage MW Percentage Percentage EGAT s Power Plants Thermal 4,699.00 14.41 4,699.00 14.94 - Combined

More information

Electricity Data Collection

Electricity Data Collection Electricity Data Collection Energy Development Department General Department of Energy MINISTRY OF MINES AND ENRGY, CAMBODIA 02 March 2016, Paris, France Content 1. Overviews of Power Sector 2. Rule of

More information

OPTIMIZATION FOR PEAKING POWER SUPPLY

OPTIMIZATION FOR PEAKING POWER SUPPLY CHAPTER 6 MASTER PLAN ON OPTIMIZATION FOR PEAKING POWER SUPPLY Chapter 6. Master Plan on Optimization for Peaking Power Supply 6.1 Preliminary Study of Optimization of Peaking Power Supply 6.1.1 Efficient

More information

ECONOMIC ANALYSIS. B. Calculation of Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis

ECONOMIC ANALYSIS. B. Calculation of Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis Sustainable Power Sector Support Project (RRP SRI 39415) ECONOMIC ANALYSIS A. Background and Approach 1. The analysis was undertaken to determine the economic viability of the project components. The analysis

More information

The Study on Power Network System Plan in Lao People s Democratic Republic. Final Report (Summary)

The Study on Power Network System Plan in Lao People s Democratic Republic. Final Report (Summary) Department of Electricity, Ministry of Energy and Mines Electricité du Laos Lao People s Democratic Republic The Study on Power Network System Plan in Lao People s Democratic Republic Final Report (Summary)

More information

Newfoundland Power Marginal Cost of Electricity Service Study

Newfoundland Power Marginal Cost of Electricity Service Study 12. Marginal Cost Study Newfoundland Power Marginal Cost of Electricity Service Study Newfoundland Power 2008 General Rate Application Newfoundland Power Marginal Cost of Electricity Service Study Prepared

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

Increase Type of Power Plant MW Percentage MW Percentage Percentage

Increase Type of Power Plant MW Percentage MW Percentage Percentage Key Statistical Data System Installed Generating Capacity 2013 2012 Increase Type of Power Plant MW Percentage MW Percentage Percentage EGAT s Power Plants Thermal 4,699.00 13.95 4,699.00 14.41 - Combined

More information

Current status and Development plan for Grid Small Hydro Power in Thailand

Current status and Development plan for Grid Small Hydro Power in Thailand Current status and Development plan for Grid Small Hydro Power in Thailand Krittiya Petsee Plan and Policy Analyst Department of Alternative Energy Development and Efficiency Thailand 4, April 2013 Hanoi,

More information

National Stakeholders Workshop on Accessible and Affordable Sustainable Energy. Brief Report

National Stakeholders Workshop on Accessible and Affordable Sustainable Energy. Brief Report ASIAN AND PACIFIC CENTRE FOR TRANSFER OF TECHNOLOGY (APCTT) National Stakeholders Workshop on Accessible and Affordable Sustainable Energy 11-12 February 2014 Vientiane, Lao People's Democratic Republic

More information

Rural Electrification by Renewable Energy in Cambodia

Rural Electrification by Renewable Energy in Cambodia Capacity and Institutional Strengthening for Rural Electrification and Development-Decentralized Energy Options Rural Electrification by Renewable Energy in Cambodia Heng Kunleang Deputy Director Energy

More information

Theme 7: Good practice of Renewable Energy projects in Lao PDR

Theme 7: Good practice of Renewable Energy projects in Lao PDR Theme 7: of Renewable Energy projects in Lao PDR Dr. Khamphone Nanthavong Faculty of Engineering, National University of Laos 03.02.2013 Seite 1 Case Person In charge Number of slides Renewable energy

More information

2.24 VIENGPHOUKA THERMAL PROJECT

2.24 VIENGPHOUKA THERMAL PROJECT 2.24 VIENGPHOUKA THERMAL PROJECT The Viengphouka Thermal Project is a mine-mouth coal-fired base load power generation project located in Luangnamtha Province. The Consultant has evaluated the Project

More information

2.29 XE KONG 5 HYDROPOWER PROJECT

2.29 XE KONG 5 HYDROPOWER PROJECT 2.29 XE KONG 5 HYDROPOWER PROJECT The Xe Kong 5 Hydropower Project is located in Kaleum District, Xe Kong Province on the upper reaches of the Xe Kong, immediately upstream of the proposed Xe Kong 4 Hydropower

More information

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid ONTARIO ENERGY REPORT Q3 Y T ELECTRICITY Electricity Highlights Third Quarter Electricity Generation Output by Fuel Type (Q3) Nuclear Ontario Peak Demand (Q3) 21,363 MW 25.0 TWh 65.7% Hydro 8.8 TWh 23.1%

More information

NPCC 2017 Ontario Interim Review of Resource Adequacy

NPCC 2017 Ontario Interim Review of Resource Adequacy NPCC 2017 Ontario Interim Review FOR THE PERIOD FROM 2018 TO 2020 APPROVED BY THE RCC ON DECEMBER 5, 2017 This page intentionally left blank. ii Document Change History Issue Reason for Issue Date 1.0

More information

USING A BATTERY ENERGY STORAGE SYSTEM AND DEMAND RESPONSE CONTROL TO INCREASE WIND POWER PENETRATION IN AN ISLAND POWER SYSTEM

USING A BATTERY ENERGY STORAGE SYSTEM AND DEMAND RESPONSE CONTROL TO INCREASE WIND POWER PENETRATION IN AN ISLAND POWER SYSTEM USING A BATTERY ENERGY STORAGE SYSTEM AND DEMAND RESPONSE CONTROL TO INCREASE WIND POWER PENETRATION IN AN ISLAND POWER SYSTEM ABSTRACT This paper defines a study where the wind power generation in an

More information

CAMBODIA ENERGY SECTOR

CAMBODIA ENERGY SECTOR CAMBODIA ENERGY SECTOR Overview of potential electricity sector opportunities June 2018 Background This summary paper has been prepared by Investing In Infrastructure Cambodia (3i) a development program

More information

Contents Overview of Laos Current energy policy and Measure Energy demand and Supply in Laos Energy outlook in Laos Difficulties and bottlenecks in fo

Contents Overview of Laos Current energy policy and Measure Energy demand and Supply in Laos Energy outlook in Laos Difficulties and bottlenecks in fo IEEJ : June 2012 Country report Lao PDR Litthanoulok LASPHO Engineer Ministry of Energy and Mines, Department of Energy Policy and Planning. Contents Overview of Laos Current energy policy and Measure

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources Tim Burdis Lead Strategist, State Government Policy October 10, 2017 Cleveland, Ohio PJM as Part of the Eastern Interconnection Key Statistics Member companies 1,000+ Millions

More information

Universal Access to Modern Energy Services and Clean Energy Development

Universal Access to Modern Energy Services and Clean Energy Development Universal Access to Modern Energy Services and Clean Energy Development USEA Global Workshop on Clean Energy Development December 5, 2012 Junhui Wu, Senior Policy Advisor Retired World Bank Director of

More information

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool 2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.

More information

SUMMARY OF PROCEEDINGS

SUMMARY OF PROCEEDINGS GREATER MEKONG SUBREGION 24 th MEETING OF THE REGIONAL POWER TRADE COORDINATION COMMITTEE (RPTCC-24) NAY PYI TAW, MYANMAR, 19-20 JUNE 2018 SUMMARY OF PROCEEDINGS I. Introduction 1. The 24 th Meeting of

More information

Total Market Demand Wed Aug 08 Thu Aug 09 Fri Aug 10 Sat Aug 11 Sun Aug 12 Mon Aug 13 Tue Aug 14

Total Market Demand Wed Aug 08 Thu Aug 09 Fri Aug 10 Sat Aug 11 Sun Aug 12 Mon Aug 13 Tue Aug 14 MW This report provides a summary of key market data from the IESO-administered markets. It is intended to provide a quick reference for all market stakeholders. It is composed of two sections: Section

More information

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh) For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold

More information

ERAV Electricity Regulatory Authority of Vietnam

ERAV Electricity Regulatory Authority of Vietnam MINISTRY OF INDUSTRY AND TRADE ELECTRICITY REGULATORY AUTHORITY OF VIETNAM SOLAR ENERGY DEVELOPMENT POLITICAL AND REGULATORY FRAMEWORK IN VIETNAM Presented by: Mr. Dinh The Phuc Deputy Director General

More information

Ex-Ante Evaluation. Japanese ODA Loan

Ex-Ante Evaluation. Japanese ODA Loan Japanese ODA Loan Ex-Ante Evaluation 1. Name of the Project Country: Kingdom of Cambodia Project: Phnom Penh City Transmission and Distribution System Expansion Project (Phase 2) (I) Loan Agreement: March

More information

The LMB Sustainable Hydropower Development Strategy. Regional Power Trade Coordination Committee 24 Nay Pyi Taw, 20 June 2018

The LMB Sustainable Hydropower Development Strategy. Regional Power Trade Coordination Committee 24 Nay Pyi Taw, 20 June 2018 The LMB Sustainable Hydropower Development Strategy Regional Power Trade Coordination Committee 24 Nay Pyi Taw, 20 June 2018 The Lower Mekong Basin Most of Cambodia Most of Lao PDR North-East Thailand

More information

ALTERNATIVES FOR POWER GENERATION IN THE GREATER MEKONG SUB-REGION

ALTERNATIVES FOR POWER GENERATION IN THE GREATER MEKONG SUB-REGION ALTERNATIVES FOR POWER GENERATION IN THE GREATER MEKONG SUB-REGION Volume 7: GMS Power Sector Vision Modelling Assumptions Summary Final 29 March 2016 Disclaimer This report has been prepared by Intelligent

More information

Modeling of Autonomous Power Systems A Mathematical Model of a Hybrid Power System

Modeling of Autonomous Power Systems A Mathematical Model of a Hybrid Power System Modeling of Autonomous Power Systems A Mathematical Model of a Hybrid Power System Suvisanna Mustonen 1,* and Khamphone Nanthavong 2 1 Turku School of Economics, Finland Futures Research Centre, Finland

More information

Large-Scale Distributed Photovoltaic Power Dispatching and Operation Management Review

Large-Scale Distributed Photovoltaic Power Dispatching and Operation Management Review Journal of Power and Energy Engineering, 2015, 3, 326-331 Published Online April 2015 in SciRes. http://www.scirp.org/journal/jpee http://dx.doi.org/10.4236/jpee.2015.34044 Large-Scale Distributed Photovoltaic

More information

Coincidence Factor Study Residential and Commercial & Industrial Lighting Measures. Prepared for; New England State Program Working Group (SPWG)

Coincidence Factor Study Residential and Commercial & Industrial Lighting Measures. Prepared for; New England State Program Working Group (SPWG) Coincidence Factor Study Residential and Commercial & Industrial Lighting Measures Prepared for; New England State Program Working Group (SPWG) For use as an Energy Efficiency Measures/Programs Reference

More information

Solar PV in ASEAN Challenges and Opportunities. Peerapat Vithayasrichareon Centre for Energy and Environmental Markets (CEEM), UNSW Australia

Solar PV in ASEAN Challenges and Opportunities. Peerapat Vithayasrichareon Centre for Energy and Environmental Markets (CEEM), UNSW Australia Solar PV in ASEAN Challenges and Opportunities Peerapat Vithayasrichareon Centre for Energy and Environmental Markets (CEEM), UNSW Australia ESI Workshop on the value of PV in Singapore 18 February 2016

More information

Seminar on African Electrical Interconnection. Module 2- Market Analysis

Seminar on African Electrical Interconnection. Module 2- Market Analysis Seminar on African Electrical Interconnection Module 2- Market Analysis Module 2-2 Market Analysis Contents 1. Chapter I Economic Appraisal of the Interconnection Project: the Case of Pooling Generation

More information

Clean Development Mechanism CDM

Clean Development Mechanism CDM Workshop on Improving the Regional Distribution of CDM Projects in Asia and the Pacific 8-9 September 2010, ADB Headquarters, Manila, Philippines Clean Development Mechanism CDM Xeset 2 Hydropower Project

More information

ALTERNATIVES FOR POWER GENERATION IN THE GREATER MEKONG SUB-REGION

ALTERNATIVES FOR POWER GENERATION IN THE GREATER MEKONG SUB-REGION ALTERNATIVES FOR POWER GENERATION IN THE GREATER MEKONG SUB-REGION Volume 7: GMS Power Sector Vision Modelling Assumptions Summary Final 29 March 2016 Disclaimer This report has been prepared by Intelligent

More information

DEVELOPMENT OF ELECTRICITY GENERATION & TRANSMISSION PLAN (EGTP)

DEVELOPMENT OF ELECTRICITY GENERATION & TRANSMISSION PLAN (EGTP) PN CER2307 This is a proprietary document of the King Fahd University of Petroleum & Minerals, Research Institute. It is not to be disclosed or reproduced without prior written permission of the University.

More information

Programme of Activities (PoA) for Sustainable Renewable Energy Power Generation in Papua New Guinea (PNG) Journey So Far

Programme of Activities (PoA) for Sustainable Renewable Energy Power Generation in Papua New Guinea (PNG) Journey So Far Programme of Activities (PoA) for Sustainable Renewable Energy Power Generation in Papua New Guinea (PNG) Journey So Far Darshak Mehta Technical Support Facility Carbon Market Program Asian Development

More information

MODULE 3: Conservation and Demand Response Outlook. August 2016

MODULE 3: Conservation and Demand Response Outlook. August 2016 MODULE 3: Conservation and Demand Response Outlook August 2016 Summary In 2015, conservation is estimated to have contributed nearly 13 TWh of energy reductions Conservation savings come from energy efficiency

More information

CLEAN POWER ASIA on Policy and incentives to encourage renewable energy development in Cambodia

CLEAN POWER ASIA on Policy and incentives to encourage renewable energy development in Cambodia CLEAN POWER ASIA on Policy and incentives to encourage renewable energy development in Cambodia 29-30 April 2013 Bangkok, Thailand Prepared Mr. HANG Seiha Department of Energy Technique Ministry of Industry,

More information

Thailand Power Development Plan ( ) TANONGSAK WONGLA

Thailand Power Development Plan ( ) TANONGSAK WONGLA Thailand Power Development Plan (2010-2030) TANONGSAK WONGLA August 2013 GOV. POLICY Structure of Thailand Power Sector Regulators EGAT (44%) IPPs (38%) Imports (7%) SPPs (10%) VSPPs (

More information

NPCC 2016 Ontario Interim Review Of Resource Adequacy

NPCC 2016 Ontario Interim Review Of Resource Adequacy Approved by the RCC December 6, 2016 NPCC 2016 Ontario Interim Review Of Resource Adequacy FOR THE PERIOD FROM 2017 TO 2020 DECEMBER 2016 [Type here] This page intentionally left blank. ii Document Change

More information

CHAPTER THREE. Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve.

CHAPTER THREE. Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve. CHAPTER THREE Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve. Daily Load Curve Maximum Load (Peak Load) It represents

More information

Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic Blueprint Perspective

Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic Blueprint Perspective Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic Blueprint Perspective Akhomdeth Vongsay and Xayphone Bounsou Abstract Electric energy generation mostly from

More information

Report on development indicator evaluation in electricity sector in Lao PDR. (Program evaluation analysis)

Report on development indicator evaluation in electricity sector in Lao PDR. (Program evaluation analysis) Report on development indicator evaluation in electricity sector in Lao PDR (Program evaluation analysis) March 2013 Japan International Cooperation Agency Laos Office Abbreviations and Acronyms ADB ASEAN

More information

Addressing reliability requirements in the Flemington substation load area

Addressing reliability requirements in the Flemington substation load area Addressing reliability requirements in the Flemington substation load area Notice on screening for non-network options May 2018 Title of Contents DISCLAIMER... 1 1 INTRODUCTION... 2 2 FORECAST LOAD AND

More information

HOW GOVERNMENT AND PRIVATE SECTOR INTIATIVES HAVE SUPPORTED SUSTAINABLE ENERGY IN ZAMBIA

HOW GOVERNMENT AND PRIVATE SECTOR INTIATIVES HAVE SUPPORTED SUSTAINABLE ENERGY IN ZAMBIA HOW GOVERNMENT AND PRIVATE SECTOR INTIATIVES HAVE SUPPORTED SUSTAINABLE ENERGY IN ZAMBIA PRESENTED BY FRANCESCA ZYAMBO DIRECTOR PLANNING AND INFORMATION Ministry of Energy and W ater Development ZAMBIA

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (RRP VIE 46391) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems and Opportunities 1. The Ministry of

More information

Electrical Power Exchange in GMS and Its Influence on Power Systems in Vietnam and Thailand

Electrical Power Exchange in GMS and Its Influence on Power Systems in Vietnam and Thailand IEEE leset 2010 6-9 Dec 2010, Kandy, Sri Lanka Electrical Power Exchange in GMS and Its Influence on Power Systems in Vietnam and Thailand Tran Thi Dieu Linh Project Manager Department ABB Ltd, Nol A National

More information

RURAL ELECTRIFICATION WITH PV - MARKET POTENTIAL IN CAMBODIA

RURAL ELECTRIFICATION WITH PV - MARKET POTENTIAL IN CAMBODIA RURAL ELECTRIFICATION WITH PV - MARKET POTENTIAL IN CAMBODIA Paper for Renewable Energy Policy Dialogue and Working Visit 10-16 Jun 2012, Munich By Dr BUN NARITH; Deputy Director General Of Energy; Cambodian

More information

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005 2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability

More information

Future key factors of PV power generation to become a mainstream power source - Action plans of -

Future key factors of PV power generation to become a mainstream power source - Action plans of - Future key factors of PV power generation to become a mainstream power source - Action plans of PV150@2030 - New installation target of 150 GW by 2030 was proposed based on the forecast on

More information

An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004

An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004 Independent Electricity Market Operator : An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004 January 6, 2003 Public This page intentionally left blank. IMO_REP_0093v1.1

More information

Short-Term and Medium-Term Load Forecasting for Jordan's Power System

Short-Term and Medium-Term Load Forecasting for Jordan's Power System American Journal of Applied Sciences 5 (7): 763-768, 2008 ISSN 1546-9239 2008 Science Publications Short-Term and Medium-Term Load Forecasting for Jordan's Power System 1 I. Badran, 2 H. El-Zayyat and

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector Project ID Borrower Implementing Agency Report No. PID6033

More information

Tariffs January 1, 2017

Tariffs January 1, 2017 Tariffs January 1, 2017 Nova Scotia Power Inc. Tariffs & Regulations Approved by the Nova Scotia Utility and Review Board pursuant to The Public Utilities Act, R.S.N.S., 189,c.380 as amended Tariffs For

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.:45460 Project Name Rural Electrification and Transmission Interconnection Project (RETP) Region EAST ASIA AND PACIFIC Sector Energy Project ID

More information

Understanding Utility Revenue and Customer Tariffs Impact of DPV Deployment: Thailand Case Study

Understanding Utility Revenue and Customer Tariffs Impact of DPV Deployment: Thailand Case Study PHOTO CREDIT: ISTOCK.COM Understanding Utility Revenue and Customer Tariffs Impact of DPV Deployment: Thailand Case Study Alexandra Aznar, National Renewable Energy Laboratory Sopitsuda Tongsopit, USAID

More information

LOADS, CUSTOMERS AND REVENUE

LOADS, CUSTOMERS AND REVENUE Page of LOADS, CUSTOMERS AND REVENUE The purpose of this evidence is to present the Company s load, customer and distribution revenue forecast for the test years. The detailed test year forecasts are shown

More information

COMPONENT 1 ASIAN DEVELOPMENT BANK FINAL REPORT MODULE 1 UPDATE OF THE GMS REGIONAL MASTER PLAN EXECUTIVE SUMMARY RETA NO. 6440

COMPONENT 1 ASIAN DEVELOPMENT BANK FINAL REPORT MODULE 1 UPDATE OF THE GMS REGIONAL MASTER PLAN EXECUTIVE SUMMARY RETA NO. 6440 RTE International Tour Initiale 1, Terrasse Bellini TSA 41000 92929 La Défense CEDEX Tel: +33-1-41 45 66 88 Fax: +33-1-41 02 28 67 e-mail: michel.caubet@orange.fr http://www.rte-france.com in Association

More information

Projection of the Future Electricity Demands ( ) for Rajasthan, India and a Sustainable Development Energy Model for Developing States

Projection of the Future Electricity Demands ( ) for Rajasthan, India and a Sustainable Development Energy Model for Developing States Projection of the Future Electricity Demands (2021-2041) for Rajasthan, India and a Sustainable Development Energy Model for Developing States Namrata Sengar 1, Manpreet Kaur 2, Kanwardeep Singh 3 1 Department

More information

CHAPTER 6 - Load Forecast & Resource Plan

CHAPTER 6 - Load Forecast & Resource Plan CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching

More information

Is the "duck curve" eroding the value of energy efficiency?

Is the duck curve eroding the value of energy efficiency? Is the "duck curve" eroding the value of energy efficiency? Edward Burgess, Strategen Consulting Jeff Schlegel, Schlegel & Associates/Southwest Energy Efficiency Project (SWEEP) Ellen Zuckerman, Schlegel

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

Technical Series, Edition 8

Technical Series, Edition 8 Totally Integrated Power Technical Series, Edition 8 SIESTORAGE Energy Storage System a Technology for the Transformation of Energy System Answers for infrastructure and cities. Introduction: transformation

More information

QUÉBEC CONTROL AREA 2004 INTERIM REVIEW RESOURCE ADEQUACY

QUÉBEC CONTROL AREA 2004 INTERIM REVIEW RESOURCE ADEQUACY QUÉBEC CONTROL AREA 2004 INTERIM REVIEW OF RESOURCE ADEQUACY Prepared by Plan Pluriannuel Direction Planification et optimisation de la production Hydro-Québec Production December 2004-1 - Executive summary

More information

Reserve Capacity Mechanism - Availability Curve Definition

Reserve Capacity Mechanism - Availability Curve Definition Reserve Capacity Mechanism - Availability Curve Definition Presentation Market Advisory Committee 13 June 2012 By Brendan Clarke Issue Statement There is a lack of clarity in the formation of the Availability

More information

Funded by: European Union

Funded by: European Union 1 Enhancing Institutional Capacity for the Market Development of Decentralised Energy Systems in Thailand WADE DE Model Development for Thailand and Key Results Sridhar Samudrala Director ASIA World Alliance

More information

Appendix 4.4 Industrial Energy and Peak Demand Forecast

Appendix 4.4 Industrial Energy and Peak Demand Forecast Appendix 4.4 Industrial Energy and Peak Demand Forecast 2016-2035 14 November 2016 Contents 1.1 Introduction... 2 1.2 Background... 2 1.3 Source of Information... 2 1.4 Industrial Projects Requirements...

More information

National Energy Policy 1995

National Energy Policy 1995 National Energy Policy 1995 National Energy Policy I.I Background In recognition of the importance of energy in socio-economic development, the Government of Bangladesh has given continuing attention to

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Interim Country Partnership Strategy: Myanmar, 2012 2014 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 A. Sector Performance, Problems, and Opportunities 1. Overview. Myanmar has abundant energy resources, particularly

More information

Ministry of Industry and Trade General Directorate of Energy. Viet Nam s Power Development Plan

Ministry of Industry and Trade General Directorate of Energy. Viet Nam s Power Development Plan Ministry of Industry and Trade General Directorate of Energy Viet Nam s Power Development Plan Ha Noi, April 2017 Structure 1. Power Development Plan 2. Renewable Development 1. Power Development Plan

More information

Study on the value of flexibility in the management and design basis of distribution networks in France

Study on the value of flexibility in the management and design basis of distribution networks in France Study on the value of flexibility in the management and design basis of distribution networks in France Summary - Version dated 7 December 2015 This document is a translation of E-CUBE Strategy Consultants

More information

SECTOR ASSESSMENT (SUMMARY): POWER Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): POWER Sector Performance, Problems, and Opportunities Country Partnership Strategy: Papua New Guinea, 2011 2015 SECTOR ASSESSMENT (SUMMARY): POWER 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. In Papua New Guinea (PNG), less than

More information

Terms of Reference. Review and provide recommendations on how to improve STEG s current methodology for forecasting electricity demand

Terms of Reference. Review and provide recommendations on how to improve STEG s current methodology for forecasting electricity demand Terms of Reference Review and provide recommendations on how to improve STEG s current methodology for forecasting electricity demand 1. Background The European Bank for Reconstruction and Development

More information

Ramachandran Kannan and Hal Turton Energy Economics Group, Laboratory for Energy Systems Analysis

Ramachandran Kannan and Hal Turton Energy Economics Group, Laboratory for Energy Systems Analysis Wir schaffen Wissen heute für morgen Cost of ad-hoc nuclear policy uncertainties in the evolution of the Swiss electricity system Ramachandran Kannan and Hal Turton Energy Economics Group, Laboratory for

More information

Figure Gross Domestic Product Growth of Viet Nam,

Figure Gross Domestic Product Growth of Viet Nam, 1.4 Viet Nam Viet Nam is a country with a population of 92.7 million (2016). The United Nations (UN) estimates that by July 2018 the country s population will be 96.49 million (World Population Review,

More information

Portland General Electric Company Eleventh Revision of Sheet No. 76R-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No.

Portland General Electric Company Eleventh Revision of Sheet No. 76R-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No. Portland General Electric Company Eleventh Revision of Sheet No. 76R-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No. 76R-1 PURPOSE SCHEDULE 76R PARTIAL REQUIREMENTS ECONOMIC REPLACEMENT

More information

Cambodia Power Sector

Cambodia Power Sector Cambodia Power Sector Cambodia Power Sector 31 August 2015, Phnom Penh, Cambodia 1 Content 1. Structure of Electricity Organization 2. Energy Policy 3. Cambodia Power Strategy 4. Overviews of Power Sector

More information

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES Evangelos Dialynas Professor in the National Technical University of Athens Greece dialynas@power.ece.ntua.gr

More information

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201 TARIFF FOR WHOLESALE TRANSMISSION SERVICE 1900 North Akard Dallas, Texas 75201 Applicability: Entire System Sheet No. 1 Effective Date: May 25, 2018 Revision: 17 Availability Wholesale Transmission Service

More information

Understanding Electrical Load the Load Duration Curve

Understanding Electrical Load the Load Duration Curve Understanding Electrical Load the Load Duration Curve Smith College, EGR 325 February 27, 2018 1 Class Objectives Start today... Hmm, how do people use electricity? The purpose of an electric power system

More information