Actions taken in WANO-Moscow Centre to incorporate lessons learned from Fukushima Accident

Size: px
Start display at page:

Download "Actions taken in WANO-Moscow Centre to incorporate lessons learned from Fukushima Accident"

Transcription

1 Actions taken in WANO-Moscow Centre to incorporate lessons learned from Fukushima Accident Sergey Vybornov Adviser, peer review programme World Association of Nuclear Operators Moscow Centre Technical Meeting on Novel Design and Safety Principles of Nuclear Power Plants IAEA Headquarters, Vienna, Austria 3 6 October 2016

2 Contents Actions taken among WANO members to prevent severe accidents and mitigate their consequences Changes in WANO peer reviews with focus on design vulnerabilities of existing plants 2

3 What is WANO Mission of the World Association of Nuclear Operators is to maximise the safety and reliability of nuclear power plants worldwide by working together to assess, benchmark and improve performance through mutual support, exchange of information, and emulation of best practices. Four main programmes: Operating experience exchange Technical and professional development Technical support and exchange of technical information Peer reviews 3

4 Lessons learned from Fukushima 4

5 SEVERE ACCIDENT MANAGEMENT PROJECT 5

6 WANO SAM Project: Background WANO Post-Fukushima Commission: The full focus of WANO since its formation has been accident prevention, and no procedures were in place to address nuclear response or mitigation. We have to shift from a focus on accident prevention to a focus on both prevention and mitigation. Recommendation No.1 resulted in the launching of the SAM Project. Overall responsibility for the SAM Project was delegated to the WANO Moscow Centre. 6

7 SAM project The purpose of the SAM Project was to: expand the scope of WANO programmes to include severe accident management establish a worldwide standard for performing station and corporate assessments in the area of severe accident management 7

8 SAM project As a result SAM Performance Objectives and Criteria (SAM PO&Cs) were developed and were supposed to be used during station peer reviews to review readiness of nuclear plants to manage beyond-design-basis and severe accidents. The SAM PO&Cs are a set of the following three performance objectives, with corresponding criteria: SAM.1: SAM MANAGEMENT AND LEADERSHIP SAM.2: SEVERE ACCIDENT MANAGEMENT PROGRAMME SAM.3: SEVERE ACCIDENT RESPONSE 8

9 SAM project Decision was made that all WANO member utilities/stations should carry out self-assessments. Self-assessments have been conducted for WANO member stations worldwide (Final report issued on 30 August 2015 ). Question: Are Severe Accident Management programs adequate: to provide effective direction and coordination of mitigation strategies to prevent the escalation of a beyond-design-basis event into a severe accident, to mitigate the consequences of a severe accident and achieve a long-term safe stable state if a severe accident has occurred. 9

10 Results of self-assessment Overall results: members meet most standards and are prepared to manage severe accidents effectively. However: Some not adequately provided with equipment and facilities (mobile emergency equipment to ensure long-term heat removal from the core and from spent fuel, equipment for in-containment hydrogen suppression, alternative paths for water supply, seismic protection of systems, structures and components, etc. Development of SAMGs and other documentation for severe accident response has not been completed. Sufficient capability is not ensured to manage severe accidents, including multi-unit events, from protected emergency control centres both during the design-basis phases and during prolonged events. Weaknesses in SAM training (simulator training, drills for SAM, handover of command and control during prolonged events, relief/rotation, communication, multiple-unit drills. 10

11 SAM self-assessment SAM Performance Objectives Implementation, WANO MC Performanc e Objective Category Number of Stations SAT AI UNSAT SAM.1 SAM.2 SAM MANAGEMENT AND LEADERSHIP SEVERE ACCIDENT MANAGEMENT PROGRAM Source: WANO-MC Director presentation WANO Post-Fukushima Severe Accident Management Project SAM.3 SEVERE ACCIDENT RESPONSE

12 Further steps revise the SAM PO&Cs based on the self-assessment results and comments from the members incorporate the revised SAM PO&Cs in the WANO PO&Cs make arrangements to review SAM on peer reviews proceed with adding SAM to the scope of WANO programmes and activities. 12

13 DESIGN INFORMED PEER REVIEWS 13

14 Design informed peer reviews WANO s mission is to maximise the safety and reliability of nuclear power plants ; for achieving this mission, it is very important to have in mind that nuclear safety of a plant strongly depends on two fundamentals: the design phase which results in the definition of the Design Basis and Beyond Design basis considerations of the plant, the operation phase which corresponds to the day-by-day life of the plant. The Design Project has been established by the 2011 with the mandate to provide recommendations to extend the scope of WANO activities to include some aspects of Design. The Design Project Design-Informed Peer Reviews = More global appreciation of the nuclear safety of a plant 14

15 Objectives of the Design Informed Peer Reviews To appreciate the nuclear safety performance of the plant taking into account the main characteristics of the design, To ensure potential design vulnerabilities are known and managed by the plant, To evaluate whether the Fundamental Safety Functions (control of reactivity, removal of heat from the reactor core and from the spent fuel, confinement of radioactive material), are challenged or not by the plant operation performance. As a result: More focused peer review teams An analysis of the available data in terms of safety function performance 15

16 Extreme Meteorological / Hydrological Conditions Seismic Design Information Survey (DIS) P1 Generic questions P2 External Events P3 Control of reactivity P4 Confinement P5 Heat Removal P6 Emergency Power supply P7 Monitoring of plant parameters Unit: X External Events Station name Is this event considered as Design Basis, Design If the event is not taken into Extension Condition, account for your station, Beyond Design Basis or explain why. not relevant for the station? Specify the Design Basis limit values and the duration for the specific event where appropriate and give a reference (e.g. maximum water (wave) height / temperature; frequency and acceleration; liquid equivalent, etc.). Provide the maximum values for which it is proven that the plant is protected against, if different from previous question (e.g. maximum water (wave) height / temperature; duration; frequency and acceleration; liquid equivalent, etc.) Has such an event occurred which challenged safety functions at your station since erection? If yes, provide the event code and characteristic value (e.g. Max. water height / temperature; duration; frequency and acceleration; liquid equivalent; etc. Did the Design Basis Limit values change since the plant was built? (Was the event originally foreseen for the station?) Earthquake Extreme air temperature (high and low) Extreme humidity / Drought Lightning Heavy Rain 16 WANOPC TG - 16 Dr. Mori

17 Probabilistic Safety Assessment Survey (PSAS) Initiating events and operational modes. Identifies the systems and components of higher importance 17 WANOPC TG - 17 Dr. Mori

18 Safety Function Examination (SaFE) A-B-C-X - Excel spreadsheets: facts and conclusions grouped for Safety functions 18

19 Results for the peer review team This information is then used in order to: Determine areas that might warrant particular focus of the peer review team, Highlight some priorities for the on-site Peer Review, Evaluate the potential cumulating challenge to Fundamental Safety Functions. DiPR were conducted for several technologies: BWR (different types), PWR (different types), PHWR, AGR, VVER Target: in 2019 all 100% member stations will host design informed peer reviews 19

20 Feedback from the customers Station A: Valuable feedback. The DiPR has identified aspects that need to be reconsidered before [ ] implementing any modifications, not necessarily design modification. Station B: The analysis shows that the DiPR analysis added value to the existing process by identifying gaps in safety function performance that were not otherwise identified by the peer review. Station C: Station has not got inputs and additional questions on design resulted from the peer review. Vienna, Austria October WANOPC

21 Conclusions The methodology has proved to be robust and valuable: New approach provides new insights e.g. aggregation of small gaps that can result in a cumulative challenge. Independent review provides a new perspective e.g. margin assessments for unexpected conditions. Results can be used to inform or validate decision making on e.g. capital projects, modifications, safety reviews 21

22 QUESTIONS??? WANO Moscow Centre Tel: Fax: Web: Sergey Vybornov Tel: Vienna, Austria. 3 6 October 22

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK Impact of Extreme Events on Nuclear Facilities following Fukushima by Dr C H Shepherd Nuclear Safety Consultant, UK CRA PSA/HFA Forum 8-9 September 2011, Warrington Contents of the Presentation IAEA views

More information

Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited

Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited cmbhatia@npcil.co.in Presentation Contents Indian nuclear power

More information

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS Todd Brumfield World Association of Nuclear Operators (WANO) Atlanta, Georgia, USA ABSTRACT: The requirements for performance of pre-startup reviews

More information

Evaluation of Nuclear Safety Culture During the Pre-Operational Phase

Evaluation of Nuclear Safety Culture During the Pre-Operational Phase Evaluation of Nuclear Safety Culture During the Pre-Operational Phase Todd Brumfield WANO-World Association of Nuclear Operators Formed in 1989 following accident at Chernobyl Has members in more than

More information

CNSC Evaluation of Plant-Specific SAMG

CNSC Evaluation of Plant-Specific SAMG CNSC Evaluation of Plant-Specific SAMG Quanmin Lei IAEA Technical Meeting on Verification and Validation of SAMG Vienna, Austria December 12-14, 2016 e-docs # 5104918 nuclearsafety.gc.ca Outline Summarize

More information

STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT

STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT Frank Nuzzo IAEA Nuclear Power Engineering f.nuzzo@iaea.org ENSREG High Level Requirements Following the extreme events

More information

India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited

India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited 13 th Meeting of the Technical Working Group on Advanced Technologies for HWRs

More information

CNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria

CNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria CNSC Fukushima Task Force E-doc 3743877 July 2011 Executive Summary In response to the March 11, 2011 accident at the Fukushima Daiichi Nuclear Power Plant (NPP), the CNSC convened a Task Force to evaluate

More information

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the Council of the European Union declared

More information

WANO peer review program

WANO peer review program WANO peer review program Yuriy Schhelik, Adviser to WANO Moscow Centre May, 2018 Table of Contents Introduction Purposes of peer reviews Peer review process Design-informed peer reviews Pre-startup peer

More information

Assessing and Managing Severe Accidents in Nuclear Power Plant

Assessing and Managing Severe Accidents in Nuclear Power Plant Assessing and Managing Severe Accidents in Nuclear Power Plant Harri Tuomisto Fortum, Finland IAEA Technical Meeting on Managing the Unexpected - From the Perspective of the Interaction between Individuals,

More information

ONE YEAR AFTER FUKUSHIMA: LESSONS FOR A SAFER NUCLEAR ENERGY. Denis Flory. Deputy Director General of the IAEA

ONE YEAR AFTER FUKUSHIMA: LESSONS FOR A SAFER NUCLEAR ENERGY. Denis Flory. Deputy Director General of the IAEA ONE YEAR AFTER FUKUSHIMA: LESSONS FOR A SAFER NUCLEAR ENERGY Denis Flory Deputy Director General of the IAEA Head of the Department of Nuclear Safety and Security Introduction The accident at Fukushima

More information

China s HWR activities and technology development

China s HWR activities and technology development 13th Meeting of the Technical Working Group on Advanced Technologies for HWRs (TWG-HWR) China s HWR activities and technology development CNNC Nuclear Operation Management Co. Ltd. (CNNO) Chen Mingjun

More information

PERFORMANCE INDICATORS

PERFORMANCE INDICATORS PERFORMANCE INDICATORS ENABLE COMPARISON The WANO Performance Indicator Programme Grid-Related Loss Factor (GRLF) supports the exchange of operating experience information by collecting, trending and disseminating

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

European Nuclear Stress Test

European Nuclear Stress Test European Nuclear Stress Test - Peer Review Process and Results - 9. St. Galler Energietagung Oskar Grözinger Symposium : The Fukushima accident and the future of nuclear energy in Europe Den Haag, 23.11.2012

More information

Ibero-American Forum of Radiological and Nuclear Regulators, FORO. Complementary Safety Assessments of the Iberoamerican FORO Countries

Ibero-American Forum of Radiological and Nuclear Regulators, FORO. Complementary Safety Assessments of the Iberoamerican FORO Countries Ibero-American Forum of Radiological and Nuclear Regulators, FORO IAEA Technical Meeting on EVALUATION OF NUCLEAR POWER PLANT DESIGN SAFETY IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT 26 29 August

More information

Performance Indicators 2016

Performance Indicators 2016 Performance Indicators Enable Comparison The WANO Performance Indicator Programme supports the exchange of operating experience information by collecting, trending and disseminating nuclear plant performance

More information

ASSESSMENTS OF SWEDISH NUCLEAR POWER PLANT IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT

ASSESSMENTS OF SWEDISH NUCLEAR POWER PLANT IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT ASSESSMENTS OF SWEDISH NUCLEAR POWER PLANT IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT Lovisa Wallin-Caldwell Outline Introduction Swedish nuclear power plants Swedish nuclear power regulation Back-fitting

More information

Attachment VIII-1. July 21, 2011 Nuclear and Industrial Safety Agency

Attachment VIII-1. July 21, 2011 Nuclear and Industrial Safety Agency Assessment Procedures and Implementation Plan Regarding the Comprehensive Assessments for the Safety of Existing Power Reactor Facilities Taking into Account the Accident at Fukushima Dai-ichi Nuclear

More information

in China Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August , Vienna

in China Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August , Vienna Post-Fukushima Safety Improvement Measures for NPPs in China ZHENG Lixin Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August 26-2929 2013, Vienna 1 Background

More information

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety

More information

Preparation of NPP Dukovany Periodic Safety Review

Preparation of NPP Dukovany Periodic Safety Review Preparation of NPP Dukovany Periodic Safety Review Dubský Ladislav Petr Vymazal Nuclear Research Institute Řež plc., Czech Republic ČEZ, a.s., Nuclear Division, Dukovany NPP, Czech Republic 1. ABSTRACT

More information

TS1-5: Revision of NS-G-2.15 and Its Implementation for Verification and Validation of Severe Accident Management Guidelines

TS1-5: Revision of NS-G-2.15 and Its Implementation for Verification and Validation of Severe Accident Management Guidelines Technical Meeting on Verification and Validation of Severe Accident Management Guidelines for Nuclear Power Plants 12-14 December 2016, Vienna, Austria TS1-5: Revision of NS-G-2.15 and Its Implementation

More information

MEETING THE OBJECTIVES OF THE VIENNA DECLARATION ON NUCLEAR SAFETY: LICENSING OF NEW NUCLEAR POWER PLANTS IN PAKISTAN

MEETING THE OBJECTIVES OF THE VIENNA DECLARATION ON NUCLEAR SAFETY: LICENSING OF NEW NUCLEAR POWER PLANTS IN PAKISTAN MEETING THE OBJECTIVES OF THE VIENNA DECLARATION ON NUCLEAR SAFETY: LICENSING OF NEW NUCLEAR POWER PLANTS IN PAKISTAN N.MUGHAL Email: nasir.mughal@pnra.org F.MANSOOR J.AKHTAR Abstract In the aftermath

More information

Compilation of recommendations and suggestions

Compilation of recommendations and suggestions Post- Fukushima accident Compilation of recommendations and suggestions Peer review of stress tests performed on European nuclear power plants 26/07/2012 Compilation of Recommendations and Suggestions

More information

Arab Journal of Nuclear Science and Applications, 48(3), ( ) 2015

Arab Journal of Nuclear Science and Applications, 48(3), ( ) 2015 Specific Considerations in the Safety Assessment of Predisposal Radioactive Waste Management Facilities in Light of the Lessons Learned from the Accident at the Fukushima-Daiichi Nuclear Power Plant A.

More information

Nuclear Safety Enhancement in China after Fukushima Event. July 11, 2013

Nuclear Safety Enhancement in China after Fukushima Event. July 11, 2013 Nuclear Safety Enhancement in China after Fukushima Event July 11, 2013 1. Introduction 2. State Policy 3. Regulatory Requirement 4. Margin Improvement 5. Summary 1. Introduction In 1991, Qinshan unit

More information

WENRA views on Defence-in-Depth for new reactors

WENRA views on Defence-in-Depth for new reactors WENRA views on Defence-in-Depth for new reactors International Conference on Topical Issues in Nuclear Installation Safety: Defence in Depth Advances and Challenges for Nuclear Installation Safety 21 24

More information

Document Preparation Profile (DPP) [Final] Version 5 dated 16 November, 2015

Document Preparation Profile (DPP) [Final] Version 5 dated 16 November, 2015 Document Preparation Profile (DPP) [Final] Version 5 dated 16 November, 2015 1. IDENTIFICATION Document Category: Specific Safety Guide Working ID: Proposed Title: Proposed Action: DS449 Format and Content

More information

Protection of Nuclear Installations Against External Hazards

Protection of Nuclear Installations Against External Hazards TM on Evaluation of Nuclear Power Plant design safety in the Aftermath of the Fukushima Daiichi Accident Vienna, 26-29 August 2013 Protection of Nuclear Installations Against External Hazards Ovidiu Coman

More information

POST-FUKUSHIMA STRESS TESTS OF EUROPEAN NUCLEAR POWER PLANTS CONTENTS AND FORMAT OF NATIONAL REPORTS

POST-FUKUSHIMA STRESS TESTS OF EUROPEAN NUCLEAR POWER PLANTS CONTENTS AND FORMAT OF NATIONAL REPORTS HLG_p(2011-16)_85 POST-FUKUSHIMA STRESS TESTS OF EUROPEAN NUCLEAR POWER PLANTS CONTENTS AND FORMAT OF NATIONAL REPORTS This document is intended to provide guidance for the European Nuclear Regulators

More information

From the Accident at the Fukushima Daiichi NPS: Efforts to Improve Safety

From the Accident at the Fukushima Daiichi NPS: Efforts to Improve Safety From the Accident at the Fukushima Daiichi NPS: Efforts to Improve Safety Luc OURSEL President and CEO, AREVA Tokyo, April 19, 2012 Agenda Safety assessments in the EU and in France AREVA Safety of our

More information

TERM TASK FORCE. Presented to: Waste Management Symposia By: Dr. Charles L. Miller. Phoenix, AZ. Fukushima Daiichi NRC Near Term Task Force 1

TERM TASK FORCE. Presented to: Waste Management Symposia By: Dr. Charles L. Miller. Phoenix, AZ. Fukushima Daiichi NRC Near Term Task Force 1 FUKUSHIMA DAIICHI NRC NEAR TERM TASK FORCE Presented to: Waste Management Symposia By: Dr. Charles L. Miller Phoenix, AZ 1 NRC RESPONSE Monitoring Mode Japan site team Information gathering Near Term Task

More information

Enhancing Nuclear Regulation in the Post-Fukushima World

Enhancing Nuclear Regulation in the Post-Fukushima World Enhancing Nuclear Regulation in the Post-Fukushima World Robert Lojk Regulatory Program Director Directorate of Power Reactor Regulation Canadian Nuclear Safety Commission Presentation to the 2012 INPRO

More information

A new environment for nuclear safety: Main challenges for the OECD/NEA

A new environment for nuclear safety: Main challenges for the OECD/NEA A new environment for nuclear safety: Main challenges for the OECD/NEA Javier Reig Director Nuclear Safety OECD Nuclear Energy Agency TSO Conference, Beijing, October 2014 2014 Organisation for Economic

More information

Mr. Director General,

Mr. Director General, Statement of the Head of the Delegation of the Republic of Armenia, Minister of Energy Infrastructures and Natural Resources Mr. Ashot Manukyan at the 61st Annual Regular Session of the IAEA General Conference

More information

Development and use of SAMGs in the Krško NPP

Development and use of SAMGs in the Krško NPP REPUBLIC OF SLOVENIA Development and use of SAMGs in the Krško NPP Tomaž Nemec Slovenian Nuclear Safety Administration tomaz.nemec@gov.si IAEA TM on the Verification and Validation of SAMGs, Vienna, 12

More information

Highlights From the Work of the NEA on Impacts of the Fukushima Accident. Javier Reig Head, Nuclear Safety Division

Highlights From the Work of the NEA on Impacts of the Fukushima Accident. Javier Reig Head, Nuclear Safety Division Highlights From the Work of the NEA on Impacts of the Fukushima Accident Javier Reig Head, Nuclear Safety Division 1 Areas for NEA Post- Accident Activities 1 Accident Management and Progression a. TRANSITION:

More information

Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents

Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents Jean BARBAUD IAEA, August 2013 1 1 Context - Timeline 6 fields assessed : Earthquake Flooding Loss of heat sink LHS

More information

IAEA-J4-TM TM for Evaluation of Design Safety

IAEA-J4-TM TM for Evaluation of Design Safety Canadian Nuclear Utility Principles for Beyond Design Basis Accidents IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects Ontario Power Generation Overview

More information

STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA MARCH 27-29, 2017 1 ANPP * The ANPP is located in the western part of Ararat valley, 30 km west of Yerevan, close

More information

Post Fukushima Safety Margins

Post Fukushima Safety Margins Post Fukushima Safety Margins Nuclear Codes and Standards Workshop Prague, Czech Republic July 7, 2014 Bryan Erler P.E. Chair Task Group on Design Basis and Response to Severe Accident and Vice President,

More information

Development of SAMG and its implementation in China

Development of SAMG and its implementation in China Development of SAMG and its implementation in China Yang Zhiyi 1, Zhang Lin 2, etc. 1. Nuclear and Radiation Safety Center, China 2. National Nuclear Safety Administration, China Vienna Austria, 2014/3/20

More information

SUMMARY OF SE NNEGC ENERGOATOM PERFORMANCE IN POST-FUKUSHIMA PERIOD

SUMMARY OF SE NNEGC ENERGOATOM PERFORMANCE IN POST-FUKUSHIMA PERIOD МИНИСТЕРСТВО ЭНЕРГЕТИКИ И УГОЛЬНОЙ ПРОМЫШЛЕННОСТИ УКРАИНЫ НАЦИОНАЛЬНАЯ АТОМНАЯ ЭНЕРГОГЕНЕРИРУЮЩАЯ КОМПАНИЯ SUMMARY OF SE NNEGC ENERGOATOM PERFORMANCE IN POST-FUKUSHIMA PERIOD D.V. Biley Inspector General

More information

Safety enhancement of NPPs in China after Fukushima Accident

Safety enhancement of NPPs in China after Fukushima Accident Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

Final 14 TH September Stress test peer review Follow-up fact finding site visit. Germany

Final 14 TH September Stress test peer review Follow-up fact finding site visit. Germany Final 14 TH September 11.30 Stress test peer review Follow-up fact finding site visit Germany 1. BACKGROUND/INTRODUCTION In the context of the ENSREG action plan to follow-up the implementation of safety

More information

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident Nuclear Energy Safety Symposium Academy of Science of South Africa October 13, 2011 Hideki Nariai Professor Emeritus of the University

More information

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA

More information

New Safety Requirements Addressing Feedback From the Fukushima Daiichi Accident

New Safety Requirements Addressing Feedback From the Fukushima Daiichi Accident New Safety Requirements Addressing Feedback From the Fukushima Daiichi Accident Alexander Sapozhnikov Federal Environmental, Industrial and Nuclear Supervision Service of Russia, 109147 Moscow, Taganskaya,

More information

Implementing the Treaty on the Non-Proliferation of Nuclear Weapons: peaceful uses of nuclear energy

Implementing the Treaty on the Non-Proliferation of Nuclear Weapons: peaceful uses of nuclear energy 2015 Review Conference of the Parties to the Treaty on the Non-Proliferation of Nuclear Weapons 29 April 2015 NPT/CONF.2015/WP.46 Original: English New York, 27 April-22 May 2015 Implementing the Treaty

More information

OPG s Response to Fukushima Event- Update

OPG s Response to Fukushima Event- Update OPG s Response to Fukushima Event- Update Darlington and Pickering Joint Community Advisory Committee Meeting- January 21, 2014 Mark Knutson- Director- Fukushima Support Tho-Dien Le- Projects Design Manager-

More information

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Jiří Duspiva ÚJV Řež, a. s. Division of Nuclear Safety and Reliability Dept. of Severe Accidents and Thermomechanics

More information

Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs

Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs RAHUL PORWAL Atomic Energy Regulatory Board Mumbai, INDIA Outline Introduction AERB Safety Review Methodology Safety Observations

More information

EPRI Utility Requirement Document

EPRI Utility Requirement Document EPRI Utility Requirement Document 11 February 2015 Sang-Baik KIM Analyst, NEA NDD Overview of URD Background and Objectives - Purpose of the URD is to present a clear, comprehensive set of design requirements

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

Post-Fukushima WANO: The Safety Culture Challenge

Post-Fukushima WANO: The Safety Culture Challenge Post-Fukushima WANO: The Safety Culture Challenge World Nuclear University Summer Institute Oxford George Felgate WANO Managing Director August 1, 2012 WANO Overview In 1986, the accident at Chernobyl

More information

IAEA-TECDOC Probabilistic safety assessments of nuclear power plants for low power and shutdown modes

IAEA-TECDOC Probabilistic safety assessments of nuclear power plants for low power and shutdown modes IAEA-TECDOC-1144 Probabilistic safety assessments of nuclear power plants for low power and shutdown modes March 2000 The originating Section of this publication in the IAEA was: Safety Assessment Section

More information

INPRO Criterion Robustness of Design Position of the EPR TM reactor Part 3. Franck Lignini Reactor & Services / Safety & Licensing

INPRO Criterion Robustness of Design Position of the EPR TM reactor Part 3. Franck Lignini Reactor & Services / Safety & Licensing INPRO Criterion 1.1.1 Robustness of Design Position of the EPR TM reactor Part 3 Franck Lignini Reactor & Services / Safety & Licensing 0 E.P?.?.?.? Robustness against External Hazards 1 External Hazards

More information

IAEA International Conference on Topical Issues in Nuclear Installation Safety

IAEA International Conference on Topical Issues in Nuclear Installation Safety IAEA International Conference on Topical Issues in Nuclear Installation Safety Guidance on the Implementation of Modifications to Mitigate Beyond Design Basis Accidents Fred Dermarkar Vice President Engineering

More information

An overview of what happened at Fukushima NPPs

An overview of what happened at Fukushima NPPs An overview of what happened at Fukushima NPPs Per F. Peterson Professor and Chair Department of Nuclear Engineering University of California, Berkeley 2011 PEER Annual Meeting Hotel Shattuck Berkeley

More information

M ertinssafety. The new German Safety Criteria for Nuclear Power Plants in the view of international standards. Prof. Dr. M.

M ertinssafety. The new German Safety Criteria for Nuclear Power Plants in the view of international standards. Prof. Dr. M. The new German Safety Criteria for Nuclear Power Plants in the view of international standards Prof. Dr. M. Mertins 1 Content Introductory remarks Major Information Sources for elaboration of the new Safety

More information

Strategic Vision and Implementation of Human and Organizational Factors in the Nuclear Industry. Kerstin Dahlgren Persson CNSO, Vattenfall, Sweden

Strategic Vision and Implementation of Human and Organizational Factors in the Nuclear Industry. Kerstin Dahlgren Persson CNSO, Vattenfall, Sweden Strategic Vision and Implementation of Human and Organizational Factors in the Nuclear Industry Kerstin Dahlgren Persson CNSO, Vattenfall, Sweden Content Fukushima and Systemic Failures Integrated approach

More information

Fukushima Daiichi NPP Accident, Japan. Brief of AMEC Capabilities to Support Regulators Plant Operators and Licensees (29 March 2011)

Fukushima Daiichi NPP Accident, Japan. Brief of AMEC Capabilities to Support Regulators Plant Operators and Licensees (29 March 2011) Fukushima Daiichi NPP Accident, Japan Brief of AMEC Capabilities to Support Regulators Plant Operators and Licensees (29 March 2011) Following a major earthquake, a tsunami disabled the power supply of

More information

DIRECTIONS FOR NUCLEAR SAFETY COOPERATION IN THE ASIA/PACIFIC REGION

DIRECTIONS FOR NUCLEAR SAFETY COOPERATION IN THE ASIA/PACIFIC REGION DIRECTIONS FOR NUCLEAR SAFETY COOPERATION IN THE ASIA/PACIFIC REGION Soon Heung Chang Department of Nuclear Engineering Korea Advanced Institute of Science and Technology Republic of Korea shchang@sorak.kaist.ac.kr

More information

EU STRESS TESTS: SPANISH RESULTS ON SEISMIC EVENTS IAEA, International Experts Meeting on External Events

EU STRESS TESTS: SPANISH RESULTS ON SEISMIC EVENTS IAEA, International Experts Meeting on External Events IAEA (Vienna) 4-7 September, 2012 EU STRESS TESTS: IAEA, International Experts Meeting on External Events INDEX 1. NUCLEAR FLEET IN SPAIN UNDER STRESS TESTS 2. PURPOSE AND SCOPE OF EU STRESS TESTS 3. SPECIFIC

More information

New Safety Requirements Addressing Feedback From the Fukushima Daiichi Accident

New Safety Requirements Addressing Feedback From the Fukushima Daiichi Accident FEDERAL ENVIRONMENTAL, INDUSTRIAL AND NUCLEAR SUPERVISION SERVICE (ROSTECHNADZOR) New Safety Requirements Addressing Feedback From the Fukushima Daiichi Accident Alexander Sapozhnikov Department for Safety

More information

Safety Provisions for the KLT-40S Reactor Plant

Safety Provisions for the KLT-40S Reactor Plant 6th INPRO Dialogue Forum on Global Nuclear Energy Sustainability: Licensing and Safety Issues for Small and Medium-sized Nuclear Power Reactors (SMRs) 29 July - 2 August 2013 IAEA Headquarters, Vienna,

More information

Overview of Regulations and Guides in Japan

Overview of Regulations and Guides in Japan Technical Meeting on Novel Design and Safety Principles of NPPs Overview of Regulations and Guides in Japan IAEA, Vienna, Austria 3-6 October 2016 Tsuyoshi Nakajima Regulatory Standards and Research Division

More information

ACTIONS TO PROTECT NPPS AGAINST EXTERNAL AND INTERNAL EVENTS AND R&D ACTIVITIES IN FINLAND

ACTIONS TO PROTECT NPPS AGAINST EXTERNAL AND INTERNAL EVENTS AND R&D ACTIVITIES IN FINLAND ACTIONS TO PROTECT NPPS AGAINST EXTERNAL AND INTERNAL EVENTS AND R&D ACTIVITIES IN FINLAND International Experts Meeting on Strengthening Research and Development Effectiveness in the Light of the Accident

More information

Managing the Unexpected

Managing the Unexpected ROSATOM STATE ATOMIC ENERGY CORPORATION ROSATOM Managing the Unexpected IAEA International Experts Meeting on Human and Organizational Factors in Nuclear Safety in the Light of the Accident at the Fukushima

More information

Improvements in defense in depth on French NPPs following Fukushima Accidents

Improvements in defense in depth on French NPPs following Fukushima Accidents Improvements in defense in depth on French NPPs following Fukushima Accidents Xavier Pouget-Abadie Jean BARBAUD IAEA, October 2013 1 Copyright EDF 2013 1 Context -Timeline 6 fields assessed : Earthquake

More information

Strengthening safety by learning lessons from the accident at TEPCO s Fukushima Daiichi NPP. Akira OMOTO, Atomic Energy Commission

Strengthening safety by learning lessons from the accident at TEPCO s Fukushima Daiichi NPP. Akira OMOTO, Atomic Energy Commission Strengthening safety by learning lessons from the accident at TEPCO s Fukushima Daiichi NPP Akira OMOTO, Atomic Energy Commission 1 Part I Medium and Long term onsite and offsite activities Part II Key

More information

Approach to Practical Elimination in Finland

Approach to Practical Elimination in Finland Approach to Practical Elimination in Finland M-L. Järvinen, N. Lahtinen and T. Routamo International Conference on Topical Issues in Nuclear Installation Safety: Safety Demonstration of Advanced Water

More information

Wolsong-1 Stress Test

Wolsong-1 Stress Test PHWR Safety 2014/CANSAS-2014 Wolsong-1 Stress Test June 23, 2014 Geun-Sun Auh Korea Institute of Nuclear Safety Table of Contents 1. Stress Test Definition 2. EU Stress Test 3. Stress Test of Korea 4.

More information

Establishing the Independent, Effective Regulatory Authority in the United Arab Emirates

Establishing the Independent, Effective Regulatory Authority in the United Arab Emirates Establishing the Independent, Effective Regulatory Authority in the United Arab Emirates Ian Grant Director of Nuclear Safety Federal Authority for Nuclear Regulation Presentation Outline The Nuclear Energy

More information

REGULATORS FORUM PILOT PROJECT REPORT

REGULATORS FORUM PILOT PROJECT REPORT SMR REGULATORS FORUM PILOT PROJECT REPORT Considering the application of a graded approach, defence-in-depth and emergency planning zone size for Small Modular Reactors S. MAGRUDER International Atomic

More information

Report of the G7 Nuclear Safety and Security Group (NSSG) during the German Presidency in 2014/2015

Report of the G7 Nuclear Safety and Security Group (NSSG) during the German Presidency in 2014/2015 Report of the G7 Nuclear Safety and Security Group (NSSG) during the German Presidency in 2014/2015 Introduction 1. The Nuclear Safety and Security Group (NSSG), established at the Kananaskis Summit and

More information

Swedish action plan. for nuclear power plants

Swedish action plan. for nuclear power plants Swedish action plan for nuclear power plants Response to ENSREG s request December 2012 Page 2 (48) Abstract Following the severe accidents which started in the Fukushima Dai-ichi nuclear power plant,

More information

Introduction of Nation-wide Inspection and Reassessment to Chinese Research Reactors after Fukushima Accident

Introduction of Nation-wide Inspection and Reassessment to Chinese Research Reactors after Fukushima Accident Introduction of Nation-wide Inspection and Reassessment to Chinese Research Reactors after Fukushima Accident XIAO Zhi 1, FU Jie 1, ZHANG Ou 1, SONG Chenxiu 2 1) I Nuclear and Radiation Safety Center,

More information

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director Simposyum Siting of New Nuclear Power Plants and Irradiated Fuel Facilities Buenos Aires Argentina 24-28 June 2013 Panel Fukushima Daiichi s Impact in Nuclear Power Programs Worldwide Brazilian Operator

More information

Risk-Informed Review of Actual Maintenance Strategy at Paks NPP

Risk-Informed Review of Actual Maintenance Strategy at Paks NPP Risk-Informed Review of Actual Maintenance Strategy at Paks NPP Tibor Kiss a, Zoltan Karsa b a Paks NPP, Paks, Hungary b NUBIKI, Budapest, Hungary Abstract: A common pilot project was launched in April

More information

Overview of Fukushima accident. Nov. 9, 2011 Orland, Florida

Overview of Fukushima accident. Nov. 9, 2011 Orland, Florida Overview of Fukushima accident Nov. 9, 2011 Orland, Florida Nuclear Power Plants in Japan Japan Nuclear Japan Energy Nuclear Energy Safety Safety Organization Japan Atomic Industrial Forum, Inc. -Tohoku

More information

Answers to Questions on the National Report

Answers to Questions on the National Report Status of the National Action Plan at the Paks NPP in Hungary on the implementation actions decided upon lessons learned from Fukushima Daiichi accident Answers to Questions on the National Report András

More information

The Nuclear Safety Authority (ASN - Autorité de Sûreté Nucléaire),

The Nuclear Safety Authority (ASN - Autorité de Sûreté Nucléaire), REPUBLIQUE FRANÇAISE ASN Resolution 2014-DC-0406 of 21 th January 2014 instructing Electricité de France - Société Anonyme (EDF-SA) to comply with additional prescriptions applicable to the Gravelines

More information

Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne. Severe Accident Mitigation in German NPP - Status and Future Activities -

Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne. Severe Accident Mitigation in German NPP - Status and Future Activities - Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne Severe Accident Mitigation in German NPP - Status and Future Activities - Content History and status of implementation of Severe Accident Management

More information

The EU-Stresstest Dr. Christoph Pistner

The EU-Stresstest Dr. Christoph Pistner The EU-Stresstest Dr. Christoph Pistner 23.10.2015 Nuclear power plants in Europe as of 25.05.2014 Reactors in operation: Europe (West): 117 KKW 113,5 GW el. Europe (Middle and east): 68 KKW 48,6 GW el.

More information

Seismic Capacity Test before and after the Fukushima Dai-ichi Accident

Seismic Capacity Test before and after the Fukushima Dai-ichi Accident PSAM2013-1013 1 PSAM2013-1013 Seismic Capacity Test before and after the Fukushima Dai-ichi Accident April 16, 2013 Tokyo, Japan Masakatsu INAGAKI, Toru IIJIMA Seismic Safety Standards and Test Group Seismic

More information

IAEA Safety Standards

IAEA Safety Standards IAEA Safety Standards Contact IAEA Publications Marketing and Sales Unit Publishing Section International Atomic Energy Agency Vienna International Centre, P.O. Box 100 1400 Vienna, Austria Email: sales.publications@iaea.org

More information

OVERVIEW ON FINAL STRESS TEST REPORT CERNAVODA NPP Dumitru DINA CEO Nuclearelectrica. 16 th of May 2012 Nuclear 2012 Pitesti, Romania

OVERVIEW ON FINAL STRESS TEST REPORT CERNAVODA NPP Dumitru DINA CEO Nuclearelectrica. 16 th of May 2012 Nuclear 2012 Pitesti, Romania OVERVIEW ON FINAL STRESS TEST REPORT CERNAVODA NPP Dumitru DINA CEO Nuclearelectrica 16 th of May 2012 Nuclear 2012 Pitesti, Romania 1 PREAMBLE On 25 March, 2011, European Council decided that nuclear

More information

Safety Research Activities on Severe Accident Management in S/NRA/R after Fukushima Daiichi Nuclear Power Plant Accident

Safety Research Activities on Severe Accident Management in S/NRA/R after Fukushima Daiichi Nuclear Power Plant Accident Safety Research Activities on Severe Accident Management in S/NRA/R after Fukushima Daiichi Nuclear Power Plant Accident K. AONO, H. HOSHI, A. HOTTA, M. FUKASAWA Regulatory Standard and Research Department,

More information

Data requirements during a severe accident

Data requirements during a severe accident Data requirements during a severe accident presented to International Experts Meeting on Assessment and Prognosis in Response to a Nuclear or Radiological Emergency (IEM 9) Vienna, Austria 2015 April 23

More information

THE FUKUSHIMA ACCIDENT: IMPLICATIONS FOR NUCLEAR SAFETY. Edwin Lyman Union of Concerned Scientists May 26, 2011

THE FUKUSHIMA ACCIDENT: IMPLICATIONS FOR NUCLEAR SAFETY. Edwin Lyman Union of Concerned Scientists May 26, 2011 THE FUKUSHIMA ACCIDENT: IMPLICATIONS FOR NUCLEAR SAFETY Edwin Lyman Union of Concerned Scientists May 26, 2011 The accident: many unknowns Many of the details of the Fukushima Daiichi accident are still

More information

Overview of NRA Human Resource Development Center and NRA Cooperation and Support for IAEA/ANSN

Overview of NRA Human Resource Development Center and NRA Cooperation and Support for IAEA/ANSN Overview of NRA Human Resource Development Center and NRA Cooperation and Support for IAEA/ANSN International Conference on Human Resource Development for Nuclear Power Programmes: Building and Sustaining

More information

Experience and Lessons Learned in Developing Training Course for Stakeholders

Experience and Lessons Learned in Developing Training Course for Stakeholders Experience and Lessons Learned in Developing Training Course for Stakeholders (INDONESIA) Technical Meeting on Cooperation for Human Resource Development among Embarking and Experienced Countries 4 ~ 6

More information

DOCUMENTATION FOR REVIEW AND ASSESSMENT - Application Set -

DOCUMENTATION FOR REVIEW AND ASSESSMENT - Application Set - DOCUMENTATION FOR REVIEW AND ASSESSMENT - Application Set - Contents 1. Overview 2. Licensing Practice in Korea 3. Safety Reviews for License or Approval 4. Licensing Review Documents 5. Safety Approval

More information

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements Sorin Holostencu IAEA Technical Meeting on Operational Experience with Implementation of Post-Fukushima Actions in Nuclear Power Plants,

More information

SAMGs for German NPPs Main Features and Implementation Engineering & Projects (E&P)

SAMGs for German NPPs Main Features and Implementation Engineering & Projects (E&P) SAMGs for German NPPs Main Features and Implementation Engineering & Projects (E&P) H. Plank, M. Braun, M. Loeffler Senior Advisor Severe Accidents Management Guidance AREVA GmbH, PEPA-G In collaboration

More information