California Clean Air Act Annual Progress Report February 27, 2001
|
|
- Melvyn Dalton
- 5 years ago
- Views:
Transcription
1 SAN JOAQUIN VALLEY Air Pollution Control District California Clean Air Act Annual Progress Report 2000 February 27, 2001 Approved by: David Crow, Executive Director/Air Pollution Control Officer Reviewed by: Mark Boese, Deputy Air Pollution Control Officer Robert Dowell, Director of Planning David Jones, Planning Manager Scott Nester, Supervising Air Quality Engineer Prepared by: Joan Merchen, Senior Air Quality Planner
2 INTRODUCTION In 1991, the San Joaquin Valley Unified Air Pollution Control District, in accordance with the requirements of the California Clean Air Act, prepared an Air Quality Attainment Plan (AQAP) which set forth the District s strategy for attaining the California one-hour ozone standard. The strategy includes numerous measures that require District rulemaking and program development for their implementation. Section (a) of the California Health and Safety Code requires each air district to submit an annual report to the California Air Resources Board (ARB) that summarizes its progress in meeting the schedules for developing, adopting and implementing the air pollution control measures in the AQAP. Specifically, ARB s 1993 Guidance for Annual and Triennial Progress Reports Under the California Clean Air Act (Guidance) requires that the Annual Report include the following information: The status of stationary source control measures for the most recent calendar year The status of transportation control measures (TCMs), focussing on activity in TCM implementation through such avenues as federal, state, and local transportation sources; district and other agency programs/interagency agreements for TCM implementation and district rules to backstop such actions Similar information for area source and indirect source control programs Table summarizing, for all measures, the planned adoption and implementation years(s) versus the actual adoption and implementation years Where measures are pending, more detail such as planned workshop activity and the projected adoption month/year. STATIONARY SOURCES The 1991 AQAP committed the District to develop a number of new rules and rule amendments to reduce ozone precursor emissions and established a timeline for their development. However, in 1994, the District s ozone attainment strategy was comprehensively revised in conjunction with the preparation of the Ozone Attainment Demonstration Plan (OADP), prepared to demonstrate attainment of the Federal One-Hour Ozone Standard. The 1994 California Clean Air Triennial Progress Plan and Plan Revision (1994 Triennial Plan) was incorporated into the OADP and reflected the new ozone attainment strategy. New control measures were added and the District s rulemaking schedule was revised. In, the District prepared its 1997 California Clean Air Act Progress Report and Plan Revision (1997 Triennial Plan) and once again reviewed and updated its rulemaking schedule. The rulemaking schedules established in the 1991 AQAP, 1994 Triennial Plan, and 1997 Triennial Plan and the current status of rulemaking are shown in Table 1. 2
3 TRANSPORTATION CONTROL MEASURES AND INDIRECT SOURCES The District s schedule for rule/program development for TCMs and Indirect Source Control s identified in the AQAP is shown in Table 2. The 1994 Triennial Plan did not revise the District s TCMs and Indirect Source Control s. It did, however, indicate that the District and the TPAs would continue to expeditiously implement the TCMs outlined in Chapter 8 of the 1991 AQAP and Appendix E of the 96 ROP Plan. Appendix E listed a number of TCMs to serve as contingency measures in the event that the District did not meet a required emission reduction goal of three percent per year between 1997 and 1999 for ozone precursors that was established by the Federal Clean Air Act Amendments of Most, but not all, of these TCMs were already included in the 1991 AQAP list. The status of the programs outlined in Appendix E of the ROP Plan is shown on Table 3. The 1997 Triennial Plan did not modify the TCMs and Indirect Sources Measures s. 3
4 TABLE 1 STATIONARY SOURCE CONTROL MEASURE RULE MAKING SCHEDULE AND STATUS 1991 AQAP 94 Triennial Plan 97 Triennial Plan Actual Rule Notes 2280-Portable Equipment Registration 4Q/92 3Q/93 10/24/94 10/20/ In-Situ Combustion Crude Oil Production Well Vents Oil Pipeline Pumping Fugitives 4409-Discharge of Production Oil/Flashing Loses 4Q/92 4Q/94 3/19/94 5/19/96 4Q/93 2Q/ Open Burning 4Q/96 1Q/97 4Q/ Final Workshop: 2/2001 Adoption: 5/ Smaller External Combustion Devices (Phase 3) 3Q95 3Q/99 12/19/96 05/31/01 Adopted as an amendment to Rule Dryers (BARCT Phase 4Q/93 4Q/95 1Q/96 1Q/ ) 4308-Asphalt Batch Plants 4Q/93 2Q/ Glass Melting Furnaces 1Q/96 1/Q/98 04/16/98 01/01/ Gas Plant Glycol Regenerators 2001-
5 1991 AQAP 94 Triennial Plan 97 Triennial Plan Actual Rule Notes 4411-Well Cellars 1Q/94 1Q/95 2Q/96 2Q/98 4Q/00 4Q/02 On hold - Only insignificant emission reductions would occur 4412-Oil Well Drilling and Workover Rig Piston Engines 2Q/94 2Q/97 2Q/96 2Q/98 Preempted by ARB s portable equipment rule 4608-Plastic Parts Coating Operations 4611-Small Printing Operations 4501-Marine Vessel Operations (4451) 4502-Marine Vessel Loading Operations (4452) 4601-Architectural Coatings 1Q/96 1Q/98 4Q/99 4Q/02 Final Workshop: 5/2001 Adoption: 8/ Graphic Arts (Includes Paper, Fabric, and Film Coatings) 2Q/94 2Q/97 4Q/95 1Q/98 09/17/97 09/14/ Q/94 2Q/9l6 4Q/95 4Q/97 09/17/97 09/14/00 Adopted as part of Rule Gasoline Transfer into 4Q/93 4Q/95 2Q/96 2Q/98 06/18/98 05/31/99 Stationary Storage Containers, Delivery Vessels, and Bulk Plants 4622-Transfer of Gasoline into Vehicle Fuel Tanks 4Q/93 4Q/95 2Q/95 2Q/98 06/18/98 05/31/ Storage of Organic 2Q/93 3Q/95 3Q/95 3Q/98 4Q/00 4Q/02 4
6 1991 AQAP 94 Triennial Plan 97 Triennial Plan Actual Rule Notes Liquids Workshop 2: 2/2001 Final Workshop: 5/2001 Adoption: 8/ Wastewater Separators 3Q/94 3Q/ Solid Waste Disposal Sites 4Q/92 4Q/94 1Q/95 4Q/98 07/20/ Coatings and Ink Manufacturing Adhesives 4Q/92 2Q/9l4 3/17/94 3/17/ Organic Solvents 1Q/96 1Q/98 2Q/99 2Q/01 To be incorporated into Rule Organic Solvent Degreasing Operations 1Q/94 1Q/96 1Q/96 1Q/98 2Q/99 2Q/01 Final Workshop: 1/2001 Adoption: 3/ Organic Solvent Waste 2Q/96 2Q/98 2Q/99 2Q/01 Workshop 2 2/2001 Final Workshop: 5/2001 Adoption: 8/ Perchloroethylene Dry Cleaning Perc deregulated as a VOC on 12/18/ Polyester Resin Operations 3Q/93 1Q/95 5/19/94 5/19/96 5
7 1991 AQAP 94 Triennial Plan 97 Triennial Plan Actual Rule Notes 4692-Commercial Charbroiling 2Q/96 2Q/98 On hold - Only insignificant emission reductions would occur 4702-Stationary Internal Combustion Engines 2Q/93 4Q/94 2Q/95 4Q/99 12/19/96 5/31/01 Adopted as an amendment to Rule Stationary Gas Turbine 2Q/93 4Q/96 8/18/94 8/18/ Residential and Commercial Water Heaters
8 TABLE 2 TRANSPORTATION CONTROL MEASURES AND INDIRECT SOURCES 1991 AIR QUALITY ATTAINMENT PLAN Indirect Source Control /Transportation Control Measure Development Implementation Status Enhanced CEQA Participation Ongoing program, District reviews and comments on air quality issues on multiple CEQA documents from agencies throughout its boundaries each year. Air Quality Elements Air Quality Guidelines for General Plans was adopted in October 1995 New and Modified Indirect Source Review District is relying on voluntary programs rather than adopting a rule. Prepared Designs for Air Quality in 1997 and a land use/transportation video This or That in for use in promoting voluntary programs. Smoking Vehicles Ongoing program since Between 1993 and 1999, over 37,400 smoking vehicles have been reported, with an average 28.5% response rate from persons receiving smoking vehicle letters each year. Traffic Flow Improvements Ongoing Ongoing Public Transit Ongoing Ongoing Passenger Rail and Support Ongoing Ongoing Facilities Ongoing program. The TPAs have implemented traffic flow improvements including signal synchronization, interconnection, and improved timing projects. In some cases these improvements were funded through the District AB2766 (REMOVE). Ongoing program: Public transit programs continue to occur. Ongoing program: The Valley continues to advocate for better rail service. The Altamonte Commuter Express (ACE) began operation in 1999 and carries more than 9000 passengers per day. Rideshare FY * FY Ongoing program: Each of the District s transportation planning agencies has a voluntary rideshare program that includes services such as carpool ride matching and employer ridesharing assistance. Park and Ride Lots Suburban Area Lots FY * FY Ongoing program: TPA s fund park and ride lots each year with CMAQ funds. 7
9 Indirect Source Control /Transportation Control Measure Development Implementation Status Park and Ride Lots Fringe Area Lots F Y FY Ongoing program: TPA s fund park and ride lots each year with CMAQ funds. Bicycling FY * FY Ongoing program. There are numerous ongoing bicycle programs throughout the SJV, with funding provided by various cities and counties and by the District through its AB2766 (REMOVE) Trip Reduction FY FY District adopted Rule 9001, but rule was rescinded due to state legislation prohibiting such programs. The program is not currently being actively pursued. Parking Management Supply Limits FY FY District encouraged the program through Rule 9001; program lost impetus when rule was rescinded. The program is currently being actively pursued. Parking Management Increased Prices FY FY District encouraged the program through Rule 9001; program lost impetus when rule was rescinded. Telecommunications FY * FY District encouraged the program through Rule 9001; some programs lost impetus when rule was rescinded. District developed a telecommunications network for its 3 offices in October. Alternative Work Schedules FY * FY District encouraged the program through Rule 9001; program lost some impetus when rule was rescinded. The District began an alternative work schedule in Fleet Operator Alternate Fuels FY FY Ongoing. In 1997, the District initiated its Heavy Duty Vehicle Emission Reduction, which provides financial incentives for the purchase of new, replacement or retrofit technology for low emission heavy-duty on-road and off-road vehicles meeting program requirements. The District also provides incentives for light-duty alternative-fuel vehicle purchases and leases through its REMOVE program. It also operated a voluntary Vehicle Buy-Back to remove pre-1982 vehicles from the road during * had already been implemented in some areas within the SJVAB at the time of adoption of the AQAP. 8
10 TABLE 3 TRANSPORTATION CONTROL MEASURES AND INDIRECT SOURCES APPENDIX E, REVISED POST RATE OF PROGRESS PLAN Control Measure Status TCM-1 Traffic Flow Improvements TCM-2 Public Transit TCM-3 Rideshare s TCM-4 Bicycle s TCM-5 Alternative Fuels The TPAs have implemented traffic flow improvements including signal synchronization, interconnection, and improved timing projects. In some cases these improvements were funded through the District AB2766 (REMOVE). Ongoing program: Public transit programs continue to occur. Each of the District s TPAs has a voluntary rideshare program that includes services such as carpool ride matching and employer ridesharing assistance. There are numerous ongoing bicycle programs throughout the SJV, with funding provided by various cities and counties and by the District through its AB2766 (REMOVE) In 1997, the District initiated its Heavy Duty Vehicle Emission Reduction, which provides financial incentives for the purchase of new, replacement or retrofit technology for low emission heavy-duty on-road and off-road vehicles meeting program requirements. The District also provides incentives for light-duty alternative-fuel vehicle purchases and leases through its REMOVE program. It also operated a voluntary Vehicle Buy-Back to remove pre-1982 vehicles from the road during Model Air Quality Element Air Quality Guidelines for General Plans was adopted in October 1995 Enhanced CEQA Review Ongoing, District reviews and comments on air quality issues on multiple CEQA documents from agencies throughout its boundaries each year. Department of Motor Vehicles (DMV) The District s REMOVE program has been in effect since Between 1992 and 1999, Surcharge Vehicle Emission Reduction the program has resulted in 2,304 tons of emission reductions at a total cost of $22,588,166. Fleet Operators Light Emission Vehicle (LEV) Rule Development Auto Buy-Back Coordinate Valley-Wide Regional Transportation Planning Agency Process Rule not adopted because California adopted a low emission vehicle program that satisfied the federal requirement for the rule. implemented as a District-Managed program during the fiscal year and is ongoing through A number of valley wide transportation planning groups are currently active. These include the Modeler s Working Group, Conformity Working Group and the TPA Directors Association. 9
11 Control Measure Incident Management/Call-Box Comprehensive Signal Synchronization System Emergency Freeway Towing Service Valley Rail Consolidation Indirect Source Review Rule Congestion Management Plans Smoking Vehicle Public Education s Status Implementation ongoing. Several Counties have already implemented the program and two counties are currently studying the possible implementation of the program. Implementation ongoing: CMAQ funds are being widely used throughout the Valley to implement this program. The program continues to be implemented in Fresno County. Not implemented, efforts are ongoing. District is relying on voluntary programs rather than adopting a rule. Prepared Designs for Air Quality in 1997 and a land use/transportation video This or That in for use in promoting voluntary programs. Implementation is limited to only some counties in the Valley. Ongoing program since Between 1993 and 1999, over 37,400 smoking vehicles have been reported, with about a 29 percent response rate from individuals receiving a Smoking Vehicle letter. The District began an ozone season public education program, Spare the Air, in and has a number of ongoing public outreach programs to schools, children and the general public. 10
California Clean Air Act Triennial Progress Report and Plan Revision
San Joaquin Valley Air Pollution Control District California Clean Air Act Triennial Progress Report and Plan Revision 1997-1999 March 15, 2001 San Joaquin Valley Air Pollution Control District 1990 East
More informationBay Area 2005 Ozone Strategy
Bay Area 2005 Ozone Strategy Community Meeting Richmond Memorial Auditorium Wednesday, October 26, 2005 Bay Area Air Quality Management District 1 Presentation Ozone background Ozone planning process Overview
More informationPublic Workshop on Developing Expedited BARCT Implementation Schedule
Public Workshop on Developing Expedited BARCT Implementation Schedule November 1, 2018 webcast@valleyair.org San Joaquin Valley Air Pollution Control District AB 617 Background Under AB 617: Accelerated
More informationSan Joaquin Valley Unified Air Pollution Control District November 20, Chapter 10
Chapter 10 Summary of Attainment Strategy 2012 PM2.5 Plan SJVUAPCD Chapter 10: Summary of Attainment Strategy This page intentionally blank. Chapter 10: Summary of Attainment Strategy Chapter 10: Summary
More informationCALIFORNIA CLEAN AIR ACT TRIENNIAL PROGRESS REPORT AND PLAN REVISION
Chapter 8 CALIFORNIA CLEAN AIR ACT TRIENNIAL PROGRESS REPORT AND PLAN REVISION 8 CALIFORNIA CLEAN AIR ACT TRIENNIAL PROGRESS REPORT AND PLAN REVISION 8.1 INTRODUCTION Section 40910 of the California Health
More information07/08 TABLE OF CONTENTS: 1
TABLE OF CONTENTS REGULATION I. GENERAL Rule 1...Title Rule 2...Definitions Rule 3...Advisory Committee Rule 4...Rules Supplemental Rule 5...Effective Date Rule 6...Severability Rule 7...Zone Boundaries
More informationSacramento Regional 8-Hour Ozone Attainment Revised August 25, 2011 and Reasonable Further Progress Plan March 26, 2009
The following Table 1-3 contains a summary of the proposed new regional and local control measures and expected VOC and NOx emission reductions for the Sacramento nonattainment area for the 2018 attainment
More informationExecutive Summary PM2.5 Plan. SJVUAPCD Executive Summary. San Joaquin Valley Unified Air Pollution Control District December 20, 2012
Executive Summary SJVUAPCD This page intentionally blank. The San Joaquin Valley (Valley) faces unique and unprecedented air quality challenges, and this plan is a continuation of the San Joaquin Valley
More informationChapter 7 RATE OF PROGRESS DEMONSTRATION
Chapter 7 RATE OF PROGRESS DEMONSTRATION 7 RATE OF PROGRESS 7.1 INTRODUCTION The Federal Clean Air Act (FCAA) specifies that ozone nonattainment areas must submit to EPA SIP revisions documenting that
More informationCHAPTER 4 EMISSION CONTROL MEASURES
CHAPTER 4 EMISSION CONTROL MEASURES INTRODUCTION EMISSION CONTROL MEASURE MANDATES EMISSION CONTROL MEASURES ADOPTED BEFORE 2004 EMISSION CONTROL MEASURES ADOPTED DURING THE REPORTING PERIOD (2004-2006)
More informationHear perspective and receive input for plan from all affected stakeholders and subject matter experts Provide committee members with resources to
1 January 11, 2017 Hear perspective and receive input for plan from all affected stakeholders and subject matter experts Provide committee members with resources to reach out to constituents that you represent
More informationREASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) STATE IMPLEMENTATION PLAN (SIP) UPDATE ANALYSIS STAFF REPORT
EL DORADO COUNTY AIR QUALITY MANAGEMENT DISTRICT REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) STATE IMPLEMENTATION PLAN (SIP) UPDATE ANALYSIS STAFF REPORT DECEMBER 15, 2006 This Page Intentionally Left
More informationMeeting PM2.5 Standards in the San Joaquin Valley. September 26, 2017
Meeting PM2.5 Standards in the San Joaquin Valley September 26, 2017 Objectives of Today s Workshop 2 Describe Valley s PM challenge Outline attainment strategy Provide update on modeling analysis Solicit
More information1.1 Purpose of the Climate Action Plan Update
Chapter 1 Introduction and Purpose 1.1 Purpose of the Climate Action Plan Update The County of Marin (County) plans to reduce and avoid greenhouse gas (GHG) emissions associated with both community and
More informationAir Quality Management in San Diego County
Air Quality Management in San Diego County asdf San Diego Snapshot 4,255 square miles 65 miles N to S 86 miles E to W 3 million people 3.5 million by 2020 1.4 million jobs 1.7 million by 2020 2.5 million
More information2012 Air Quality Management Plan
2012 Air Quality Management Plan DR. ELAINE CHANG DEPUTY EXECUTIVE OFFICER LOS ANGELES CHAMBER OF COMMERCE ENERGY, WATER & ENVIRONMENTAL SUSTAINABILITY & TRANSPORTATION & GOODS MOVEMENT COUNCILS LOS ANGELES,
More informationSan Joaquin Valley Air Pollution Control District Annual Report. Indirect Source Review Program
San Joaquin Valley Air Pollution Control District 2009 Annual Report Indirect Source Review Program Reporting Period: March 1, 2008 to February 28, 2009 San Joaquin Valley Unified Air Pollution Control
More informationSTATE MANDATED TRIENNIAL PROGRESS REPORT
CHAPTER 11 STATE MANDATED TRIENNIAL PROGRESS REPORT AND TRIENNIAL PLAN REVISION Introduction Triennial Progress Report Air Quality Indicators Transportation Performance Standards Triennial Plan Revision
More informationChapter 7 RATE OF PROGRESS DEMONSTRATION
Chapter 7 RATE OF PROGRESS DEMONSTRATION 7 RATE OF PROGRESS 7.1 INTRODUCTION The FCAA specifies that ozone nonattainment areas must submit to EPA SIP revisions documenting that emissions of volatile organic
More informationREASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) STATE IMPLEMENTATION PLAN (SIP) REVISION WESTERN NEVADA COUNTY 8-HOUR OZONE NONATTAINMENT AREA
NORTHERN SIERRA AIR QUALITY MANAGEMENT DISTRICT Gretchen Bennitt, Executive Director DISTRICT HEADQUARTERS NORTHERN FIELD OFFICE 200 Litton Drive, Suite 320 257 E. Sierra, Unit E Grass Valley, CA 95945
More informationChapter 7. Local, State, and Federal Controls PM2.5 Plan
Chapter 7 Local, State, and Federal Controls This page intentionally blank. 7.1 INTRODUCTION This chapter presents the fourth facet of the District s control strategy: local, state, and federal controls.
More informationEmission Inventory EMISSIONS INVENTORY DEVELOPMENT IN CALIFORNIA. Presentation Outline 9/30/2015
EMISSIONS INVENTORY DEVELOPMENT IN CALIFORNIA San Joaquin Valley Public Advisory Workgroup September 3, 215 Gabe Ruiz Sylvia Vanderspek California Air Resources Board Presentation Outline Emission Inventory
More informationCHAPTER 4: CONTROL STRATEGIES AND REQUIRED ELEMENTS
CHAPTER 4: CONTROL STRATEGIES AND REQUIRED ELEMENTS 4.1 INTRODUCTION The Dallas-Fort Worth (DFW) nonattainment area for the 2008 eight-hour ozone National Ambient Air Quality Standard (NAAQS), which consists
More informationSAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT THE OZONE ATTAINMENT DEMONSTRATION PLAN
SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT THE OZONE ATTAINMENT DEMONSTRATION PLAN PRESENTED NOVEMBER 3, 1994 ADOPTED NOVEMBER 14, 1994 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT
More informationChapter 5 FUTURE OZONE AIR QUALITY
Chapter 5 FUTURE OZONE AIR QUALITY 5 FUTURE OZONE AIR QUALITY 5.1 INTRODUCTION AND SUMMARY Air quality models are used to predict ozone concentrations in future years. These models simulate the formation,
More informationProtect AQ & public health. Governing Board: Large, complex region: 9 counties / 101 cities > 7 million people > 5 million vehicles
Integrating GHGs in the Bay Area 2010 Clean Air Plan David Burch Principal Planner November 16, 2011 Bay Area AQMD Protect AQ & public health in SF Bay Area Governing Board: 22localelected officials Large,
More informationSAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT. Appendix E: Cost Effectiveness Analysis for Rules 9510 and 3180 November 17, 2005
Appendix E: Cost Effectiveness Analysis for Rules 9510 and 3180 November 17, 2005 APPENDIX E Cost Effectiveness Analysis for Proposed Rule 9510 (Indirect Source Review) and Rule 3180 (Administrative Fees
More informationFine Particles in the Air
Fine Particles in the Air Presentation for STAPPA Outreach Committee Rich Damberg, EPA Office of Air Quality Planning and Standards April 6, 2004 Particulate Matter: What is It? A complex mixture of extremely
More informationSACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT. Board of Directors Sacramento Metropolitan Air Quality Management District
SACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT For Agenda of March 25, 2010 To: From: Subject: Board of Directors Sacramento Metropolitan Air Quality Management District Larry Greene Executive
More informationSACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT 2016 ANNUAL PROGRESS REPORT
SACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT 2016 ANNUAL PROGRESS REPORT This Report summarizes the 2016 progress in meeting, adopting and implementing control measures contained in the Sacramento
More informationSan Joaquin Valley Unified Air Pollution Control District PM10 ATTAINMENT DEMONSTRATION PLAN PROGRESS REPORT
San Joaquin Valley Unified Air Pollution Control District PM10 ATTAINMENT DEMONSTRATION PLAN PROGRESS REPORT 1997-1999 Governing Board Hearing Thursday, August 17, 2000 TABLE OF CONTENTS LIST OF TABLES,
More informationChapter 6. Attainment Demonstration, RACM, RFP, and Contingency 2016 PLAN FOR THE HOUR OZONE STANDARD
Chapter 6 Attainment Demonstration, RACM, RFP, and Contingency 2016 PLAN FOR THE 2008 8-HOUR OZONE STANDARD This page intentionally blank. Chapter 6: Attainment Demonstration, RACM, RFP, and Contingency
More informationRULE 206 MOBILE AND TRANSPORTATION SOURCE EMISSION REDUCTION CREDITS Adopted (Amended ) INDEX
RULE 206 MOBILE AND TRANSPORTATION SOURCE EMISSION REDUCTION CREDITS Adopted 12-15-92 (Amended 12-05-96) 100 GENERAL 101 PURPOSE 102 APPLICABILITY 103 SEVERABILITY INDEX 200 DEFINITIONS 201 ACTUAL EMISSION
More informationDRAFT 2015 OZONE CONFORMITY ANALYSIS FOR THE 2019 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM AND THE 2018 REGIONAL TRANSPORTATION PLAN
DRAFT 2015 OZONE CONFORMITY ANALYSIS FOR THE 2019 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM AND THE 2018 REGIONAL TRANSPORTATION PLAN JANUARY 9, 2019 KINGS COUNTY ASSOCIATION OF GOVERNMENTS This report
More informationAIR QUALITY CONFORMITY ANALYSIS
AIR QUALITY CONFORMITY ANALYSIS For the 2011 Regional Transportation Plan and 2013 Federal Transportation Improvement Program Adopted on July 25, 2012 Stanislaus Council of Governments 1111 I Street, Suite
More informationChapter 3. Demonstration of Federal Clean Air Act Requirements. PROPOSED 2016 Moderate Area Plan for the 2012 PM2.5 Standard
Chapter 3 Demonstration of Federal Clean Air Act Requirements This page intentionally blank. Chapter 3: Demonstration of Federal CAA Requirements PROPOSED Moderate Area Plan for the 2012 PM2.5 Standard
More informationApril 2003 RTPA BACM Submittal
OVERVIEW OF REGIONAL TRANSPORTATION PLANNING AGENCY PROCESS TO IDENTIFY AND IMPLEMENT BEST AVAILABLE CONTROL MEASURES IN SUPPORT OF THE PM-10 ATTAINMENT PLAN FOR THE SAN JOAQUIN VALLEY The San Joaquin
More informationChapter 4. Attainment Strategy for PM2.5
Chapter 4 Attainment Strategy for PM2.5 This page intentionally blank. Chapter 4: Attainment Strategy for PM2.5 TABLE OF CONTENTS 4. Attainment Strategy for PM2.5... 4-1 4.1 Comprehensive Existing Regulatory
More informationSAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT. Appendix B: Emissions Reduction Analysis for Rule 9510 and 3180 December 15, 2005
APPENDIX B Emissions Reduction Analysis for Proposed Rule 9510 (Indirect Source Review) and Rule 3180 (Administrative Fees for Indirect Source Review) December 15, 2005 B - 1 EMISSION REDUCTION ANALYSIS
More informationAPPENDIX VIII AIR QUALITY CONFORMITY ANALYSIS
2018 Kings County Regional Transportation Plan APPENDIX VIII AIR QUALITY CONFORMITY ANALYSIS H:\RTPA\2018 RTP Update\Final RTP\APPENDIX VIII - Air Quality Conformity Title Page.docx Appendix VIII CONFORMITY
More informationGeneral Plan. Air Quality Element. Adopted December 15, 1993 Amended November 9, 2011 Amended September 26, 2017
General Plan Air Quality Element Adopted December 15, 1993 Amended November 9, 2011 County of Sacramento Office of Planning and Environmental Review Table of Contents GOALS AND POLICIES... 1 Multidisciplinary
More informationDFW SIP Development Update and Oil & Gas Inventory Follow-Up
DFW SIP Development Update and Oil & Gas Inventory Follow-Up Air Quality Division Heather Evans, Michael Ege, Chris Kite Air Quality Technical Information Meeting Arlington, Texas April 17, 2014 Air Quality
More informationRULES & REGULATIONS APPENDICES
RULES & REGULATIONS APPENDICES AUGUST 2018 COUNTY OF SAN DIEGO AIR POLLUTION CONTROL DISTRICT 10124 OLD GROVE ROAD SAN DIEGO, CA 92131-1649 (858) 586-2600 (For information concerning permits use the above
More informationUpdating our Plan for Clean Air in Santa Barbara County
1 I N T R O D U C T I O N Updating our Plan for Clean Air in Santa Barbara County The 2016 Ozone Plan (2016 Plan) is the eighth triennial update to the initial state Air Quality Attainment Plan adopted
More information42 USC 7511a. NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see
TITLE 42 - THE PUBLIC HEALTH AND WELFARE CHAPTER 85 - AIR POLLUTION PREVENTION AND CONTROL SUBCHAPTER I - PROGRAMS AND ACTIVITIES Part D - Plan Requirements for Nonattainment Areas subpart 2 - additional
More informationEMISSION INVENTORY PM10 PLAN Revised 12/18/03 INTRODUCTION
2003 PM10 PLAN Revised 12/18/03 EMISSION INVENTORY INTRODUCTION This chapter discusses the District's emission inventory (EI). It also describes the federal requirements pertaining to emissions inventories
More information2008 EIGHT-HOUR OZONE REASONABLY AVAILABLE CONTROL TECHNOLOGY DEMONSTRATION FOR SAN DIEGO COUNTY FINAL - DECEMBER 2016
2008 EIGHT-HOUR OZONE REASONABLY AVAILABLE CONTROL TECHNOLOGY DEMONSTRATION FOR SAN DIEGO COUNTY FINAL - DECEMBER 2016 SAN DIEGO COUNTY AIR POLLUTION CONTROL DISTRICT 10124 OLD GROVE ROAD SAN DIEGO, CA
More informationSAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT
SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT FINAL STAFF REPORT AND RECOMMENDATIONS ON AGRICULTURAL BURNING May 20, 2010 () Prepared by: Koshoua Thao, Senior Air Quality Specialist Anna Myers,
More informationSan Joaquin Valley Air Pollution Control District Annual Report. Indirect Source Review Program
San Joaquin Valley Air Pollution Control District 2015 Annual Report Indirect Source Review Program Reporting Period: July 1, 2014 to June 30, 2015 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT
More informationSan Joaquin Valley Air Pollution Control District Annual Report Indirect Source Review Program
San Joaquin Valley Air Pollution Control District 2011 Annual Report Indirect Source Review Program Reporting Period: March 1, 2010 to June 30, 2011 San Joaquin Valley Unified Air Pollution Control District
More informationSJVUAPCD. Chapter 5. Attainment Strategy DRAFT 2016 PLAN FOR THE HOUR OZONE STANDARD
SJVUAPCD Chapter 5 Attainment Strategy DRAFT 2016 PLAN FOR THE 2008 8-HOUR OZONE STANDARD This page intentionally blank. Chapter 5: Attainment Strategy Chapter 5: Attainment Strategy The District s strategy
More informationTestimony of Seyed Sadredin Executive Director/Air Pollution Control Officer San Joaquin Valley Air Pollution Control District
Executive Director/Air Pollution Control Officer San Joaquin Valley Air Pollution Control District Before the Written Testimony on H.R. 806, Ozone Standards Implementation Act of 2017 Chairman Shimkus,
More information2016 OZONE PLAN October 2016
2016 OZONE PLAN October 2016 Santa Barbara County Air Pollution Control District 260 North San Antonio Road, Suite A, Santa Barbara, CA 93110 805-961-8800 www.ourair.org Aeron Arlin Genet Air Pollution
More informationSenate Bill 700 (Florez): Agriculture & Air Quality Summary and Implementation April 2004
Paper on SB 700. It is intended to provide guidance to the California Air Districts as they implement the program. Senate Bill 700 (Florez): Agriculture & Air Quality Summary and Implementation April 2004
More informationSAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT. APPENDIX D: Technical Support Document August 18, 2011 APPENDIX D
APPENDIX D: Technical Support Document APPENDIX D EPA Technical Support Document (TSD) D-1 Final Draft Staff Report with Appendices APPENDIX D: Technical Support Document This page intentionally blank.
More informationSACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT EXPEDITED BARCT IMPLEMENTATION SCHEDULE FOR ASSEMBLY BILL 617.
SACRAMENTO METROPOLITAN AIR QUALITY MANAGEMENT DISTRICT EXPEDITED BARCT IMPLEMENTATION SCHEDULE FOR ASSEMBLY BILL 617 Prepared by: Approved by: Kevin J. Williams, Ph.D. Program Supervisor Mark Loutzenhiser
More informationPotential Amendments to Rule 4901 Wood Burning Fireplaces and Wood Burning Heaters. December 12, 2018
Potential Amendments to Rule 4901 Wood Burning Fireplaces and Wood Burning Heaters December 12, 2018 webcast@valleyair.org Purpose of Meeting Kick-off public rule development process for potential enhancements
More informationChapter 1. Progress and Current Air Quality Ozone Plan
Chapter 1 Progress and Current Air Quality This page intentionally blank. 1.1 INTRODUCTION This chapter presents an overview of the progress that has been made and the current state of the San Joaquin
More informationBackground. North Carolina RACT Rules. Attachment
Clarifying Information for Group I Control Techniques Guidelines and Nitrogen Oxide and Volatile Organic Compounds Reasonably Available Control Technology for Major Sources Background On April 15, 2004,
More informationMOUNTAIN HOUSE SPECIFIC PLAN II
CHAPTER TEN: AIR QUALITY AND TRANSPORTATION MANAGEMENT 10.1 INTRODUCTION 10.1 10.2 OVERALL ISSUES AND CROSS-REFERENCES 10.1 10.3 CLEANER FUELS 10.2 10.4 CONSTRUCTION PROGRAM FOR AIR QUALITY 10.3 10.5 HOUSES
More informationSan Joaquin Valley Unified Air Pollution Control District April 16, 2013
Appendix D Vehicle Miles Traveled Emissions Offset Demonstration 2013 Plan for the Revoked 1-Hour Ozone Standard SJVUAPCD Appendix D: VMT Emissions Offset Demonstration This page intentionally blank. Appendix
More informationAir Pollution Control Board San Diego County Air Pollution Control District
Governing Body Air Pollution Control Board San Diego County Air Pollution Control District AGENDA ITEM GREG COX First District DIANNE JACOB Second District PAM SLATER-PRICE Third District RON ROBERTS Fourth
More informationExecutive Summary. TCAG 2014 Regional Transportation Plan
Executive Summary TCAG 2014 Regional Transportation Plan About Tulare County Tulare County is located in California's San Joaquin Valley (SJV)[Figure 1-1]. Tulare County is bordered by Inyo County to the
More informationMonterey Bay Unified Air Pollution Control District (
3.3.8 Air Quality Introduction The Air Quality section addresses the impacts of the project on ambient air quality and the exposure of people, especially sensitive individuals, to hazardous pollutant concentrations.
More informationAgenda. Background PM2.5 Attainment Plan Public Workshop
2012 PM2.5 Attainment Plan Public Workshop webcast@valleyair.org April 30, 2012 Agenda Overview of 2012 PM2.5 Plan PM2.5 in the San Joaquin Valley Air Quality Trends Emissions Inventory Modeling Analysis
More informationCHAPTER 4 ALTERNATIVES
CHAPTER 4 ALTERNATIVES Introduction Alternatives Rejected as Infeasible Alternatives to the 2004 Ozone Strategy Alternatives Analysis Comparison CHAPTER 4: ALTERNATIVES 4.0 ALTERNATIVES 4.1 INTRODUCTION
More information3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS
3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS 3.1 INTRODUCTION Construction activities have the potential to generate a substantial amount of air pollution. In some cases, the
More informationOzone State Implementation Plan (SIP) Revision. Reasonably Available Control Technology (RACT) as Applicable to the 8-Hour Ozone Standard
Ozone State Implementation Plan (SIP) Revision Reasonably Available Control Technology (RACT) as Applicable to the 8-Hour Ozone Standard Sacramento Metropolitan Air Quality Management District October
More informationBarry Young CAPCOA Engineering & Toxics Symposium October 31, 2018
AB 617: Community Health Protection Program Bay Area Air Quality Management District Barry Young CAPCOA Engineering & Toxics Symposium October 31, 2018 Presentation Topics Community Selection West Oakland
More informationAir Pollution Sources Overview. Amy Roberts, Division Manager January 24, 2019
Air Pollution Sources Overview Amy Roberts, Division Manager January 24, 2019 Types of Air Pollutants Criteria Pollutants Particulate Matter Nitrogen Dioxide Ozone Carbon Monoxide Lead Sulfur Dioxide Air
More informationBAY AREA AIR QUALITY MANAGEMENT DISTRICT
BAY AREA AIR QUALITY MANAGEMENT DISTRICT Created by the State Legislature in 1955 Board of Directors-- --23 Members, Representatives from Each County Hearing Board-- --Quasi-Judicial Panel composed of
More informationNOTICE OF PREPARATION OF A DRAFT ENVIRONMENTAL IMPACT REPORT AND PUBLIC SCOPING MEETING FOR COALINGA OIL FIELD EIR No. 7180
NOTICE OF PREPARATION OF A DRAFT ENVIRONMENTAL IMPACT REPORT AND PUBLIC SCOPING MEETING FOR COALINGA OIL FIELD EIR No. 7180 TO: FROM: SUBJECT: Responsible and Trustee Agencies, other interested agencies,
More informationAir Quality Conformity. TTP220 S. Handy 4/25/16
Air Quality Conformity TTP220 S. Handy 4/25/16 The 4-Step Model INPUTS? Land use data Network Population, income, autos by zone Employment by type by zone Represented as nodes and links Travel times from
More informationNOTICE OF PREPARATION
City of Ceres City of Hughson City of Modesto City of Newman City of Oakdale City of Patterson City of Riverbank City of Turlock City of Waterford County of Stanislaus Date: January 4, 2013 NOTICE OF PREPARATION
More informationChapter 1 Introduction
Chapter 1 Introduction SJVUAPCD Chapter 1: Introduction This page intentionally blank. Chapter 1: Introduction CHAPTER 1: INTRODUCTION The U.S. Environmental Protection Agency (EPA) periodically reviews
More informationREASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) STATE IMPLEMENTATION PLAN (SIP) REVISION WESTERN NEVADA COUNTY 8-HOUR OZONE NONATTAINMENT AREA
NORTHERN SIERRA AIR QUALITY MANAGEMENT DISTRICT Gretchen Bennitt, Executive Director DISTRICT HEADQUARTERS NORTHERN FIELD OFFICE 200 Litton Drive, Suite 320 257 E. Sierra, Unit E Grass Valley, CA 95945
More informationImplementation of the National Ambient Air Quality Standards (NAAQS): Opportunities for Public Participation
Implementation of the National Ambient Air Quality Standards (NAAQS): Opportunities for Public Participation EPA Environmental Justice Training Research Triangle Park, NC March 18, 2014 Rich Damberg U.S.
More informationOIL AND GAS SUPPLEMENT
Santa Barbara County Oil and Gas Supplement Page 1 OIL AND GAS SUPPLEMENT The purpose of this supplement is to ensure that sufficient information is provided at the application submittal stage per Section
More informationSAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT FINAL DRAFT STAFF REPORT
FINAL DRAFT STAFF REPORT Proposed Amendments to Rule 4621 (Gasoline Transfer into Stationary Storage Containers, Delivery Vessels, and Bulk Plants) and Rule 4622 (Gasoline Transfer into Motor Vehicle Fuel
More informationCrittenden County NOx, VOC & CO Emission Inventory Ozone NAAQS Nonattainment
Crittenden County NOx, VOC & CO Emission Inventory 2008 NAAQS Nonattainment 2014 TABLE OF CONTENTS 1 Introduction 2 A. Background B. Emissions Summary Section I 3 Area Source Inventory Section II 6 On-road
More information4.8 GREENHOUSE GAS INTRODUCTION ENVIRONMENTAL SETTING. Section 4.8 Greenhouse Gas
4.8 GREENHOUSE GAS 4.8.1 INTRODUCTION This section provides an overview of the existing greenhouse gas conditions within the project area and surrounding region, regulatory framework, and environmental
More informationVista Canyon Transit Center - Air Quality Technical Memorandum
803 Camarillo Springs Road, Suite C Camarillo, California 93012 (805) 437-1900 FAX (805) 437 1901 www.impactsciences.com MEMORANDUM To: Kris Markarian, City of Santa Clarita Job No. 1046.003 From: Susan
More informationAppendix I. Summary of Significant Comments and Responses PM2.5 Plan. SJVUAPCD Appendix I: Summary of Significant Comments and Responses
Appendix I Summary of Significant Comments and Responses SJVUAPCD Appendix I: Summary of Significant Comments and Responses This page intentionally blank. Appendix I: Summary of Significant Comments and
More informationAppendix I. Candidate Control Measures Ozone Plan
Appendix I Candidate Control Measures This page intentionally blank. The San Joaquin Valley Unified Air Pollution Control District (District) conducted an exhaustive search for emissions reductions to
More informationProposed Repeal of Volatile Organic Compounds (VOC) Regulations for Pulaski County
Proposed Repeal of Volatile Organic Compounds (VOC) Regulations for Pulaski County Overview History of the Pulaski County VOC Regulations Pulaski County Air Quality Monitoring Trends Air Quality Modeling
More informationAppendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY
Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY 2014 REGIONAL CONGESTION MANAGEMENT PROGRAM 2014 RTP/SCS APPENDIX O SAN JOAQUIN COUNCIL OF GOVERNMENTS
More informationChapter 5. Congestion Management Program. Chapter 5
Chapter 5 Congestion Management Program Chapter 5 67 Chapter 5 Congestion Management Program Enacted in the early 1990s, California s Congestion Management Program (CMP) statutes encourage local jurisdictions
More informationTRANSPORTATION CONTROL MEASURES
CHAPTER 5 TRANSPORTATION CONTROL MEASURES Introduction Memorandum of Understanding Transportation Control Measures Emission Reduction Overview Adopted Measures Proposed Measures Contingency Measures Proposed
More informationAir Quality Memorandum - DRAFT
Air Quality Memorandum - DRAFT REPORT NO. 39 DATE February 15, 2019 SUBJECT CONFORMITY ANALYSIS FOR THE WFRC 2019-2050 REGIONAL TRANSPORTATION PLAN. ABSTRACT The FAST Act and the Clean Air Act Amendments
More informationProfile of California Air Quality
Profile of California Air Quality STAPPA and ALAPCO Fall 2003 Membership Meeting October 18, 2003 Catherine Witherspoon Executive Officer California Environmental Protection Agency Air Resources Board
More informationEl Cerrito Draft Climate Action Plan Public Comment and Responses April 9, 2013
El Cerrito Draft Climate Action Plan Public Comment and Responses April 9, 2013 Summary of Changes Made to the Climate Action Plan Based on public comment received during the public review period of February
More informationThe Metropolitan Transportation Plan. Public Meetings February 2016
The Metropolitan Transportation Plan for North Central Texas Public Meetings February 2016 Presentation Agenda Mobility 2040 Draft Recommendations RTC Policy Bundle Concept Transportation Improvement Program
More informationPierre Delforge, NRDC
Pierre Delforge, NRDC Electrification of buildings in context To minimize climate change impacts, we need to reduce GHG emissions by 80% by 2050 (below 1990) 80/50 Decarbonization Framework Energy Efficiency
More informationSJVUAPCD. Chapter 2. Air Quality in the Valley: Challenges and Progress DRAFT 2016 PLAN FOR THE HOUR OZONE STANDARD
SJVUAPCD Chapter 2 Air Quality in the Valley: Challenges and Progress DRAFT 2016 PLAN FOR THE 2008 8-HOUR OZONE STANDARD This page intentionally blank. Chapter 2: Air Quality in the Valley: Challenges
More informationCongestion Mitigation & Air Quality Call for Projects/Programs. Overview Presentation December 12, 2018
Congestion Mitigation & Air Quality Call for Projects/Programs Overview Presentation December 12, 2018 Nonattainment designation on July 17, 2018 Effective date: September 24, 2018 Bexar County has violated
More informationProcedures for Implementing the California Environmental Quality Act. August 2000
ENVIRONMENTAL REVIEW GUIDELINES Procedures for Implementing the California Environmental Quality Act Prepared by the Mobile Source/CEQA Section of the Planning Division of the San Joaquin Valley Unified
More informationSan Joaquin Valley Unified Air Pollution Control District. Best Performance Standard (BPS) x.x.xx
San Joaquin Valley Unified Air Pollution Control District Best Performance Standard (BPS) x.x.xx Class Category VOC Control/Gas Disposal Oil and Gas Production, Processing, and Refining 1) -Incineration
More informationTriennial Assessment and Plan Update
Triennial Assessment and Plan Update 07-13- 2016 Yolo Solano Air Quality Management District 1947 Galileo Court, Suite 103 Davis, CA 95618 Phone: (530) 757-3650 Fax: (530) 757-3670 www.ysaqmd.org Triennial
More information2006 PM10 Plan. San Joaquin Valley Air Pollution Control District
San Joaquin Valley Air Pollution Control District San Joaquin Valley Strategy for Meeting Federal Air Quality Requirements for Particulate Matter 10 Microns and Smaller San Joaquin Valley Unified Air Pollution
More informationDRAFT Triennial Assessment and Plan Update March 11, 2016
DRAFT Triennial Assessment and Plan Update March 11, 2016 Yolo Solano Air Quality Management District 1947 Galileo Court, Suite 103 Davis, CA 95618 Phone: (530) 757-3650 Fax: (530) 757-3670 www.ysaqmd.org
More information