1 INSPIRE case study DECIPHER: Distributed European Community Individual Patient Healthcare Electronic Record Acknowledgement: This case-study has been produced thanks to the contribution of DECIPHER Consortium (see: decipherpcp.eu) DECIPHER PCP Project, funded under the European Commission 7th Framework Programme for research and technological development (FP7), is an ongoing project and challenges the industry to develop mobile solutions that enables secure cross-border access to existing patient healthcare portals and efficient and safe medical care of mobile patients in EU member states. These solutions (the DECIPHER Service) shall be of special interest in the management of patients with chronic diseases or unplanned care episodes. DECIPHER PCP Procedure follows the Phased Pre-commercial Procurement model described by the European Commission in the Communication "Pre-commercial Procurement: Driving innovation to ensure sustainable high quality public services in Europe", Brussels, COM [2007] 799 as well as in a EC staff working document Example of a possible approach for procuring R&D services applying risk-benefit sharing at market conditions, i.e. pre-commercial procurement SEC [2007] 1668 as a competitive procedure for acquiring Research and Development ("R&D") services. All procurement activities are conducted by the Procuring Entity as single procuring entity. The Procuring Entity is the Agència de Qualitat i Avaluació Sanitàries de Catalunya (AQuAS), a public agency attached to the Health Department of the Regional Government of Catalonia (SPAIN). The Procuring Entity is purchasing on behalf of three procuring authorities: ESTAV CENTRO (Ente per i Servizi Tecnico-amministrativi di Area Vasta Centro) (ITAL), a Tuscany Regional Agency in charge of centralized procurement, logistics, health technology and Information and Communications Technology (ICT) support for Central Tuscany Public Health Entities (ASL10 Firenze, AOU Careggi, AOU Meyer, ASL3 Pistoia, ASL4 Prato, ASL11 Empoli and ISPO). TICSALUT (SPAIN), a public foundation attached to the Health Department of the Regional Government of Catalonia (Spain) that works to promote the development and use of ICT and networking in the field of health, acts as an observatory for new trends, innovation and monitoring of emerging initiatives and provides services for the standardization and accreditation of products. CMFT-TRUSTECH (Central Manchester foundation Trust) (UK), an United Kingdom National Health Service (NHS) organization that aims to improve healthcare through the development of innovative products and services, providing consultancy services and expert advisory to help individuals and teams to develop and commercialize or disseminate their innovative products and services, to protect their intellectual property, as well as to manage their innovations and to introduce new technologies to meet clinical needs and improve patient care. Page 1 of 8

2 Roles involved: Procuring entity (AQuAS): project manager, expert in innovation, legal department, contracting department, expert in evaluation of innovation, Procuring authorities (TICSALUT, ESTAV Centro, CMFT-TRUSTECH): experts in innovation, end-users, experts in technology, contracting departments to monitor current PCP and plan for future PPI. Other DECIPHER project partners (VTT, ANCI Innovazione, BDIGITAL): R&D/innovation departments responsible to analyse the state-of-the-art, set-up test environment, evaluate and monitor the bidders; dissemination departments responsible to attract bidders and disseminate the results. Status: on-going Contact person: Rossana Alessandrello Key information Object: R&D services Demand side driven approach (need /challenge definition) Separation with the procurement of commercial volumes of end-product and no preferential treatment in the supply of the final product (re-opened competition) Absence of exclusive condition: the public purchaser does not reserve the R&D results exclusively for its own use Competitive procurement (no invitation-based or restricted procedure) Development in phases Multiple-sourcing contract Retaining at least two participating companies until the last phase to ensure a (future) competitive market Open, transparent, non-discriminatory selection procedure based on objective selection and award criteria specified in advance of the bidding procedure Contractual arrangements (including IPRs), rights and obligations allocation decided upfront and made available to all interested bidders in advance All potential bidders (including SMEs) have equal chances to bid against the same contractual condition Awarded criterion: MEAT (competition also on price) 1. Identification and assessment of unmet needs within (and starts from) the public bodies The main objective of DECIPHER project is to enable secure cross-border mobile access to existing Personal Health Records (PHRs) which are individually supported by national (governmental) bodies. DECIPHER project is making use of Pre-commercial Procurement (PCP) to create step-change innovations in mobile patient ICTs. During the Need Assessment phase (Phase 0) the procuring authorities shared their own strategic requirements and identify their common needs. They validated those requirements and needs with patients and healthcare professionals through specific workshops run at each procuring authorities Page 2 of 8

3 country and they identified the relevant business case. Finally they verified the concept viability with the technological suppliers and through a patent search. The outcome of this phase was a first level of definition of requirements specifications further developed together with the ITT documentation. DECIPHER came up with its own definition of Phase 0, making sure that all the steps identified in the literature are present but at the same time adding overlapping temporal windows among the different stages ensuring in this way a major efficiency in the PCP scope definition. DECIPHER Phase 0 process can be represented as per figure below: Figure 1 DECIPHER Phase 0 Process 2. Involvement of users in specification of requirements and/or piloting During the Needs Identification phase the three procuring authorities carried individual analysis at their own countries interviewing healthcare professionals, institutions and opinion leaders. Six moderated workshops took place (two in Manchester, two in Florence and two in Barcelona) to verify with citizens and healthcare professionals the identified needs and to further develop DECIPHER requirements. In total, some 30 patients and 30 healthcare professionals were consulted for this analysis. 3. SoA analysis via open technical dialogue and early market engagement The state-of-the-art study aims were to provide technical background information for the development and procurement of the DECIPHER Service. Most importantly, the DECIPHER Service requires access to Personal Health Record (PHR) data residing in national health-data repositories. There are many challenges both Page 3 of 8

4 technical and privacy-related - in accessing the PHRs by other applications. Therefore applications accessing PHR systems are typically tethered e.g. solutions provided by the national authorities and bound to particular EHR systems. Prior to the technical dialogue, an Horizon Scan was carried out, which consisted of a review of the Literature of scientific, technical publications and patent search to guarantee that the technological solutions developed during the project are innovative and can be protected by IPR The Market consultation consisted of the technical dialogue and early market engagement. This stage was one of the most critical for the success of the project since it was not only a way to attract bidders to the PCP programme but it was a tool to validate with the market the procuring authorities requirements, the PCP procedure (budget distribution, phases duration and awarded proposals) and technological gap. The outcomes of this phase were: The validation of the technology gap with the technology providers The validation of the PCP procedure characteristics with the technology providers All Phase 0 stages were the different filters the innovation ideas went through when crossing the DECIPHER Innovation Funnel. Thanks to these filters the scope of the PCP programme was reduced just to the three procuring authorities common needs that are still uncovered by the existing technologies and that the industry is willing to deliver within the defined timeframe and sharing risks and benefits as defined in the programme: Figure 2 DECIPHER Innovation Funnel Page 4 of 8

5 4. Specification of functional / performance-based requirements The Functional specification phase was crucial for the success of the project since its outcome not only determined the next steps to perform to complete Phase 0 (the state of the art analysis in DECIPHER domain, the patent search, business cases and the engagement of the industry players) but also its outcome made part of the tender documentation the bidders used to define their proposals. The methodology used to elicit the functional specifications is called FAST (Functional Analysis System Technique). According to this methodology the basic element of a system is the Function that describes the original intent or purpose that a product, process or service expected to be performed. The description of a Function is restricted to a two words format: Active Verb + Measurable Name. The Verb is used to answer to the question: What does it do? While the Name is used to answer to the question: What does the Verb apply to? (e.g.: record data, maintain data) DECIPHER opted to define each of the functions by means of questions.the use of questions is expected to offer opportunity to bidders to propose their most innovative solutions An example extracted from DECIPHER Challenge Brief could be: The function of Manage Treatments expresses the needs: Q3.1 - How can we increase treatment adherence? Q3.2 - How can we reduce the number of times patients run out of medicines? Q3.3 - How can we ensure treating physician is informed about all the known treatments adverse effects, interactions and intolerances before prescribing new ones? Some of the functionalities to be addressed by DECIPHER Service are: i. Register effects. Patients can report in DECIPHER treatments adverse effects, interactions and intolerances of the prescribed treatments and this report should be sent back to the PA-PHR-S. ii. Register events. Patients are requested to confirm in DECIPHER they follow the treatment schedule. iii. Manage and Send Reminders. Page 5 of 8

6 Patients are reminded from DECIPHER to follow the treatment. (...) 5. Verification of innovative solutions (either within the tendering process or in precommercial phase) The innovative solution developed during the DECIPHER process will be verified in different ways: During each of the phases the bidders are requested to submit an interim report that indicates the progress made during the phases and is evaluated by the monitoring team, composed by the procuring authorities, external experts and technical experts. The monitoring team will evaluate the interim report and provide recommendations that will have to be taken into consideration by the bidders for the end of phase report. The Expert Board, composed by different members of the monitoring team and including healthcare professionals and patients, will evaluate the end of phase report which is determinant for the bidders to join next phase of the PCP process. During the last phase, the proof of concept, there will be patients and healthcare professionals involved in the validation of the competing solutions. 6. Shared allocation of risks and benefit (including IPR) In co-sponsoring the R&D services between suppliers and the procuring authorities, the latters share the risk inherent to these activities. As a condition of the PCP, the ownership of the IPR generated within the project activities will remain with the Suppliers. However a free licence will be provided to each procuring authority for possible implementation of new proofs of concept and the training of new users (both professionals and patients) in the solutions reached throughout the PCP process. A call-back provision is included in case bidders are not progressing with the exploitation within a maximum of three-year period after the end of the PCP process or are used to the detriment of the public interest behind the DECIPHER PCP at any time. 7. Enable the participation of SMEs One of the main objectives of the project is to support SMEs in their R&D activities by sharing with them the related costs and risks of this investment. The PCP is also a mean by which the procurements are giving Page 6 of 8

7 access to a potential market for suppliers who would not have had the opportunity without the initial boost in their R&D on innovative solutions. These technological solutions will be closer to market and health procurers will have access to innovative products that has been designed according to their specific requirements, while at the same time entrepreneurs will develop commercially competitive solutions. Given that the exclusion criteria are low-demanding in DECIPHER s call for tender, SMEs can be suitable for the procurement process and come forward with their innovative ideas and work in cooperation with the procuring entities in defining the specifications of the product in accordance with their needs. Partner finding option provided from DECIPHER website & and the possibility to create consortium is regulated within the ITT, allowing SME to joint strength and asset to bid together 8. Enhance the competition during execution and facilitate innovation over the contract period (for PCP multiple sourcing and approach in phases, for PPI performance condition, lots.) The joint PCP will be conducted ensuring that the competition is conducted using an open, fair and transparent tendering process. The DECIPHER PCP Procedure will be divided into four Phases. Each phase will result in a competition between the Bidders in such a way that the number of Bidders will decrease from one Phase to the next one to ensure selecting those that best address the technical challenge on which this PCP is based: Phase 0: Initial Selection.- Any Bidder will be entitled to submit a preliminary innovative solution, for which will receive no payment (no budget nor payments at this stage). Phase 1: Solution Design Selection. A maximum of 9 Bidders awarded with the Phase 1 will be entitled to submit a final design for an innovative solution, for which each Bidder will receive a maximum payment of EUR (VAT excluded). Phase 2: Prototype Development Selection.- A maximum of 6 Bidders awarded with the Phase 2 will be entitled to develop prototypes on the basis of the final innovative solutions selected at the end of Phase 1, for which each Bidder will receive a maximum payment of EUR (VAT excluded). Phase 3: Proof of Concept.- A maximum of 3 Bidders awarded with the Phase 3 will be entitled to produce and test a small scale products on the basis of the prototypes finally selected at the end of Phase 2, for which each Bidder will receive a maximum payment of EUR (VAT excluded). 9. (Identified) Knowledge, skills and resources needed to conduct PCP/PPI DECIPHER consortium did not have significant previous experience in the PCP process. The project is an opportunity the entities involved in developing and testing knowledge, skills and resources necessary for the implementation of innovation procurement and innovation in procurement processes. In the partners organizations, apart from the Innovation department, the legal contract department and end-users, such as healthcare professionals and patients, had to face a new perspective to this innovative approach to technology and services provision. The project management team in the innovation Page 7 of 8

8 departments, as such were prepared for this approach as part of their tasks, whereas legal and contract departments and end-users came on board as stakeholders within the organizations that required understanding and learning new skills and know-how to tackle a PCP. It is worth mentioning, that expertise in keeping up with the state-of-the-art in m-health and innovation in the health technology mastering were crucial. Better understanding of the business and entrepreneurial contexts and requirements on behalf of the partners is essential. Furthermore, the communication departments had to become familiarized with the concepts involved to effectively disseminate information on the PCP process to all stakeholders, potential bidders and SMEs. 10. Business / service case development- was this present and relevant As from the early stages of the Need Assessment for the 3 procuring authorities, the development of a business case was taken into consideration. During this process, the three regional procurers defined the common needs and benefits. They came to the consensus on 3 benefits that would support investment in DECIPHER: I. Improvement in patients health status and quality of life II. Reduction of healthcare burden through mainly the increase of treatment adherence and the decrease of possible complications of long term conditions III. Increase of mhealth industry market through the adoption of interoperability standards Both the Business Case and the Qualitative business model were defined during the Feasibility Analysis and Concept Viability phase 11. What was the main aim of the procurement? Procure only new technology/solution or technology+ service (service procurement) leading also possibly to change in care model/delivery? The main aim was to procure for a new solution where technology providers were not given preconceptions on whether it should be a technology only or technology+service. Their business model should define how this solution would be sustainable. In any case the ultimate goal is to positively impact the healthcare services delivery thanks to the technology provided and the bidders business model should take into account this change in the service. 12. Procurement results was it worth the investment in the pre-procurement phase? At this stage, it is too early to draw a definitive conclusion, so far the learning process has been enriching for our consortium. 13. Main lessons learnt in general As above, at this stage it is too early to make such analysis. Page 8 of 8

D 2.1 Analysis of innovation procurement practices

D 2.1 Analysis of innovation procurement practices Work Package: 2. WP2 PCP Academy D 2.1 Analysis of innovation procurement practices Version: 1.0 Date of Issue: August 2015 Page 1 of 13 Page 2 of 13 Document Information Authors Name Partner Main author

More information

E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants

E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants E. Specific requirements for innovation procurement (PCP/PPI) supported by Horizon 2020 grants This annex applies to PCPs and PPIs for which the tender preparation and/or the call for tender implementation

More information

PCP experiences in Healthcare

PCP experiences in Healthcare PCP experiences in Healthcare EPP workshop, Suzan Ikävalko 12.5.2016 Agenda 1 Decipher mhealth PCP: Lessons learned 2 Case example: Noona ehealth services for cancer patients 3 Nordic PCP & PPI experiences

More information

BroadMap Final Stakeholders Workshop

BroadMap Final Stakeholders Workshop BroadMap Final Stakeholders Workshop 6 April 2017 Website: www.broadmap.eu Pre-commercial Procurement of solutions to enable EU Interoperable Broadband for PPDR What are PCP and PPI? Marie-Christine BONNAMOUR

More information

The eafip innovation procurement Toolkit

The eafip innovation procurement Toolkit The eafip innovation procurement Toolkit Brussels, 4 th of December 2015 12/7/2015 1 The eafip-initiative The eafip initiative focuses on promotion of the benefits of innovation procurement, as well as

More information

DECIPHER PCP project Second Major EAFIP Event on Innovation Procurement Athens, 18 th 19 th October 2016 Anna Sachinopoulou, VTT Ltd.

DECIPHER PCP project Second Major EAFIP Event on Innovation Procurement Athens, 18 th 19 th October 2016 Anna Sachinopoulou, VTT Ltd. DECIPHER PCP project Second Major EAFIP Event on Innovation Procurement Athens, 18 th 19 th October 2016 Anna Sachinopoulou, VTT Ltd. http://www.decipherpcp.eu/ Public Procurer Organizations Partners Project

More information

H2020 support through PCP/PPI action instruments. Vassilis Tsanidis Start-ups and Innovation Unit (F3) DG CNECT European Commission

H2020 support through PCP/PPI action instruments. Vassilis Tsanidis Start-ups and Innovation Unit (F3) DG CNECT European Commission H2020 support through PCP/PPI action instruments Vassilis Tsanidis Start-ups and Innovation Unit (F3) DG CNECT European Commission 1 Forms of support Coordination and Support Actions (100% funding rate):

More information

Guidelines for Assessors

Guidelines for Assessors FP7 288028 Framework Programme (FP) 7 ICT -2011.5.3 Patient Guidance Service (PGS), safety and healthcare record information reuse Combination of CP & CSA Page 1 of 7 Table of Contents GUIDELINES FOR ASSESSORS...

More information

Joint Action on Health Workforce Planning and Forecasting UPDATE REPORT Working Group on European Health Workforce Brussels, November 24, 2014

Joint Action on Health Workforce Planning and Forecasting UPDATE REPORT Working Group on European Health Workforce Brussels, November 24, 2014 Joint Action on Health Workforce Planning and Forecasting UPDATE REPORT Working Group on European Health Workforce Brussels, November 24, 2014 Michel Van Hoegaerden, Programme Manager WP1 Interim report

More information

Pre-Commercial Procurement actors in ITS: feedback and guidance. Sébastien Mure, ERTICO ITS Europe Stockholm 6 th December 2012

Pre-Commercial Procurement actors in ITS: feedback and guidance. Sébastien Mure, ERTICO ITS Europe Stockholm 6 th December 2012 Pre-Commercial Procurement actors in ITS: feedback and guidance Sébastien Mure, ERTICO ITS Europe Stockholm 6 th December 2012 The Public-Private Partnership of ITS stakeholders in Europe 106 Partners

More information

Innovation Procurement main steps & pre-requisites

Innovation Procurement main steps & pre-requisites C o m m e r c i a l & L e g a l e x p e r t s I n s t r a t e g i c a l l i a n c e w i t h B a r t e l s S u e t e r s A a n b e s t e d i n g s a d v o c a t e n Innovation Procurement main steps & pre-requisites

More information

Deliverable 4.2 WP4Phase 1: evaluation report

Deliverable 4.2 WP4Phase 1: evaluation report FP7 288028 Framework Programme (FP) 7 ICT -2011.5.3 Patient Guidance Service (PGS), safety and healthcare record information reuse Combination of CP & CSA Work Package: WP4 Evaluation Deliverable 4.3 Phase

More information

COMMISSION STAFF WORKING DOCUMENT. Horizon Europe Stakeholder Consultation Synopsis Report. Accompanying the document.

COMMISSION STAFF WORKING DOCUMENT. Horizon Europe Stakeholder Consultation Synopsis Report. Accompanying the document. EUROPEAN COMMISSION Brussels, 7.6.2018 SWD(2018) 309 final COMMISSION STAFF WORKING DOCUMENT Horizon Europe Stakeholder Consultation Synopsis Report Accompanying the document Proposals for a REGULATION

More information

Joint actions 2017: Frequently Asked Questions

Joint actions 2017: Frequently Asked Questions EUROPEAN COMMISSION CONSUMERS, HEALTH, AGRICULTURE AND FOOD EXECUTIVE AGENCY Health Unit Luxembourg, 12 April 2017 Joint actions 2017: Frequently Asked Questions Frequently Asked Questions' content 1.

More information

An evaluation of the Irish Remote Interpreting Service (IRIS) Request for Tenders

An evaluation of the Irish Remote Interpreting Service (IRIS) Request for Tenders An evaluation of the Irish Remote Interpreting Service (IRIS) 2018. Request for Tenders The latest date for receipt of tenders is Thursday 30 th August 2018 at 4 pm July 2018 Sign Language Interpreting

More information

Gambling-Related Harm Minimisation in Criminal Justice Invitation to Tender

Gambling-Related Harm Minimisation in Criminal Justice Invitation to Tender Gambling-Related Harm Minimisation in Criminal Justice Invitation to Tender Responsible Gambling Trust Friday 19 th February 2016 1. About the Responsible Gambling Trust (RGT) 1.1 RGT is the leading charity

More information

The Role of Energy Service Companies (ESCOs) in Energy Performance Contracting (EPC) IEE project TRANSPARENSE

The Role of Energy Service Companies (ESCOs) in Energy Performance Contracting (EPC) IEE project TRANSPARENSE The Role of Energy Service Companies (ESCOs) in Energy Performance Contracting (EPC) IEE project TRANSPARENSE Dr. KONSTANTINOU Kostas, Director of Local Development, ANATOLIKI S.A Thessaloniki, November

More information

Webinar IMI2 Call 13 Support and coordination action for the projects of the neurodegeneration area of the Innovative Medicines Initiative

Webinar IMI2 Call 13 Support and coordination action for the projects of the neurodegeneration area of the Innovative Medicines Initiative Webinar IMI2 Call 13 Support and coordination action for the projects of the neurodegeneration area of the Innovative Medicines Initiative 27.11.2017 15:00 CET Agenda How to use GoToWebinar Catherine Brett,

More information

Procurement Strategy

Procurement Strategy Procurement Strategy Contents Introduction... 2 Objectives... 2 Our Key Procurement Principles... 3 The Procurement Process... 4 Sustainable Procurement... 5 1 P a g e Introduction Procurement is defined

More information

Horizon 2020 SME Instrument Evaluation

Horizon 2020 SME Instrument Evaluation Horizon 2020 SME Instrument Evaluation CONTENT 1. SME INSTRUMENT OVERVIEW 2. The Evaluation Process 3. Proposal Scoring 4. The SEAL OF EXCELLENCE 1. SME INSTRUMENT OVERVIEW SME INSTRUMENT OVERVIEW SME

More information

RWE Thames Water. GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final

RWE Thames Water. GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final Position RWE Thames Water Introduction: RWE Thames Water welcomes the Commission s Green

More information

Deliverable 2.7 Phase 2: Submissions evaluated

Deliverable 2.7 Phase 2: Submissions evaluated FP7 288028 Framework Programme (FP) 7 ICT -2011.5.3 Patient Guidance Service (PGS), safety and healthcare record information reuse Combination of CP & CSA Work Package: WP2 Pre-Commercial Procurement Coordination

More information

Deliverable 4.4 Phase 3: evaluation

Deliverable 4.4 Phase 3: evaluation FP7 288028 Framework Programme (FP) 7 ICT -2011.5.3 Patient Guidance Service (PGS), safety and healthcare record information reuse Combination of CP & CSA Work Package: WP4 Evaluation Deliverable 4.4 Phase

More information

EUROCITIES position on the European Commission legislative proposal on public procurement

EUROCITIES position on the European Commission legislative proposal on public procurement EUROCITIES position on the European Commission legislative proposal on public procurement EUROCITIES EUROCITIES is the political platform for major European cities towards the EU institutions. We network

More information

Procurement. Workforce Matters in Procurement Policy. Policy Review Period/Expiry. August 2017

Procurement. Workforce Matters in Procurement Policy. Policy Review Period/Expiry. August 2017 Procurement Workforce Matters in Procurement Policy Policy Manager Andy Hay Policy Group Procurement Policy Established August 2015 Policy Review Period/Expiry August 2017 Last Updated August 2015 Aims

More information

How to buy, what to buy

How to buy, what to buy the voice of the NHS in Europe consultation March 2011 How to buy, what to buy Revising the EU public procurement rules Key points The European Commission Green Paper investigates ways in which the current

More information

Athens, 08 November 2016

Athens, 08 November 2016 ΚΕΝΤΡΟ ΜΕΛΕΤΩΝ ΑΣΦΑΛΕΙΑΣ CENTER FOR SECURITY STUDIES This project has received funding from the European Union s Seventh Framework Programme for research, technological development and demonstration under

More information

Italy-Trento: Research and development services and related consultancy services 2015/S Contract notice. Services

Italy-Trento: Research and development services and related consultancy services 2015/S Contract notice. Services 1/7 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:308513-2015:text:en:html Italy-Trento: Research and development services and related consultancy services 2015/S 169-308513 Contract

More information

Main steps for preparing and conducting an innovation procurement project

Main steps for preparing and conducting an innovation procurement project Main steps for preparing and conducting an innovation procurement project SEREN3 PCP & PPI training Brussels, 1 st of February 2017 2/2/2017 1 Preparing an innovation procurement Preparing an innovation

More information

D2.5 Country Report on Recommendations for Action for Development of EPC Markets

D2.5 Country Report on Recommendations for Action for Development of EPC Markets D2.5 Country Report on Recommendations for Action for Development of EPC Markets NORWAY Transparense project This document has been conducted within the framework of project Transparense Increasing Transparency

More information

COMMENTS ON GREEN PAPER ON PPP AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS

COMMENTS ON GREEN PAPER ON PPP AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COMMENTS ON GREEN PAPER ON PPP AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS 1. General The European Dredging Association is pleased to respond to the Commission Green Paper COM(2004)327. EuDA

More information

GENERAL GUIDELINES FOR THE COOPERATION BETWEEN CEN, CENELEC AND ETSI AND THE EUROPEAN COMMISSION AND THE EUROPEAN FREE TRADE ASSOCIATION

GENERAL GUIDELINES FOR THE COOPERATION BETWEEN CEN, CENELEC AND ETSI AND THE EUROPEAN COMMISSION AND THE EUROPEAN FREE TRADE ASSOCIATION 16.4.2003 Official Journal of the European Union C 91/7 GENERAL GUIDELINES FOR THE COOPERATION BETWEEN CEN, CENELEC AND ETSI AND THE EUROPEAN COMMISSION AND THE EUROPEAN FREE TRADE ASSOCIATION 28 March

More information

Towards EMAS Action Plan

Towards EMAS Action Plan Towards EMAS Action Plan Italy Document carried out by PP 3: Sant Anna School of Advanced Studies Pisa, Italy 1 st version: December 27 th, 2018 Last version: March 8 th, 2019 1 INDEX INTRODUCTION... 3

More information

Deliverable 2.1 Environment scan (including stakeholders, scenarios, constraints and opportunities)

Deliverable 2.1 Environment scan (including stakeholders, scenarios, constraints and opportunities) Electronic Health Records for Clinical Research Deliverable 2.1 Environment scan (including stakeholders, scenarios, constraints and opportunities) Version 1.0 2 nd March 2012 Project acronym: EHR4CR Project

More information

Pillar II. Institutional Framework and Management Capacity

Pillar II. Institutional Framework and Management Capacity PILLAR II. INSTITUTIONAL FRAMEWORK AND MANAGEMENT CAPACITY Pillar II. Institutional Framework and Management Capacity Pillar II assesses how the procurement system defined by the legal and regulatory framework

More information

The Provision of North West Non-Emergency Patient Transport Services

The Provision of North West Non-Emergency Patient Transport Services The Provision of North West Non-Emergency Patient Transport Services NHS Blackpool Clinical Commissioning Group on behalf of the 33 North West Clinical Commissioning Groups Final Evaluation Report for

More information

ELANBiz: Government Procurement in Chile

ELANBiz: Government Procurement in Chile DISCLAIMER The positions expressed are those of the authors and do not necessarily reflect the official opinion of the European Union. Neither the European Union nor any person acting on behalf of the

More information

Proposal template (technical annex) SME instrument phase 1

Proposal template (technical annex) SME instrument phase 1 Proposal template (technical annex) SME instrument phase 1 The application shall provide 1) an outline of the envisaged overall innovation project, its intended scope, merits, risks and state of development

More information

HORIZON 2020 WORK PROGRAMME

HORIZON 2020 WORK PROGRAMME H. Evaluation rules Selection Criteria 1. Financial capacity: In line with the Financial Regulation No 966/2012 and the Horizon 2020 Rules for Participation Regulation No 1290/2013. For grants, coordinators

More information

A DECREE ON PROCLAMATION OF THE LAW ON CONCESSIONS AND PUBLIC PRIVATE PARTNERSHIP

A DECREE ON PROCLAMATION OF THE LAW ON CONCESSIONS AND PUBLIC PRIVATE PARTNERSHIP 20120060164 ASSEMBLY OF THE REPUBLIC OF MACEDONIA On the basis of Article 75 paragraph 1 and 2 of the Constitution of the Republic of Macedonia, the President of the Republic of Macedonia and the President

More information

Portugal-Lisbon: FC.14.ADM Provision of language training services for the EMCDDA 2015/S Contract notice.

Portugal-Lisbon: FC.14.ADM Provision of language training services for the EMCDDA 2015/S Contract notice. 1/7 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:121273-2015:text:en:html Portugal-Lisbon: FC.14.ADM.034.5.0 Provision of language training services for the EMCDDA 2015/S 068-121273

More information

C-Roads Platform Terms of Reference

C-Roads Platform Terms of Reference C-Roads Platform Terms of Reference Dissemination level: C-Roads Platform internal Author: AustriaTech Status: Final Index 1 Purpose... 3 2 Governance Structure... 4 3 C-Roads Steering... 6 3.1 Tasks and

More information

16/06/2017. Workshop : How to write a proposal. H2020 in a nustchell. Introduction. 1st phase. Pre writing

16/06/2017. Workshop : How to write a proposal. H2020 in a nustchell. Introduction. 1st phase. Pre writing H2020 in a nustchell Workshop : How to write a proposal How to write a proposal Ho Chi Minh Introduction Find a call Organise the writing calendar Build your partnershiph Pre writing 1st phase Writing

More information

MOBILITY PROGRAMME Call for Proposals 2017/2018. FBK MOBILITY4RESEARCH PROGRAMME - 2 nd Phase CALL FOR PROPOSALS 2017/2018 OVERVIEW

MOBILITY PROGRAMME Call for Proposals 2017/2018. FBK MOBILITY4RESEARCH PROGRAMME - 2 nd Phase CALL FOR PROPOSALS 2017/2018 OVERVIEW FBK MOBILITY4RESEARCH PROGRAMME - 2 nd Phase CALL FOR PROPOSALS 2017/2018 OVERVIEW The Bruno Kessler Foundation fosters the enhancement of human capital engaged in research by introducing instruments for

More information

C-Roads Platform Terms of Reference

C-Roads Platform Terms of Reference C-Roads Platform Terms of Reference Dissemination level: C-Roads Platform internal Author: AustriaTech Status: Final C-Roads Platform Coordinator AustriaTech www.austriatech.at Index 1 Purpose... 3 2 Governance

More information

REFIT Platform Opinion

REFIT Platform Opinion REFIT Platform Opinion Date of Adoption: 23/11/2017 REFIT Platform Opinion on the submissions by the Royal Norwegian Ministry of Trade, Industry and Fisheries on the 'Digital consent-based solution through

More information

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 26th May 2016 1. Purpose of this Invitation to Tender (ITT) 1.1. This invitation to tender is for appointment to a three-year framework

More information

QUESTIONS AND ANSWERS

QUESTIONS AND ANSWERS QUESTIONS AND ANSWERS INVITATION TO TENDER NO. ACER/OP/DIR/08/2013 Provision of legal, economic and technical assistance in the field of energy regulation for the Agency for the Cooperation of Energy Regulators

More information

Quantifying the impact of Pre- Commercial Procurement (PCP) in Europe based on evidence from the ICT sector

Quantifying the impact of Pre- Commercial Procurement (PCP) in Europe based on evidence from the ICT sector Quantifying the impact of Pre- Commercial Procurement (PCP) in Europe based on evidence from the ICT sector FINAL REPORT (EN) A study prepared for the European Commission DG Communications Networks, Content

More information

Specifications Invitation to tender No VT/2008/061

Specifications Invitation to tender No VT/2008/061 Specifications Invitation to tender No VT/2008/061 1. Title of the contract Establishment of a European observatory to inform the social policy debate and to provide analytical support on the social situation

More information

Study on Analysis of the Needs for Cross-Border Services and Assessment of the Organisational, Legal, Technical and Semantic Barriers SMART 2011/0074

Study on Analysis of the Needs for Cross-Border Services and Assessment of the Organisational, Legal, Technical and Semantic Barriers SMART 2011/0074 Background document introducing the Study on the Analysis of the Needs for Cross-Border Services and Assessment of the Organisational, Legal, Technical and Semantic Barriers SMART 2011/0074 1. Study Objectives

More information

MEAT Value-Based Procurement (VBP) initiative

MEAT Value-Based Procurement (VBP) initiative supported by MEAT Value-Based Procurement (VBP) initiative Interactive session with current and future pilot experimenters EVENT REPORT 26 October 2017 Brussels SUMMARY Value-based procurement can ensure

More information

Apprentices KPIs In Public Contracts. Daniel Milnes Head of Business Law Forbes 2012

Apprentices KPIs In Public Contracts. Daniel Milnes Head of Business Law Forbes 2012 Apprentices KPIs In Public Contracts Daniel Milnes Head of Business Law Forbes 2012 Legal Notice Your Attention Is Directed To This Note These materials are supplied as general illustrations of legal issues

More information

What are Pre Commercial Procurement (PCP) and Public Procurement of Innovation (PPI)?

What are Pre Commercial Procurement (PCP) and Public Procurement of Innovation (PPI)? What are Pre Commercial Procurement (PCP) and Public Procurement of Innovation (PPI)? Sara BEDIN Innovation management consultant and EU expert on Innovation Procurement The European House Ambrosetti SpA

More information

Participation and the Practice of Rights (PPR) Technical Evaluation Terms of Reference March March 2014

Participation and the Practice of Rights (PPR) Technical Evaluation Terms of Reference March March 2014 Participation and the Practice of Rights (PPR) Technical Evaluation Terms of Reference March 2012 - March 2014 Outlined below are terms of reference for an evaluation of the Participation and Practice

More information

Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017

Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017 1. Introduction: Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017 1.1 Invitation to Tender This is an invitation to submit a tender to provide services ( Services ) to meet the requirements,

More information

In the Netherlands social procurement is called social return, which is the abbreviation for social return on investment (SROI).

In the Netherlands social procurement is called social return, which is the abbreviation for social return on investment (SROI). SMEs cooperate to meet social procurement conditions Presentation http://www.useconference.com/homeuse 1 Good morning Cooperation and dialogue, those are important terms these days. Certainly when I read

More information

Belgium-Brussels: HOME/2015/ISFP/PR/DRUG/0062 Waste water analysis report on the stimulant illicit drug markets in the EU 2016/S

Belgium-Brussels: HOME/2015/ISFP/PR/DRUG/0062 Waste water analysis report on the stimulant illicit drug markets in the EU 2016/S 1 / 6 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:254272-2016:text:en:html Belgium-Brussels: HOME/2015/ISFP/PR/DRUG/0062 Waste water analysis report on the stimulant illicit drug

More information

Procurement Strategy Approved: 7 December 2016 Review Date: March 2018

Procurement Strategy Approved: 7 December 2016 Review Date: March 2018 Procurement Strategy Approved: 7 December 2016 Review Date: March 2018 If you have difficulty with sight, or if you require a translated copy of this policy, we would be pleased to provide the information

More information

Ethics & Research Integrity

Ethics & Research Integrity H2020-ITN-2016 Coordinators Day Ethics & Research Integrity Timea BALOGH Research Executive Agency Unit REA-A1 A strong Legal Basis for Ethics in H2020 Rules for Participation of Horizon 2020 (EU REGULATION

More information

Efficiency. Purpose of the Checklist. Description

Efficiency. Purpose of the Checklist. Description Efficiency Purpose of the Checklist To guide and support public procurement practitioners in reviewing, developing and updating their procurement framework, according to the 12 principles of the Recommendation

More information

ECB - Framework contract for network, WLAN, security and WDM components including services (D-Frankfurt-on-Main) 2008/S

ECB - Framework contract for network, WLAN, security and WDM components including services (D-Frankfurt-on-Main) 2008/S 1/6 ECB - Framework contract for network, WLAN, security and WDM components including services (D-Frankfurt-on-Main) 2008/S 41-056148 Contract notice Section I: Contracting authority I.1) Name, addresses

More information

GP Systems of Choice Lot 3 How to Buy Guide

GP Systems of Choice Lot 3 How to Buy Guide GP Systems of Choice Lot 3 How to Buy Guide Contents 1. Introduction 2. Disclaimer 3. Benefits of Catalogue 4. The Buying Process 5. Selection Process 6. Legal Documentation 7. Completing the Contract

More information

Question & Answers on Invitation to tender for Framework Contract 2007/S

Question & Answers on Invitation to tender for Framework Contract 2007/S Question & Answers on Invitation to tender for Framework Contract 2007/S 130-158835 Impact Assessment and Evaluation (ex-ante, intermediate and ex-post) Updated: 02/08/2007 Before submitting any written

More information

PUBLIC-PRIVATE PARTNERSHIPS TRANSPARENCY AND ACCOUNTABILITY BILL. No. 605

PUBLIC-PRIVATE PARTNERSHIPS TRANSPARENCY AND ACCOUNTABILITY BILL. No. 605 PUBLIC-PRIVATE PARTNERSHIPS BILL 1 No. 605 An Act respecting the Transparency and Accountability of Public-Private Partnerships (Assented to ) Preamble WHEREAS the residents and taxpayers of Saskatchewan

More information

Puglia Region s experience on pre-commercial-procurement

Puglia Region s experience on pre-commercial-procurement Puglia Region s experience on pre-commercial-procurement Lithuanian Academy of Sciences - Vilnius October 30, 2015 Marco Di Ciano InnovaPuglia S.p.A. Servizio Ricerca e Innovazione Policy maker governance

More information

Municipality of the District of Lunenburg POLICY

Municipality of the District of Lunenburg POLICY Municipality of the District of Lunenburg Title: Purchasing and Tendering Policy Policy No. MDL-33 Effective Date: January 1, 2014 1. Purpose and Objectives POLICY Amended Date: January 12, 2016 The Municipality

More information

Sustainable Procurement Procurement of Innovation Public Procurement Directives 2014

Sustainable Procurement Procurement of Innovation Public Procurement Directives 2014 Sustainable Procurement Procurement of Innovation Public Procurement Directives 2014 2 nd European Engineers Day Mobile Engineers Build an Innovative Europe Sofitel, Brussels, 20 November 2014 Jaroslav

More information

Public tendering and legal aspects of project business in Romania

Public tendering and legal aspects of project business in Romania Public tendering and legal aspects of project business in Romania Ligia Cecilia Popescu/Fabiola Meister Wolf Theiss Bucharest, Romania April 9, 2013 Public Procurement plays key role in new Government

More information

United Kingdom-Normanton: Medical consumables 2018/S Contract notice. Supplies

United Kingdom-Normanton: Medical consumables 2018/S Contract notice. Supplies 1 / 9 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:50479-2018:text:en:html United Kingdom-Normanton: Medical consumables 2018/S 024-050479 Contract notice Supplies Directive 2014/24/EU

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

briefing The new EU Remedies Directive: prudent procurement is of the essence Key points the voice of the NHS in Europe JANUARY 2010 ISSUE 5

briefing The new EU Remedies Directive: prudent procurement is of the essence Key points the voice of the NHS in Europe JANUARY 2010 ISSUE 5 the voice of the NHS in Europe briefing JANUARY 2010 ISSUE 5 The new EU Remedies Directive: prudent procurement is of the essence Revised EU rules will improve access suppliers have to a review when it

More information

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 9.11.2004 COM(2004) 745 final REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT ON INCENTIVES FOR EMAS REGISTERED ORGANISATIONS {SEC(2004)1375}

More information

EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS

EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS / / / 1) Motivation for this evaluation According to the founding Regulation (168/2007) of the Fundamental

More information

Voluntary Code of Business Ethics in Vietnamese Biopharmaceutical Sector

Voluntary Code of Business Ethics in Vietnamese Biopharmaceutical Sector Voluntary Code of Business Ethics in Vietnamese Biopharmaceutical Sector I/ Preamble: In September 2010 at the conference at ministerial level (Ministers of Foreign Affairs and Ministers of Trade), APEC

More information

Ref. Ares(2016) /04/2016. EU Public Procurement reform: Less bureaucracy, higher efficiency

Ref. Ares(2016) /04/2016. EU Public Procurement reform: Less bureaucracy, higher efficiency Ref. Ares(2016)1875822-20/04/2016 EU Public Procurement reform: Less bureaucracy, higher efficiency An overview of the new EU procurement and concession rules introduced on 18 April 2016 New EU public

More information

ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE PARTNERSHIP (PPP) PROJECTS IN THE APEC REGION

ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE PARTNERSHIP (PPP) PROJECTS IN THE APEC REGION Beijing, the People s Republic of China, 22 October 2014 2014 APEC Finance Ministers Meeting Joint Ministerial Statement ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE

More information

Request for Proposal (RFP)

Request for Proposal (RFP) Request for Proposal (RFP) For: Research on Higher Education institutional collaborations between Greece and the UK in the field of Trans-National Education (TNE) Date: 29 January 2017 1 Overview of the

More information

The EC e-procurement platform

The EC e-procurement platform The EC e-procurement platform Open Source World Conference Granada, 12/01/2012 Introduction Data exchange is going digital e-procurement Digital Agenda for Europe ICT-enabled benefits for EU society Action

More information

How to map excellence in research and technological development in Europe

How to map excellence in research and technological development in Europe COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 12.3.2001 SEC(2001) 434 COMMISSION STAFF WORKING PAPER How to map excellence in research and technological development in Europe TABLE OF CONTENTS 1. INTRODUCTION...

More information

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Purpose The Business Case describes and seeks approval to award the contract for the replacement of the existing Pathology

More information

Sustainable and innovative Procurement under Directives 2014/24 and 2014/25

Sustainable and innovative Procurement under Directives 2014/24 and 2014/25 Sustainable and innovative Procurement under Directives 2014/24 and 2014/25 ERF/GSV Seminar on Public Procurement An Baeyens DG for Internal Market, Industry, Entrepreneurship and SME's Unit G4 I. INTRODUCTION

More information

Building a Global Virtual Repository of E/M-Gov Knowledge Sharing KMB DPADM UNDESA

Building a Global Virtual Repository of E/M-Gov Knowledge Sharing KMB DPADM UNDESA Building a Global Virtual Repository of E/M-Gov Knowledge Sharing KMB DPADM UNDESA 6 August 2007 Table of Contents Title Page Background and rationale 3 Content Framework 1. National Policies and Strategies...4

More information

COMMISSION INTERPRETATIVE COMMUNICATION

COMMISSION INTERPRETATIVE COMMUNICATION COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 23.6.2006 COMMISSION INTERPRETATIVE COMMUNICATION on the Community law applicable to contract awards not or not fully subject to the provisions of the Public

More information

Contract notice. Services

Contract notice. Services 1 / 6 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:6023-2016:text:en:html Hungary-Budapest: Provision of interim staff services for the European Institute of Innovation and Technology

More information

Streamlining processes and increasing value for the oil and gas supply chain

Streamlining processes and increasing value for the oil and gas supply chain Streamlining processes and increasing value for the oil and gas supply chain 1 What is the Supply Chain Code of Practice? The Supply Chain Code of Practice outlines a set of best practice guidelines and

More information

Contract notice utilities

Contract notice utilities Business Opportunity Title: United Kingdom-Warrington: CHP Schemes servicing and repair and maintenance and provision of spares and consumables Document Type: Contract Notice Published By: United Utilities

More information

Pre-Commercial Procurement for Intelligent Transport Systems The P3ITS Handbook. A Guide for PCP Actors

Pre-Commercial Procurement for Intelligent Transport Systems The P3ITS Handbook. A Guide for PCP Actors Pre-Commercial Procurement for Intelligent Transport Systems The P3ITS Handbook A Guide for PCP Actors Produced by the P3ITS consortium. June 2011 1 P3ITS is a coordination action funded by the European

More information

Research and Innovation Roadmap Call for Tender Appendix I Statement of Work

Research and Innovation Roadmap Call for Tender Appendix I Statement of Work Research and Innovation Roadmap 2014-2020 Call for Tender Appendix I Statement of Work E2BA/CFT-2011/1 E2BA/CFT-2011/1 December 2, 2011 Page 1 Table of Contents 1. TECHNICAL SPECIFICATIONS... 3 1.1 Background...

More information

EU Public Sector Directive Coverage and Procedures

EU Public Sector Directive Coverage and Procedures Dr Aris Georgopoulos Assist. Professor in European and Public Law- Advocate University of Nottingham Global Governance Fellow, Robert Schuman Centre of Advanced Studies, Outline Introduction Coverage Procedures

More information

I. Objectives. Public-Private Partnerships Demonstration Program to Transform Delivery of Elderly Care Services in Yichang, Hubei (RRP PRC 50201)

I. Objectives. Public-Private Partnerships Demonstration Program to Transform Delivery of Elderly Care Services in Yichang, Hubei (RRP PRC 50201) Public-Private Partnerships Demonstration Program to Transform Delivery of Elderly Care Services in Yichang, Hubei (RRP PRC 50201) CAPACITY BUILDING COMPONENT FOR DEVELOPING AND IMPLEMENTING PUBLIC PRIVATE

More information

The Act on Public Contracts, EU state aid rules, and funding granted by Innovation Funding Agency Business Finland

The Act on Public Contracts, EU state aid rules, and funding granted by Innovation Funding Agency Business Finland Guide 1 (5) The Act on Public Contracts, EU state aid rules, and funding granted by Innovation Funding Agency Business Finland Contents 1 Scope of application of the guide 1 2 The Act on Public Contracts

More information

BUILDING CAPACITIES: THE PATHWAY TO SUSTAINABLE DEVELOPMENT

BUILDING CAPACITIES: THE PATHWAY TO SUSTAINABLE DEVELOPMENT A quarterly newsletter published by LOGMOS Logistics Processes and Motorways of the Sea Project an ENPI project funded by European Unions for TRACECA Countries - Special edition August 2013 LOGMOS Objectives

More information

Building critical mass for innovation. AERTOs Final Conference, Brussels March 28th, AERTOs Strategic Research Agendas Freek Heidekamp - TNO

Building critical mass for innovation. AERTOs Final Conference, Brussels March 28th, AERTOs Strategic Research Agendas Freek Heidekamp - TNO Building critical mass for innovation AERTOs Final Conference, Brussels March 28th, 2012 AERTOs Strategic Research Agendas Freek Heidekamp - TNO Content of the presentation 1. RTO cooperation 2. AERTOs

More information

Developing a Policy & Governance Framework for an Operational Learning Health System Discussion with the NCHICA Informatics & Analytics Roundtable

Developing a Policy & Governance Framework for an Operational Learning Health System Discussion with the NCHICA Informatics & Analytics Roundtable Developing a Policy & Governance Framework for an Operational Learning Health System Discussion with the NCHICA Informatics & Analytics Roundtable April 7, 2015 What is a Learning Health System? IOM Report

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL. IDA II Mid-Term Evaluation

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL. IDA II Mid-Term Evaluation COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 07.03.2003 COM(2003)100 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL IDA II Mid-Term Evaluation REPORT FROM THE COMMISSION

More information

Mechanism of coordinated access to Orphan Medicinal Products. MoCA. NIHDI Belgium

Mechanism of coordinated access to Orphan Medicinal Products. MoCA. NIHDI Belgium Mechanism of coordinated access to Orphan Medicinal Products MoCA dr Ri DeRidder NIHDI Belgium Context The Issue: Delays and disparities in access to OMP s Decisions on Pricing and Reimbursement exclusive

More information

Clean Power for Transport. Implementaton of Directive 2014/94/EU on the deployment of alternative fuels infrastructure

Clean Power for Transport. Implementaton of Directive 2014/94/EU on the deployment of alternative fuels infrastructure Clean Power for Implementaton of Directive 2014/94/EU on the deployment of alternative fuels infrastructure José Fernandez Garcia Brussels, 26 January 2016 The Directive on the deployment of alternative

More information

Tender Document for the Provision of services for the: Development and Testing of a Dynamic Positioning Prototype for Small Vessels

Tender Document for the Provision of services for the: Development and Testing of a Dynamic Positioning Prototype for Small Vessels Tender Document for the Provision of services for the: Development and Testing of a Dynamic Positioning Prototype for Small Vessels Employer: Super Toys Country: Greece Contents INVITATION TO TENDER...

More information