Introduction to Project Management 1Day Seminar

Size: px
Start display at page:

Download "Introduction to Project Management 1Day Seminar"

Transcription

1 LB0010 Introduction to Project Management 1Day Seminar Program Notes

2

3 This manual, its contents and layout and all its inclusions are the intellectual property of ProjectWare, and may not be reproduced in any form without the written permission of ProjectWare. The information contained in this manual and materials handed out during the course are designed for educational purposes only. Neither ProjectWare nor the course facilitators can be held accountable for the content, accuracy or technical correctness of the material. Trademarks, brands and product names are either trademarks or registered trademarks of their respective holders and are used for identification purposes only. All rights reserved - ProjectWare ABN PO Box 2064 Parkdale, VIC 3195 Phone Melbourne, Australia Rob Jeges iii

4 Overview Aims of the program This program introduces participants to the modern techniques of Project

5 Table of Contents Overview...iv Aims of the program... iv Course Objective... iv Additional resources... iv Table of Contents...v Processes and Organisation...7 Learning Objectives... 7 What is a Project?... 7 Project Management... 7 Activity The Project Constraints... 8 Project Stakeholders... 9 Advantages of Project Management... 9 Project Phases and the Project Life Cycle... 9 The Project Sequence Product Life Cycles Business Description of Each Phase Project Management Process The Project Management Functions Activities in the Initiation and Planning Phases Activities in the Execution, Control and Finalisation Phases Understanding Organisations Functional Organisation Project Organisation Matrix Organisation Organisation Structure Influences on Projects Maturity Levels Amateur Project Manager Semi-professional Project Manager Professional Project Manager Core Functions...17 Learning Objectives Scope Management Activities Methods for Selecting Projects Concept Statement Activity The Work Breakdown Structure Approaches for Developing a WBS Activity Time Management Activities Task Sequencing Types of Work Estimating Task Duration Gantt Charts Critical Path Method (CPM) Controlling Changes to the Project Schedule Project Cost Management Activities Estimating Resources Cost Estimation Tools and Techniques Monitoring and Control of the Budget Rob Jeges v

6 Table of Contents Project Integration...25 Learning Objectives Integration Management Activities The Project Plan Stakeholders Stakeholder Categories Management of Stakeholders Activity Communications Management Activities Stakeholder Communications Analysis Activity Performance Reporting Common Reporting Problems Conducting Effective Team Meetings (4P Model) Risk Management Activities Risk Identification Types of Analysis Qualitative Measures of Impact Qualitative Measures of Likelihood Qualitative Risk Analysis Matrix Activity Risk Quantification Risk Response Development Risk Response Control Support Functions...33 Learning Objectives Human Resource Management Activities Organisational Planning Organisation Breakdown Structure (OBS) Responsibility Assignment Matrix (RAM) Work Packages Project Staff Acquisition Team Development Procurement Management Activities The Procurement Management Process Statement of Work Source Selection Balanced Scorecard Model Activity Project Quality Management Activities Characteristics of a Quality Control System Improving Project Quality Project Management Maturity Model Glossary...39 Index...44 References...47 vi Rob Jeges

7 Processes and Organisation Learning Objectives On completion of this module you should be able to:!" Discuss the 4 project constraints!" Identify the major project stakeholders!" Describe the Processes and Functions of Project Management!" Differentiate between projects phases and product phases!" Describe 3 types of organisational structures!" Discuss Project Management Maturity Levels What is a Project? A project is a unique set of inter-related activities designed to achieve a common objective, with defined start and finish times. Characteristics of a project:!" Delivers a unique outcome!" Has defined start and end dates (although these can change)!" Uses multiple skilled resources, with specific skills in different disciplines!" Has a primary sponsor(s) and customer(s)!" Involves uncertainty!" Deals with conflict. This can originate internally within the project team, or externally due to conflicting objectives Project Management Projects are the means by which resources can be deployed to produce outcomes and tangible benefits. This usually involves a team of individuals faced with a common task. A project is an intense and focused activity driven by a specific outcome. Successful completion means delivering scope on time and within budget, without accountability for benefit realisation. It is important to differentiate between the direct benefit of delivering the product or service, and the business benefits that that product or service will deliver to its end users. Activity 1.1 Identify a project and determine its characteristics. This document is known as the Project Charter and is usually the first document to be produced when developing a project. At a later stage it is developed into a Concept Statement. Rob Jeges 7

8 Processes and Organisation Project name: Purpose: (A brief description of the project background and the rationale, including the problem or opportunity that the project seeks to address). Start Date: End date: Skills: (What are the main skills required to complete the project and where are these skills going to be sourced). Sponsor: (The highest project authority, and who will ultimately receive the benefits of the project). Customers: (Who are the main beneficiaries of the project). The Project Constraints Every project is constrained in different ways by its:!" Quality goals this is a combination of the scope and quality of the deliverable!" Cost goals this can be either explicit cost or implicit in the use of corporate resources!" Time goals time can be specified as a deadline for completion or be implicit as a "window of opportunity" It is the project manager's duty to balance these competing goals. It is usually possible to achieve 2 of the goals at the expense of the third goal. For instance cutting corners on scope or quality may help to meet budget and the schedule. 8 Rob Jeges

9 Processes and Organisation Project Stakeholders Stakeholders are individuals and organisations affected by the project activities and its outcome. Stakeholders include:!" Customers and suppliers!" Sponsor!" Project manager!" Steering Committee!" Performing organisation!" Opponents to the project!" Regulatory bodies Advantages of Project Management Good project management provides assurance and reduces risk. It provides the tools and environment to plan, monitor, track, and manage schedules, resources, costs, and quality. It also provides a history or metrics base for future planning as well as good documentation. Project members learn and grow by working in a cross-functional team environment. Project Phases and the Project Life Cycle A project life cycle is a collection of project phases. The phases are a natural progression of activity throughout the life of the project. Each phase is characterised by the type of activity and the skills required, such as analysis, planning and technical execution. Project phases vary by project or industry, but some general phases include:!" Concept and Scope definition!" Analysis and Business case development Rob Jeges 9

10 Processes and Organisation!" Planning and Development!" Implementation and Commissioning!" On-going Support The project life cycle is the time sequence of the project phases. The Project Sequence The natural sequence of events usually commences by the identification of needs, or statement of requirements. This answers the question "What is the problem or opportunity". The next step is to determine the best approach to resolve this problem or take advantage of the opportunity. This is the question of "What is the best solution". The third step is to decide how to implement the selected solution. At this point work can commence and the objective will be to deliver the outcome within the resource limitations. Once the project is finished, a review of the management processes will deliver valuable lessons for future projects. These should be documented. Product Life Cycles The objective of the project is to deliver a product or service. Products also have life cycles, and these should not be confused with the project life cycle. The Systems Development Life Cycle (SDLC) is a framework for describing the phases involved in developing and maintaining information systems. Typical SDLC phases include planning, analysis, design, implementation, and support. Although there are great similarities between project and product phases, it is important to make the distinction, so we can emphasise the importance of project management against the technical management 10 Rob Jeges

11 Processes and Organisation Business Description of Each Phase required to develop a product in a particular industry. Whilst the management techniques vary from industry to industry, the techniques to manage a project are common across all industries. Project Management Process Project management process include the following Phases: Initiation establishment of the project objectives and approval to proceed Planning creation of management framework and work plans Execution execution of the work plans Control adherence to objectives and correction of deviations Finalisation administrative closure of the project Note the iterative process between planning, execution and control. The Project Management Functions Knowledge areas define the key competencies that project managers must develop. Rob Jeges 11

12 Processes and Organisation Activities in the Initiation and Planning Phases There is a single activity in the definition phase, and that is the Project initiation. This is a mandatory activity to commence a project. There are mandatory (light) and discretionary (dark) activities during the planning phase. Activities in the Execution, Control and Finalisation Phases 12 Rob Jeges

13 Processes and Organisation Understanding Organisations A model of an organisation comprises four major elements: Structural dimension the structural dimension documents the formal roles and responsibilities as described in the organisational chart and job descriptions. Political dimension there is a difference between formal roles and informal authority. The political dimension relates to the informal power and influence. HR dimension the HR dimension provides a balance between needs of the organisation and needs of the team members. Symbolic dimension this dimension takes into account the Cultural values that distinguish an organisation from the others. Functional Organisation The functional organisation is aligned to the main functions of the organisation. CEO Marketing Production Sales Data Processing Marketing Staff Production Staff Sales Staff DP Staff Advantages!" Individual experts can be used across multiple projects!" Specialists can be grouped!" Provides technical continuity!" Provides promotion paths Disadvantages!" The client is not the focus of activity and concern!" Fragmented responsibility for a project!" Poor integration across divisions!" Too many layers of management Project Organisation The project organisation sees the project as the main unit of management. CEO IT Project Manager New Plant Project Acquisition Project IT Project Staff New Plant Project Staff Acquisition Project Staff Advantages!" Project manager has full line authority!" All team members are directly responsible to the project manager!" Short lines of communication Rob Jeges 13

14 Processes and Organisation!" Highly efficient in repetitive projects of similar nature!" Motivated team Disadvantages!" Duplication of effort!" Silo specialisation reduces overall skills!" Uneven adherence to company policy!" Team member alienation and concern with career after project completion Matrix Organisation The matrix organisation is a hybrid between functional organisation and project organisation. Its main characteristic is the dual accountability and lines of authority required for it to operate successfully. CEO Program Management Sales Department Production Plant IT Department New Plant Project Staff X Staff X Staff X IT System Project Staff Y Staff Y Staff Y Advantages!" Most benefits of project organisations!" Sharing of skilled resources!" Flexibility and responsiveness to client requirements!" Company policy is implemented evenly Disadvantages!" Critical balance of power!" Generates conflict between project managers for access to critical resources!" Difficult to close projects!" Violation of the principle of unity of command Organisation Structure Influences on Projects Depending on the organisational structure of the performing organisation, the project will experience different degrees of independence and authority to perform the required tasks: Project Characteristics Functional Matrix Project Project Manager's authority Little or none Low to moderate Very high Full time staff Virtually none 15-60% % Project Manager's role Part time Full time Full time Administrative staff Part time Full time Part time Maturity Levels There are 3 types of project management capabilities, corresponding with 3 levels of organisations:!" Amateur adequate for routine-based operational organisations. 14 Rob Jeges

15 Processes and Organisation!" Semi-professional sufficient for organisations in transition.!" Professional required in project-based organisations where projects are the dominant management activity. Amateur Project Manager The first level is characterised by a focus in the end result with little regard or use of project management tools and techniques. They are seen more as a hindrance than assistance. This level is best described as the "just-do it" approach. Project completion is the major success factor High incidence of project failure.!" Incomplete!" Over budget!" Missed deadlines!" Quality issues Semi-professional Project Manager At this stage project management tools and techniques are recognised and used with varied results. Some work but others are difficult to implement and the results are not always satisfactory. Follows a prescribed process Includes major project management functions.!" Scope definition!" Time Management!" Cost Management!" Project Integration Professional Project Manager At the highest level of maturity there is great flexibility and careful consideration to the management approach. The selection of tools and techniques is influenced by the needs of the project and its stakeholders, not to comply with a prescribed process. Flexible application of methodology Manages the outcome, not the process. Can shorten or skip steps to achieve a result. Focuses on what needs to be done, not on what has been done. Rob Jeges 15

16

17 Core Functions Learning Objectives On completion of this module you should be able to:!" Describe the purpose of a Concept Statement!" Understand how to develop a WBS!" Explain the different types of task dependency!" Understand Critical Path Method!" Estimate resource requirements and costs!" Describe some estimating techniques Scope Management Activities There are five activities in the scope management function. Three activities are mandatory and two activities are discretionary. Initiation decision to begin a project or project phase. Scope planning preparation of the project documentation. Scope definition subdivision of de the major project deliverables into smaller, more manageable components and document for future project decisions. Scope approval formal acceptance of the project scope by stakeholders. Scope management management and control of changes to project scope. Methods for Selecting Projects There are usually more projects than available time and resources to implement them. This requires the sponsoring organisation to select the projects that will maximise value. Selection methods include:!" Focusing on strategic needs!" Financial analysis!" Weighted scoring models Other factors include allocation of capital, organisational readiness and maximisation of shareholder value. Concept Statement After deciding what project to implement, it is important to formalise its selection. A Concept Statement is a document that formally recognises the existence of a project and provides direction on the project's objectives and management organisation. Rob Jeges 17

18 Core Functions The key project stakeholders should sign the Concept Statement, agreeing on the need and intent of the project. The Concept Statement is used to develop and confirm a common understanding of the project scope. The main elements of the document are:!" Project justification!" Brief description of the project's objective!" Summary of all project deliverables!" Main roles and responsibilities!" A statement of what determines project success Activity 2.1 Develop a Concept Statement for your current project. Estimated Budget: An approximate cost of the project, divided into the following categories: Capex: Capital expenditure, such as equipment, royalties and property. Opex: Operational expenditure. These expenses include personnel costs, leases, licence costs, maintenance and consumables. Management Reserve: Funds allocated to contingency and unforseen expenses. The project cost should be reviewed after a detail plan is completed. Objectives: The objectives of the project are the specific outcomes to satisfy the purpose of the project. The Objectives must be Specific Measurable Achievable Realistic Timely Scope and Constraints: A list of all the specific items that the pr3(i)1illy ftal-9.2(o)teli-9.2(ta Rob Jeges

19 Core Functions The Work Breakdown Structure After completing scope definition, the next step is to further define the work by breaking it into manageable pieces. Good scope definition:!" Helps improve the accuracy of time, cost, and resource estimates!" Defines a baseline for performance measurement and project control!" Aids in communicating clear work responsibilities A work Breakdown structure (WBS) is an outcome-oriented analysis of the work involved in a project that defines the total scope of the project. The WBS is a foundation document in project management because it provides the basis for planning and managing project schedules, costs, and changes. Approaches for Developing a WBS There are a number of approaches to develop a WBS. A combination of strategies is sometimes the best approach.!" Using guidelines some organisations develop guidelines for preparing a WBS.!" The analogy approach it often helps to review the WBS of similar project.!" Top-down approach start with the largest items of the project and keep breaking it down. Bottom-up approach start with the detailed tasks and roll them up. Activity 2.2 Work Breakdown Structure Develop a WBS for your current project. Phase: The first level of work subdivision Activity: Each Phase is further divided at a second level. Rob Jeges 19

20 Core Functions Task: Specific units of work that can be assigned to individual resources. Time Management Activities There are five activities in the time management function. Four activities are mandatory and one activity is discretionary. Activity definition Specification of the work and division of labour. Activity sequencing Establishing the dependencies. Duration estimation Elapsed time based on effort and resources. Schedule development Preparing a project network and determining the critical path. Schedule control Coordination of changes and updates to the schedule. Task Sequencing Task sequencing Involves reviewing tasks and determining dependencies:!" Mandatory dependencies inherent in the nature of the work. These dependencies cannot be altered.!" Discretionary dependencies defined by the project team, usually as the result of constraints and arbitrary priorities. Changing the assumptions that produce them can modify these dependencies.!" External dependencies involve relationships between project and non-project activities. Examples of external dependencies include approvals and external audits. You must determine dependencies in order to use critical path analysis. This is a technique to predict and manage the total project duration. Types of Work Work effort depends on the resources employed. There are 3 types of task: Perfectly divisible task the work can be distributed to any number of resources. The total effort remains constant, but the unit effort is inversely proportional to the number of resources, therefore the total time decreases as resources increase 20 Rob Jeges

21 Core Functions Un-divisible task the work cannot be divided, and more resources have no effect on the total time required. Complex interrelationships Division of the work requires communication and synchronisation. As the number of resources increases, a diminution of the total time is replaced by an increase of the total time required as the communication overhead increases. Estimating Task Duration The elapsed time is the total duration of the task, including unproductive time waiting for resource availability or other external event. There are two steps to determine the elapsed time or duration of a task. Firstly, the effort required to complete the task needs to be estimated. The effort divided by the amount of resources gives an indication of effective work duration. The lag time, or delays is added to this figure to arrive at the elapsed time. The effective work duration depends on the number and efficiency of the resources. A common practice is to allocate "standard productivity" resources. The plan can be revised by changing the productivity factor at a later stage. This is one of the functions of resource management. Work Effort Duration = + lag time ResourceUnits Work can be classified into different types: Discrete Effort Tasks with a specific end-result. The effort is usually proportional to the task size. Level of Effort Work that does not result in a final product, such as management and control activities. The effort is constant. Apportioned Effort Effort that by itself is not divisible into small units but is related to some other measured effort. Testing and architectural design are examples of this work. Gantt Charts Gantt charts provide a standard format for displaying project schedule information. Activities and their corresponding start and finish dates are shown in a calendar format. Dependencies are shown as connecting arrows. Rob Jeges 21

22 Core Functions The WBS structure can be implemented to assist with the maintenance of all related documents. Milestones are activities with no duration. They can have resources assigned to them, and denote significant events in the project life. Critical Path Method (CPM) The critical path for a project is the series of activities that determines the earliest time by which the project can be completed. Developing the Critical Path The critical path is the longest path through the network diagram that has no slack. There can be multiple paths with identical duration. In this case the critical path is the collection of all these equal paths. If one of more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken. On the other hand, if one or more activities in the critical path take less time to complete, then the project duration will reduce until another critical path becomes predominant. Controlling Changes to the Project Schedule Change is an inescapable reality during the life of a project. There are a number of tasks that can be performed to ensure that change is properly incorporated in the project plan.!" Perform reality checks on schedules. Peer reviews are a good way to validate assumptions.!" Allow for contingencies. These have to be explicitly addressed, not as inflated time estimates.!" Don't plan for everyone to work at 100% capacity all the time. Allow for holidays, study leave, sick leave, etc.!" Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues. Project Cost Management Activities There are four activities in the cost management function. Three activities are mandatory and one activity is discretionary. Resource planning determining what resources and quantities of them should be used. Cost estimating 22 Rob Jeges

23 Core Functions developing an estimate of the costs and resources needed to complete a project. Cost budgeting allocating the overall cost estimate to individual work items to establish a baseline for measuring performance. Cost control controlling changes to the project budget. Estimating Resources Cost and time estimates depend on:!" What resources are used!" For how long they are used!" Quantities used Resources include:!" People!" Contractors!" Facilities!" Materials!" Equipment Cost Estimation Tools and Techniques There are four main techniques to estimate costs. Each technique has its pros and cons.!" Analogous or top-down use the actual cost of a previous, similar project as the basis for the new estimate.!" Bottom-up or detailed estimate individual work items and sum them to get a total estimate.!" Parametric use project characteristics in a mathematical model to estimate costs.!" Unit rate apply unit rates to resources assigned to WBS elements. Monitoring and Control of the Budget The main tasks required to monitor costs are:!" Collect actual costs (in accrual form). The objective is to measure Capturing Actuals the performance of the project, not to produce accounting reports.!" Collect progress measures. This is a measure of how much work has been performed.!" Compare with the budget.!" Analyse and report variances and manage corrective action. Rob Jeges 23

24

25 Project Integration Learning Objectives On completion of this module you should be able to:!" Develop a project plan!" Identify the project stakeholders!" Develop a communications plan!" Run better meetings!" Identify sources of risk and areas of impact!" Develop risk treatment strategies Integration Management Activities There are three mandatory activities in the integration management function: Project plan development taking the results of other planning processes and putting them into a consistent, coherent document the project plan. Project plan execution carrying out the project plan. Overall change control coordination of changes across the entire project. The Project Plan These are the main elements of a project plan. This can be used to develop a table of contents. Description of the background and rationale for the project!" Strengths, weaknesses. Opportunities and Threats!" Economic and strategic justification Definition of the scope and objectives!" Deliverables and Milestones!" Budget!" Environment Assumptions and constraints!" Economic!" Technological!" Environmental Broad description of the strategy!" Time available!" Preliminary risk assessment!" Resource constraints!" Customer requirements!" Product constraints Rob Jeges 25

26 Project Integration!" Business constraints!" Project size and complexity Master schedule Project budget and contingency allocation Quality plan Organisational structure and resource allocation Risk plan!" Contractual matters Communications plan and stakeholder identification!" Reporting structure Change management procedures Stakeholders There are a number of people with an interest in the project. These people are known as the stakeholders. Stakeholder Categories The stakeholders will have an impact on the outcome of the project. They will have influence over the execution of the project. They will also be affected by the project; they can be supporters of the project or opponents to it. Stakeholders can be classified into a number of categories. This will help to develop strategies to manage their influence in the project.!" Members of the client organisation!" End users!" Regulatory authorities!" Members of the community!" Own organisation!" Members of the project team!" Vendors and suppliers Management of Stakeholders There are a number of key questions that can help to develop a stakeholder management plan: Who are the stakeholders of this project?!" Identification of the individuals and classification into a group What influence or impact can they have?!" What is the motivation behind a specific behaviour 26 Rob Jeges

27 Project Integration Activity 3.1 Stakeholder Analysis What is the level of impact?!" Low!" Medium!" High!" Critical Action plan to protect the project outcome Identify the stakeholders in your project and develop a stakeholder management plan. Communications Management Activities There are four discretionary activities in the communications management function. Communications planning determining the information and communications needs of the stakeholders. Information distribution making needed information available in a timely manner. Performance reporting collecting and disseminating performance information. Administrative closure generating, gathering, and disseminating information to formalise phase or project completion. Stakeholder Communications Analysis The purpose of the stakeholder communications analysis is to identify the group of people that need information about the project, and to select the best strategy to address that information need. The following elements need to be specified:!" Audience identification of the stakeholders that need to be kept informed of the activities and progress of the project.!" Information specific needs for information vary between stakeholders.!" Media choose the best media and distribution channel to satisfy the audience.!" Frequency how often does the information need to be communicated and also response to exceptional events? Activity 3.2 Prepare a communications plan for your project. Communications Plan Performance Reporting Status Report Performance reporting keeps stakeholders informed about how resources are being used to achieve project objectives. Status reports describe where the project stands at a specific point in time. Rob Jeges 27

28 Project Integration Progress reports describe what the project team has accomplished during a certain period of time. Project forecasting predicts future project status and progress based on past information and trends. Status review meetings often include performance reporting. Common Reporting Problems Too much detail puts a burden on the team and is not used upstream.!" Reduced usability!" Careless preparation Poor interface between the project report and the organisation's MIS.!" Accounting periods!" Client liaison Poor correspondence between planning and monitoring. Conducting Effective Team Meetings (4P Model) Meetings can be a very effective media to communicate wit the project team, but if not properly structure can be a waste of time and a source of frustration. Here is a simple model that can help to plan an effective meeting and to avoid the common pitfalls of ineffective meetings. Purpose!" Information sharing!" Commitment building!" Information dissemination!" Problem solving and decision making Participants!" Decision making 5!" Brainstorming 10!" Seminars 15!" Presentations unlimited Planning!" Agenda!" Time distribution and management!" Reports!" Minutes Process!" Review and introduction!" Ground rules 28 Rob Jeges

29 Project Integration!" Reports!" Participation Risk Management Activities There are six activities in the risk management function. One is mandatory and five are discretionary. Risk management planning defining the approach to be taken. Risk identification determining which risks are likely to affect a project. Risk qualification Risk quantification evaluating risks to assess the range of possible project outcomes. Risk response development taking steps to enhance opportunities and developing responses to threats. Risk response control responding to risks over the course of the project. Risk Identification Risk identification is the process of understanding what potential adverse outcomes are associated with a particular project. Several risk identification tools commonly used include checklists, flowcharts, and interviews. Types of Analysis There are three types of analysis, depending on the data available.!" Qualitative analysis uses words from a descriptive scale to describe the magnitude of potential consequences and the likelihood that those consequences will occur. This is a subjective analysis done in the absence of hard data.!" Semi-quantitative analysis arbitrary values are assigned to the descriptors. This enables arithmetic manipulation of the results.!" Quantitative analysis uses numeric values for both consequences and likelihood. The quality of the analysis depends on the quality of the data Qualitative Measures of Impact The following scale provides 5 points to classify the impact. A threepoint scale can be used to simplify the process. 1. Insignificant low financial loss. 2. Minor medium financial loss and some delays. 3. Moderate high financial loss and severe delays. 4. Major loss of production capability, uncertain schedule. 5. Catastrophic environmental impact, huge financial loss. Rob Jeges 29

30 Project Integration Qualitative Measures of Likelihood A. Almost certain it is expected to occur in most circumstances. B. Likely it will probably occur in most circumstances. C. Possible it might occur at some time. D. Unlikely it could occur at some time. E. Rare it may occur only in exceptional circumstances. Qualitative Risk Analysis Matrix Quantified risks are plotted in the grid for an overall assessment. Activity 3.3 Risk Analysis Risk Quantification Identify the major risks affecting your project. Risk quantification or risk analysis is the process of evaluating risks to assess the range of possible project outcomes. The key outcome of risk quantification is to determine the risk's probability of occurrence and its impact to the project if the risk does occur. Risk quantification techniques include expected monetary value analysis (EMV), calculation of risk factors, PERT estimations, simulations, and expert judgment. Risk Response Development There are three basic strategies to deal with risks once they have been identified and quantified:!" Risk avoidance eliminating a specific threat or risk, usually by eliminating its causes.!" Risk acceptance accepting the consequences should a risk occur.!" Risk mitigation reducing the impact of a risk event by reducing the probability of its occurrence. 30 Rob Jeges

31 Project Integration Risk Response Control Issues Log Risk response control involves executing the risk management processes and the risk management plan to respond to risk events. Risks must be monitored based on defined milestones and decisions made regarding risks and mitigation strategies. Sometimes workarounds or unplanned responses to risk events are needed when there are no contingency plans. Rob Jeges 31

32

33 Support Functions Learning Objectives On completion of this module you should be able to:!" Describe the allocation of work and the RAM!" Discuss staff acquisition and team development!" Describe the main procurement processes!" Explain the balanced scorecard method!" Discuss the project management quality activities!" Explain how to improve project quality Human Resource Management Activities There are three discretionary activities in the HR management function. Organisational planning Deciding on the best organisational structure for the project. Staff acquisition Selection and recruitment of the necessary skilled resources. Team development Ongoing management of the team and project needs. Organisational Planning Organisational planning involves identifying, documenting, and assigning project roles, responsibilities, and reporting relationships. Outputs and processes include:!" Project organisational charts (OBS)!" Work definition and assignment process!" Responsibility assignment matrix (RAM)!" Work packages!" Resource histograms Organisation Breakdown Structure (OBS) The organisational breakdown structure (OBS) defines the management structure in the project, and identifies each role. Organisation Breakdown Structure Required people and skills!" Numbers, expertise and availability Where will the people come from!" Internal availability v/s external recruitment!" Career management Project organisation structure!" Control and supervision v/s autonomy and specialisation Defined Roles and functions Rob Jeges 33

34 Support Functions Responsibility Assignment Matrix (RAM) The responsibility assignment matrix (RAM) enables to allocate tasks to the individuals identified in the OBS. Various roles can be defined, such as the main responsible, contributor or supervisor. The tasks are defined in the WBS. 34 Rob Jeges

35 Support Functions!" Storming during this phase of team development differences lead to conflict!" Conforming the third phase is characterised by conflict resolution through regulation and rule setting!" Performing the stage when the team is most productive.!" Adjourning A period of restlessness and uncertainty about the future after the project. Productivity is affected by the individual needs of the team members. Rewards and recognition Target behaviours and outcomes Allow for team and individual needs Procurement Management Activities There are six activities in the procurement management function. One activity is mandatory and four activities are discretionary. Procurement planning determining what to acquire and when. Tender planning documenting requirements and identifying potential sources Tendering obtaining quotations, bids, offers, or proposals. Source selection choosing from amongst potential vendors. Contract administration managing the relationship with the vendor. Contract closeout completion and settlement of contracts. The Procurement Management Process There are six major stages in the procurement process: Rob Jeges 35

36 Support Functions Statement of Work The Statement of Work (SOW) is the document used to communicate with the prospective vendor. Statement of Business Requirements. Provided for legal protection. Detailed User requirements and specifications. Clear and unambiguous as changes are very hard to implement after bids are received. Draft contractual arrangements. To establish legal basis of agreement. Source Selection Source selection involves the following phases:!" Evaluating tender proposals!" Choosing the best one (lowest price and risk)!" Negotiating the contract!" Awarding of the contract It is helpful to prepare formal evaluation procedures for selecting vendors. Balanced Scorecard Model A balanced scoring model provides a systematic process for selecting options based on multiple criteria:!" Identify criteria important to the selection process!" Assign weights (percentages) to each criterion so they add up to 100%!" Assign scores to each criterion for each project The higher the weighted score, the better the solution. Activity 4.1 Selection Criteria Design and apply selection criteria for a specific product. A template is available at the website. 36 Rob Jeges

37 Support Functions Project Quality Management Activities There are three discretionary activities in the quality management function. Quality planning identifying which quality standards are requires for this particular project. Quality assurance evaluating overall project performance to ensure the project will satisfy the relevant quality standards. Quality control monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality. Characteristics of a Quality Control System A quality control system should have the following characteristics in order to be effective:!" Selection of what to control!" Set of standards as a baseline!" Establish a measurement method!" Compare actuals observations with expected values!" Act to correct deviations!" Calibration of the measurement method Improving Project Quality Several suggestions for improving quality in projects include:!" Leadership that promotes quality!" Understanding the cost of quality!" Focusing on organisational influences and workplace factors that affect quality!" Following maturity models to improve quality Project Management Maturity Model 1. Ad-Hoc no defined systems and processes. Project success depends on individual effort. 2. Abbreviated there are systems in place to track cost, schedule, and scope. 3. Organised there are standardised project management processes and systems that are integrated into the rest of the organisation. 4. Managed management collects and uses detailed measures of the effectiveness of project management. 5. Adaptive feedback from the project management process enables continuous improvement. Rob Jeges 37

38

39 Glossary Activity A unit of work defined under the work breakdown structure. It is composed of one or more tasks. Actual Cost The cost actually incurred and paid for. Actual Dates The dates of task commencement and termination as the project progresses. Baseline A copy of the project schedule before the project is started used for measuring progress against the current schedule. Bottom Up Cost Estimating A method of estimating every task in the work breakdown structure and aggregating them to provide a total project cost estimate. Budget Cost The cost anticipated at the start of a project. Concept Statement Document describing the purpose of the project and strategy to perform. Configuration Management A process to define and monitor the technical specifications of the system or product being delivered by the project. Constraints Limitations such time and cost affecting the execution of the project. Contingency A reserve of resources to cater for unforseen situations. Contract An agreement between parties where an offer has been accepted and a consideration of value exchanged. Cost Overrun The amount by which the actual cost exceeds the budgeted cost. Critical Path Series of consecutive critical activities that represent the longest path through the project network. It defined the total project duration. Dependencies Relationships between tasks that determine the sequence of execution. Direct Costs Costs that can be unequivocally related to work performed. Rob Jeges 39

40 Glossary Discrete Effort Tasks that have a specific measurable end result. Duration Length of time required for the completion of a task. Effort The number of work units necessary to complete a task. Effort is usually expressed in resource days, hours or months. Elapsed Time Elapsed time is the total number of calendar periods required to complete a task. Fixed Price Contracts A generic category of contracts based on the establishment of firm legal commitments to complete the required work. At a fixed price. The vendor wears the risk. Functional Organisation An organisational structure where the company is divided into its main operating functions. Gantt Chart Time-phased graphic display of task durations and dependencies. Impact The adverse effects of an occurring risk. Indirect Cost Resource costs that are not directly identified to any specific task. Work that does not result in a direct outcome and which cannot be effectively associated with a task. Likelihood The probability that a risk will occur. Matrix Organisation An organisational structure where the Project Manager and the Functional Managers share the responsibility of assigning priorities and for directing the work. Milestones A milestone is a task with zero duration. Monitoring Analysis and reporting of project performance as compared to the plan. Organisational Breakdown Structure (OBS) A hierarchical structure defining responsible parties for each part of a project. Overall Change Control The coordination of changes across the entire project Overhead Costs incurred in the operation of a project that cannot be directly related to the individual tasks. Overload The amount of required effort that exceeds the resource limit. 40 Rob Jeges

41 Glossary Overrun An overrun is the amount of money needed to complete a project, over the budget originally authorised by management. Performing Organisation The organisational unit responsible for the performance and management of resources to accomplish the project. Phase A high level hierarchical element in the work breakdown structure. Post Implementation Review A review of the outcome between 6-12 months after a project has completed. Predecessor A task that must be completed before another specified task can begin. Process A set of interrelated work activities in which value is added to the inputs to provide specific outputs. Program Evaluation and Review Technique (PERT) PERT is a technique for estimating how much time is required for a project to complete. It is based on the probabilistic distribution of time among tasks. Progress Payments Payments made to a contractor during the life of a fixed-price type contract, on the basis of some agreed formula linked to progress. Project A set of interrelated activities directed to a common goal. Project Lifecycle The series of events, from beginning to end, necessary to perform project. Project Manager The Project Manager is the individual responsible for the day-to-day management of the project. Project Matrix An organisation structure that is project based but in which the functional structures are duplicated within the project. Project Schedule Planned start dates for tasks and milestones. Project Status Report A report on the status and any variances to spending and schedule plans. Qualitative Risk Analysis Subjective methods for assessing risk. Quality The totality of characteristics of an entity that bear on its ability to satisfy stated or implied needs. Rob Jeges 41

42 Glossary Quality Assurance (QA) The process of evaluating project processes on a regular basis to verify that they meet project quality standards. Quality Control (QC) The process of monitoring specific project outcomes to verify that they meet quality specifications. Recurring Costs Expenditures against specific tasks that occur on a repetitive basis. Relationship A logical connection between two tasks that establish their sequence of execution. Remaining Duration Time needed to complete the remaining work of a task. Request for Change A proposal to the project manager for a change to the project scope. Request for Proposal (RFP) A bid document used to request proposals from prospective vendors of products or services. Request for Quotation (RFQ) Equivalent to a Request for Proposal but with more specific pricing information. Resource An item required performing a task. Resources can be people, equipment, facilities, funding or anything else needed to perform the work of a project. Resource Assignment The work on a task relating to a specific resource. Resource Driven Task Durations Task durations that are driven by the use of scarce resources. Resource Histogram A chart where resource requirements, usage, and availability are shown on a time scale. Resource Levelling A resource scheduling process of determining scheduled dates by ensuring that resources are not over committed. Responsibility Assignment Matrix (RAM) The RAM correlates the work required by the project (WBS) with the element of the functional organisation responsible for accomplishing the assigned tasks (OBS). Risk The probability of an undesirable outcome multiplied by the impact of that outcome. Risk Avoidance Planning activities to avoid risks that have been identified. Risk Event A discrete occurrence that affects a project. 42 Rob Jeges

43 Glossary Risk Identification Determining which risk events might affect the project. Risk Matrix A matrix with risk likelihood located in rows, and with risk impact in columns. Risk Prioritising Ordering of risks according to their risk value to be considered for risk reduction, risk avoidance, and risk transfer. Risk Quantification Evaluating the likelihood and impact of risks. Scheduling Scheduling is the process of determining when project activities will take place depending on defined durations and precedent activities. Schedule constraints specify when an activity should start or end based on duration, predecessors, external predecessor relationships, resource availability, or target dates. Scope The scope is the sum of work content of a project. Slippage Slippage is the amount of slack or float time used up by the current activity due to a delayed start. If an activity without float is delayed, the entire project will slip. Sponsor A sponsor is a person or group concerned with the ultimate success of the project in terms of achieving its business objectives. Stakeholders Stakeholders are the people who have a vested interest in the outcome of the project and the manner in which it is performed. Statement of Work (SOW) A statement of requirements and description of the product or service to be procured under a contract. Successor A successor is a task whose start or finish depends on the start or finish of a predecessor task. Task A task is the smallest unit of work defined in the work breakdown structure. Tendering The process of obtaining quotes, bids or proposals. Tender Planning Identifying targets for quotes, bids or proposals. Time-Limited Resource Scheduling Scheduling of dates in which resource constraints are relaxed in order to avoid any delay in project completion. Rob Jeges 43

Project Management Framework

Project Management Framework Project Management Framework What s Project? - Why Project? What s Project Management? - Why Project Management? What s Project Management Professionals? - Why Project Management Professionals? Project

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

International Association of Certified Practicing Engineers

International Association of Certified Practicing Engineers www.iacpe.com Knowledge, Certification, Networking Page: 1 71 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International is providing the introduction to the Training Module for your

More information

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder

More information

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma, Project vs Operation PROJECTS OPERATIONS Temporary Ongoing Unique Repetitive Closes after attaining the objectives Objective is to sustain business Prototyping the new car model Assembly line production

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration Knowledge Areas According to the PMBOK edition 5 Chapter 4 - Integration 4.1 - Develop Project Charter Process Project statement of work Expert Judgment Project charter Business case Facilitation techniques

More information

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012 5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes

More information

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set4.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are

More information

Appendix. Process Inputs and Outputs

Appendix. Process Inputs and Outputs 3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the

More information

Unit 381 IT Project Management Level 3. Credit value 10. Rationale

Unit 381 IT Project Management Level 3. Credit value 10. Rationale Unit 381 IT Project Management Level 3 Credit value 10 Rationale The aim of this unit is to enable candidates to understand the business environment within which new projects are initiated. Candidates

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business Case Contract Enterprise environmental factors Project charter Expert judgement 26/02/2013 18:22:56 1 2

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Project Fundamentals Qualification Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use

More information

Software Project & Risk Management Courses Offered by The Westfall Team

Software Project & Risk Management Courses Offered by The Westfall Team Software Project & Risk Management is a 5-day course designed to provide a knowledge base and practical skills for anyone interested in implementing or improving Software Project and Risk Management techniques

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

PROJECT SCHEDULING & CONTROL

PROJECT SCHEDULING & CONTROL PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,

More information

International Diploma in Project Management. (Level 4) Course Structure & Contents

International Diploma in Project Management. (Level 4) Course Structure & Contents Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

Integration Knowledge Area

Integration Knowledge Area Integration Knowledge Area Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Initiation Group Process. Planning Group Process

Initiation Group Process. Planning Group Process Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Time Management PLANNING

Time Management PLANNING Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule

More information

Compiled by Rajan Humagai

Compiled by Rajan Humagai Compiled by Rajan Humagai www.pavementengineering.com.au Project Processes Inputs, Tools & Techniques and Outputs. (Based on PMBOK 5 th Edition) 1. Project Integration 1. Develop 1. Project Statement Of

More information

Information Technology Project Management, Seventh Edition

Information Technology Project Management, Seventh Edition Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning

More information

Construction Project Management Training Curriculum Integration Map

Construction Project Management Training Curriculum Integration Map Construction Project Management Training Curriculum Integration Map Value of the Project Management is being recognized all over the world. Most businesses manage their business by successfully implementing

More information

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500 Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500 Thierry Labriet, STS STS SA, Lausanne, Switzerland +41 21 510 11 50 office@sts.ch www.sts.ch 1 Contents 1 Foreword... 3 2 Executive

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

Guidance on project management

Guidance on project management BSI Standards Publication NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW raising standards worldwide Guidance on project management BRITISH STANDARD National foreword This British

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

Certificate IV in Project Management Student Assessment Guide

Certificate IV in Project Management Student Assessment Guide Overview The assessment for the Certificate IV in Project Management comprises Team Assignment Development of a detailed Project Management Plan for chosen case study - 30% for blended classes Individual

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

Successful Project Management. Overview Houston Community College Fall, 2017

Successful Project Management. Overview Houston Community College Fall, 2017 Successful Project Management Overview Houston Community College Fall, 2017 Agenda Introduction Project Management Processes What Is a Process? Inputs, Tools and Techniques, Outputs Process Groups Overview

More information

Project Execution Plan For

Project Execution Plan For Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended

More information

7.11b: Quality in Project Management: A Comparison of PRINCE2 Against PMBOK

7.11b: Quality in Project Management: A Comparison of PRINCE2 Against PMBOK by Peter Whitelaw, Rational Management Pty Ltd, Melbourne Introduction This comparison takes each part of the PMBOK and provides comments on what match there is with elements of the PRINCE2 method. It's

More information

Chapter 4 Project Management

Chapter 4 Project Management Chapter 4 Project Management For internal use of BSNL only Page 1 Project Management 1.0 Introduction Project management is concerned with the overall planning and co-ordination of a project from conception

More information

PMP TRAINING COURSE CONTENT

PMP TRAINING COURSE CONTENT PMP TRAINING COURSE CONTENT SECTION1: INTRODUCTION PMI, PMP AND PMBOK What is PMI, PMP, and PMBOK? What do I get out of PMP? How do I get certified? Exam qualifications and PM experience Guidelines to

More information

Information Technology Audit & Cyber Security

Information Technology Audit & Cyber Security Information Technology Audit & Cyber Security Managing Information System Projects Systems & Infrastructure Lifecycle Management Introduction Definitions INTRODUCTION Governance Roles and Responsibilities

More information

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani PRINCESS NOURA UNIVESRSITY Project BUS 302 Reem Al-Qahtani This is only for helping reading the PMBOK it has our notes for focusing on the book Project Framework What is PMBOK? o PMBOK= Project Body of

More information

What is PMP Certification exam? PMP stands for Project Management Professional certification exam. PMP, is one of the most respected and globally recognized certification is offered by the Project Management

More information

Project Management Auditing Guide

Project Management Auditing Guide Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5

More information

Unit 3: Traditional Project Delivery Using IT Applications

Unit 3: Traditional Project Delivery Using IT Applications Unit 3: Traditional Project Delivery Using IT Applications 3.1 Construction Project Process Flow i. In a typical construction project, the major key to its success hinges on how well the project process

More information

EXHIBIT 2-2-C SCHEDULES

EXHIBIT 2-2-C SCHEDULES EXHIBIT 2-2-C SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The Work specified in this section consists of furnishing transportation, labor, materials, equipment, and incidentals necessary for preparation,

More information

ActualTests.CAPM.660Questions. Certified Associate in Project Management (CAPM)

ActualTests.CAPM.660Questions. Certified Associate in Project Management (CAPM) ActualTests.CAPM.660Questions Number: CAPM Passing Score: 800 Time Limit: 120 min File Version: 4.1 http://www.gratisexam.com/ Certified Associate in Project Management (CAPM) I have corrected few questions

More information

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: )

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: ) E2-E3: MANAGEMENT CHAPTER-3 PROJECT MANAGEMENT (Date of creation: 01-04-2011) Page: 1 Project Management Introduction: Project management is concerned with the overall planning and co-ordination of a project

More information

Project+ Examination Blueprint Version June 1, 2003

Project+ Examination Blueprint Version June 1, 2003 Introduction The Project + examination is designed for business professionals involved with projects with a technology component. The examination is designed for candidates possessing at least 12 months

More information

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005 IMS1501: Unit framework IMS 1501 Studio 1: Information Systems Foundations 1 Ethics Documentation Developing Information Systems Efficiency Tools Seminar 6: Project Management Part 1 Semester 1, 2005 System

More information

PMP Exam Prep Study Group Input-Output-Tools #3a

PMP Exam Prep Study Group Input-Output-Tools #3a PMP Exam Prep Study Group Input-Output-Tools #3a Presented by Project Masters Inc. *Throughout this presentation, we reference and recognize the following trademarks, service marks, and copyrights of the

More information

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED IN LEADERSHIP AND MANAGEMENT The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

A Primer for the Project Management Process by David W. Larsen 1. Table of Contents

A Primer for the Project Management Process by David W. Larsen 1. Table of Contents A Primer for the Project Management Process by David W. Larsen 1 Table of Contents Description... 2 STAGE/STEP/TASK SUMMARY LIST... 3 Project Initiation 3 Project Control 4 Project Closure 6 Project Initiation...

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Supply chain management theory, NQF level 6, Credits 10

Supply chain management theory, NQF level 6, Credits 10 SUPPLY CHAIN MANAGER Knowledge modules 132401-001-01-00 KM-01 Supply chain theory, NQF level 6, Credits 10 132401-001-01-00 KM-02 Supply chain service delivery operational planning, NQF level 6, Credits

More information

3.1 Edition APMP Syllabus APMP

3.1 Edition APMP Syllabus APMP 3.1 Edition APMP Syllabus APMP 2 APMP 3rd Edition 3.1 Edition APMP Syllabus All of the syllabus elements should be taken within the context of a project, and project. The syllabus assumes that candidates

More information

Testkings PMP 705q. PMI PMP. Project Management Professional v5

Testkings PMP 705q.  PMI PMP. Project Management Professional v5 Testkings PMP 705q Number: PMP Passing Score: 800 Time Limit: 120 min File Version: 14.5 PMI PMP Project Management Professional v5 This is my first share of braindumps questions. Very helpful study center

More information

Definition. Name of the tool or technique Project mission statement

Definition. Name of the tool or technique Project mission statement Tools and Techniques Definitions (or by alphabetic order ; see below) A definition of each of the tools and techniques is provided below. The primary sources of definitions were the PMBOK Guide and Max

More information

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005 IMS 1501 Studio 1: Information Systems Foundations 1 Seminar 6: Project Management Part 1 Semester 1, 2005 Seminar 6.1 - Sem 1, 2005 IMS1501: Unit framework Ethics Documentation Efficiency Tools System

More information

6 PROJECT TIME MANAGEMENT

6 PROJECT TIME MANAGEMENT CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 2 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falconppm.com Agenda 9:00 10:15 Practice the PMP Questions 10:15 10:30 Break 10:30

More information

Geog 469 GIS Workshop. Project Management

Geog 469 GIS Workshop. Project Management Geog 469 GIS Workshop Project Management Outline Basic principles of project management 6.1 What is a project versus an application? 6.2 What is a scoping statement for your project? 6.3 Why are critical

More information

Project Planning & Scheduling

Project Planning & Scheduling Project Planning & Scheduling 2 Objectives To introduce and discuss key concepts and techniques for planning and scheduling major projects To provide ideas for development of a practice session to apply

More information

TenStep Project Management Process Summary

TenStep Project Management Process Summary TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize

More information

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition? 1. Which of the following is true regarding the project charter? A. The project charter is a document that formally authorize a project or phase.. B. The project charter represent a high level planning

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

Abbreviations Foreword Author s Note. PART I Key Principles, Processes and Methodologies 1. 1 Introduction to Project Management Techniques 3

Abbreviations Foreword Author s Note. PART I Key Principles, Processes and Methodologies 1. 1 Introduction to Project Management Techniques 3 Contents Abbreviations Foreword Author s Note PART I Key Principles, Processes and Methodologies 1 1 Introduction to Project Management Techniques 3 1. What is a Project? 5 2. Types of Projects 6 3. What

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

Content Break-up & Methodology for awarding Contact Hours / PDUs

Content Break-up & Methodology for awarding Contact Hours / PDUs N.I.T.E - Project Management Professional (PMP) Exam Prep Course Content Break-up & Methodology for awarding Contact Hours / PDUs This course is based on Project Management Book of Knowledge PMBOK Guide

More information

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering application abilities, and

More information

PROJECT MANAGEMENT. Quality Management (QM) Course 7 Project Management Knowledge Areas (5) Risk Management (RM)

PROJECT MANAGEMENT. Quality Management (QM) Course 7 Project Management Knowledge Areas (5) Risk Management (RM) PROJECT MANAGEMENT Course 7 Project Management Knowledge Areas (5) Quality Management (QM) Risk Management (RM) Cătălina Mancaș QM + RM Processes: Inputs Tools & Techniques Outputs Project Quality Management

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500 Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: office@sts.ch Phone:

More information

Project Time Management

Project Time Management Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis

More information

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1 Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different

More information

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES Document Status: Approving Body: Last Update: Author: Approved Information Services

More information

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2 Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 7-1 Project Resources

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

Project Management Body of Knowledge (PMBoK)

Project Management Body of Knowledge (PMBoK) Project Management Body of Knowledge (PMBoK) Knowledge & Practice Areas Project Management PMBoK Prince 2 ISO 10006 General Management Application high performance sport 2 Theory vs. Practice: A Disclaimer

More information

Project Management Professional(PMP ) Course

Project Management Professional(PMP ) Course and Program Professional(PMP ) Course CERTIFICATE: Professional (PMP ) DURATION: 4 Days COURSE DELIVERY: Classroom PDUs: 35 LANGUAGE: English With a charter to enable and enhance the industry's competency

More information

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),

More information

Project Management Knowledge Areas SECTION III

Project Management Knowledge Areas SECTION III Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

pm4dev, 2015 management for development series Project Management Glossary of Terms PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Management Glossary of Terms PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Management Glossary of Terms PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

Principles of Planning for IT Projects

Principles of Planning for IT Projects Principles of Planning for IT Projects Introduction Building Timings Exercises Meals & refreshments Mobile Phones Part 1 Setting the Scene 1. Course Objectives 2. Where projects come from 3. What is a

More information

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1 MGT/437 Project Management Session #2 University of Phoenix 02/12/2004 Brian Smithson 02/12/2004 MGT/437 #2 -- Brian Smithson 1 Agenda Review/Questions Session content PMI project framework Project Knowledge

More information

Information Systems. Rationale Aims & Objectives. Rationale Aims & Objectives. Introduction to Project management. Ruel Ellis

Information Systems. Rationale Aims & Objectives. Rationale Aims & Objectives. Introduction to Project management. Ruel Ellis Information Systems Introduction to Project management Ruel Ellis rellis@eng.uwi.tt http://www.eng.uwi.tt/depts/mech/staff/rellis/rellis.htm Rationale Aims & Objectives Rationale Even when most modern

More information

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms GLOSSARY 1. Inclusions and Exclusions This glossary includes terms that are: Unique or nearly unique to project management (e.g., project scope statement, work package, work breakdown structure, critical

More information

Time has the least. amount of flexibility; Schedule issues are the main reason for

Time has the least. amount of flexibility; Schedule issues are the main reason for PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely

More information

1 P a g e Contents About this Workbook...3 Project Management Ethics and Professional Responsibility...4 Organizational Project Management Maturity...5 The Project Management Office...7 Choosing the Right

More information

Braindumps PMP 918q. PMI PMP. Project Management Professional v5

Braindumps PMP 918q.   PMI PMP. Project Management Professional v5 Braindumps PMP 918q Number: PMP Passing Score: 800 Time Limit: 120 min File Version: 26.5 http://www.gratisexam.com/ PMI PMP Project Management Professional v5 This is my first share of braindumps questions.

More information

Identify Risks. 3. Emergent Identification: There should be provision to identify risks at any time during the project.

Identify Risks. 3. Emergent Identification: There should be provision to identify risks at any time during the project. Purpose and Objectives of the Identify Risks Process The purpose of the Identify Risks process is to identify all the knowable risks to project objectives to the maximum extent possible. This is an iterative

More information

ISO INTERNATIONAL STANDARD. Risk management Principles and guidelines. Management du risque Principes et lignes directrices

ISO INTERNATIONAL STANDARD. Risk management Principles and guidelines. Management du risque Principes et lignes directrices INTERNATIONAL STANDARD ISO 31000 First edition 2009-11-15 Risk management Principles and guidelines Management du risque Principes et lignes directrices http://mahdi.hashemitabar.com Reference number ISO

More information

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management PMP Training Training Topics Chapter 1 Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus Chapter 2 Objectives of Project Management Framework What is Project

More information

Software Engineering

Software Engineering Software Engineering Project Management 1 Objectives To explain the main tasks undertaken by project managers To introduce software project management and to describe its distinctive characteristics To

More information