SABRe Design & Development Process
|
|
- Donna Walters
- 6 years ago
- Views:
Transcription
1 SABRe Design & Development Process 2017 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for any purpose other than that for which it is supplied without the express written consent of Rolls-Royce plc. This information is given in good faith based upon the latest information available to Rolls-Royce plc, no warranty or representation is given concerning such information, which must not be taken as establishing any contractual or other commitment binding upon Rolls-Royce plc or any of its subsidiary companies.
2 Introduction & Contents 2 This brief explains the essential requirements of the Engineering change control process including major and minor changes, and how design change authority is flowed down from Rolls-Royce to the supplier. This briefing pack will explain: Engineering Change Control Purpose Engineering Change Control Scope Engineering Change Control Process Engineering Change Control PCB Process Engineering Change Control General Requirements Supplier Authorisation Process
3 Engineering Change Control - Purpose The Engineering Change Control process ensures that decisions about changing the product are made with due consideration of all relevant factors. To show how the change forms used by Rolls-Royce in the UK, US and Germany interrelate with the overall generic Engineering Change Control process. This includes the principle of Rolls-Royce Authorised Approver Process, together with the vital disciplines of design control and configuration management (i.e., no design change permitted, unless agreed by Rolls- Royce).
4 Engineering Change Control - Scope 4 The procedure covers both pre- and post- Entry Into Service (EIS) products. All suppliers operating to SABRe processes in accordance with Rolls- Royce approval and purchase order requirements. All suppliers of goods and / or services that impact upon Rolls-Royce or our customer requirements. Application for engineering change process. All changes to designs including those which affect fit, form, or function requiring Rolls-Royce engineering project action, where the change does not meet the criteria for the Design Alteration Request (DAR) process. Changes to contractual scope as a result of requirements change or clarification.
5 Engineering Change Control - Process 5 The process requires a defined baseline against which changes can be managed. The processes detailed within the following flow charts are applicable to all generic requirements related to Engineering design changes. When major design changes (as defined in appendix D of RRES90009) are proposed then one of the following forms is completed, depending on Rolls- Royce location: - Rolls-Royce UK: Design Change Process (DCP) - Rolls-Royce Deutschland : Request For Alteration (RFA) - Rolls-Royce Corporation: Definition Alteration Request (DAR) For all minor changes (as defined in appendix D of RRES90009) the DAR form is completed for all sites. All templates and guides are available on the Global Supplier Portal.
6 Engineering Change Control PCB Process 6 ESID/DDQP
7 Engineering Change Control PCB Process 7
8 Engineering Change Control 8 General Requirements For changes made in development prior to type certification, the process shall continue up to the point that the change has been incorporated into the main development programme and all impacts agreed. Rolls-Royce will not accept liability for changes to contractual scope as a result of technical requirements change or clarification, unless formally agreed through this process or through contract renegotiation. Where the supplier identifies that such a change has been requested informally, the supplier shall request the change is formalised in accordance with this process.
9 Engineering Change Control 9 PCB Process The control of change shall be applied by the use of formal Product Change Boards (PCB) that review and authorise a change package at four stages. The PCB reviews a set of prerequisite deliverables appropriate to the stage of approval. The PCB is a business-driven process, not an engineering process, and makes decisions on the basis of the business case and programme policy. This process is intended to ensure full integration of supplier activity with the Rolls-Royce Product Change Review process.
10 Engineering Change Control 10 PCB 1 PCB1 reviews a problem or improvement opportunity presented on an investigation/change request and either approves the launch of an investigation into the solution or rejects it. Approval at PCB1 authorises the exact amount of work that the task owner is expected to perform before returning for PCB2 review and approval (i.e., understanding of the issues and development of a proposed solution with preliminary costs and plans). Any work beyond that authorised above requires further PCB approval.
11 Engineering Change Control 11 PCB 2 PCB2 reviews the proposed solution concept, business case, associated costs and plans. If these are approved, PCB2 authorises the full concept definition work together with verification and validation planning, production planning and customer approval processes. Ordering of any validation hardware may also be authorised provided appropriate risk analysis and technical reviews have been done. Potential changes to key product attributes (e.g., weight, cost, component classification) may be managed using specific processes and system. PCB2 is the key business decision-making meeting in the change board process.
12 Engineering Change Control 12 PCB 3 PCB3 reviews and, if appropriate, approves the updated business case. PCB3 also reviews the complete list of engineering definitions in a change package, and all committed plans associated with it. If validation hardware is not already available, PCB3 authorises orders for such hardware required to validate the change package in the development programme on the agreed test vehicles. PCB3 will also consider approving change packages for advance release ahead of standardisation or certification. PCB 4 PCB4 ensures the final business case is satisfactory, reviews the verification and validation evidence and all other relevant aspects of the modification plans. PCB4 is the final release by the programme of a modification for production. Standardisation reports must be complete before any change package can be launched to production.
13 Engineering Change Control 13 Forms Required for PCB The site-specific forms relevant to each stage of PCB will be used as the basis of presentations to the relevant PCB. Direct supplier attendance at the review may or may not be required, dependant upon sitespecific/project requirements. The Product Change Process is intended to support the staged consideration of all business factors affecting a proposed change. As well as the technical aspects of the change, the process considers the impact of the change on such aspects as manufacturing, purchase, assembly, test, shipping, overhaul, repair, and decommissioning or disposal. The PCB decisions reflect the formal acceptance of these factors by the accountable individuals or organisations within Rolls-Royce.
14 Engineering Change Control Supplier Authorisation Process (For detailed process description see RRMS process LP ES 0-3 Manage Supplier Approvals) Purpose The following process is to be used to enable a supplier to self-approve predetermined categories of defined engineering change. Demonstrably competent individuals within the supplier organisation will be authorised by Rolls-Royce to approve the changes on behalf of the applicable Rolls-Royce technical authority. 14 Scope Design Sub-Contract and Design & Make suppliers only. Only applicable to changes that do not affect form, fit, and function as defined in appendix D of RRES90009.
15 Supplier Authorisation Process (For detailed process description see RRMS process LP ES 0-3 Manage Supplier Approvals) /ESID? ESID
SABRe Design & Development Process
SABRe Design & Development Process 2017 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for any purpose
More informationSABRe Design & Development Process
SABRe Design & Development Process 2016 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for any purpose
More informationSABRe : Supplier Problem Resolution Process. Supplier Briefing Pack. Problem Improvement Request (PIR) Rolls-Royce plc The information in this
SABRe : Supplier Problem Resolution Process.. Problem Improvement Request (PIR). 2007 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated
More informationSABRe : Inspection Processes. Supplier Briefing Pack.
SABRe : Inspection Processes. Supplier Briefing Pack. 2008 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or
More informationSABRe Briefs & Guidance
SABRe Briefs & Guidance 2015 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for any purpose other than
More informationAerospace MRO Supplier Quality Supplier Quality Assurance Requirements MRO1001. Rolls-Royce plc 2012 Page 1 of 7
Aerospace MRO Supplier Quality Supplier Quality Assurance Requirements MRO1001 Rolls-Royce plc 2012 Page 1 of 7 Table of contents 1 Purpose 2 2 SABRe Scope and Applicability 2 3 Definitions 2 4 Forms and
More informationPPAP. Supplier Hand Book. Production Product Approval Process. Version 0.1 June 2013
PPAP Production Product Approval Process Version 0.1 June 2013 Supplier Hand Book Supplier PPAP Hand Book Rolls-Royce plc 2013 This document Provides guidance on the Production Product Approval Process
More informationPPAP. Supplier Submission Preparation Guide. Production Product Approval Process. Version 1.0 April 2015
PPAP Production Product Approval Process Version 1.0 April 2015 upplier ubmission Preparation Guide upplier ubmission Preparation Guide This document Provides guidance on the Production Product Approval
More informationData is the Fuel that Powers the Service Management Capabilities for Rolls-Royce Engines
Data is the Fuel that Powers the Service Management Capabilities for Rolls-Royce Engines Rolls-Royce plc 2016 The information in this document is the property of Rolls-Royce plc and may not be copied,
More informationUsing Employee Surveys to Measure and Improve Ethics and Compliance Programme Effectiveness
Using Employee Surveys to Measure and Improve Ethics and Compliance Programme Effectiveness Jillian Swain Ethics and Compliance Officer Engineering and Technology Rolls-Royce plc 5 April 2017 2017 Rolls-Royce
More informationDeveloping Europe s nuclear supply chain
Developing Europe s nuclear supply chain Platts European Nuclear Power conference Warsaw, June 26-27 2013 Laurent PONTHIEU Executive Vice-President, Civil Nuclear 2013 Rolls-Royce plc The information in
More informationRoadmap towards autonomous ships
Roadmap towards autonomous ships Morten Skogvold TPM, Autonomous Navigation System Innovasjonskonferansen e-nav.no 2018 Oslo, 12.9.2018 2018 Rolls-Royce plc The information in this document is the property
More informationThe era of Ship Intelligence
The era of Ship Intelligence Karno Tenovuo, VP Ship Intelligence, Rolls-Royce Marine Ship Efficiency Event 2016 London, 3.11.2016 2016 Rolls-Royce plc The information in this document is the property of
More informationSABRe. FAQs Supplier Handbook. SABRe FAQs - Supplier Handbook. Last updated: 27 June 2013
SABRe SABRe FAQs - Supplier Handbook Last updated: FAQs Supplier Handbook 27 June 2013 Rolls-Royce plc 2013 Page 1 of 18 1. Purpose The purpose of the SABRe FAQs Supplier Handbook is to provide suppliers
More informationSafety Risks in an Airworthiness Organisation
Safety Risks in an Airworthiness Organisation Belinda Swain Chief Airworthiness Engineer Rolls-Royce Plc May 2016 2016 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc
More informationGlobal Supplier Code of Conduct
Global Supplier Code of Conduct Message from our Chief Executive Officer At Rolls-Royce our strategy focuses on customer, innovation and profitable growth to ensure a sustainable business. This includes
More informationRailway Industry Supplier Approval Scheme - BRIEFING NOTE
Briefing Note: BN 003 Railway Industry Supplier Approval Scheme - BRIEFING NOTE Subject: Advice to: Bogie Overhaul RISAB s Reference: Standard: RISAS/003/001 Issue: 2 Section A Clause:2 Appendix B Applies
More informationPURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "A"
PURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "A" 1. SOFTWARE QUALITY PROGRAM. This attachment establishes the software quality requirements
More informationMaking IoT / Industry 4.0 implementation a success through the alignment of culture, technology, strategy and people
Making IoT / Industry 4.0 implementation a success through the alignment of culture, technology, strategy and people Product Innovation Berlin 27 th February 2017 Heiko Witte Head of Engineering Improvement
More informationSpace Project Management
EUROPEAN COOPERATION FOR SPACE STANDARDIZATION Space Project Management Configuration Management Secretariat ESA ESTEC Requirements & Standards Division Noordwijk, The Netherlands Published by: Price:
More informationIntegrated Computational Materials Engineering from a Gas Turbine Engine Perspective
Integrated Computational Materials Engineering from a Gas Turbine Engine Perspective ICME Workforce Development Tutorial & Panel Session AIAA SciTech 2016 San Diego, CA Dr. John F. Matlik Rolls-Royce Corporation
More informationCODE: FD10 Rev: A Date: 9/24/2008 CONFIGURATION MANAGEMENT
1.0 Definition of terms: CONFIGURATION MANAGEMENT 1.01 The term shall, will and may are used with specific intent thought-out these documents and will observe the following rules: 1.1 Requirements defined
More informationThe Intelligent Factory: How IoT is optimising operations across the value chain
The Intelligent Factory: How IoT is optimising operations across the value chain Internet of Manufacturing Munich 7 th February 2017 Heiko Witte Head of Engineering Improvement & Quality 2017 Rolls-Royce
More informationGlobal Supplier Code of Conduct
Global Supplier Code of Conduct Message from our Chief Executive Officer At Rolls-Royce our strategy focuses on customer, innovation and profitable growth to ensure a sustainable business. This includes
More informationPURCHASING QUALITY NOTES
0001 Documented approval scopes issued by VerTechs Enterprises, Inc. Quality are adhered to at all times. When issued, the supplier shall maintain these documents for reference when servicing VerTechs
More informationWaste Acceptance Procedure. Waste Forecasting Guide
Waste Acceptance Procedure September 2013 Page 2 of 12 Contents 1. Introduction... 3 1.1. Waste Acceptance Procedure... 3 1.2. Process Guide... 4 1.3. Help and Support... 4 2. Waste Forecasting Process...
More informationRolls-Royce plc PO Box 31, Derby, DE24 8BJ, England Telephone: +44 (0)
Rolls-Royce plc PO Box 31, Derby, DE24 8BJ, England Telephone: +44 (0) 1332 242424 www.rolls-royce.com NOTICE TO SUPPLIERS NUMBER 162 ISSUE 001 ORIGINATOR Nat Russhard Direct Dial: +44 (0) 1332 240209
More informationExternal Providers Quality Requirements.
External Providers Quality Requirements. 1. General Requirements. 1.1 Introduction. This document establishes the quality assurance requirements for external providers of process, product and service pursuant
More informationI-SEM Programme Project Office Programme Change Control Procedure
Project Office Programme Change Control Procedure Version: 1.1 FINAL Date: 8 March 2017 Document Control Production Authors Responsibility Date Jim McAllister I-SEM PMO 01/07/2015 Helen Mounsey I-SEM PMO
More informationECB-UNRESTRICTED T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK
T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK Status: Baseline TABLE OF CONTENTS 1 INTRODUCTION... 1 2 CHANGE MANAGEMENT... 3 2.1 CHANGE MANAGEMENT FOR COMMON AND SPECIFIC CHANGE... 3 2.2 PRINCIPLES...
More informationBetter power for a changing world
Better power for a changing world Taieb Ben Sghaier Customer Strategy & Marketing 11 November 2015 2015 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be
More informationQuality Management System. Manual MASTER COPY
Quality Management System Manual MASTER COPY Revisions: Date Summary Rev. July 2010 14 Oct 2010 28 Jan 2011 9 Feb 2011 9 June 2011 6 March 2012 11 July 2013 13 July 2017 Initial Draft Issued Minor changes
More informationCertifiable Production Code Development
Certifiable Production Code Development David Owens Rolls-Royce Control Systems 2017 Rolls-Royce plc and/or its subsidiaries The information in this document is the property of Rolls-Royce plc and/or its
More informationOperating Margins Report July 2016
Operating Margins Report July 2016 Introduction In accordance with Special Condition 8C, this document provides an overview of our procurement activities used to secure our Gas Operating Margins (Gas OM)
More informationSUPPLIER WEBEX Resource Efficiency: Finding waste reduction opportunities
SUPPLIER WEBEX Resource Efficiency: Finding waste reduction opportunities Nigel Marsh Global Head of Environment Matthew Payne Environment Manager 2016 Rolls-Royce plc and/or its subsidiaries The information
More informationCASS TOES FOR FUNCTIONAL SAFETY MANAGEMENT ASSESSMENT (IEC : 2010)
CASS S FOR FUNCTIONAL SAFETY MANAGEMENT ASSESSMENT (IEC 61508-1: 2010) For general guidance on using CASS conformity assessment documents, refer to: Guidance for assessors on using the CASS s available
More informationMeasurement System Analysis. Version 3.1 August How-to Guide - Workbook
Measurement System Analysis Version 3.1 August 2013 How-to Guide - Workbook MSA How-to Guide 2013 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied
More informationSMR Staffing Solutions: Human Factors Integration
SMR Staffing Solutions: Human Factors Integration IAEA TM 55245: Challenges in the Application of the Design Safety Requirements for Nuclear Power Plants to Small and Medium Sized s Alison Flower CEng,
More informationManaging Data From POMS/ CMIS
Managing Data From POMS/ CMIS Rolls-Royce - Nuclear Engineering Services Presented by: Rob Littles Director of Obsolescence 2016 Rolls-Royce plc The information in this document is the property of Rolls-Royce
More informationOsprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -
February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February
More informationBetter power for a changing world
Better power for a changing world Powering a greener footprint through innovation Jim Payton V.P. Customer Business, Rolls-Royce, Asia 2015 Rolls-Royce plc and/or its subsidiaries The information in this
More informationQUALITY ASSURANCE REQUIREMENTS
SPACE AT MUCKLENEUK CAMPUS PRETORIA QUALITY ASSURANCE REQUIREMENTS SPACE AT MUCKLENEUK CAMPUS, PRETORIA Page 1 1.1 QUALITY ASSURANCE REQUIREMENTS In undertaking the works (including all incidental services
More informationAPPENDIX C Configuration Change Management Verification and Validation Procedures
DCMA-INST 217 APPENDIX C Configuration Change Management Verification and Validation Procedures Table of Contents C1. Introduction... C-1 C2. Implementation... C-1 C3. Pre-Inspection: Verification... C-1
More informationPROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT
PDG PROJECT DESIGN A00.1 GUIDES PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT Project Name: Name Project No.: Number Date: Date Document No.: PDG-PDG-PRO-A00.1 Date Created: 30 th Mar
More informationESCC NON-CONFORMANCE CONTROL SYSTEM. ESCC Basic Specification No
Page 1 of 16 ESCC NON-CONFORMANCE CONTROL SYSTEM ESCC Basic Specification Issue 2 January 2014 Document Custodian: European Space Agency see https://escies.org PAGE 2 LEGAL DISCLAIMER AND COPYRIGHT European
More informationBrochure IMS Brochure. Integrated Management System (IMS) of the ILF Group
Brochure IMS Brochure Integrated Management System (IMS) of the ILF Group FOREWORD ILF Consulting Engineers always endeavours to precisely analyse the requests and needs of its clients and to subsequently
More informationTechnology Progression of Maritime Autonomous Surface Ships
MSC 100 One hundred sessions enhancing safety and security of international shipping Technology Progression of Maritime Autonomous Surface Ships Kevin Daffey Director Ship Intelligence, Engineering & Technology
More informationThermal Commissioning Guidance
Thermal Commissioning Guidance 80% of Installed Capacity Operational Condition Precedent 2.1 (B) Version 2.0 Issued on 21 November 2017 Applicable to Investment Contracts, CFD Agreement and CFD Standard
More informationInvitation to Tender. Development Legal Services. August 2015
Development Legal Services August Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 5 1.5. Copyright...
More informationThis part of the Works Information sets out the obligations of the Contractor with regards to:
Works Information Volume 2B Part 13 Assurance, Records and Certification Part 13 Assurance, Records and Certification 13.1 Introduction The Contractor self-certifies the quality of the works. This part
More informationGENERIC QUALITY ASSURANCE REQUIREMENTS FOR: BUILT TO PRINT ITEMS, ITEMS TO STANDARD AND OFF THE SHELF ITEMS
GENERIC QUALITY ASSURANCE REQUIREMENTS FOR: BUILT TO PRINT ITEMS, ITEMS TO STANDARD AND OFF THE SHELF ITEMS APPLICABLE FOR: AIRBUS DEFENCE AND SPACE - SPACE BUSINESS UNIT ORBITAL ISSUE: 02c RELEASE DATE:
More informationGARDNER AEROSPACE SUPPLIER QUALITY REQUIREMENTS MANUAL
GARDNER AEROSPACE SUPPLIER QUALITY REQUIREMENTS MANUAL Issue Number: 2 Issue Date: 12/8/15 1 of 19 Contents Revision Summary... 4 1.0 Introduction... 5 2.0 Supplier Quality System Requirements... 6 3.0
More informationINS QA Programme Requirements
Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued
More informationAttachment D: Cost Proposal, RFP Section 3.4
ATTACHMENT D: COST PROPOSAL, RFP SECTION 3.4 Instructions: Use this template to comply with Section 3.4, Cost Proposal. Because the requirements of this RFP are part of a portfolio of projects designed
More informationQUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A
Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production
More informationPurchase Order Quality Clause SCC20 Revision E, Effective 1/20/2015
Clause A - Quality System Requirements All references to the term Government in any of the documents referenced below shall be replaced with the term Curtiss-Wright and/or the Government. All references
More informationCasework Technical Support (Social Welfare - Project Management)
Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend
More informationAS9003A QUALITY MANUAL
Your Logo AS9003A QUALITY MANUAL Origination Date: (month/year) Document Identifier: Date: Document Status: Document Link: AS9003A Quality Manual Latest Revision Date Draft, Redline, Released, Obsolete
More informationTemperature Measurement for Better Processes to Create Better Products and Services
Temperature Measurement for Better Processes to Create Better Products and Services The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third
More informationAM GENERAL SUPPLIER RELIABILITY ASSURANCE REQUIREMENTS
Introduction 1.0 Reliability Assurance Requirements 1.1 Reliability Program 2.0 Reliability Development Program 2.1 Reliability Development Program Plan 2.1.1 Reliability Performance Level 2.1.2 Reliability
More informationGeneral user conditions for supplier s applications and the AUMA supplier portal
Page 1 of 7 General user conditions for supplier s applications and the AUMA supplier portal AUMA Riester GmbH & Co. KG ( AUMA, we, us or our ) is continuously interested in finding national as well as
More informationOracle Hospitality Cruise Shipboard Property Management System Maintenance User Guide Release 8.0 E
Oracle Hospitality Cruise Shipboard Property Management System Maintenance User Guide Release 8.0 E84864-01 November 2017 Copyright 1995, 2017, Oracle and/or its affiliates. All rights reserved. This software
More informationTASK REQUIREMENTS. Supplier Quality Requirements
This document is applicable only to suppliers of Production Items as defined below and their subtier suppliers. Non-Production Item suppliers are not subject to this document. This document specifies the
More informationRSC-G-009D-Annex1 (SP) Checklist for evaluation of a Project Safety Plan
RSC-G-009D-Annex1 (SP) Checklist for evaluation of a Project Safety Plan Prepared by: Maik Wuttke 22.02.2012 Reviewed by: Mary Molloy 22.02.2012 1 Introduction This checklist will be employed by the RSC
More informationSUPPLIER QUALITY PROGRAM Procurement Standard
SUPPLIER QUALITY PROGRAM Procurement Standard Revision: E Notice: This standard is subject to periodic review and may be revised at any time; users are cautioned to obtain the latest revision. 1.0 Purpose:
More informationDocument Rev: 18 State: RELEASED see Smarteam for approval authorities TASK REQUIREMENTS. Supplier Quality Requirements
Document 0000000000000045 Rev: State: RELEASED see Smarteam for approval authorities This document is applicable only to suppliers of Production Items as defined below and their sub-tier suppliers. Non-
More informationInvitation for Bid - Standard Office Furniture / Task Chair
Invitation for Bid - Bid#2016-09-001 Instructions to Bidders 1. General Information Rice University is issuing this Invitation for Bid (IFB) for the procurement of goods and/or trade services as described
More informationProject Engineering Support for the Site Construction Preparation and Coordination Activities. Technical Specification
Project Engineering Support for the Site Construction Preparation and Coordination Activities Technical Specification Page 1 of 8 Table of Contents 1. SCOPE OF WORK...3 2. ESTIMATED DURATION...3 3. WORK
More informationQnx Standard Support Plan User s Guide. Version 3.1
Qnx Standard Support Plan User s Guide Version 3.1 Contents Introduction......................................2 The Standard Support Plan..........................2 Qnx support plans at a glance.....................3
More information1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General
1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General The organization s management with executive The commitment and involvement of the responsibility shall define, document
More informationVol. 2 Management RFP No. QTA0015THA A2-2
Manufacturing and Assembly: All MetTel manufacturing and assembly activities are focused on the reduction of supply chain risk. MetTel s SCRM Plan and the associated Systems Acquisition (SA) controls for
More informationBRC Storage and Distribution Quality and Safety Management System Implementation Workbook
We have written this workbook to assist in the implementation of your BRC quality & safety management system. The workbook is divided into 8 steps that are designed to assist you in implementing your quality
More informationProduction Part Approval Process (PPAP)
Document ID: QN-M04 Page 1 of 13 Aerojet Rocketdyne Quality Note M04 Date: 03/16/2016 Table of Contents 1. PURPOSE... 2 2. APPLICATION... 2 2.1. Resubmissions... 2 2.2. Applicable Documents... 3 3. CONVENTIONS...
More informationPercival Aviation Limited 15 Barnes Wallis Road, Segensworth, Hampshire, PO15 5TT, UK Tel: + 44 (0)
TABLE OF CONTENTS INTRODUCTION... 4 1. Purpose... 4 2. Scope... 4 3. References... 4 4 Terminology and Definitions... 5 4.1.1 Subcontractor... 5 4.1.2 Significant Subcontractor... 5 4.1.3 Manufacturers...
More informationYOUR TRANSPORTATION CO.
For fast dependable Transportation Services YOUR TRANSPORTATION CO. Compliments of Marc T. Smith CAYMAN SYSTEMS INTERNATIONAL Specializing in Small & Medium Business Compliance Help e-mail to:cayman@qs9000.com
More informationAffinity Water Limited New Supplies
1 of 13 Affinity Water Limited New Supplies Policy and Company Specific Requirements for Water Mains and Service Pipes Constructed by Self-Lay Organisations 2 of 13 CONTENTS 1 Introduction 3 1.1 General
More informationSupplier Quality Requirements Document (SQRD)
Supplier Quality Requirements Document (SQRD) D127135 Rev. AE Supplier Quality Requirements Document Page 2 of 8 1.0 SCOPE This document applies to all worldwide production suppliers of Coherent, Inc.
More informationANCHOR ISO9001:2008 RPR-007 MARINE SERVICES ADDITIONAL PROCEDURE PRODUCT REALISATION
PRODUCT REALISATION Document Control Revision History PAGE REASON FOR CHANGE REV. REVIEWER / AUTHORISED BY: RELEASE DATE: ALL NEW DOCUMENT A J.BENTINK 5/08/2016 Revision Approval: J.BENTINK Signature:
More informationCONTRACT CONDITIONS, TECHNICAL, STANDARD FOR
CONTRACT CONDITIONS, TECHNICAL, STANDARD FOR SUBTITLE : PART 4: PRODUCTION PROGRAMMES SUMMARY : ARMSCOR S TECHNICAL CONTRACT REQUIREMENTS FOR PRODUCTION PROGRAMMES. KEY WORDS : TECHNICAL CONTRACT CONDITIONS,
More informationIntegrated Power Solutions Modular and cost-effective power plant design
Integrated Power Solutions Modular and cost-effective power plant design Rolls-Royce modular concept The concept boosts productivity and operating economics Generating set Engine + generator + baseplate
More informationServicing of drilling-rig BOPs
Subsurface INVESTMENT OPPORTUNITY: Servicing of drilling-rig BOPs Executive summary There is potential to have a local facility (operated by a local or international company) carry out periodic maintenance
More informationSupplier Requirements Manual
ABACO-EQP-001 REV A Supplier Requirements Manual (European Edition) : Approved By Department Signatory Martin Edwards Quality A 13 TH Sep 2017 Martin Edwards Peter Rhodes Purchasing A 13 TH Sep 2017 Peter
More informationInvitation to Tender. External Audit Services. July 2015
External Audit Services July Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 4 1.5. Copyright...
More informationLONG TERM AGREEMENT NO. ( LTA ) dated
LONG TERM AGREEMENT NO. ( LTA ) dated This LTA by and between Sikorsky Aircraft Corporation, a Delaware Corporation having an office and place of business in Stratford, CT ("Buyer") and a Corporation having
More informationPURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe
Page 1 of 12 DOCUMENT TITLE Supplier Quality Assurance Manual PURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe REVISION HISTORY Revision Change
More informationTITLE: SQR-001 Supplier Quality Requirements
Page: Page 1 of 8 TITLE: SQR-001 Supplier Quality Requirements Page: Page 2 of 8 Contents REVISION HISTORY... 3 REFERENCED QUALITY DOCUMENTS... 3 DOCUMENT DETAILS... 3 1. PURPOSE OF DOCUMENT... 4 2. DOCUMENT
More informationCONFIGURATION MANAGEMENT PLAN TEMPLATE
CONFIGURATION MANAGEMENT PLAN TEMPLATE This template helps you to create a Configuration Management (CM) Plan that allows a formal structure to describe how configuration management will be managed to
More information3. OBJECTIVES AND PRIORITIES:
3. OBJECTIVES AND PRIORITIES: 3.1. Priorities related to bridging missing links, removing bottlenecks, enhancing rail interoperability, and, in particular, improving cross-border sections 3.1.4. European
More informationIBM Integrated Product Development (IPD)
IBM Integrated Product Development (IPD) Project Executive: Bijan Salimi 09/14/11 Agenda What is IPD and its objectives? IPD Teams Hierarchy IPD Phases Teams Roles & Responsibilities Decision Checkpoints
More informationCertificate of Acceptance
Specific Conditions The following Conditions are specific to the approved product/s contained within this Certificate. These conditions must be adhered to in addition to the Network Rail General Conditions
More informationDesign Management Plan
Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.
More informationSpace product assurance
ECSS-Q-ST-10C Space product assurance Product assurance management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of
More informationSpecifications. Level 1 Essential Energy Works for the Warialda Truck Wash
Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification
More informationMarine Nuclear Propulsion
Marine Nuclear Propulsion Presentation to KIVI-NNS Symposium 3/11/17 Aidan Goldsworth Chief Engineer Capability and Sustainment The information in this document is the property of Rolls-Royce plc and may
More informationMBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar
MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar L2 Project Scope Management www.notes638.wordpress.com Project Scope Management Scope initiation/planning Scope definition Issue
More informationService Level Agreement For Interconnect Paths
Service Level Agreement For Interconnect Paths 21/06/17 Version 3.0 - Final 1 Version Control Version Status Update Effective Date 2.7 Document rebranded to open eir 16 th September 2015 V3.0 Final This
More informationCOSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management
Manage project completion and handover in built environment design Overview This unit applies to designers who are engaged in projects at site level at the handover stage and who are responsible for completing
More informationRSUD Quality Clause List
1 of 14 Signatures & Approval Name Signature Date Prepared by : Approved by : Scotty CALDWELL Senior Quality Engineer RSU Randy DARLING Quality Manager RSU RESTRICTIONS ON USE AND DISTRIBUTION This document
More informationNATO STANDARD AQAP-2110 NATO QUALITY ASSURANCE REQUIREMENTS FOR DESIGN, DEVELOPMENT AND PRODUCTION
NATO STANDARD AQAP-2110 NATO QUALITY ASSURANCE REQUIREMENTS FOR DESIGN, DEVELOPMENT AND PRODUCTION Edition D Version 1 JUNE 2016 NORTH ATLANTIC TREATY ORGANIZATION ALLIED QUALITY ASSURANCE PUBLICATION
More information