1 NHA s Operational Excellence (OpEx) Program Program Information & Safety Reports Summary Visit: Northwest Hydroelectric Association Meeting October 30, 2014
2 OpEx Introduction OpEx is: NHA program and member benefit with a new website hydroexcellence.org A voluntary event reporting system that receives, distributes, archives, and catalogs operating experiences and any resulting best practices and lessons learned. The only Event Reporting program and database available to the hydro industry A clearinghouse of all hydro related information event reports, best practices, lessons learned, and technical information OpEx Scope & Focus: Event Reports, Best Practices, and Lessons Learned in four functional areas: Safety Dam, Employee, and Public Operations Maintenance Environmental Performance OpEx is not policy, legislative, or regulatory in nature
3 OpEx Purpose A foundational goal of OpEx is to prevent a defining event in the hydropower industry. The secondary benefits of this goal results in improved safety, strict environmental performance, and reduced O&M costs and unplanned outages. Sayano Shushenskaya Hydro Plant August 17, 2009 Failure South Fork Dam Catastrophic Failure Johnstown, PA Flood May 31, 1889 Watts Bar Hydro Plant Fire September 27, 2002
4 Benefits of OpEx Participation Tool for managing aging assets Educational resource for training a workforce in transition Forum for learning and collaborating with fellow industry members: Best Practices Lessons Learned Event Reports Avoiding similar events experienced by others employee injuries, forced outages, and others Saving limited financial resources NHA Member benefit
5 Results To Date Overview Achievements to Date 38 Event Reports from: 14 Utilities including 8 reports from the Federal sector, 1 from an equipment supplier Sample Reports Loose Generator Rotor Pole Wedges Lower Turbine Shrink Ring Crack Turbine Discharge Ring Repair Penstock Hydraulic Valve Seal Failure n = Equipment Maintenance Environmental Event Reports By Functional Area 4 1 These Event Reports contain: 115 Corrective Actions 60 Lessons Learned 48 Recommendations 7 13 Operations Safety Procedure Adherence Over 35 member companies are participating in OpEx
6 Public Landing Page Web Address:
7 OpEx Main Page
8 Best Practices
9 Resources
10 Results To Date Safety Specific Safety Event Report Received & Titles 1. Drill Press Injuries 2. Carbon Monoxide Near Miss 3. Near Miss Incorrect Prints for 480V Feeder 4. Injury Working on Fire Water Pump 5. Gantry Crane Movement 6. Work performed outside of clearance limits 7. Control Room Fire Part 1 Description of Event Two employees were working on a Fire Protection Service Water Pump. One employee was holding a flashlight while the other employee was attempting to remove the old bearing race with a hammer and punch. The employee holding the flashlight received a fragment of metal into the forearm. Immediate Actions: Work was stopped Notified Site Management The employee was treated and return to work with no restrictions Conducted a safety stand down with personnel 10
11 Results To Date Safety Specific Part II Cause Analysis On site investigation and interviews: Improper tool use. Part III Corrective Action Plan Ongoing Actions: Develop a Job Safety Analysis to be utilized while performing maintenance on the Fire pump Develop a detailed work package for removal of pump rotating element The fire protection pump is a critical component. Procure and maintain a pump rotating element as a critical spare. Part IV Lessons Learned & Recommendations The pump element should have been removed from the pump casing and a bearing puller used to remove the old bearing. Use brass when removing case hardened pump components. 11
12 Conclusion & Next Steps Register at: hydroexcellence.org As the industry contends with aging assets and an aging workforce, OpEx and the event reporting system will provide a trusted and reliable database of historical and current operational issues and serve as an educational and training resource for future personnel.
13 OpEx Contact Information Further Information Contact: David Zayas National Hydro Association Phone: ext. 20 e mail: david@hydro.org Jim Miller Signal Hydropower Consultants, LLC Phone: e mail: ljmiller sec@epbfi.com Thank you 13
Power plant Asset. Thermal power Hydro power Geothermal power. QuestIntegrity.com CHALLENGE CONVENTION
Power plant Asset Integrity Management Thermal power Hydro power Geothermal power QuestIntegrity.com CHALLENGE CONVENTION Effective Asset Integrity Management in Power Plants Effective asset integrity
More informationRock Island Powerhouse 2 Rehabilitation. Board Presentation. November 20, 2017
Rock Island Powerhouse 2 Rehabilitation Board Presentation November 20, 2017 Objectives Present recommendation for scope, schedule and budget for Rock Island Powerhouse 2 (RI PH2) Rehabilitation program
More informationNational Hydropower Association Operational Excellence Event Report. Environmental
1) Submitting Organization: Redacted 2) Name of Preparer, Phone & Email: Redacted 3) Report Number (OE Internal Use): To Be Supplied Later 4) Date & Time of Event: 5) Duration of Event: 6) Functional Area:
More informationCHAPTER - 6 BEST PRACTICES IN OPERATION & MAINTENANCE OF HYDRO POWER STATIONS
CHAPTER - 6 BEST PRACTICES IN OPERATION & MAINTENANCE OF HYDRO POWER STATIONS Operation and Maintenance of hydro power stations must aim at reducing failure rate by ensuring smooth operational levels of
More informationPriest Rapids Turbine Upgrade Project. May 26 th, 2015
Priest Rapids Turbine Upgrade Project May 26 th, 2015 1 Agenda Project Update Change Order #1 Schedule & Next Steps 2 PROJECT UPDATE 3 Project Update Scope of Work 4 Project Update Major Components Contract
More informationSMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016
SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples
More informationDEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-E Washington, DC Engineering and Design HYDROELECTRIC DESIGN CENTER
DEPARTMENT OF THE ARMY ER 1110-2-109 U.S. Army Corps of Engineers CECW-E Washington, DC 20314-1000 Regulation No. 1110-2-109 1 November 2001 Engineering and Design HYDROELECTRIC DESIGN CENTER 1. Purpose.
More informationGLENFIELD DAMS, RESERVOIRS AND HYDROPOWER DAMS, RESERVOIRS AND HYDROPOWER VALVE SOLUTIONS DAMS, RESERVOIRS AND HYDROPOWER SOLUTIONS 1
GLENFIELD DAMS, RESERVOIRS AND HYDROPOWER DAMS, RESERVOIRS AND HYDROPOWER VALVE SOLUTIONS DAMS, RESERVOIRS AND HYDROPOWER SOLUTIONS 1 2 DAMS, RESERVOIRS AND HYDROPOWER SOLUTIONS DAMS, RESERVOIRS & HYDROPOWER
More informationSteam Turbines-Generators and Auxiliary Systems - Program 65
Steam Turbines-Generators and Auxiliary Systems - Program 65 Program Description Program Overview Up to 70% of outages planned for steam power plants involve work on the turbines. Power producers continually
More informationTypes of Hydropower Facilities
Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River
More informationOptimising hydropower plant performance with digital technology
Optimising hydropower plant performance with digital technology As the world searches for more sustainable energy sources, hydropower is currently leading the field, supplying 71% of all renewable electricity
More informationFERC DAM SAFETY PROGRAM
National Hydropower Association Hydraulic Power Committee April 28, 2010 Meeting Washington, DC FERC DAM SAFETY PROGRAM FERC Presenters Daniel J. Mahoney, Director William H. Allerton, Deputy Director
More informationJohn Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55
John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationHyCon MD Monitoring, Analysis and Diagnosis
HyCon MD Monitoring, Analysis and Diagnosis The Voith HyCon MD Monitoring, Analysis and Diagnosis system combines our engineering and manufacturing expertise with your operational experience and knowledge
More informationDesign and Construction of a Mini Hydro Turbine Model
American Journal of Modern Energy 2018; 4(1): 1-6 http://www.sciencepublishinggroup.com/j/ajme doi: 10.11648/j.ajme.20180401.11 ISSN: 2575-3908 (Print); ISSN: 2575-3797 (Online) Design and Construction
More informationHow to Maximize the Return on Investment. Monitoring and Inspection of Mechanical Systems by Using Infrared Thermography
According to the recent developments in both theory and practice, the maintenance concept is no longer simply considered as a set of activities for preserving assets or preventing failures, but it has
More informationRisk Mitigation in Gas Natural Fenosa Power Generation. Sevilla, 14 th June 2013
1 Risk Mitigation in Gas Natural Fenosa Power Generation Sevilla, 14 th June 2013 2 Content 1. GNF Power Generation Fleet and Organization 2. Continues Monitoring and Diagnostics Processes 3. Operations
More informationAPPRENTICE IDENTIFICATION
APPRENTICE IDENTIFICATION Trade: Industrial Electrician Name: Individual Identification Number Contract Number Email: This is your Logbook! It is a record of your progress towards achieving certification
More information1. Why is NB Power recommending Life Achievement as the best option?
F.A.Q. Mactaquac Generating Station Life Achievement Project December 2016 1. Why is NB Power recommending Life Achievement as the best option? This approach has the lowest cost estimate when compared
More informationAPPRENTICE IDENTIFICATION
1 LOGBOOK SIGNOFF An individual holding one of the following credentials qualifies as a Workplace Assessor and may sign off on the Workplace Competencies in this Logbook: Registered Industrial Electrician
More informationHydropower and Water Resources
Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures
More informationSteam Turbines-Generators and Auxiliary Systems - Program 65
Steam Turbines-Generators and Auxiliary Systems - Program 65 Program Description Program Overview Because up to 70% of outages planned for steam power plants involve work on the turbine, power producers
More informationSteam Turbine Solutions
Steam Turbine Solutions Steam Turbine Solutions Unique Turbine Designs Optimized For Energy Efficiency And Power Recovery 03 04 05 06 Unique Turbine Designs Optimized For Energy Efficiency Most innovative
More informationLife Cycle Management through Cost Effective Refurbishment, Rehabilitation and Maintenance in Eskom Power Stations.
Life Cycle Management through Cost Effective Refurbishment, Rehabilitation and Maintenance in Eskom Power Stations. 24 th February 2010 Compiled by: Nigel Volk (Senior Manager: Asset Management) Eskom
More informationProspect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Ramping May 2015
Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Ramping May 2015 Prepared by: PacifiCorp Hydro Resources 925 South Grape Street Medford, OR 97501 For Public Review TABLE
More informationconsulting engineers hydraulic steel structures
consulting engineers hydraulic steel structures Floating Sector Gate at Yeonsang Front cover Five of the seven rising sector gates at the Gangchon bridge and weir at Yeoju on the Han River in central Korea.
More informationPresentation Outline. Review of CEATI Background Conventional Hydro Program Update
Presented to: Presentation Outline Review of CEATI Background Conventional Hydro Program Update CEATI Interest Groups: CEATI currently operates 14 focused Interest Groups Generation & Utilization Hydraulic
More informationHydroelectric power. Made by: Kekoa, Sara, Kupaa and Bree
Hydroelectric power Made by: Kekoa, Sara, Kupaa and Bree How it s produced General: Hydroelectric power creates kinetic energy by using water to turn a propeller turbine which turns a metal shaft in a
More informationESP Electrophysical Separation Process
ESP Electrophysical Separation Process CLEAN YOUR SYSTEMS OF VARNISH & DOUBLE THE LIFE OF YOUR LUBRICANTS. IS IT A MIRACLE CURE? ALMOST. ESP improves reliability and slashes O&M costs in these industries:
More informationModule 2: Conventional Power Generation I
Lecture 7 Module 2: Conventional Power Generation I Canada's Electricity Generating Capacity was 126,000 MW in 2007 Hydro 58.7% Coal 16.6% Fuel Oil 1.2% natural gas 6.6% Nuclear 15.5% Other (e.g., Wind,Tidal
More informationRenewable Energy. Visible light. Cool air. Warm air. Condensation. Precipitation. Evaporation
Renewable Energy All renewable energy sources derive from the Sun. The Sun provides the energy that drives our weather systems and water cycle. It is the prime source of all energy on Earth and it is essential
More informationTechnologie - Wasserkraft für den Strommarkt der Zukunft: Von der Komponentenoptimierung zur Systemoptimierung
ZHAW Energie- und Umweltforum Wasserkraft Schweiz Technologie - Wasserkraft für den Strommarkt der Zukunft: Von der Komponentenoptimierung zur Systemoptimierung Mirjam Sick, VP R&D Programm und Innovationsmanagement
More informationNew Hydropower Innovation Collaborative
New Hydropower Innovation Collaborative NWHA mall Hydro Development Workshop July 14, 2015 New Hydropower Innovation Collaborative (NHIC) Commissioned by Oak Ridge National Laboratory to: Reduce the cost
More informationAMI information. for improved outage management
Utilities the way we see it AMI information for improved outage management The information contained in this document is proprietary. 2013 Capgemini. All rights reserved. Rightshore is a trademark belonging
More informationInstallation Guidelines for Flygt Pumps Pump Anchoring Recommendations
Issued: Installation Guidelines for Flygt Pumps Pump Anchoring Recommendations Introduction Proper installation and anchorage of Flygt pumps and installation accessories is critical to limiting vibration
More informationFunctional Problems and Maintenance Operations of Hydraulic Turbines
Functional Problems and Maintenance Operations of Hydraulic Turbines Liliana Topliceanu, Puiu Gabriel, Iulian Furdu Vasile Alecsandri University of Bacau, Faculty of Engineering 157 Marasesti Street, Bacau
More informationDigital Asset Management: Optimizing the Asset Life-cycle with new generation of tools. Filip Kowalski, SAP CEE
Digital Asset Management: Optimizing the Asset Life-cycle with new generation of tools Filip Kowalski, SAP CEE #NP#_JZBta4MwEID/iuTTxmyrLhr1m1Vr fwnnuszbyjdmi3u4d SqsUPrfd+ngCJ d7nssduak6rv4 VTW3a IB+Zhg
More informationPooled Inventory Management (PIM) Program PIM 101
Pooled Inventory Management (PIM) Program PIM 101 PIM PROGRAM Proven program Nuclear plant owner directed Joint inventory program Independent storage facility 37 years of success 2 ORIGINAL PIM SCOPE To
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Horizontal Centrifugal Water Pumps C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 11931 - Horizontal Centrifugal Water Pumps C O N T E N T S PART 1 - GENERAL... 1 1.01 PUMP - GENERAL... 1 1.02 CERTIFIED PUMP CURVES... 1 1.03 NPSH REQUIREMENTS...
More informationElliott Engineered Solutions SERVICES
Elliott Engineered Solutions SERVICES Engineered Solutions Elliott Engineered Solutions has one clear focus to help customers derive additional value from their critical turbomachinery. Elliott has more
More informationRock Anchors for Dams, The National Research Project: The Evolution of Post-tensioned Anchors on Hydropower Dams
Rock Anchors for Dams, The National Research Project: The Evolution of Post-tensioned Anchors on Hydropower Dams Dr. Donald A. Bruce, Geosystems, L.P., USA and John S. Wolfhope, P.E., Freese and Nichols,
More informationHYDROPOWER SYSTEMS BY APPOINTMENT TO H.M. THE QUEEN WATER TURBINE ENGINEERS, GILBERT GILKES & GORDON LTD, KENDAL
HYDROPOWER SYSTEMS BY APPOINTMENT TO H.M. THE QUEEN WATER TURBINE ENGINEERS, GILBERT GILKES & GORDON LTD, KENDAL 7.5MW Twin Jet Horizontal Pelton Turbine Youngs Creek,Snohomish County PUD, Monroe, WA,
More informationADVANTAGES OF VSG LUBRICATION OVER RETROFITTED "GREASELESS" BEARINGS
Providing Tribological Solutions 58 Garnock Avenue Toronto, ON, Canada M4K 1M2 Phone: 416 466-3144 toll free 888 442-5008 Fax: 416 466-3807 www.fluidcenter.com ADVANTAGES OF VSG LUBRICATION OVER RETROFITTED
More informationBrian Day, Group EVP, Customer Services Division Growth through life cycle management
21 June 2017 Brian Day, Group EVP, Customer Services Division Growth through life cycle management Capital Market Day 2017 Life cycle management Delivering the lowest total cost of ownership (TCO) CAPEX
More informationGRUNDFOS WHITE PAPER. Although a baseplate is designed to be a. FOUNDATIONS by Greg Towsley DESIGN RECOMMENDATIONS
GRUNDFOS WHITE PAPER FOUNDATIONS by Greg Towsley Although a baseplate is designed to be a rigid support for a pump and its driver, it will deflect. For this reason a foundation may be provided for additional
More informationPARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012
PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC SEPTEMBER 19, 2012 PARR AND FAIRFIELD LOCATIONS Lockhart Neal Shoals Monticello
More informationOELG Event Categories
OELG Event Categories The table below outlines a proposed set of event categories. These have been developed from the MOD event categories and those used previously by the OELG. The aim of the work has
More informationJohn Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53
John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationEngineering for SH Operations Voith s new StreamDiver technology. StreamDiver B Murtha, NWHA Sisters Oregon
Engineering for SH Operations Voith s new StreamDiver technology 1 97% of existing dams in the US are not used for hydropower and similarly with 85% worldwide. Today the investment costs and projected
More informationCost savings from the CMS Vibration Monitoring and Predictive Maintenance Presented by: Tim Parmer Manufacturing in America 02/22-23/2017
Cost savings from the CMS Vibration Monitoring and Predictive Maintenance Presented by: Tim Parmer Manufacturing in America 02/22-23/27 Condition Monitoring with SIPLUS CMS For early detection of mechanical
More informationPrinting Version: for optimal viewing set the print to A3 and print two pages of the catalogue (including this one) on each sheet.
Printing Version: for optimal viewing set the print to A3 and print two pages of the catalogue (including this one) on each sheet. CUSTOM-MADE WATERWORKS VALVES SINCE 1967 Table of Contents The company
More informationHYDROPOWER INDUSTRY SOLUTIONS
HYDROPOWER INDUSTRY SOLUTIONS Solutions That Increase Reliability and Reduce Costs Chesterton is a global manufacturer of industrial fluid sealing systems, industrial coatings, lubricants, and maintenance
More informationsince 1928 ALBIN PUMP RB INTERNAL GEAR PUMP SERIES since 1928
since 1928 ALBIN PUMP RB INTERNAL GEAR PUMP SERIES since 1928 THE LEGEND To come up with a really good product demands plenty of knowledge and fresh, innovative ideas. Yet most important of all is to
More informationStandards Summary Sheet
Standards Summary Sheet CSA Standard B167-2008 (R2015) Overhead Travelling Cranes Design, Inspection, Testing, Maintenance and Safe Operation Scope and Application This standard specifies the minimum requirements
More informationRenewable Energy Sources. Lesson Plan: NRES F1-2
Renewable Energy Sources Lesson Plan: NRES F1-2 1 Anticipated Problems 1. What are renewable energy sources? 2. What are advantages and disadvantages of renewable energy sources? 2 Terms biomass biopower
More informationRehabilitation of Kidatu Power Plant Project Presentation
Rehabilitation of Kidatu Power Plant Project Presentation Norconsult The 200 MW Kidatu power plant is located on the Great Ruaha River in the region of Morogoro in central Tanzania about 280 km west of
More information12/12/2017. Hydropower and Pumped Storage. The Benefits of Hydropower The Number One Renewable Energy
Hydropower and Pumped Storage Peter Stettner, ANDRITZ HYDRO @ Eurelectric Conference - The Value of Storage for Clean Energy Transition, 2017-12-07, Brussels The Benefits of Hydropower The Number One Renewable
More informationYour Reliable Service Partner in Scotland for Rotating Equipment
Your Reliable Service Partner in Scotland for Rotating Equipment The Sulzer Advantage Capabilities HV (high voltage) and LV (low voltage) rewinds Electrical supply Field services Condition monitoring
More informationAPPENDIX A: EMERGENCY RESPONSE AND CONTINGENCY PLAN TEMPLATE
APPENDIX A: EMERGENCY RESPONSE AND CONTINGENCY PLAN TEMPLATE This template is designed to be a starting point to aid you in preparing your own plan. Please modify to suit the needs of your water supply
More informationNVD-40 NEAR VERTICAL DRUM LIFTER INSTRUCTION MANUAL
VESTIL MANUFACTURING CORP. 2999 North Wayne Street, P.O. Box 507, Angola, IN 46703 Telephone: (260) 665-7586 -or- Toll Free (800) 348-0868 Fax: (260) 665-1339 www.vestilmfg.com e-mail: info@vestil.com
More informationLoy Yang B Environment Improvement Plan
Loy Yang B Environment Improvement Plan 2017 Table of Contents 1 Endorsement 1 2 Environment Policy 2 3 Operating Arrangements 3 4 Site Management and Business Systems 4 5 Environmental Impacts and Risks
More informationLifting Appliances of Ships and Offshore Installations
CCS Rule Change Notice For: Lifting Appliances of Ships and Offshore Installations Version: May, 2016. RCN No.1 Effective date: 19 May, 2016 Beijing CONTENTS Chapter 3 CRANES, LIFTS, RAMPS AND SELF-LOADING
More informationREACTION TANKS BUILD OWN OPERATE WATER MANAGEMENT PROGRAM
REACTION TANKS BUILD OWN OPERATE WATER MANAGEMENT PROGRAM EVOQUA YOUR SERVICE PARTNER FOR INDUSTRY With more than 3,000 dedicated service engineers, technicians, and professionals across the country, we
More informationLCM CC & TCC. A member of the Possehl Group
LCM CC & TCC A member of the Possehl Group LCM LONG CONTINUOUS MIXERS These continuous mixers compete with the quality level of products obtained by discontinuous internal mixers. They overcome both processing
More informationEnergy Effiency of Circulators
Energy Effiency of Circulators December 2011 Energy efficiency of circulators Voluntary industry commitment (since 2005) In March 2005 Europump launched the voluntary industry commitment to improve the
More informationHeavy Intermodal Lift & Transport Engineering Considerations
Heavy Intermodal Lift & Transport Engineering Considerations Host: Mike Parnell ITI President/CEO ASME B30 Vice Chair (Cranes & Rigging) ASME P30 Chair (Lift Planning) Guest Speaker: Jim Yates, P.E. SVP
More informationSEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA
SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA Overview Romania has built 2,617 dams out of which 246 are large and medium dams and 1260 are small dams, as per
More informationENERGY STORAGE EXPLORING THE BUSINESS LINK OPPORTUNITY: TRANSMISSION & CLEAN ENERGY DEVELOPMENT IN THE WEST FEBRUARY
ENERGY STORAGE EXPLORING THE BUSINESS LINK OPPORTUNITY: TRANSMISSION & CLEAN ENERGY DEVELOPMENT IN THE WEST FEBRUARY 7-8 2012 Presented by: Michael A. Stosser 2011 Day Pitney LLP Energy Storage What is
More informationEvaluating Hydraulic Transient Analysis Techniques in Pumped- Storage Hydropower Systems
Evaluating Hydraulic Transient Analysis Techniques in Pumped- Storage Hydropower Systems Michael George Pullinger Murdoch University, May 2011 Master of Science in Renewable Energy PEC 624 Renewable Energy
More informationApplied Maintenance Supplies & Solutions
Applied Maintenance Supplies & Solutions SM Inventory Management, Vending and More Applied Maintenance Supplies & Solutions (Applied MSS SM) brings lean principles to your management of MRO consumables
More informationFluid Mechanics. The Energy Equation [7] Dr. Mohammad N. Almasri
1 Fluid Mechanics The Energy Equation [7] Dr. Mohammad N. Almasri http://sites.google.com/site/mohammadnablus/home 2 Introduction There are various types of devices and components that are utilized in
More informationFocus on reliability to improve availability, profitability and safety.
Focus on reliability to improve availability, profitability and safety. Prediction and Protection for Production Assets Recognize business goals and achieve top-quartile reliability by implementing predictive
More informationHydropower factoring in climate change
Hydropower factoring in climate change 1. Global Supply & Potential 2. Principles of Power Generation 3. Climate Aspects 4. Sustainability Aspects Richard M. Taylor, FEI CEO, International Hydropower Association
More information- CONSTRUCTIONS 300 SECTIONAL VIEW 300 SECTIONAL TABLE 301 QUANTITY FOR MODEL 302 MECHANICAL SEAL 303 BEARINGS 304
CONTENTS Page - SPECIFICATIONS 200 PERFORMANCE RANGE and SELECTION CHART 201 TYPE KEY and CURVE SPECIFICATIONS 202 PERFORMANCE CURVE 40 203 PERFORMANCE CURVE 80 204 - CONSTRUCTIONS 300 SECTIONAL VIEW 300
More informationCurrent Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View
Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View J. Mayrhuber and P. Stering VERBUND Austrian Hydro Power AG, Am Hof 6a, A-1010 Wien, Austria
More informationHydroelectric Pumped Storage Potential and Renewable Energy Integration in the Northwest
Hydroelectric Pumped Storage Potential and Renewable Energy Integration in the Northwest Wind generation on Bonneville Power Administration s (BPA) system in the Northwest grew from almost nothing in 1998
More informationHYDRO RECs. Creating and Selling Purpose Future
HYDRO RECs Creating and Selling Purpose Future HYDRO RECs Part I Creating RECs Laws and Regulations How Did We Get Here? Steps it took to sell our RECs 2009 Failed to get Low Impact Hydro Institute RECs
More informationTable of Contents. A Operate and monitor Micro Hydel Power Plant (MHP) plant 04
Page 2 Table of Contents Competency Standards A Operate and monitor Micro Hydel Power Plant (MHP) plant 04 B Carry out corrective maintenance procedures on electrical components in a MHP plant 05 C Carry
More informationSECTION SLUDGE HOLDING TANK DECANTER PUMP
PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish and install all materials, labor and equipment to put into service the Sludge Holding Tank Decanter Pumping System in accordance with the
More informationHydropower & Dams Services
Hydropower & Dams Services We represent a world-class concentration of hydropower and dam expertise. Since 1920, we have designed hundreds of new hydropower and dams globally, producing clean reliable
More informationMC/TM INFORMATION TO BETTER MANAGE YOUR MACHINES. Complete Monitoring Solutions for the HYDRO INDUSTRY
MC/TM INFORMATION TO BETTER MANAGE YOUR MACHINES Complete Monitoring Solutions for the HYDRO INDUSTRY Complete Monitoring Solutions for the Hydro Industry VibroSystM s online monitoring solutions for hydroelectric
More informationPART 5 WATER SYSTEMS
PART 5 WATER SYSTEMS Abbreviations and Symbols Plan 501 Abbreviations and symbols for water... 205 Concrete Boxes and Hardware 502 27" Frame and cover... 207 503 38" Frame and cover... 209 505 Concrete
More informationHYDRAULICAL SERVOVALVES HYDRAULIC PROPORTIONAL SERVOVALVES AND ELECTRONICS. Convincing Technology.
HYDRAULICAL SERVOVALVES HYDRAULIC PROPORTIONAL SERVOVALVES AND ELECTRONICS Convincing Technology www.selec.ch ABOUT our offer Since 1969 a valuable partner for precise and dynamic hydraulic control tasks.
More informationNashville District October 2011 Update
Nashville District October 2011 Update Tom Cayce Chief of Programs and Project Management October 18, 2011 US Army Corps of Engineers Nashville District Value to the Nation LRN 12% of inland navigable
More informationCF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE
CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document
More informationMicro Hydroelectricity Installer Skills Assessment
Micro Hydroelectricity Installer Skills Assessment Philip V. Hofmeyer August 2011 Page 1 Overview: This document contains an extensive skills assessment for renewable energy professionals who intend to
More informationThis is another in a series of educational articles on water/wastewater. This
Wastewater Treatment Plant: Develop An O&M Manual This article is intended to cover wastewater treatment plant - Develop an O&M Manual. Read on... By Daniel L. Theobald This is another in a series of educational
More informationThe Alberta 2013 Flood
The Alberta 2013 Flood June 20, 2013 was a day few Albertans will forget. After relentless rainfall and a heavier than normal snowpack, catastrophic flooding occurred throughout Southern Alberta. Four
More informationNew applications for ultrasonic sensors in process industries
Ultrasonics 44 (2006) e1379 e1383 www.elsevier.com/locate/ultras New applications for ultrasonic sensors in process industries Alf Püttmer * Siemens AG, Automation and Drives, PI13, Oestliche Rheinbrueckenstr.
More informationSeries A-C Single Stage Double Suction Large Split Case. TECHNICAL Brochure BAC9100
Series A-C 9100 Single Stage Double Suction Large Split Case TECHNICAL Brochure BAC9100 TABLE OF CONTENTS Useful Pump Formulas 2 Pump Engineering Data 3 Materials of Construction 4 Exploded View 6 USEFUL
More information- CONSTRUCTIONS 300 SECTIONAL VIEW DRAWING 300 SECTIONAL VIEW TABLE 301 QUANTITY FOR MODEL 302 MECHANICAL SEAL and BEARINGS 303
CONTENTS Page - SPECIFICATIONS 200 PERFORMANCE RANGE and SELECTION CHART 201 TYPE KEY 202 CURVE SPECIFICATIONS 203 PERFORMANCE CURVE 40 203 PERFORMANCE CURVE 80 204 - CONSTRUCTIONS 300 SECTIONAL VIEW DRAWING
More informationEnergy Services. Your one-stop-shop solutions provider
Energy Services Your one-stop-shop solutions provider We are Uniper We are a leading international energy company with operations in more than 40 countries and 12,600 employees. We combine a balanced portfolio
More informationRFMP Series Service and Parts
Filters RFMP Series Service and Parts up to 26 gpm (98 lpm), up to 100 psi (7 bar) 1. Maintenance 1.1 General Please follow the maintenance instructions. 1.2 Installation Before installing the filter into
More informationImproving the Quality of Ghanaian Parboiled Rice. Training Manual
Improving the Quality of Ghanaian Parboiled Rice Training Manual The Role of Millers This publication is an output from the Crop Post-harvest Research Programme of the UK Department for International Development
More informationINVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING)
INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) Bid Title : EPC Bid for Planning, detailed design& engineering, construction/manufacturing of civil, electro-mechanical, hydro- mechanical and switch
More informationSection 5 Contents Specialty Products & Services
Slewing Ring Bearings Catalog 390 Kaydon Bearings Section 5 Contents Page Number WireX Wire-Race Bearings...115 Custom Bearings... 116-117 Remanufacturing Program...118-121 Endurakote Plating...122-123
More informationUsing AAM To Drive O&M Decisions
Q4a. Using AAM To Drive O&M Decisions AMPLE Asset Management Program Learning Environment Core AAM Program Process Tools System Layout; Data Hierarchy; Data Standards; Data Inventory Condition Assessment
More informationEvaluation-Ready A practical approach for no savings left on the table. Lorene Flaming, PECI Keith Forsman, PG&E
Evaluation-Ready A practical approach for no savings left on the table Lorene Flaming, PECI Keith Forsman, PG&E October 16, 2012 Introduction Genesis of the Statewide Commercial HVAC Quality Maintenance
More informationHybrid Hydroelectric Power Plant : The Ultimate Technology For Electricity Generation
Hybrid Hydroelectric Power Plant : The Ultimate Technology For Electricity Generation Prof. Nilesh P. Patil. 1*, Prof. Dr. V. S. Patil. 2 1 - Asst. Professor (Chemical Engineering), University Institute
More informationVALVES FOR HYDROPOWER PLANTS
VALVES FOR HYDROPOWER PLANTS The company 4 Company ADAMS Switzerland Company ADAMS Switzerland 5 Safety for hydropower plants from the Grison in the Swiss Alps Hydropower makes an indispensable contribution
More information