John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

Size: px
Start display at page:

Download "John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53"

Transcription

1 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) or (C)

2 Project Status Mucking and excavation of the approach channel rock on the reservoir bottom is finished and Fraser River Pile and Dredge is demobilized. The significant in-water intake work (upstream side of the dam) is now complete; Scaffolding is in place for the installation of the upper gate guides at the intake (downstream side of dam) and this work will continue through December; Concrete paving of the nearly 1.6 km-long power tunnel invert (floor) is ongoing, with an average of about 150 metres completed each day; At the surge tank site, for the power tunnel, the formwork for concrete placements is being dismantled and the site is being prepared for the backfill phase; The office complex is taking shape as the fireproofing and finishing work (drywall, lighting, plumbing) is underway. Concrete for the stair landings is complete; Surge chamber draft tube gate guide installation has begun for the gates which can be used in any of the draft tube gate slots for either the bypass outlets or generator unit outlets; The drilling and final blast to remove the tailrace rock plug is set for early December; and The substation is preparing for the installation of the cable bus (brings the power from the generating station to the substation) this includes installing conduit, paving the cable bus footings, and preparing to erect H-frame poles. The first new substation transformer also arrived at the site late this month. The 70-year-old generating station and the new tunnel outlet that will enter the Campbell River.

3 Project Schedule December: Rock plug blast and excavation of tailrace outlet channel; December: Rotor installation for Turbine/Generator #2; December: Turbine inlet valves installed; December: Low level outlet installation begins; December: Powerhouse air compressor system commissioning; December-February: Water intake structure installation of electrical and mechanical works (cable trays, lighting, piping, valves, etc.); December-February: Draft tubes and bypass outlet gates testing; January: Dry testing of turbine/generator #3 underway; January: Testing of hydroelectric pressure unit for Turbine/Generator #3; February: Dry test low level outlet; February: Dry test and commissioning of tailrace dewatering pump; and March/April: Tailrace water up and then power tunnel water up. This media story is a good reminder on why we are doing this project. In 2018, the new water bypass facility within the new underground John Hart generating station will be in operation to protect downstream fish habitat from unplanned flow events. In such incidents, water flows will be immediately re-directed from the generators that may go off-line through the water bypass facility in providing seamless water flows for fish habitat downstream. The John Hart project will also have new transformers placed within the substation.

4 Project Schedule Media Victoria Times Colonist, Nov 1,

5 Construction Pictures John Hart Dam Nov 14 5

6 Low Work on the Level surge tank. Outlet Formwork August 6-27 Crews getting ready to remove some of the concrete formwork on the low level outlet structure. The platform and crew can be seen on the previous page. 6

7 The low level outlet works for water flows down Elk Falls Construction Canyon the left, and the right, the Pictures top of the liners John Hart Dam for the entrance into the power tunnel intake shaft. 7

8 The steel liner that takes water from the intake operating Construction gate into the shaft down to the power tunnel. Pictures John Hart Dam 8

9 9 Placing the concrete invert (floor) within the nearly 1.6 km long power tunnel.

10 10 The surge tank is beginning to take shape. Located between the water intake at the dam and powerhouse, it provides power tunnel protection/hydraulic management.

11 11 View down the power tunnel to the power tunnel manifold.

12 12 Looking down the manifold.

13 13 From left to right, the specialized formwork structures that shape the concrete placements for the water inlets to turbines/generators #1, #2 and #3.

14 14 The water inlets to turbines/generators #2 and #3.

15 15 The turbine inlet valve to Turbine/ Generator #3 is now installed.

16 16 View from the main access tunnel into the powerhouse area. The office space is above and right.

17 Construction Looking Pictures back to the main access tunnel Powerhouse and the office complex. 17

18 Powerhouse view from the service tunnel entrance. Powerhouse view. 18

19 19 The three water bypass valves are to ensure constant water flows are provided downstream to protect fish habitat.

20 20 Bypass operating valve for Unit #2.

21 21 Crews removing the concrete formwork for the gate guides from the gate gallery above. Water from the three water bypass units will enter into this surge chamber and then continue on in the tailrace tunnel to discharge into the river.

22 22 Drilling work and preparations for the early December rock plug blast.

23 The removal of the rock plug area will allow the tailrace tunnel outlet to join Campbell River. 23

24 24 Upgrade work within the John Hart substation as we replace the old equipment with new works for the three new generators within the powerhouse.

25 Environment Water intake work complete: zero water quality impacts within the John Hart reservoir As 2.5 years of in-water work in the reservoir comes to an end, the project team is celebrating their significant record of zero water quality impacts to the City of Campbell River s drinking water. The 30 months of complex in-water work was necessary to build the new intake works in the Campbell River reservoir. The project's environmental monitoring teams successfully managed and monitored this critical work which included: installing the steel-pile temporary cofferdam; blasting and constructing intake maintenance gates on the John Hart dam behind the cofferdam; removing the cofferdam; blasting out of the rock for the intake approach channel; and clamshell excavation of the blasted rock. A large rock removed from the October rock blast courtesy Norm James of FRPD.

26 People Profile Will Kingston About Will Background: Will has been able to use his education in mechanical technology in a number of different industries. As a result, he brings experience from several interesting projects including power generation and renewable energy, manufacturing and construction, and helping implement programs and processes improve equipment reliability. Home: Originally from Toronto, Will has lived in BC for the past 12 years - most of it in Fort St. John. He recently relocated to Campbell River and is nicely settling in to his new surroundings. Hobbies: Will loves exploring the outdoors with his wife Lynn and dog Gus. He also loves music and plays the guitar to relax. Project Responsibility: A key member of the InPower BC team, Will s title is Services Director. It is Will s responsibility to work with the services providers and BC Hydro to ensure the completed John Hart facility is maintained in a safe and reliable manner during the 15-year service period. People are always the most important part of any job, and the quality of the team here is amazing. I m proud to be working on a project that means so much to the province and community.

27 Construction Point Of Interest Each month, BC Hydro and InPower BC will provide a construction fact, occurrence, or situation. Point of Interest Interconnection of power supply from the powerhouse to the substation. The project team discovered during the excavation and geotech drilling process that the slope down to the substation was not suitable for the ground works needed to install the power cable trays from the powerhouse to the substation. Engineers have turned to the H-frame poles to carry the cables to the substation. To suspend the 27 large copper cables (750 MCM) that collectively will convey the 132 MW of power generated by the three new turbine/generators, the H-frame hydro poles will be installed by three spans (shown roughly below) from the powerhouse to the substation; The use of wooden H-frame poles allows the project to have flexibility in their placement; BC Hydro has used H-frame power poles since the 1940s to support suspended power lines; and Wooden H-frame poles, which have effective surge voltage insulating properties, can be up to approximately 30 metres tall.

John Hart Generating Station Replacement Project. December 2017 Community Construction Update Report #54

John Hart Generating Station Replacement Project. December 2017 Community Construction Update Report #54 John Hart Generating Station Replacement Project December 2017 Community Construction Update Report #54 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56 John Hart Generating Station Replacement Project February 2018 Community Construction Update Report #56 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47 John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45 John Hart Generating Station Replacement Project March 2017 Community Construction Update Report #45 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. June 2017 Community Construction Update Report #48

John Hart Generating Station Replacement Project. June 2017 Community Construction Update Report #48 John Hart Generating Station Replacement Project June 2017 Community Construction Update Report #48 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. October 2017 Community Construction Update Report #52

John Hart Generating Station Replacement Project. October 2017 Community Construction Update Report #52 John Hart Generating Station Replacement Project October 2017 Community Construction Update Report #52 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. January 2016 Community Construction Update Report #31

John Hart Generating Station Replacement Project. January 2016 Community Construction Update Report #31 John Hart Generating Station Replacement Project January 2016 Community Construction Update Report #31 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. July 2016 Community Construction Update Report #37

John Hart Generating Station Replacement Project. July 2016 Community Construction Update Report #37 John Hart Generating Station Replacement Project July 2016 Community Construction Update Report #37 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. November-December 2018 Community Construction Update Report #65

John Hart Generating Station Replacement Project. November-December 2018 Community Construction Update Report #65 John Hart Generating Station Replacement Project November-December 2018 Community Construction Update Report #65 This is the final public construction report. Prepared by: Stephen Watson, BC Hydro (O)

More information

BRILLIANT EXPANSION PROJECT

BRILLIANT EXPANSION PROJECT BRILLIANT EXPANSION PROJECT Utilizes power tunnel 120 MW Capacity 500 GWh Energy Transmission link to Brilliant Terminal Station Will reduce TGP downstream Intake Transmission Link Transmission Link Extent

More information

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng. HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the

More information

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8 John Hart Generating Station Replacement Project December 2013 - January 2014 Community Construction Update Report #8 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16

John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16 John Hart Generating Station Replacement Project October 2014 Community Construction Update Report #16 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank. Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge

More information

PROJECT BRIEF for the John Hart Generating Station Replacement Project

PROJECT BRIEF for the John Hart Generating Station Replacement Project PROJECT BRIEF for the John Hart Generating Station Replacement Project Issue Date: March 13, 2012 TABLE OF CONTENTS John Hart Generating Station Replacement Project Page ii of 17 1. INTRODUCTION... 3 1.1

More information

Yukon Energy. Rural Generating Facilities

Yukon Energy. Rural Generating Facilities photo : Yukon Energy Yukon Energy Rural Generating Facilities Yukon Energy s Rural Facilities Yukon Energy has three hydro facilities one in Whitehorse on the Yukon River, one located at Aishihik Lake

More information

Annex V Concrete Structures Removal Plan

Annex V Concrete Structures Removal Plan Appendix D Annex V Concrete Structures Removal Plan Figure V1 Lower Granite Sequences of Concrete Removal and Cofferdam Figure V2 Little Goose Sequence of Concrete Removal and Cofferdam Figure V3 Lower

More information

MIEL I Hydroelectric Power Plant

MIEL I Hydroelectric Power Plant MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers

More information

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No ) Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides

More information

At Kipling GS, turbine and generator work continues along with electrical components, panels and instrumentation.

At Kipling GS, turbine and generator work continues along with electrical components, panels and instrumentation. Lower Mattagami River Project Archived News Updates June 25, 2014 A new 78 MW unit at Harmon Generating Station is now generating clean, renewable electricity for Ontarians, ahead of schedule and on budget.

More information

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by:

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by: DRAFT SEDIMENT and EROSION CONTROL PLAN BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION Prepared by: Electric Department 1.0 INTRODUCTION The Electric Department ( City ) is in the process of

More information

The Rio Grande project - Argentina

The Rio Grande project - Argentina The Rio Grande project - Argentina Introduction The Rio Grande pumped storage project is located on the Rio Grande river near the town of Santa Rosa de Calamucita in the Province of Cordoba in Argentina.

More information

Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis

Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis United States Departme nt of Agriculture Forest Service Alaska Region Tongass National Forest (907) 747-6671 Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis Dear Planning

More information

Lower Mattagami River Project

Lower Mattagami River Project Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added

More information

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT A CASE STUDY OF 1200 MW TEESTA-III HEP, SIKKIM Abstract - The Case study brings out the use of IT application in

More information

IEEE 18-May Intake. Tunnel. Outlet

IEEE 18-May Intake. Tunnel. Outlet IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion

More information

FINAL LICENSE APPLICATION Exhibit C Construction History

FINAL LICENSE APPLICATION Exhibit C Construction History FINAL LICENSE APPLICATION Exhibit C Construction History Portland, Oregon April 2004 Copyright 2004 by Reproduction in whole or in part without the written consent of is prohibited. TABLE OF CONTENTS

More information

Eglinton Crosstown LRT Construction Liaison Committee

Eglinton Crosstown LRT Construction Liaison Committee Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated

More information

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Structure of Presentation Outline of the Project Development Phases Key Attributes of the Project Environmental Considerations Scheme Layout

More information

New Hydro without a new Dam NWHA FEBRUARY 16, 2016

New Hydro without a new Dam NWHA FEBRUARY 16, 2016 New Hydro without a new Dam NWHA FEBRUARY 16, 2016 Agenda Background Perceptions & Misconceptions about Hydro Legislative Environment Snohomish PUD s search for new Hydro resources Sunset Project Overview

More information

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1 Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...

More information

Passage Over Canadian Projects

Passage Over Canadian Projects Passage Over Canadian Projects Keenleyside Brilliant and Waneta Columbia Power Corporation Hydro Expansion Projects Peter Christensen, P.E. R2 Resource Consultants, Redmond, Washington Keenleyside, Brilliant,

More information

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

CASE STUDY OKUYOSHINO, JAPAN

CASE STUDY OKUYOSHINO, JAPAN SEDIMENT MANAGEMENT CASE STUDY OKUYOSHINO, JAPAN Key project features Name: Okuyoshino Country: Japan Category: bypass channel/tunnel Reservoir volume (original): 15.47 Mm 3 Installed capacity: 1,206 MW

More information

Hydropower Project Summary YADKIN, NC W. KERR SCOTT HYDROELECTRIC PROJECT (P-12642) This summary was produced by the. Hydropower Reform Coalition.

Hydropower Project Summary YADKIN, NC W. KERR SCOTT HYDROELECTRIC PROJECT (P-12642) This summary was produced by the. Hydropower Reform Coalition. Hydropower Project Summary YADKIN, NC W. KERR SCOTT HYDROELECTRIC PROJECT (P-12642) Photo Courtesy of Army Corp of Engineers This summary was produced by the Hydropower Reform Coalition and River Management

More information

The Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments

The Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments HOOVER DAM Need arose to control the Colorado River flow and the cycles of flood and drought. Responsibility fell on the Department of the Interior s Bureau of Reclamation Colorado River Compact History

More information

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K)

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K) ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT Project Location State District River Vicinity Latitude Longitude Nearest Railhead; Udhapur (J&K) Hiachal Pradesh Chaba Chenab River Luj village

More information

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Campbell River System Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation Resource Management Nov 21, 2012 v6 Campbell River System Water Use Plan Page i Table of Contents

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

Site C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017

Site C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017 Site C Clean Energy Project Monthly Environmental Monitoring Summary Report - February 2017 Prepared by BC Hydro Submitted May 8, 2017 Page 1 of 17 Table of Contents Introduction... 4 Project Progress...

More information

Takatz Lake Project - Alaska

Takatz Lake Project - Alaska BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT SUBMITTED BY: City and Borough of Sitka Electric Department 105 Jarvis Street Sitka, Alaska 99835 June, 2008 Initial Statement

More information

Environmental Working Group. Monthly Report

Environmental Working Group. Monthly Report Monthly Report July 2012 ENVIRONMENTAL WORKING GROUP Relationship Organizational Chart Weekly (EWG) and EWG/Kiewit Alarie, a Partnership (KAP) meetings. The EWG review its Action Items that include priority

More information

CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013

CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013 CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013 RIVER DIVERSION SEGMENT This week on the River Diversion, Ducworks completed the steel pipe installation below the waterline elevation.

More information

North and South Dams Project Overview

North and South Dams Project Overview North and South Dams Project Overview Construction performed by Barnard Pennecon LP Mobilized in late-2015 Anticipated Completion in mid-2019 Major Features of Our Contract Include: Diversion of Churchill

More information

Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric

Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric Michael Hemelstrand, P.E., Portland General Electric Portland, OR, USA and Jan Buermans, P.Eng., ASL AQFlow

More information

Hydropower. See the notes in Compedu Source: Marianne KTH

Hydropower. See the notes in Compedu   Source: Marianne KTH Hydropower See the notes in Compedu http://www.energy.kth.se/compedu/webcompedu/index.html Source: Marianne Salomon @ KTH Global Renewable Energy Source: IEA Worldwide Hydropower Source: IEA Hydropower

More information

Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the

Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) Photo Credit: Bakersfield.com This summary was produced by the Hydropower Reform Coalition KERN RIVER, CA KERN

More information

FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO )

FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO ) Brookfield Renewable Energy Group Focusing on Renewable Power Generation FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO. 14439) October 2012 HAWKS NEST PROJECT (FERC

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

A. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010.

A. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010. Requests for Information CA-NP-036 NP 2013/2014 GRA 1 2 3 4 5 6 7 8 9 10 11 12 Q. [Decommissioning] Please all workpapers, assumptions, considerations and material reviewed and/or relied upon in developing

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

EXHIBIT C CONSTRUCTION SCHEDULE

EXHIBIT C CONSTRUCTION SCHEDULE EXHIBIT C CONSTRUCTION SCHEDULE C.1 CONSTRUCTION SCHEDULE A preliminary construction schedule as shown in Figure C-1 has been developed for the to show the sequencing of principal activities through the

More information

Evaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP

Evaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP Evaluation of the hydrological risk during the construction phase of Dr.-Ing. Ronald Haselsteiner Björnsen Consulting Engineers, Germany (formerly: EnerjiSA) Stavanger, Norway 15-16 June 2015 MSc. Koray

More information

Introduction. General Description

Introduction. General Description Introduction General Description The 3-Gorges project is a vitally important and backbone project in the development and harnessing of the Yangtze River (Changjiang River). The dam site is situated at

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

TRANSFORMING CHALLENGES INTO OPPORTUNITIES

TRANSFORMING CHALLENGES INTO OPPORTUNITIES ... TRETHEWAY CREEK PROJECT TRANSFORMING CHALLENGES INTO OPPORTUNITIES CANADIAN CONSULTING ENGINEERING AWARDS 2017 Natural Resources, Mining, Industry & Energy Category bba.ca Summary The construction

More information

2 FINDING OF THE POTENTIAL SITES

2 FINDING OF THE POTENTIAL SITES EXECUTIVE SUMMARY 1 Background S-1 2 User of Manual S-1 3 Applicable Range of Micro-hydro power in the Indonesia S-2 4 How to use this Manual S-2 Chapter 1 INTRODUCTION 1-1 1.1 Purpose of the Manual

More information

Milestones: September 4 NTP

Milestones: September 4 NTP September September 30, 2018 : Mobilization to site Install Erosion Control Early shop drawing review Material Procurement o Obermeyer Gates o Rip Rap & Boulders o Pedestrian Bridges o Rapid Blocks o Debris

More information

Previous Tunnel News

Previous Tunnel News Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above

More information

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM 1. PROJECT INFORMATION Intoduction: Tamakoshi V Hydroelectric Project The Tamakoshi-V Hydropower Project is a cascade development

More information

Table of Contents. Nov. 2008

Table of Contents. Nov. 2008 Nov. 2008 What is involved? Electrical loads in Yukon are increasing. By 2011, Yukon Energy expects to need additional renewable power to help minimize the use of diesel to generate electricity. As outlined

More information

TUNNELLING ASSOCIATION OF CANADA

TUNNELLING ASSOCIATION OF CANADA TUNNELLING ASSOCIATION OF CANADA October 29, 2015 Nordic Forum - Regional Report Prepared by: Steve Skelhorn, Vice President East Contributors: Walter Trisi, Director, Ontario André Rancourt, Director,

More information

DEAD RIVER DEAD RIVER HYDROELECTRIC PROJECT (P-10855)

DEAD RIVER DEAD RIVER HYDROELECTRIC PROJECT (P-10855) DEAD RIVER DEAD RIVER HYDROELECTRIC PROJECT (P-10855) A. SUMMARY 1. License Issued: October 4, 2002 2. Expiration: September 30, 2042 3. Waterway: Dead River 4. Capacity: 15.5 MW (megawatts) 5. Licensee:

More information

The Construction of the Langham Place in Mong Kok An Introduction

The Construction of the Langham Place in Mong Kok An Introduction The Construction of the Langham Place in Mong Kok An Introduction Artist Impression of Langham Place r o j e c t c o m p r i s i n g a i l / h o t e l c o m p a n o f f i c e / r e t Fast Fact The site

More information

Inter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal

Inter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal Inter-office memo TO: File DATE: 8 November 2007 FROM: Engineering FILE: GENMIS08 NRGPLN SUBJECT: Jordan River Pumped Storage 1.0 Introduction The British Columbia Utility Commission has directed BC Hydro

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

CHAPTER 9 BASIC DESIGN

CHAPTER 9 BASIC DESIGN CHAPTER 9 BASIC DESIGN TABLE OF CONTENTS Chapter 9 Basic Design 9.1 General...9-1 9.2 Maximum Allowable Vibration due to Blasting against Existing Structures...9-3 9.2.1 Characteristics of Vibration due

More information

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 4 WORK PROGRAM AND SCHEDULE TABLE OF CONTENTS

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 4 WORK PROGRAM AND SCHEDULE TABLE OF CONTENTS SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 4 WORK PROGRAM AND SCHEDULE TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 SUBMITTALS... 1 2.2 Submittal Summary...

More information

SITE C CLEAN ENERGY PROJECT

SITE C CLEAN ENERGY PROJECT el SITE C CLEAN ENERGY PROJECT Update to Peace River Regional District June 25, 2015 OVERVIEW Project Activities Old Fort Worker Accommodation Monitoring and Mitigation Recreation and River Access Procurement

More information

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan EXECUTIVE SUMMARY The consultative process was initiated in April 2000 and completed in November 2001. The consultative process follows the steps outlined in the 1996 provincial government Water Use Plan

More information

Service SIC/NAIC Code Code Direct Subcontract Description

Service SIC/NAIC Code Code Direct Subcontract Description ROTATING EQUIPMENT 2100 Pump Installation 2200 Compressor Installation (new) 2300 Compressor Repair (field) 2400 Millwright Work 4000 CLARIFIERS, THICKENERS FIRED HEATERS AND INTERNALS 6100 Furnace & Heater

More information

Sullivan Lake Cold Water Intake. Pend Oreille PUD No. 1 of Pend Oreille County, WA

Sullivan Lake Cold Water Intake. Pend Oreille PUD No. 1 of Pend Oreille County, WA Sullivan Lake Cold Water Intake Pend Oreille PUD No. 1 of Pend Oreille County, WA April 7, 2016 Project Location Sullivan Lake Project Location Pend Oreille River Sullivan Lake Project Team Project Team

More information

Grant Lake Hydroelectric Project (FERC No ) Operation Compliance Monitoring Plan Draft. Kenai Hydro, LLC

Grant Lake Hydroelectric Project (FERC No ) Operation Compliance Monitoring Plan Draft. Kenai Hydro, LLC (FERC No. 13212) Operation Compliance Monitoring Plan Draft May 2015 TABLE OF CONTENTS 1 Introduction...1 1.1. Location...1 1.2. Project Description...1 1.2.1. Grant Creek Diversion... 5 1.2.2. Grant

More information

SIEA LUNGGA POWER STATION RETAINING WALL

SIEA LUNGGA POWER STATION RETAINING WALL SIEA LUNGGA POWER STATION RETAINING WALL 1. Glossary In this scope of work the following abbreviations and definitions apply. Term AS 3000 AS 3600 AS 3700 Boundary Lines AS 4678 Brick Works Contract Contractor

More information

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental

More information

Asst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26

Asst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 2 of 26 Water is often more useful to people when it is properly controlled, conveyed,

More information

P U B L I C U T I L I T Y D I S T R I C T N O.

P U B L I C U T I L I T Y D I S T R I C T N O. P U B L I C U T I L I T Y D I S T R I C T N O. 1 o f C H E L A N C O U N T Y P.O. Box 1231, Wenatchee, WA 98807-1231 327 N. Wenatchee Ave., Wenatchee, WA 98801 (509) 663-8121 Toll free 1-888-663-8121 www.chelanpud.org

More information

Concurrent Sessions D: Downstream Migrant Surface Collectors-What Works and Doesn't Work - North Fork Dam Floating Surface Collector Design

Concurrent Sessions D: Downstream Migrant Surface Collectors-What Works and Doesn't Work - North Fork Dam Floating Surface Collector Design University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

5 Muskrat Falls Project

5 Muskrat Falls Project 5 Muskrat Falls Project Report by: P. Rae, P. Eng. 5.1 Introduction The Muskrat Falls Project comprises the hydropower generation facility proposed on the Lower Churchill River. The main project elements

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING i MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING ii Table of contents 1 Enhancement Scope of Work 1 1.1 Introduction 1 2 McKays Intake

More information

BC s Magazine for Trenchless Construction

BC s Magazine for Trenchless Construction BC s Magazine for Trenchless Construction Microtunneling at John Hart Lake Laura Anderson Marketing and Communications Director Akkerman Residents of Campbell River are fortunate to have access to a generous

More information

Texas-Sized Challenges

Texas-Sized Challenges Aerial view of the City of Austin s Water Treatment Plant No. 4 in northwest Austin near the intersection of RM 620 and Bullick Hollow Road. cover story Delivering Water Provides Texas-Sized Challenges

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report February 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems ABSTRACT Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems By Ron Monk, M.Eng., P.Eng.; Stefan Joyce, P.Eng.; and Mike Homenuke, P.Eng. Kerr Wood Leidal

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 14-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 14-1 Alberta Environment Page 14-1 14.0 LOW LEVEL OUTLET WORKS 14.1 General In general, a low level outlet structure can be used to provide one or more of the following functions: Supply adequate water to meet

More information

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District

More information

Dewatering & Foundations. Water. Low tech

Dewatering & Foundations. Water. Low tech Dewatering & Foundations Water It seems every time we dig a hole it fills up with rainwater, or groundwater.if we re lucky we hit an underground river or spring that keeps the hole nice and wet. But a

More information

Fulbright Letter-7 At the End of the Channel. Dear friends,

Fulbright Letter-7 At the End of the Channel. Dear friends, Dear friends, This letter continues from the previous letter Water: Phewa Lake, and extends the water/solid waste issues to the regions below Phewa Lake. Phewa Lake has two major outlets: one from the

More information

EXPERIMENTS WITH THE THERMODYNAMIC METHOD

EXPERIMENTS WITH THE THERMODYNAMIC METHOD 1 EXPERIMENTS WITH THE THERMODYNAMIC METHOD Emmanuel Côté, Eng. and Gilles Proulx, Eng. Test Engineers, Hydro-Québec, 5565, rue De Marseille, Montréal, Qc, Canada, H1N 1J4 SUMMARY The thermodynamic method

More information

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS 669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects

More information

CROSSTOWN LRT Construction Liaison Committee November 1, 2017

CROSSTOWN LRT Construction Liaison Committee November 1, 2017 CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole

More information

Environmental Working Group. Monthly Report

Environmental Working Group. Monthly Report Monthly Report June 2012 ENVIRONMENTAL WORKING GROUP Relationship Organizational Chart Weekly (EWG) and EWG/Kiewit Alarie, a Partnership (KAP) meetings. The EWG review its Action Items that include priority

More information