John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53
|
|
- Alvin Day
- 6 years ago
- Views:
Transcription
1 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) or (C)
2 Project Status Mucking and excavation of the approach channel rock on the reservoir bottom is finished and Fraser River Pile and Dredge is demobilized. The significant in-water intake work (upstream side of the dam) is now complete; Scaffolding is in place for the installation of the upper gate guides at the intake (downstream side of dam) and this work will continue through December; Concrete paving of the nearly 1.6 km-long power tunnel invert (floor) is ongoing, with an average of about 150 metres completed each day; At the surge tank site, for the power tunnel, the formwork for concrete placements is being dismantled and the site is being prepared for the backfill phase; The office complex is taking shape as the fireproofing and finishing work (drywall, lighting, plumbing) is underway. Concrete for the stair landings is complete; Surge chamber draft tube gate guide installation has begun for the gates which can be used in any of the draft tube gate slots for either the bypass outlets or generator unit outlets; The drilling and final blast to remove the tailrace rock plug is set for early December; and The substation is preparing for the installation of the cable bus (brings the power from the generating station to the substation) this includes installing conduit, paving the cable bus footings, and preparing to erect H-frame poles. The first new substation transformer also arrived at the site late this month. The 70-year-old generating station and the new tunnel outlet that will enter the Campbell River.
3 Project Schedule December: Rock plug blast and excavation of tailrace outlet channel; December: Rotor installation for Turbine/Generator #2; December: Turbine inlet valves installed; December: Low level outlet installation begins; December: Powerhouse air compressor system commissioning; December-February: Water intake structure installation of electrical and mechanical works (cable trays, lighting, piping, valves, etc.); December-February: Draft tubes and bypass outlet gates testing; January: Dry testing of turbine/generator #3 underway; January: Testing of hydroelectric pressure unit for Turbine/Generator #3; February: Dry test low level outlet; February: Dry test and commissioning of tailrace dewatering pump; and March/April: Tailrace water up and then power tunnel water up. This media story is a good reminder on why we are doing this project. In 2018, the new water bypass facility within the new underground John Hart generating station will be in operation to protect downstream fish habitat from unplanned flow events. In such incidents, water flows will be immediately re-directed from the generators that may go off-line through the water bypass facility in providing seamless water flows for fish habitat downstream. The John Hart project will also have new transformers placed within the substation.
4 Project Schedule Media Victoria Times Colonist, Nov 1,
5 Construction Pictures John Hart Dam Nov 14 5
6 Low Work on the Level surge tank. Outlet Formwork August 6-27 Crews getting ready to remove some of the concrete formwork on the low level outlet structure. The platform and crew can be seen on the previous page. 6
7 The low level outlet works for water flows down Elk Falls Construction Canyon the left, and the right, the Pictures top of the liners John Hart Dam for the entrance into the power tunnel intake shaft. 7
8 The steel liner that takes water from the intake operating Construction gate into the shaft down to the power tunnel. Pictures John Hart Dam 8
9 9 Placing the concrete invert (floor) within the nearly 1.6 km long power tunnel.
10 10 The surge tank is beginning to take shape. Located between the water intake at the dam and powerhouse, it provides power tunnel protection/hydraulic management.
11 11 View down the power tunnel to the power tunnel manifold.
12 12 Looking down the manifold.
13 13 From left to right, the specialized formwork structures that shape the concrete placements for the water inlets to turbines/generators #1, #2 and #3.
14 14 The water inlets to turbines/generators #2 and #3.
15 15 The turbine inlet valve to Turbine/ Generator #3 is now installed.
16 16 View from the main access tunnel into the powerhouse area. The office space is above and right.
17 Construction Looking Pictures back to the main access tunnel Powerhouse and the office complex. 17
18 Powerhouse view from the service tunnel entrance. Powerhouse view. 18
19 19 The three water bypass valves are to ensure constant water flows are provided downstream to protect fish habitat.
20 20 Bypass operating valve for Unit #2.
21 21 Crews removing the concrete formwork for the gate guides from the gate gallery above. Water from the three water bypass units will enter into this surge chamber and then continue on in the tailrace tunnel to discharge into the river.
22 22 Drilling work and preparations for the early December rock plug blast.
23 The removal of the rock plug area will allow the tailrace tunnel outlet to join Campbell River. 23
24 24 Upgrade work within the John Hart substation as we replace the old equipment with new works for the three new generators within the powerhouse.
25 Environment Water intake work complete: zero water quality impacts within the John Hart reservoir As 2.5 years of in-water work in the reservoir comes to an end, the project team is celebrating their significant record of zero water quality impacts to the City of Campbell River s drinking water. The 30 months of complex in-water work was necessary to build the new intake works in the Campbell River reservoir. The project's environmental monitoring teams successfully managed and monitored this critical work which included: installing the steel-pile temporary cofferdam; blasting and constructing intake maintenance gates on the John Hart dam behind the cofferdam; removing the cofferdam; blasting out of the rock for the intake approach channel; and clamshell excavation of the blasted rock. A large rock removed from the October rock blast courtesy Norm James of FRPD.
26 People Profile Will Kingston About Will Background: Will has been able to use his education in mechanical technology in a number of different industries. As a result, he brings experience from several interesting projects including power generation and renewable energy, manufacturing and construction, and helping implement programs and processes improve equipment reliability. Home: Originally from Toronto, Will has lived in BC for the past 12 years - most of it in Fort St. John. He recently relocated to Campbell River and is nicely settling in to his new surroundings. Hobbies: Will loves exploring the outdoors with his wife Lynn and dog Gus. He also loves music and plays the guitar to relax. Project Responsibility: A key member of the InPower BC team, Will s title is Services Director. It is Will s responsibility to work with the services providers and BC Hydro to ensure the completed John Hart facility is maintained in a safe and reliable manner during the 15-year service period. People are always the most important part of any job, and the quality of the team here is amazing. I m proud to be working on a project that means so much to the province and community.
27 Construction Point Of Interest Each month, BC Hydro and InPower BC will provide a construction fact, occurrence, or situation. Point of Interest Interconnection of power supply from the powerhouse to the substation. The project team discovered during the excavation and geotech drilling process that the slope down to the substation was not suitable for the ground works needed to install the power cable trays from the powerhouse to the substation. Engineers have turned to the H-frame poles to carry the cables to the substation. To suspend the 27 large copper cables (750 MCM) that collectively will convey the 132 MW of power generated by the three new turbine/generators, the H-frame hydro poles will be installed by three spans (shown roughly below) from the powerhouse to the substation; The use of wooden H-frame poles allows the project to have flexibility in their placement; BC Hydro has used H-frame power poles since the 1940s to support suspended power lines; and Wooden H-frame poles, which have effective surge voltage insulating properties, can be up to approximately 30 metres tall.
John Hart Generating Station Replacement Project. December 2017 Community Construction Update Report #54
John Hart Generating Station Replacement Project December 2017 Community Construction Update Report #54 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55
John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56
John Hart Generating Station Replacement Project February 2018 Community Construction Update Report #56 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47
John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45
John Hart Generating Station Replacement Project March 2017 Community Construction Update Report #45 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. June 2017 Community Construction Update Report #48
John Hart Generating Station Replacement Project June 2017 Community Construction Update Report #48 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. October 2017 Community Construction Update Report #52
John Hart Generating Station Replacement Project October 2017 Community Construction Update Report #52 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. January 2016 Community Construction Update Report #31
John Hart Generating Station Replacement Project January 2016 Community Construction Update Report #31 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. July 2016 Community Construction Update Report #37
John Hart Generating Station Replacement Project July 2016 Community Construction Update Report #37 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationJohn Hart Generating Station Replacement Project. November-December 2018 Community Construction Update Report #65
John Hart Generating Station Replacement Project November-December 2018 Community Construction Update Report #65 This is the final public construction report. Prepared by: Stephen Watson, BC Hydro (O)
More informationBRILLIANT EXPANSION PROJECT
BRILLIANT EXPANSION PROJECT Utilizes power tunnel 120 MW Capacity 500 GWh Energy Transmission link to Brilliant Terminal Station Will reduce TGP downstream Intake Transmission Link Transmission Link Extent
More informationHydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.
HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the
More informationJohn Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8
John Hart Generating Station Replacement Project December 2013 - January 2014 Community Construction Update Report #8 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com
More informationJohn Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16
John Hart Generating Station Replacement Project October 2014 Community Construction Update Report #16 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com
More informationChakachamna Hydro. AEA Geothermal Conference
Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings
More information11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.
Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge
More informationPROJECT BRIEF for the John Hart Generating Station Replacement Project
PROJECT BRIEF for the John Hart Generating Station Replacement Project Issue Date: March 13, 2012 TABLE OF CONTENTS John Hart Generating Station Replacement Project Page ii of 17 1. INTRODUCTION... 3 1.1
More informationYukon Energy. Rural Generating Facilities
photo : Yukon Energy Yukon Energy Rural Generating Facilities Yukon Energy s Rural Facilities Yukon Energy has three hydro facilities one in Whitehorse on the Yukon River, one located at Aishihik Lake
More informationAnnex V Concrete Structures Removal Plan
Appendix D Annex V Concrete Structures Removal Plan Figure V1 Lower Granite Sequences of Concrete Removal and Cofferdam Figure V2 Little Goose Sequence of Concrete Removal and Cofferdam Figure V3 Lower
More informationMIEL I Hydroelectric Power Plant
MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers
More informationCondition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )
Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides
More informationAt Kipling GS, turbine and generator work continues along with electrical components, panels and instrumentation.
Lower Mattagami River Project Archived News Updates June 25, 2014 A new 78 MW unit at Harmon Generating Station is now generating clean, renewable electricity for Ontarians, ahead of schedule and on budget.
More informationRÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant
RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80
More informationThen the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.
11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration
More informationDRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by:
DRAFT SEDIMENT and EROSION CONTROL PLAN BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION Prepared by: Electric Department 1.0 INTRODUCTION The Electric Department ( City ) is in the process of
More informationThe Rio Grande project - Argentina
The Rio Grande project - Argentina Introduction The Rio Grande pumped storage project is located on the Rio Grande river near the town of Santa Rosa de Calamucita in the Province of Cordoba in Argentina.
More informationBlue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis
United States Departme nt of Agriculture Forest Service Alaska Region Tongass National Forest (907) 747-6671 Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis Dear Planning
More informationLower Mattagami River Project
Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added
More informationUSE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT
USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT A CASE STUDY OF 1200 MW TEESTA-III HEP, SIKKIM Abstract - The Case study brings out the use of IT application in
More informationIEEE 18-May Intake. Tunnel. Outlet
IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion
More informationFINAL LICENSE APPLICATION Exhibit C Construction History
FINAL LICENSE APPLICATION Exhibit C Construction History Portland, Oregon April 2004 Copyright 2004 by Reproduction in whole or in part without the written consent of is prohibited. TABLE OF CONTENTS
More informationEglinton Crosstown LRT Construction Liaison Committee
Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated
More informationVinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa
Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Structure of Presentation Outline of the Project Development Phases Key Attributes of the Project Environmental Considerations Scheme Layout
More informationNew Hydro without a new Dam NWHA FEBRUARY 16, 2016
New Hydro without a new Dam NWHA FEBRUARY 16, 2016 Agenda Background Perceptions & Misconceptions about Hydro Legislative Environment Snohomish PUD s search for new Hydro resources Sunset Project Overview
More informationTender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1
Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...
More informationPassage Over Canadian Projects
Passage Over Canadian Projects Keenleyside Brilliant and Waneta Columbia Power Corporation Hydro Expansion Projects Peter Christensen, P.E. R2 Resource Consultants, Redmond, Washington Keenleyside, Brilliant,
More informationElko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights
Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project
More informationLower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project
Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located
More informationCASE STUDY OKUYOSHINO, JAPAN
SEDIMENT MANAGEMENT CASE STUDY OKUYOSHINO, JAPAN Key project features Name: Okuyoshino Country: Japan Category: bypass channel/tunnel Reservoir volume (original): 15.47 Mm 3 Installed capacity: 1,206 MW
More informationHydropower Project Summary YADKIN, NC W. KERR SCOTT HYDROELECTRIC PROJECT (P-12642) This summary was produced by the. Hydropower Reform Coalition.
Hydropower Project Summary YADKIN, NC W. KERR SCOTT HYDROELECTRIC PROJECT (P-12642) Photo Courtesy of Army Corp of Engineers This summary was produced by the Hydropower Reform Coalition and River Management
More informationThe Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments
HOOVER DAM Need arose to control the Colorado River flow and the cycles of flood and drought. Responsibility fell on the Department of the Interior s Bureau of Reclamation Colorado River Compact History
More informationANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K)
ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT Project Location State District River Vicinity Latitude Longitude Nearest Railhead; Udhapur (J&K) Hiachal Pradesh Chaba Chenab River Luj village
More informationCampbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights
Campbell River System Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation Resource Management Nov 21, 2012 v6 Campbell River System Water Use Plan Page i Table of Contents
More informationEAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT
EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract
More informationTypes of Hydropower Facilities
Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River
More informationSite C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017
Site C Clean Energy Project Monthly Environmental Monitoring Summary Report - February 2017 Prepared by BC Hydro Submitted May 8, 2017 Page 1 of 17 Table of Contents Introduction... 4 Project Progress...
More informationTakatz Lake Project - Alaska
BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT SUBMITTED BY: City and Borough of Sitka Electric Department 105 Jarvis Street Sitka, Alaska 99835 June, 2008 Initial Statement
More informationEnvironmental Working Group. Monthly Report
Monthly Report July 2012 ENVIRONMENTAL WORKING GROUP Relationship Organizational Chart Weekly (EWG) and EWG/Kiewit Alarie, a Partnership (KAP) meetings. The EWG review its Action Items that include priority
More informationCWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013
CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013 RIVER DIVERSION SEGMENT This week on the River Diversion, Ducworks completed the steel pipe installation below the waterline elevation.
More informationNorth and South Dams Project Overview
North and South Dams Project Overview Construction performed by Barnard Pennecon LP Mobilized in late-2015 Anticipated Completion in mid-2019 Major Features of Our Contract Include: Diversion of Churchill
More informationFlow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric
Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric Michael Hemelstrand, P.E., Portland General Electric Portland, OR, USA and Jan Buermans, P.Eng., ASL AQFlow
More informationHydropower. See the notes in Compedu Source: Marianne KTH
Hydropower See the notes in Compedu http://www.energy.kth.se/compedu/webcompedu/index.html Source: Marianne Salomon @ KTH Global Renewable Energy Source: IEA Worldwide Hydropower Source: IEA Hydropower
More informationHydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the
Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) Photo Credit: Bakersfield.com This summary was produced by the Hydropower Reform Coalition KERN RIVER, CA KERN
More informationFERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO )
Brookfield Renewable Energy Group Focusing on Renewable Power Generation FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO. 14439) October 2012 HAWKS NEST PROJECT (FERC
More informationCoire Glas Pumped Storage Scheme
About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,
More informationA. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010.
Requests for Information CA-NP-036 NP 2013/2014 GRA 1 2 3 4 5 6 7 8 9 10 11 12 Q. [Decommissioning] Please all workpapers, assumptions, considerations and material reviewed and/or relied upon in developing
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationEXHIBIT C CONSTRUCTION SCHEDULE
EXHIBIT C CONSTRUCTION SCHEDULE C.1 CONSTRUCTION SCHEDULE A preliminary construction schedule as shown in Figure C-1 has been developed for the to show the sequencing of principal activities through the
More informationEvaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP
Evaluation of the hydrological risk during the construction phase of Dr.-Ing. Ronald Haselsteiner Björnsen Consulting Engineers, Germany (formerly: EnerjiSA) Stavanger, Norway 15-16 June 2015 MSc. Koray
More informationIntroduction. General Description
Introduction General Description The 3-Gorges project is a vitally important and backbone project in the development and harnessing of the Yangtze River (Changjiang River). The dam site is situated at
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More informationTRANSFORMING CHALLENGES INTO OPPORTUNITIES
... TRETHEWAY CREEK PROJECT TRANSFORMING CHALLENGES INTO OPPORTUNITIES CANADIAN CONSULTING ENGINEERING AWARDS 2017 Natural Resources, Mining, Industry & Energy Category bba.ca Summary The construction
More information2 FINDING OF THE POTENTIAL SITES
EXECUTIVE SUMMARY 1 Background S-1 2 User of Manual S-1 3 Applicable Range of Micro-hydro power in the Indonesia S-2 4 How to use this Manual S-2 Chapter 1 INTRODUCTION 1-1 1.1 Purpose of the Manual
More informationMilestones: September 4 NTP
September September 30, 2018 : Mobilization to site Install Erosion Control Early shop drawing review Material Procurement o Obermeyer Gates o Rip Rap & Boulders o Pedestrian Bridges o Rapid Blocks o Debris
More informationPrevious Tunnel News
Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above
More informationPROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project
PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM 1. PROJECT INFORMATION Intoduction: Tamakoshi V Hydroelectric Project The Tamakoshi-V Hydropower Project is a cascade development
More informationTable of Contents. Nov. 2008
Nov. 2008 What is involved? Electrical loads in Yukon are increasing. By 2011, Yukon Energy expects to need additional renewable power to help minimize the use of diesel to generate electricity. As outlined
More informationTUNNELLING ASSOCIATION OF CANADA
TUNNELLING ASSOCIATION OF CANADA October 29, 2015 Nordic Forum - Regional Report Prepared by: Steve Skelhorn, Vice President East Contributors: Walter Trisi, Director, Ontario André Rancourt, Director,
More informationDEAD RIVER DEAD RIVER HYDROELECTRIC PROJECT (P-10855)
DEAD RIVER DEAD RIVER HYDROELECTRIC PROJECT (P-10855) A. SUMMARY 1. License Issued: October 4, 2002 2. Expiration: September 30, 2042 3. Waterway: Dead River 4. Capacity: 15.5 MW (megawatts) 5. Licensee:
More informationThe Construction of the Langham Place in Mong Kok An Introduction
The Construction of the Langham Place in Mong Kok An Introduction Artist Impression of Langham Place r o j e c t c o m p r i s i n g a i l / h o t e l c o m p a n o f f i c e / r e t Fast Fact The site
More informationInter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal
Inter-office memo TO: File DATE: 8 November 2007 FROM: Engineering FILE: GENMIS08 NRGPLN SUBJECT: Jordan River Pumped Storage 1.0 Introduction The British Columbia Utility Commission has directed BC Hydro
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More informationCHAPTER 9 BASIC DESIGN
CHAPTER 9 BASIC DESIGN TABLE OF CONTENTS Chapter 9 Basic Design 9.1 General...9-1 9.2 Maximum Allowable Vibration due to Blasting against Existing Structures...9-3 9.2.1 Characteristics of Vibration due
More informationSUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 4 WORK PROGRAM AND SCHEDULE TABLE OF CONTENTS
SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 4 WORK PROGRAM AND SCHEDULE TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 SUBMITTALS... 1 2.2 Submittal Summary...
More informationSITE C CLEAN ENERGY PROJECT
el SITE C CLEAN ENERGY PROJECT Update to Peace River Regional District June 25, 2015 OVERVIEW Project Activities Old Fort Worker Accommodation Monitoring and Mitigation Recreation and River Access Procurement
More informationEXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan
EXECUTIVE SUMMARY The consultative process was initiated in April 2000 and completed in November 2001. The consultative process follows the steps outlined in the 1996 provincial government Water Use Plan
More informationService SIC/NAIC Code Code Direct Subcontract Description
ROTATING EQUIPMENT 2100 Pump Installation 2200 Compressor Installation (new) 2300 Compressor Repair (field) 2400 Millwright Work 4000 CLARIFIERS, THICKENERS FIRED HEATERS AND INTERNALS 6100 Furnace & Heater
More informationSullivan Lake Cold Water Intake. Pend Oreille PUD No. 1 of Pend Oreille County, WA
Sullivan Lake Cold Water Intake Pend Oreille PUD No. 1 of Pend Oreille County, WA April 7, 2016 Project Location Sullivan Lake Project Location Pend Oreille River Sullivan Lake Project Team Project Team
More informationGrant Lake Hydroelectric Project (FERC No ) Operation Compliance Monitoring Plan Draft. Kenai Hydro, LLC
(FERC No. 13212) Operation Compliance Monitoring Plan Draft May 2015 TABLE OF CONTENTS 1 Introduction...1 1.1. Location...1 1.2. Project Description...1 1.2.1. Grant Creek Diversion... 5 1.2.2. Grant
More informationSIEA LUNGGA POWER STATION RETAINING WALL
SIEA LUNGGA POWER STATION RETAINING WALL 1. Glossary In this scope of work the following abbreviations and definitions apply. Term AS 3000 AS 3600 AS 3700 Boundary Lines AS 4678 Brick Works Contract Contractor
More informationClient: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation
Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental
More informationAsst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26
1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 2 of 26 Water is often more useful to people when it is properly controlled, conveyed,
More informationP U B L I C U T I L I T Y D I S T R I C T N O.
P U B L I C U T I L I T Y D I S T R I C T N O. 1 o f C H E L A N C O U N T Y P.O. Box 1231, Wenatchee, WA 98807-1231 327 N. Wenatchee Ave., Wenatchee, WA 98801 (509) 663-8121 Toll free 1-888-663-8121 www.chelanpud.org
More informationConcurrent Sessions D: Downstream Migrant Surface Collectors-What Works and Doesn't Work - North Fork Dam Floating Surface Collector Design
University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish
More information5 Muskrat Falls Project
5 Muskrat Falls Project Report by: P. Rae, P. Eng. 5.1 Introduction The Muskrat Falls Project comprises the hydropower generation facility proposed on the Lower Churchill River. The main project elements
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationMCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING
i MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING ii Table of contents 1 Enhancement Scope of Work 1 1.1 Introduction 1 2 McKays Intake
More informationBC s Magazine for Trenchless Construction
BC s Magazine for Trenchless Construction Microtunneling at John Hart Lake Laura Anderson Marketing and Communications Director Akkerman Residents of Campbell River are fortunate to have access to a generous
More informationTexas-Sized Challenges
Aerial view of the City of Austin s Water Treatment Plant No. 4 in northwest Austin near the intersection of RM 620 and Bullick Hollow Road. cover story Delivering Water Provides Texas-Sized Challenges
More informationDORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018
DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report February 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development
More informationTABLE OF CONTENTS Public Safety Building
DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary
More informationRapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems
ABSTRACT Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems By Ron Monk, M.Eng., P.Eng.; Stefan Joyce, P.Eng.; and Mike Homenuke, P.Eng. Kerr Wood Leidal
More informationWater Control Structures Selected Design Guidelines Alberta Environment Page 14-1
Alberta Environment Page 14-1 14.0 LOW LEVEL OUTLET WORKS 14.1 General In general, a low level outlet structure can be used to provide one or more of the following functions: Supply adequate water to meet
More informationThe Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok
The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District
More informationDewatering & Foundations. Water. Low tech
Dewatering & Foundations Water It seems every time we dig a hole it fills up with rainwater, or groundwater.if we re lucky we hit an underground river or spring that keeps the hole nice and wet. But a
More informationFulbright Letter-7 At the End of the Channel. Dear friends,
Dear friends, This letter continues from the previous letter Water: Phewa Lake, and extends the water/solid waste issues to the regions below Phewa Lake. Phewa Lake has two major outlets: one from the
More informationEXPERIMENTS WITH THE THERMODYNAMIC METHOD
1 EXPERIMENTS WITH THE THERMODYNAMIC METHOD Emmanuel Côté, Eng. and Gilles Proulx, Eng. Test Engineers, Hydro-Québec, 5565, rue De Marseille, Montréal, Qc, Canada, H1N 1J4 SUMMARY The thermodynamic method
More informationIssued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS
669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects
More informationCROSSTOWN LRT Construction Liaison Committee November 1, 2017
CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole
More informationEnvironmental Working Group. Monthly Report
Monthly Report June 2012 ENVIRONMENTAL WORKING GROUP Relationship Organizational Chart Weekly (EWG) and EWG/Kiewit Alarie, a Partnership (KAP) meetings. The EWG review its Action Items that include priority
More information