15Things to Know. About Cooling Water Treatment. An objective evaluation of competing cooling water proposals

Size: px
Start display at page:

Download "15Things to Know. About Cooling Water Treatment. An objective evaluation of competing cooling water proposals"

Transcription

1 The following article was published in ASHRAE Journal, July Copyright 2007 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes only. This article may not be copied and/or distributed electronically or in paper form without permission of ASHRAE. 15Things to Know About Cooling Water Treatment By Bill Gaines, Martin R. Orban, and David R. Welch An objective evaluation of competing cooling water proposals only can be made when they are uniform. An unambiguous specifi cation would seem ideal for this purpose. Yet each facility is unique and industry standards of quality and performance still leave open areas of interpretation due to those unique system characteristics. How can a facility manager know when a change in suppliers or chemical program is warranted? This article provides a practical guide to determine the value of a water treatment program and to perform a critical review of alternative programs. It is equally suitable when proposals are solicited or when an end-user wants to compare a new supplier to an existing program. In the auto industry, a tight part specification is a necessity. Components must meet rigid tolerances, be of high quality, perform to expected standards, and, of course, be economical and provide value to the customer. A cooling water treatment program must have the same qualities. Poorly specifying performance metrics is unwise and imprudent, yet writing entirely prescriptive requirements for a cooling water program is, at best, difficult and impermanent. Constantly changing regulations, variable manufacturing fluids/processes, and development of new treatment chemistries demand that a treatment program be flexible to reflect optimum conditions. A comprehensive system specification that rules out discovery, experience, and innovation minimizes the opportunity to use a supplier s expertise. It also sets the stage to focus on the specification rather than actual system performance. Does this mean a well-defined performance specification isn t necessary? Indeed not! The need for an explicit specification is critical to protect the integrity of process equipment. The individual elements of what must be included have been well documented in previous literature. 1,2 Unfortunately, industry standards of quality and performance still leave areas open to interpretation due to unique system requirements, and create significant variations between apparently similar proposals. Given this situation, About the Authors Bill Gaines is a principal engineer with Ford Motor Company in Dearborn, Mich. Martin R. Orban is a director of product management & technology at Mitco in Grand Rapids, Mich. David R. Welch is the Michigan district manager at Mitco. 50 ASHRAE Journal ashrae.org ashrae.org July 2007

2 how can a facility manager know when a change in suppliers or chemical program is warranted? Five Front-End Elements to Establish There is no single right solution to selecting a treatment regime. Even the best program involves tradeoffs between cost and effectiveness. However, certain elements always improve the likelihood of success: 1. System Characterization Nothing is more important than an accurate system characterization -- it is the foundation upon which all other decisions are made, and provides the basis for proposals that optimize cost and performance. Even greater benefit is gained when suppliers are offered the opportunity to survey the system to gain additional information. Essential system characteristics include: The volume of water used in the previous year (if unknown, start measuring it); The number of operating days and seasonal variation; The total system volume (easy to determine); A complete makeup water analysis (if you don t have one, get one); The recirculation rate (if unknown, pump horsepower or tons of cooling capacity can be used to estimate it until it is measured); Present cycles of concentration (CoC); and A list of the materials of construction for all wetted parts within the system. Water usage is a source of difficulty in bid preparation and evaluation. Left to their own, suppliers who may have to estimate makeup and blowdown will skew cost estimates. In the absence of reliable metered water usage, it is essential that annual water usage be defined in the specifications. 2. Restrictions Any restrictions due to discharge requirements or corporate policies must be communicated (e.g., zinc and/or molybdate not allowed). Equally important is when there is a bias toward a particular program (e.g., halogen). In this case, the active chemical and its control range must be defined, while still allowing voluntary alternate programs that use supplier experience. 3. Performance Metrics The current metrics (if satisfactory) or expectations (if unsatisfactory) must be communicated. Remember that high demands escalate costs and may promote future dissatisfaction. The best method for determining performance metrics is to combine information garnered during the bidding process with knowledge from the vendor, end-user and industry organizations. High performance cannot be sustained without proper training. Vendors need to provide a manual to administer the program safely and as designed. Such a manual needs to include at a minimum: Emergency contact information; Chemical treatment programs and control limits; Test procedures, interpretation of results, and corrective actions; Product bulletins and material safety data sheets (MSDSs); and Routine service reports. 4. Face Time Treatment programs are provided on either a full service or limited (namely, advisory) basis. Under a full-service agreement, the supplier provides total management of the program. Under a limited agreement, the supplier recommends a program, provides chemicals and offers consulting to the site. Facility personnel maintain the equipment, administer the chemicals, and monitor water quality, operational characteristics, and program performance. The primary responsibility of a water treatment supplier is to manage the water treatment program. The supplier should ensure the completeness of analytical tests, know how to interpret them and foresee potential problem areas. Face time is the frequency and duration of service provided by the supplier. In many cases, this is the most costly of all the program components. Therefore, interview the representative as if you were hiring a full-time employee. Realize that when you specify service frequency, you are directly impacting the program cost and inviting a cost that may not connect to your desired program value. The experience of the representative plays a critical role in program success and cost. Although dollars spent divided by hours of service may be a helpful calculation, it is the quality of service that determines the largest portion of program value. Alternatively, one must ask What are the components of the present service program? What actually happened in the hour of service that I received and how much am I willing to do in support of the program that I specify? Many high-performing programs are 90% self-managed. 5. Deliverables Operator logs and vendor service reports provide valuable data that in conjunction with water, deposit, and other analyses, measure progress against defined performance metrics. Regular reviews of the program cover performance, costs, problem areas and corrective action plans. Therefore, it is common to request a copy of a review authored by the representative you are considering. Also, a water treatment company s corporate support structure impacts its pricing. Be aware of the type and amount of additional support that you most likely will need. Five Elements to Establish During the Selection Process Uniformity among the various proposals is crucial to allow objective evaluation. Seeking an apples-to-apples comparison works well for apples, but not always for water treatment programs. Each facility is unique and industry standards of quality and performance still leave many areas open to interpretation based upon those unique system characteristics. Once proposals are received, the process of evaluating them can be quite challenging. Five areas requiring evaluation are: July 2007 ASHRAE Journal 51

3 1. Product Evaluation MSDSs don t provide sufficient information to compare products. End-users usually address this is by requiring full disclosure with submittals. Full disclosure allows the end-user to examine programs in terms of suitability, health and safety, and material compatibility. Once the proposals and product information are in hand, one can compare them to the previous years total pounds of each chemical used, cost per pound, total program cost, and the number of hours that the supplier spent on site. One must consider the product recommendation and its impact on CoC. The product concentration (dilution) accounts for wide variations in unit pricing, making it impossible to compare usage and cost. Therefore, respondents must also provide annual use rates. Maximum cycles also vary depending on the treatment chemistry. Similar programs from different vendors ought to yield similar CoC. If a program has greater cost but higher CoC, then the evaluation should reflect the reduced makeup. An insightful metric is total annual cost divided by million pounds of blowdown. Ideally, deviations are addressed during the pre-bid meeting and walk-through. But if a reasonable irregularity surfaces after the fact, then bidders need to be offered an opportunity to make appropriate revisions. However, they should not be allowed license for changes outside the irregularity identified. 2. Method of Application Just as the choice of chemistry must be appropriate to the individual system, so too must be the method of addition. Proposals must address: a. Control Method: Is the feed and monitoring equipment appropriate for the chemical program? Will it be on a continuous or intermittent basis, or a combination of both? If additional equipment is required, several options are available: Direct Purchase: End-user purchases and installs required equipment; Lease-to-Own: A third-party lease agreement; Added to Price of Chemical: This is popular when capital budgets are limited. However, both parties must understand the term and/or volume limits for which the adder is applied (a depreciation schedule is advantageous if there is a need to change vendors before satisfying the terms of the agreement); and Vendor Supplied: The vendor retains ownership and maintenance and folds the cost into the chemical price. This method is gaining in popularity as more end-users view this as an opportunity to keep up with advances in control technology. b. Inventory Management: Proposals must be consistent with the end-user inventory needs and storage of each product appropriate for its usage. They must also demonstrate that adequate Advertisement formerly in this space. 52 ASHRAE Journal ashrae.org July 2007

4 Advertisement formerly in this space.

5 but not excessive inventory levels will be provided. Many companies do not want to dispose of containers when drums are used, and some vendors have responded with drumless programs. c. Ordering/Shipping: While most endusers specify FOB delivered, this is often not the most economical choice. Overall charges are cheaper when higher volumes Advertisement formerly in this space. are shipped, but some vendors apply a higher freight charge in case only a few drums are ordered. Usually it s better to specify prepay and add. This way, the end-user enjoys the quantity freight discounts for large orders, as well as, lower charges when only a few containers are shipped. Alternatively, it s often advantageous to ship on a consignment basis if the end-user has storage space and the parties agree on invoicing methods. The vendor minimizes cost by shipping larger truckloads less frequently and passes the savings on to the end-user. 3. Who Do You (And Who Do You Not) See? Proposals must identify resources that will be made available when the primary representative is unavailable. They must include names and biographical information for the primary and backup support personnel, as well as, the key corporate support personnel to be assigned under such conditions. Thoroughly check all references! Evaluation of services cannot be made by a predetermined formula that applies to all cases. However, certain questions aid in the review: Does the service representative have the skill to identify and correct problem areas as they arise? Does the proposal consider plant procedures, safety training and lockout procedures? What is supplier turnover rate, and how long have the personnel been assigned to the local area? Is there an allowance for emergency service? If so, are separate charges clearly delineated? Is periodic (typically annual) indepth equipment inspection provided? Proposals should describe how this will be done and what inspection equipment is to be used. 4. Corrective Measures for Routine Out of Control Parameters Given the highly dynamic nature of plant systems, an unexpected event will occur. When the program is collaborative, service is proactive, and standard operating procedures have been written; then personnel follow uniform methods to act and correct following an upset. The answer to a water treatment problem is not always the application or increased usage of a chemical. The representative must always be cognizant of physical or operational changes, as well as, chemical upsets. It has been reasonably stated that 80% of chemical problems are mechanical. Above all we must try to 54 ASHRAE Journal ashrae.org July 2007

6 remember that, in the real world, change is sometimes necessary. When this occurs, the method of change should be thoroughly considered, rather than a knee-jerk reaction. The management of change is best achieved when a systematic approach is applied to each process and subprocess. 5. Non-routine Service If one accepts the premise anything that can fail will ultimately fail, then it follows that a well-designed program must allow for unforeseen and unscheduled equipment outages. It is in the best interest of both parties that non-routine service be addressed upfront. Although there is no single correct formula for defining this, the most common method resembles the following: Basic contract allows for x hours of routine service plus y hours of nonroutine/emergency service in conjunction with z hours of analytical laboratory work for a contracted price. Work required beyond these allowances to be charged at a predefined hourly rate. Five Ongoing Elements Once a program is established and underway, there are ongoing aspects that require continuing evaluation: 1. Meeting Performance Metrics The most fundamental measure of supplier performance is that all metrics and deliverables identified in the front-end elements are being met. Proof that tests were performed at their scheduled frequency, all parameters were within prescribed control limits, and performance objectives were achieved, must be clearly documented. 2. Risk Management A risk management program (that should have been jointly developed) includes a hazard analysis and risk assessment. Each portion needs to be reviewed annually to ensure it remains current for changes made during the previous year. The hazard analysis is intended to identify safety and environmental hazards by rating their severity and likelihood of occurrence, and then establishing controls to reduce or eliminate them. It is fundamental to evaluate and improve the safety of cooling water systems. A process flow diagram needs to indicate where spill prevention is required and where personnel exposure potential exists. Sensible control for strategies for hazards must be included. A Legionella-specific system assessment must review all water systems for their aerosol potential, temperature, physical condition, cleanliness, and location. 3 Risk assessment data should include: makeup and system water analyses, system design, operating characteristics, and potential for equipment fouling due to scale and bioslime. improve results and reduce costs. He crawls upstream to discover manufacturing fluid and process changes, and then reacts ahead of time. He becomes involved in water treatment issues and checks performance of equipment outside the scope of his services. The representative must recognize downsides to proposed changes. For example, reducing circulating pumps to save energy may decrease flow velocities and turn heat exchangers into sedimentation tanks. Isolating (no flow) loops for energy savings may promote corrosion and uncontrolled microbiological growth. Cycling standby equipment at greater than one week frequencies may allow proliferation of bacteria to inoculate the system upon startup. It takes an experienced water-treater to know when these types of changes are prudent. Methods have been developed that quantify the subjective portion of the evaluation. Most of these involve a matrix consisting of a comprehensive list of qualities in the first column, a weighting factor determined by the end-user in the second, and a force-ranked rating in the third. Multiplying each score by its weighting factor and totaling all scores produces a single final score The Happiness Factor The most difficult portion of supplier evaluation to examine is the happiness factor. How much of my present satisfaction with the program is unrelated to system performance or cost? Advertisement formerly in this space. 3. Exhibiting Innovation and Foreseeing Problems The subjective aspect of supplier evaluation is the most difficult. However, one can examine a supplier s ability to continually demonstrate eagerness and innovation. When the representative is engaged in the treatment program, he s not concerned solely with routine testing, but rather strives to July 2007 ASHRAE Journal 55

7 Advertisement formerly in this space.

8 If there is a component of satisfaction that is not covered in the specification, then examine whether or not that criteria is appropriate. For instance, some managers want all information immediately communicated and want to be involved in every decision (high supplier visibility); while others value quarterly reviews and exception reporting, knowing the supplier is managing the details of the program (supplier invisibility). An ongoing program evaluation process helps to reduce the reliance on the happiness factor for supplier retention or change. 5. Knowing When a Cost Increase is Justified Owners are often approached for a cost increase due to a changed condition from the specification. The question is whether or not the so-called changed condition should have been foreseen during the bidding process. Manufacturing fluids and processes are constantly changing, so sometimes a cost increase is justified. Other times, it is an unjustified ploy by the supplier to increase sales or unnecessarily push one up the technology scale. Equipment and chemicals are closely interrelated. A sticking solenoid valve can cause chemical use to dramatically increase which is not a water treatment problem but rather a maintenance issue. New production equipment, accidental contamination of the cooling water (for example, by hydraulic oil), and new discharge restrictions are examples of changes that the supplier would not have foreseen (and for which they must be compensated). However, many common occurrences ought to have been anticipated and are not to be compensated. These include: 1) Sediment buildup from wind-blown dirt into a cooling tower causing additional biocide usage; 2) A makeup float that became stuck open but was repaired in a timely manner; and 3) Legionella entering a cooling tower requiring immediate disinfection. Advertisement formerly in this space. Conclusions No single correct method exists for selecting and managing a cooling water program. High-performance programs can range anywhere from nearly 100% vendor-managed to almost completely self-managed. Under any condition, however, it is a well-defined set of performance metrics, a disciplined data acquisition and analysis approach, and a mutual sense of ownership that drives success. Knowledge and application of several key elements during the front-end development, selection process, and ongoing periods can ensure a solid platform for balance of cost and performance. References 1. Chesney, W.W Preparation of bidding specifications for chemical services relating to cooling water and boiler treatments in industrial facilities. 57 th International Water Conference, p Simon, D.E Comprehensive specifications for contracted water treatment service programs. 58 th Annual International Water Conference, p Turvey, T., Kuchinski, J IWC The Legionella shift: how the risk from Legionnaires disease has changed the perception of water treatment. 67 th Annual International Water Conference. 4. Howard, K., Winters, M A performance-driven approach to cooling water treatment evaluation. 63 rd International Water Conference, p July 2007 ASHRAE Journal 57

RICHMOND PUBLIC SCHOOLS DIVISION OF PURCHASES 2395 Hermitage Road, Vatex Building RICHMOND, VIRGINIA May 24, 2016 ADDENDUM NO.

RICHMOND PUBLIC SCHOOLS DIVISION OF PURCHASES 2395 Hermitage Road, Vatex Building RICHMOND, VIRGINIA May 24, 2016 ADDENDUM NO. RICHMOND PUBLIC SCHOOLS DIVISION OF PURCHASES 2395 Hermitage Road, Vatex Building RICHMOND, VIRGINIA 23220-1307 May 24, 2016 ADDENDUM NO. 1 Invitation No.: BID#16-6721-5 Dated: May 13, 2016 Opening Date:

More information

RISK Management. Sustainable and Integrated Water Energy Solutions

RISK Management. Sustainable and Integrated Water Energy Solutions Legionella RISK Management Program Sustainable and Integrated Water Energy Solutions Legionellosis is the term used for infections caused by the inhalation of airborne droplets containing the Legionella

More information

TITLE: WATER TREATMENT PROGRAM FOR CHILLED WATER PLANTS THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR CLARIFICATIONS IN RED:

TITLE: WATER TREATMENT PROGRAM FOR CHILLED WATER PLANTS THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR CLARIFICATIONS IN RED: Procurement Department Bid Section Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 May 17, 20 ADDENDUM NUMBER: ONE (1) TITLE: WATER TREATMENT PROGRAM FOR CHILLED WATER

More information

RFP for Elevator Maintenance

RFP for Elevator Maintenance Housing Authority of the City of Shreveport Request for Proposals for Elevator Maintenance and Repair Services for the HACS Administrative Office at 2500 Line Avenue, Shreveport, LA 71104 Proposals due:

More information

EXHIBIT A UNIVERSITY OF NEVADA - LAS VEGAS WATER TREATMENT BEST PRACTICES

EXHIBIT A UNIVERSITY OF NEVADA - LAS VEGAS WATER TREATMENT BEST PRACTICES UNIVERSITY OF NEVADA - LAS VEGAS WATER TREATMENT BEST PRACTICES This document is designed to guide the UNIVERSITY OF NEVADA - LAS VEGAS HVAC systems through the difficult task of managing the water treatment

More information

To 3PL or Not to 3PL:

To 3PL or Not to 3PL: To 3PL or Not to 3PL: An Overview of Third Party Logistics Outsourcing 866.672.2862 m33integrated.com 511 Rhett Street, Suite 3 Greenville, South Carolina 29601 Third party logistics (3PL) is the business

More information

HIGH EFFICIENCY 0.5 & 0.25 MICRON COOLING WATER FILTRATION SYSTEM

HIGH EFFICIENCY 0.5 & 0.25 MICRON COOLING WATER FILTRATION SYSTEM HIGH EFFICIENCY 0.5 & 0.25 MICRON COOLING WATER FILTRATION SYSTEM THE HIGHEST QUALITY COMMERCIAL AND INDUSTRIAL WATER FILTRATION EQUIPMENT 28 APPLETON STREET HOLYOKE, MA 01040 Phone: 413/536-8186 Fax:

More information

EXHIBIT A. 1) General:

EXHIBIT A. 1) General: 1) General: EXHIBIT A FINDINGS OF FACT FOR EXEMPTION FROM COMPETITIVE BIDDING AND USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) METHOD OF CONTRACTING FOR TILLAMOOK PUD OPERATIONS CENTER AND

More information

Cooling Tower Water Management Plan. 901 Fifth Avenue

Cooling Tower Water Management Plan. 901 Fifth Avenue 2013 Cooling Tower Water Management Plan 901 Fifth Avenue Table of Contents I. INTRODUCTION II. GOAL III. SCOPE IV. RESPONSIBILITIES V. TIME PERIOD VI. PERFORMANCE METRIC VII. PROCEDURES AND STRATEGIES

More information

Addendum #4. Addendum No. 4

Addendum #4. Addendum No. 4 Addendum #4 Purchasing Services 4202 East Fowler Avenue, SVC 1073 Tampa, Florida 33620 (813) 974-2481 Web Address: http://www.usf.edu/business-finance/purchasing/public-bids/index.aspx October 27, 2017

More information

POSITION DESCRIPTION SYSTEM ENGINEER

POSITION DESCRIPTION SYSTEM ENGINEER POSITION DESCRIPTION SYSTEM ENGINEER I. OBJECTIVES The position of System Engineer was created to help the purpose for which the Association was organized, which is: Our mission at Benton Rural Electric

More information

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard.

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard. Quality Manual This manual complies with the requirements of the ISO 9001:2015 International Standard. Northeast Power Systems, Inc. 66 Carey Road Queensbury, New York 12804 Quality Manual Rev 0 Printed

More information

This paper is copyrighted (April 2007), and may not be redistributed or published in part or full without the author s permission.

This paper is copyrighted (April 2007), and may not be redistributed or published in part or full without the author s permission. This paper is copyrighted (April 2007), and may not be redistributed or published in part or full without the author s permission. A Creative Approach to Strategic Sourcing and Supplier Engagement Purchasing

More information

News. Power Generation 11. ph Control Reduces Acid Consumption in Neutralization Process up to 90 % Perspectives in Pure Water Analytics THORNTON

News. Power Generation 11. ph Control Reduces Acid Consumption in Neutralization Process up to 90 % Perspectives in Pure Water Analytics THORNTON Power Generation 11 Perspectives in Pure Water Analytics News THORNTON Leading Pure Water Analytics ph Control Reduces Acid Consumption in Neutralization Process up to 90 % THORNTON new instrumentation

More information

Page 1 of 5 The director's role in strategy development. Article from: Directors & Boards Article date: September 22, 2000 Author: STEINBERG, RICHARD M. ; BROMILOW, CATHERINE L. Despite inherent difficulties

More information

Legionella Mitigation

Legionella Mitigation Legionella Mitigation Better Have A Plan!!! Legionella bacteria John T. Dunford, CWT Regional Manager Bond Water Technologies, Inc. What is this ASHRAE 188-2015 ASHRAE 188-2015, entitled Legionellosis:

More information

AN INTRODUCTION HARFST AND ASSOCIATES, INC.

AN INTRODUCTION HARFST AND ASSOCIATES, INC. Harfst and Associates, Inc. Water Management Consultants William F. Harfst AN INTRODUCTION TO HARFST AND ASSOCIATES, INC. William F. Harfst Consultant HARFST AND ASSOCIATES, INC. P.O. Box 276 Crystal Lake,

More information

ONE POINT OF CONTACT Facility Services Manager

ONE POINT OF CONTACT Facility Services Manager Building Maintenance Solutions We are pleased to present this proposal for Building Maintenance Services for your offices. We have made an extensive survey of your facility in order to design a maintenance

More information

White Paper. Managed IT Services as a Business Solution

White Paper. Managed IT Services as a Business Solution White Paper Managed IT Services as a Business Solution 1 TABLE OF CONTENTS 2 Introduction... 2 3 The Need for Expert IT Management... 3 4 Managed Services Explained... 4 5 Managed Services: Key Benefits...

More information

HVAC WATER TREATMENT 1.01 RELATED CORNELL DESIGN AND CONSTRUCTION STANDARDS. D. Section Plumbing (Potable) Water Treatment

HVAC WATER TREATMENT 1.01 RELATED CORNELL DESIGN AND CONSTRUCTION STANDARDS. D. Section Plumbing (Potable) Water Treatment 232500 HVAC WATER TREATMENT PART 1 GENERAL 1.01 RELATED CORNELL DESIGN AND CONSTRUCTION STANDARDS A. Section 230510 Chilled Water Systems B. Section 230520 Heat Generation C. Section 230530 Clean Steam

More information

Ensuring Near-Perfect On-Time Performance

Ensuring Near-Perfect On-Time Performance Ensuring Near-Perfect On-Time Performance Examining the cost of failure-free service and the technology to support it Corporate Headquarters: 320 Interlocken Parkway, Suite 100 Broomfield, CO 80021 Phone:

More information

Rethinking the way personal computers are deployed in your organization

Rethinking the way personal computers are deployed in your organization IBM Global Technology Services August 2009 Rethinking the way personal computers are deployed in your organization Leveraging an innovative, end-to-end model to save time and reduce costs 2 IBM Global

More information

Cooling Tower Water Management

Cooling Tower Water Management Cooling Tower Water Management Cooling tower water systems are subject to corrosion, scaling, deposition, and biological fouling; which increase operating costs due to downtime and equipment replacement,

More information

IBM SMARTER COMMERCE: SPSS MUELLER, INC.

IBM SMARTER COMMERCE: SPSS MUELLER, INC. ROI CASE STUDY March 2014 IBM SMARTER COMMERCE: SPSS MUELLER, INC. THE BOTTOM LINE Mueller, Inc., a manufacturing company, chose IBM SPSS for predictive analytics to provide better insight into how its

More information

Management Information Systems, Sixth Edition. Chapter 13: Choices in Systems Acquisition

Management Information Systems, Sixth Edition. Chapter 13: Choices in Systems Acquisition Management Information Systems, Sixth Edition Chapter 13: Choices in Systems Acquisition Objectives Explain the differences among the alternatives to tailored system development: outsourcing, licensing

More information

New filter materials for hydraulic systems: Longer service life and reduced operating costs

New filter materials for hydraulic systems: Longer service life and reduced operating costs New filter materials for hydraulic systems: Longer service life and reduced operating costs Bosch Rexroth is introducing a new generation of filter media, using state-of-the-art materials and advanced

More information

Why the New Standard?

Why the New Standard? Why the New Standard? Quick Side-Bar We Currently Have Lots of Guidance Documents, Why do We Need Another One? Lots of Legionella Guidance Documents Lots of Legionella Guidance Documents The Law 40 Years

More information

SARBANES. Compliance with the Sarbanes-Oxley T H E I M P A C T O F F L E E T

SARBANES. Compliance with the Sarbanes-Oxley T H E I M P A C T O F F L E E T T H E I M P A C T O F SARBANES O N F L E E T Examined are the implications of the Sarbanes-Oxley Act on fleet incentive monies that are not capitalized into the cost of a vehicle, the sale of out-ofservice

More information

Saturation Index -100 F

Saturation Index -100 F Case History Report Dolphin Nonchemical Device Cooling Tower Device Evaluated While this is our third case history report (Dolphin III), on the "Dolphin Pulsed Power non chemical device (NCD) for water

More information

GUILFORD COUNTY SCHOOLS JOB DESCRIPTION JOB TITLE: PROGRAM ADMINISTRATOR III ENERGY / HVAC MAINTENANCE DEPARTMENT GENERAL STATEMENT OF JOB

GUILFORD COUNTY SCHOOLS JOB DESCRIPTION JOB TITLE: PROGRAM ADMINISTRATOR III ENERGY / HVAC MAINTENANCE DEPARTMENT GENERAL STATEMENT OF JOB GUILFORD COUNTY SCHOOLS JOB DESCRIPTION JOB TITLE: PROGRAM ADMINISTRATOR III ENERGY / HVAC MAINTENANCE DEPARTMENT GENERAL STATEMENT OF JOB Under occasional supervision, ensures that all utilities including

More information

Consequences of Poorly Performing Software Systems

Consequences of Poorly Performing Software Systems Consequences of Poorly Performing Software Systems COLLABORATIVE WHITEPAPER SERIES Poorly performing software systems can have significant consequences to an organization, well beyond the costs of fixing

More information

REPORT ON THE BENEFITS OF ICE- BASED THERMAL STORAGE FOR DISTRICT COOLING IN THE UAE MARKETS

REPORT ON THE BENEFITS OF ICE- BASED THERMAL STORAGE FOR DISTRICT COOLING IN THE UAE MARKETS REPORT ON THE BENEFITS OF ICE- BASED THERMAL STORAGE FOR DISTRICT COOLING IN THE UAE MARKETS Prepared by: Brady Consulting Services, Inc. SUMMARY ADVANTAGES OF THERMAL STORAGE WITH 1.1ºC WATER SUPPLY 1)

More information

ADDITIVE DEPLETION: IMPACT ON USEABLE OIL LIFE AND EQUIPMENT WEAR

ADDITIVE DEPLETION: IMPACT ON USEABLE OIL LIFE AND EQUIPMENT WEAR ADDITIVE DEPLETION: IMPACT ON USEABLE OIL LIFE AND EQUIPMENT WEAR Abstract Pentair Additives are introduced into lubrication and hydraulic oils in order to minimize the rate of wear occurring in costly

More information

Engineering for Legionella Control at Cooling Towers. Clive Broadbent AM, FIE Aust.

Engineering for Legionella Control at Cooling Towers. Clive Broadbent AM, FIE Aust. Engineering for Legionella Control at Cooling Towers Clive Broadbent AM, FIE Aust. www.broadbent.com.au Legionella in the environment Chain of Causation Total Microbial Control Temperature Biofilm Protozoa,

More information

Corrosion Monitoring in Cooling Water Systems

Corrosion Monitoring in Cooling Water Systems Corrosion Monitoring in Cooling Water Systems Application Note Efficient removal of heat is an economic consideration in the design and operation of cooling systems. Failure of these systems can have severe

More information

Cambium Care Services Guide

Cambium Care Services Guide Cambium Care Services Guide THIS SERVICES GUIDE IS DESIGNED TO HELP YOU SELECT THE CONFIGURATION OF SERVICES THAT BEST FITS YOUR ORGANIZATION S SUPPORT CAPABILITIES AND BUDGET. Cambium Networks Global

More information

Servicing All Makes and All Models of Equipment and Software

Servicing All Makes and All Models of Equipment and Software Customer Service Solutions Servicing All Makes and All Models of Equipment and Software Optimize Your Supply Chain. Total Life Cycle Support Optimizing the productivity and longevity of your investment

More information

COOLING TOWER WATER TREATMENT

COOLING TOWER WATER TREATMENT An Industrial Facility s Guide to COOLING TOWER WATER TREATMENT A PUBLICATION OF SAMCO TECHNOLOGIES TABLE OF CONTENTS 1 2 3 4 5 What Is a Cooling Tower Water Treatment System and How Does It Work? How

More information

DW Module 11: Administration Answer Key

DW Module 11: Administration Answer Key DW Module 11: Administration Answer Key What is an example of the use of a grab sample to cross calibrate a continuous sample? One example might be that the continuous chlorine residual analyzer should

More information

Recording and Quality Monitoring Systems Making the ROI Case

Recording and Quality Monitoring Systems Making the ROI Case Recording and Quality Monitoring Systems Making the ROI Case February 4, 2004 Jim Veilleux, VoiceLog LLC Recording-based quality monitoring systems ( RBMS ) are rapidly penetrating the contact center marketplace,

More information

The 5 Building Blocks of a CAPA Solution. Managing Corrective Actions/Preventive Actions for the Consumer Products Industry

The 5 Building Blocks of a CAPA Solution. Managing Corrective Actions/Preventive Actions for the Consumer Products Industry The 5 Building Blocks of a CAPA Solution Managing Corrective Actions/Preventive Actions for the Consumer Products Industry 1 Table of Contents 3 Introduction 5 Tackling Quality Issues & Incidents 8 Five

More information

Energy Project Measurement and Verification Procedures

Energy Project Measurement and Verification Procedures PDHonline Course E335 (8 PDH) Energy Project Measurement and Verification Procedures Instructor: George E. Thomas, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone &

More information

Workforce Solutions Guide

Workforce Solutions Guide Workforce Solutions Guide [Innovative Solutions To Everyday Challenges] Part 2 1/15 Control costs. Meet deadlines. Improve productivity. Capitalize on opportunities. Manage resource constraints. Build

More information

COOLING TOWER WATER TREATMENT

COOLING TOWER WATER TREATMENT COOLING TOWER WATER TREATMENT 1 2 3 1 2 3 OXIDIZING NON-OXIDIZING Solid BCDMH used to control problems in the system caused by microorganisms. Solid DBNPA used to control problems in the system caused

More information

Application Center Equipment Guide. Product Type Category Name Product. Heating & Cooling Equipment Unitary Packaged Heating & Cooling Air Conditioner

Application Center Equipment Guide. Product Type Category Name Product. Heating & Cooling Equipment Unitary Packaged Heating & Cooling Air Conditioner HVAC TECHNICAL SHEET GENERAL INFORMATION SMECO s Business Solutions program is designed to help commercial and industrial customers maximize energy efficiency and manage energy costs. With cost-saving

More information

BRINGING WATER TREATMENT IN HOUSE - MONITORING AND CONTROL STRATEGIES AND IMPROVED RESULTS AT NRG PHOENIX

BRINGING WATER TREATMENT IN HOUSE - MONITORING AND CONTROL STRATEGIES AND IMPROVED RESULTS AT NRG PHOENIX BRINGING WATER TREATMENT IN HOUSE - MONITORING AND CONTROL STRATEGIES AND IMPROVED RESULTS AT NRG PHOENIX MICHAEL FEHR, PH.D. FEHR SOLUTIONS, LLC AGENDA A VERY BRIEF HISTORY OF COOLING WATER TREATMENT

More information

An Epicor White Paper. Best Practices for ERP Implementation Success

An Epicor White Paper. Best Practices for ERP Implementation Success An Epicor White Paper Best Practices for ERP Implementation Success Table of Contents Introduction...1 Best Practices for ERP Implementation...3 Understand business processes and key requirements...3 Build

More information

Request for Proposals Town of Plymouth, New Hampshire

Request for Proposals Town of Plymouth, New Hampshire 1. General Information Request for Proposals Town of Plymouth, New Hampshire Building Energy Audits The Town of Plymouth is seeking bids for qualified individuals or firms to provide six (6) Building Energy

More information

5 STEPS TO TO DATA-DRIVEN BUSINESS DECISIONS

5 STEPS TO TO DATA-DRIVEN BUSINESS DECISIONS 5 STEPS TO TO DATA-DRIVEN BUSINESS DECISIONS INTRODUCTION Tons of companies today want to be data-driven, and with all of the powerful insights data can provide to guide your company, they should be. Yet,

More information

Issue in Focus: Designing Products for Performance, Risk, and Compliance. Leveraging Product Analytics to Optimize Design Decisions and Tradeoffs

Issue in Focus: Designing Products for Performance, Risk, and Compliance. Leveraging Product Analytics to Optimize Design Decisions and Tradeoffs Issue in Focus: Designing Products for Performance, Risk, and Compliance Leveraging Product Analytics to Optimize Design Decisions and Tradeoffs Tech-Clarity, Inc. 2013 Table of Contents Introducing the

More information

TrueSense* for Cooling

TrueSense* for Cooling Fact Sheet TrueSense* for Cooling Ready, Set, Go Whether serving manufacturing or comfort cooling processes, cooling tower system performance for operational efficiency, asset preservation, water conservation,

More information

This policy will outline the requirements for competitive bids on goods and services purchased by the College.

This policy will outline the requirements for competitive bids on goods and services purchased by the College. Policy Name: Procurement Sole Source/Competitive Bid Policy Updated/Reviewed: August 10, 2017 Effective Date: November 15, 2010 Office with Primary Responsibility: Procurement Services Offices with Secondary

More information

Managing User Service Level Expectations By Harris Kern s Enterprise Computing Institute

Managing User Service Level Expectations By Harris Kern s Enterprise Computing Institute Managing User Service Level Expectations By Harris Kern s Enterprise Computing Institute It is the objective of every IT organization to be the best service provider to their end-users. However, this is

More information

AP1000 European 9. Auxiliary Systems Design Control Document

AP1000 European 9. Auxiliary Systems Design Control Document 9.2 Water Systems 9.2.1 Service Water System The service water system (SWS) supplies cooling water to remove heat from the nonsafety-related component cooling water system (CCS) heat exchangers in the

More information

GRAND PRAIRIE ISD Executive Director, Maintenance & Operations (Page 1 of 6)

GRAND PRAIRIE ISD Executive Director, Maintenance & Operations (Page 1 of 6) GRAND PRAIRIE ISD Executive Director, Maintenance & Operations (Page 1 of 6) Job Title: Ex Director of Maintenance and Operations Wage/Hour Status: Exempt Reports To: Assistant Superintendent Pay Grade:

More information

WAREHOUSE EXECUTION SYSTEMS BUYERS GUIDE

WAREHOUSE EXECUTION SYSTEMS BUYERS GUIDE WAREHOUSE EXECUTION SYSTEMS BUYERS GUIDE BY: DAVE WILLIAMS Director of Software and Solution Delivery Westfalia Technologies, Inc. www.westfaliausa.com 717.764.1115 It s time to branch out Warehouse inefficiencies

More information

Table of Contents INTEGRATED MANAGEMENT SYSTEM GUIDANCE

Table of Contents INTEGRATED MANAGEMENT SYSTEM GUIDANCE Table of Contents INTRODUCTION... 3 THE CORE VALUES OF THE IMS... 3 IMPLEMENTATION & DEVELOPMENT... 3 TOP MANAGEMENT COMMITMENT... 4 RECOMMENDED INITIAL GOALS... 5 GAP ANALYSIS... 5 BUDGET & RESOURCES...

More information

FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT

FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT FSC36 Safe Feed/Safe Food (www.safefeedsafefood.org) is a facility certification program for the American Feed Industry Association (www.afia.org) Version 7.0

More information

GE Digital Executive Brief. Enhance your ability to produce the right goods in time to satisfy customer demand

GE Digital Executive Brief. Enhance your ability to produce the right goods in time to satisfy customer demand Enhance your ability to produce the right goods in time to satisfy customer demand Traditionally, successful production has relied heavily on skilled personnel. Experienced employees installed equipment

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL ACQUISITION & IMPLEMENTATION OF A CORPORATE WIDE BOX STYLED STANDARD LOCKERS Proposal Release Date: March 25, 2008 Proposal Due Date: April 25, 2008 Page - 1 - of 9 TABLE OF CONTENTS

More information

A beginners guide to moving to an ERP

A beginners guide to moving to an ERP A beginners guide to moving to an ERP 2 Contents This paper is for companies considering an ERP and looking to justify the investment in new technology. This paper will provide methods to identify and

More information

Underf loor For Schools

Underf loor For Schools The following article was published in ASHRAE Journal, May 2008. Copyright 2008 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes

More information

SANITARY DISTRICT OF MICHIGAN CITY, INDIANA APPLICATION FOR EMPLOYMENT An Equal Opportunity Employer

SANITARY DISTRICT OF MICHIGAN CITY, INDIANA APPLICATION FOR EMPLOYMENT An Equal Opportunity Employer The Sanitary District of Michigan City is seeking applicants for a Wastewater Treatment Plant Operator II position to operate, and maintain the District's wastewater treatment facility including primary,

More information

Vendor Support Agreements: A Competitive Weapon for Optimizing Organizational Assets

Vendor Support Agreements: A Competitive Weapon for Optimizing Organizational Assets 998-2095-07-02-15AR0 Vendor Support Agreements: A Competitive Weapon for Optimizing Organizational Assets by Brian Courchesne Executive summary For manufacturers, sustaining operations performance levels

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

Expert Reference Series of White Papers. Managing Risk An Integrated Approach

Expert Reference Series of White Papers. Managing Risk An Integrated Approach Expert Reference Series of White Papers Managing Risk An Integrated Approach 1-800-COURSES www.globalknowledge.com Managing Risk An Integrated Approach Gloria Cook Brown, Global Knowledge Instructor, PMP

More information

Tech Byte 11: Benefits of Filtration for Open Cooling Tower Systems

Tech Byte 11: Benefits of Filtration for Open Cooling Tower Systems The need for filtration of any cooling tower system is somewhat understood and accepted by most building professionals and plant operating engineers. However, for some, that need is finally driven home

More information

BOMA Chicago Brown Bag Lunch Hosted by Global Water Technology, Inc. Day, Month, Day, Year 12:00 1:00 p.m.

BOMA Chicago Brown Bag Lunch Hosted by Global Water Technology, Inc. Day, Month, Day, Year 12:00 1:00 p.m. Can Water Treatment Reduce Facility Operating Costs? An introductory presentation for Property Managers, Administrators, and Owners on the essentials of HVAC Water Treatment BOMA Chicago Brown Bag Lunch

More information

APPENDIX A - TECHNICAL SPECIFICATIONS. JEA Fleet Services Light Duty Equipment Maintenance and Repair

APPENDIX A - TECHNICAL SPECIFICATIONS. JEA Fleet Services Light Duty Equipment Maintenance and Repair APPENDIX A - TECHNICAL SPECIFICATIONS JEA Fleet Services Light Duty Equipment Maintenance and Repair 1. GENERAL SCOPE OF WORK This scope of work is looking for a Respondent(s) to provide JEA Fleet Services

More information

reasons to invest in a CMMS

reasons to invest in a CMMS 11 reasons to invest in a CMMS 11 reasons to invest in a CMMS 1. Effectively plan preventive maintenance The purpose of preventive maintenance (PM) is to plan scheduled inspections so that defects are

More information

Staff Augmentation Informational Inquiry

Staff Augmentation Informational Inquiry Staff Augmentation Informational Inquiry Introduction The Commonwealth s current contract vehicle for obtaining contract IT staffing expires on 6/30/2013. In preparation for developing a replacement contract,

More information

Pump selection: a real example

Pump selection: a real example 28 Feature WORLD PUMPS March 2010 Centrifugal pumps Pump selection: a real example Choosing the most appropriate and cost-effective centrifugal pump for a given duty requires strict adherence to a thorough

More information

Why Buy a Facilities Management System

Why Buy a Facilities Management System White Paper Why Buy a Facilities Management System A Publication of Overview In this white paper, we'll explore a number of reasons why a facilities management system is needed by many multi-location companies

More information

Cooling Water System Inspection Process. Presented by Craig Nicks, City of Onkaparinga

Cooling Water System Inspection Process. Presented by Craig Nicks, City of Onkaparinga Cooling Water System Inspection Process Presented by Craig Nicks, City of Onkaparinga What is the cooling water system used for? Air handling i.e. Commercial A/C Industrial / Commercial i.e. Plastics moulding

More information

A. Submit manufacturer s data, qualifying documents, and shop drawings on the proposed water treatment system before starting any work.

A. Submit manufacturer s data, qualifying documents, and shop drawings on the proposed water treatment system before starting any work. 15545 WATER TREATMENT ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 232516 An optional keynote to

More information

Estimating the Cost of Enterprise Software System Implementations: It s Often Buyer Beware. White Paper. Ben Harrison, MAVERICK Technologies

Estimating the Cost of Enterprise Software System Implementations: It s Often Buyer Beware. White Paper. Ben Harrison, MAVERICK Technologies Estimating the Cost of Enterprise Software System Implementations: It s Often Buyer Beware White Paper Ben Harrison, Introduction... 3 Cost of Ownership...3 Software Price, Discounting and Maintenance...4

More information

Data Lake or Data Swamp?

Data Lake or Data Swamp? Data Lake or Data Swamp? Keeping the Data Lake from Becoming a Data Swamp. 1 INTRODUCTION Increasingly, businesses of all kinds are beginning to see their data as an important asset that can help make

More information

White Paper Realizing the Benefits of Preventive Maintenance for Hydraulic Valves

White Paper Realizing the Benefits of Preventive Maintenance for Hydraulic Valves White Paper Realizing the Benefits of Preventive Maintenance for Hydraulic Valves Mickey Heestand, Hunt Valve, Inc. Downtime will happen. But, will it be on your terms, or will it be a middle-of-the-night

More information

HOW TO REDUCE YOUR ENERGY COSTS. A guide to temperature control efficiencies

HOW TO REDUCE YOUR ENERGY COSTS. A guide to temperature control efficiencies HOW TO REDUCE YOUR ENERGY COSTS A guide to temperature control efficiencies INTRODUCTION There is no denying that the spotlight is firmly on energy consumption within the manufacturing industry. As a nation

More information

WHAT ARE WE GOING TO COVER?

WHAT ARE WE GOING TO COVER? WHAT ARE WE GOING TO COVER? Steps to Prolong the Life of Your Maintaining Your & Why It s Important Preventative Maintenance : Industry Insider Perspectives Determining & Maintaining Quality & WHY YOU

More information

Benchmarking the Perfect Order: A Comprehensive Analysis of the Perfect Order in the Retail Industry Report GEORGIA SOUTHERN

Benchmarking the Perfect Order: A Comprehensive Analysis of the Perfect Order in the Retail Industry Report GEORGIA SOUTHERN Benchmarking the Perfect Order: A Comprehensive Analysis of the Perfect Order in the Retail Industry 2005 Report GEORGIA SOUTHERN Table of Contents Introduction... 3 What is a Perfect Order?... 3 Measuring

More information

economics of long-term leasing of membrane-based water make-up systems

economics of long-term leasing of membrane-based water make-up systems Water Technologies & Solutions technical paper economics of long-term leasing of membrane-based water make-up systems Author: John C. Kiernan, Ionics This paper was originally presented at the 58th Annual

More information

Texas International Oilfield Tools, Ltd.

Texas International Oilfield Tools, Ltd. Originated by: J. Tuttle Texas International Oilfield Tools, Ltd. QUALITY SYSTEM MANUAL Revision Date: May 26, 2010 Number: QSM000 Subject: Texas International Quality System Revision: A 1.0 INTRODUCTION

More information

Improving the Measurement of Sales Readiness Initiatives

Improving the Measurement of Sales Readiness Initiatives Improving the Measurement of Sales Readiness Initiatives Executive Summary Accurate measurement of the impact of training is both critical and challenging for most learning organizations, but sales teams

More information

Cooling Tower Treatment Chemicals

Cooling Tower Treatment Chemicals Cooling Tower Treatment 1) Scale & Corrosion Inhibitors 1. Cooling Tower Treatment Code Product Name 2048 Combined Scale Control / Anti-Foulant-cooling Systems 2202 Scale & Corrosion Inhibitor (Hard Water)

More information

Audit Report. Audit of Contracting and Procurement Activities

Audit Report. Audit of Contracting and Procurement Activities Audit Report August 2012 Recommended for Approval to the Deputy Minister by the Departmental Audit Committee on October 12, 2012 Approved by the Deputy Minister on October 18, 2012 Table of Contents Table

More information

Revolutionizing Asset Management in the Electric Power Industry

Revolutionizing Asset Management in the Electric Power Industry Revolutionizing Asset Management in the Electric Power Industry A Bentley White Paper Richard Irwin Senior Product Marketer Published: August 2017 www.bentley.com Introduction The industrial world is awash

More information

UNION PUBLIC SCHOOLS HAZARD COMMUNICATION PLAN

UNION PUBLIC SCHOOLS HAZARD COMMUNICATION PLAN UNION PUBLIC SCHOOLS HAZARD COMMUNICATION PLAN UNION PUBLIC SCHOOLS INDEPENDENT SCHOOL DISTRICT NO. 9 TULSA COUNTY, OKLAHOMA Union Public Schools Page 1 TABLE OF CONTENTS I. POLICY STATEMENT -------------------------------------------------------------------------------4

More information

A REPORT FROM THE OFFICE OF INTERNAL AUDIT

A REPORT FROM THE OFFICE OF INTERNAL AUDIT A REPORT FROM THE OFFICE OF INTERNAL AUDIT PRESENTED TO THE CITY COUNCIL CITY OF BOISE, IDAHO AUDIT / TASK: #12-08S1, Purchasing Compliance AUDIT CLIENT: Purchasing / Cross-Functional REPORT DATE: August

More information

White Paper: ITSC Planning: Performing Business Impact Analysis

White Paper: ITSC Planning: Performing Business Impact Analysis White Paper: ITSC Planning: Performing Business As given by ITIL, IT strives to ensure that the required technical and services facilities can be recovered within required and agreed business timescales.

More information

WHITE PAPER. How Startup Businesses Can Maximize Human Capital 10 Principles for building an effective human capital plan

WHITE PAPER. How Startup Businesses Can Maximize Human Capital 10 Principles for building an effective human capital plan WHITE PAPER How Startup Businesses Can Maximize Human Capital 10 Principles for building an effective human capital plan What is Human Capital? Your startup s competences, knowledge, and personality attributes

More information

EcoCooler Evaporative Cooler. Legionella Risk Assessment

EcoCooler Evaporative Cooler. Legionella Risk Assessment EcoCooler Evaporative Cooler Legionella Risk Assessment Dr. Tom Makin BA, PhD, FIBMS, Chartered Scientist. Directorate Manager of the Department of Medical Microbiology at the Royal Liverpool University

More information

Driving Performance with Embedded Business Intelligence Analytics in Your Voice Applications

Driving Performance with Embedded Business Intelligence Analytics in Your Voice Applications TABLE OF CONTENTS Introduction... 1 Lack of Voice Application Data Damages The Customer Experience... 2 Embedded BI Analytics in Your Voice Application Provides Invaluable Data on Customer Behaviors and

More information

Ten Steps to Evaluate and Select A Mid-Market Budgeting, Forecasting, and Reporting Solution

Ten Steps to Evaluate and Select A Mid-Market Budgeting, Forecasting, and Reporting Solution Ten Steps to Evaluate and Select A Mid-Market Budgeting, Forecasting, and Reporting Solution August 2007 BPM Partners, Inc. Six Landmark Square Stamford, CT 06901 203-359-5677 www.bpmpartners.com Introduction

More information

Microsoft REJ Framework: Step by Step

Microsoft REJ Framework: Step by Step Microsoft REJ Framework: Step by Step Quantifying the Business Value of Information Technology (IT) Investments Abstract IT managers today face challenges of delivering products to markets faster, making

More information

Multiple-Prime Top 10 Concerns Especially when

Multiple-Prime Top 10 Concerns Especially when Multiple-Prime Top 10 Concerns Especially when There have been many articles written about the benefits of multiple-prime contracting as a successful delivery method alternative for Public Owners especially

More information

Cooling Tower Systems Roles and Responsibilities. Presented by: Catherine Donoghue and Zina Maaliki Environmental Health Officers

Cooling Tower Systems Roles and Responsibilities. Presented by: Catherine Donoghue and Zina Maaliki Environmental Health Officers Cooling Tower Systems Roles and Responsibilities Presented by: Catherine Donoghue and Zina Maaliki Environmental Health Officers Welcome Introduction Legionnaires disease Cooling tower systems Roles and

More information

Cooling tower efficiency U2 Eco-efficiency resources for the food processing industry

Cooling tower efficiency U2 Eco-efficiency resources for the food processing industry Cooling tower efficiency U2 Eco-efficiency resources for the food processing industry Cool savings Many food processors operate cooling towers to meet the cooling needs of the factory. Cooling towers supply

More information

CONTINUAL SERVICE IMPROVEMENT: BRINGING IT TO LIFE

CONTINUAL SERVICE IMPROVEMENT: BRINGING IT TO LIFE CONTINUAL SERVICE IMPROVEMENT: BRINGING IT TO LIFE Author : Gary Case Version : 0 Date : August 2009 Location : Pink Elephant Inc. 1 EXECUTIVE SUMMARY If you are thinking about implementing ITIL processes

More information

Project Management Professional (PMP) Exam Prep Course 4 - Project Integration Management

Project Management Professional (PMP) Exam Prep Course 4 - Project Integration Management Project Management Professional (PMP) Exam Prep Course 4 - Project Integration Management Slide 1 Project Integration Management Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster

More information