Request for Proposals Town of Plymouth, New Hampshire
|
|
- Vivian Gregory
- 6 years ago
- Views:
Transcription
1 1. General Information Request for Proposals Town of Plymouth, New Hampshire Building Energy Audits The Town of Plymouth is seeking bids for qualified individuals or firms to provide six (6) Building Energy Audits and one Commissioning Audit. The auditor will work in conjunction with the Plymouth Area Renewable Energy Initiative (PAREI) who is administering the Town s AARA Funded Energy Efficiency and Conservation Block Grant (EECBG). Auditor must abide by all compliance and reporting requirements required by the American Recovery and Reinvestment Act Block Grants (particularly the Buy American and Davis Bacon requirements). These requirements known as Exhibit C- Special Provisions American Recovery and Reinvestment Act Standard Terms: EECBG Program can be viewed on the home page of Look for link titled ARRA Standard Terms for Plymouth Block Grant Additionally, the grantee and all contractors or service providers must adhere to all Federal, State and Local regulations and guidelines as it pertains to the activities of this project. 2. Scope of Professional Services Requested a) Perform Six (6) ASHRAE Level II Building Energy Audits in accordance with the attached Appendix A, Building Energy Audit Requirements. The municipal buildings to be audited are as follows: 1. Plymouth Elementary School, 43 Old Ward Bridge Road, built 1970 with major renovation in 1990 and Gross square footage: 117, Plymouth Regional High School. 88 Old Ward Bridge Road, Built 1970 with major renovations in Gross Square footage: 211, SAU 48 Office Building, 49 Old Ward Bridge Road, built 1970 with major renovation in Gross square footage: 2, Plymouth Town Hall. 6 Post Office Square, Plymouth, NH Built 1890 with major renovation in Gross square footage: 6, Plymouth Police Department. 334 Main Street s. Gross square footage: 7, Plymouth Fire and Rescue, 42 Highland Street, built Gross square footage: 5,204. b) Perform one Commissioning Audit for the Pease Public Library, 1 Russell Street. 12,000 gross square feet. The Pease Library has just completed major renovation and additions project. The renovation and additions nearly doubled the size of the Library and included installing a new
2 heat pump driven HVAC system, building controls, and envelope improvements and air sealing. The commissioning audit shall: Evaluate post-construction EUI on a kbtu/sf basis to determine savings and percentage change from pre-construction energy use Using as-built drawings, specifications, test and balance reports and other available project documentation associated with the renovation and additions to the Library as a guide, report on the results of the following on-site analysis o Examine and evaluate the systems installed for completeness, functionality, and quality o Review energy management system schedules and sequence of operations, identifying issues and suggesting changes as appropriate o Obtain trend data via the existing EMS and/or conduct witness tests and/or use independent metering equipment to confirm the following key sequence of operations Space temperatures within acceptable setpoint range Functional and appropriate equipment scheduling and/or space temperature setback Proper amount of outside air is being delivered to the building, including an affective economizer sequence (as applicable) Appropriate modulation of variable speed drive applications (as applicable) o Conduct a blower door test to evaluate post-construction building performance with respect to infiltration/exfiltration to identify any significant uncontrolled air exchanges Summarize methodology and key findings in a Commissioning Audit Report 3. Statement of Qualifications The proposal must include a statement of qualifications including but not limited to the following information: 1. Experience of the individual conducting building energy audits, specifically ASHRAE Level II. 2. List of related certifications held by the individual conducting the audits such as BPI, HERS, etc. 3. Familiarity with applicable NH State Energy and building Codes. 4. Proposal Content 4. The submittal shall include each of the following elements: 1. Identify a single individual who will serve as the point of contact for the duration of the project. 2. Names and resumes of all individuals that will be assigned to work on the audits. 3. A proposed schedule for completion. Project must be completed by 8/31/ List of information and assistance needed from the Town of Plymouth to complete the audits. 5. A sample Building Energy Audit of a similar building type prepared by the individual identified in Section Include a proposed fee structure for professional services rendered for each property. 5. The bids will be scored. The scoring will be based on the following criteria. Please address each criteria in your bid. o Level of experience of individuals conducting energy audits (30 points)
3 o Quality and level of detail in Sample Energy Audit Report (30 points) o Competitive Cost Proposal (30 points) o Certifications held by individual conducting energy audits (10 points) The Town of Plymouth reserves the right to reject all bids. 6. Insurance Requirements Certificates of Insurance are required and shall be provided on forms and endorsements approved for use in the State of New Hampshire by the Department of Insurance and issued by insurers licensed in New Hampshire. The insurance requirements as per the New Hampshire Energy Efficiency and Conservation Block Grant Agreement are and the Town of Plymouth are: 1. General Liability- $1,000,000 per occurrence and $2,000,000 aggregate 2. Automotive Liability- provided for all owned, non-owned and hired vehicles used in performance of services 3. Workers' Compensation- the statutory requirements of RSA Ch. 281 must be met. Sole Proprietors may be excluded. The certificates referred to above are required prior to contract execution. 7. Instructions to Bidders Craig Cadieux with Plymouth Area Renewable Energy will be the primary point of contact for the town and will assist the consultant in providing the information necessary to complete the Building Energy Audits. The Building Energy Audit bids shall be provided in an electronic format in addition to four (4) hard copies. Deadline for submittal: No later than 5:00 pm, Monday, May 2nd. Proposals shall be clearly marked: RFP 2011 Building Energy Audits. Submit hard copy proposals to: Craig Cadieux, Plymouth Area Renewable Energy, P.O. Box 753, 69 Main Street Plymouth, NH and submit electronic proposals to both craig@plymouthenergy.org and Paul J. Phillips, Chair, Town of Plymouth Energy Commission at plymouthpaul@live.com The Town of Plymouth has the right to reject incomplete bids. Questions regarding this Request for Proposals should be directed to: Craig Cadieux, (best), (alternative) or Craig@plymouthenergy.org. Proposals submittal via Fax will not be accepted. "Women and Minority owned businesses are encouraged to apply. EOE Scoring process Bids will be scored by a committee of three people using the above criteria.
4 Appendix A Building Energy Audit Requirements For the Town of Plymouth, NH Task 1: Site Assessment Planning 1. Obtain utility bills for evaluation to summarize historical building energy use and utility cost. 2. Use above data to benchmark building performance (kbtu/sf, or other metric). 3. Obtain and review available building documentation floor plans, design equipment schedules, control sequences. 4. Prepare survey plan and make arrangement with site personnel regarding trip scheduling, meetings, escorts and electricians to make meter connections to equipment, etc. Task 2: Site Survey and Assessment Conduct walk-through of the building(s), including occupied areas, roof, grounds, mechanical and electrical areas. In addition review kitchen, laundry, swimming pool and/or any other significant energy consuming process that may be on-site. The assessment process shall consist of the following: 1. Project kick-off meeting (review scope, schedule, team, roles and responsibilities). 2. On-site assessment (staff interviews, building use review, equipment condition, etc). Review and analyze documentation to understand original design and current operation of existing systems (HVAC, lighting and ATC design drawings, sequences of operation, operating procedures, point lists, etc.). Review and obtain operating data on following equipment: Main Air Handling Units Rooftop Units Kitchen and Toilet Exhaust Fans CHW Systems (as applicable), plus associated pumps and cooling towers. Heating System: Heating boilers and associated pumps. Domestic Hot Water Systems. Building Automation System. Envelope: Make note of areas with air balance issues. Other systems laundry, swimming pool, gas or air compressors, process systems. Lighting System: Sample of fixtures and their controls, including review of potential technology update for exits signs and other. Site work shall include spot measurements of building temperature, humidity, CO 2, as well as fan and pump kw. If not already, Engineer shall setup trends on the EMS to confirm system shutdown, reset and modulation as expected. Use of independent trending devices shall be used, if trending capability is not available on existing EMS. 3. Develop recommendations and discuss with site personnel while on-site (exit interview). Improvement recommendations might include: Lighting updates Operation and maintenance policy changes. Repair/re-calibration of identified or likely deficiencies. For example, air balance or ventilation issues. Revisions to sequences of operation to improve performance.
5 Addition of control points/control algorithms to provide additional control capabilities and optimization. Design of equipment modifications/improvements to enhance building energy performance and/or reduce cost of operations. For example new high efficiency chiller, boiler or packaged systems. EMS trend logging and/or independent data logging of selected points to identify deficiencies in the sequences of operation for systems recommended for retrocommissioning. Test and balancing work on select systems. Task 3: Evaluation and Reporting Conduct a BIN-weather type energy evaluation of all major energy consuming equipment in the building to be calibrated to historical energy used as determined in Task 1. Use above evaluation (model) as basis for savings calculations by running alternates using updated operating or performance parameters. Research and obtain pricing on major new equipment; use standard cost estimating practices to estimate installed cost for balance of system updates. Develop outline specifications for project opportunities. Develop implementation plan, including suggested follow-on engineering activities. TASK 4: Renewable energy opportunities Provide a high-level assessment of renewable and distributed energy measures which: Provides recommendations on the potential/viability of various renewable/distributed energy technologies; Identifies available grants and incentives and sources of funding; and Analyzes costs and savings comparing current and future costs of electric and thermal energy with and without each technology assessed. TASK 5: Energy Purchasing and Procurement Strategies Identify energy purchasing and procurement strategies for each facility by: Developing a load profile for each electric and fuel account; Providing an analysis of the utility tariff under which the facility is currently served; and Assessing potential savings by purchasing from third party suppliers. Deliverable Provide an energy assessment report consisting of the following: Executive Summary with project summary table outlining anticipated areas of energy reduction measures with estimated cost, energy savings, cost savings, and simple payback for each item, including any potential utility rebates. Brief facilities description. Energy use summary including breakout of estimated equipment energy use. Energy conservation measure descriptions including outline performance specifications, and implementation plans. Renewable energy opportunities with economic analysis Brief description of any item(s) considered which is not recommended or has been shelved for economic reasons. Appendix containing cost estimates, savings calculations, and any related backup data.
REQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I
Dover School District (Owner) requests written proposals to secure commissioning authority (CxA) services for the renovations project at the Garrison Elementary School in Dover, New Hampshire. The Owner
More informationConnecticut Housing Finance Authority. Construction Guidelines: Energy Conservation 2019
Connecticut Housing Finance Authority Construction Guidelines: Energy Conservation 2019 These Guidelines are effective I. Energy Conservation Guidelines Energy efficiency is strongly encouraged. An objective
More informationREQUEST FOR PROPOSAL TO PROVIDE DESIGN AND BUILD SERVICES FOR THE RE-ROOF OF THE PUBLIC LIBRARY / SAM FOX MUSEUM DUE MARCH 2, 2013
REQUEST FOR PROPOSAL TO PROVIDE DESIGN AND BUILD SERVICES FOR THE RE-ROOF OF THE PUBLIC LIBRARY / SAM FOX MUSEUM DUE MARCH 2, 2013 The City of Dillingham is the owner of the Dillingham City Library / Sam
More informationCommercial Retro-Commissioning Program Manual for 2015 SECTION 1
Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.
More informationREQUEST FOR QUALIFICATIONS DESIGN PROFESSIONAL
FACILITIES MANAGEMENT Planning, Design & Construction REQUEST FOR QUALIFICATIONS DESIGN PROFESSIONAL BOWEN SCIENCE BUILDING MODERNIZE BUILDING SYSTEMS Project No. 0548201 October 24, 2014 The University
More informationENERGY AUDIT REPORTS SUMMARY
Steven Winter Associates, Inc. 293 Route 18, Suite 330 Telephone (866) 676-1972 Building Systems Consultants East Brunswick, NJ 08816 Facsimile (203) 852-0741 www.swinter.com February 16, 2011 Sussex Community
More informationMultifamily Upgrade Program 2017 Partner Orientation
Multifamily Upgrade Program 2017 Partner Orientation Matt Jones, Technical Manager, TRC January 18, 2017 PG&E refers to the Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. 2010 Pacific
More informationEnergy Audits: Lessons Learned Over 30 Million Square Feet
Energy Audits: Lessons Learned Over 30 Million Square Feet Presented to: Environment, Energy Security & Sustainability By: Corry W Freeman, CEM AMEC Earth & Environmental, Inc. Midwest Plaza Building 800
More informationVILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information
VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction
More informationT H E T O W N O F G U I L F O R D V E R M O N T
Project Title: Contact: Capital Needs Assessments Town of Guilford Buildings Peder Rude, Town Administrator Email: pederrude@guilfordvt.net (802) 254-6857, ext. 105 Town of Guilford 236 School Road Guilford,
More informationConnecticut Housing Finance Authority. Construction Guidelines: Energy Conservation 2018
Connecticut Housing Finance Authority Construction Guidelines: Energy Conservation 2018 These Guidelines are effective January 1, 2018 I. Energy Conservation Guidelines Construction Guidelines: Energy
More informationProposals must be received in the Office of the City Manager no later than 2:00 p.m. on December 3, 2018.
REQUEST FOR PROPOSAL Proposals are now being accepted in the Office of the City Manager, 745 Forest Parkway, Forest Park, Georgia 30297 for: COMPREHENSIVE CLASSIFICATION & COMPENSATION STUDY FOR THE CITY
More informationREQUEST FOR COMPETITIVE PROPOSALS FOR ARCHITECTURAL SERVICES CITY OF PERRIS
REQUEST FOR COMPETITIVE PROPOSALS FOR ARCHITECTURAL SERVICES BY CITY OF PERRIS Perris, California December 4 th, 2018 City of Perris is requesting Competitive Proposals from licensed architectural firms
More informationREQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa #
REQUEST FOR PROPOSAL Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # Addendum #1 Issued Wednesday, February 10, 2016 Changes: Item #01: Item #02: Section
More informationProgram Ally On-Boarding Process and Criteria for Scoping Audits, Engineering Studies and Retro and Re- Commissioning (RCx) Investigations
for Scoping Audits, Engineering Studies and Retro and Re- Commissioning (RCx) Investigations Thank you for your interest in being a Program Ally, working with your customers to support their participation
More informationREQUEST FOR PROPOSALS ENERGY AUDIT GASTONIA HOUSING AUTHORITY MARCH 23, 2009
REQUEST FOR PROPOSALS ENERGY AUDIT GASTONIA HOUSING AUTHORITY MARCH 23, 2009 1.0 ADVERTISEMENT The Gastonia Housing Authority (GHA) hereby requests proposals from qualified firms to provide services to
More informationRequest for Qualifications
Request for Qualifications For Newport School District Proposals Due July 16, 2018 2:00 p.m. Request for Qualifications: Energy Performance Contracting Services Page 2 of 14 Table of Contents REQUEST FOR
More informationUSD 497. Request for Qualifications Commissioning Engineers Building Commissioning Services. August 11, 2017
USD 497 Request for Qualifications Commissioning Engineers Building Commissioning Services August 11, 2017 1 INTRODUCTION Lawrence Public Schools, in accordance with the policies of the Board of Education,
More informationSouth Carolina Society for Hospital Engineers
South Carolina Society for Hospital Engineers Selecting Energy Partners: Criteria & Pitfalls and the Top 10 Ways to Reduce Energy in a Hospital Presented by Jon Dierking, PE, CEM, LEED AP Director of Energy
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS FOR COMPENSATION STUDY Proposals Due: November 3, 2016, 4:00 PM 1.0 OBJECTIVE SECTION 1 SUBMITTAL PROCEDURES & DEADLINE The City of Signal Hill is seeking proposals from qualified
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction November 26, 2014 Re: Request for Qualifications - Commissioning Services Bowen Science Building Modernize Building Systems University of Iowa The
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction February 17, 2015 Re: Request for Proposals- Commissioning Services Madison Street Residence Hall Construct Facility University of Iowa The University
More informationSECTION 900: BUILDING AND SITES
PROCEDURE TITLE: Building & Grounds Maintenance & Development Policy Energy Conservation POLICY NO: 902.50P1 PAGE 1 of 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 ENERGY
More informationSouth Whidbey School District - Elementary Kitchen Remodel Project - General Information p - 1
Request for Proposal for Design Services South Whidbey Elementary School Kitchen Remodel Project: F2017-03-01 The South Whidbey School District is seeking qualified design consultants to submit a proposal
More informationNew York State Contract Reporter
The New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together Statements of Qualifications are sought from engineering firms to provide
More informationBETA OPTION 1: PERFORMANCE RATING METHOD. Section General Information
LEED-CS 2. Certification Submittal Template OPTION 1: PERFORMANCE RATING METHOD I confirm that the energy simulation software used for this project has all capabilities described in EITHER section `G2
More informationEnergy Reduction Programs: Understanding, Implementing & Delivering. PL Energy Services
Energy Reduction Programs: Understanding, Implementing & Delivering PL Energy Services PL Energy Services Value to Condominium Directors Control Maintenance Fees Maximize Rebates Measurement & Verification
More informationRetro-Commissioning in Hospitals
Retro-Commissioning in Hospitals American Society of Healthcare Engineering () Introduction Elements of the Health Facility Retro-Cx Process Retro-Cx Case Studies Hospital Hospital Oklahoma Heart Hospital
More informationCITY OF NEWARK CITY HALL COMPLEX City Hall Building Police Building Courthouse ENERGY ASSESSMENT. for NEW JERSEY BOARD OF PUBLIC UTILITIES
CITY OF NEWARK CITY HALL COMPLEX City Hall Building Police Building Courthouse ENERGY ASSESSMENT for NEW JERSEY BOARD OF PUBLIC UTILITIES CHA PROJECT NO. 21823 February 2011 Prepared by: 6 Campus Drive
More informationREQUEST FOR PROPOSALS. Request for Proposals for Classification Pay and Benefits Study (A )
CITY OF TUSCALOOSA ) STATE OF ALABAMA ) REQUEST FOR PROPOSALS TO: FROM: RE: Qualified Firms The City of Tuscaloosa, Alabama Request for Proposals for Classification Pay and Benefits Study (A17-0172) DATE
More informationEnergy Trigger (A Existing Building Upgrade Mechanism Model)
Trigger (A-11.2.1.2 Existing Building Upgrade Mechanism Model) Applicability All Building Permit applications for projects related to existing buildings are required to follow the energy upgrade trigger
More informationCity of Dawson Creek Request for Proposals No
City of Dawson Creek Request for Proposals No. 2011-29 SANITARY SEWER MASTER PLAN The City of Dawson Creek is requesting proposals for the creation of a Sanitary Sewer Master Plan. All contract documents
More informationENHANCED BUILDING OPERATIONS PROGRAM
ENHANCED BUILDING OPERATIONS PROGRAM TABLE OF CONTENTS Introduction 1 Building eligibility 2 How to take part 3 Financial incentives 4 Technical assistance and guide 5 System investigation templates 5
More informationENERGY AUDIT. Prepared For: Wayne Public School District. John D. Maso, Director of Facilities Mgmt. Office of Building Services
Prepared For: Wayne Public School District John D. Maso, Director of Facilities Mgmt. Office of Building Services ENERGY AUDIT Prepared By: Dome-Tech, Inc. Prepared Under the Guidelines of the State of
More informationFact Sheet. Commissioning WHAT IS THE PURPOSE OF THIS REQUIREMENT? WHAT VALUE DOES IT PROVIDE TO THE OWNER? HOW DOES IT SAVE ENERGY?
Commissioning Fact Sheet Funding for this publication is provided by the Northwest Energy Efficiency Alliance. OCTOBER 2017 VOLUME 1, ISSUE 2 WHAT IS THE PURPOSE OF THIS REQUIREMENT? There is a saying
More informationImplementing Low-Cost Energy Savings Projects & Conducting Energy Audits
AEP Ohio Customer Seminar Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits Presented by: Julie Birchfield Customer Manager Energy Optimizers, USA May, 2018 Test your Energy IQ 11
More informationGas Optimization Study Program Application
Instructions for Use All Gas Optimization Studies must receive pre-approval from the program BEFORE the study begins. For detailed instructions, please refer to the steps below. If you have any questions,
More informationProcuring and Financing Energy Efficiency. September 20, 2011
Procuring and Financing Energy Efficiency September 20, 2011 Oro Valley, Arizona Located just a few miles north of Tucson, Arizona Incorporated in 1974 with 1,500 residents Over 41,000 residents today
More informationREQUEST FOR PROPOSAL. HRIS Human Resources Information Software Fort Morgan, Colorado
REQUEST FOR PROPOSAL HRIS Human Resources Information Software Fort Morgan, Colorado October 7, 2014 Michael Boyer Director, Human Resources and Risk Management CITY OF FORT MORGAN P.O. BOX 100 FORT MORGAN,
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa
More informationEnergy Efficiency Solutions for Multifamily Housing. Clark Energy Group LLC
Energy Efficiency Solutions for Multifamily Housing Clark Energy Group LLC 1 Agenda About Clark Energy Group Energy Service Company (ESCO) Overview ESCO Services Utility Rate Forecasts Making the Decision
More informationPROFESSIONAL SERVICES DESCRIPTION FOR THE POSITION OF: Building Commissioning Services
PROFESSIONAL SERVICES DESCRIPTION FOR THE POSITION OF: Building Commissioning Services SUBMISSION DEADLINE: October 23, 2009 11:00am FAIR AND OPEN PUBLIC SOLICITATION PROCESS FOR PROFESSIONAL SERVICES
More informationCOMMISSIONING REQUIREMENTS NEW YORK CITY COMMERCIAL CODE
COMMISSIONING REQUIREMENTS NEW YORK CITY COMMERCIAL CODE For New and Substantial Renovation OVERVIEW New York State has established significant energy goals in its Reforming the Energy Vision strategy.
More informationDIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING
DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York
More informationCommercial Retro-Commissioning Program Manual for 2019 SECTION 1
Commercial Retro-Commissioning Program Manual for 2019 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.
More informationNational Grid USA Service Company. Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects. Final Report
National Grid USA Service Company Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects Final Report July 11, 2010 Submitted to: National Grid USA Service Corporation Waltham, MA Submitted
More informationCity of Sultan Request for Proposals City Attorney Services
The City Council of the ( City ) invites interested law firms and individuals with a minimum of seven (7) years of municipal experience to submit a written proposal to provide City Attorney services. As
More informationNew York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together
The New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together This document printed Friday, 04/15/2016 Contracting Opportunity Title:
More informationAbsolute Energy Raters Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither
More informationMay 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS
May 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS You are hereby invited to submit a proposal to the McPherson Implementing Local Redevelopment Authority (hereafter referred
More informationGeoff Howland. Value Development Manager
Geoff Howland Value Development Manager Chevron Energy Solutions MacArthur Plaza 5525 N. MacArthur Blvd Suite 290 Irving, TX 7 75038 Tel 972.550.3045 Cel 972.757.9154 Fax 972.550.3049 ghowland@chevron.com
More informationPromulgation Details for 1 RCNY
Promulgation Details for 1 RCNY 103-07 This rule became effective on October 13, 2012. Since such date, one or more amendments have been made to this rule. Each rule amendment has its own effective date
More informationNation Environmental Policy Act (NEPA)
COMPLIANCE WITH AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) PROVISIONS In an effort to let ARRA SECO Sub-recipients know what the major federal contract requirements will be, SECO Stimulus is providing
More informationHOUSING AUTHORITY OF THE CITY OF BOULDER (dba Boulder Housing Partners)
HOUSING AUTHORITY OF THE CITY OF BOULDER (dba Boulder Housing Partners) SOLICITATION TYPE: DESCRIPTION: Request For Proposals Paperless Invoice Automation Software ISSUE DATE: 04/03/2018 DUE DATE: 04/20/2018
More informationCentre for Addiction and Mental Health Queen Street Campus Energy Conservation and Demand Management Plan
Centre for Addiction and Mental Health Queen Street Campus Energy Conservation and Demand Management Plan In Transition to Sustainable Infrastructure The Centre for Addiction and Mental Health is in the
More informationNORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES
NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES September 12, 2008 INTRODUCTION North Dakota Department of Transportation (NDDOT) is seeking an asbestos
More informationStrategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions
Strategies for Persistence: Measurement and Verification Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The
More informationREQUEST FOR PROPOSALS YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS
REQUEST FOR PROPOSALS GUTHRIE MEMORIAL LIBRARY ENVELOPE REHABILITATION YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS Table of Contents Section 1: Background...... 2 Section 2: Scope of Services... 2 Section
More informationThe deadline for submittal of proposals is 4:00 PM, Pacific Time, January 8, 2014.
CITY OF BAINBRIDGE ISLAND, WASHINGTON REQUEST FOR PROPOSALS CLASSIFICATION AND COMPENSATION STUDY INTRODUCTION The City of Bainbridge Island, Washington invites proposals from qualified consulting firms
More informationDCAS Energy Management. August 15, 2014 Ellen Ryan & Mike Dipple
DCAS Energy Management August 15, 2014 Ellen Ryan & Mike Dipple DCAS Energy Management Mission DCAS Energy Management (DEM) serves as the hub for City government s energy management. DEM provides energy
More informationRequest for Proposals: New Hangar Building Project, Port of St. Helens Scappoose Industrial Airpark
Request for Proposals: New Hangar Building Project, Port of St. Helens Scappoose Industrial Airpark Columbia City, Oregon December 2017 Purpose The Port of St. Helens, a municipal corporation and port
More informationEnergy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT
Report Clayville Elementary School October 2016 3 George Washington Highway, Clayville, RI 02815 Clayville Elementary School Summary of Findings On behalf of the School Building Authority at Rhode Island
More informationEnergy Retrofit Loan Program
Energy Retrofit Loan Program Service Provider Profile General Firm Information Altanova & Taitem Engineering, PC 11-05 44th Drive, Long Island City, NY 11105 Primary Contact: Kendra Pierre-Louis, 347-732-3041,
More informationGround Transportation Management Services
ONE (1) HARDCOPY ORIGINAL AND ONE (1) ELECTRONIC COPY FLASH DRIVE MUST BE SUBMITTED REQUEST FOR INFORMATION - RFI #PGT-2018-002 Ground Transportation Management Services Department of Ground Transportation
More informationEnergy Study. Commercial Custom Design Program Retrofit Projects. November 2014
Energy Study Commercial Custom Design Program Retrofit Projects November 2014 Table of contents 1.0 Energy Study Guide 2 1.1 Introduction 2 1.2 Eligibility requirements 2 1.3 General requirements 3 2.0
More informationMassachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant
Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant RFP FY2017-BFD-01 Release Date: May 8 th, 2017 Applications Due: June 23 rd, 2017 1. PROGRAM SUMMARY
More informationOPTION 1: PERFORMANCE RATING METHOD
OPTION 1: PERFORMANCE RATING METHOD I confirm that the energy simulation software used for this project has all capabilities described in EITHER section `G2 Simulation General Requirements' in Appendix
More informationWEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES
1. Introduction WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES The Town of West Yellowstone (Town) is seeking a qualified
More informationREQUEST FOR BIDS Supply and Delivery of Swimming Pool Chemicals FY 1819
REQUEST FOR BIDS Supply and Delivery of Swimming Pool Chemicals FY 1819 Objective: Pleasant Hill Recreation & Park District (District) is seeking competitive sealed bids for the supply and delivery of
More informationSTATE OF NEW JERSEY Honorable Jon S. Corzine, Governor
SCOPE OF WORK ENERGY AUDIT & COGENERATION (CHP) FEASIBILITY STUDY Vineland Developmental Center East Campus Vineland, Cumberland County, N.J. PROJECT NO. A1098-00 STATE OF NEW JERSEY Honorable Jon S. Corzine,
More informationRequest for Proposal: City of Claremont Parking Garage Evaluation & Maintenance Program
Request for Proposal: City of Claremont Parking Garage Evaluation & Maintenance Program October 2015 Page 1 of 10 Table of Contents 1.0 General Information 2.0 Evaluation & Maintenance Program Overview
More informationCITY OF HAPEVILLE CITY ATTORNEY SERVICES
CITY OF HAPEVILLE CITY ATTORNEY SERVICES REQUEST FOR PROPOSALS The Mayor and City Council of the City of Hapeville (the City) invite interested legal firms or qualified individuals to submit written proposals
More informationHigh Impact Hotel Projects
High Impact Hotel Projects Greater Boston Energy Efficient Hotels Conference December 6, 2012 Agenda High Energy Impact Projects Case Studies Millennium Bostonian Viking Hotel Available Resources Questions
More informationBetter By Design Energy Efficiency in Needham s Public Construction Projects
Better By Design Energy Efficiency in Needham s Public Construction Projects Green Needham Monday, November 26 th, 2012 7:00PM Needham Public Library Energy Efficiency in Town Projects Presenters tonight
More informationTechnical Retro-Commissioning of Existing Buildings
Standard S0 0 0 Technical Retro-Commissioning of Existing Buildings Review Draft (--) This draft has been recommended for public review by the responsible project committee. To submit a comment on this
More informationGreen Retrofit. Why you should consider it, what it means, and how to get it done
Green Retrofit Why you should consider it, what it means, and how to get it done Table of Contents What is green retrofit and green rehab Fundamental Principals Why the Demand? Why it is important A macro
More informationReceive a no-cost detailed water audit to learn about your building s water use and how you can save water and money.
Multi-Residential Water Audit Program Application Form Receive a no-cost detailed water audit to learn about your building s water use and how you can save water and money. These audits will provide tailored
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER
More informationREQUEST FOR PROPOSAL
REQUEST FOR PROPOSAL ACQUISITION & IMPLEMENTATION OF A CORPORATE WIDE BOX STYLED STANDARD LOCKERS Proposal Release Date: March 25, 2008 Proposal Due Date: April 25, 2008 Page - 1 - of 9 TABLE OF CONTENTS
More informationLocal Government Energy Audit:
Local Government Energy Audit: i Energy Audit Report Lift Station #1, 3, 5, 6, 7, 8, and 9 Copyright 2018 TRC Energy Services. All rights reserved. Reproduction or distribution of the whole, or any part
More informationRetro-commissioning and on-going commissioning 23 November 2016
Retro-commissioning and on-going commissioning 23 November 2016 1 CONTENTS 1. Needs for Retro-Commissioning (RCx) 2. Retro-Commissioning (RCx) Definition and Scope 3. Briefing of RCx Process 4. Alternative
More informationusername: U16062 password: 8ojhiog2
University of Illinois at Urbana-Champaign Request for Professional Services Qualifications (QBS): Bevier Hall - Infrastructure Renovation Phase 2 First published September 23, 2015 QBS #PSSU16062 Project
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction February 26, 2015 Re: Request for Proposals- Commissioning Services College of Public Health Building - Fit Out Fifth Floor University of Iowa The
More informationTechnology Services RFP Town of Hooksett. Administration Department Dr. Dean Shankle May 2, 2019
Town of Hooksett Administration Department Dr. Dean Shankle May 2, 2019 REQUEST FOR PROPOSAL Proposal for TECHNOLOGY SERVICES Bid #18-05 Invitation to Bid Acceptance Date: 10:00 am, June 4th, 2018 Sealed
More informationMASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK
MASSACHUSETTS STATE COLLEGE BUILDING AUTHORITY REQUEST FOR QUALIFICATIONS TRADE CONTRACTOR SERVICES PART I PROJECT INFORMATION AND DESCRIPTION OF WORK DATE ISSUED: January 10, 2018 DEADLINE FOR WRITTEN
More informationREQUEST FOR PROPOSAL PHOTOGRAPHY SERVICES
Prepared by 3fold Communications for SouthEast Alaska Regional Health Consortium (SEARHC) REQUEST FOR PROPOSAL for PHOTOGRAPHY SERVICES Healthy Is Here Campaign Proposals are due 5:00 p.m., Pacific time,
More informationRetrocommissioning Investigation Study of the Sheraton Chicago Hotel
Retrocommissioning Investigation Study of the Sheraton Chicago Hotel & Towers Cityfront Center Tracy Phillips May 4, 2007 May 4, 2007 You can go anywhere you want, if you look serious and carry a clip
More informationMAP Guidelines and Energy Efficiency and Sustainability Guidelines for MIP Reduction
MAP Guidelines and Energy Efficiency and Sustainability Guidelines for MIP Reduction September 9, 2016 Maximizing building efficiency, sustainability, and profitability for clients nationwide. Other Multifamily
More informationSTATE OF NEW JERSEY Honorable Jon S. Corzine, Governor
SCOPE OF WORK FACILITY ENERGY AUDIT New Lisbon Developmental Center Woodland Twp, Burlington County, N.J. PROJECT NO. A1085-00 STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor DEPARTMENT OF THE TREASURY
More informationREQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES For the renovation of existing apartment buildings August 15, 2016 INVITATION Bath Housing Development Corporation is soliciting proposals for
More informationB U I L D I N G P E R M I T A P P L I C A T I O N
B U I L D I N G P E R M I T A P P L I C A T I O N City of Sand Springs, Oklahoma Sand Springs Fire Department Neighborhood Services Department 108 E. Broadway, Sand Springs ok 74063 Phone: (918) 246-2500
More informationMissoula Parks & Recreation Missoula, Montana. California Street Bridge Repair and Maintenance PROJECT PR10-08CSB DESIGN/BUILD RFQ & PROJECT SCOPE
Missoula Parks & Recreation Missoula, Montana California Street Bridge Repair and Maintenance PROJECT PR10-08CSB DESIGN/BUILD RFQ & PROJECT SCOPE 1 1.0 PROJECT INTRODUCTION Project Name: California Street
More informationEA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE
THRESHOLD ATTEMPTED LEED 29 for New Construction and Major Renovations EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE Project # 138123 Jacobs Hall All fields and uploads are required unless otherwise noted.
More informationMEASURING NZE HOME PERFORMANCE IN THE NORTHEAST
MEASURING NZE HOME PERFORMANCE IN THE NORTHEAST Nick Collins, ERS Ryan Pollin, ERS Headquarters: 120 Water Street, Suite 350, North Andover, MA 01845 With offices in: CA, CT, ME, NY, OR, TX, VT www.ers-inc.com
More informationSaving Energy on a Tight Budget
IASB * IASA * IASBO JOINT ANNUAL CONFERENCE Chicago, Illinois November 19, 2011 Saving Energy on a Tight Budget Jean Ascoli Registered Architect, Energy Analyst Greg Swiss Energy Engineer SEDAC University
More informationREQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County
REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County Proposals Due: 10:00 A.M., Thursday, March 28, 2019 Address Proposals
More informationREQUEST FOR PROPOSAL FOR. CONSTRUCTION MANAGER and DESIGN TEAM FOR. Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER and DESIGN TEAM FOR Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH December 2010 I. GENERAL The Urban Redevelopment Authority of
More information2.2 The Purposes and Advantages of a Central Utility Plant
2.2 The Purposes and Advantages of a Central Utility Plant The purpose of the Central Utility Plant (CUP) at NIST is to provide steam, chilled water, and compressed air for hot and cold water, warm and
More informationLocal Government Energy Audit: Energy Audit Report
Local Government Energy Audit: Energy Audit Report Panzer Athletic Center Copyright 2017 TRC Energy Services. All rights reserved. Reproduction or distribution of the whole, or any part of the contents
More information