AUTOMOTIVE CORE TOOLS; SPC, MSA, FMEA, APQP/CONTROL PLAN
|
|
- Silas Johns
- 6 years ago
- Views:
Transcription
1 AUTOMOTIVE CORE TOOLS; SPC, MSA, FMEA, APQP/CONTROL PLAN CQI Wessex - 11 December 2012 John Skinner rdaconsultancy.com 1
2 AUTOMOTIVE PROGRESS SINCE 1990 Best selling car in the UK in 1990 Ford Fiesta sold in EU 1.4, 1.6 CVH engines were very harsh and had early failures (valve guide wear, dropping valve seats damaging the engine). Rust was still a problem, though better than the 1970 s & 80 s. Radio-cassette, some speaker adjustments, maybe electric windows. No a/c and definitely no climate control. No airbags, little in the way of crumple zones. Central locking on higher end models. Door mirrors had remote adjustment on top models. Security was very poor cars like the XR2 were being stolen by joyriders on a regular basis (epidemic levels in some areas). Car insurance costs on hot models went through the roof. No ABS, stability control etc. Cost around 8500 roughly equivalent to in today s prices
3 WHAT CHANGED? Improvements demanded by legislation (emissions, safety), safety (NCAP), competition (i.e. VW/Audi), consumer demand (phone compatibility, convenience features etc.) A thorough focus on improved product quality achieved through; computer modelling/simulation, enhanced testing techniques (bench and road), consumer feedback (JD Power), supplier capability, effective corrective action (8D) Increased use of electronics (particularly powertrain) Need to improve product reliability (reducing warranty/ product recall costs) Application of ISO/TS16949 and mandated use of Automotive Core Tools?
4 ISO/TS16949 Initiated as QS9000 in 1995, based on the requirements of ISO9001, but adds many automotive industry specific requirements (though only one additional documented procedure from ISO9001) Produced and controlled by the International Automotive Task Force (IATF) Members include; Ford, GM, VW/Audi, PSA, BMW, Chrysler, Renault, Daimler and major trade organisations across the globe Recognised and required as a prerequisite for becoming an approved supplier to the respective automotive customers
5 AUTOMOTIVE REQUIREMENTS APQP; Advanced Product Quality Planning FMEA; Failure Mode & Effect Analysis Control Plan SPC; Statistical Process Control MSA; Measurement System Analysis These require a team approach (cross functional teams with management commitment) Automotive Industry Action Group (AIAG) manuals define basic requirements for application There are other requirements, based on the customer
6 Advanced Product Quality Planning (APQP) ISO9001 requires Planning of Product Realisation; The Automotive industry goes further; Some customers refer to project management or APQP as a means to achieve product realization. APQP embodies the concepts of error prevention and continual improvement as contrasted with error detection and is based on a multidisciplinary approach. (extract from ISO/TS)
7 Advanced Product Quality Planning Why plan? What gets in the way of planning?
8 Product Quality Concept Initiation /Approval Program Approval Prototype Planning Timing Chart Pilot Launch Planning Planning Product design Process design Validation Production Feedback assessment & corrective action Plan & Define Programme Product Design & Development Verification Product & Process Validation Feedback Assessment & Corrective Action
9 APQP Project Scope 2011 model year Range Rover minor changes
10 APQP Project Scope 2012/13 model year Range Rover - major project. New design, technologies, material aluminium, using self piercing rivets and aerospace sourced epoxy adhesive
11 Advanced Product Quality Planning (APQP) Advantages; Thorough planning and improved decision making Shorter development timescales Simultaneous engineering (design & manufacturing) Early procurement of long lead time tooling/facilities Defined objectives, measured as project stages are achieved Defined project gateways, with key deliverables Improved use of resources Significant cost savings (known impact on company finances) Effective feedback & corrective action (enhanced with use of computer systems)
12 Failure Mode & Effect Analysis (FMEA) Typically used at design (DFMEA) and manufacturing process planning (PFMEA) stages FMEA - a systematic set of activities intended to: a) Recognise and evaluate the potential failure of a product/process and the consequential effects of failure (risk management) b) Identify actions that could eliminate or reduce the chance of the potential failure occurring (improvement) c) Document the entire process d) Needs a team approach to be successful
13 Severity Class Occurrence Detection RPN Severity Occurrence Detection RPN DFMEA DFMEA System FMEA Number: 001 FMEA Team: xxxxxxxx Subsystem FMEA Date: (Original) xxxxxxxxxx Team Leader: xxxxxxxx X Component xxxxxxx (Revised) Action Results Item and Function/ Requirements Potential Failure Mode Potential Effect(s) of Failure Potential Cause(s)/ Mechanism( s) of Failure Current Controls - Prevention Current Controls - Detection Recommended Action Responsibility and Target Completion Date Action Taken
14 CC Severity Class Occurrence Detection RPN DFMEA DFMEA System FMEA Team: xxxxxxxx Subsystem Team Leader: xxxxxxxx X Component Wheel hub Item and Function/ Requirements Potential Failure Mode Potential Effect(s) of Failure Potential Cause(s)/ Mechanism(s) of Failure Current Controls - Prevention Current Controls -Detection Wheel bolts; Support Bolts fail after wheel & tyre wheel impact Transmit loads to stub with kerb axle/vehicle suspension Loss of wheel,loss of control of vehicle, possible fatalities, resulting legal action 10 Incorrect material grade (new hub nut design) 7 Design calculations Pre design freeze test to failure vaidation 5 350
15 Severity Occurrence Detection RPN DFMEA FMEA Date: (Original) xxxxxxxxxx (Revised) FMEA Number: 001 Action Results Recommended Action Responsibility and Target Completion Date Action Taken Conduct a full virtual PTO engineering; Q1 analysis using design FEA 2013 & simulation software (proven performance) Virtual anlysis completed; results acceptable to spec. xxxx
16 DFMEA Ignores manufacturing issues; i.e. manufacturing producing/using parts that are to specification Can direct design effort to critical/significant characteristics and improve design validation/ verification testing results, avoiding late design changes Identifies special characteristics that need to be controlled in manufacturing to assure product quality Provides a documented record of the analysis which can be used into the future (many vehicle recalls could have been prevented by effective DFMEA) Needs to be maintained as a live document; continual improvement
17 PFMEA A PFMEA will follow the stages defined for the manufacturing route from material receipt, through the manufacturing stages to despatch Typically the manufacturing route will be defined on a process flow diagramme, including locations, machines, operation sequences etc.
18 CC Severity Class Occurrence Detection RPN PFMEA PFMEA System FMEA Team: xxxxxxxx Subsystem Team Leader: xxxxxxxx X Component Wheel hub/new design Item and Function/ Requirements Potential Failure Mode Potential Effect(s) of Failure Potential Cause(s)/ Mechanism(s) of Failure Current Controls - Prevention Current Controls - Detection OP 70; Finish machine bearing bores (CNC)/ dimensions to specification Bearing Ø oversize Bearing wear (with warning), loss of wheel, loss of control of vehicle, possible fatalities, resulting legal action. 100% of product may be scrapped 9 Incorrect tooling set up 5 Pre-set tooling used Post operation gauging - 10% 6 270
19 Severity Occurrence Detection RPN PFMEA FMEA Number: 001 FMEA Date: (Original) xxxxxxxxxx (Revised) Action Results Recommended Action Responsibility and Target Completion Date Action Taken Install in-station gauging as part of machine upgrade PTO engineering; Q in-station gauging integrated into machine; auto lockout on detection
20 PFMEA Focuses on potential for non-conforming product (in use and impact on manufacturing process including employee safety) and mistake proofing techniques Identification/prioritisation of potential failure modes and implementation of preventive/corrective action Focus on special characteristics Continual improvement Assumes product as designed will meet intent Should be extended to other areas; receiving, storage, transport, despatch etc. (complete process) Provide feedback to design (mistake proofing features etc.)
21 Control Plan A documented description of the systems and processes required for controlling product This is a key output once the DFMEA and PFMEA analysis has been completed Applies to distinct stages; Prototype, Pre-launch and Production. Each part must have a control plan, but family control plans can be used where justified (e.g. a foundry producing many different castings)
22 Control Plan Control Plan Part #: N/A Prepared By: xxxx xxx, xxx, aaa, Part Name/Description: Wheel Hub / new design Core Team: bbb, ccc Latest Change Level: #REF! Supplier/Plant App./Date: Production Control Plan Vendor ID: #REF! Other Approval/Date: #REF! Supplier Plant/Code: Notes: Oper. # Process Description Machine/Device/Jig/Tools Characteristics CC Item# Product Process SC Process/Pdt. Spec./Tolerance G.ID 70 OP 70; Finish machine bearing bores (CNC) XXX CNC machining centre Bearing Inner Bore diameter Finish machine; 25mm/min, CBN tip (XYZ) CC mm mm run out max In cycle gauging.
23 Control Plan Date (Original): xxxxx Customer Engg. Appr./Date (Opt): Cust. Quality Appr./Date (Opt): Other Approval/Date (Optional): Control Plan No.: CP001 Methods Eval. Mst. Technique Sample Size Sample Frequency Control Method Reaction Plan In cycle gauging. 100% 100% Machine control datalogger Lock out; setter informed, machine checked and re-set. Suspect material quarantined; (Corrective Action Report - CAR)
24 Control Plan Identifies the controls required to ensure product quality with a focus on special characteristics Defines the reaction plans required to be implemented where non-conformance is identified (containment of product, 100% inspection to ensure process becomes stable and capable) Is an output from the FMEA process
25 Statistical Process Control Traditional inspection techniques (patrol inspection, batch sampling etc.) rely on detection, which is wasteful as time and resources are put into producing parts that are not always useable Prevention verses detection; i.e. not producing the non-conforming parts in the first place is an obvious preferred situation If we can predict the process output, then we may be able to ensure conforming parts Statistical techniques can be used for process control
26 Process Control System Model with Feedback Statistical Process Control (SPC) People Equipment Materials Methods Environment Manufacturing Process Product Customers Identifying changing expectations; direct feedback on product quality Inputs Feedback from Customers
27 Goals of SPC To achieve a state of statistical control (stability) To maintain a state of statistical control (stability over time; prevention verses detection) To improve process capability
28 Statistical Process Control Taking action on the result of the output of a process (traditional inspection techniques) permits waste rejected/reworked product, wasted resources, potential for rejects to escape the process Understanding the variation of the process and applying statistical techniques allows for predictable process output (capability) To do this, we need to understand the types of variation present in the process
29 Statistical Process Control Machining process; part dimensions vary from each other Size If the output is stable (only common cause variation), the results form a pattern that can be described as distribution Size
30 Statistical Process Control Common cause variation; inherent in the process backlash/clearances, coolant feed, machine tolerances Special cause variation (or assignable cause) machine set up, material change, environment
31 Special Cause Variation Target line Predictable? Time Size If special causes of variation are present, the process output is not stable over time and is not generally predictable; we cannot always use sampling and SPC to control the process.
32 Common Cause Variation Target line Time Size If only common causes of variation are present, the output of a process forms a distribution that is stable over time and is predictable; we can then monitor the process using sampling and SPC charts
33 Statistical Process Control _ X Range Control chart (AIAG SPC manual)
34 General Rules for Interpretation A point outside a control limit 7 points in a row on one side of the centreline 6 points in a row steadily increasing or decreasing 2 out of 3 points more than 2 standard deviations from the centreline (same side) 4 out of 5 points less than one standard deviation from the centreline (same side)
35 Process Capability Capability indices are able to summarise process performance as a number to reflect how well the process will meet customer requirements (specification). They will indicate; - How variable the process is (i.e. spread of results) - Where the process output is in relation to the specification limits.
36 Process Capability Lower specification Upper specification Process variation or spread Tolerance
37 Capability Indices Process capabilities are an index produced by comparing the observed process variation or spread against the required tolerance. Examples include; Capability Index C p = USL - LSL 6 δ (process variation) Capability Index C pk = USL x OR x - LSL (largest of) 3 δ 3 δ i.e. Worst case result C pk will indicate the position of the process relative to the specification (i.e. centering)
38 If the process data has a normal distribution, the following can be used to interpret C pk : C pk Capability Indices Approximate proportion out of spec /1,000, /1,000, /1,000,000 (Where the process is centred between the specification limits)
39 Attribute Charting Attribute data is the result of inspection or testing that produce a fixed result and cannot be measured using measurement equipment e.g. number of paint defects on a door panel, number of rejected units from a functional test batch, number of weld failures on a floor-pan assembly Attributes can also be monitored using control charts with control limits to determine long term stability
40 What are the Benefits of SPC? Properly used, control charts and SPC can: Distinguish special from the common causes of variation, as an aid to improvement in capability Enable the process perform consistently and predictably Provide a common language for discussing the performance of the process (capability indices) Be used by employees for on-going control of a process
41 Measurement System Analysis (MSA) As measurement data is often used to make decisions with regard to manufacturing (and test) activities then the quality of this data needs to be assured No measurement system is perfect (i.e. measures exactly with reference to known standards each time); some variation will be evident in all systems, including human influences A series of analytical techniques can be used to ensure that the inherent variation in measurement systems can be determined and the effects understood i.e. possibility for accepting bad parts and rejecting good parts In essence, we need to understand the variation and limitations of the measurement systems we are using to enable confidence in those results (for equipment on the control plan)
42 Measurement System Analysis
43 Variable Gauge R&R study Gauge repeatability and reproducibility data sheet used for the numerical analysis of the study data (MSA software is also available). 10 parts used to represent variability of the process; 3 appraisers. Typically 3 trials per appraiser Complete the study using usual equipment and individuals (random presentation of parts to avoid influence on the results)
44 Gauge R&R Extract from the AIAG MSA manual
45 Variable Gauge R&R study The study estimates the variation and percentage of process variation for the measurement system (Gauge R&R) and its components - Repeatability - Reproducibility - Part to part variation (how representative the parts are; this will influence the results).
46 Gauge R&R Acceptable Gauge R&R% results; Up to 10% - generally acceptable 10 to 30% - may be acceptable based on importance of measurement feature, cost of better equipment, cost of refurbishment/repair of equipment, OR the skill level of the appraisers Over 30% - would be considered un-acceptable and improvement is required Where results are not acceptable, check the data, calculations etc. to determine if there are any errors
47 Use of Graphical Techniques There are many different methods for presenting data for analysis A picture paints a thousand words. The AIAG MSA manual strongly recommends the use of both calculated methods and graphical techniques. Other methods are available for specific situations and where more detail is required Analysis of Variance (ANOVA), gauge performance curves, regression analysis etc.
48 Attribute Studies Go/No-go gauging systems (acceptance gauging, gap gauges etc.) A series of comparative techniques are available to evaluate the effectiveness of attribute gauging systems, again using several appraisers and trials
49 Product Part Approval Process (PPAP) The intent of PPAP is to validate that products made from production tools/processes meet engineering requirements (specifications), that the processes are capable (Cpk, SPC data) and are capable of producing acceptable product consistently over time. The type and format of submission will depend on the customer requirements, but the AIAG PPAP manual has defined formats
50 PPAP To support this, appropriate data has to be completed and be made available for review by the customer; Part Submission Warrant (PSW), DFMEA, PFMEA, Control Plan, MSA data, initial process capability results, material certification, marked up drawing/ dimensional results, engineering change documents, material/performance test results, qualified laboratory documentation, appearance approval report (if applicable), sample product Approval may require full or partial submission of the information (invariably depending on supplier approval status) reviewed at the customer location or supplier site
51 PPAP Acceptance of the PPAP detail is key for several possible events; Authority to ship production parts Meeting customer timing requirements for the project Support the supplier approval rating (i.e. PSW submission on time) Trigger tooling payments to the supplier (tooling will typically be owned by the customer)
52 AUTOMOTIVE PROGRESS SINCE 1990 Best selling car in the UK 2012 (to date) - Ford Fiesta ex. Zetec OTR price 3 year warranty, plus breakdown cover sold in EU & USA Airbags x2, side airbags, knee airbag, anti-whiplash head restraints, optional curtain airbags ABS, brake force distribution, stability control, traction assist, auto brake assist, auto hazard warning lights High strength steels, active seat belts, anti-submarine seats, Halogen projector head lights Immobiliser/alarm, deadlock doors Heated, electric remote door mirrors, auto wipers with rain sensor, alloy wheels Radio/CD,, AUX connection for phones, IPODs, A/C etc. 4 way adjustable front seats Electronic power assist steering, advanced engines up to 85 mpg possible with some models
53 Summary In truth, many factors have influenced the improvement in product quality over the past 20 odd years, but the use of APQP and core tools have provided a focus on improved process capability and product quality/ reliability throughout the automotive supply chain. The aerospace industry are now utilizing many of these tools to improve supplier performance
54 Questions Thank you
Overview of Production Part Approval Process PPAP. Factor Quality, Inc.
Overview of Production Part Approval Process PPAP Factor Quality, Inc. Purpose of the PPAP To determine if the supplier understands all customer requirements and if the production process has the potential
More informationIndustry Forum SPECIAL OFFER. Industry Forum... A Common Approach Universally Applied. ISO/TS16949: 2009 Lead Auditor Re-Certification Training
Industry Forum Newsletter Volume 13 ISO/TS16949: 2009 Lead Auditor Re-Certification Training You may be coming up to your Re-Certification date after attending one of our ISO/TS16949 Lead Auditor Training
More informationHTNA SUPPLIER QUALITY MANUAL
SECTION II.9.3 PROCESS CONTROL PLAN PURPOSE: To establish the development and submission requirements of a process control plan for HTNA that defines and controls the method of consistent production processes.
More informationWITTUR PRODUCTION PART APPROVAL PROCESS
PURPOSE SCOPE REFERENCE RESPONSIBILITY PROCESS OWNER Corporate Local RELATED DOCUMENTS Procedures Instructions Forms Other WPPAP s purpose to provide the evidence that all engineering design record and
More informationProduction Part Approval Process (PPAP)
Document ID: QN-M04 Page 1 of 15 Aerojet Rocketdyne Quality Note M04 Date: 12/23/2016 Table of Contents 1. PURPOSE... 2 2. APPLICATION... 2 2.1. Resubmissions... 3 2.2. Applicable Documents... 3 3. CONVENTIONS...
More informationIts purpose is to define the approval process of new or revised parts, or parts resulting from new or significantly revised production methods.
SUPPLIER PPAP HANDBOOK NORTH AMERICA Revision D May 24, 2018 Table of Contents Table of Contents 1 Foreword.. 2 Production Part approval Process (PPAP) Purpose.. 3 When is a Submission Required?. 3 Significant
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 6/26/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationLOTUS SUPPLIER HANDBOOK rev14 09/05/2018. Supplier Handbook
rev14 09/05/2018 Supplier Handbook Issue 14 May 2018 SECTION 0.0 Foreword to Issue 14 The LOTUS Supplier Handbook Issue 14 was issued with revisions to the following: Chapters re-organised Section 2.0
More informationPROCESS. Failure Mode & Effects Analysis. Practitioner Guide
TOOLKIT PROCESS Failure Mode & Effects Analysis Practitioner Guide Creating and managing effective Part Number Specific Process FMEAs using Reference (Unit) FMEAs Dr. Ian Riggs Contents LIST OF FIGURES
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 8/2/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationEdition: Revision 09, February 19, This document is controlled by: Mayco International, LLC. Edited by
Working together as a team QUALITY AT THE SOURCE Page: 2 of 24 Supplier Quality Standard Edition: Revision 09, February 19, 2018 This document is controlled by: Mayco International, LLC Edited by Mayco
More informationGLB QM 02. Supplier Quality Manual 05. 3/2/18 Supplier Quality 1 of 19. Issue Date Issuing Department Page
3/2/18 Supplier Quality 1 of 19 3/2/18 Supplier Quality 2 of 19 Table of Contents 1.0 Introduction 3 2.0 Manual 4 2.1 Application 4 2.2 Quality Management System of the Supplier 4 2.3 Quality Management
More informationSupplier Manual Rev /15
Supplier Manual Rev. 01-05/15 www.kamax.com Operations Europe KAMAX GmbH & Co. KG Petershütter Allee 29, 37520 Osterode am Harz, Germany Dr.-Rudolf-Kellermann-Str. 2, 35315 Homberg/Ohm, Germany Am Kreuzweg
More informationProduction Part Approval Process (PPAP)
Document ID: QN-M04 Page 1 of 13 Aerojet Rocketdyne Quality Note M04 Date: 03/16/2016 Table of Contents 1. PURPOSE... 2 2. APPLICATION... 2 2.1. Resubmissions... 2 2.2. Applicable Documents... 3 3. CONVENTIONS...
More informationHow to perform PPAP Level 1 Level 2 Level 3 Level 4 Level 5
How to perform PPAP The process of completing a PPAP submission is complex. This detailed process is a collection of key elements that must be completed to verify that the production process will produce
More informationIndustry Forum. Aerospace Management System Tools Training and Implementation Programmes. Web:
Industry Forum Aerospace Management System Tools Training and Implementation Programmes Web: www.industryforum.co.uk/training Email: courses@industryforum.co.uk Phone: +44(0)121 717 6600 Why choose Industry
More informationVisteon Corporation. Customer Specific Requirements Fifth Edition. For Use with ISO/TS 16949:2009
Visteon Corporation Customer Specific Requirements Fifth Edition For Use with ISO/TS 16949:2009 SP-WW-SG-1007 Page 1 of 9 Printed Copies of this I. Introduction Quality professionals from Visteon collaboratively
More informationR.H. SHEPPARD CO., INC. HANOVER, PA QUALITY BY DESIGN SUPPLIER QUALITY MANUAL NINTH EDITION
R.H. SHEPPARD CO., INC. HANOVER, PA. 17331 QUALITY BY DESIGN NINTH EDITION TABLE OF CONTENTS TITLE PAGE 1. SUPPLIER QUALITY SYSTEM REQUIREMENTS 1 2. PURCHASE ORDERS, SPECIFICATIONS AND PRINTS 1 3. REQUESTS
More informationSupplier Quality Manual
QP #: 8.4.1.2 Rev. #:0 Date Issued: 12/19/17 Date Revised: Page 1 of 8 Supplier Quality Manual Approved by: Mike Cornwell ( VP of Materials) Date: 12/19/17 1.0 Purpose: To provide Suppliers of BRC Rubber
More informationTorque Transfer Solutions
SUPPLIERS QUALITY ASSURANCE MANUAL TREMEC 5F/ PE Level 9 Issued Date March 02 nd, 2015 Revision Date May 17 th, 2017 - Page 1 of 135 Dear Supplier: In these times of global markets, it is not longer enough
More informationCulture of Excellence: Advanced Product Quality Planning (APQP) for Manufacturers
Culture of Excellence: Advanced Product Quality Planning (APQP) for Manufacturers M A Y 2018 MEET ALI Advance Product Quality Planning (APQP) for Manufacturers Presented by: Ali Rizwan LinkedIn: bit.ly/alirizwan
More informationRevision no: 01 Date: Global Supplier Quality Assurance Network
Title: H-APQP Template Manual Purpose and Scope This document is aimed at internal and external stakeholders to describe the use of the H-APQP Template. Contents Introduction H-APQP... 2 1. Planning and
More informationSupplier Quality Standard
Supplier Quality Standard Sherex Industries & Sherex Fastening Solutions "First Time Quality at the Source" Through Teamwork Supplier Quality Standard Edition: Rel. September 6, 2007 This document is controlled
More informationGlobal Supplier Quality Process Manual. Quality Processes for Suppliers to Merkle-Korff Industries. Abstract
Global Supplier Quality Process Manual Quality Processes for Suppliers to Merkle-Korff Industries Abstract This document contains quality requirements for suppliers to Merkle-Korff Industries and provides
More informationWorks Standard. PPAP - Production Part Approval Process
Works Standard PPAP - Production Part Approval Process WN 50 020 1 AREA OF APPLICATION AND PURPOSE This works standard contains the general, basic requirements for the approval of vendor parts for production.
More informationEsigenze di formazione e qualifica per soddisfare i Customer Specific Requirement degli OEM
1 Esigenze di formazione e qualifica per soddisfare i Customer Specific Requirement degli OEM Alessandro Ferracino (Intertek Certification General Manager) 2 IATF: 14 elements IATF members include the
More informationDaimlerChrysler (Chrysler Group) Customer-Specific Requirements
DaimlerChrysler (Chrysler Group) Customer-Specific Requirements For Use With ISO/TS 16949 Second Edition September, 2005 1. Scope ISO/TS 16949 and this document define fundamental quality system requirements
More informationSupplier Quality Manual. QF-SQR001 / Rev. Date: / Rev. Level: D
1 Table of Contents COMMITMENT TO SUPPLIERS 4 SUPPPLIER CERTIFICATION REQUIREMENTS 5 SUBCONTRACTOR DEVELOPMENT 6 CERTIFICATE OF CONFORMANCE 6 ENGINEERING AND PROCESS CHANGES 7 MATERIAL LABELING 8 IMDS
More informationIATF transition. Only 1 year to go for over 69,000 ISO/TS16949 certified organizations to transition to ISO9001: 2015 and IATF 16949: 2016.
ISO/TS16949:2009 IATF 16949:2016 Risk or Opportunity? Quality Partner Newsletter September 2017 For More Information Visit www.qualitypartner.co.uk Author: Paul Hardiman Welcome to the ninth edition of
More informationDanfoss Supplier Quality Manual
Danfoss Supplier Quality Manual Revision 9.3 January 2014 1 Quality Policy... 3 2 Purpose... 3 3 General Requirements... 3 3.1 Quality Targets... 4 3.2 Quality Improvement Plan (QIP)... 4 3.3 Communication...
More informationMetric Manufacturing Supplier Manual
Metric Manufacturing Supplier Manual This Manual applies to all suppliers of Metric Manufacturing Co. Compliance to all requirements within this manual, as well as the general terms and conditions, are
More informationPPAP Process Checklist \ Sign Off Sheet instructions
PPAP Process Checklist \ Sign Off Sheet instructions In addition to these requirements you must meet all Nexteer Automotive Supplier Requirements noted in the Nexteer Automotive Supplier Website. Nexteer
More informationMetal Powder Products Company
Metal Powder Products Company Supplier Quality Manual Revision 1 Page 1 of 10 Introduction 1. Purpose: This manual has been created for Metal Powder Product s (MPP) Production, Prototype and Service Suppliers.
More informationQUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A
Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production
More informationPRODUCTION PART APPROVAL PROCESS. Peter BÓLLO
PRODUCTION PART APPROVAL PROCESS Peter BÓLLO Author: Workplace: Address: E-mail: Peter Bóllo Johnson Controls spol. s r.o., Bratislava Business Centre Sturova 4, 81102 Bratislava, Slovak Republic Peter.Bollo@jci.com
More informationIng.-Büro Pfeufer. FMEA Alignment AIAG and VDA. Join the conversation: #AQMS2018 VDA QMC
Ing.-Büro Pfeufer New Your global Workshop FMEA Title standard Goes Here FMEA Alignment AIAG and VDA Join the conversation: #AQMS2018 Status November 2018 FMEA Alignment AIAG and VDA Project Leader: AIAG:
More informationApplied PPAP within a Process Approach, Including Fourth Edition Updates. Jim Collins
Applied PPAP within a Approach, Including Fourth Edition Updates Jim Collins Outline Applied PPAP within a Approach, Including Fourth Edition Updates Approach Review Model Example Measuring Performance
More informationSupplier Quality Manual
Supplier Quality Manual Document No. F-PM010 Rev 3 Owner Supplier Quality Page 1 OF 11 TABLE OF CONTENTS 1.0 Purpose 3 2.0 Scope... 3 3.0 Quality System Requirements... 3 4.0 Approved Supplier List (ASL).
More informationQAA1, Appendix 2. APQP Elements. Customer order. 1.1 Customer specifications
QAA1, Appendix 2 APQP Elements The objectives, expectations and requirements for documenting individual elements of the APQP Status Reports (see QSR-1, Appendix 3) are described as follows: Customer order
More informationQUALITY PLANNING FOR SUPPLIERS - PERFECTION IS OUR DRIVE -
QUALITY PLANNING FOR SUPPLIERS - PERFECTION IS OUR DRIVE - 1 Contents 1 Contents... 2 2 Introduction... 3 3 Quality Management Systems... 4 3.1 Quality promotion as a supplier assumption 4 3.2 Quality
More informationIntegrated Quality Systems
Integrated Quality Systems Introduction THE PRODUCT IQS provides a powerful and proven solution that offers a unique model for integrating quality systems to achieve superior enterprise-wide performance.
More informationSupplier Quality Manual
Supplier Quality Manual Second Edition Issued: August 25, 2015 Meeting Our Customers Needs Through Business Excellence First Edition All rights reserved under the copyright laws. 1 Marion Body Works Inc.
More informationFord Motor Company Customer-Specific Requirements
Ford Motor Company Customer-Specific Requirements For use with PPAP 4.0 Scope The US English language version of this document is the official version. Any translations of this document shall: be for reference
More informationSUPPLIER GUIDELINES MANUAL
1.0 INTRODUCTION 1.1 This guidelines manual defines the minimum requirements for Supreme Machined Products Co.; Inc. LTD (to be referenced as Supreme throughout the document) Supplier s and does not supersede
More informationSupplier Quality Manual (QQS )
Monticello Spring Corporation Quality Management System Supplier Quality Manual (QQS 100.00) 1.0 Introduction 1.1 Scope The details stipulated in this manual are the minimum mandatory requirements for
More informationSUPPLIER SELF ASSESSMENT
Company name: (In both English and your official language) Company address: (In both English and your official language) Tel.: E-Mail: Fax: Web-Site: Date: Executed by: Function: Submission reason: New
More informationSupplier Requirements Manual
Supplier Requirements Manual 1.0 Control Responsibility TABLE OF CONTENTS 1.1 Proprietary Information Sharing 1.2 Purpose & Approval 1.2.1 Scope 1.3 Quality Systems Management & Evaluation 1.3.1 QMS 1.3.2
More informationQuality Management Systems for Automotive Industry based on IATF 16949
TRAINING CATALOGUE Quality Management Systems for Automotive Industry based on IATF 16949 HOW CAN YOU BENEFIT FROM THE IATF 16949 CERTIFICATION? This certification will give you the opportunity to acquire
More informationQUALITY PLANNING II. Study supports
PROJECT IRP Creation of English Study Supports for Selected Subjects of the Follow-up Master Study in the Quality Management Study Field IRP/2015/104 QUALITY PLANNING II Study supports Jiří Plura Language
More informationProduction Part Approval Process Supplier Information. - Version 1.0
Supplier Information Quality@Suppliers - Version 1.0 Navigation What s PPAP? meaning Benefits & Targets What does it mean for you as the supplier? origin past today PPAP PPAP Content PPAP Timeline Additional
More informationAgreement. Between. Cooper Standard. (Hereafter referred to as the CS ) And. (Hereafter referred to as the Supplier )
Global Supplier Quality Manual Revision 1 Agreement Between Cooper Standard (Hereafter referred to as the CS ) And (Hereafter referred to as the Supplier ) This agreement is made between the above named
More informationSuppliers Quality Assurance Manual
Suppliers Quality Assurance Manual Revision: 10 Issued Date: 9 July 2018 2016 Marketing Plan Avenida 5 de Febrero 2115 Fracc. Industrial Benito Juárez Santiago de Querétaro, Querétaro C.P. 76120 Tel: +52
More informationProgressive Metal Forming, inc Hall Road Hamburg, MI 48139
SUPPLIER QUALITY MANUAL Progressive Metal Forming, inc. 10850 Hall Road Hamburg, MI 48139 www.pmfdraw.com Rev. 1/30/17 Page 1 of 11 TABLE OF CONTENTS 1.0 INTRODUCTION. 3 2.0 SUPPLIER QUALITY GUIDELINES...3
More informationCUSTOMER SPECIFIC REQUIREMENTS FOR ISO/TS APPLICABLE TO FIASA/POWERTRAIN SUPPLIERS
Betim, July 27 th, 2012. CUSTOMER SPECIFIC REQUIREMENTS FOR ISO/TS 16949 APPLICABLE TO FIASA/POWERTRAIN SUPPLIERS Updates and replaces, from 08/06/2012, the "LETTER OF SPECIFIC REQUIREMENTS" from FIASA
More informationSupplier Requirement Manual. Preface
1 Preface This manual has been created to assist our suppliers in understanding the purchasing expectations and quality requirements for products supplied to RCO Engineering. The manual is also a tool
More informationAnnex 1. Customer Specific Requirements For Use With ISO/TS16949
Annex 1. Customer Specific Requirements For Use With ISO/TS16949 Issue: July 2015 CONTENTS I. Introduction... 3 II. Customer Specific Requirements Document Structure... 3 III. Reference Documents... 3
More informationPPAP 3rd Edition Check List (Steel Suppliers)
PPAP 3rd Edition Check List (Steel Suppliers) Supplier: Date: Submission Level: Part #: Eng. Chg. Level (PS#): Reviewed By: Yes No N/A Comments 1. Design Records / Drawings Correct Eng. Chg. Level 2. Eng.
More informationWestern Diversified Plastics, LLC. Supplier Requirements Manual
Western Diversified Plastics, LLC. Supplier Requirements Manual Revision Date: 12/10/2019 TABLE OF CONTENTS 1.0 Introduction.. 3 2.0 WDP Supplier Policy.. 4 3.0 Scope... 4 4.0 Launch Readiness Measures...
More informationMERIT Customer Specific Requirements
MERIT Customer Specific Requirements For Use with ISO 9001:2015 And IATF16949:2016 Effective March 31, 2018 1 Table of Contents INTRODUCTION /BUSINESS PHILOSOPHY... 6 1. SCOPE... 7 1.1 Scope General...
More informationJDI Quality Assurance Guideline
JDI Quality Assurance Guideline For Supplier, 2017 Japan Display Inc. 7/1/2017 - Table of Contents - 1. Introduction... - 7-1.1. Purpose of this Guideline...- 8-1.2. Structure of this Guideline...- 8-1.3.
More informationSupplier Quality Systems Requirements Manual
Supplier Quality Systems Requirements Manual Brink Towing Systems Version: 2.4 Date: 23-07-2018 Changed text in blue Page 1 / 9 Table of Contents 1. Introduction 3 1.1 Scope 3 1.2 Purpose 3 1.3 Background
More informationSupplier Containment
Page 1 of 14 1. PURPOSE The purpose of supplier containment is to protect the customer by preventing nonconforming material from being shipped to Delphi Technologies or subsequently passed to Delphi Technologies
More informationSupplier Manual Rev /18
Supplier Manual Rev. 03-05/18 www.kamax.com Operations Europe KAMAX GmbH & Co. KG Petershütter Allee 29, 37520 Osterode am Harz, Germany Dr.-Rudolf-Kellermann-Str. 2, 35315 Homberg/Ohm, Germany Am Kreuzweg
More informationSUPPLIER QUALITY MANUAL
Global Supplier of Automotive Tire Products & Refrigeration Components SUPPLIER QUALITY MANUAL Air Controls Products, LLC Oxford, NC Air Controls Products maintains sole control rights to the master copy
More informationTSV Supplier Quality Manual TABLE OF CONTENTS
TABLE OF CONTENTS 1.1. Preface... 2 1.2. Scope... 2 1.3. Confidentiality... 3 2.1. Supplier Approval Review... 4 2.2. Supplier Quality System Requirements... 4 2.3. Maintaining and Changing Quality System
More informationSupplier Quality Requirements Manual
Supplier Quality Requirements Manual 1 TABLE OF CONTENTS Page Number 1.0 Forward 3 2.0 Introduction 4 3.0 Supplier Selection Requirements 5 4.0 Supplier Development 5 5.0 Supplier Quality Rating System
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL QD-SUPPLIER-QUALITYMANUAL 1 of 13 02.20.15 TABLE OF CONTENTS Page A. Goal 3 B. Purpose 3 C. Approach 3 D. Applicability 3 E. Implementation 3 F. Zero Defects Policy 3 Section 1:
More informationSisler Manufacturing Group Supplier Quality Manual
Sisler Manufacturing Group Supplier Quality Manual Revision Date: 01/01/2018 INTRODUCTION Welcome to Sisler Manufacturing Group Sisler Manufacturing Group utilizes strong engineering support to specialize
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL 2 TABLE OF CONTENTS PAGE 1. INTRODUCTION 3 2. SCOPE 4 3. REFERENCE MATERIAL 4 4. SUPPLIER APPROVAL PROCESS 4-6 5. PRODUCT APPROVAL PROCESS 6 6. ON-GOING PRODUCTION 6-7 7. SUPPLIER
More informationFAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM
FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM 1 QA.101 rev. 3-2012 PURPOSE OF THIS STANDARD Fairfield is committed to continuous product quality improvement. Our management team is convinced that only with
More informationSupplier Quality Manual. QF-SQR001 / Rev. Date: 10/14/2017 / Rev. Level: E
Supplier Quality Manual QF-SQR001 / Rev. Date: 10/14/2017 / Rev. Level: E 1 Table of Contents COMMITMENT TO SUPPLIERS 4 SUPPPLIER CERTIFICATION REQUIREMENTS 5 SUBCONTRACTOR DEVELOPMENT 6 CERTIFICATE OF
More informationGLOBAL PURCHASING. Supplier Technical Assistance. Phased PPAP
GLOBAL PURCHASING Supplier Technical Assistance Phased PPAP Edition 1, October 2002 Phased Production Part Approval Process Phased PPAP Ford Motor Company Supplier Technical Assistance October, 2002 Table
More informationPPAP Process Checklist \ Sign Off Sheet Instructions
Global Supply Management PPAP Process Checklist \ Sign Off Sheet Instructions In addition to these requirements, you must meet all Nexteer Automotive Supplier Requirements noted in the Nexteer Automotive
More informationSUPPLIER QUALITY MANUAL For ISO/TS16949:2009 (Level 1)
1 of 8 General Introduction Standard Motor Products, Inc. Greenville Operations (SMP) is a registered TS-16949 facility. SMP has earned a reputation for providing products of consistent quality, competitive
More informationJSP Supplier Quality Assurance Manual
Changes to the Supplier Quality Assurance Manual: The 2011 has been reviewed for updates and revisions needed to keep our forms, policies and procedures current. The updates will be communicated to suppliers
More informationVernay Quality System Supplier Quality Manual
Table of Contents Revision: G Approvals: Manager, Quality Systems/Improvements NA Purchasing Manager Section A Overview Revision: G Page Approval 1 Table of Contents 2 Section A Section B Section C Section
More informationThe Callen Group of Companies. Callen Manufacturing Aluminum Die Casting
The Callen Group of Companies...represent a solid financial entity distinguishing itself as a "Best In Class" Full Service Supplier of high pressure and miniature non-ferrous Die Castings. The Callen Group,
More informationSupplier Quality Assurance Manual NSK Corporation NSK-AKS NSK NSSA NSK NBMX
As displayed on the intranet, this is a controlled document. All printouts are uncontrolled copies for reference only. PAGE NO: 1 of 24 Supplier Quality Assurance Manual NSK Corporation NSK-AKS NSK NSSA
More informationA V Manivannan Principal Consultant & Trainer CSR
& P P A P A V Manivannan Principal Consultant & Trainer CSR A new product development & approval process A most practical workshop 2 Sri Padhmam Consultancy & Training +91 94428 92185 office@sripadhmam.com
More informationABC Metals, Inc. NONFERROUS METALS PRECISION SLITTING
SCOPE This section describes the responsibility, authority, and management structure of the facility. 1.1 QUALITY POLICY The President has the ultimate responsibility for the facility s products and services.
More informationGENERAL SUPPLIER GUIDELINE DATE: OCTOBER 2013
GENERAL SUPPLIER GUIDELINE DATE: OCTOBER 2013 Introduction With its two business units Engine Systems and Components as well as Filtration and Engine Peripherals, MAHLE ranks among the top three systems
More informationSupplier Quality Manual. Autoneum Group Supplier Quality Manual
Autoneum Group Supplier Quality Manual Owner: Autoneum Group Quality Revision No.: 1 1 of 21 Table of Contents 1. Introduction 5 1.1. Overview 5 1.2. Purpose of this manual 5 1.3. Supply chain 5 2. Supplier
More informationSAM automotive production GmbH SAM automotive GmbH Kolomanstr D Böhmenkirch
Quality Guidelines For Suppliers Of The SAM automotive group SAM automotive production GmbH SAM automotive GmbH Kolomanstr. 16 20 D 89558 Böhmenkirch www.sam-automotive.com contact@sam-automotive.com Page
More informationA CHECKLIST FOR QUALITY. Seven Questions to Gauge Quality in Metal Stamping Suppliers
A CHECKLIST FOR QUALITY Seven Questions to Gauge Quality in Metal Stamping Suppliers The Value of Quality Quality. It s the #1 concern for OEM engineering and purchasing managers when evaluating and measuring
More informationIntegrated Supplier Quality Requirements
Integrated Supplier Quality Requirements April 1, 2013 ISQ-001-QM Revision B The controlled and current version of this document is available on www.navistarsupplier.com. Supplier Quality Lifecycle Management
More informationGlobal Supplier Quality Manual. Revision 4
Global Supplier Quality Manual Revision 4 Introduction 1. Purpose: This manual has been created for Cooper Standard s (CS) Production, Prototype and Service Suppliers. The manual includes all CS locations
More informationHow ISO/TS Developed
ISO/TS16949 Documentation Structure 3 rd Party Certification Requirements Role of Top Management- for Implementation TS defines the Quality Management System requirements for the design and development,
More informationQCL and DSS Training For Suppliers. May 4, 2016
QCL and DSS Training For Suppliers May 4, 2016 Training Agenda 1. Introduction to Nexteer Engineering Procedure G1331 2. DSS Assessment & Control Level Charts 3. DFMEA / DSS / PFMEA / PCP 4. Alternative
More informationSNAP-ON INCORPORATED STANDARD ON FACILITY SPECIFIC REQUIREMENTS
SNAP-ON INCORPORATED STANDARD ON FACILITY SPECIFIC REQUIREMENTS Approval: Date: SEQ80.01.doc Page 1 of 15 Rev. 05/01/05 0.0 Introduction and overview The QFS system document (Tier I) includes both corporate
More informationCore Tool Updates. Scott. A. Gray John M. Cachat Brian Martensen
Core Tool Updates Scott. A. Gray John M. Cachat Brian Martensen Topics AIAG VDA FMEA Handbook Risk Based Audit Days Problem Solving Core Tools Software App Traceability Guideline Core Tools Self Assessment
More informationSupplier Quality Requirements Manual
Supplier Quality Requirements Manual ISO-020-1 Revision G January 20, 2012 ISO-020-1 Rev G 01/20/12 Page 1 of 17 Table of Contents Quality Commitment and Expectations... 3 SECTION 1- Introduction... 4
More informationSUPPLIER MANUAL SUPPLIER MANUAL
SUPPLIER MANUAL Rev.: 4, 01.11.2013 Page: 1 of 9 IER-QSF 003 TABLE OF CONTENTS PAGE 1. INTRODUCTION 2 2. SCOPE 3 3. REFERENCE MATERIAL 3 4. SUPPLIER APPROVAL PROCESS 3 5. PRODUCT APPROVAL PROCESS 5 6.
More informationGeneral Motors Global Purchasing and Supply Chain Global Supplier Quality
General Motors Global Purchasing and Supply Chain Global Supplier Quality GM Customer Specifics - ISO/TS 16949 October 2010 Including GM Specific Instructions for PPAP 4 th Ed. (see Section 5) 2010, General
More informationSupplier Quality System Requirements Manual
Supplier Quality System Requirements Manual This manual available ON-LINE at www.axletech.com website Quality Policy "AxleTech International is committed to exceeding our customers expectations by continually
More informationGlobal Supplier Manual Appendix K Nissan Customer Specific Requirements for Suppliers. October 30, 2017
Global Supplier Manual Appendix K Nissan Customer Specific Requirements for Suppliers October 30, 2017 TABLE OF CONTENTS Contents TABLE OF CONTENTS... 2 Scope of this document... 3 Responsibility... 3
More informationPRODUCTION QUALITY PLANNING
Your Logo Here PRODUCTION QUALITY PLANNING Operational Procedure: QOP-02-04 Rev.: A Pg. 1 1 of 6 DISTRIBUTION President Purchasing Human Resources Design Engineering Service Quality Assurance Production
More informationMeasurement Systems Analysis
Measurement Systems Analysis Components and Acceptance Criteria Rev: 11/06/2012 Purpose To understand key concepts of measurement systems analysis To understand potential sources of measurement error and
More informationLG SOURCING VENDOR QUALITY MANAGEMENT SYSTEM REQUIREMENTS
LG SOURCING VENDOR QUALITY MANAGEMENT SYSTEM REQUIREMENTS LG Sourcing QMS ver01 03.29.2010 Page 1 of 16 PAGE INTENTIONALLY LEFT BLANK Copyright 2010, LF Corporation - All rights reserved No part of this
More informationA CHECKLIST FOR QUALITY. Seven Questions to Gauge Quality in Metal Stamping Suppliers
A CHECKLIST FOR QUALITY Seven Questions to Gauge Quality in Metal Stamping Suppliers The Value of Quality Quality. It s the #1 concern for OEM engineering and purchasing managers when evaluating and measuring
More informationFour Innovative Methods to Evaluate Attribute Measurement Systems
Four Innovative Methods to Evaluate Attribute Measurement Systems Thomas Rust Reliability Engineer/Trainer Sept. 206 Saving More Lives Autoliv Global Footprint Japan RoA 0% Europe 7% 3% China 7% Sales
More information