QUESTION NO. : 15-1 RESPONSE:
|
|
- Cori Baker
- 6 years ago
- Views:
Transcription
1 QUESTION NO. : 15-1 Q. In their response to PPRP DR No. 7-10(a), Applicants state that the DC vendor has not been selected at this time and the vendor s selection is not expected until the third quarter of a. Will the DC portions of the MAPP project still use VSC technology? Please begin your answer with a yes, no, or Applicant cannot answer yes or no. If your answer begins with either a no or Applicant cannot answer yes or no, please explain your answer with reasonable specificity. b. Is all the technical information concerning the DC portions of the MAPP project, as presented in the direct testimony and exhibits of William Gausman, still accurate? Please begin your answer with a yes, no, or Applicant cannot answer yes or no. If your answer begins with either a no or Applicant cannot answer yes or no, please identify with specificity those parts of such technical information which are no longer accurate, and provide updated accurate information. c. Please describe with reasonable specificity the impact (if any) which the selection of the DC vendor may reasonably have on estimated costs for the MAPP project? A. a. Yes, the DC portions of the MAPP project will use VSC technology. b. Yes, the technical information presented in the direct testimony and exhibits of William Gausman is accurate. VSC technology offers many benefits over both AC and conventional DC technologies, including reduced footprint, dynamic control of system voltage, dynamic control of both the power flow and direction, the ability to use XLPE cables containing no fluid and black start capability. c. The selection of the DC vendor, based on those presently under consideration, should allow the MAPP project to be constructed within the budget estimate of $1.2 billion. SPONSOR: William M. Gausman
2 QUESTION NO. : 15-2 Q. Page 19 of the direct testimony of Paul McGlynn makes reference to a Capacity Emergency Transfer Obligation ( CETO ) that PJM establishes for each load deliverability area. Although Mr. McGlynn s direct testimony does not address the method for determining CETO, in Maryland PSC Case No. 9223, Mr. McGlynn s Supplemental Direct Testimony dated September 14, 2010 stated: The CETO calculated for the load deliverability tests is the import capability required for the area to meet a Loss of Load Expectation ( LOLE ) risk level of one day in twenty-five years. Please refer to Mr. McGlynn s response to OPC DR No. 4-6 in Case No. 9223, a copy of which is attached hereto and incorporated herein as if restated in full. In this regard: a. Is the CETO calculated by PJM for the load deliverability tests the import capability required for the area to meet a Loss of Load Expectation ( LOLE ) risk level of one day in twenty-five years? Please begin your answer with a yes or a no. If your answer is in the negative, please state how PJM calculates CETO and explain your answer with reasonable specificity. b. Please explain with reasonable specificity why the LOLE used in calculating CETO one day in 25 years rather than one day in 10 years. c. If the one day in 10 year standard had been used in calculating CETO, what would the CETO have been? d. If the one day in 10 year standard had been used in calculating CETO, state how and why this would (or would not) have affected PJM s conclusions as to the need for the MAPP Project? e. Provide all workpapers supporting any analyses done on a revised LOLE/CETO calculation. f. Please explain with reasonable specificity why an LOLE of 1/15, or an LOLE of 1/20, provides an insufficient margin to ensure that the transmission risk does not appreciably diminish the overall target of a 1/10 LOLE? In your answer, please do not simply refer to a PJM document but rather write out your explanation with reasonable specificity. (1) Provide the formulae and workpapers which support your answer.
3 g. Please explain with reasonable specificity how PJM knows whether an LOLE of 1/25 is itself sufficient to ensure that the transmission risk does not appreciably diminish the overall target of a 1/10 LOLE for PJM. h. Understanding that PJM has not previously calculated CETOs using a 1-in-10 LOLE, please perform the calculation and state the resulting CETO if the one day in 10 year standard had been used in the calculation. Please provide the workpapers or active Excel spreadsheets showing how the result was determined. i. With reference to the result obtained in your response to subpart (h) above, please state with reasonable specificity how this result affects (or does not affect) PJM s conclusions as to the need for the proposed MAPP transmission line project. A. In addition to the objections set forth in the cover letter incorporated in all responses, Applicants object to any requests to conduct new studies not already performed. a. Yes. The aggregate loss-of-load risk to the customer is a combination of reserve adequacy risk and transmission risk. The one-day in-25 years is the transmission risk associated with a one-day in ten reserve adequacy risk. The PJM Planning and Engineering Committee determined (more than 10 years ago) that a 1D/25 Y transmission risk level was sufficiently small and that any greater level of risk was not. See also response to OPC-15-2-(b). b. PJM does not calculate a LOLE transmission risk for every possible level of capacity; capacity levels can and do vary, even more so since the implementation of the PJM RPM auction capacity construct. Given the reality of changing capacity levels, the PJM Planning Committee (more than 10 years ago) discussed and selected 1-in-25 as a reasonably small transmission LOLE risk to reasonably ensure that a 1-in-10 aggregate overall LOLE risk criteria is maintained. Mathematically, a 1-day-in-10-years LOLE is the same as 0.1 days-per-year. Likewise, a 1-day-in-15-years LOLE is the same as days-per year; 1- day-in-20-years is the same as 0.05 days-per-year and 1-day-in-25-years is the same as 0.04 days-per year. The PJM Planning Committee decided that the transmission risk should not be more than one-half of the overall generation capacity risk of 1-day-in-10-years. As a result, the Planning
4 Committee selected the 1-in-25 LOLE criteria, given that 0.04 is less than ½ of 0.1. c. PJM presumes that the question is asking what the CETO values would be on a 1-day-in-10-years LOLE basis for the Eastern MAAC and MAAC LDAs, per the limiting NERC reliability criteria voltage violations listed in Exhibit PFM-1-1 of Mr. McGlynn s November 3, 2010 Direct Testimony. Eastern Mid-Atlantic 1-day-in-10 years 7260 Mid-Atlantic 1-day-in-10 years 4940 d. RTEP analysis was not performed for CETO values at a transmission risk other than the 1-day-in-25 years associated with a one-day in ten reserve adequacy risk. See response to OPC-15-2-(a). e. Without waiving the objections to this request, no such work papers exist. The CETO values provided in response to OPC-15-2-(c) are the output of software applications. f. See responses to OPC-15-2-(a) and (b). g. See responses to OPC-15-2-(a) and (b). h. Without waiving the objections to this request, see response to OPC-15-2-(c). i. See response to OPC-15-2-(c). SPONSORS: Paul F. McGlynn Steven R. Herling
5 QUESTION NO. : 15-3 Q. For your responses to this Data Request, please refer to the questions in, and Paul McGlynn s responses to, OPC DR No in Case No. 9223, a copy of which is attached hereto and incorporated herein as if restated in full. a. For each of Mr. McGlynn s answers to OPC DR No in Case No. 9223, respectively, please state whether those answers regarding the CETOs used by PJM are accurate as to determining the need for MAPP in the instant case. For each respective answer, please begin your response with either Yes, that answer remains accurate, No, that answer is now inaccurate or Cannot state whether that answer remains accurate. b. If any answer is no to any subpart of OPC DR No. 15-3(a) immediately above, please explain with reasonable specificity why it is not accurate as regards the determination of the need for MAPP; and, please explain with reasonable specificity what the correct answer should be. c. If any answer is cannot answer yes or no to any subpart of OPC DR No. 15-3(a) above, please explain with reasonable specificity the reasons and bases for your answer. A. a. Yes, PJM s 2010 CETOs were accurate in light of PJM s answers to OPC DR No in Case No See explanation provided in OPC-15-2-(a) and (b). Notwithstanding, while PJM s CETO methodology has not changed in 2011, PJM s 2011 cycle of analyses are likely to include different CETO values than those used in 2010 based on updated load forecast, generation and other system changes. Subsequent to its April 5, 2011 meeting, the PJM Board requested that additional sensitivity analyses be completed by August Results of the same will be provided to the Board and to stakeholders as completed, beginning in April b. See response to OPC-15-3-(a). c. See response to OPC-15-3-(a). SPONSOR: Paul F. McGlynn
6 QUESTION NO. : 15-4 Q. For your responses to this Data Request, please refer to the questions in, and Paul McGlynn s responses to, OPC DR No. 4-6, including Attachment OPC 4-6-A, in Maryland PSC Case No. 9223, a copy of which is attached hereto and incorporated herein as if restated in full. a. For each of Mr. McGlynn s answers to OPC DR No. 4-6 in Case No. 9223, respectively, please state whether those answers regarding the CETOs used by PJM are accurate as to determining the need for MAPP in the instant case. For each respective answer, please begin your response with either Yes, that answer remains accurate, No, that answer is now inaccurate or Cannot state whether that answer remains accurate. b. If any answer is no to any subpart of OPC DR No. 15-4(a) immediately above, please explain with reasonable specificity why it is not accurate as regards the determination of the need for MAPP; and, please explain with reasonable specificity what the correct answer should be. c. If any answer is cannot answer yes or no to any subpart of OPC DR No. 15-4(a) immediately above, please explain with reasonable specificity the reasons and bases for your answer. A. a. Yes, PJM s 2010 CETOs were accurate in light of PJM s answers to OPC DR No. 4-6, including Attachment OPC 4-6-A, in Maryland PSC Case No See explanation provided in OPC-15-2-(a) and (b). Notwithstanding, while PJM s CETO methodology has not changed in 2011, PJM s 2011 cycle of analyses are likely to include different CETO values than those used in 2010 based on updated load forecast, generation and other system changes. Subsequent to its April 5, 2011 meeting, the PJM Board requested that additional sensitivity analyses be completed by August Results of the same will be provided to the Board and to stakeholders as completed, beginning in April b. See response to OPC-15-4-(a). c. See response to OPC-15-4-(a). SPONSOR: Paul F. McGlynn
7 QUESTION NO. : 15-5 Q. For your responses to this Data Request, please refer to the questions in, and Paul McGlynn s responses to, OPC DR No. 4-7 in Maryland PSC Case No. 9223, a copy of which is attached hereto and incorporated herein as if restated in full. A. a. For each of Mr. McGlynn s answers to OPC DR No. 4-7 in Case No. 9223, respectively, please state whether those answers regarding the CETOs used by PJM are accurate as to determining the need for MAPP in the instant case. For each respective answer, please begin your response with either Yes, that answer remains accurate, No, that answer is now inaccurate or Cannot state whether that answer remains accurate. b. If any answer is no to any subpart of OPC DR No. 15-5(a) immediately above, please explain with reasonable specificity why it is not accurate as regards the determination of the need for MAPP; and, please explain with reasonable specificity what the correct answer should be. c. If any answer is cannot answer yes or no to any subpart of OPC DR No. 15-5(a) immediately above, please explain with reasonable specificity the reasons and bases for your answer. a. Yes, PJM s 2010 CETOs were accurate in light of PJM s answers OPC DR No. 4-7 in Maryland PSC Case No See explanation provided in OPC (a) and (b). Notwithstanding, while PJM s CETO methodology has not changed in 2011, PJM s 2011 cycle of analyses are likely to include different CETO values than those used in 2010 based on updated load forecast, generation and other system changes. Subsequent to its April 5, 2011 meeting, the PJM Board requested that additional sensitivity analyses be completed by August Results of the same will be provided to the Board and to stakeholders as completed, beginning in April b. See response to OPC-15-5-(a). c. See response to OPC-15-5-(a). SPONSOR: Paul F. McGlynn
8 QUESTION NO. : 15-6 Q. For your responses to this Data Request, please refer to the questions in, and Paul McGlynn s responses to, OPC DR No. 4-8 (but excluding Attachment OPC DR No. 4-8-A-CONF thereto) in Maryland PSC Case No. 9223, a copy of which is attached hereto and incorporated herein as if restated in full. a. For each of Mr. McGlynn s answers to OPC DR No. 4-8 in Case No. 9223, respectively, please state whether those answers regarding the CETOs used by PJM are accurate as to determining the need for MAPP in the instant case. For each respective answer, please begin your response with either Yes, that answer remains accurate, No, that answer is now inaccurate or Cannot state whether that answer remains accurate. b. If any answer is no to any subpart of OPC DR No. 15-6(a) immediately above, please explain with reasonable specificity why it is not accurate as regards the determination of the need for MAPP; and, please explain with reasonable specificity what the correct answer should be. c. If any answer is cannot answer yes or no to any subpart of OPC DR No. 15-6(a) immediately above, please explain with reasonable specificity the reasons and bases for your answer. d. Please provide the document supplied in Attachment OPC DR No. 4-8-A- CONF in Case A a. Yes, PJM s 2010 CETOs were accurate in light of PJM s answers to OPC DR No. 4-8 (but excluding Attachment OPC DR No. 4-8-A-CONF thereto) in Maryland PSC Case No See explanation provided in OPC-15-2-(a) and (b). Notwithstanding, while PJM s CETO methodology has not changed in 2011, PJM s 2011 cycle of analyses are likely to include different CETO values than those used in 2010 based on updated load forecast, generation and other system changes. Subsequent to its April 5, 2011 meeting, the PJM Board requested that additional sensitivity analyses be completed by August Results of the same will be provided to the Board and to stakeholders as completed, beginning in April 2011.
9 b. See response to OPC-15-6-(a). c. See response to OPC-15-6-(a). SPONSOR: Paul F. McGlynn
10 QUESTION NO. : 15-7 Q. On Page 89 of the 2010 PJM Regional Transmission Expansion Plan ( RTEP ) dated February 28, 2011, an operational solution to the delay in completing the Susquehanna Roseland 500 kv transmission line is described as including operating to the NERC category C double-circuit tower line contingencies that are driving the need for the line. a. Please describe what the phrase operating to the NERC category C double-circuit tower line contingencies that are driving the need for the line means in the way of operating the electric system, or in the way of planning to operate the system. b. Please describe how (if at all) this solution differs from PJM s normal operating policy, or from PJM s normal planning to operate the system. If this solution does not differ from PJM s normal operating policy, or from PJM s normal planning to operate the system, please explain why this is so. c. Please describe how this solution affects the treatment of demand resources, from both an operational viewpoint and from a planning viewpoint, respectively. A. a. In actual operations, PJM s normal operating policy requires real-time mitigation of first-contingency transmission constraints, or n-1 NERC Category B violations. The specific situation to which Question OPC-15-7 refers anticipates a likely delay in the availability of the Susquehanna Roseland 500 kv line, requiring PJM to take steps to ensure system reliability absent that line, given that it would otherwise solve the identified DCTL Category C common mode violations. In collaboration with PJM Operations staff, PJM has developed an operational solution to address the criteria violations that would otherwise be expected to occur in 2012 without the Susquehanna - Roseland line. The operational solution includes extending the RMR for Hudson Unit #1 into 2012 and operating to the NERC category C double-circuit tower line contingencies that are driving the need for the line. DCTL system
11 configurations will be treated in real-time operations as if they were an n- 1 event. Operating to the double circuit tower line contingencies will provide PJM Operations staff the time needed to implement Demand Resources to manage flow on constrained facilities once other generation redispatch options have been exhausted. Analysis shows the combination of retaining the Hudson Unit #1 on RMR along with implementing Demand Resources would be effective at controlling the thermal violations expected to occur in 2012 without the Susquehanna Roseland line. b. See response to OPC-15-7-(a). c. See response to OPC-15-7-(a). SPONSOR: Paul F. McGlynn
12 QUESTION NO. : 15-8 Q. On pages 158 and 159 of the 2010 PJM RTEP, Figures 6.5, 6.6, and 6.7 chart the EMAAC maximum import limit in MW for the base case and for various combinations of reinforcement projects. These combinations all include PATH or a PATH alternative. Please provide similar data for the following reinforcement projects or combinations of reinforcement projects: a. The Mt. Storm to Doubs 500 kv rebuild. b. MAPP. c. The Northern Alternative. d. The Mt. Storm to Doubs 500 kv rebuild plus MAPP. e. The Mt. Storm to Doubs 500 kv rebuild plus the Northern Alternative. A. In addition to the objections set forth in the cover letter incorporated in all responses, Applicants object to any requests to conduct new studies not already performed, including with respect to combinations (a), (d) and (e), which have not been evaluated by PJM and would constitute new and original work. Without waiving the foregoing objections, Applicants respond as follows: Regarding the Mount Storm Doubs 500 kv transmission line rebuild, while the rating of the line will be higher, the rebuild does not materially affect the transmission system impedance matrix and, thus, does not materially affect the flows on other transmission lines. Therefore, PJM does not intend to conduct studies related to the need for the MAPP line with and without the Mount Storm Doubs line. Notwithstanding the aforementioned, Figures 6.6 and 6.7 referenced in the question both show the effect of Dominion Alternatives 1, 2 and 3, each of which included a rebuild of the Mt. Storm Doubs line along with other upgrades, as shown on Slide #16 of the November 10, 2010 PJM TEAC presentation materials, accessible form PJM s web site via the following URL link: reliability-and-market-efficiency-update.ashx
13 Combinations (b) and (c) were evaluated by PJM, per July 14, 2010 TEAC meeting materials, Slides #27 through 30, accessible from PJM s web site via the following URL link: SPONSOR: Paul F. McGlynn
14 QUESTION NO. : 15-9 Q. Pages 18 and 160 of the 2010 PJM RTEP state that, Analysis performed on the Preliminary 2011 PJM RTEP process analysis suggests that the need for the PATH line has moved several years beyond The outlook for a slower economic recovery reflected in the reduced load growth rates in PJM s January 2011 published forecast has led the PJM Board to direct transmission owners to suspend efforts on the PATH line pending a more complete analysis in 2011 of all RTEP upgrades, including MAPP. a. Please provide a copy of the 2011 PJM RTEP Retool for the MAPP project. b. If the 2011 PJM RTEP Retool for the MAPP project is not yet completed, please state whether it will be complete and provided by Friday, April 15, A. In addition to the objections set forth in the cover letter incorporated in all responses, Applicants object to any requests to conduct new studies not already performed. Without waiving these objections, Applicants respond as follows: a. See response to OPC-8-1-(a). b. Subsequent to its April 5, 2011 meeting, the PJM Board requested that additional sensitivity analyses be completed by August Results of the same will be provided to the Board and to stakeholders as completed, beginning in April The retool will not be completed by Friday April 15, SPONSOR: Paul F. McGlynn
4 Pepco Holdinqs Inc. April 23,2009. Re: DNR Data Request No. I - MAPP CN Dear Messrs. Hare and Bolea:
4 Pepco Holdinqs Inc 701 Ninth Street, NW Suite 1100 Washington. DC 20068 202 872-2850 (DC Office) 202 872-3281 (Fax) jwboone@.pepcoholdings.com James W. Boone Assistant General Counsel April 23,2009 M.
More informationSCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.
SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become
More information2017/2018 RPM Base Residual Auction Planning Period Parameters
Introduction The RPM Base Residual Auction (BRA) for the 2017/2018 Delivery Year is scheduled to be conducted in May of 2014. This document describes the 2017/2018 BRA planning period parameters and also
More information2018/2019 RPM Base Residual Auction Planning Period Parameters
Introduction The planning parameters for the 2018/2019 RPM Base Residual Auction (BRA) that is to be conducted in May of 2015 were posted on the PJM RPM website on January 30, 2015. Two versions of the
More informationPJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, Prepared by Capacity Market Operations
PJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, 2017 Prepared by Capacity Market Operations PJM 2017 Table of Contents Table of Contents Table of Exhibits...9 Approval...10 Current
More informationLOAD SERVING ENTITIES PJM REGION
Intra-PJM Tariffs --> RELIABILITY ASSURANCE AGREEMENT PJM Interconnection, L.L.C. Rate Schedule FERC No. 44 RELIABILITY ASSURANCE AGREEMENT Among LOAD SERVING ENTITIES in the PJM REGION Effective Date:
More information2750 Monroe Blvd Audubon, PA
2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report
More informationSystem Impact Study and Facilities Study Process Manual For Cleco Power LLC
System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2
More informationPJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016
PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session June 3, 2016 By Vilna Gaston Associate General Regulatory Counsel PSEG Services Corporation
More informationPJM Regional Transmission Expansion Plan BOOK 1. RTEP in Review February 28, Book 2 Input Data and Process Scope
BOOK 1 PJM 2014 RTEP in Review February 28, 2015 Book 2 Book Book Input Data and Process Scope 3 Baseline and Market Efficiency Results 4 Scenario and Interregional Results Book 5 State RTEP Summaries
More informationIntroduction to the PJM Markets
Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility
More informationCon Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection
Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection DRAFT For Discussion Purposes Only V 4.0 December 19, 2016 Table of Contents
More informationBusiness Practice Manual for Reliability Requirements. Version 34
Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM
More informationMARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING
MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING April 17, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs
More informationOpen Access Transmission Tariff ATTACHMENT K
ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct
More informationCommitted Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day.
Proposed Tariff Revisions Attachment K-Appendix and Schedule 1 of the Operating Agreement Generator Offer Flexibility Senior Task Force Revisions Related To Make-Whole and Lost Opportunity Cost Payments
More informationDispatch Signal & Locational Marginal Pricing (LMP)
Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal
More informationPJM PROMOD Overview. August 1, PJM
PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,
More informationStandard TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationLOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals
Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationELECTRIC POWER OUTLOOK FOR PENNSYLVANIA
ELECTRIC POWER OUTLOOK FOR PENNSYLVANIA 2014 2019 August 2015 Published by: Pennsylvania Public Utility Commission P.O. Box 3265 Harrisburg, PA 17105-3265 www.puc.pa.gov Technical Utility Services Paul
More informationMay 4, 2017 PLANNING COMMITTEE. Dear Committee Members:
2750 Monroe Blvd. Audubon, PA 19403 May 4, 2017 PLANNING COMMITTEE Dear Committee Members: 2017 PJM RESERVE REQUIREMENT STUDY - DETERMINATION OF THE PJM INSTALLED RESERVE MARGIN, FORECAST POOL REQUIREMENT
More informationRPM 101 Overview of Reliability Pricing Model
RPM 101 Overview of Reliability Pricing Model PJM 2017 Agenda Introduction Resource Adequacy Demand in RPM Supply in RPM Auction Structure Auction Clearing Resource Clearing Prices CTRs & ICTRs/CTR & ICTR
More information2015/2016 RPM First Incremental Auction Results
Introduction This document provides information for PJM stakeholders regarding the results of the 2015/2016 Reliability Pricing Model (RPM) First Incremental Auction. Incremental Auctions provide both
More informationCapacity Resource versus Energy Resource
Capacity Resource versus Energy Resource Seasonal Capacity Resource Senior Task Force April 18, 2016 Capacity Resource or Energy Resource? When a new generator connects to PJM s system through the PJM
More informationPOTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More informationRE: Initiating Near Term Transmission Components of the Central Toronto Integrated Regional Resource Plan
ONTARIO 120 Adelaide Street West Suite 1600 Toronto, Ontario M5H 1T1 POWER AUTHORITY\Jr T 416-967-7474 F 416-967-1947 www.powerauthority.on.ca December 27, 2013 Mr. Bing Young Director, Transmission System
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...
More informationPJM Manual 20: PJM Resource Adequacy Analysis Revision: 08 Effective Date: July 1, Prepared by Resource Adequacy Planning
PJM Manual 20: PJM Resource Adequacy Analysis Revision: 08 Effective Date: July 1, 2017 Prepared by Resource Adequacy Planning PJM 2017 Table of Contents Table of Contents Table of Exhibits...4 Approval...5
More informationPJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department
PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7
More informationLocal Market Power Mitigation Enhancements
Local Market Power Mitigation Enhancements Draft Final Proposal May 6, 2011 CAISO/M&ID/CRH May 6, 2011 page 1 Draft Final Proposal Local Market Power Mitigation Enhancements Table of Contents 1. Introduction...
More informationORLANDO UTILITIES COMMISSION Open Access Transmission Tariff Original Sheet 91 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service The Transmission Customer shall compensate
More informationPJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan
PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan David Schweizer Manager, Generation OC Meeting June 6, 2017 Overview PJM target for issuing next 5-Year RTO Wide Black Start RFP
More informationRequirements For Generation and Transmission Interconnections
Requirements For Generation and Transmission Interconnections Table of Contents 1.0 INTRODUCTION... 1 2.0 INTERCONNECTION POLICY... 2 3.0 STANDARD INTERCONNECTION PROCESS... 3 3.1 ASSUMPTIONS... 3 3.2
More informationPROJECT PROPOSAL. Palmyra 500 kv Switching Station. Dominion Virginia Power. for: 2014/2015 Long Term Window
Cover Dominion Virginia Power Public Version PROJECT PROPOSAL Palmyra 500 kv Switching Station for: 2014/2015 Long Term Window ATTN: Nancy Muhl PJM Interconnection 955 Jefferson Avenue Norristown, PA 19403
More informationATTACHMENT K TRANSMISSION PLANNING PROCESS
ATTACHMENT K TRANSMISSION PLANNING PROCESS 1.0 Introduction This Attachment K addresses the rights and obligations of Transmission Customers, relevant stakeholders and the Transmission Provider related
More informationPJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017
PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 Prepared by System Planning Department PJM 2017 Table of Contents Table of Contents
More informationTransmission Expansion Advisory Committee Market Efficiency Update
Transmission Expansion Advisory Committee Market Efficiency Update November 3, 2016 PJM TEAC 11/3/2016 Agenda 2016/2017 Market Efficiency Congestion Drivers Acceleration Analysis Status Next Steps PJM
More informationSummary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of
More information2013/2014 RPM Base Residual Auction Results
Executive Summary The 2013/2014 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 152,743.3 MW of unforced capacity in the RTO at a Resource Clearing Price of $27.73/MW-day. This MW and
More informationInternal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff
ConOp Internal NYISO HVDC Controllable Line Scheduling Concept of Operation Author: Scott Harvey, LECG Reviewers: ISO Staff LECG Staff Project Sponsor: Point of Contact: C. King B. Kranz Document Locator:
More informationSummary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of
More informationORA DATA REQUEST ORA-SCG-014-DAO SOCALGAS 2019 GRC A SOCALGAS RESPONSE DATE RECEIVED: NOVEMBER 16, 2017 DATE RESPONDED: NOVEMBER 04, 2017
Exhibit Reference: SCG-04 Testimony and Workpapers Subject: Gas Distribution O&M Cathodic Protection Please provide the following: 1. Referring to SCG s workpapers, pages 46 to 48, please provide the following:
More informationCOMMENTS OF THE PJM INDUSTRIAL CUSTOMER COALITION ON PJM'S CAPACITY PERFORMANCE PROPOSAL. September 17, 2014
COMMENTS OF THE PJM INDUSTRIAL CUSTOMER COALITION ON PJM'S CAPACITY PERFORMANCE PROPOSAL September 17, 2014 The PJM Industrial Customer Coalition ("PJMICC") appreciates the opportunity to submit these
More informationConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:
ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications
More informationGeneration Contingency Analysis
Generation Contingency Analysis PJM 2016 Objectives Identify the procedure for redispatching generation to alleviate an overloaded monitored transmission line caused by a contingency PJM 2016 2 Agenda
More informationBusiness Practice Manual for the Transmission Planning Process
Business Practice Manual for the Transmission Planning Process Order 890 Compliance Version 76.0 September 15,February 11, 2010 TABLE OF CONTENTS Order 890 Compliance... i 1. Introduction... 6 1.1 Purpose
More informationISO New England Available Transfer Capability. Implementation Document. Version 1.0
ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6
More informationNew PJM Rules Contribute To 37 Percent Increase In Capacity Auction Clearing Price
RESEARCH North America Power and Utilities Smart Grid New PJM Rules Contribute To 37 Percent Increase In Capacity Auction Clearing Price Power Generators To Gain From High Capacity Payments While Power
More informationNBP (ATG) IR 01 March 5, Reference: NBP 18.01
NBP (ATG) IR 01 March 5, 2015 Reference: NBP 18.01 a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence
More information2012 PJM Reserve Requirement Study
2012 PJM Reserve Requirement Study 11-year Planning Horizon: June 1 st 2012 - May 31 st 2023 Analysis Performed by PJM Staff October 5, 2012 Reviewed by Resource Adequacy Analysis Subcommittee (RAAS) DOCS
More informationPublic Policy and Multi-Driver Projects. RPPTF August 10, 2012
Public Policy and Multi-Driver Projects RPPTF August 10, 2012 Order 1000 Requirements: Planning authority required to consider public policy requirements (defined as legislative and regulatory requirements)
More informationFRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools
FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS Reliability Coordinator Processes and Tools Objectives Describe how the FRCC Security Process addresses planning/coordination of the Bulk Electric System Describe
More informationBEFORE THE PUBLIC SERVICE COMMISSION STATE OF MISSOURI
BEFORE THE PUBLIC SERVICE COMMISSION STATE OF MISSOURI In the Matter of the Application of Ameren ) Transmission Company of Illinois for Other Relief, ) or, in the Alternative, a Certificate of Public
More informationBUSINESS PRACTICE MANUAL CHANGE MANAGEMENT CAISO RESPONSE TO APPEALS
BUSINESS PRACTICE MANUAL CHANGE MANAGEMENT CAISO RESPONSE TO APPEALS I. Introduction The CAISO followed its business practice manual change management process 1 and submitted proposed revision request
More informationWes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED
Ramapo Phase Angle Regulator Cost Recovery Wes Yeomans Vice President Operations Management Committee May 31, 2017 Agenda Background Benefits of Two Ramapo Phase Angle Regulators Annual Cost Projections
More informationANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM
ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying
More informationEducating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours
Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists
More informationPJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017
PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents
More informationCapacity Accreditation and External Resource Zones 06/30/2016
Capacity Accreditation and External Resource Zones 06/30/2016 Overview MISO requested guidance on areas that require additional discussion and resolution in the seasonal / locational proposal In the last
More informationPower System Economics and Market Modeling
Power System Economics and Market Modeling 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com PowerWorld Simulator OPF and Locational Marginal
More informationTransmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008
Transmission Planning at the Midwest ISO Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008 Midwest ISO: What We Do Monitor flow of power over the high voltage
More informationI Pepco Holdings, Inc
I Pepco Holdings, Inc April 8, 20 II PIA ELECTRONIC TRANSMISSION AND HAND DELIVERY Kathy B. Anderson, Chief Maryland Section Southern Department of the Army Baltimore District, U.S. Army Corps of Engineers
More informationPJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal
PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal March 2, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com 2 P age Contents Executive Summary 6 Introduction and
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. NORTH AMERICAN ELECTRIC ) Docket No. RD13- RELIABILITY CORPORATION )
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION NORTH AMERICAN ELECTRIC ) Docket No. RD13- RELIABILITY CORPORATION ) PETITION OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION
More informationFundamentals of Transmission Operations
Fundamentals of Transmission Operations Equipment Outages PJM State & Member Training Dept. Objectives At the end of this presentation the Learner will be able to: Identify how weather may influence outage
More informationICAP Reform Proposals In New England and PJM
ICAP Reform Proposals In New England and PJM John D. Chandley LECG Cambridge, MA Revised: October 6, 2005 Table of Contents Page Introduction...1 Common Issues Driving ICAP Reform Efforts in New England
More informationMarket Settlements - Advanced
Market Settlements - Advanced RPM Module PJM State & Member Training Dept. PJM 2017 Capacity vs. Energy Capacity A commitment of a resource to provide energy during PJM emergency under the capped energy
More informationWritten comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results
Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results COMMENTS OF THE ALLIANCE FOR RETAIL ENERGY MARKETS ON THE
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014
No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide
More informationBusiness Practice Manual for Managing Full Network Model. Version 1011
Business Practice Manual for Managing Full Network Model Version 1011 Last Revised: November 16, 2016January 31, 2017 Approval History Approval Date: October 1, 2009 Effective Date: October 1, 2009 BPM
More informationIncremental Black Start RFP Response Template & General Information
Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section
More informationTechnical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations
Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations
More informationTransmission Systems of the Future: Trends, Challenges and innovative Solutions
Transmission Systems of the Future: Trends, Challenges and innovative Solutions Rainer Krebs, Principal Expert, Head of Protection and Control System Studies Dept. siemens.at/future-of-energy Transmission
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationPSE&G/ConEd Wheel Modeling
PSE&G/ConEd Wheel Modeling Stan Williams Director, Compliance & Settlements MC Webinar June 27, 2016 Overview of PSE&G-ConEd 600/400 Contract PJM NYISO Wheel Overview 1,000 MW from NYISO to PJM at the
More informationLesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System
Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators
More informationMOD Data for Power System Modeling and Analysis
MOD-032-1 Data for Power System Modeling and Analysis A. Introduction 1. Title: Data for Power System Modeling and Analysis 2. Number: MOD-032-1 3. Purpose: To establish consistent modeling data requirements
More informationIMM Quarterly Report: Fall 2017
IMM Quarterly Report: Fall 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics December 5, 2017 Highlights and Findings: Fall 2017 The MISO markets performed competitively this fall,
More informationPOWER SYSTEM STABILITY GUIDELINES
PREPARED BY: DOCUMENT REF: Planning PSSG-02 VERSION: 1.0 DATE: 25 May 2012 FINAL Final Matt Zema CEO Date 25/ 5 /2012 Version Release History VERSION DATE AUTHOR PEER REVIEW APPROVED COMMENTS 1.0 25/5/12
More informationElectricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)
For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold
More informationReserve Market. PJM State & Member Training Dept. PJM /06/2016
Reserve Market PJM State & Member Training Dept. PJM 2016 Objectives Define Reserve products Explain the Reserve requirements Calculate Reserve offers PJM 2016 2 Reserves Reserves are additional generation
More informationMONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN
MONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN Gee-Yu Liu National Center for Research on Earthquake Engineering, Taipei, Taiwan karl@ncree.gov.tw C.-W. Liu
More informationATTACHMENT P. Transmission Planning Process
ATTACHMENT P Transmission Planning Process Overview of Western s Transmission Planning Processes The Western Area Power Administration (Western) is a Federal agency under the Department of Energy that
More informationStandard BAL-502-RFC-02
A. Introduction 1. Title: Planning Analysis, Assessment and Documentation 2. Number: BAL-502-RFC-02 3. Purpose: To establish common criteria, based on one day in ten year loss of Load expectation principles,
More informationSPP at a Glance. Located in Little Rock. Approximately 600 employees
SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment
More informationFunctional Entity Roles and Responsibilities
Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...
More informationSERVICE AGREEMENT. For. Network Integration Transmission Service. Between. The City of Wauchula, Florida (Transmission Customer) And
SERVICE AGREEMENT For Network Integration Transmission Service Between The City of Wauchula, Florida (Transmission Customer) And Duke Energy Florida, LLC (Transmission Provider) Dated: January 1, 2017
More informationDominion Virginia Power
Dominion Virginia Power 701 E. Cary Street, Richmond, VA 23219 Web Address: www.dom.com April 13, 2017 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E.
More informationthe Real-Time Market will be based on the system marginal costs produced by the Real-Time
17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch
More informationGeneration Capacity Mechanisms and Resource Adequacy Planning
Generation Capacity Mechanisms and Resource Adequacy Planning Jennifer Heintz Public Service Commission of the State of Missouri February 7, 2013 Abu Dhabi, UAE Electricity Markets in the U.S. and Canada
More informationthe most promising locations for new renewables in the Imperial CREZ.
March 3, 2016 Imperial Irrigation District (IID) appreciates the opportunity to comment on the California Independent System Operator (CAISO) presentation during its 2/18/16 Stakeholder meeting discussing
More informationISO New England - ISO New England Inc. Transmission, Markets and Services Tariff
ATTACHMENT K REGIONAL SYSTEM PLANNING PROCESS TABLE OF CONTENTS 1. Overview 2. Planning Advisory Committee 2.1 Establishment 2.2 Role of Planning Advisory Committee 2.3 Membership 2.4 Procedures (a) Notice
More informationPJM Perspective of the EPA Clean Power Plan: Analysis
PJM Perspective of the EPA Clean Power Plan: Analysis Consortium for Energy Policy Research Harvard University March 9, 2015 Cambridge, MA Muhsin K. Abdur-Rahman Senior Market Strategist Paul M. Sotkiewicz,
More informationUniform Price vs. Differentiated Payment Auctions
Uniform Price vs. Differentiated Payment Auctions A Discussion of Advantages and Disadvantages PREPARED FOR Independent Electricity System Operator ICA Fundamentals and Concepts Stakeholder Meeting PREPARED
More informationTABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...
TABLE OF CONTENTS 4 DESCRIPTION AND EVALUATION OF ALTERNATIVES... 4-1 4.1 INTRODUCTION... 4-1 4.2 METHODOLOGY... 4-1 4.3 DESCRIPTION OF ALTERNATIVES... 4-2 4.3.1 No Project Alternative... 4-2 4.3.2 Alternative
More informationAn Assessment of the Public Benefit Set Aside Concept Taking Into Account the Functioning of the Northeast/Mid-Atlantic Electricity Markets
An Assessment of the Public Benefit Set Aside Concept Taking Into Account the Functioning of the Northeast/Mid-Atlantic Electricity Markets October 11, 2004 Mark Younger (prepared for AES-NY, LLC) I. Introduction
More informationEastside System Energy Storage Alternatives Screening Study. Prepared for:
Eastside System Energy Storage Alternatives Screening Study Prepared for: MARCH, 2015 1 Eastside System Energy Storage Alternatives Screening Study Prepared by: Mark Higgins Jim Eyer Randy Fish Prepared
More informationINVESTING IN OUR ECONOMY: NORTH-SOUTH CORRIDOR TRANSMISSION REINFORCEMENT
INVESTING IN OUR ECONOMY: NORTH-SOUTH CORRIDOR TRANSMISSION REINFORCEMENT Government of Alberta Response to the Critical Transmission Review Committee Report February 23, 2012 Alberta s Electricity Transmission
More information