1 Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering July 17, 2011

2 Project Quality Assurance Program Quality Assurance All those planned and systematic actions necessary to provide confidence that a product or facility will perform satisfactorily in service (TRV Circular E-C037/AASHTO R10-06)

3 Project Quality Assurance Program Two Primary Components 1. Quality Control DB Responsibility 2. Acceptance Agency Responsibility

4 Quality Assurance - Contract Provisions Design QA Program White Kiewit MassDOT Design Quality Control System Design Acceptance System Construction QAProgram White Kiewit MassDOT Contractors Construction Quality Control System Construction Acceptance System Independent Assurance Dispute Resolution System Qualified/Accredited Labs Qualified/Certified Inspection & Testing

5 I93F14 QC System Unique Challenges Schedule Establish QC System Fast Rigorous but Efficient QC System Design Project Right the First Time Build Project Right the First Time D/B work proceeds during QC System Development Numerous Stakeholders

6 W-K Quality System Manual (QSM) 1. Introduction 2. Quality Control Organization and Roles 3. Document Management and Control 4. Design Quality Control 5. Construction Quality Control

7 QSM Development Process Weekly Meetings: January 27 May 6 Participants W-K QC Team W-K Design Production W-K Construction Production MassDOT Boston MassDOT District FHWA Reach Consensus Fast Final Rev. 2 - Conformed June 14 QC Procedures Implemented during Development

8 QSM - 2. Quality Control Organization QC Administrator: Paul Moyer, PE Design QC Manager: Mark Negrotti, PE Design QC Team 14 Design Components Construction QC Manager: Andrea Burke Field Inspectors Shop Inspectors Independent Testing

9 QSM - 3. Document Mgmt & Control Electronic Filing System Expedition Sharepoint DB Team Sharepoint MassDOT

10 QSM 4. W-K Design Quality Control Targeted QC Review Procedures by Document Type Guiding Principles 1. Rigorous QC Review Procedures 2. Eliminate Unnecessary Review Steps 3. PE-Stamped Deliverables: Full QC Review 4. Other Deliverables: Streamlined Technical Review

11 W-K Design QC PE-Stamped Docs Design Docs & Construction Procedures Full QC Review Technical Review - Design Production Team Design QC Review Discipline Coordination Review Construction QC Review Documentation Design Review Comment Resolution (RCR) Form Discipline Coordination RCR Form Construction RCR Form Quality Control Checklist (QCC)

12

13

14

15 W-K Design QC Unstamped Docs Permit Applications, Schedule Updates Technical Review Design and/or Construction Production Team Documentation - QC Cover Sheet Preparer Reviewer Project Engineer (or designee) QC Administrator

16 W-K Design QC Construction QC Plans Prepared by Construction QC Manager Technical Review by QC Administrator Review Documentation - QC Checklist Construction QC Mgr QC Administrator

17 W-K Design QC Shop Drawings Constructability Review by Project Engineer Technical Review by Design Production Team Documentation: Constructability: Acceptance Stamp Technical: Shop Drawing Stamp

18 W-Q Design QC Early Release Work Starts Prior to Final Design Acceptance Early Release Packages Structural Steel & Bearings Beam Seats & Substructure Repairs Temporary Crossover Sawcutting, Median Barrier Deployment Highway Lighting

19 W-Q Design QC Early Release Draft Early Release Submittal Page-Flip Review Meeting Final Early Release Submittal W-K Proceeds at Risk Except: Construction Involving Moving Traffic Delivery of Major Components to I-93 Site

20 W-Q Design QC Early Release Shop Drawing Approval Early Release Approval Re-review and Approval after Final Design Acceptance

21

22 QSM 5. W-K Construction Quality Control Project Produced Materials Fabricated Materials Standard Manufactured Work Items

23 W-K Constr. QC Project Produced Materials Construction QC Plans Earthwork Bridge Substructure Repairs, Beam Seats Bridge Superstructure Bridge Bearings and Composite Deck Members Bridge Deck Closure Concrete Bridge Deck Membrane & Strip Seals Portland Cement Concrete Other Hot Mix Asphalt Pavement Field Inspection Independent Field Testing Mobile Lab

24 W-K Constr. QC Fabricated Materials Fabricator Quality System Manuals Bridge Bearings - DS Brown Structural Steel Structal (w/greiner & Michelman) P/C Modular Structural Elements - Jersey Precast W-K Inspectors in Fabrication Shops Structal Jersey Precast Fabrication Shop Testing

25 W-K Constr. QC Standard Manufactured Work Items Manufacturer s Quality System Manuals Manufacturer Testing Project Site QC Inspection and Testing

26 W-K Constr. QC Inspection & Testing W-K Shop Inspection Structal: Steel Jersey P/C: PMSE W-K Field Inspection Independent Testing Mobile Laboratory

27 W-K Constr. QC Non-Conforming Work Nonconformance Report (NCR) Non-Conformance Disposition Sign-off W-K QC Administrator W-K Design Engineer MassDOT Corrective Action Verification W-K QC MassDOT RE

28

29 DB QC System Critical Success Factors Weekly Meetings during QSM Development All Stakeholders Attend Get Everyone s Input Make Decisions Reach Consensus Anticipate Everything, Have Plan in Place Targeted QC Procedures Early Start: Development & Implementation Keep Team Educated During Development

30 Questions? GILL ENGINEERING Paul Moyer, P.E Vice President eng.com.

2007 Summer Meeting AASHTO Highway Subcommittee on Construction Project Quality for Design- Build

2007 Summer Meeting AASHTO Highway Subcommittee on Construction Project Quality for Design- Build 2007 Summer Meeting AASHTO Highway Subcommittee on Construction Project Quality for Design- Build by Bob Burns Quality Program Manual Requirements ISO 9001:2000; Third Edition and the guide for ISO 9004

More information

CALCULATION COVER SHEET

CALCULATION COVER SHEET Doc. No.: DQP410FA Rev. Page DQP410FA - 1 of 1 CALCULATION COVER SHEET Calculation Title: Calculation Number: Total Number of Pages (including cover sheet): Total Number of Computer Runs: Prepared

More information

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Review MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Introduction to Quality Management Dave Ahlvers, P.E. Review of Job Special Provision & Terms Dennis

More information

Quality Assurance Program for Design-Build Projects with an Optional 15-Year Capital Maintenance Agreement

Quality Assurance Program for Design-Build Projects with an Optional 15-Year Capital Maintenance Agreement Quality Assurance Program for Design-Build Projects with an Optional 15-Year Capital Maintenance Agreement July 25, 2011 2011 by Texas Department of Transportation (512) 416-2055 All Rights Reserved TABLE

More information

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,

More information

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART

More information

LTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It

LTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It LTRC Seminar - Building Quality Pavements QUALITY What It Is and How to Get It LTRC Seminar - Building Quality Pavements Quality in General What is it? Who s Quality? How do we get it? LTRC Seminar - Building

More information

May 2004 Construction Forms A-i. Table of Contents APPENDIX A CONSTRUCTION FORMS... A-1. SCDOT Construction Form Description Table...

May 2004 Construction Forms A-i. Table of Contents APPENDIX A CONSTRUCTION FORMS... A-1. SCDOT Construction Form Description Table... APPENDIX A Construction Forms SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION May 2004 May 2004 Construction Forms A-i Section Table of Contents Page APPENDIX A CONSTRUCTION FORMS... A-1 SCDOT Construction

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS

More information

TABLE OF CONTENTS PROCEDURES AND FORMS

TABLE OF CONTENTS PROCEDURES AND FORMS Doc. No.: DQP001 Rev. Page DQP001-1 of 3 TABLE OF CONTENTS PROCEDURES AND FORMS Document No. Description Tab No. Latest Rev. No. Rev. Date DQP001 Table of Contents Procedures and Forms 5 0

More information

1.2 The engineer will provide Quality Assurance (QA) inspection. The role of QA is to verify the performance of the QC.

1.2 The engineer will provide Quality Assurance (QA) inspection. The role of QA is to verify the performance of the QC. Quality Management Quality Management is a pro-active and efficient method of incorporating quality into the planning and scheduling of all project activities. The contractor works together with the engineer

More information

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms.

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms. Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms August 29, 2017 2017 by Texas Department of Transportation 512/506-5808 All

More information

PROJECT ITEMS CHECK LIST Project No.

PROJECT ITEMS CHECK LIST Project No. PROJECT ITEMS CHECK LIST Project No. Action Required Action Completed Form No Action or Form Name Responsible for work 1 Obtain plans, proposals and cross sections from the Construction. and/or 2 Check

More information

Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects

Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects WSDOT Design-Build Guidance Statement Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects Date October 2, 2006 Format Final Relevant section of WSDOT DB Guidebook

More information

Summary of Critical Findings Reviews for the National Bridge Inspection Program

Summary of Critical Findings Reviews for the National Bridge Inspection Program 2013 Pacific Northwest Bridge Inspectors Conference Maximizing your Bridge Inspection Program Session 2B April 23, 2013 Summary of Critical Findings Reviews for the National Bridge Inspection Program Brian

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved: VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Revisions to Chapter VII of Manual of Instructions Materials Acceptance and Materials Notebook Program NUMBER: MD 407-17

More information

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction

More information

Essentials QA/QC Plan Sample for Ericsson Qualifications

Essentials QA/QC Plan Sample for Ericsson Qualifications Essentials QA/QC Plan Sample for Ericsson Qualifications Good for smaller projects and bid qualifications Has All the Essential Elements of a well-founded Quality Control Plan Contact: Ed Caldeira 410-451-8006

More information

CONSTRUCTION SPECIFICATION FOR MODULAR BRIDGE STRUCTURES FOR TEMPORARY INSTALLATIONS

CONSTRUCTION SPECIFICATION FOR MODULAR BRIDGE STRUCTURES FOR TEMPORARY INSTALLATIONS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 918 APRIL 2017 (formerly OPSS 918 Common, March 1998) Note: The MUNI implemented in April 2017 replaces OPSS 918 COMMON, March 1998 with no technical

More information

STRUCTURES SPECIFICATIONS FOR BRIDGE CONSTRUCTION ISSUES. John Westphal, P.E. State Construction Office January 2017

STRUCTURES SPECIFICATIONS FOR BRIDGE CONSTRUCTION ISSUES. John Westphal, P.E. State Construction Office January 2017 STRUCTURES SPECIFICATIONS FOR BRIDGE CONSTRUCTION ISSUES John Westphal, P.E. State Construction Office January 2017 Introduction Discuss Defective Materials, as defined within the Specifications Recent

More information

Quality Assurance Program for the Carolina Crossroads Project

Quality Assurance Program for the Carolina Crossroads Project Quality Assurance Program for the Carolina Crossroads Project 08/31/18 (Draft QAP) Contents Scope... 1 1.1 General... 1 1.2 Program Components... 1 1.3 Construction Quality Management Plan... 2 1.4 Owner

More information

Michael Lewis Director, Rhode Island Department of Transportation

Michael Lewis Director, Rhode Island Department of Transportation Michael Lewis Director, Rhode Island Department of Transportation AASHTO Subcommittee on Construction August 14, 2013 Today s Session Rhode Island s Engagement in the Implementation Assistance Program

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL PLAN FOR WELDING FOUNDATION PILING SPLICES

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL PLAN FOR WELDING FOUNDATION PILING SPLICES MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL PLAN FOR WELDING FOUNDATION PILING SPLICES BFS:MJC 1 of 5 APPR:MJF:POJ:10-25-12 FHWA:APPR:11-30-12 a. Description. This work

More information

Fire Protection Contractor QA/QC Plan Sample

Fire Protection Contractor QA/QC Plan Sample Fire Protection Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Fire Protection Standards & Inspection Forms Contact: Ed

More information

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following: MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL EFFECTIVE DATE: OCTOBER 14, 2011 200.07 Contractor Quality Control - is replaced with the following: (a) (b) (c) Scope: These requirements

More information

Retention 4 Years unless otherwise noted. Workzone Enforcement Contracts 104

Retention 4 Years unless otherwise noted. Workzone Enforcement Contracts 104 File # Description MDOT Form # Minimum Element Component Naming Examples 100 Administration 100 Award Letter Award YYYY-MM-DD 101 Contract Form Progress Schedule 1130 1130 YYYY-MM-DD Weekly Statement of

More information

Special Provision No. 599S22 March 2001

Special Provision No. 599S22 March 2001 RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM RETAINED SOIL SYSTEM, WALL/SLOPE,

More information

Pennsylvania ASphalt Improvement Network 2008 Construction Pilots Implementation Update Report (Phase 2)

Pennsylvania ASphalt Improvement Network 2008 Construction Pilots Implementation Update Report (Phase 2) Pennsylvania ASphalt Improvement Network 2008 Construction Pilots Implementation Update Report (Phase 2) A. FOLINO CONSTRUCTION INC. Submitted to: PennDOT Deputy Secretary for Highway Administration and

More information

FHWA Initiatives. Southeast Pavement Preservation Partnership

FHWA Initiatives. Southeast Pavement Preservation Partnership FHWA Initiatives Southeast Pavement Preservation Partnership Joe Gregory, P.E. System Preservation Engineer FHWA Office of Asset Management Washington, D.C. Transportation System Preservation Research

More information

Contract Administration Section

Contract Administration Section Contract Administration Section 1 Challenges 25,000+ bridges statewide PENNDOT S BRIDGE PROGRAM Currently at 3,200 structurally deficient bridges Approximately 300 bridges become structurally deficient

More information

Certified Welding Fabricator (CWF) Program Information

Certified Welding Fabricator (CWF) Program Information Certified Welding Fabricator (CWF) Program Information (The enclosed documents provide information about the AWS Certified Welding Fabricator Program.) General Program Information Program Requirements

More information

TDOT PROPOSED SCOPE OF WORK CEI

TDOT PROPOSED SCOPE OF WORK CEI REVISED 12/14/09 TDOT PROPOSED SCOPE OF WORK CEI SCOPE OF SERVICES SUMMARY This document is to define as clearly as possible the duties of the consultant with regard to administration of the TDOT construction

More information

Precast Concrete Pavement (R05)

Precast Concrete Pavement (R05) Precast Concrete Pavement (R05) 1 Agenda SHRP2 Overview What is SHRP2? Focus Areas Implementation Assistance Technical Product Description Product Implementation Implementation Timeline Questions Source:

More information

BRIDGE JOINT PERFORMANCE IN CALIFORNIA

BRIDGE JOINT PERFORMANCE IN CALIFORNIA BRIDGE JOINT PERFORMANCE IN CALIFORNIA TONY BRAKE, M.S, P.E. Tony_Brake@dot.ca.gov Senior Bridge Engineer CA State Dept. of Trans. MAY 2016 Salt Lake City, UT CALIFORNIA STATE DEPARTMENT OF TRANSPORTATION

More information

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan)

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan) DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: FirstTimeQuality 410 451 8006 Pat [Pick the

More information

Communications Contractor QA/QC Plan Sample

Communications Contractor QA/QC Plan Sample Communications Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Communications Standards & Inspection Forms Contact: Ed Caldeira

More information

Texas Department of Transportation Book 2 Technical Provisions. Grand Parkway Project. Attachment 2-2. Work Breakdown Structure Requirements

Texas Department of Transportation Book 2 Technical Provisions. Grand Parkway Project. Attachment 2-2. Work Breakdown Structure Requirements Texas Department of Transportation Book 2 Technical Provisions Grand Parkway Project Work Breakdown Structure Requirements Table 1 represents the minimum levels of the WBS that all schedule information

More information

TC3 AASHTO Technical Service Program for Training

TC3 AASHTO Technical Service Program for Training TC3 AASHTO Technical Service Program for Training Feb. 7 th 9 th Mid Atlantic Quality Assurance Workshop Ron Stanevich, PE Director of Materials Division, WVDOH TC3 AASHTO Technical Service Program for

More information

Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014

Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014 Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014 A. GENERAL DESCRIPTION The Consultant, acting as an independent contractor will serve to supplement the Authority

More information

SCOPE OF SERVICES. Consultant Engineering and Inspection Services. Interstate 85/385 Interchange Improvements Greenville County.

SCOPE OF SERVICES. Consultant Engineering and Inspection Services. Interstate 85/385 Interchange Improvements Greenville County. SCOPE OF SERVICES Consultant Engineering and Inspection Services Interstate 85/385 Interchange Improvements Greenville County Description The Interstate 85/385 Interchange Project consists of improvements

More information

Construction Quality Assurance Plan (CQAP)

Construction Quality Assurance Plan (CQAP) Construction Quality Assurance Plan (CQAP) for Lucks Lane Widening Project (Spirea Rd. to E. Evergreen Pkwy.) and (E. Evergreen Pkwy. To Rte. 288)- (UPC 104290 and 105674) Cover Sheet I. Date of Original

More information

Bituminous PWT (Percent Within Tolerance)

Bituminous PWT (Percent Within Tolerance) Bituminous PWT (Percent Within Tolerance) Steven L. Koser, P.E. Pennsylvania Department of Transportation 1 Spec Limits and Goal Posts are Similar 2 Quality Measure: Percent Within Tolerance (PWT) Estimates

More information

SOURCE INSPECTION QUALITY MANAGEMENT PLAN

SOURCE INSPECTION QUALITY MANAGEMENT PLAN SOURCE INSPECTION QUALITY MANAGEMENT PLAN FOR CAMPUS PARKWAY / STATE ROUTE 140 PROJECT Prepared By: NV5 2109 West Bullard Ave #145 Fresno, CA 93711 (559) 661-5220 For: Merced County 11/20/2017 Rev 1: 3/15/2018

More information

USACE NAVFAC Design Sample QA/QC Plan

USACE NAVFAC Design Sample QA/QC Plan USACE NAVFAC Design Sample QA/QC Plan 20 selected pages (out of ) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: First Time Quality 410 451 8006 Pat [Pick

More information

Earthworks QA/QC Plan Sample

Earthworks QA/QC Plan Sample Earthworks QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact: FirstTimeQuality

More information

Quality Management Systems in Engineering Practice. Shane R. Beabes, P.E.

Quality Management Systems in Engineering Practice. Shane R. Beabes, P.E. Quality Management Systems in Engineering Practice Shane R. Beabes, P.E. ASQ Northern Virginia Section 11 May 2016 Agenda 1. Quality Management System 2. Quality 3. Client Requirements 4. Quality Assurance

More information

Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan)

Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan) Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact:

More information

NOTICE. Registration Form and Notice of Needed Revisions

NOTICE. Registration Form and Notice of Needed Revisions CONSTRUCTION MANUAL SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION May 2004 NOTICE Registration Form and Notice of Needed Revisions Complete and return this registration form to receive revisions to this

More information

Application Document Submittal for AISC Certification - Fabricators and Manufacturers

Application Document Submittal for AISC Certification - Fabricators and Manufacturers This document submittal checklist applies to Building Fabricators, Bridge Fabricators, Hydraulic Fabricators and Metal Component Manufacturers. The Fracture Critical endorsement is only available to Bridge

More information

Specification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010

Specification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010 Specification Changes and Their Effect on Plans Bridge Construction Issues BRG VTC April, 2010 Brian D. Merrill, P.E. BRG Construction & Maintenance Branch Also: Common Plan Review Items Revised Specifications

More information

Lessons Learned Impacting Bridget Malinowski and John Stevens

Lessons Learned Impacting Bridget Malinowski and John Stevens Lessons Learned Impacting 2015 Bridget Malinowski and John Stevens Agenda Review lessons learned Maintain the schedule Potential change orders Agency coordination Claims process Design and construction

More information

Presentation to NCAUPG/OAPC

Presentation to NCAUPG/OAPC Presentation to NCAUPG/OAPC Industry Objectives Ensure best quality pavements Assisting with QC/QA processes Improve the durability asphalt pavements Currently Managing for pay Driven by current acceptance

More information

TxDOT Design-Build Quality Assurance Program Implementation Guide

TxDOT Design-Build Quality Assurance Program Implementation Guide TxDOT Design-Build Quality Assurance Program Implementation Guide November 1, 2011 2011 by (512) 416-2055 All Rights Reserved Table of Contents Table of Contents 1 Overview... 1-1 1.1 Background...1-1

More information

Overview & Pavement Update. Thomas Van November 2013

Overview & Pavement Update. Thomas Van November 2013 Overview & Pavement Update Thomas Van November 2013 What is SHRP2? Tools to save lives, save money, save time. Products developed from objective, credible research Solutions that respond to challenges

More information

Project Planning and Development Process

Project Planning and Development Process Project Planning and Development Process The project development process (PDP) involves hundreds of tasks. Many of these are internal agency activities that help an agency follow a methodical process of

More information

General Info. Number: PROJECT NO

General Info. Number: PROJECT NO General Info Number: PROJECT NO. 43-16-04 Description: BRIDGE DECK REPLACEMENT AND REHABILITATION, RAKER-BARDEN ROAD (CR. 7-2) OVER OHIO TURNPIKE M.P. 41.9, DELTA-SANTEE ROAD (CR. 7) OVER OHIO TURNPIKE

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa 2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. ASCE STRUCTURAL ENGINEERING CONFERENCE Ames Iowa WHAT DO YOU DO IF YOU HAVE MORE PROJECT THAN BUDGET? DESIGN BUILDER SELECTION METHOD Fixed Price

More information

ENHANCING STEEL BRIDGES

ENHANCING STEEL BRIDGES ENHANCING STEEL BRIDGES A series of NSBA focus groups brings to light methods to improve the cost, speed and quality of steel bridges By Andy Johnson and Bill McElency Of critical importance to designers

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

FHWA CONCRETE PAVEMENT PROGRAM DIRECTION UNDER MAP-21

FHWA CONCRETE PAVEMENT PROGRAM DIRECTION UNDER MAP-21 FHWA CONCRETE PAVEMENT PROGRAM DIRECTION UNDER MAP-21 DESIGN SUNEEL N. VANIKAR, P.E. TEAM LEADER-PAVEMENT AND ANALYSIS 89 th Annual Meeting NESMEA Portsmouth, NH Moving Ahead for Progress in the 21 st

More information

GUIDE FOR ASME REVIEW TEAM LEADERS FOR REVIEW OF APPLICANTS FOR ASME CERTIFICATES OF AUTHORIZATION H (Cast Iron/Cast Aluminum)

GUIDE FOR ASME REVIEW TEAM LEADERS FOR REVIEW OF APPLICANTS FOR ASME CERTIFICATES OF AUTHORIZATION H (Cast Iron/Cast Aluminum) GUIDE FOR ASME REVIEW TEAM LEADERS FOR REVIEW OF APPLICANTS FOR ASME CERTIFICATES OF AUTHORIZATION H (Cast Iron/Cast Aluminum) The American Society of Mechanical Engineers Two Park Avenue New York, NY

More information

NQA-1 Graded Approach, 55-Gallon Drum Summary

NQA-1 Graded Approach, 55-Gallon Drum Summary 1, Organization 2, Quality Assurance program 3, Design 4, Procurement Document 5, Instructions, procedures, and Drawings 100 Basic 200 Structure and Responsibility 201 General 202 Delegation of Work 300

More information

The Design-Builder shall provide Project preconstruction conference minutes within seven Days after the preconstruction conference.

The Design-Builder shall provide Project preconstruction conference minutes within seven Days after the preconstruction conference. 2 PROJECT MANAGEMENT 2.1 Scope Management 2.1.1 General The Design-Builder shall conduct all Work necessary to meet the requirements of scope management, including preparing, documenting, revising, and

More information

Federal Highway Administration s Role in Bridge Preservation. Anwar S. Ahmad 1

Federal Highway Administration s Role in Bridge Preservation. Anwar S. Ahmad 1 Federal Highway Administration s Role in Bridge Preservation Anwar S. Ahmad 1 Abstract The purpose of this paper is to provide a brief overview of the bridge preservation efforts in the United States and

More information

Florida Department of Transportation District 4. To Design, Build, Finance, Operate and Maintain. The I-595 Corridor Roadway Improvements Project

Florida Department of Transportation District 4. To Design, Build, Finance, Operate and Maintain. The I-595 Corridor Roadway Improvements Project I-595 RFP Volume II - Technical Requirements Division II, Section 6 Value Added Specification Section Florida Department of Transportation District 4 To Design, Build, Finance, Operate and Maintain The

More information

Exhibit A Mn/DOT Contract No SCOPE OF WORK AND DELIVERABLES

Exhibit A Mn/DOT Contract No SCOPE OF WORK AND DELIVERABLES SCOPE OF WORK AND DELIVERABLES Construction Oversight for US 52 & CSAH 9 Interchange Design-Build Project in Goodhue County State Project (SP) 2506-72 PROJECT OVERVIEW The State of Minnesota has identified

More information

Northeast Bridge Preservation Partnership Meeting

Northeast Bridge Preservation Partnership Meeting Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM):

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM): SECTION 05120 STRUCTURAL STEEL PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03342 - Insulating Cellular Concrete. 2. 05210 - Steel Joists. 3. 09900 - Painting. 1.02 REFERENCES A. America Society

More information

William N. Nickas, P.E. Managing Technical Director of Transportation Precast/Prestressed Concrete Institute Chicago, IL

William N. Nickas, P.E. Managing Technical Director of Transportation Precast/Prestressed Concrete Institute Chicago, IL PCI Overview Comprehensive Quality Systems: A Smart Choice for Bridges 2011 Caltrans-PCMAC Precast Bridge Workshop Sacramento, CA November 17, 2011 William N. Nickas, P.E. Managing Technical Director of

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION

VIRGINIA DEPARTMENT OF TRANSPORTATION VIRGINIA DEPARTMENT OF TRANSPORTATION Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects January 2012 July 2018 Contents Amendment

More information

January 31, 2018 Asset Management and Performance Measures for Roads and Bridges Maryland Department of Transportation State Highway Administration

January 31, 2018 Asset Management and Performance Measures for Roads and Bridges Maryland Department of Transportation State Highway Administration January 31, 2018 Asset Management and Performance Measures for Roads and Bridges Maryland Department of Transportation State Highway Administration Amy J. Purves, PE Asset Management and Performance Measures

More information

STRUCTURAL CONCRETE - LIGHTWEIGHT

STRUCTURAL CONCRETE - LIGHTWEIGHT SPECIAL PROVISION May 27, 2010 Add Section 03312: PROJECT #MP-I15-6(178)245 PIN #7037 SECTION 03312S STRUCTURAL CONCRETE - LIGHTWEIGHT PART 1 GENERAL 1.1 SECTION INCLUDES A. Materials and procedures for

More information

PRECAST CONCRETE GIRDER ERECTION

PRECAST CONCRETE GIRDER ERECTION 7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

Bids JANUARY 25, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $3,600,000)

Bids JANUARY 25, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $3,600,000) General Info Number: PROJECT NO. 43-7-05 Description: BRIDGE DECK REPAIR AND REHABILITATION, BOSTON MILLS ROAD OVER OHIO TURNPIKE M.P. 78.0, OLDE EIGHT ROAD OVER OHIO TURNPIKE M.P. 79.5, NICHOLS ROAD OVER

More information

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure. Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE

More information

APWA Public Works Construction Management Seminar. March 22, 2018

APWA Public Works Construction Management Seminar. March 22, 2018 APWA Public Works Construction Management Seminar March 22, 2018 Seminar Objectives Exchange of Ideas CM - Definition & Purpose Relationship to Overall Effort Your Expectations Working with Contractors

More information

Performance Specifications What are they?

Performance Specifications What are they? Performance Specifications What are they? ALDOT Bureau of Materials and Tests Montgomery, Alabama Victor (Lee) Gallivan, P.E. Asphalt Pavement Engineer November 6, 2015 Performance Specifications for Rapid

More information

Inexpensive Durable Bridges with Simple Rapid Construction

Inexpensive Durable Bridges with Simple Rapid Construction Inexpensive Durable Bridges with Simple Rapid Construction Alan Cukurs P.E., S.E. J-U-B ENGINEERS Scott Ellsworth P.E., P.L.S. LOCAL HIGHWAY TECHNICAL ASSISTANCE COUNCIL (LHTAC) 1 Three Take Away Questions

More information

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS BRIDGE PREVENTIVE MAINTENANCE STRATEGY Approved January 3, 2007 BLANK Purpose To maximize the non-deficient service life of local bridges in the Erie-Niagara region, members of the Greater Buffalo-Niagara

More information

NON CONFORMITY REPORT

NON CONFORMITY REPORT CERN CH-1211 Geneva 23 Switzerland the Large Hadron Collider project LHC Project Document No. LHC-PM-QA-509.00 rev 2.1 CERN Div./Group or Supplier/Contractor Document No. - EDMS Document No. 112679 Date:

More information

Third Party Contracts Quality Management Plan (TPCQMP) Revision 00 Issue Date: August 6, 2018

Third Party Contracts Quality Management Plan (TPCQMP) Revision 00 Issue Date: August 6, 2018 Third Party Contracts Quality Management Plan (TPCQMP) Revision 00 Issue Date: August 6, 2018 Northeast Illinois Regional Commuter Railroad Corporation 547 West Jackson Boulevard Chicago, Illinois 60661

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

[Project Name] Project Quality Management Plan (PQMP) [Sub-Project, phase, etc.] [Company] [Company Address]

[Project Name] Project Quality Management Plan (PQMP) [Sub-Project, phase, etc.] [Company] [Company Address] This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 16, 2015 [Ref. number] Marc Arnecke, PMP [Project Name]

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

DMS-7370 Steel Bridge Member Fabrication Plant Qualification

DMS-7370 Steel Bridge Member Fabrication Plant Qualification Steel Bridge Member Fabrication Plant Qualification Effective Date: January 2015 1. DESCRIPTION This Specification describes the qualification processes for fabrication plants producing steel bridge members,

More information

Design-Builder Peformance Evaluation (DBPE)

Design-Builder Peformance Evaluation (DBPE) Design-Builder Peformance Evaluation (DBPE) There are five (5) major components of the DBPE document. Each component has multiple categories to facilitate performance evaluation for the Design-Builder,

More information

IMPORTANT NOTE for the Materials Webinar

IMPORTANT NOTE for the Materials Webinar IMPORTANT NOTE for the Materials Webinar Everyone Please Read Participants MUST use the Optional teleconference instructions (sent with the invitations and reminder) in order to hear the webinar audio.

More information

NACE Coating Inspector Bridge Specialty Written Exam NACE-Bridge-001

NACE Coating Inspector Bridge Specialty Written Exam NACE-Bridge-001 NACE Coating Inspector Bridge Specialty Written Exam NACE-Bridge-001 Exam Preparation Guide June 2017 Copyright 2017 by NACE International Institute. All rights reserved. Table of Contents Introduction...

More information

2010 FDOT/FTBA CONSTRUCTION CONFERENCE FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE

2010 FDOT/FTBA CONSTRUCTION CONFERENCE FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Structures Construction Updates FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Critical Structures Construction Issues Self Study Course This course is mandatory for all Structures res

More information

Special Inspection Program Guide. City of Novi Community Development Building Division

Special Inspection Program Guide. City of Novi Community Development Building Division Special Inspection Program Guide Based on the Michigan Building Code 2015 City of Novi Community Development Building Division TABLE OF CONTENTS PAGE NO. INTRODUCTION...1 GUIDELINES FOR THE SPECIAL INSPECTION

More information

MOP Update The New Inspection Process! Gary Angles, P.E., Construction Administrator Craig Landefeld, P.E., Pavements Specialist

MOP Update The New Inspection Process! Gary Angles, P.E., Construction Administrator Craig Landefeld, P.E., Pavements Specialist MOP Update 2017 The New Inspection Process! Gary Angles, P.E., Construction Administrator Craig Landefeld, P.E., Pavements Specialist Overview FHWA Requirements Risk Based Inspection prioritization Process

More information

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE Keith Donington, P.E. October 2012 1 Sibley Pond - Bridge Elevation 2 Bridge Open to Traffic November 2011 3 Bridge Highlights

More information

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT

More information

Managing a Design-Build vs. Bid-Build Project

Managing a Design-Build vs. Bid-Build Project Managing a Design-Build vs. Bid-Build Project January 30, 2018 Claude Ipock, P.E. SCDOT State Construction Engineer Jay Thompson, P.E. SCDOT State Pavement Design Engineer Contract Documents Bonds Performance

More information

Urban. Initiative. Meeting. Construction. Annual. City of Lynchburg

Urban. Initiative. Meeting. Construction. Annual. City of Lynchburg 2014 Urban Construction Initiative Annual Meeting City of Lynchburg Materials Testing Requirements for Locally Administered Projects Don French, P.E. VDOT Lynchburg District District Materials Engineer

More information

SECTION UNDERGROUND STORAGE TANK REMOVAL

SECTION UNDERGROUND STORAGE TANK REMOVAL SECTION 02 65 00 UNDERGROUND STORAGE TANK REMOVAL SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit project. 2. Consider including unit prices for additional

More information