1 UCD IT Services <Project ID> ITRM Project Initiation Document Version 1.0 8th Dec 2014 Version History Version Date Summary of Changes Changed by /12/14 Initial doc Paul Barry <Project Name> Project Initiation Document Page 1 of 12
2 Contents 1 Objectives & Scope 1.1 Background to the Project 1.2 Project Objectives 1.3 Expected Benefits 1.4 Project Scope 1.5 Change Control 2 Project Plan 2.1 Project Approach 2.2 Milestones & Deliverables 2.3 Project Plan 3 Project Structure 3.1 Roles & Responsibilities 3.2 Project Team Meetings 4 Risks & Issues 4.1 Initial Risk & Issue Log 4.2 Ongoing Management of Risks and Issues 5 Communication Plan 6 Project Costs 6.1 Initial Project Budget 6.2 Ongoing Costs 1 <Project Name> Project Initiation Document Page 2 of 12
3 Objectives & Scope This Project Initiation Document (PID) defines the ITRM Project in detail including objectives, scope, approach, deliverables, timescale and structure of the project so that it can be understood and agreed by all stakeholders. 1.1 Background to the Project The I.T. Relationship Management project (ITRM), is a project designed to setup a new group inside the Customer Services Team in IT Services. The ITRM project is based on Business Relationship Management (BRM) model which is a formal approach to understanding, defining and supporting inter business activities in an organisation. ITRM project is a method to re engage with ITS customer base and ensure the work that we carry out as a department is relevant and aligned with the IT needs of the community as a whole. It is also a project where we aim to get IT involved in the dicussions of decision makers at an early stage of strategic choices. 1.2 Project Objectives The objectives for this project are as follows: Internal audit of all ITS services currently in place and a detailed listing of all of our support and service offering's as a whole. Identify key members of the UCD community and engage with them to raise awareness of the ITRM project. Raise awareness in the UCD community about the services and support ITS offer to the community currently. ITRM will co ordinate the UCD community and the ITS department linking the demands of the customer to the service required. Analysis and trending of aggregate demand to ensure ITS project selection is relevant and required by the customer base. Make ITS the partner of choice for the UCD community. 1.3 Expected Benefits The expected benefits are increased customer satisfaction with IT Services offerings, Strategic alignment between ITS and customers demands, increased clarity on project proposals into the future and creating value for both ITS and its customers <Project Name> Project Initiation Document Page 3 of 12
4 1.4 Project Scope The scope of this project is as follows: To setup a new group inside IT Services. To audit all IT Services current services and support mechanisms. To engage with key staff members in UCD from both academic and administrative affairs groups To raise awareness of ITS current service offerings To identify technology trends and demands from Staff and using this data feed into IT Services groups to satisfy these demands where possible or advise best practice or a vendor of choice. Not in scope for this project is: Student groups Vendor management of existing relationships ITRM will not disrupt existing relationships that are in place with ITS groups, however involvement and updates on these relationships would be required. 1.5 Change Control The Project Initiation Document will be approved on commencement of the project by the relevant project members. Following this, an ongoing Project Plan will be maintained and updated to accommodate any minor changes occur. Once the scope is agreed herein, any further changes to scope or major deviation from the proposed time frames will be the subject of the change control and logged using our Jira change management tool. Once requirements have been agreed, additional changes to the requirements will be managed under change control using Jira, as will changes to the agreed design. <Project Name> Project Initiation Document Page 4 of 12
5 2 Project Plan 2.1 Project Approach The ITRM project is a new initiative in IT Services, the ITRM group will be part of the Customer Service team and report into Ciara Acton Head of Customer Services. The project itself has no rigid deadlines as this is not a end product or system rather it is an evolving service which will in the future work closely with senior staff members to form and shape IT demand. As outlined the service will be an evolving one and as such there will be a number of iterations of this as time progress and the service is shaped. As an overall structure there is an internal and external focus on this project. Internal Focus: A period of time will be spend analysing existing services and support methods. This will be done by members of the ITRM project team and carried out by the use of informal / semi structured interviews or meetings to capture a detailed outline of services. Following on from this the ITRM project will gather as much secondary data as possible about current customer data, this includes but is not limited to call logging data, customer requests and local knowledge of different departments and staff of the university. External Focus: The ITRM project will promote both itself and IT Services via a number of methods such as information days / stands, workshop events, one to one meetings with staff and staff groups with an aim to raise awareness and also to get data, demands and requests from our community as a whole. Following on from these data gathering stages the ITRM project will report back to the SMT group with the project findings and demands and based on this align our department strategy with the university strategy and requirements. <Project Name> Project Initiation Document Page 5 of 12
6 2.2 Milestones & Deliverables The following milestones, deliverables and target delivery dates have been defined for the project: Milestone Deliverable Responsibility Reviewers/ Due Date Approvers 0 Project Initiation completed Project Initiation Document completed Paul Barry ITRM group 09/12/14 1 Requirements completed Statement of Requirements 2 ITS Service offerings Detailed listing of all current ITS services ID key customers Paul Barry ITRM grp. Q Project awareness Workshop events Information events F2F meetings Paul Barry Ciara Acton 4 Pilot College College TBA Paul Barry Ciara Acton ITRM grp and SMT ITRM grp Project Sponsor Q Q The individual(s) listed in the Responsibility column above are responsible for the relevant deliverables. Typically each deliverable will have one or many reviewer and a final approval by one or more individuals. Acceptance and sign off of a deliverable is required by the Approval person. 2.3 Project Plan Insert the initial, albeit high level, Project Plan. This can be completed using Excel or MS Project and imported into this document or can be merely a simple timeline to show proposed key milestones. 3 <Project Name> Project Initiation Document Page 6 of 12
7 Project Structure The project comprises a Project Team and a Steering Group. The Steering Group will agree project schedules, approve major deliverables and resolve any critical issues that arise during the lifetime of the project. The Project Team will manage the project on a daily basis and will report regularly to the Steering Group. 3.1 Roles & Responsibilities Define the responsibilities for each group and role within the project. some sample responsibilities for common project groups and roles. The following are Role Responsibilities Names Steering Ensure that the project direction is SMT Exec. Group appropriate to the achievement of the ultimate objectives Review progress reports from the Project Manager and determine actions needed to address deviations Provide guidance to the Project Team on high level principles to be complied with Review and approve deliverables Monitor and proactively manage risks as they arise. Project Sponsor Ensure that resources are provided as required for the project Take action on any issues escalated by the Project Team Seamus Shaw Project Manager Prepare the Project Plans Determine resource requirements and ensure that appropriate resources are allocated Manage the project to ensure that the desired results are achieved within agreed time scales Monitor progress and report on a regular basis to the Steering Committee Ciara Acton / Paul Barry <Project Name> Project Initiation Document Page 7 of 12
8 Prepare project deliverables and their presentation for approval Project Team Conduct the tasks and activities of the project in accordance with the Project Plan Prepare the project deliverables by the agreed due dates Report progress to the Project Manager Caroline Hackman Gary Chapman Other TBA 3.2 Project Team Meetings The following are the scheduled project governance meetings: Team Attendees Frequency Steering Ciara Acton, Seamus Shaw, Paul Barry and Monthly Group members of SMT exec as required Project Team Ciara Acton, Caroline Hackman, Paul Barry,Gary Chapman Weekly 4 <Project Name> Project Initiation Document Page 8 of 12
9 Risks & Issues 4.1 Initial Risk & Issue Log The following project risks or issues have been identified on commencement of the project. These initial tasks to address these risks or issues are outlined. Risk / Issue ITS not involved in IT decision making in UCD Probabilit y H M L Impact H M L Actions Mitigate X X Implement ITRM to Responsibility 4.2 Ongoing Management of Risks and Issues Any additional risks and issues identified will be maintained on an ongoing basis by the Project Manager in separate Risks and Issues logs. <Project Name> Project Initiation Document Page 9 of 12
10 Communication Plan Identify the key stakeholders in the project and the plans for interaction and communication with each. Stakeholders are individuals and groups who will be capable of influencing the success of a project, directly impacted by the project as users or customers or involved in approving or implementing project deliverables. The following table highlights the communication and interaction activities planned for each stakeholder group: Stakeholder Actions Responsibility <Project Name> Project Initiation Document Page 10 of 12
11 5 Project Costs 5.1 Initial Project Budget Outline the proposed costs of the project by phase, typically to cover items such as consultancy resource costs, product/vendor & licence costs, training, any specific hardware costs, etc. You might also want to consider adding in an element of contingency into these costs. 5.2 Ongoing Costs Provide an estimate of any ongoing costs such as recurring licence fees, maintenance charges, etc. <Project Name> Project Initiation Document Page 11 of 12
12 Related Documentation It is often useful to list any related documentation here, such as supporting documentation provided by the business/customer. <Project Name> Project Initiation Document Page 12 of 12
UCD IT Services. Project Initiation Document. Version February Version History
UCD IT Services Application Jukebox Project Initiation Document Version 1.2 12 February 2015 Version History Version Date Summary of Changes Changed by 1.0 01.12.2014 Initial Draft 1.1 09.12.2014 Revisions
More informationProject Manager CAFM Project (Fixed Term) EHA
It is important to note that this job description is a guide to the work you will initially be required to undertake. It may be changed from time to time to meet changing circumstances. It does not form
More informationPOSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8
1200, Scotia Place, Tower 1 10060 Jasper Avenue Edmonton, Alberta T5J 3R8 edmonton.ca/auditor POSSE System Review January 30, 2017 The conducted this project in accordance with the International Standards
More informationInformation Services Group Public Sector
IV&V Assessment Report - Deliverable IVV2.2 Presented by: Information Services Group Public Sector February 12, 2019 2019 Information Services Group, Inc. All Rights Reserved Copyright 2019, Information
More informationTennessee Board of Regents Shared Services Initiative*
Tennessee Board of Regents Shared Services Initiative* Governance Model 1/17/2017 * Note: Tentative project name pending final branding approval Modification History: Date Change made by Description of
More informationISACA Systems Implementation Assurance February 2009
ISACA Pressures Today Pressure to increase realization of value from IT spending Pressure to deliver on IT projects at a time when resources/budgets are constrained Pressure from risk of technology-based
More informationJOB DESCRIPTION & PERSON SPECIFICATION
JOB DESCRIPTION & PERSON SPECIFICATION HIAL AMSL DAL 1. JOB DETAILS JOB HOLDER JOB TITLE REPORTS TO Vacant ICT Advisor Head of ICT and Digital Transformation 2. JOB PURPOSE The Air Traffic Management 2030
More informationProject Charter. A. General Information
A. General Information Project Title: Brief Project Description: Prepared By: Date: Version: B. Project Objective: Explain the specific objectives of the project. For example: What value does this project
More informationProject Execution Plan For
Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended
More informationROLE DESCRIPTION. Strategic Procurement Manager
ROLE DESCRIPTION POSITION Strategic Procurement Manager STATUS Full time AWARD CLASSIFICATION Grade 17 DIVISION Corporate & Organisational Services SECTION Commercial & Business Services - Procurement
More informationCapability Manager, Security and Risk
Capability Manager, Security and Risk Technology Services and Solutions, Service and System Transformation The Capability Manager a key role in the delivery of Security and Risk services across DIA. The
More informationProject Highlight Report
Powys County Council - Standard/Small Level Template Revision July This document is used to give a progress report for a project. It is also a communication tool for the project manager to inform the project
More informationDetermine the project s level of complexity and agree with the owner the options and appropriate approach for delivery.
Job title Senior Project Manager - Migration Job family Project Management Grade 9 Job purpose The Senior Project Manager will deliver a project or multiple projects and expected outcomes, to stakeholder
More informationWHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing cgi.com
WHITE PAPER Business Process Services: A Successful Transition Is the Foundation of World- Class Outsourcing A summary of the key transition questions asked by our clients In this paper, we examine five
More informationManitoba Health, Seniors and Active Living Transformation Program Charter. February 16, 2018 Version 1.0
Manitoba Health, Seniors and Active Living Transformation Program Charter February 16, 2018 Version 1.0 Table of Contents 1 Purpose... 3 2 Background... 3 3 Scope of the Transformation Program... 5 3.1
More informationPOSITION DESCRIPTION
POSITION DESCRIPTION Role Description This role will be responsible for the project management and successful delivery of the Procurement Transformation project. The project s objectives are to gain
More informationA project supported by the European Union s INTERREG VA Programme, managed by the Special EU Programmes Body.
A project supported by the European Union s INTERREG VA Programme, managed by the Special EU Programmes Body. MACE (Breaking the Cycle) Children s Services Project Co-operation and Working Together (CAWT)
More informationTusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018
Tusla Programme Management (PMO) Design and Establishment Fergal Collins 20 th September 2018 1 Contents Tusla Overview Executive Summary. Choosing an operating model for the PMO. 3 PMO Models to choose
More informationInformation Services Group Public Sector
IV&V Assessment Report - Deliverable IVV2.2 Presented by: Information Services Group Public Sector November 8, 2018 2018 Information Services Group, Inc. All Rights Reserved Copyright 2018, Information
More informationPROJECT MANAGEMENT. By Pompeyo Rios
PROJECT MANAGEMENT By Pompeyo Rios PROJECT A project is a temporary endeavor undertaken to create a unique product, service, or result. Por example, constructing a building or plant, or implementing, improving,
More informationWho Should be on Your Project Team: The Importance of Project Roles and Responsibilities
Who Should be on Your Project Team: The Importance of Project s and One significant factor contributing to the success of projects is having the right people engaged in the process. Who are the right stakeholders
More informationJOB DESCRIPTION. Senior Project Manager.docx. Job family Project Management Grade 9
Job title Senior Project Manager Job family Project Management Grade 9 Job purpose To deliver a project, or multiple projects and expected outcomes, to stakeholder expectations, within the agreed brief,
More informationISO/IEC INTERNATIONAL STANDARD. Corporate governance of information technology. Gouvernance des technologies de l'information par l'entreprise
INTERNATIONAL STANDARD ISO/IEC 38500 First edition 2010-06-01 Corporate governance of information technology Gouvernance des technologies de l'information par l'entreprise Reference number ISO/IEC 38500:2008(E)
More informationJOB DESCRIPTION. Senior Business Analyst Proposed band
Job title Senior Business Analyst Job family Business Analysis Proposed band D Job purpose To undertake the business analysis function within Design & Engineering ensuring that business requirements and
More information<Project Name> Charter
< NOTE: Remove the italicized, bracketed guidance before routing for approvals. > General Information 1. Project Number: 2. Project Name: 3. Executive : 4. Business : 5. IT : 6. Project Manager/Lead: Executive
More informationC22(12) COUNCIL. GOC Business Plan KPIs and Core Activity Performance Indicators. Lead responsibility: Samantha Peters Chief Executive and Registrar
C22(12) COUNCIL GOC Business Plan KPIs and Core Activity Performance Indicators Meeting: Public 25 April 2012 Lead responsibility: Samantha Peters Chief Executive and Registrar Status: for decision Contact
More information1.0 PART THREE: Work Plan and IV&V Methodology
1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring
More informationInternal Audit. Consultants Job Planning. February 2018
Internal Audit Consultants Job Planning February 2018 Internal Audit assessment: Objective Objective Objective Objective One Two Three Four Significant Objective Objective Objective Objective Five Six
More informationLoch Lomond & The Trossachs National Park Authority and Cairngorms National Park Authority
Loch Lomond & The Trossachs National Park Authority and Cairngorms National Park Authority Internal audit report 2014-15 Project Management 15 January 2015 Contents This report is for: Action David Cameron
More informationAnnex 2: Statement of work. Table of contents
UNFCCC/CCNUCC Page 1 Annex 2: Statement of work Table of contents Annex 2... 2 Objective... 2 Engagement... 2 Overall approach... 2 Partnering... 3 Quality and reviews... 3 Developer contract... 4 Operator
More informationINTERNAL AUDIT DIVISION REPORT 2019/009. Audit of the Unified Judicial Database project at the International Residual Mechanism for Criminal Tribunals
INTERNAL AUDIT DIVISION REPORT 2019/009 Audit of the Unified Judicial Database project at the International Residual Mechanism for Criminal Tribunals There is need to harmonize the work processes, revise
More informationA Primer for the Project Management Process by David W. Larsen 1. Table of Contents
A Primer for the Project Management Process by David W. Larsen 1 Table of Contents Description... 2 STAGE/STEP/TASK SUMMARY LIST... 3 Project Initiation 3 Project Control 4 Project Closure 6 Project Initiation...
More informationEnterprise Data Strategy and Governance
Project Charter DATE: 9/20/2017 VERSION 1.0 Prepared By: Melany Leavitt and Paul Given Page 1 Document Revision History Version Number Date Description.01 5/25/2017 Draft Charter.02 9/1/2017 Draft for
More informationHealth and Safety Management Profile (HASMAP)
Health and Safety Management Profile (HASMAP) Contents Introduction 02 HASMAP overview 03 Getting started 04 Indicator summaries A Leadership 07 B Planning for emergencies 15 C Health and safety arrangements
More informationKronos Workforce Ready Implementation Methodology and Customer Responsibilities for WFR Time Keeping Implementations
DATASHEET WORKFORCE READY DEPLOYMENT GUIDE Kronos Workforce Ready Implementation Methodology and Customer Responsibilities for WFR Time Keeping Implementations As you begin your Kronos Workforce Ready
More informationBANNER 9 IMPLEMENTATION PROJECT
BANNER 9 IMPLEMENTATION PROJECT TEAM ROLES & RESPONSIBILITIES Table of Contents Executive Sponsors... 3 Steering Committee and Project Owner... 4 Project Director Responsibilities... 5 Project Manager
More informationAPPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS
APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required
More information- Not Protectively Marked - NOTTINGHAMSHIRE POLICE JOB DESCRIPTION
NOTTINGHAMSHIRE POLICE JOB DESCRIPTION Job title: Department/Location: Responsible to: Responsible for: Project Manager Business & Finance Head of Programme Management N/A Date: 10 th September 2012 Library
More informationJOB DESCRIPTION. Proposed band. Technical Systems & Delivery
Job title Job family Business Analyst Technical Systems & Delivery Proposed band D Job purpose Business Analysts ensure that business requirements and processes are fully understood and clearly documented.
More informationRISK MANAGEMENT - FRAMEWORK. OBJECTIVE To outline the Bay of Plenty District Health Board (BOPDHB) framework for risk management
OBJECTIVE To outline the Bay of Plenty District Health Board (BOPDHB) framework for risk management STANDARD All employees are responsible for ongoing identification of risk. Risk management at BOPDHB
More informationUNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES
UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES Document Status: Approving Body: Last Update: Author: Approved Information Services
More informationJOB DESCRIPTION. 3. To ensure the team provide benefits advice, signposting and an effective income collection service.
JOB DESCRIPTION POST TITLE: Team Leader - Credit Control SECTION: Tenancy & Leasehold Services POST No. [If applicable]: DATE LAST REVIEWED: LOCATION: Within the London Borough of Hackney RESPONSIBLE TO:
More information1 P a g e P r i s m e t r i c T e c h n o l o g i e s
1 P a g e P r i s m e t r i c T e c h n o l o g i e s Our Methodology Over the years of developing challenging technology solutions for our multi-national clients, we have devised a practical process of
More informationESTABLISHMENT OF A QUALITY SYSTEM
GENERAL CIVIL AVIATION AUTHORITY OF BOTSWANA ADVISORY CIRCULAR CAAB Document GAC-009 ESTABLISHMENT OF A QUALITY SYSTEM GAC-009 Revision: Original 19 Mar 2013 Page 1 of 29 Intentionally left blank GAC-009
More informationISC: UNRESTRICTED AC Attachment. Environmental & Safety Management- EnviroSystem Oversight Audit
Environmental & Safety Management- EnviroSystem Oversight Audit September 9, 2016 THIS PAGE LEFT INTENTIONALLY BLANK ISC: UNRESTRICTED Table of Contents Executive Summary... 5 1.0 Background... 7 2.0 Audit
More informationPASA GUIDANCE. Trustees Administration Governance Checklist. July 2018
PASA GUIDANCE Trustees Administration Governance Checklist July 2018 Administration Governance Occupational Pension Scheme Trustee Checklist The Pensions Administration Standards Association (PASA) has
More informationHead of HSE. Group Services, Risk
Policy Title: Document Owner: Owning Department: Classification: Environmental Sustainability Policy Head of HSE Group Services, Risk KCOM Group Internal use only Business Units affected by this Policy:
More informationCore Skills: Contributing Skills: Role Title: Senior Project Manager EXAMPLE. Reference: SFIA level 5
Role Title: Senior Project Manager EXAMPLE Reference: SFIA level 5 Core Skills: Requirements definition and management Stakeholder relationship management (REQM) Level 5 (RLMT) Level 5 Financial management
More informationGOVERNANCE SMART objectives / SUHFT board development programme
GOVERNANCE SMART objectives / SUHFT board development programme Specific objective Measurable Success Actions required Relevance / Outcome Owner Time Documented set of Trust Board objectives will be in
More informationTemporary, contract and interim recruitment services Permanent and fixed term selection recruitment services Retained & executive recruitment services
QUALITY MANAGEMENT POLICY & PROCEDURES Policy Statement CDS Recruitment Limited specialises in the recruitment of Engineering, Technical and Scientific personnel in the Chemical and Pharmaceutical, Oil
More informationCOMPLIANCE MANAGEMENT FRAMEWORK FOR VICTORIA UNIVERSITY
COMPLIANCE MANAGEMENT FRAMEWORK FOR VICTORIA UNIVERSITY July 2018 Prepared by: Policy Services (Compliance) Portfolio of the Vice-President (Planning) and Registrar Contents 1. BACKGROUND... 2 2. COMMITMENT
More informationOE PROJECT CHARTER PROJECT NAME: PREPARED BY: PROJECT CHARTER VERSION HISTORY VERSION DATE
PROJECT : PREPARED BY: Josh Blatt DATE (MM/DD/YYYY): 1/9/2012 Institutional Data Council Project Manager PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED CURRENT STATUS) (MM/DD/YYYY)
More informationJIGAWA STATE GOVERNMENT. Office of the Head of the Civil Service Organisational Performance Management Model
JIGAWA STATE GOVERNMENT Office of the Head of the Civil Service Organisational Performance Management Model November 2014 Content List Content List... 2 Acknowledgment... 3 Abbreviations and Acronyms...
More informationHead of Business Strategy
Empower Limited Job Description empower.co.tz info@empower.co.tz +255 758 778 886 9th Floor Tanzanite Park, Victoria, Dar es Salaam, Tanzania Roles and Responsibilities Head of Business Strategy Strategic
More informationWDVA EMR Project Readiness Assessment Report
WDVA EMR Project Readiness Assessment Report 1 Prepared by: Marcus Bailey Project QA Assurance Consultant New Compass Consulting, LLC marcus@newcompassconsulting.com Tele: 360-239-4607 Transformation Leadership
More informationInformation Services Group Public Sector
IV&V Assessment Report - Deliverable IVV2.2 Presented by: Information Services Group Public Sector December 12, 2018 2018 Information Services Group, Inc. All Rights Reserved Copyright 2018, Information
More informationPROJECT DESIGN GUIDE D02 COMMUNICATION PLAN
PDG PROJECT DESIGN GUIDES D02 PROJECT DESIGN GUIDE D02 COMMUNICATION PLAN Project Name: Name Project No.: Number Date: Date Document No.: PDG-PDG-PRO-D02.0 Date Created: 2 nd May 2012 Date Revised: R01
More informationThe purpose of this paper is to present the outcome of recent PR19 assurance activities for note by the Water Forum.
BUSINESS PLAN UPDATE ASSURANCE DASHBOARD PAGE 1 OF 1 1. PURPOSE OF PAPER The purpose of this paper is to present the outcome of recent PR19 assurance activities for note by the Water Forum. 2. QUALITY
More informationCOF: Assessing, Analyzing and Improving the Role of our Current Learning Technologies in Student Success FORMAL RFP
COF: Assessing, Analyzing and Improving the Role of our Current Learning Technologies in Student Success FORMAL RFP I. GENERAL INFORMATION: Colleges of the Fenway ( COF ), is a consortium of six (6) colleges
More informationCOMPLIANCE MANAGEMENT FRAMEWORK. Conceptual Design Document
COMPLIANCE MANAGEMENT FRAMEWORK Conceptual Design Document 18 February 2013 1. INTRODUCTION & SUMMARY The purpose of the Compliance Management Framework is to ensure the University meets all of its external
More informationNote: appendix may include further responsibilities or experience necessary for the particular role.
Job title Job family Project Manager Project Management Proposed band D Job purpose To collaborate with a business or product owner to deliver a project, or many projects; deliver expected outcomes and
More informationRisk Management at Statistics Canada
Risk Management at Statistics Canada Presentation to Workshop on Risk Management Practices in Statistical Organizations J. Mayda April 25 th, 2016 Introduction Statistics Canada has had a formal Integrated
More informationCapital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017
Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and
More informationVISION To make Sydney and NSW one of the world s most successful tourism and events destinations.
ROLE DESCRIPTION International Partnerships Co-ordinator Division: Industry Partnerships and Government Policy Location: Sydney, Australia Grade Equivalent: 7/8 Kind of Employment: Permanent ANZSCO Code:
More informationCUSTOMER BANK ACCOUNT MANAGEMENT SYSTEM PROJECT PLAN 10 TH FEB Approved On. 20 Feb 2015 Page 1 of 11 Project Plan Approved By.
CUSTOMER BANK ACCOUNT MANAGEMENT SYSTEM PROJECT PLAN 10 TH FEB 2015 Approved On. 20 Feb 2015 Page 1 of 11 Project Plan Contents 1. INTRODUCTION 3 1.1. Project Overview 3 1.2. Scope of Work 3 1.3. Project
More informationWell Led Governance Review
Preparing Governors for the : Well Led Governance Review Julie Dawes - Interim Trust Secretary Lindsay Winterton Interim Joint Membership and Governance Manager Tuesday 7 October 2014 Objectives of today
More informationProject Management Handbook
Project Management Handbook Version 0.1 September 2011 1 CONTENTS Introduction 3 The Project Lifecycle 3 Aspyre 4 Project or Programme 5 Project Management 6 Phase 1 Prepare 7 Project Brief 7 Business
More informationEstablishing a Medical Licensing Assessment Programme Board
Agenda item: 8 Report title: Report by: Action: Establishing a Medical Licensing Assessment Programme Board John Carr, Programme Manager, MLA john.carr@gmc-uk.org, 0161 240 8308 To consider Executive summary
More informationModeration and Validation of Assessment TAFE Procedure. Moderation and Validation of Assessment
PROCEDURE Operational Responsibility: Related Policy: Moderation Validation of Assessment TAFE Procedure Academic Registrar Moderation Validation of Assessment PROCEDURE STATEMENT INTENT SCOPE To ensure
More informationCHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS
CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS Objectives Introduction The objectives are: Describe the purpose of the phase planning activity, preconditions, and deliverables in the implementation methodology.
More informationALBANY PORT AUTHORITY ENVIRONMENTAL MANAGEMENT SYSTEM
ALBANY PORT AUTHORITY ENVIRONMENTAL MANAGEMENT SYSTEM May 2006 Document Status Rev Author Reviewer/s Date Approved for Issue No. Name Distributed To Date 1 J. Prout V. Ee 26/05/06 V. Ee Albany Port Authority
More informationDEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018
DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018 3 FACILITATOR: RYAN WEST 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: MELISSA TURNER, CAROLYN HICKS, PAUL LAVERY, RACHAEL LIEBLICK, ANGIE ROBERTSON
More informationProject Plan City of Newport News; Department of Health and Human Services
Project Plan City of Newport News; Department of Health and Human Services 7/14/2010 Harmony Information Systems, Inc. 12120 Sunset Hills Road, Suite 500 Reston, VA 20190 MAIN: 703-674-5100 www.harmonyis.com
More informationRTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning
1 Project Management Plan Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning SOUTH WEST CORRIDOR STUDY (OXLEY ROAD) PROJECT OWNER: GRAEME READ 2 Document Change History
More informationServices Description. Transformation and Plan Services. Business Transformation and Plan Services
Services Description Business ation and Plan Services Business ation and Plan Services SAP Business ation and Plan Services provides consulting and prototyping services to facilitate Licensee innovation
More informationLEGAL AID BOARD BOARD EVALUATION FINAL REPORT
LEGAL AID BOARD BOARD EVALUATION FINAL REPORT May 2018 Governance Advisory Services Ireland Limited, 32 Leeson Street Lower, Dublin 2, Ireland. Telephone: +353 (0)1 639 2928, Email: info@governanceireland.ie,
More informationAction to date: Recommendation 2: Response: Action to date:
ANNEX C 360 Assurance Report Urgent and Emergency Care Centre Project 3rd Project Governance Assurance Report Response to recommendations Background: 360 Assurance were appointed by the CCG to provide
More informationAudit Report. Audit of Spectrum Application Modernization - Commercial Software Implementation
Audit Report Audit of Spectrum Application Modernization - Commercial Software Implementation June 2012 Recommended for approval to the Deputy Minister by the Departmental Audit Committee on July 12, 2012
More informationInternal: Executive, IS Team, All business stakeholders, Business Process Owner External: IS Service Providers, Vendors, Software Consultants
Position Title: IS Project Manager No.: HSF136 Reports to: Title: Senior Programme Manager and Team Lead No.: HSF135 Business Unit: Information Services Date created: April 2018 Division: CFO Review date:
More informationJOB DESCRIPTION. Proposed band
Job title Job family Senior Project Manager Project Management Proposed band D Job purpose To deliver a project, or multiple projects and expected outcomes, to stakeholder expectations, within the agreed
More informationFIRECONTROL PROJECT. Transition Governance, Roles & Responsibilities. Release: Version 1.0. Release Date: DRAFT
FIRECONTROL PROJECT Transition Governance, Roles & Release: Version 1.0 Release Date: DRAFT Doc Ref: RPT0697 User Division: FRD Created by: Christophe Halcrow, national transition workstream Approved by:
More informationProject Origination: Item Description (Origination) Comments (or reasons for NOT completing)
Project Origination: (Origination) Develop Project Proposal: 24 Formulate business need/problem and 24 anticipated benefits to all parties Review project s fit with organization s mission 24 Identify project
More informationI-SEM Programme Project Office Programme Change Control Procedure
Project Office Programme Change Control Procedure Version: 1.1 FINAL Date: 8 March 2017 Document Control Production Authors Responsibility Date Jim McAllister I-SEM PMO 01/07/2015 Helen Mounsey I-SEM PMO
More informationTHE INSTITUTE OF INTERNAL AUDITORS
THE INSTITUTE OF INTERNAL AUDITORS Job description Position : Manager in the Office of the CEO Unit: CEO s Office Incumbent s Name: Department Head s Name: Department Head s position: CEO Accepted By:
More informationThe Corporation of the City of London Management compensation process assessment Internal Audit Report
The Corporation of the City of London Management compensation process assessment Internal Audit Report Audit performed: October 2017 - January 2018 Final report issued: April 23 2018 The Corporation of
More informationPART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)
PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes
More informationProject Management Initiation Document
Project Management Initiation Document This document provides an ideal project management plan template which can be used by anyone at any level who is undertaking a project and is looking for a plan structure
More information1. INTRODUCTION The Mining Qualification Authority (MQA) is a public entity established in terms of section 45 of the Mine Health and Safety Act, Act No. 29 of 1996 (MHSA) and is a Sector Education and
More informationFlorida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015
Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: April June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Financial
More informationERM Component No. Recommendations Management Response Status Update
Internal Environment 1. Medicaid formally establish an Steering Committee to oversee efforts to identify, assess, measure, respond to, monitor, and report risks. The Committee should include an executive
More informationPRODUCING A WORKFORCE DEVELOPMENT PROJECT PLAN
PRODUCING A WORKFORCE DEVELOPMENT PROJECT PLAN 1. WE ARE ALL PROJECT MANAGERS Project management is not difficult. People can be difficult. The art of being a good change manager is getting people to do
More informationHealth Information Technology Administrative Technology Subcommittee
Mission Health Information Technology Administrative Technology Subcommittee The Administrative Technology Subcommittee has been created to define strategies for the development and use of Administrative
More informationANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance
ANNEX THREE Regime for Monitoring of Separation of Batelco and NBN Compliance Compliance Monitoring Regime Draft for Discussion Purpose: To establish a regime for monitoring Batelco s compliance with the
More informationKING IV GOVERNANCE PRINCIPLES APPLICATION BY MURRAY & ROBERTS FY The governing body should lead ethically and effectively (Leadership)
KING IV GOVERNANCE PRINCIPLES APPLICATION BY MURRAY & ROBERTS FY2018 LEADERSHIP, ETHICS AND CORPORATE CITIZENSHIP 1. The governing body should lead ethically and effectively (Leadership) The Board is the
More informationUniversity of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives
University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives Updated: October 2017 1. Introduction This procedure exists to ensure operational adherence with
More informationCustomer Support Group (CSG) Invoicing and Monitoring Arrangements. April 2016
Internal Audit Customer Support Group (CSG) Invoicing and Monitoring Arrangements April 2016 Distributed to: Chief Operating Officer Commercial Director Director of Resources Head of Finance Partnership
More informationQuality Management_100_Quality Checklist Procedure
Quality Management_100_Quality Checklist Procedure Last updated 05/15/2017 Audience: Project Team, Process Owners, Project Management Office Frequency: As Required This procedure provides detailed information
More informationEAST SUSSEX FIRE AUTHORITY Job Description
EAST SUSSEX FIRE AUTHORITY Job Description Job Title: Supplier Service Manager Job Family: JF6 Specialist/Technical Manager Reporting to: ITG Manager Responsible for: 1 direct report (Support Officer,
More informationNATIONAL COLLEGE FOR HIGH SPEED RAIL JOB DESCRIPTION. Job title: Project Manager
NATIONAL COLLEGE FOR HIGH SPEED RAIL JOB DESCRIPTION Job title: Project Manager Job title: Project Manager Salary c 40,000 fixed term contract until end December 2017 Reporting to: Location: Programme
More informationRole Description Development Officer
Role Description Development Officer Cluster Planning and Environment Agency Sydney Living Museums Division/Branch/Unit Strategy & Engagement Division/Development & Fundraising Team Location The Mint Classification/Grade/Band
More information