SECTION GENERAL REQUIREMENTS

Size: px
Start display at page:

Download "SECTION GENERAL REQUIREMENTS"

Transcription

1 SECTION GENERAL REQUIREMENTS PART 1 GENERAL 1.01 WORK COVERED BY CONTRACT DOCUMENTS A. Work of this Contract comprises the chiller and cooling tower replacement at Five Oaks Middle School which includes general construction, mechanical, plumbing, and electrical work CONTRACTOR USE OF PREMISES A. Work Sequence: Perform Work in manner required to accommodate the District s use of premises during the Contract Period. Coordinate Work schedules and operations with the District s use requirements. 1. Owner s Maintenance Staff will be in the building from 6 am until 4 pm, Contractor shall coordinate use of the premises so as to not interfere with the Owner s Use during that time. 2. Complete and exclusive use of the construction areas except as outlined above or noted in Special Conditions, will be permitted from Notice to Proceed until Substantial Completion. 3. During the Owner s occupancy there may be days (Down Days) during the Contract Period when occupied areas will be closed. Contractor shall request from the District a list of Down Days that may occur during the Contract Period. Contractor shall notify the District at least 48 hours in advance of Down Days during which time the Contractor intends to work. The District will pay for custodians time during such Down Days when the building is required to be open for the Contractor s use. B. Noninterference with School 1. Perform work upon or adjacent to existing Owner occupied structures, in such manner as to not interfere with continued free and comfortable use of structures. 2. During normal school hours, keep building exists safe, protected, restricted use from rest of construction site and clear of obstructions at all times. If closure of an exit is required by the Work, notify the Principal and allow ample time for an alternate plan to be executed. 3. Work shall not be performed in Owner occupied area and similar spaces during normal school hours when such spaces are required for school purposes. Such Work shall be performed after normal school hours up to 10:00 p.m. if no nighttime school activities are planned, or during weekends and vacations periods when school is normally closed. All Work required to be planned in spaces being utilized for school purposes must be closely scheduled with the District so that such spaces may be safely reused when classes resume. C. Noninterference With Serving Utilities 1. Do not interrupt electric, gas, water or other services to existing Owner occupied structures without prior notice to the District and then only at a definite time and for a definite duration approved by the District. 2. Contractor shall schedule demolition, remodel and new construction to accommodate Owner s continued use of existing and/or new mechanical, plumbing, and electrical services as required for Owner s continued occupancy and beneficial use of designated areas GENERAL REQUIREMENTS

2 3. Consult with public and private utility companies for location and extent of all utilities before commencing Work. 4. Provide all services required. Protect and maintain existing utilities, active electrical conductors, sewers, pipes, and other active lines on school property or in street excavations. 5. Arrange for and pay cost of disconnecting, removing, relocating, capping, replacing, or abandoning of public and private utilities in the way of construction operations in accordance with serving utilities, local regulations and governing codes. Utilities, pipes, sewers, electrical conductors and the like to be abandoned shall be capped in accordance with instruction of governing authority or as directed. D. Protections 1. Protect sidewalks, asphalt paving, concrete, shrubs and lawn areas at all times from spillage of materials used in carrying out the Work. Exercise care to preclude materials from clogging catch basins and yard drains. Leave all drainage items clean and in proper working condition. 2. Clean, repair, resurface or restore existing surfaces to their original condition, or completely replace such surface to match existing, where damaged by construction operations. 3. Whenever it is necessary to cut and remove fences and/or power lines (whether on private or public property), restore such demolished work to condition at least equal to that which existed prior to such demolition. 4. Damage to property adjacent to District s property shall be restored to the satisfaction of respective property owners TIME OF COMPLETION A. The Work of this Contract shall be commenced on the date of written notice to proceed and shall be completed by dates established in Section III, Statement of Work SAFETY REQUIREMENTS A. Associated General Contractors of America, Inc., Manual of Accident Prevention in Construction, Workmen s Compensation Board Safety Code for Construction Work, Oregon State Employment Act Safety Requirements, and Occupational Safety and Health Act (OSHA) requirements, as applicable, apply to Work specified herein ASBESTOS FREE CERTIFICATION A. Absolutely no materials containing asbestos are to be provided or installed as part of this Project. The Contractor shall ensure that no subcontractor or any of Contractor s own forces installs any materials containing asbestos. At final closeout of the Project, the Contractor shall provide to the School District certification that no materials containing asbestos have been installed in the Project and that the Project is asbestos free as required by the State of Oregon CONTRACTOR USE OF PREMISES A. Contractor will have access to site after issuance of written notice to proceed. B. Coordinate use of premises under direction of Owner CHANGE ORDERS GENERAL REQUIREMENTS

3 A. Submit name of the individual authorized to accept changes, and to be responsible for informing others in Contractor s employ of changes in the Work. B. Change Order Forms: Beaverton School District Change Order Form (replaces AIA G701) COORDINATION A. The Contractor is responsible for overall coordination of the Project. B. The Drawings and Specifications are arranged for convenience only and do not necessarily determine which trades perform the various portions of the Work. C. Coordinate sequence of the Work to accommodate Owner occupancy. D. Do all necessary Work to receive or join the Work of all trades. E. Verify location of existing utilities and protect from damage CUTTING AND PATCHING A. Provide cutting (including excavating), fitting and patching of the Work as required. B. Make its several parts fit properly together. C. Uncover Work to provide for installation of ill-timed Work. D. Remove and replace defective Work. E. Remove and replace Work not conforming to requirements of Contract Documents. F. Remove samples of installed Work as specified or where directed for testing. G. Install specified Work in existing construction. H. Uncover Work to provide for Engineers observation of Work covered prior to inspection or approval. I. Provide routine penetrations of non-structural surfaces for installation of piping, ducts, electrical conduit, and other mechanical and electrical items SUBMITTALS A. Submit schedule of all shop drawings, product data and samples specified in each individual section of the project manual. Coordinate construction schedule and installation dates of each product and assembly and allow ample time for the Engineer s review. Allow time for possible disapproval and resubmittal. B. Deliver submittals to the Engineer of Record, Scott Miller, P.E. of MFIA, Inc. Consulting Engineers located at 2007 SE Ash St., Portland, OR C. Transmit each item under Engineer s-accepted form. Identify Project, Contractor, Subcontractor, and major supplier; identify pertinent Drawing sheet and detail number, and Specification Section number, as appropriate. Identify deviations from Contract Documents. Provide space for Contractor and Engineer review stamps GENERAL REQUIREMENTS

4 D. Apply Contractor s stamp, signed or initialed certifying that review, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents. E. Coordinate submittal of related items with construction schedule for timely submittal to Engineer. F. After Engineer review of submittal, revise and resubmit as required, identifying changes made since previous submittal. G. Do not fabricate products or begin work which requires submittals until return of submittal with Engineer acceptance. H. Timing of Submittals: 1. Submittals Within 7 days of Notice of Award of Contract a. A designation of the Work to be performed by the Contractor by his own forces. b. List of Subcontractors and major materials suppliers for principal portions of the Work. 2. Submittals Prior to Notice to Proceed: a. Executed Agreement b. Performance and Labor & Material Payment bonds per Oregon Law (ORS , , ) with certified copy of Power of Attorney from Attorney-in-Fact executing bonds. c. Certified copies of Contractor s Liability Insurance Policies (AIA Doc.G705) 3. Submittals Within 30 days After Notice to Proceed and Prior to first Payment Application: a. Schedule of values. b. Schedule of submittals. c. Copies of acquired building permit licenses etc. to complete the work of this contract. d. Construction schedule. 4. Submittals Prior to each Month s Payment: a. Application and Certificate for Payment (AIA Document G702 and G703). b. Notarized affidavit of payments to all subcontractors and major material suppliers. c. Updated construction schedule. d. Public Works Contractor Wage Certification per Oregon Law. 5. Submittals Prior to Substantial Completion: Notification to Engineer that work of the Project is substantially complete, including a listing of items of work to be completed or corrected, together with certificate of occupancy or occupancy permit issued by the Local Building Department for the entire Project. I. Schedule of Values; Submit typed schedule on AIA Form G703; Contractor s standard form or media-driven printout will be considered on request QUALITY CONTROL A. Inspection and Testing Laboratory Services: Owner will employ and pay for services of an Independent Testing Laboratory to perform inspections, test and other services required by individual Specification Sections. 1. Services will be performed in accordance with requirements of governing authorities and with specified standards GENERAL REQUIREMENTS

5 2. Contractor shall cooperate with Testing Laboratory personnel; furnish tools, samples of materials, design mix, equipment, storage and assistance as requested. 3. Notify Engineer and Testing Laboratory 24 prior to expected time for operations requiring testing services. 4. Make arrangements with Testing Laboratory and pay for additional samples and test for Contractor s convenience. B. When tests or inspections indicate non-compliance with the Contract Documents, subsequent retesting occasioned by such non-compliance shall be performed by the same personnel as performed the initial test or inspections. Cost for retesting will be charged to the Contractor by deducting expenses from the contract sum CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS A. Barriers: 1. Provide barriers to prevent unauthorized entry to construction areas while allowing for Owner s use of site, and to protect existing facilities and adjacent properties from damage from construction operations and demolition. 2. Protect non-owned vehicular traffic, stored materials, site and structures from damage. B. Pollution Control: 1. Provide dump box for collection of waste materials. 2. Disposal of volatile fluid wastes (such as mineral spirits, oil or paint thinner) in storm or sanitary sewer systems is prohibited. 3. Keep Site and surrounding areas clear of accumulation of waste material and rubbish resulting form operations under this Contract. Remove waste from Site immediately upon completion of Work. C. Exterior Enclosures: 1. Provide temporary weather-tight closure of exterior openings to accommodate acceptable working conditions and protection for Products, to allow for temporary heating and maintenance of required ambient temperatures identified in individual specification sections, and to prevent entry of unauthorized persons. 2. Provide access doors with self-closing hardware and locks. 3. Provide temporary roofing as required. After work is stated at each site, Contract is responsible for providing a watertight roof enclosure at the end of each day s work. D. Interior Enclosure: 1. Provide temporary partitions and ceilings as required to separate work areas from Owner occupied areas, to prevent penetration of dust and moisture into Owner occupied areas, and to prevent damage to existing materials and equipment. 2. Construction: Framing and reinforced polyethylene sheet materials with closed joints and sealed edges at intersections with existing surfaces in accordance with ASTM E90 (maximum Flame Spread Rating of 75) and in accordance with ASTM E84. E. Protect of Installed Work: 1. Protect Installed Work and provide special protection where specified in individual Specification Sections. 2. Provide temporary and removable protection for installed Products. Control activity in immediate work area to minimize damage GENERAL REQUIREMENTS

6 3. Do not remove temporary bracing, and shoring until adequate permanent connections or structural elements are in final position and positively anchored. 4. Provide protective coverings at walls, projects, jambs, sills, and soffits of openings. 5. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials. 6. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer. 7. Prohibit traffic from landscaped areas. F. Vegetation Damage Control: 1. Protect all existing trees to remain on site from foliage, trunk, and root damage. 2. Provide barricades and maintain same around all trees, shrubs, or other landscaped areas adjacent to work of this Contract to protect such areas from damage of any nature caused by construction operations. 3. Replace any plantings damaged or destroyed with plants of equivalent size, type and nature as approved by the Engineer. G. Security: 1. Provide security and facilities to protect Work, and Owner s operations from unauthorized entry, vandalism, or theft. 2. Provide temporary locks and doors at all openings after building is enclosed. 3. Coordinate with Owner s security program/ H. Field Offices and Sheds: 1. General: Furnish and install a field office building(s) adequate in size and accommodation for all Contractor s offices, job site meetings, Superintendent s office, supply room and tool room. 2. Locate office and sheds as directed MATERIAL AND EQUIPMENT A. Product Options: 1. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description. 2. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not specifically named. 3. Products Specified by Naming Several Manufacturers: Products of named manufacturers meeting specifications: No options, no substitutions allowed. B. Limitations on Substitutions: 1. Submit requests for substitution of products to the Engineer prior to Bid opening date as outlined under AIA Document A701- Instructions to Bidders. Requests received after that time will not be considered. 2. Substitute products shall conform with all requirements of product specified including, but not limited to function, appearance, quality, performance, and fire and life safety and other code requirements. 3. Substitutions will not be considered when indicated on shop drawings or product data submittals without separate formal request, when requested directly by subcontractor or supplier, or when acceptance will require substantial revision of Contract Documents. 4. Substitute products shall not be ordered or installed without written acceptance CONTRACT CLOSEOUT GENERAL REQUIREMENTS

7 A. Prerequisites to Substantial Completion 1. Obtain and submit releases enabling Owner s full and unrestricted use of the work and access to services and utilities, including (where required) occupancy permits, operating certificates, and similar releases. 2. Complete final cleaning up requirements, including touch up of marred surfaces. 3. Upon receipt of Contractor s written request for substantial completion inspection, Engineer will either proceed with inspection or advise Contractor of prerequisites not fulfilled. 4. Following initial inspection, Engineer will either prepare certificate of substantial completion, or advise Contractor of work which must be performed prior to issuance of certificate; and repeat inspection when requested and assured that work has been substantially completed. 5. Results of completed inspection will form initial punch list for final acceptance. B. Prerequisites to Contract Closeout: 1. Letter referencing the Engineers last punch list by date, stating that all items listed have been completed and requesting a contract completion inspection. 2. Submit final payment request with final releases and supporting documentation not previously submitted and accepted. Include releases and waivers of liens from Contractors subcontractors and material suppliers, in form approved by the Owner. Include certificates of insurance for projects and completed operations where required. 3. Submit updated final statement, accounting for additional (final) changes to Contract sum. 4. Submit certified copy of Engineers final punch list of itemized work to be completed or corrected, stating that each item has been completed or otherwise resolved for acceptance, endorsed and dated by Engineer. 5. Submit consent of surety. 6. Revise and submit evident of final, continuing insurance coverage complying with insurance requirements. 7. Submit specific warranties, workmanship/ maintenance bonds, maintenance agreements, final certification and similar documents, all complete in final form C. Project Record Comments: Maintain on site, on set of Contract Documents; record actual revisions to the Work. D. Record Documents: Legibly mark each item to record actual construction including: 1. Measured horizontal and vertical locations of underground utilities and appurtenances referenced to permanent surface improvements. 2. Measured locations of internal utilities and accessible features of the Work. 3. Field changes of dimension and detail. 4. Details not on original Contract Drawings. E. Warranties: Provide notarized copies. END OF SECTION GENERAL REQUIREMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

SECTION A. Examination, preparation, and general installation procedures.

SECTION A. Examination, preparation, and general installation procedures. SECTION 01 7000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Cutting and patching. C. Cleaning and protection. D. Substantial Completion E. Final

More information

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT)

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) 1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) The use of an existing elevator during construction shall be strictly prohibited. Any deviation

More information

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 01 7000- PART 1 GENERAL 1.01 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Pre-installation meetings. C. Cutting and patching. D. Surveying for laying out

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION SECTION 02 41 14 SELECTIVE BUILDING DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for systematic removal of site improvements or portions of exterior and interior of buildings

More information

DIVISION 2- EXISTING CONDITIONS

DIVISION 2- EXISTING CONDITIONS DIVISION 2- EXISTING CONDITIONS 024100- SELECTIVE DEMOLITION PART 1 - GENERAL: 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION SUMMARY OF WORK

SECTION SUMMARY OF WORK SECTION 01010 - SUMMARY OF WORK PART 1 - GENERAL 1.01 SUMMARY OF WORK A. Work covers construction of the new Southeast Kentucky Regional Business Park Speculative Building #3, with associated site work.

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 024116 - STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

SAFEGUARDS DURING CONSTRUCTION

SAFEGUARDS DURING CONSTRUCTION CHAPTER 14 SAFEGUARDS DURING CONSTRUCTION SECTION 1401 GENERAL [B] 1401.1 Scope. The provisions of this chapter shall govern safety during construction that is under the jurisdiction of this code and the

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings.

A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings. SECTION 024113 - SITE DEMOLITION PART 1 -GENERAL 1.1 SUMMARY A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings. 1.2 SUBMITTALS A. Obtain

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16.

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16. SECTION 01 77 00 - PROJECT CLOSE-OUT PART 1 - GENERAL DESCRIPTION OF REQUIREMENTS: Definitions: Project close-out is the term used to describe certain collective project requirements, indicating completion

More information

PRIVATE PLAN ROOM. Document Information Sheet

PRIVATE PLAN ROOM. Document Information Sheet PRIVATE PLAN ROOM Document Information Sheet Job Name: Partial Renovation for Lewes Streets Department Breakroom Bid Date: October 22, 2018 2:00 pm Placed on file by: George, Miles, and Buhr Contact: Lee

More information

SECTION SUPPLEMENTARY GENERAL CONDITIONS

SECTION SUPPLEMENTARY GENERAL CONDITIONS SECTION 00800 SUPPLEMENTARY GENERAL CONDITIONS PART 1 - GENERAL 1.1 SCOPE OF WORK In general, the Work consists of application of a fluid applied membrane, installation of new tapered insulation, installation

More information

MEB AV TRAINING CENTER PROJECT MANUAL

MEB AV TRAINING CENTER PROJECT MANUAL MEB AV TRAINING CENTER PROJECT MANUAL LSU Health New Orleans MEDICAL EDUCATION BUILDING 1901 PERDIDO ST NEW ORLEANS, LA 70112 November 30, 2018 1 LSU Health New Orleans MEB AV TRAINING CENTER 3 RD FLOOR

More information

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION CITY OF PENSACOLA November 2018 SECTION 011000- SUMMARY OF WORK PART 1 - GENERAL 1.1 DOCUMENTS A. Drawings and general

More information

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION SECTION 024119 SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

ATTACHMENT A. Bid # 6793

ATTACHMENT A. Bid # 6793 ATTACHMENT A SCOPE OF WORK TECHNICAL SPECIFICATIONS AND CONTRACT DRAWINGS STORAGE SHED INSTALLATION AT THE SAN JOAQUIN COUNTY HOUSEHOLD HAZARDOUS WASTE FACILITY Bid # 6793 Department of Public Works Solid

More information

SECTION MAINTENANCE OF EXISTING CONDITIONS

SECTION MAINTENANCE OF EXISTING CONDITIONS SECTION 02 01 00 MAINTENANCE OF EXISTING CONDITIONS PART 1 GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged

More information

SECTION SELECTIVE DEMOLITION

SECTION SELECTIVE DEMOLITION SECTION 024113- PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to the

More information

GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM

GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM 1. GENERAL 1.01 DESCRIPTION GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM A. The Contractor shall furnish all labor, equipment and materials necessary

More information

A. The Contractor shall limit his construction activities, including materials storage, to areas designated by the Owner's Representative.

A. The Contractor shall limit his construction activities, including materials storage, to areas designated by the Owner's Representative. DIVISION 1 - GENERAL REQUIREMENTS CONSTRUCTION AREA A. The Contractor shall limit his construction activities, including materials storage, to areas designated by the Owner's Representative. VEHICLE PARKING

More information

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5 ADDENDUM NO. 1 TO SCOPE OF WORK: Section 0220, Form 01004/5 PROJECT: Tankless Water Heaters Installation Glenn Edge and Rich Martin Apartments and Main Office Water Heater Replacement New Memorial Community

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

Addendum #2 B14/9830. East Campus Student Life/Business Services/DSR Renovation

Addendum #2 B14/9830. East Campus Student Life/Business Services/DSR Renovation September 25, 2013 Addendum #2 B14/9830 East Campus Student Life/Business Services/DSR Renovation SPECIFICATIONS for East Campus Student Life/Business Services/DSR Renovation Dated: September 5, 2013 This

More information

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner.

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner. SECTION 02 41 19 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION BID PROPOSAL FORM. Telephone NO: ( ) Facsimile NO: ( ) Oklahoma License NO:

SECTION BID PROPOSAL FORM. Telephone NO: ( ) Facsimile NO: ( ) Oklahoma License NO: ISSUE DATE: MARCH 21, 2012 (REVISION 2-08/31/12) PROJECT: CNB BUILDINGS 2 AND 3 CATOOSA, OKLAHOMA OWNER: BID TO: (Mail & Fax) CHEROKEE NATION BUSINESSES 777 WEST CHEROKEE STREET CATOOSA, OKLAHOMA 74015

More information

BEAR LAKE MARINA DOCK REPLACMENT DFCM#

BEAR LAKE MARINA DOCK REPLACMENT DFCM# TECHNICAL SPECIFICATIONS BEAR LAKE MARINA DOCK REPLACMENT DFCM#17122510 September, 2016 10/20/2016 Project No. 57-16-030 Civil 1047 South 100 West, Ste. 180, Logan, UT 84321 p 435 713 9514 f 435 713 9503

More information

SECTION 2 DIVISION 01C DESIGN SERVICES PROJECT GUIDELINES (INFORMAL)

SECTION 2 DIVISION 01C DESIGN SERVICES PROJECT GUIDELINES (INFORMAL) SECTION 2 DIVISION 01C DESIGN SERVICES PROJECT GUIDELINES (INFORMAL) PART 1 - PROJECT TITLE PAGE February 8, 2018 Project No. PROJECT NAME PART 2 - PROJECT GUIDELINES 2.1 BIDDERS/CONTRACTORS SHOULD CHECK

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

SECTION UNDERGROUND STORAGE TANK REMOVAL

SECTION UNDERGROUND STORAGE TANK REMOVAL SECTION 02 65 00 UNDERGROUND STORAGE TANK REMOVAL SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit project. 2. Consider including unit prices for additional

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the

More information

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING INDEX OF DRAWINGS SHEET NO. DESCRIPTION 1 TITLE SHEET AND LOCATION PLAN 2 GENERAL NOTES AND SITE ACCESS AND STAGING AREA LAYOUT 3 EXISTING CONDITIONS AND DEMOLITION PLAN 4 CONSTRUCTION PLAN AND PROFILE

More information

TYPICAL APARTMENT FLOOR PLAN

TYPICAL APARTMENT FLOOR PLAN PHOTO #7 PHOTO #8 EAST 8TH STREET (60' WIDE STREET) P L P L PHOTO #4 P L P L A B C D E F G H I #21 ASTOR PLACE 11 STORY BUILDING HEIGHT = 130' (11 STORIES) STAIR #3 BROADWAY (100' WIDE STREET) L STAIR

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

155 North Beech, Casper, WY * (307) * (307) Fax INDEX

155 North Beech, Casper, WY * (307) * (307) Fax INDEX INSTRUCTION TO BIDDERS 155 North Beech, Casper, WY 82602 * (307) 265-0603 * (307) 266-5414 Fax PART 1: INSTRUCTION TO BIDDERS INDEX BIDDING DOCUMENTS. 2 CONTRACTOR APPLICATION FORM.2 EXAMINATION OF CONTRACT

More information

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows: SECTION 16050 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: General requirements for providing basic electrical materials and methods. B. Related Work Specified in Other Sections Includes: 1. Certain

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

B. Sections and all references contained therein form a part of this Section of the Specifications.

B. Sections and all references contained therein form a part of this Section of the Specifications. KARGES-FAULCONBRIDGE, INC. KFI: 14-044.00 SEWARD MONTESSORI SCHOOL ADDITION & REMODELING SECTION 260010 - PART 1 - GENERAL 1.01 SCOPE OF WORK A. Drawings and general provisions of the Contract, including

More information

INVITATION TO BID. Prospective bidders are encouraged to conduct a pre-bid site visit to aid in their bidding assessments.

INVITATION TO BID. Prospective bidders are encouraged to conduct a pre-bid site visit to aid in their bidding assessments. February 12, 2014 INVITATION TO BID The City of Coffeyville, Kansas, is accepting sealed bids for the demolition and removal of certain structures located within the City. The proposed work will be on

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS PART 1 GENERAL 1.1 DESCRIPTION A. Temporary Utilities: Electricity, lighting, heating, cooling, ventilation, water, and sanitary facilities. B. Temporary Controls: Barriers, fencing, erosion control, exterior

More information

City Of Mendota Construction Procedures

City Of Mendota Construction Procedures City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

Appendix 3. POLICY & PROCEDURE No

Appendix 3. POLICY & PROCEDURE No DEPARTMENT OF PUBLIC WORKS DIVISION: ENGINEERING SERVICES SECTION: ADMINISTRATIVE PAGE NO: 1 OF 10 REVISION NO: 3 DATE: 1995 05 01 ESTABLISHED: 1986 03 03 Appendix 3 POLICY & PROCEDURE No. 2.3.1-020 TITLE:

More information

1. Before selective demolition, Owner will remove the following items:

1. Before selective demolition, Owner will remove the following items: SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected

More information

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS GENERAL The commercial bidding process is a well-defined path of positioning oneself to be the successful bidder amongst a group purporting to offer the same quality materials and labor. There are certain

More information

TOWN OF ROTTERDAM BUILDING DEPARTMENT RESIDENTIAL ACCESSORY BUILDINGS AND STRUCTURE PERMIT APPLICATION Ext 395

TOWN OF ROTTERDAM BUILDING DEPARTMENT RESIDENTIAL ACCESSORY BUILDINGS AND STRUCTURE PERMIT APPLICATION Ext 395 TOWN OF ROTTERDAM BUILDING DEPARTMENT RESIDENTIAL ACCESSORY BUILDINGS AND STRUCTURE PERMIT APPLICATION 518-355-7575 Ext 395 Needed to Obtain a Residential Accessory Structure Building Permit: 1. Building

More information

DOCUMENT BID PROPOSAL

DOCUMENT BID PROPOSAL DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of

More information

BID FORMS AND SPECIFICATIONS FOR THE DEMOLITION OF COMMERCIAL STRUCTURES IN THE 1700 BLOCK OF M STREET. CITY OF BELLEVILLE

BID FORMS AND SPECIFICATIONS FOR THE DEMOLITION OF COMMERCIAL STRUCTURES IN THE 1700 BLOCK OF M STREET. CITY OF BELLEVILLE BID FORMS AND SPECIFICATIONS FOR THE DEMOLITION OF COMMERCIAL STRUCTURES IN THE 1700 BLOCK OF M STREET. CITY OF BELLEVILLE BIDS DUE: December 22 nd 2016 @ 2:00 P.M. Belleville City Hall City Hall 1819

More information

SECTION SINGLE-PLY ROOFING SYSTEM

SECTION SINGLE-PLY ROOFING SYSTEM PART 1 - GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish all labor, materials, equipment and incidentals required to provide single-ply adhered roofing system. 1.02 COORDINATION A. The Contractor

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No PART 1 GENERAL 1.1 RELATED DOCUMENTS REQUIREMENTS COMMON TO ALL WORK CATEGORIES 1. Drawings and general provisions of the Contract, including General Special Conditions and other Division 1 Specification

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

More information

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products. SECTION 01400 QUALITY CONTROL SERVICES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification

More information

Chapter 6, Construction

Chapter 6, Construction Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference

More information

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7.1 E-Permit and U-Permit Permit Description and Purpose The Excavation Permit (E-Permit) and the Utility Permit (U-Permit) are issued to allow construction,

More information

Submission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit

Submission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit Building Code The Florida State University Building Code Administration Program (BCA) was established in 2001 and is responsible for ensuring that all construction activities on FSU owned facilities are

More information

WEST THAMES PARK SYNTHETIC TURF LAWN

WEST THAMES PARK SYNTHETIC TURF LAWN BATTERY PARK CITY AUTHORITY WEST THAMES PARK SYNTHETIC TURF LAWN TECHNICAL SPECIFICATIONS AUGUST 18, 2015 OWNER: HUGH L. CAREY BATTERY PARK CITY AUTHORITY ONE WORLD FINANCE CENTER, 24 TH FLOOR NEW YORK,

More information

STORM DRAINAGE - 1 DETAILED SPECIFICATIONS - STORM DRAINAGE

STORM DRAINAGE - 1 DETAILED SPECIFICATIONS - STORM DRAINAGE STORM DRAINAGE - 1 DETAILED SPECIFICATIONS - STORM DRAINAGE 2-7-1 Scope 2-7-2 General 2-7-3 Location and Grade of Sewers 2-7-4 Order of Work 2-7-5 Existing Water, Sanitary Sewer, Gas, and Other Utility

More information

A62 UT PRE-CONSTRUCTION MEETING AGENDA

A62 UT PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

PROJECT MANUAL FOR ORANGE COUNTY CORRECTIONAL COMPLEX PHOENIX BUILDING HVAC REPLACEMENT FOR ORANGE COUNTY GOVERNMENT FACILITIES

PROJECT MANUAL FOR ORANGE COUNTY CORRECTIONAL COMPLEX PHOENIX BUILDING HVAC REPLACEMENT FOR ORANGE COUNTY GOVERNMENT FACILITIES PROJECT MANUAL FOR ORANGE COUNTY CORRECTIONAL COMPLEX PHOENIX BUILDING HVAC REPLACEMENT FOR ORANGE COUNTY GOVERNMENT FACILITIES PREPARED BY: 1059 Maitland Center Commons Boulevard Suite 200 Maitland, Florida

More information

SECTION TEMPORARY SEWER BYPASS PUMPING

SECTION TEMPORARY SEWER BYPASS PUMPING PART 1 GENERAL 1.1 DESCRIPTION A. The CONTRACTOR shall provide a complete sewer bypassing system including, but not limited to, the following: 1. Developing a sewer bypassing plan 2. Developing a spill

More information

1ARCHITECTURE TABLE OF CONTENTS

1ARCHITECTURE TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 0102 COVER 00 0107 SEALS PAGE 00 0111 TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 1000 01 2000 01 2100 01 2300 01

More information

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices. SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section

More information

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages TABLE OF CONTENTS VOLUME 1 DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages SCHEDULE OF DRAWINGS...... 1 PROJECT PERSONNEL & DIRECTORY......

More information

Town of Atkinson, New Hampshire INVITATION TO BID. Town Garage Roof Replacement Issued: June 30, 2015

Town of Atkinson, New Hampshire INVITATION TO BID. Town Garage Roof Replacement Issued: June 30, 2015 Town of Atkinson, New Hampshire INVITATION TO BID Town Garage Roof Replacement Issued: June 30, 2015 The Town of Atkinson invites qualified contractors to bid on the replacement of the roof of the Town

More information

SECTION ALTERATION PROJECT PROCEDURES

SECTION ALTERATION PROJECT PROCEDURES SECTION 013516 ALTERATION PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for protection of existing facilities during construction operations. 2. Demolition and removals

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Site Grading C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Site Grading C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 02210 - Site Grading C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 STRUCTURE PROTECTION... 2 1.03 JOB CONDITIONS... 3 PART 2 - PRODUCTS...

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR PROJECT MANUAL FOR Ogden Regional Medical Center 5475 South 500 East Ogden, UT 84405 for MountainStar Healthcare Construction Documents NJRA Architects, Inc. 5272 South College Dr. Murray, Utah 84123 Telephone:

More information

SECTION TEMPORARY FACILITIES AND CONTROLS

SECTION TEMPORARY FACILITIES AND CONTROLS SECTION 015000 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 GENERAL A. Each Contractor shall be responsible for arranging for and providing construction facilities and temporary controls as required

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) Emergency Removal and Crushing of Rubble and Debris Management PAL 10-92895 Lot # 13: Rubble Removal from Different Locations of Gaza Governorates Bill of Quantity (BOQ) Bill of Quantity (BOQ) PREAMBLE

More information

Copyright 2010 AIA Georgia Institute of Technology Facilities Closeout Procedures. 2/15

Copyright 2010 AIA Georgia Institute of Technology Facilities Closeout Procedures. 2/15 SECTION 017700 - CLOSEOUT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following: 1.

More information

PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR

PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR 99.0 PUBLIC AND PRIVATE IMPROVEMENTS CODE 99.0 PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR TABLE OF CONTENTS 99.1. ADMINISTRATION AND GENERAL REGULATIONS...2 99.1.1. Title...2

More information

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464

More information

TRIAD ENGINEERING CONSULTANTS, INC.

TRIAD ENGINEERING CONSULTANTS, INC. TRIAD ENGINEERING CONSULTANTS, INC. 2638 Willard Dairy Rd Providing High Point, NC Suite 100 Plumbing, Mechanical and 27265 (336) 454-0225 Electrical Engineering Services Since 1984 admin@triadengmep.com

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Lot C Walkway and Bridge Repair Project #23829

Lot C Walkway and Bridge Repair Project #23829 Lot C Walkway and Bridge Repair Project #23829 PREPARED BY: Moody Nolan, Inc. MKEC Engineering Consultants Inc. Division 00 through Division 33 Bid Documents, August 13, 2012 SPECIFICATIONS for Lot C

More information

GENERAL REQUIREMENTS

GENERAL REQUIREMENTS CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 01001-1 PART 1 GENERAL 1.1 Work Covered By Contract Documents.1 Work covers, in general terms: demolition, removals, site preparation and complete construction

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

A62 PRE-CONSTRUCTION MEETING AGENDA

A62 PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

OSNI PONCA OFFICE REMODEL

OSNI PONCA OFFICE REMODEL OSNI PONCA OFFICE REMODEL PROJECT MANUAL OCTOBER 2016 SCHEMMER PROJECT NO. 06571.002 OSNI PONCA OFFICE REMODEL TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000115 LIST OF DRAWING

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

SECTION INTUMESCENT MASTIC FIREPROOFING

SECTION INTUMESCENT MASTIC FIREPROOFING PART 1 GENERAL 1.01 SUMMARY SECTION 07 81 23 - INTUMESCENT MASTIC FIREPROOFING A. Section Includes: 1. Intumescent Mastic Fireproofing for Application to Exposed Steel 2. Protection of Adjacent Surfaces

More information

REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County

REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County Proposals Due: 10:00 A.M., Thursday, March 28, 2019 Address Proposals

More information

REQUEST FOR SEALED BIDS No

REQUEST FOR SEALED BIDS No REQUEST FOR SEALED BIDS No. 2018-013 Project: Granger Site Development Phase 2 Issued: December 19, 2018 CONTENTS Section 1. Bid Announcement and General Information Section 2. Bid Specifications and Bid

More information

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous

More information

The following requirements shall supplement the Standard Specifications:

The following requirements shall supplement the Standard Specifications: Page 1 of 5 DESIGN STANDARDS FOR: GENERAL CONSTRUCTION REQUIREMENTS This design narrative contains general requirements that must be followed by contractors/developers. This section includes a general

More information

SECTION FLUID-APPLIED WATERPROOFING

SECTION FLUID-APPLIED WATERPROOFING SECTION 07140 FLUID-APPLIED WATERPROOFING PART 1 GENERAL 1.1 SUMMARY A. Section includes fluid applied rubberized asphalt and/or elastomeric membrane waterproofing; and surface dusting and/or protective

More information