1 Contractor and A-E Safety Requirements for Overseas Contracts including Guam Roger A. Urbi, P.E., CSP Safety Program Manager NAVFAC Pacific 1 Dec 2010
2 AGENDA Safety Requirements For: A/Es Contractor On-site Personnel Vendors/Visitors Contractor SSHO Contractor Superintendent 2 Designer-Builder Symposium 1 Dec 2010
3 A-E Requirements Must employ a dedicated SSHO. SSHO to have completed the 40-hr Construction Safety Hazard Awareness Course offered by GCA- Hawaii, BIA-Hawaii, ABC-Hawaii and Guam Contractors Association. SSHO also completed other safety training per contract requirements. Prepare and submit site specific APP. Prepare and submit AHA. SSHO must be on site at all times whenever work is performed. 3 Designer-Builder Symposium 1 Dec 2010
4 Contractor On-site Personnel Must have completed the 16-hr EM indoctrination offered by GCA-Hawaii, BIA-Hawaii, ABC-Hawaii and Guam Contractors Association and their authorized representatives prior to starting work. Note: Employees who already completed the 40-hr Construction Safety Hazard Awareness Course for Contractors are exempt. 4 Designer-Builder Symposium 1 Dec 2010
5 Vendors/Visitors Vendors/visitors staying on site longer than 4 hours will need to complete the 16-hr EM indoctrination class offered by GCA-Hawaii, BIA- Hawaii, ABC-Hawaii and Guam Contractors Association and their authorized representatives prior to entry into any NAVFAC jobsite. 5 Designer-Builder Symposium 1 Dec 2010
6 Contractor SSHO Must have completed the OSHA 30 hr Construction Safety Course. Must have completed the 40-hr Construction Safety Hazard Awareness Course offered by GCA-Hawaii, BIA-Hawaii, ABC- Hawaii and Guam Contractors Association and other authorized providers. Must have completed other safety training required in the specifications. Must have a minimum of 5 years construction safety experience. Must be able to prepare and submit a site specific APP. Must be able to prepare and submit AHA. Collect manhours and submit to GDA every month. Conduct a self-assessment of the contractor s safety program every month and attach report with each request for payment. 6 Designer-Builder Symposium 1 Dec 2010
7 Contractor Superintendent May act as an Alternate SSHO. If assigned as an alternate, must have completed the 40-hr Construction Safety Hazard Awareness Course offered by GCA-Hawaii, BIA-Hawaii, ABC- Hawaii and Guam Contractors Association, and other authorized providers. Must also have completed the OSHA 30 hr Construction Safety Course. 7 Designer-Builder Symposium 1 Dec 2010
8 Requirements for all Contractor On-Site Personnel: All contractor workers shall complete a minimum 16 hours of classroom training on the requirements of the latest version of the U.S. Army Corps of Engineers Safety & Health Requirements Manual (EM ) to include but not limited to the following topics: Sanitation; Medical and First Aid Requirements; Temporary Facilities; Personal Protective Equipment; Electrical; Hand and Power Tools; Material Handling and Storage; Motor Vehicles; Fall Protection; Work Platforms and Scaffoldings; Demolition; Safe Access, Ladders, Floor & Wall Openings, Stairs and Railing Systems; Excavations and Trenching; and Confined Spaces, prior to reporting to the jobsite 8 Designer-Builder Symposium 1 Dec 2010
9 Additional Requirements Submit a list of workers who have completed the training to the Contracting Officer prior to them reporting to the jobsite. Update the list as additional workers are added. Maintain the updated list at the jobsite for review by the government designated authority. Vendors and suppliers who will be on the jobsite for more than 4 hours on any given day shall also complete the training prior to reporting to the jobsite. Personnel who have taken the Construction Safety Hazard Awareness Training for Contractors are not required to take the training. 9 Designer-Builder Symposium 1 Dec 2010
10 Authorized Providers The 16 hours classroom training may be provided by the Guam Contractors Association or their authorized representatives, General Contractors Association of Hawaii, Building Industry Association - Hawaii, Associated Builders and Contractors - Hawaii Chapter or other authorized/qualified providers. 10 Designer-Builder Symposium 1 Dec 2010
11 Construction Safety Hazard Awareness Training The training requirements for the Site Safety and Health Officer SSHO) must include the successful completion of the course entitled "Construction Safety Hazard Awareness Training for Contractors". If the SSHO do not have a current certification, they must obtain the course certification within sixty (60) calendar days from award. This course is periodically offered by Guam Contractors Association, General Contractors Association of Hawaii, Building Industry Association - Hawaii, Associated Builders and Contractors- Hawaii Chapter, and other authorized/qualified providers. Upon completion of this course, the Project Superintendent may act on behalf of the SSHO for a period of no more than three (3) days per occurrence, and no more than thirty (30) days total annually. 11 Designer-Builder Symposium 1 Dec 2010
12 Questions?????? 12 Designer-Builder Symposium 1 Dec 2010
Accident Prevention Plans Randy Acosta Safety Officer OICC MCI East Camp Lejeune NC 31 October 2012
NAVFAC MIDLANT Accident Prevention Plans Randy Acosta Safety Officer OICC MCI East Camp Lejeune NC 31 October 2012 Accident Prevention Plans Sometimes the difference in Acceptance and re-submission is
More informationSubcontractor Project Management Plan
Subcontractor Project Management Plan FOR LAYTON PROJECT: COMPANY: CONTACT NAME: ACTIVITY: Signed Date Written by: Reviewed by: Accepted by: Issue Date Description of Revisions Change Introduced by Change
More informationSWT CONSTRUCTION PARTNERING
1 The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated
More information2019 ABC Maine Training Calendar
2019 ABC Maine Training Calendar 8th First Aid/CPR with AED with Kevin Quist Learn Red Cross Adult and Pediatric Member 15 th Accident Investigation/Injury Analysis When work doesn't go as planned, accidents
More informationMANAGING PROJECT SAFETY. Alternatives in a Changing Market
MANAGING PROJECT Alternatives in a Changing Market SHIFTING THE BURDEN Clients reduce their costs by increasing safety requirements of contractors working on their property. Clients shift the burden of
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 20 (February 2010) Changed 1-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02.10 (November 2008) UNIFIED FACILITIES
More informationSCAFFOLDS Revision No: 3
PAGE 1 OF 6 1.0 PURPOSE/ SCOPE To communicate the safety requirements for the erection, inspection and safe use of scaffolds. Compliance with these requirements will assure employee safety while working
More informationSAME Orange County Post Federal Business Opportunities Symposium Amanda Barber, PE CDR, CEC, USN Assistant Operations Officer, NAVFAC SW
NAVFAC Southwest SAME Orange County Post Federal Business Opportunities Symposium Amanda Barber, PE CDR, CEC, USN Assistant Operations Officer, NAVFAC SW 9 November 2016 Safety Summary of Fatal Mishaps
More informationPERFORMANCE WORK STATEMENT FOR AJJY , REMOVAL AND DISPOSAL OF COMPUTERS (HARDWARES) IN B21000, ANDERSEN AIR FORCE BASE, GUAM
PERFORMANCE WORK STATEMENT FOR AJJY 14-1081, REMOVAL AND DISPOSAL OF COMPUTERS (HARDWARES) IN B21000, ANDERSEN AIR FORCE BASE, GUAM 29 August 2014 1 of 6 AJJY 14-1081, REMOVAL AND DISPOSAL OF COMPUTERS
More informationSECTION 1: APPLICANT INFORMATION. 1. Have you contacted your local Chapter regarding their established submission process or procedure?
2018 CONSTRUCTION SAFETY EXCELLENCE AWARDS APPLICATION INSTRUCTION STEPS: 1. DOWNLOAD FORM 2. FILL OUT 3. SUBMIT DEADLINE FEBRUARY 2, 2018 SECTION 1: APPLICANT INFORMATION 1. Have you contacted your local
More informationI. Introduction/Welcome to MAPP
I. Introduction/Welcome to MAPP II. Company Policy HSE POLICY It is the commitment of MAPP to perform ALL work in the safest manner possible, while maintaining the highest level of construction practices.
More informationConstruction Safety Initiative
Construction Safety Initiative Legacy of Success A global construction company with a 90-year history that specializes in developing, managing, and building highly complex projects. dck s Reach Headquartered
More informationACCIDENT PREVENTION PROGRAM HAZARD ANALYSIS SAFETY HEIRARCHY
ACCIDENT PREVENTION PROGRAM HAZARD ANALYSIS SAFETY HEIRARCHY Engineering Controls Work Practices Personal Protective Equipment (PPE) SAFETY HEIRARCHY Engineering Controls Example: Three foot high parapet
More informationSafety & Environmental Orientation Program for Northeast Utilities Contractors. Northeast Utilities Safety 12/10
Safety & Environmental Orientation Program for Northeast Utilities Contractors Northeast Utilities Safety 12/10 How Electric Utilities Work Plan the Work & Work the Plan! Agenda Introduction NU Contractor
More informationConstruction Contract Performance & Documentation Requirements Update
ACTIVITY NAME Construction Contract Performance & Documentation Requirements Update Construction Contract Cost & Schedule Adherence Construction Management System (CMS) efiles Revised Payments for Materials
More informationNAWIC 2017 SAFETY EXCELLENCE AWARDS Page 1
NAWIC 2017 SAFETY EXCELLENCE AWARDS Page 1 INTRODUCTION NAWIC s Safety & Health Awareness Committee is pleased to offer the Safety Excellence Award to recognize NAWIC member companies which recognize safety
More informationSafety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10
Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors Northeast Utilities Safety 12/10 How Electric Utilities Work Plan the Work & Work the Plan! Agenda Introduction
More informationDirectorate of Construction AGA Executive Leadership Safety Summit November 8, 2017
Directorate of Construction AGA Executive Leadership Safety Summit November 8, 2017 Scott C. Ketcham, Deputy Director Directorate of Construction Occupational Safety and Health Administration AGENDA Statistics
More informationField Leadership Safety Conference
Resident Officer In Charge of Construction MCB Camp Pendleton Field Leadership Safety Conference February 22, 2011 Agenda Program Review How are we doing? Andy s Safety Tool Box Recent Incidents/Near Misses
More informationOSHA New Confined Space Rule
OSHA New Confined Space Rule OSHA CLAIMS NEW CONFINED SPACE RULE WILL PREVENT 780 INJURIES A YEAR The Occupational Safety and Health Administration issued a final rule to increase protections for construction
More informationSafely Operating Forklift in the Workplace... P. 8
March : Safe Use of Portable Circular Saws... P. 2-3 Safe Use of Pneumatic Nailing & Stapling Equipment... P. 4-5 Power Hand Drill Safety... P. 6-7 Benefits of Good Housekeeping Safety Article March 2016
More informationSavard Labor & Marine Staffing, Inc. Fall Prevention Program Rev3/14
Fall Prevention Program Purpose Slips, trips, and falls constitute a significant amount of accidents. They cause 15% of all accidental deaths, and are second only to motor vehicles as a cause of fatalities.
More informationCherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12
SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and
More informationAN OVERVIEW OF THE NEW MIOSHA WALKING-WORKING SURFACES STANDARD
AN OVERVIEW OF THE NEW MIOSHA WALKING-WORKING SURFACES STANDARD Michigan Safety Conference April 2018 LJB Booth 612 CRAIG GALECKA, P.E., C.S.P. PRINCIPAL, LJB INC. (517) 285-3663; CGALECKA@LJBINC.COM FOR
More informationSECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1
SECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1 It is our company s policy to perform its work in the safest manner possible, consistent with safe work practices, and according to all governing laws
More informationsupplier & Associate Entry Form 2013 ABC National DIVER SITY Excellence Awards
2013 ABC National DIVER SITY Purpose The ABC National Diversity recognize members that display exemplary diversity leadership in their company, workforce, supply chain and community with best-in-class
More informationThomas Connors Executive Director, Construction Site Safety
Thomas Connors Executive Director, Construction Site Safety Agenda Site Safety Plans Site Safety Requirements BEST Squad Inspections 2 Site Safety Plans 4 Site Safety Logistics Plan Material/ Personal
More informationROICC MCB Quantico Fatality at P-547, Camp Barrett occurring 8 Aug 2011
NAVFAC WASHINGTON ROICC MCB Quantico Fatality at P-547, Camp Barrett occurring 8 Aug 2011 Prepared by LCDR Julie Hrdlicka Agenda BLUF Project Background Incident Summary Direct Causes Contributing Causes
More informationConstruction, Safety, Quality Control Standards
Construction, Safety, Quality Control Standards Philip Stavrides Chief of Construction US Army Corps of Engineers Chicago District February 21, 2017 The views, opinions and findings contained in this report
More informationProperty and Public Protection Plan
Property and Public Protection Plan OTTO CONSTRUCTION PROPERTY AND PUBLIC PROTECTION PLAN Otto Construction s pre-planning of construction activities includes procedures to protect the general public and
More informationSafety & Environmental Orientation Program for Contractors
Transmission Group Safety & Environmental Orientation Program for Contractors Applies To Eversource Connecticut, Western Massachusetts, and New Hampshire 1 Agenda Introduction ES Contractor Work Rules
More informationConsultation on Proposed Miscellaneous Amendments to the Construction Projects Regulation (O. Reg. 213/91)
Consultation on Proposed Miscellaneous Amendments to the Construction Projects Regulation (O. Reg. 213/91) Summary of Proposal The Ministry of Labour (MOL) is proposing to make miscellaneous amendments
More informationAugust 28, 2018 QLN Conference Center North County 1
August 28, 2018 QLN Conference Center North County 1 2 3 4 5 6 7 8 9 10 Required Submissions CONTRACTOR PRE-CONSTRUCTION ORIENTATION J.6 Each contractor shall submit at the Pre-Construction meeting the
More informationScope of Work Bid Package C-4 - West Polished Concrete
Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationCOMMITMENT. U.S. ARMY CORP OF ENGINEERS Richardson Pool Schofield Barracks Renovation
COMMITMENT U.S. ARMY CORP OF ENGINEERS Richardson Pool Schofield Barracks Renovation O U R U N C O M P R O M I S I N G V A L U E S For more than two decades, Alan Shintani, Inc. has earned a solid reputation
More information2018 ConocoPhillips Alaska Excellence in Safety Awards
Introduction These awards are to promote and recognize excellence in safety throughout the construction industry in Alaska. Applications are reviewed by an independent panel of safety professionals with
More informationGUELPH WATER RECLAMATION HEALTH, SAFETY AND SECTION GUELPH, ON. EMERGENCY PROCEDURES PAGE 1 PROJECT NO
GUELPH, ON. EMERGENCY PROCEDURES PAGE 1 DIVISION 01 - GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS.1 The Instructions to Bidders, the General Conditions of CCDC 2-1994, Supplementary
More informationFrederic Lecat, ICAO Regional Officer APAC Regional Office January 2016
4 Instructions To Tenderers (ITT) Frederic Lecat, ICAO Regional Officer APAC Regional Office January 2016 Outline Content of ITT Procurement schedule Evaluation CONTENT OF ITT Overview of the tender package
More informationWHITMAN COLLEGE TRENCHING AND SHORING PLAN
Purpose: WHITMAN COLLEGE TRENCHING AND SHORING PLAN This is a statement of official college policy to establish the process for compliance with safety standards as stated in the Washington State Administrative
More informationSection: TABLE OF CONTENTS Temporary Facilities. 04.A General B Access and Haul Roads
Section 4 TABLE OF CONTENTS Temporary Facilities Section: Page 04.A General... 4-1 04.B Access and Haul Roads... 4-3 4-i SECTION 4 Temporary Facilities 04.A General. 04.A.01 Plans for the layout of temporary
More informationAre designed to provide a safe working environment, and Govern use of fall protection procedures and equipment.
Fall Protection Plan for Construction OSHA currently regulates fall protection for construction under Part 1926, Subpart M. The standards for regulating fall protection systems and procedures are intended
More informationSECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 GENERAL 1.01 SECTION INCLUDES A. Preliminary schedule. SECTION 01 32 00 SECTION 01 32 00 B. Construction progress schedule, with network analysis diagrams and reports. C. Daily construction reports.
More informationWritten Safety and Health Program
Written Safety and Health Program For XYZ Company Required for all Hawaii Businesses with 25 or More Employees Incorporates Provisions of Hawaii Administrative Rules Title 12, Subtitle 8, Part 2, Chapter
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS. References are in agreement with UMRL dated April 2018
USACE / NAVFAC / AFCEC / NASA UFGS-01 20 00.00 20 (November 2011) Change 1-05/16 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 20 00.00 20 (August 2011) UNIFIED FACILITIES
More informationDIVISION 1- GENERAL REQUIREMENTS
DIVISION 1- GENERAL REQUIREMENTS This division contains the following elements: 1.1 General 1.2 Summary of Work 1.3 Administration 1.4 Quality 1.5 Temporary Facilities 1.6 Products 1.7 Execution 1.8 Closeout
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS. References are in agreement with UMRL dated October 2012
USACE / NAVFAC / AFCESA / NASA UFGS-01 20 00.00 20 (November 2011) ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 20 00.00 20 (August 2011) UNIFIED FACILITIES GUIDE
More informationHow Basic Orientation Plus 2010 revision works with a company s safety program to meet OSHA requirements:
Hazard Communication (HAZCOM) 1910-1200 The program follows the 1910.1200. This training is designed to provide an understanding of the Hazard Communication Standard (HAZCOM) and meets the general awareness
More informationBABIES "R" US- TOYS R US
BABIES "R" US- TOYS R US PENSACOLA, FL PRE-BID CONFERENCE CALL NOTES ISSUED AS ADDENDUM #02 INFO: Call in #- 1-877-549-1308 Code- 296-130-0550 Leader code - 3107 DATE: Tuesday, October 2, 2012 TIME: 2:00
More informationIron Ore Company of Canada Health, Safety & Environment
Barricading 1 PURPOSE To protect personnel by preventing or controlling access to hazards in work areas by the installation and maintenance of barricades, demarcation and restricting access. This work
More informationGUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM
GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM NAHB Builder s Show Orlando, Florida February 2008 Leon Rogers President Construction Management Associates, LLC PO Box 867 Thayne, WY 83127 (801) 310-0035
More information*************************************************************************** SECTION F20 SELECTIVE BUILDING DEMOLITION 09/16
NAVFAC PTS-F20 (September 2016) ------------------------------ Preparing Activity: NAVFAC SUPERSEDING PTS-F20 (September 2015) PERFORMANCE TECHNICAL SPECIFICATION SECTION F20 SELECTIVE BUILDING DEMOLITION
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height
More informationLockheed Martin Space (LMS)
Lockheed Martin Space (LMS) Contractor Environment, Safety & Health (ESH) Site Briefing Valley Forge site, King of Prussia, PA The purpose of the Contractor ESH briefing is for LM Space to provide site
More informationU.S. Army Corps of Engineers HONOLULU DISTRICT
REQUEST FOR PROPOSAL NO. MATOC 8(A)-20 Wheeler Army Air Field, Oahu, Hawaii SPECIFICATIONS FOR Recovery 38424 Repair Ammunition Supply Point road Due to Storm Damage, WAAF, HI U.S. Army Corps of Engineers
More informationMidpeninsula Regional Open Space District
Midpeninsula Regional Open Space District PLANNER I-II DEFINITION Under direct supervision, performs various professional field and office planning work related to open space, natural resource, land acquisition
More informationSTATEMENT OF BIDDER S QUALIFICATIONS
STATEMENT OF BIDDER S QUALIFICATIONS Eastside Trail Extension This Statement is to accompany bids submitted for the project identified above. Bidders must meet the minimum qualification criteria set forth
More informationSECTION PAYMENT PROCEDURES
SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply
More informationCONTRACTOR SAFETY PRE-QUALIFICATION CHECKLIST. Name of Contractor: Date: Business Address: Telephone No.:( ) Fax No.:( )
CONTRACTOR SAFETY PRE-QUALIFICATION CHECKLIST 1. CONTRACTOR INFORMATION of Contractor: Date: _ Business Address: _ Telephone No.:( ) Fax No.:( )_ Contact Person: Company SIC Code: Years in Business: Date
More informationThe Construction Industry
The Construction Industry 90% of Construction Employers have 20 or less employees. The industry typically has very high turnover rates. Most are multi-employer worksites. Over half of OSHA compliance inspections
More informationTHE CITY OF EDMONTON PROJECT AGREEMENT VALLEY LINE LRT STAGE 1. Schedule 11. Project Safety Requirements
THE CITY OF EDMONTON PROJECT AGREEMENT VALLEY LINE LRT STAGE 1 Schedule 11 Project Safety Requirements VAN01: 3666008: v7 SCHEDULE 11 PROJECT SAFETY REQUIREMENTS TABLE OF CONTENTS 1. SAFETY... 1 1.1 Safety
More informationOSH LEGISLATION LAW AND REGULATION TO CONSTRUCTION SAFETY LAW AND REGULATION TO CONSTRUCTION SAFETY 20/2/2013
LAW AND REGULATION TO CONSTRUCTION SAFETY Sr Dr. Mohd Saidin Misnan UNIVERSITI TEKNOLOGI MALAYSIA 81310 UTM Skudai, Johor, Malaysia LAW AND REGULATION TO CONSTRUCTION SAFETY OSH LEGISLATION 1 To enable
More informationThe following is Copyright 2009 The Queen s Printer, Saskatchewan
Saskatchewan Elevated Work Platform This material has been extracted from the Regulations and Acts of the Province as an aid to help students better understand the subject. This is not an official source
More informationTHE PEOPLE'S REPUBLIC OF CHINA
ASEAN-CHINA AGREEMENT ON TRADE IN SERVICES ANNEX 1/SC1 THE PEOPLE'S REPUBLIC OF CHINA Schedule of Specific Commitments (For the First Package of Commitments) 1 THE PEOPLE'S REPUBLIC OF CHINA - SCHEDULE
More informationCHAPTER 10: FALL PROTECTION
CHAPTER 10: FALL PROTECTION PURPOSE The fall protection program provides information and procedures to minimize the occurrence of an accidental fall or falling object, resulting in injuries on a job site.
More informationSAMPLE APPLICATION 2018 CONSTRUCTION SAFETY EXCELLENCE AWARDS (CSEA) APPLICATION
SAMPLE APPLICATION 2018 CONSTRUCTION SAFETY EXCELLENCE AWARDS (CSEA) APPLICATION GETTING STARTED 1. Applicants must first contact their local AGC chapter to determine if they have an established process
More informationSection 9 Brieser Construction SH&E Manual
Brieser Construction SH&E Manual October 16 2017 The purpose of this plan is to establish a program and procedures for the evaluation of self, peers and overall jobsite safety behaviors, unsafe acts and
More informationMIRACOSTA COLLEGE. [X] MiraCosta College Bid Opportunities Website /FAX
MIRACOSTA COLLEGE BID ADDENDUM MiraCosta Community College District Distribution: One Barnard Drive [X] Owner [X] Architect Oceanside, California 92056 [X] MiraCosta College Bid Opportunities Website 760.795.6691/FAX
More informationB ADDENDUM # 1
B0001582 ADDENDUM # 1 FROM: Kim Sowell Campus Box 12 Ph: 316-978-3784 Fax: 316-978-3528 TO: All Bidders DATE: 2/11/2019 CLOSING DATE AND TIME: 2/21/2019 @ 2:00 PM SUBJECT: B0001582 Addendum Construction
More information2018 NJ CEL Course Catalog 1
2018 NJ CEL Course Catalog 1 Accident Investigation 2 hours This course leads the student through the three step process of 1) collecting good information of the incident, 2) identifying the root cause
More informationREQUEST FOR BIDS CULVERT REPLACEMENT PROJECT FREEPORT, MAINE
REQUEST FOR BIDS 1. RECEIPT OF BIDS The Town of Freeport will receive sealed Bids, clearly marked and addressed to: Bid for Culvert Replacement Project 2015-1, Freeport Town Engineer, Town Hall, 30 Main
More informationNational Safety Council Construction and Utilities Division May 21, 2018
National Safety Council Construction and Utilities Division May 21, 2018 Dean McKenzie, Director Directorate of Construction Occupational Safety and Health Administration Agenda Statistics Regulatory Trenching
More informationILLINOIS INSTITUTE OF TECHNOLOGY SAFETY POLICY COMMITTEE. Contractor Safety
ILLINOIS INSTITUTE OF TECHNOLOGY SAFETY POLICY COMMITTEE Contractor Safety Approved: October 10, 2005 Reviewed and Modified: October 17, 2016 1 TABLE OF CONTENTS Section Page 1. Purpose...1 2. Scope...
More informationUNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No
PART 1 GENERAL 1.1 RELATED DOCUMENTS REQUIREMENTS COMMON TO ALL WORK CATEGORIES 1. Drawings and general provisions of the Contract, including General Special Conditions and other Division 1 Specification
More informationA REAL-WORLD VIEW: IMPLEMENTING NEW OSHA FALL PROTECTION REGULATIONS
A REAL-WORLD VIEW: IMPLEMENTING NEW OSHA FALL PROTECTION REGULATIONS Indiana Safety Conference March 2018 TRACEY RIEPENHOFF, P.E., C.S.P. LJB INC. (419) 236-7050; TRIEPENHOFF@LJBINC.COM AGENDA Background/context
More information*************************************************************************** SECTION F20 SELECTIVE BUILDING DEMOLITION 02/18
NAVFAC PTS-F20 (February 2018) ------------------------------ Preparing Activity: NAVFAC SUPERSEDING PTS-F20 (September 2016) PERFORMANCE TECHNICAL SPECIFICATION SECTION F20 SELECTIVE BUILDING DEMOLITION
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS. References are in agreement with UMRL dated January 2017
USACE / NAVFAC / AFCEC / NASA UFGS-01 20 00.05 20 (January 2012) Change 1-09/15 Change 2-03/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 20 00.05 20 (February 2011)
More informationROLES AND RESPONSIBILITIES
ROLES AND RESPONSIBILITIES Role of Contractor Investor Companies who choose to support CMEF in the following ways are considered COIPA 3 Contractor Investors (COIPA 3 CI): 1. Within the guidelines stated
More informationFALL HAZARD CONTROL PROCESS
Sugrema Consultancy N.V. FALL HAZARD CONTROL PROCESS 02 April 2014 1 Sugrema Consultancy N.V. 2 FALL HAZARD CONTROL PROCESS Start Fall control Program Improvement cycle Audit Fall control Program Training
More informationGENERAL CONTRACTOR (OVER $33 MILLION) ENTRY FORM ABC National DIVERSITY. Excellence Awards
GENERAL CONTRACTOR (OVER $33 MILLION) ENTRY FORM ABC National DIVERSITY GENERAL CONTRACTOR (OVER $33 MILLION) ENTRY FORM Purpose The ABC National Diversity recognize members that display exemplary diversity
More informationEXECUTIVE DIRECTOR - FACILITIES DEVELOPMENT AND PLANNING
PERSONNEL COMMISSION Class Code: 5084 Salary Range: 60 (M2) EXECUTIVE DIRECTOR - FACILITIES DEVELOPMENT AND PLANNING JOB SUMMARY Under the direction of the Chief Business and Financial Officer, plan, implement
More informationRob LaFon, CAWV Safety Committee Chairman CAWV Safety Awards Program
January 23, 2018 To: From: Re: Safety Director or Person in Charge of Submitting Safety Awards Rob LaFon, CAWV Safety Committee Chairman 2017 CAWV Safety Awards Program The Safety Committee, on behalf
More informationChapter WAC Construction Work
Chapter 296-155 WAC - Page 296-155-475 Scope and application. 1 296-155-47501 Definitions applicable to this part. 1 296-155-476 General requirements. 2 296-155-477. 2, Page i PART J STAIRWAYS WAC 296-155-475
More informationAlameda County Waste Management Authority Model Specification Update March 2004 SECTION CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
SECTION 01505 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT 1.01 SUMMARY A. Section specifies diversion of construction and demolition (non-hazardous) debris from landfill. B. Related requirements specified
More informationSpecifications. Level 1 Essential Energy Works for the Warialda Truck Wash
Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification
More informationEM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities
EM385 Construction Safety and Health Certification Course Section 4 Temporary Facilities OSHAcademy Course 500 Study Guide EM 385 SAFETY AND HEALTH CERTIFICATION COURSE SECTION 4 Edited by: Steven Geigle,
More information2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS
2014 SAFETY ECELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below
More informationINSTRUCTIONS FOR COMPLETING SCHEDULE OF PRICES, ESTIMATE FOR VOUCHER, RETENTIONS SUMMARY, AND CONTRACTOR'S INVOICE
INSTRUCTIONS FOR COMPLETING SCHEDULE OF PRICES, ESTIMATE FOR VOUCHER, RETENTIONS SUMMARY, AND CONTRACTOR'S INVOICE 1. Print out these instructions first, then follow them in completing the worksheets.
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.15 10 (November 2016) Change 1-08/17 ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 00.10 10 (February 2010) UNIFIED FACILITIES
More informationCONTRACTORS ASSOCIATION OF WEST VIRGINIA. Working Hard Working Safe Safety Awards
Contractors Association of West Virginia 2114 Kanawha Boulevard East Charleston, West Virginia 25311 CONTRACTORS ASSOCIATION OF WEST VIRGINIA Working Hard Working Safe 2016 Safety Awards Award Packages
More informationNOTICE OF PROPOSED CLASSIFICATION ACTIONS BY THE HUMAN RESOURCES DIRECTOR
NOTICE OF PROPOSED CLASSIFICATION ACTIONS BY THE HUMAN RESOURCES DIRECTOR The following actions are being posted in accordance with Civil Service Rule 109. In the absence of a protest addressed to the
More informationConstruction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT
Construction Safety Education Forum 6 March 2013 Scaffolding Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT SRWSD in confidence 1 Presentation Outline Introduction
More informationSAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub
SAMPLE WORK PLAN You have just been awarded a $500,000 construction contract as a prime bidder. You will perform 60% of the work in-house (including your suppliers) and 40% will be performed by 3 different
More informationPIN s genericone time use access to the registration system online. PIN s are not tied to
1 2 PIN s genericone time use access to the registration system online. PIN s are not tied to a user in any way. It is given to them so that they can gain access to register as a user into the SCOT course.
More informationJOB POSTING Traverse City Light & Power
JOB POSTING Traverse City Light & Power Announcement No. 18-003LP March 6, 2018 JOURNEYMAN ELECTRIC LINE WORKER Traverse City Light & Power (TCL&P), a municipally owned electric utility in Traverse City,
More informationDATE ISSUED: 7/17/ of 11 UPDATE 111 CS(LEGAL)-P
Facilities Standards State Standards After January 1, 2004 Definitions All new facilities must meet the commissioner s standards for adequacy of school facilities to be eligible to be financed with state
More informationHUMAN RESOURCES ANNUAL REPORT 2017
HUMAN RESOURCES ANNUAL REPORT 2017 Human Resources Mission: To develop, establish and maintain policies and programs that ensure the successful recruitment, employment and retention of a diverse, high
More informationSummary of Changes to Occupational Health and Safety Regulations
Summary of Changes to Occupational Health and Safety Regulations (Effective June 12, 2013) The following is a summary of recent amendments to the Occupational Safety General Regulations and the newly enacted
More informationCONSTRUCTION WASTE MANAGEMENT PLAN
CONSTRUCTION WASTE MANAGEMENT PLAN The 2016 California Green Building Standards Code (Cal Green Code) is effective January 1, 2017. The Cal Green Code, Section 4.408 (Residential) and Section 5.408 (Nonresidential)
More informationReferences. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A
References EM385-1-1, Sections 22 OSHA 29CFR 1926.450 (Subpart L ) UFGS-01 35 29[Latest] ANSI A10.8-1988 What Is A Scaffold? An elevated, temporary work platform Three basic types: Supported scaffolds
More informationMassachusetts FACE Occupational Fatality Report
Massachusetts FACE Occupational Fatality Report Massachusetts Department of Public Health Occupational Health Surveillance Program Fatality Assessment and Control Evaluation Project Municipal Lead Custodian
More information