Oasis Midstream Services

Size: px
Start display at page:

Download "Oasis Midstream Services"

Transcription

1 Oasis Midstream Services Midstream Business Unit Guidelines Version 1.1 1

2 2

3 Table of Contents Section 1 - Introduction Section 2 - Environmental Health & Safety Section 3 - Program Administration Section 4 - Construction Guidelines Section 5 - General Equipment & Mechanical Guidelines

4 1.0 Introduction Oasis Midstream Services values the safety of all workers and the protection of the environment. We are committed to the quality of our work, as well as maintaining an incident free workplace. This goal can only be attained working as a team with our contractors. The following terms are used in this handbook to describe the contractor company and personnel mentioned in the guidelines: Guidebook and Handbook Terms Contractor - A contractor is defined for the purposes of this document as any company or individual whom by contract, subcontract, or purchase order performs work or provides services or equipment to or for Oasis Midstream Services. Contractor Supervisor - This individual represents the contractor company that supervises the work of a contractor or contractors. Oasis Representative - An individual authorized to oversee, manage, or direct work on behalf of Oasis Petroleum. 4 Introduction

5 Section 1 This handbook provides guidance and a minimum set of expectations for Oasis Midstream Services (OMS) employees and contractors regarding contractor work performed for OMS. As the contractor, you are required to follow the policies and procedures established by the contractor s company in addition to any of Oasis site-specific policies. This handbook is intended to supplement, not replace, the contractor s company safety program, which the contractor is required to implement. In the event of a conflict between this handbook and the contractor s company safety program, the more stringent rule shall apply. The contractor company s contract with OMS may be canceled, or an individual may be asked to leave OMS owned property if the contents of this guideline are not followed. 1.1 Excellence through Teamwork Environmental, health, safety, and production goals cannot be reached by operational groups operating independently. This is true for OMS as well as our contractors. While performing work for OMS, contractors will be exposed to hazards as well as operational challenges and will be expected to recognize, manage, and effectively solve and mitigate these obstacles. This is critical for our business to succeed. 1.3 How to Use the Contractor Handbook All of Oasis s contractors should have a copy of this handbook accessible to them. The contents of this handbook should be reviewed, discussed, and understood by contract personnel before any work is performed for Oasis. If an HSE issue arises that is not addressed in the handbook or by the contractor s own safety program, you must ask for guidance from the contractor representative or an Oasis representative. 1.4 How to Use the Inspector Handbook Inspectors and supervisors provide services that require additional information necessary for the quality assurance and control of various projects. Operational Specifications, map information, and other historical project scopes will be accessible to Oasis employee or contractor inspectors. 1.2 How to Use this Guidebook The intent of this handbook is to provide guidance to our contractors and employees regarding Oasis s expectations of its contractor workforce. Included is mapping information, operational specifications, DOT and other federal regulations, manufacturer requirements and other documents. Version 1.1 5

6 Table of Contents Introduction 1. Purpose and Scope 2. Stop Work Authority Oasis Commitment 1. Commitment to People 2. Commitment to Safety 3. Commitment to the Environment 4. Regulatory Compliance Responsibilities 1. OMS Manager Responsibility 2. OMS Employee Responsibility 3. OMS Contractor Responsibility 4. OMS Inspector Responsibility 5. Service Providers Environmental Health and Safety (EHS) Policy Expectations for Individuals Expectation of Contractors 1. Contractor s Commitment 2. General Health, Safety and Welfare 2.1 Contractor Personnel Fitness/Personal Hygiene 2.2 EHS Orientation 2.3 Incident Reporting and Investigation 2.4 Reporting Hazards, Unsafe Conditions, & Near Misses 2.5 Behavior-Based Safety Observation Programs 2.6 Substance Abuse, Dangerous Materials and Firearms 2.7 Horseplay 2.8 Housekeeping 2.9 Clothing and Other Apparel 2.10 Compressed Gas Cylinders and Compressed Air 2.11 Storage, Use and Labeling of Chemicals, Solvents and Paint 2.12 Personal Protective Equipment 2.13 Overhead Work 2.14 Scaffolds or Platforms 2.15 Fall Protection Equipment 2.16 Non-Destructive Testing (NDT) 2.17 Safe Work Systems (SWS) 2.18 Hydrogen Sulfide 2.19 Fire Protection 2.20 Safety Equipment Environmental Health & Safety

7 Section Safety Training 2.22 EHS Meetings 2.23 English Language Proficiency 2.24 DOT Safety 2.25 Minimum Certifications and Licenses 2.26 Electrical Safety 2.27 Emergencies 3. Environmental Management 3.1 Environmental Housekeeping 3.2 Reporting 3.3 Diligence 3.4 Waste Management Waste Management Plan 3.5 Tanks and Vessels 3.6 Waste Water 3.7 Wildlife Management 17 Version 1.1 7

8 Environmental Health & Safety Introduction 1. Purpose and Scope This manual was created to be a guidance document for all OMS employees, contractors, and consultants regarding best practices within Oasis Midstream Services. Our service providers are chosen based on professional integrity and are expected to perform the job correctly/ safely on all Oasis projects and location regardless of adverse circumstances, or perceived time constraints. It should be noted that these are MINIMUM expectations. Any changes to the processes outlined in this document require MOC (Management of Change) / Oasis Representative approval. 2. Stop Work Authority All contractors are authorized as well as required to stop any work that is perceived as a risk to any persons safety or a risk to the environment. No repercussions will result from any worker or contractor exercising Stop Work Authority. If a contractor or contractor s employee feel they are being discouraged from or penalized for using Stop Work Authority they must report it immediately to an Oasis Petroleum representative. Oasis Commitment 1. Commitment to People Oasis is not satisfied unless everyone goes home in the same condition they arrived. 2. Commitment to Safety Anyone; employee or contractor, can call a safety time-out or use Stop Work Authority to halt an unsafe condition or behavior. 3. Commitment to the Environment Oasis is committed to the preservation of the environment. Any incident that threatens the environment must be reported immediately and appropriate steps taken to mitigate and fix or clean up the issue. 4. Regulatory Compliance Oasis is committed to maintaining regulatory compliance on the county, state and federal level. Responsibilities 1. OMS Manager Responsibility Managers are expected to demonstrate positive HSE behaviors at all times Managers will engage in proactive leadership and two-way communication with all workers, contractors and consultants Be aware of requirements presented in the handbook 8 Oasis is committed to the safety and health of all employees and contractors as well as the communities and environment in which Oasis operates. Environmental Health & Safety Ensure that all contractors performing work for Oasis Petroleum are meeting expectations in accordance with the requirements presented in the handbook

9 Section 2 2. OMS Employee Responsibility Be aware of the contractor handbook and its requirements Ensure that contractors are aware of the requirements and expectations of them and have a copy of the handbook Ensure that all contractors working for Oasis Petroleum are meeting the expectations put forth by the handbook 3. OMS Contractor Responsibility Contractor companies are responsible for the contractors employees safety and health and ensuring that all contractors perform their work safe and acceptable manner Contractor must become familiar with Oasis Petroleum s requirements and 4. OMS Inspector Responsibility Inspectors are responsible to know, follow, and oversee contractor use and application of the guidelines in this handbook. Are accountable for technical quality assurance Responsible to ensure all forms are filled out and completed prior to start, during work, and after project is completed 5. Service Providers It is OMS expectation that service providers will ensure work is performed in accordance within the framework of OMS expectations, contractor requirements, as well as any and all county, state and federal regulations Inspectors are responsible to know, follow, and oversee contractor use and application of the guidelines in this handbook. expectations, many of which are outlined in this handbook. These guidelines are a supplement to, not a replacement of the contractors own safety program. In the case where the contractors procedures and Oasis Petroleum procedures conflict, the more stringent rule should be followed Contractors must be aware of Oasis Petroleum s contractor handbook and it s requirements Environmental Health and Safety (EHS) Policy This document is a summary of the EHS requirements and working procedures that are the minimum standards and practices to which all contractor personnel must adhere while working for Oasis Petroleum North America LLC, or Oasis Midstream Services (OMS) (collectively, Company ). These are Company minimum requirements, and are in addition to, and intended to Version 1.1 9

10 supplement, all other applicable laws, rules and regulations. Contractor must develop its own EHS program, policies and procedures and through its program, policies and procedures demonstrate compliance with all federal, state, county and municipal laws, rules and regulations applicable to Contractor s work and Contractor s services, items, materials, equipment, or personnel to be used in performing such work, including, but not limited to, the following (as may be supplemented and amended from time to time): the Occupational Safety and Health Act, the Clean Air Act, the Comprehensive Environmental Response, Compensation and Liability Act, the Federal Water Pollution Control Act, the Solid Waste Disposal Act, the Resources Conservation and Recovery Act, the Safe Drinking Water Act, the Toxic Substances Control Act, the Hazardous Materials Transportation Act, the Federal Oil Pollution Act of 1990 and comparable state and local statutes and implementing rules or regulations. Expectations for Individuals It is the minimum responsibility of every individual working at a Company location to comply with the requirements set out in this document. It is not within the scope of this document to detail all government regulations or Company EHS procedures, but rather to provide an overview of Company requirements. If any questions or concerns arise about safe work practices, consult your supervisor and/or a Company supervisor for the facility where you are working. Expectation of Contractors Contractor shall be responsible for compliance with the enclosed requirements, other Company requirements, which may be subsequently issued, and all government regulations applicable to Contractor s employees and subcontractors. 1. Contractor s Commitment Contractor shall demonstrate a strong commitment to EHS matters and must have established EHS-related policies and procedures. Contractor shall be responsible for complying with its policies and procedures related to EHS matters. Contractor shall be responsible for all aspects of Contractor s EHS performance, and for ensuring that Contractor has a supervisory person at the worksite at all times who is competent and has the authority to implement the Contractor s EHS system properly and meet Company s EHS requirements. To assist Company in evaluating Contractor s EHS program contents and implementation, Contractor shall maintain a current Standardized Safety Questionnaire (SSQ) through PEC Premier ( Although participation in other PEC Premier programs is voluntary at this time, contractors who participate will be given priority for assignment of work. 2. General Health, Safety and Welfare Contractor is responsible for maintaining all facilities and associated services under Contractor s direction or responsibility in a manner which does not create or otherwise contribute to an unhealthy working or living environment. In order to accomplish this objective, Contractor shall ensure the following: 10 Environmental Health & Safety

11 Section Contractor Personnel Fitness/ Personal Hygiene Contractor and any of its subcontractors acknowledge that the work to be performed for Company by Contractor and subcontractor employees can require extensive physical demands. Contractor and all subcontractors shall ensure that all personnel assigned to any Company location can safely perform the essential functions of his/her job assignment with or without reasonable accommodation by Company. Contractor shall ensure that Contractor s personnel maintain appropriate standards of personal hygiene in connection with the performance of the work on Company s behalf. 2.2 EHS Orientation An employee EHS orientation program shall be implemented by Contractor, and shall be given to all of Contractor s and all subcontractors personnel, regardless of prior experience. This EHS orientation shall address Contractor s mandatory EHS procedures, rules, and regulations. Each employee of Contractor and any of its subcontractors must receive the EHS orientation before being allowed on any of Company s work sites. 2.3 Incident Reporting and Investigation Contractor is required to immediately notify OWS of all safety-related incidents (e.g., any work-related injury, illness, fatality or other EHS-related recordable incidents) involving Contractor or any subcontractor personnel. In addition, a written report of such incident must be prepared by Contractor and delivered to Company within twenty-four (24) hours of each such incident. Contractor shall promptly investigate all such incidents, conduct a Root Cause Analysis, and provide final incident investigation reports (including recommendations and corrective action plans identified during investigations) to Company within thirty (30) days of the incident. The Contractor shall agree that designated Company personnel may participate in any Contractor investigation of such incidents. Contractor shall provide Company with copies of all incident reports that result in formal notification to any Government agency. Contractor will be required to provide a monthly safety performance report undertaken as part of, any work performed by Contractor, or the obligations of Contractor under any Master Service Agreement (MSA). The monthly cut off for each report shall be close of business up to and including the final day of each month. Contractor s safety performance report shall be based on the following formula for determining recordable incident frequency rate: (Total Number of Fatalities, Lost Time Incidents & Medical Treatments X 200,000) Total Number of Man-hours on Company s Work Sites This information will be reported monthly through Contractor s PEC Premier account (SSQ) and will be completed no later than the 3rd business day of the month following the reporting month. 2.4 Reporting Hazards, Unsafe Conditions, & Near Misses Unsafe conditions shall be immediately reported to Company. Near Miss Version

12 incidents that could have resulted in injury or damage shall be reported immediately to Company in order to ensure corrective action is taken. At Company s discretion, a Root Cause Analysis may be requested to fully determine causes and appropriate corrective actions to address Near Miss incidents. 2.5 Behavior-Based Safety Observation Programs Behavior-Based Safety Observation Programs are recognized as an effective tool in the development and growth of a proactive safety culture. Contractors are encouraged, but not required, to implement a Behavior- Based Safety Observation Program. When such programs are implemented by Contractor, quarterly reports shall be shared with Company where those programs are used by Contractor crews working on behalf of Company. 2.6 Substance Abuse, Dangerous Materials and Firearms 2.7 Horseplay Horseplay, such as wrestling and practical jokes, etc., can be dangerous and is prohibited at Company locations. 2.8 Housekeeping Contractor must use good maintenance practices around the work site. Work areas shall be maintained in a neat and orderly manner. Trash, spills, unused tools or materials, etc. must be cleaned up or put away as soon as possible. Aisles, emergency exits, electrical panel accesses, fire extinguishers and emergency controls must be kept clear and free of materials at all times. All wastes are to be properly and safely disposed of. Contractor shall leave all work sites clean, orderly and in good condition as directed by Company. All remaining trash, debris, surplus materials and equipment must be removed from Company locations or neighboring property upon completion of work. 2.9 Clothing and Other Apparel 12 Without prejudice to Company s other remedies, any of Contractor s personnel who are in breach of the provisions of Company s rules, regulations, and policies relating to substance abuse, dangerous materials, and firearms, shall be immediately removed from the applicable worksite. Entry into Company property is conditioned upon the Company s right to conduct unannounced searches for such contraband. Contractor shall cause Contractor s personnel to comply with and be subject to all such rules, regulations, and policies. Environmental Health & Safety Clothing suitable for the job shall be worn. Long pants and shirts or coveralls should be worn at all times during the performance of the work. Ragged or loose clothing and jewelry (rings, watches, necklaces, etc.) are not to be worn when operating equipment. Any clothing that becomes saturated with petroleum products or hazardous chemicals should be promptly removed or changed. Fire retardant clothing (FRC) must be worn when working in areas where the potential for a flash fire exists. These areas include production facilities, salt water disposal facilities, compression facilities and well sites during all phases of drilling, completions and work-over activity.

13 Section 2 Individuals on location but not engaged in work activity or not present in the area where work is conducted are not required to wear FRC. Examples of these exclusions include visits to a drilling location to make material or equipment deliveries and visits to secure signatures on work tickets. Individuals conducting construction activities on locations prior to drilling a well are not required to wear FRC Compressed Gas Cylinders and Compressed Air All compressed gas cylinders shall be returned immediately to a suitable storage area after use. Protective caps shall be placed over the cylinder valves when not in use or when being transported. Compressed gas cylinders shall be kept away from heat, fire, molten metal, or electrical lines, and shall not be transported by mobile cranes unless a special carrier is used. Compressed gas cylinders shall be stored in the upright position and secured. Acetylene or liquid compressed gas cylinders shall never be used in a horizontal position, Compressed air shall not be used for cleaning clothing or parts of the body. If used for other cleaning, the discharge shall not exceed thirty (30) psi and eye protection shall be worn Storage, Use and Labeling of Chemicals, Solvents and Paint All chemicals, solvents, and paints are to be stored in accordance with industry practice in a storage locker designed and installed to meet the requirements of NFPA 30. Chemicals, solvents and paints should be returned to the storage locker after use and at the end of each workday or shift. All chemicals, solvents and paints must be kept in clearly labeled containers. Material Safety Data Sheets ( MSDS ) must be supplied for Contractor s materials supplied under any MSA, or in connection with any work performed by Contractor or any of its subcontractors, and all of Contractor s and all of its subcontractors personnel must be instructed in the safe use of the chemicals in accordance Personal protective equipment (PPE) or clothing shall meet American National Standards Institute (ANSI) or a Companyapproved equivalent standard. as the liquid may be forced out through the hose causing a fire hazard or explosion. Cylinders shall be handled, maintained and stored as required by 29CFR Version 1.1 with an appropriate written Hazard Communication Program. Protective equipment as outlined in the MSDS or as otherwise required by operating location management must be provided to and worn by potentially exposed Contractor personnel. 13

14 Low flash point solvents shall not be used for any washing or cleaning. The use of gasoline for anything other than the intended purpose is not permitted at Company sites Personal Protective Equipment Personal protective equipment (PPE) or clothing shall meet American National Standards Institute (ANSI) or a Company-approved equivalent standard. The wearing of appropriate PPE is required at the worksite or any location where hazards exist in the work place and in all specifically designated areas. The following items of PPE shall be used and/or worn by Contractor s personnel at all times in and around the work site: Hard hats Safety Glasses with side shields Steel-Toed Safety Shoes or Boots Hearing Protection must be worn in high-noise areas 2.13 Overhead Work When working overhead, the area below shall be roped off or other equivalent measures taken to protect workers on the worksite. Danger signs to be used Contractor s personnel shall never pass under a suspended load. Tag lines will be used for positioning equipment or materials during a lift. The following PPE, along with training in its use and care, is to be furnished by Contractor: Head Protection Eye and Face Protection Hand and Foot Protection Hearing Protection Flame Resistant Clothing Clothing for Handling Hazardous Chemicals Fall Protection Other equipment, i.e., breathing apparatus, gloves, harnesses or belts, rain gear or chemical resistant clothing, etc., must be worn when the hazards to which an individual is exposed dictate their use. shall read Danger Overhead Work and will be conspicuously posted by contractor. Please follow all applicable signage requirements. When possible, tools will be tied off or equipped with a tether or lanyard. Contractor s personnel shall never pass under a suspended load. Tag lines will be used for positioning equipment or materials during a lift. All lifts will be conducted using properly rated equipment, and all slings, chains and other lifting devices will be certified and tagged. All lifting equipment will be inspected prior to use Scaffolds or Platforms All scaffolds or platforms used for installation and maintenance or removal 14 Environmental Health & Safety

15 Section 2 of machinery and equipment shall be constructed, maintained, and used in compliance with the applicable occupational health and safety construction regulations. All scaffolds shall be inspected and tagged by a competent individual prior to use Fall Protection Equipment Full body safety harnesses and lifelines shall be supplied by Contractor and worn by all workers when working above six (6 ) feet. All fall protection equipment shall be routinely inspected and maintained following manufacturer recommendations Non-Destructive Testing (NDT) Radioactive isotopes, x-rays, etc., shall only be used by licensed individuals. All others onsite shall be notified of the testing activities and instructed to stay clear of the area. NDT may have to be scheduled such that individuals do not have to work in the affected area. of potentially hazardous energy and excavation work Hydrogen Sulfide Hydrogen Sulfide, or H2S, may be encountered at Company facilities. Contractor is responsible for ensuring that Contractor s personnel are properly trained and equipped in accordance with applicable regulations and to a recognized industry standard when working in areas where hydrogen sulfide may be encountered due to the nature of the work Fire Protection Any unauthorized use of fire protection equipment for any other purpose other than its intended use is forbidden. Contractor shall provide fire protection equipment appropriate for the work being performed. Smoking is only permitted in designated areas. Any work that has the potential Contractor shall provide fire protection equipment appropriate for the work being performed Safe Work Systems (SWS) Safe Work Systems include Permit to Work (PTW), Confined Space Entry (CSE), Hot Work, Lock-out Tag- out (LOTO), and Trenching & Excavation. Contractor is required to implement SWS programs relevant to the work being performed, including, but not limited to, hot work, confined space entry, control to produce a spark or open flame (i.e., welding, cutting, grinding, electrical) in areas where flammable vapors or combustible materials may exist is strictly prohibited Safety Equipment Contractor shall provide adequate safety equipment of an approved type and amount as is required for the Version

16 performance of the work. Contractor shall maintain this equipment in a professional manner as dictated by legal and industry standards. In addition, Contractor shall keep up-to-date records of all said equipment Safety Training Contractor shall ensure that Contractor s personnel have been given the necessary safety, emergency, and jobrelated training required by petroleum industry standards and practice, as well as Contractor s and Company s EHS policies and procedures. Training records must be available to Company for review. Contractor shall ensure that certificates for mandatory training have been obtained by Contractor prior to Contractor s personnel travelling to any location to start the work English Language Proficiency Contractor shall ensure that all Contractor management and supervisory personnel are proficient in reading and writing of the English language. This is critical for all aspects of EHS including implementation of procedures, permits to work, training, signs, and emergency response actions DOT Safety Contractor shall operate all Commercial Motor Vehicles in compliance with State and Federal Motor Carrier Safety Regulations Minimum Certifications and Licenses Contractor will ensure that all personnel have the necessary certifications or Contractor shall ensure that Contractor s personnel have been given the necessary safety, emergency, and job- related training required by petroleum industry standards and practice, as well as Contractor s and Company s EHS policies and procedures EHS Meetings Regular EHS meetings should be held and pre-job toolbox talks should be established. Such EHS meetings should be documented and copies forwarded to Company s Authorized Representative as requested. licenses required for their jobs. Examples include, but are not limited to, IADC Well Control, radiation safety, rigger, crane operator, welder, electrician, plumber, forklift operator and commercial motor vehicle driver Electrical Safety 16 Environmental Health & Safety

17 Section 2 Contractor s personnel working around electrical equipment shall take precautions to ensure that the equipment is de-energized while work is being conducted on or around such equipment. Work that is to be conducted near any are questions concerning evacuation or emergency response arrangements, Contractor must immediately notify a Company supervisor for further explanation. 3. Environmental Management If there are questions concerning evacuation or emergency response arrangements, Contractor must immediately notify a Company supervisor for further explanation. overhead power line shall be planned such that a clearance of no less than ten feet is maintained throughout the duration of the job to prevent accidental contact with energized equipment or lines. If work is to be performed within a ten-foot radius of overhead energized equipment, the equipment must be de-energized prior to starting the work, unless adequately controlled by the safe work system. Ladders used around electrical equipment should be constructed of wood or other nonconductive material. Strict precautions should be taken to ensure that all equipment used is properly grounded and that accidental contact with ungrounded electrical sources is prevented Emergencies Contractor s personnel shall become familiar with Company s Emergency Response Plans and Procedures at Company work locations and will participate in emergency drills when conducted on Company property. If there Version 1.1 Contractor is responsible for compliance with all applicable U.S. Environmental Protection Agency, state and other federal laws and regulations related to the environment. Contractor shall pay due regard to the environment and shall act responsibly in order to protect the environment from adverse effects resulting from Contractor s activities and to minimize any adverse impact which may arise from such activities. In order to accomplish this objective, Contractor shall ensure the following: 3.1 Environmental Housekeeping All work and maintenance shall be completed in such a manner as to preclude contamination of land sites and subterranean fresh water zones through the use of good international oil industry practices. 3.2 Reporting Contractor shall immediately report any oil, produced water or chemical spills to Company using Oasis online reporting 17

18 system at: Diligence Company, to ensure there are no detrimental effects being imposed on surrounding inhabitants, may periodically assess noise levels from operations. When requested by Company, Contractor shall install sound absorption and mitigation devices. 3.4 Waste Management All unused chemicals NOT consumed in operations or maintenance shall be kept in stock, returned to the supplier if applicable, recycled, or returned by Contractor at its sole expense Waste Management Plan and/or Hazardous Wastes. 3.5 Tanks and Vessels Tanks or vessels for fuel and lubricants storage shall be properly closed, installed at ground level, and be contained inside an impermeable dike technically designed for this purpose, with a retention capacity equal to the 110% of the largest tank. Tanks or vessels shall comply with all technical and safety requirements to avoid excessive evaporation, contamination, explosion or fuel spill. The Contractor shall inspect these tanks on a daily basis and any accumulation of fuel/oil shall be removed to preclude eventual overflows and seepage into the ground. 3.6 Waste Water All unused chemicals NOT consumed in operations or maintenance shall be kept in stock, returned to the supplier if applicable, recycled, or returned by Contractor at its sole expense. At the discretion of Company and dependent on the nature of work, Contractor may be requested to develop and implement a Waste Management Plan (WMP) for handling and disposing of hazardous and non- hazardous waste material. This WMP shall be subject to the review and approval of Company. At a minimum, all wastes shall be identified and catalogued as either Non-Hazardous All wash down water and other water derived from execution of the work is be controlled and managed in such a manner as to prevent direct discharge to land or inland rivers and lakes. 3.7 Wildlife Management Contractor s employees shall not hunt, fish, trap, trade or keep wild animals in captivity on Company locations. 18 Environmental Health & Safety

19 Section 2 Version

20 Table of Contents 3.0 Scope 3.1 Engineering 3.2 Land Department 3.3 Construction Department 3.4 Operations Department 3.5 Regulatory Compliance 3.0 DOT Pipeline Construction 3.1 Veriforce 4.0 Non-DOT Pipelines 4.1 Recordkeeping 5.0 Internal Compliance 5.1 Management of Change Program Administration

21 Section 3 Program Administration DOT - PHMSA - Department of Transportation (Pipeline and Hazardous Materials Safety Administration). Oversees construction, integrity management, public awareness and reporting on all regulated pipelines. API - American Petroleum Institute. Provides best practices and guidelines for public awareness and construction of DOT regulated pipelines. Process Management - Methods of administrating all OMS projects from the planning stage to final completion. This includes; engineering, AFE development, landowner agreements, permitting, construction, inspection, and final reporting. Public Awareness - Required planning and sharing of knowledge in order to keep any affected public informed of Oasis projects on a consistent basis. Stakeholders - Individuals who reside or own property near a DOT regulated pipeline. AFE - Authorization for Expenditures SWD - Salt Water Disposal Departments: Engineering, Land, Construction, Production Considerations: Quality Control, Management of Change One Call - Process used to manage and track all requests to perform excavation activities. High-Consequence Area - Distance from any pipeline where higher than normal risk is thought to exist. Determined by the type of material, size of pipe, and proximity to public areas. Version

22 3.0 Scope This section has been structured to provide a guiding document for OMS personnel and service providers in order to understand the process for developing, completing, and maintaining all portions of the OMS Business Unit. 3.1 Engineering OMS Engineering performs many of the developmental and financial functions of Oasis Midstream Services. Design and coordinate project technical scopes Comply with governmental regulations and industry best practices Determine pipe size and design Determine equipment size and design Develop and communicate OMS internal scopes of work, and contractor scopes of work. Model existing and proposed pipelines Support Construction, Operations, project engineering, and commercial development Perform hydraulic computer modeling to design gathering systems, and identify methods to increase existing systems efficiency and production volumes. Develop required authorization for expenditures AFE s Create and submit AFEs and economic justification metrics Track costs and monitor expenditures for all AFE s and budgets Coordinate project activities with multiple entities including Marketing, Operations, Land, Legal, and Accounting along with external entities such as service providers, vendors, government agencies, regulatory bodies, landowners, and other production companies. Track all production volumes and audit performance Track OMS revenue and expenditures 3.2 Land Department Receives mapping information from Houston Engineering, outlining area to be developed. Contacts surface owners for survey permission Coordinates with construction group to ensure survey accuracy and confirm route with surface owners. Obtains ROW agreement in coordination with surface owners. Receives permitting for all roads or other utility crossings. Coordinates with construction department and engineering prior to project construction phase. Land and Construction coordinate as-builds post construction. Reviews as-builds information and designs with surface owners. Attaches As-build to ROW agreement. Records ROW agreement with the county. Coordinates with construction group and surface/asset owners when necessary to assess damages or other finalization concerns. 22 Program Administration

23 Section 3 Manages any and all amendments. Agreement amendments initiated by landowner, construction, or other party when necessary, will restart the agreement process. If any agreements require written documentation with: city, county, federal, land owners, stakeholders, other utility owners, land department will be present and execute such agreements. 3.3 Construction Department Develops Initial Cost Estimate. Assists team members with ongoing operations as needed. Covers for team members on days off. 3. Team Members Inspect and maintain SWD s on a daily basis. Perform quarterly pressure tests on all pipelines within the OMS system. Perform inspection and maintenance on transfer pumps on a weekly basis. Coordinates Survey with Survey Crews. Completes Construction (Review section 4). Reports to DOT and files all DOT paperwork, reports, etc. Internally files all agreements. 3.4 Operations Department 1. Foreman Coordinates with construction on new and existing pipeline layout. Works with engineering on facility design and layout. Coordinates with team lead on day to day operations of disposals and pipelines Approves invoices of venders transporting sw to disposals. 2. Team Lead Coordinates with foreman and team members in regards to daily maintenance and repair of SWD s and pipelines. Version 1.1 In the event of a spill, they coordinate cleanup and disposal of contaminated materials. 4. Measurement The measurement division of OMS Operations department is primarily responsible for the oil production custody transfer to service providers who purchase Oasis Petroleum s crude oil. Their functions are as follows: Communicates with Purchasing Service Providers. Receives information about receiving LACT Units. Organizes set-up and ensures they are correctly wired-in. Coordinates startup. Communicates with OMS Engineering for projected start-up. Performs daily measurement to collect production information. 23

24 Communicates maintenance needs with purchasing vendors. Troubleshoots problems with pumps, and other OMS equipment. Performs proving operations on sales meters. Calibrates all meters on a quarterly basis. 3.5 Regulatory Compliance Below are various regulatory considerations that must are managed by the OMS group internally, by use of service providers, or in conjunction with other departments when necessary. 1. One Call System Management Manages the process and system utilized by OMS personnel to track, record, and complete one-call requests and notifications. Completes all requirements prompted by OMS designated online reporting system. Duties include one-calls requested in Montana. Training and Awareness. Employees Contractors Line Locator Qualifications 2. Construction Documentation Project Build Record [ref. Section 4.4.2] PBR Figure 1 The Project Build Record is utilized as a recording tool for OMS Construction personnel to track and manage that all required documents are created, stored, and completed throughout the process of construction. They apply to both DOT and Non DOT Lines Completing Project Build Records Construction Administration personnel will ensure all necessary documents are contained with the appropriate files, both physically and electronically. Administrative personnel archive construction and process information electronically on the designated server. Inspectors are responsible for completing and delivering PBR s to OMS managers and/or administrative personnel. 3.0 DOT Pipeline Construction 1. Reporting Procedures A) Annual Reporting New Construction All new construction projects involving DOT Lines must be documented with as builds attached. Types of Pipe By classification, by type Must be recorded and reported annually. Length of Pipes By classification, by type must be recorded and reported annually. 24 Program Administration

25 Section 3 Figure 1 - Project Build Record Version

26 Incidents Any incidents involving OMS DOT lines must be documented and incident reports must be completed and filed immediately onto the PHSMA portal database. Drug Testing Information OMS personnel who are responsible for: constructing, completing; maintaining; or responding to emergencies on any DOT regulated pipeline must be part of a DOT standard drug testing consortium and plan. Accidents Accidents involving any DOT pipeline must also be reported immediately online within the PHMSA portal. Near Miss / Incident Reporting (to PHMSA online within 24 hours of any incident) Integrity Management Integrity management programs involve methods of ensuring the longevity and safety of DOT Regulated pipelines. This can include maintenance, public awareness programs (Including posting, mailers, and pipeline markers) and preventative maintenance. Maintenance Quarterly Maintenance (Documented) Pressure Testing Leak Testing Valve Operation / Inspection ROW Inspection Equipment Maintenance and Inspection Public Awareness Programs Public Awareness programs include the following necessary components: Mailers / Reports Response Metrics Surveys Public Awareness Meetings The value and effectiveness of these programs must be audited on an annual basis, reports compiled, and findings recorded for ongoing program development. Contractor Management DOT standards require that contractors performing work on behalf of any pipeline regulated by the DOT, complete operator qualification programs and be enrolled in DOT regulated drug & alcohol consortiums. OMS utilizes Veriforce as their approved service provider and standardization group for contractors performing construction, maintenance, or emergency response on DOT regulated pipelines. 3.1 Veriforce Drug and Alcohol Programs 100% Consortium Participation All personnel who take part in the construction of a DOT regulated pipeline; inspectors, foreman, supervisors, laborers, truck drivers, must be enrolled in a DOT consortium. Veriforce verifies that selected contractors are enrolled, and make these records available to OMS personnel. Internal Review OMS regards the safety and health of their contractors highly. To ensure that 26 Program Administration

27 Section 3 contractors are up-to-date with training and verification, OMS will perform a review semi-annually for gaps in any contractor compliance. Recordkeeping Throughout the process of construction of DOT lines, all records of construction data must be maintained. Some of these include: Pipe and special invoices and manufacturer information Fuse logs Pressure / Leak Testing information Weld tests and Welder certification information Annual Review Records will be reviewed and audited on an annual basis. This process will correlate with the April 15th deadline for DOT reporting. (MOC) process must be completed. This is to ensure that all changes with OMS production are documented thoroughly, included with justification for the change, cost savings (if applicable) and desired outcome. These processes will be reviewed from time to time to ensure that changes being made are effective. Changes that require an MOC process include, but are not limited to: Administration Procedures Existing Lines Clean-ups Processes Type of Equipment Used (Technology) Methods of Document Control Responsibility changes Divisions created Final Inspection/ Close-out Protocol 4.0 Non-DOT Pipelines 4.1. Recordkeeping Although non-regulated pipelines do not require records be kept as thoroughly and completely as regulated pipelines, OMS expects that the same recordkeeping procedures be followed. 5.0 Internal Compliance It is OMS expectation that its operations be reviewed on a regular basis by OMS personnel who will assess its process from a quality assurance and quality control perspective. Some of these functions are as follows. 5.1.Management of Change When a change to an internal OMS system occurs, a Management of Change Version

28 References Federal Standards OSHA DOT (if applicable) T.49.C.D.192 T.49.C.D.195 Other Standards ASTM F2620 D638 D C150 API NACE #1 - Construction Process Material Transfer ROW Establishment ROW Survey ROW Construction Pipelaying Tie-ins Crossings Civil Construction Facility Construction Coating Backfill Pressure Testing ROW Cleanup Pressure Testing Considerations PPE Hard Hat FR Clothing Goggles Face Shield Hard Toed boots Chemical Resistant Gloves Safety Glasses Other equipment as applicable 28 Construction Guidelines

29 Section 4 Construction Guidelines Oasis Representative - Any individual who has authority on an Oasis project, location, or situation regarding Oasis assets or personnel. Inspector - Any individual authorized to supervise construction, quality, or management of an Oasis construction project. Material Transfer - (See Material Transfer Form-OMS-10010) The process used to track OMS inventory ROW - Right-of-Way Predetermined area established by agreement or grant, to pass along a specific route through grounds or property belonging to another party. Poly (PE) - Polypropylene Pipe. Also known as Plastic or HDPE Pipe. SDS - Safety Data Sheets OSHA - Occupational Safety and Health Administration DOT - Department of Transportation ASTM - American Society for Testing & Materials AISC - American Institute of Steel Construction API - American Petroleum Institute SMYS - Specified Minimum Yield Strength NACE - National Association of Corrosion Engineers SSPC - Society for Protective Coatings Holiday - A pipe anomaly such as a ding or dent that will cause early corrosion. Instrumentation & Electrical (I&E) - Components involved in automated measurement and electrical interface with a variety of pipeline and production equipment. Version

30 Table of Contents 4.1 Material Transfer General A) Pipe Handling B) Inventory C) Loading D) Material Return 4.2 ROW Corridor Establishment General A) Engineering Develops Project Scope and Design 4.3 Right of Way (ROW) Survey General A) Construction Staking B) As Build C) Mapping 4.4 ROW Construction General A) One Call B) Line Locating C) HydroVaccing D) Relocating Project Build Record (PBR) Preparation of Right of Way (ROW) A) Clearing B) Grading C) Topsoil Housekeeping A) Poly shavings B) Tools C) Equipment Storage Preservation of ROW 4.5 Pipelining General Stringing A) Quality Control B) Unloading Methods C) Inspection A) General Considerations B) Butt Fusion Joining Restrictions C) Outside Diameter (OD) Compatibility D) Wall Thickness (DR) Compatibility Construction Guidelines

31 Section 4 E) Fusion Quality Verification Data Logging and Testing F) Fusion Evaluation Tests Mechanical Field and Laboratory Tests G) Weather Guidelines Bending A) Field-Bending Steel Pipe B) Field Bend Data - Steel Pipe Trenching / Excavation A) Trenching / Excavation Permitting B) Daily Inspection C) Trench Boxes / Shoring Lowering Pipe A) Trench Bed Condition B) Trench Bed Material C) Inspection & Testing Welding A) General B) Requirements C) Method D) Line Pipe Weld Procedures Boring A) Equipment Requirements B) Boring System C) Other Equipment D) Boring Operations E) Utility Locates 4.6 Tie-Ins General A) Water Considerations B) Backfilling C). Cold Cutting D) Live Tie-In E) Squeezing 4.7 Crossings General A) Approvals B) Line Crossings C) Road crossings D) Water Crossings E) Boring Crossings F) Section Lines Version

32 4.8 Civil Construction General A) Cement B) Structural Steel C) Roads / Walkways D) Location / Well Pad 4.9 Facility Construction General A) Pumps B) Houses C) Risers D) Instrumentation and Electrical (I&E) 4.10 Coating General A) Painting B) External Painting C) Jeep Sticks 4.11 Tracer Tape & Wire General A) Depth B) Wire Location C) Wire Protection 4.12 Backfill Material Backfill Method A) Backfill Material B) General C) Padding D) Padding Density Final Compaction A) Moisture Restoration of Construction Areas Overburden / Crown Irrigation & Drainage Reinforcing Topsoil Construction Guidelines

33 Section Leak & Pressure Testing General A) Location of Equipment B) Test Duration C) Water Sources D) Failures E) Depressurizing F) Dewatering 4.14 ROW Clean-Up Post-Construction Clean-up A) Fences B) Gates C) Line Markers D) Test Leads E) Reseeding F) Erosion Control G) Rock Picking 4.15 Start-up A) Removal of Isolation Devices B) Opening of Block Valves C) Suction Line Leak Test D) Oil System E) Pump to Line Leak Test F) System Leak Tests 4.16 Project Sign-off Final Inspection Version

34 4.1 Material Transfer General Oasis Midstream Services (OMS) requires that all operations be performed in a safe and efficient manner. A major component of operating this way involves the process of handling and transporting materials. This section reviews overviews safe guidelines in order to handle and transport materials for OMS in a safe and professional manner. A) Pipe Handling 1. Prior to loading or unloading any pipe, trucks and trailers must be parked in a way that they are level and secure. Parking (hand) brakes should be set and the wheels correctly chocked. The truck s engine should be off and left in gear and the driver s location known at all times. Personnel directly involved should be the only ones within the area of pipe handling. Non-essential personnel must stay clear of work area. 2. Poly pipe becomes extremely slippery when wet. Caution should be used at all times when handling poly pipe, especially in rainy or snowy conditions. When handling this pipe in these conditions work slowly. 3. Black poly pipe becomes extremely hot when exposed to direct sunlight, therefore exercise caution and wear appropriate PPE at all times when handling black poly pipe. B) Inventory It is the responsibility of OMS personnel to oversee and take record of all equipment, pipes, and specials that enter or leave the OMS yard. This will be accomplished through internal inventory management systems. 1.A) Equipment Storage - Jobsite Storage areas should have smooth, level surfaces that are free of stones, debris and other materials that may damage pipe. If no adequate surface can be prepared, pipe should be placed on evenly spaced planking, racks, or other means of supporting and protecting pipes and equipment. Weather conditions should also be considered when storing materials that could be damaged by extreme temperatures, ice, wind, or moisture. Pipe should be separated and stored according to length and diameter as is most feasible. Piles must only contain a single size of pipe and be constructed in a pyramid shape with the bottom layer braced to prevent movement of any kind. Rows of pipe should all for easy loading and offloading of pipe by use of available loading equipment. 1.B) Off-Site Storage When storing pipe off-site, it should be placed in pipe racks according to length and diameter of pipe to prevent from rolling or falling. Pipe larger than 2 inches should be stacked with spacing strips. If pipe is stored outdoors, pipe racks should be made of material that will not deteriorate. 1.C) Indoor/Outdoor Storage 34 Construction Guidelines

35 Section 4 Black poly pipe contains more than 2% carbon black and will resist UV damage. It may be stored unprotected from UV. Other colors must be stored no longer than two years. C) Loading 1. Operator Experience Only experienced operators are allowed to use heavy equipment. This includes a verification as per OSHA standard Staging area must be clear of workers, equipment and other obstacles while material is being loaded or unloaded and must allow for clear line of sight. 2. Weight Limitations Never exceed rated lifting capacity of equipment. The proper and safe use of forklifts and other heavy equipment is the responsibility of the contractor. care to ensure that forks are not forced underneath pipe, or positioned in a way that could damage pipe racks. 2.C) Tilt Degree When tilting the load of pipe or spools tilt slightly back in order to stabilize and prevent objects from rolling or sliding forward without control. 2.D) Handling Loads When transporting a load, move with the load as close to the ground as possible, taking care to not allow pipe to drag. Drive as slowly as necessary as to avoid bouncing. 3. Front End Loaders The proper and safe use of front end loaders falls under the responsibility of the operator. 3.A) Compliance If equipped with forks, loaders are used as forklifts and treated as such. Always Never exceed rated lifting capacity of equipment. 2.A) Inspection Check forks for jagged edges/burrs. Forks set to widest setting. Always lift from center. 2.B) Fork Application Slide forks gently underneath pipe. Take maintain stability and center of gravity precautions. 4. Pipe Handling Accessories Accessories used to handle and support pipe should be properly constructed and rated above the capacity of the load that they are intended to support. Version

36 Chains, steel cable, wire rope, or hooks are not to be used to handle poly pipe. Slings must be wide band to distribute load. Nylon rope is acceptable to use with poly pipe. When the securement banding is being cut or removed, the coiled pipe has the potential to whip away from the coil. Ensure no personnel are in the area while removing these bands. DO NOT remove straps until sling is secured. Chains, steel cable, wire rope, or hooks are not to be used to handle poly pipe. Slings must be wide band to distribute load. Nylon rope is acceptable to use with poly pipe. Only specially designed pipe tongs can be used to lift poly pipe. Only specially designed pipe tongs can be used to lift poly pipe. Lifting capacities of equipment and attachments are not to be exceeded. The angle between each lifting leg must not exceed 45 degrees. 4.A) Unloading Coiled Pipe Certain precautions must be taken into consideration prior to unloading coiled pipe. When unstrapping a load of coiled pipe, it is necessary to ensure that personnel are out of line with the ends of pipe. Trailers must be level before unloading either palletized or nonpalletized coils. Never push, pull or roll coils off of trailer. Never stand behind, under or around the load as it is being unloaded. 4.B) Straight Length Pipe It is necessary to ensure the load has not shifted during transport before removing securement straps. Bundles should be unloaded with forks, forked loaders or cranes with spreader bars. Steel bands used on bundles shall not be removed until bundle is secure and stabilized in storage area (remove from ground with extension device). Never stand on a load of pipe. If breaking the banding is not possible from the ground, personnel must remove bands by the use of extension breaker bars. 4.C) Strip Loads 36 Construction Guidelines

37 Section 4 Cranes should use spreader bars to ensure proper transportation of the pipe. Do not cut bands until pipe is secure in storage. Ensure all wheel chocks are in place before beginning to unload. D) Material Return 1. Material Transfer Forms (MTF) All materials designated to arrive to, or leave from Oasis yard, must have a Material Transfer Form (MTF) completed prior to being transported. Minimum details to be included: 2.B) Bill of Lading The yard personnel will unload the material and check the material against the packing list before signing the BOL (Bill of Lading); personnel will then stage the material in a predetermined location. 2.C) Damaged Material If material is damaged beyond use/ repair, it will be cited as Condition D and billed to contractor or rejected. 3. Outgoing Material 3.A) Gate Checkout All personnel with the crews picking up All materials designated to arrive to, or leave from Oasis yard, must have a Material Transfer Form (MTF) completed prior to being transported. Lease Name / Location AFE / LOE # Person receiving materials name/ company/signature Information about who the material is for 2. Incoming Materials 2.A) Gate Check-in All vendors or contractors delivering material for OMS projects must check in at the designated gate. material must check in at the north gate. Yard personnel will receive and must have the following information before loading any material: 1. Location 2. AFE 3. Name of Oasis supervisor 4. List of material required The yard personnel will then fill out a yard Material Transfer Form (MTF) and have the person picking up the material sign it before leaving. Version

38 Yard personnel will receive and must have the following information before loading any material: Location, AFE, Name of Oasis supervisor, and the list of material required Support documents [OMS Material Transfer Form] 4.2 ROW Corridor Establishment General The corridor is established as the beginning stage of preparation for installing a pipeline. Each department has various roles to play in this development process. They are outlined below, as well as other establishment criteria. A) Engineering Develops Project Scope and Design Responsibilities 1. The OMS engineering group will develop all pressure scopes, elevation, necessary equipment, operating specifications, and other data relative to the design and operation of the proposed pipeline. B) Land department Manages Agreements and Planning Responsibilities 1. Develop and approve proposed pipeline route taking into consideration: feasibility; financial viability; topography; environmental; operational optimization; and gaining the necessary approvals from stakeholders. Record plat to county and work with other reporting and recording agencies. 2. Record plat to county and work with other reporting and recording agencies. 3. Obtain and finalize ROW agreement and landowner signoff. 4. After project completion, obtain final signature from landowner to release the project. C) Construction Department Completes the Project Responsibilities 1. Manage contractors, understand deadlines, follow regulatory guidelines, maintain quality control and review OMS programs in order to verify compliance. In addition to ensuring all documentation is maintained, remediation is accomplished if necessary, and all procedures are followed. 2. The construction department is also required to notify Land Department when a project is complete. 38 Construction Guidelines

39 Section Right of Way (ROW) Survey General The ROW is a route that is selected on a preliminary basis to determine the scope and cost of a project (determined by the engineering department). The ROW is a legal right, established by usage or grant, to pass along a specific route through grounds or property belonging to another. A) Construction Staking Construction staking will be performed with the direction of Oasis Representatives. Oasis will mark route of the centerline of the right-of-way or ROW, as well as the ROW boundaries, at the company s discretion. Oasis contractors will be responsible for staking the ditch line within the rightof-way ROW, which will be addressed in the construction folder. Stakes will be of such regularity that continuity may be maintained, normally at 100- to 200-foot intervals, along with the beginning, middle and end of all points of intersection, bores, and any/all other landowner considerations. These stakes will also be used to gauge construction progress and to reference specific locations on drawings and in reports. Contractor is responsible for submitting One Call to coordinate locating existing pipelines, sewers, water or gas mains, and electric or telephone installations. Contractor shall take all necessary precautions to protect and to avoid damage or interference with these facilities and shall repair these lines immediately if damaged. Contractor is responsible for maintaining all survey and line markers. Failure to do so will result in immediate shutdown of the job until adequate markers are maintained. B) As Build C) Mapping -Reference Section 3- The scope of mapping is transferred from survey to the Houston mapping group with all required details and info. Houston will then complete a field map with all valves, roads, crossings, landmarks, well names, etc. 4.4 ROW Construction General The Right of Way is the most permanent picture of the quality of work that OMS does. The process involved in acquiring, maintaining, and leaving the ROW are extremely important to our relationships with our stakeholders, our assets, and our reputation. A) One Call A One Call must be made prior to any digging being performed. This can be accomplished by calling 811 in both North Dakota and Montana. In Montana, it is also possible to fax-a-locate, however there must be a pre-approval process completed prior to the One Call being processed. Montana s One Call fax number: (406) and website: ( *Faxing a locate to ND One Call will only be available through the end of Dec Locate Wait Duration Version

40 After a One Call is made, line-locating personnel will arrive at the desired location within 48 hours of the One Call submission and locate any Oasis, or other entity s lines. Oasis does not authorize excavation prior to lines being located under ANY circumstances, even if at times a locate does not occur within 48 hours. The locate ticket must be followed to the exact specifications written on the ticket. B) Line Locating 1. Project Relocating & Re-spots After a line has been located, there are many things that could require a respot including: Flags being moved by landowner; Flags being moved by contractor/service provider; Uncertainty about accuracy of utility / facility markers; Change in job scope / area; One Call tickets whose territory located does not clearly indicate where the locate starts or ends. 2. Distance from Flags Minimum distance to maintain is 2 feet from any flag or utility marker, in any direction. C) HydroVaccing Hydrovaccing is the process of locating a line with non-destructive means. Water is used in lieu of shovels, excavation equipment, etc. This process uses water at high pressures to locate lines, and has the additional benefit of vacuuming, or removing the water/mud that is created in the process. All tie-ins must be hydrovacced, as well as any time a line crossing is performed. D) Relocating Locate tickets are good for 21 days only. The locate ticket will indicate the expiration of the One Call ticket Project Build Record (PBR) A) Required forms [OMS 1001] Oasis Dig Permit [OMS 1002] Anode Installation [OMS 1003] Confined Space Entry Permit [OMS 1004] Construction Summary [OMS 1005] Foreign Line Crossing [OMS 1006] Hot Tap Permit [OMS 1007] Hot Tap Info [OMS 1008] Hydro Test Data [OMS 1009] Locate Wire Installation [OMS 1010] LOTO Process [OMS 1011] One Call Log [OMS 1012] Pipe Tally [OMS 1013] Pressure Test Data [OMS 1014] Poly Report [OMS 1015] Project Build Record [OMS 1016] Steel Pipe Record [OMS 1017] Cost Estimate [OMS 1018] Measurement Change Form [OMS 1019] Final Inspection Report Preparation of Right of Way (ROW) A) Clearing It is required prior to construction that removal of brush, grass, weeds, trees, 40 Construction Guidelines

41 Section 4 crops, or anything that is on the ROW occurs. Contractor will use Brush Hog, or other sufficient means to accomplish this. B) Grading Preparing the ROW to the standard grade, side hilling, acquiring proper highs and lows to ensure your equipment gets through without issue. C) Topsoil Cut into your soil top. Location geography will determine depth of topsoil. Topsoil is moved to one side of ROW until the final step where it will be redistributed evenly. State lands require 12 inches of topsoil to be removed ROW Access Oasis Petroleum shall obtain easements for ROW s and permits for roads and railroad crossings. Contractors may only access the ROW from approved public roads and points unless specifically designated by Oasis representatives. No two-track roads will be used unless specifically authorized. Section lines can only be used with prior Oasis authorization. Settlement of any off-row damages is the sole responsibility of the contractor, specific indemnity language is written into Oasis Master Service Agreements Housekeeping A) Poly shavings Any waste materials created during the process of stringing, fusing, bending, or shaving pipe must be gathered and disposed of in the correct manner. These spare materials are not to be buried or left behind. B) Tools Tools must be kept a minimum of 2 feet from the edge from any excavation including open excavation, trench, bell hole, etc. C) Equipment Storage Equipment storage locations/laydown areas must be established prior to the commencements of Oasis projects. All agreements for additional space will be initiated by the contractor but must have Oasis approval prior to contact with landowners. The cost of these areas may be assessed only to the contractor, however, Oasis may choose to be involved or lead in the negotiation process Preservation of ROW Contractors shall offset all centerline and locating stakes in a uniform manner, as required for clearing and grading. After clearing and grading contractors shall reset the stakes in their original position. Contractors will be held responsible for the preservation of all stakes and line markers. Contractors shall bear the cost of replacing any stakes destroyed or lost and re-survey work required. 4.5 Pipelining General The method used to lay, seal and bury pipe is foundational to the success of OMS. When contractors, internal departments, and engineering groups work together as a team, projects will be Version

42 completed correctly and to the quality OMS aspires to. The following guidelines have been created with the expectation that contractors will have reference material to rely on in order to uphold and understand OMS requirements Stringing A) Quality Control OMS requests that pipe be strung along the ROW and be aligned in accordance with good pipeline construction practices using pipe furnished only by Oasis. Stringing of pipe on the ROW should done in such a manner as to cause minimal impact to the surround area, and gaps shall be left at intervals to permit use of the land and passage of farm livestock and equipment across the ROW. B) Unloading Methods Pipe is to be unloaded from the stringing trucks and lowered onto approved padded skids by using canvas slings or pipe hooks. Pipe is not to be rolled off the truck. In areas where the ROW crosses rocky terrain, special care shall the suspension of the pipe at each end during stringing operations. In instances where spooled pipe is being laid, contractor is responsible for maintaining pipe integrity. Pipe shall not be strung without Oasis approval. C) Inspection After pipe has been strung, OMS personnel and contractors will inspect it thoroughly. Contractors will reimburse Oasis for any and all damaged pipe. D) Bedding Bedding material must be clean sand or soil and must not contain stones having a maximum dimension larger than 2 inches. Material must be placed to a minimum depth of 6 inches under the pipe and 6 inches over the top of the pipe. The remaining backfill must not contain rock larger than 6 inches. Organic material and wood are not permitted for bedding and backfill since they will deteriorate over time, allowing for subsidence and subsequent shifting and possible pipe damage. It is OMS expectation that contractors will provide trained and qualified personnel to perform buttfusion operations. be taken in lowering the pipe to see that pipe is not dropped on rocks or allowed to rest on sharp or jagged surfaces. Non-ferrous pipe can be pulled provided that no visible damage occurs. A tag line will be attached to hooks to control Fusing A) General Considerations Butt-fusing operations and procedures 42 Construction Guidelines

43 Section 4 are not for novice employees. Personnel must at minimum, prior to work, understand and review manufacturer recommendations and requirements. Oasis can provide these materials if contractor does not have access to these materials. It is OMS expectation that contractors will provide trained and qualified personnel to perform buttfusion operations. The process of butt fusion joins plain end polyethylene pipes and fittings end-to-end without couplings, inserts or additional materials. Equipment must be used to hold the components in alignment and move the components toward and away from each other during preparation, heating and joining operations. The equipment includes tools to face (plane) and heat the component ends. Butt fusion equipment is manually operated for smaller pipe sizes and hydraulically operated for larger sizes. The equipment covers a range of pipe sizes and is properly set up by adjusting pipe holding clamps, setting the heating tool temperature, and for hydraulic equipment, setting the fusion joining pressure. Additional setup will be required depending on the equipment. Butt fusion equipment is set up, operated and maintained in accordance with the equipment manufacturer s instructions. Improperly set up, operated or maintained fusion equipment can produce faulty joints. Other equipment such as pipe supports and appropriate equipment for handling pipe and fittings is required. B) Butt Fusion Joining Restrictions The ends of pipes and other components such as fittings, flange adapters, MJ adapters, etc., that are joined together must have the same outside diameter and comparable wall thickness. Additional information about thickness and diameter compatibility is found below. C) Outside Diameter (OD) Compatibility Several OD controlled sizing systems are used for Poly piping components. These include IPS (iron pipe size), DIPS (ductile iron pipe size), DIOD (ductile iron outside diameter), CTS (copper tubing size), inch-od, or mm-od as applicable. For butt fusion joining, the component ends being joined must be the same outside diameter dimension and system. For example, both pipes must be the same IPS diameter, or the same DIPS diameter. Different OD sizing systems are not compatible, e.g., IPS and DIPS cannot be butt fused to each other. ID controlled (SIDR) pipes are joined using insert type mechanical fittings and are not suitable for butt fusion joining. See Reference R-WL116 for applicable PE pipe standards. D) Wall Thickness (DR) Compatibility The DR of the lower component ends must not be less than 0.79 times the DR of the higher component end. This is to ensure the quality of flow rate, and that pressures do not compromise the components connections. In order to determine if components with different DR s can be joined together, multiply the higher DR by If the lower DR is this number or higher, the components can be joined together using this procedure. Version

44 E) Fusion Quality Verification Data Logging and Testing It is recommended that hydraulic butt fusion machines be equipped with data logging technology to monitor and record time, temperature and pressure during fusion. Field fusion data logging records that compare favorably with tested trial fusion data logging records can provide confidence in field fusion quality. Data logging records must be delivered to OMS personnel at the completion of the project. for not less than one hour. Test at 73 F and 2-in/min separation rate. Ductile elongation should exceed 400% either between the fusion and the end of the gauge area, or for the entire gauge area length. If desired, the tensile yield strength of fusion test specimens and pipe parent material test specimens may be compared; however, the preferred evaluation is ductile elongation rather than tensile yield strength. The pipes and specials shall be jointed by automatic butt or electro fusion Data logging records must be delivered to OMS personnel at the completion of the project. Fusion quality is tested by preparing a trial fusion and performing destructive tests such as two D638 tensile tests, a DF2620 bent strap test, or ASTM F2634 tensile impact tests of specimens cut from the fusion. Prior to testing, test samples must be cooled to 73 F/23 C. ASTM D638 tensile tests are conducted on Type III or Type IV tensile bar specimens machined from samples cut longitudinally from each quadrant of a trial fusion with the fusion in the center of the reduced area. The sides of the tensile bar specimen-reduced area must be smooth and free from nicks and cuts. If wall thickness is reduced, the tensile specimen fused area should be from the middle of the pipe wall. After machining, condition test specimens by immersion in temperature controlled circulating air for not less than four hours or in temperature controlled circulating water welding to form a string above ground and shall be supported by smooth rollers. Three standard lengths of pipe on each side of the fusion machine require two roller supports per length of pipe. All fusion joints shall be inspected and assessed with joint record printouts from the automatic butt or electro fusion machine. Oasis personnel must approve all joints before the contractor is allowed to proceed with pipelining works. The maximum pulling length of fusion jointed PE pipes into position alongside or directly into pipe trench after fusion jointing shall not exceed 1,000 feet or length limited by the hydraulic actuator of the automatic butt fusion machine. Dragging on ground surface is strictly prohibited. All jointing of specials, tees closing lengths etc., to be conducted in the trench shall be by automatic electro fusion couplers or other electro fusion fittings. 44 Construction Guidelines

45 Section 4 ASTM F2620 includes a bent strap test for pipes having a wall thickness of 1 inch (25 mm) or less. Butt fusions may be evaluated by cutting straps from a trial fusion and conducting an ASTM F2620 strap bend test. See Figure 2. The cut through the fusion should be visually examined. Voids or dis-bonded areas are not acceptable. Strap specimens are then bent with the pipe OD or ID to the inside of the bend so that the ends of the strap touch. Failure or dis-bonding at the or unbent specimens are not reliable indicators of butt fusion quality. G) Weather Guidelines Butt fusion can be successfully performed over a broad range of field conditions. However, some weather and temperature conditions can affect equipment operation or performance, or could potentially introduce contaminants, compromising joint Joining procedures may need to be adjusted to compensate for wind, weather or temperature. fusion is unacceptable. F) Fusion Evaluation Tests Mechanical Field and Laboratory Tests ASTM standard tests and techniques such as ASTM D638 tensile tests, ASTM D1598 sustained pressure, ASTM D1599 quick burst, ASTM D1822 tensile impact and ASTM F2634 high-speed tensile impact are strongly recommended for evaluating fusion joint quality. Published ASTM testing procedures have been confirmed to produce reliable, repeatable results. Unproven, experimental, tests and techniques even those that are being developed, may be too stringent or ineffective and are not reliable indicators of fusion quality. Experimental tests should not be used until published by ASTM. Tests such as root bend tests for metal welds, bending a strap or coupon in a bench vise, bending back and forth multiple times, or hammering on bent quality. Joining procedures may need to be adjusted to compensate for wind, weather or temperature. PE pipe and fittings will expand and contract with changes in temperature. If butt fusion machine pipe clamp closure is limited, shims of elastomeric material may be necessary to secure very cold pipe against slippage. In four-clamp machines, shims should be used only in the outer clamps. 1.A) Wind Effects A windbreak or shelter should be used when jobsite wind intensity exceeds gentle breeze conditions. Wind intensity above strong breeze may require suspending fusing operations Bending A) Field-Bending Steel Pipe Version

46 46 Contractor shall make all necessary field bends required in the construction of the line except those shop bends which company shall specifically furnish. Contractor shall also fit the pipe to the contour of the bottom of the ditch, and shall restrict the arc and increase the radius of the bends to such an extent as will prevent the buckling or flattening of the pipe, weakening of welds, and will permit the free passage through said bend of an internal inspection type of pipeline scraper. All bends shall be made using a lined bending shoe so as to eliminate scratching and gouging of the pipe. Dimensions across the minimum and maximum axis of the field bends will be subject to measurement and shall not have a difference in excess of 2.53 degrees. Each field bend shall comply with the following: The bend must be smooth and uniform. On pipe 12 inches and larger an internal mandrel shall be used. After bending the pipe must be free from buckling, cracks, or any other mechanical damage and must conform to the profile of the completed ditch. There must be no wrinkle bends or mitered bends (not including deflections up to 3 degrees that are caused by misalignment). No girth weld may be placed inside the bending shoe if the weld protrudes above the outer wall of the pipe. Construction Guidelines Pipe containing a longitudinal weld must be bent so that the seam is located near the neutral axis. No bend shall be made any closer than 5 feet from the end of a joint or 3 feet from an existing girth weld. B) Field Bend Data - Steel Pipe All field bends shall be made by the cold stretch bending method, and an accurate method of measurement shall be used to determine the tolerances as follows: Trenching / Excavation A) Trenching / Excavation Permitting 1) Dig Permit Prior to any excavation an Oasis dig permit must be complete [OMS Form 1000]. Included in this permit are required action items including: ensuring the applicable state One Call system has been utilized; all potential utilities and facilities have been identified; and areas of concern hydrovacced etc. If an excavation is determined to be 48 inches or greater in depth, adequate sloping, shoring, or trench boxes must be created or installed. Other action items include: North Dakota One Call has been notified and contacts conducted to determine existence and location of underground facilities in the work area. Available records have been referenced and a plot plan indicating the location of all underground facilities has been provided and is available for reference at the job site. Have Oasis operations personnel been consulted for obtaining or discussing:

47 Section 4 Plot plans Pipeline or facility maps Lease maps Has the work area been checked for facilities/pipelines, or utility markers? And companies on markers contacted? Are there ANY signs of ground disturbance within the proposed work area? Have attempts been made to communicate with landowner to verify buried utilities? All necessary approvals, notification and agreements have been obtained. A pre-job safety meeting including JSA and emergency response plan completed? The proposed ground disturbance area(s) are identified and all underground facilities in the dig zone/search zone have been identified and incorporated into the plan. Approved techniques for exposing facilities with 2 feet of ground disturbance have been (or will be) used to verify the location of all known underground facilities. Other required Safe Work Permits have been issued (Confined Space, Hot Work, LOTO, etc.) Precautions have been taken to prevent contact with overhead power lines New non-metallic underground facilities are being installed with tracers All personnel involved in the excavation have received the appropriate training Risk has been assessed and provisions have been made to address unattended open excavations to ensure the safety of other contractors, the public, wildlife, etc. B) Daily Inspection A competent person must inspect trenches that individuals plan to enter, or could potentially enter as a part of their All trench boxes or shoring must be approved by the manufacturer to be used at the depth they are planned to be used in, for the type of material they are supporting, and must not be modified in any manner that could affect the integrity or safety of these units. Version

48 48 work scope. Trenches will be tested for: resistivity of the soil; porosity of the soil (classification test); crumbling; distance of spoil pile from trench; as well as any shoring/trench box systems. All trench boxes or shoring must be approved by the manufacturer to be used at the depth they are planned to be used in, for the type of material they are supporting, and must not be modified in any manner that could affect the integrity or safety of these units. C) Trench Boxes / Shoring Trench boxes and shoring are protective measures designed to eliminate the likelihood of a trench caving in while personnel are working inside the trench. These methods are required whenever a trench or open excavation requires an employee to work below 4 feet of depth, and proper sloping cannot be established. Trench boxes must extend a minimum of 18 inches above the edge of the trench, on both sides of the trench Lowering Pipe A) Trench Bed Condition The trench bottom shall be free from all rocks, boulders, stones or hard particles when particles, which may damage the pipe walls. The trench bed should maintain the minimum approved depth taking into consideration the contour of the land. Before any pipes or specials are lowered into the trench, they are to be inspected again for deep cuts and scratches described above. The fusion joints should also have cooled sufficiently (specified cooling time for the last joint has elapsed) before stress is imposed on any premade joints. Construction Guidelines When lowering pipe into trenches, care should be taken to avoid scoring of the pipe by contact with the sides and bottom of the trench. Special care is needed when passing under/around obstructions or other utilities. Pipe roller supports for the first four lengths of pipes from the pipe end to be lowered into the trench shall be provided. Cut section of rejected or damaged PE pipes, planks and rope shall be used for protecting the remaining pipes where appropriate, but wire ropes or chains shall not be used. B) Trench Bed Material Trench bottoms shall be layered with well-graded earth that is free from stones or hard particles larger that may damage pipe. Under no circumstances shall hot bending, in any form, be allowed on site. A distance of one foot from obstructions and other services must be maintained for the length of the pipeline. The pipe shall be kept as central as possible within the trench to enable correct side-fill compaction. Some snaking to compensate for thermal expansion of the pipe is acceptable. Pipes and fittings to be embedded in concrete shall be firmly held in position and protected from damage during pouring or compaction by a heavy-duty polyethylene sheet. Should any pipe or specials become either partially or wholly clogged before final acceptance of work, it shall be cleaned out or replaced by the contractor at his own expense. After laying the interior of pipes or specials shall be carefully cleaned to

49 Section 4 remove any debris, dirt, stones or other matter that may have entered during installation. Except when work is proceeding, all open ends of pipes and specials in the trench shall be kept closed by means of a fine wire gauge, wooden stopper or other approved means to prevent the entry of dirt, soil, stones and the like, but still allow the entry of water. C) Inspection & Testing Inspectors must look for deep cuts or scratches that gouge deeper than 10% of the pipe wall thickness. The depth of these gouges should be measured with approved depth gauges of suitable accuracy supplied or approved by OMS personnel. All damaged or flawed sections of pipe will be cut out and removed to the satisfaction of the Oasis representative before jointing according to OMS Section Welding A) General 1.A) Contractors are responsible for adhering to welding specifications and guidelines set out by ASME B B) Hot Work Permits must be completed by contractors when any hot work is performed on behalf of OMS. B) Requirements Joint design, materials, procedures and practices shall be in accordance with the latest edition of API standard 1104, Standard for welding pipelines and related facilities, ASME code B3 1.8, Gas Transmission and Distribution Piping Systems and all applicable DOT regulations. Version 1.1 C) Method Shielded metal-arc welding shall be used for all manual welding. Gas metal-arc and submerged metal-arc welding may be used with prior approval from Oasis. Back-up rings are prohibited. D) Line Pipe Weld Procedures 1. Requirements With manual, shielded metal-arc butt welds, pipe with a wall thickness ¼ inch and less shall have three weld beads. Four or more beads shall be used on pipe having a thickness greater than ¼ inch. Two welders will be used to run the stringer bead on pipe 12 inches O.D. and larger. The second bead, or hot pass, shall be applied immediately after the stringer bead. Hot passes shall be completed up to and including the last completed stringer bead whenever the stringer welding is stopped for any reason and at the end of the day s work. No two succeeding passes shall start or stop at the same point. All beads are to be made by starting the pass near the top of the pipe and proceeding downward on each side of the pipe to the bottom. On any land-laid section of line not more than an interval of 25 joints shall separate the hot pass welding and the filler and cap welding processes. This interval may be reduced by Oasis inspector if conditions warrant. Before the end of the day, all cap welding shall be complete. 2. Qualifications Prior to the start of production a detailed procedure shall be established 49

50 and verified to demonstrate that welds having suitable mechanical properties and soundness can be accomplished by this procedure. The quality of the welds shall be determined by testing with the destructive tests described below. 3. Records The details of each qualified procedure shall be recorded and maintained on approved forms. This record shall show complete results of the procedure qualification tests. Similar records shall be made for all weld methods employed whether in field or shop construction. Strict compliance with these procedures shall be required during construction except where a change is specifically authorized by Oasis and its qualification recorded. 4. Procedure Specifications Contractor is responsible for maintaining specific welding procedures and welder qualifications as outlined in ASME B 31.8., however, Oasis may at times accept other standards that are equal to or more stringent than ASME B Line Pipe Welder Qualification Welders must pass all required verification tests in order to weld any OMS DOT, or other line. 6. Qualification Test Contractor shall provide only competent, skilled and qualified welders. Each welder shall be required to pass satisfactorily a test in accordance with ASME B 31.8 for each of the procedures to which he will be assigned, before being allowed to weld on the line. Oasis welding inspectors or designated qualified representatives, other than an employee of the contractor, shall witness the tests and judge the specimens. A report form describing each of the procedures and the results of each test shall be completed for each welder and submitted to the Oasis. A welder is disqualified at any time during the test if his performance is judged unsatisfactory by an Oasis inspector. 7. Equipment Contractor shall furnish all welding equipment, prepare all spools used in testing and shall bear all cost in connection with the test other than the cost of the pipe, which will be furnished by OMS. Test welds will be accomplished and the weld quality tested in accordance with ASME B 31.8, unless otherwise specified. An Oasis approved pulling machine for tensile tests will be furnished by contractor with certified gauge and calibration dates and tests. 8. Preparation For Welding Line Pipe 8.A) Welding Surfaces Welding surfaces must be thoroughly cleaned so as to be dry and free from paint, oil, rust, scale, and any other material detrimental to weld quality. Each bead shall be ground or buffed before any following weld passes are made. 8.B) Alignment 8.B.1) Joints The ends of pipe to pipe or fitting to pipe joints shall be aligned as accurately as practicable in consideration of 50 Construction Guidelines

51 Section 4 the commercial tolerances on pipe diameters, wall thickness and out-ofroundness. Methods of alignment to provide the proper size and deposition of stringer beads shall comply API standard 1104, except as noted below: Internal line-up clamps shall be used for all welded joints on pipe sizes 12-inch and larger, or where specified by Oasis, except on tie-in and other prohibitive joints. Internal line-up clamps shall be left in place until the stringer bead has been 1003 completed, unless otherwise approved by company welding inspector. External line-up clamps shall be left in place until a minimum of 503 of the stringer bead, which shall be equally spaced, has been completed. Spacing tools shall be used in conjunction with the line-up clamp to assure proper joint spacing and to permit full weld penetration. When external clamps are used, all tack welds shall be ground to ensure complete stringer bead continuity. All slag cavities, surface porosity, cold laps, starts and stops, and high points shall be removed by grinding. All slag and remaining flux shall be buffed with a power buffer between passes. 8.B.2) Rotation Of Seams Electric resistance welded pipe shall be aligned so that the longitudinal seams will be located on either side of the line within 30 degrees of horizontal. Successive joints of pipe shall be rotated to the right or left not less than 20 degrees, or have the seam located on the opposite side to avoid aligning seams on adjacent joints. Longitudinal seams on pipe bends, however, shall be located 90 degrees from the radius of the bend. On bends requiring more than one joint of pipe, longitudinal seams shall be located 180 degrees from each other. 8.C) Weather Welding areas must be protected from conditions that would impair the quality of the completed weld. At times this may require constructing a barrier wall or enclosure (provided with adequate ventilation) to protect the welds from adverse weather conditions. 8.D) Materials And Equipment For Welding 8.D.1) Electrodes - Rod or Wire Electrodes shall be in size and kind suitable for the material being welded and acceptable to Oasis. They shall conform to API standard D.2) Shielding Gases Shall conform to API standard D.3) Handling & Storage Welding electrodes must be protected from all forms of deterioration prior to actual use. Bectrodes and fluxes, which show any sign of damage or deterioration, shall not be used. Any welding materials condemned by Oasis welding inspector shall be promptly removed from the job site and disposed of according to contractors waste management procedures. Version

52 8.E) Equipment 8.E.1) Machines Welding machines shall be operated at the approximate voltage and current ranges recommended for each type of electrode used and shall not be operated beyond their rated capacity. Generating sets and/or automatic or semiautomatic welding machines shall be maintained in good working order and equipment that does not meet OMS requirements must be either repaired or replaced. 8.E.2) Leads The ground leads of welding machines shall be fastened securely to the pipe metal by means of clamps or other mechanical means (not by welding). No arcing between the ground leads and the pipe will be permitted and any leads with insulation damaged to the extent that wire is exposed shall be discarded. 8.F) Inspection & Testing of Line Pipe Welds 8.F.1) Non-Destructive Testing All completed weld surfaces and surrounding areas shall be cleaned and excessive spatter must be removed prior to welding inspection. Radiographic Inspection All field welds must have a radiographic inspection completed for 10% of the weld. A larger percentage up to and including 10% of the field welds may be inspected at OMS discretion. A minimum of 10% of all field welds made within railroad or public highway ROW, river and stream crossing rights-of-way, above ground piping, and at tie-ins will be inspected for 10% of the weld. The contractor may be required to provide transportation to the job site and along the ROW as well as to provide space at the work location for equipment and personnel. Leads Magnetic particle, ultrasonic, or other non-destructive test methods may be utilized at OMS discretion. Defects All welds or portions of welds disclosed by radiographic inspection to be defective will be repaired in accordance with API 1104 at contractor s expense. Welds which are found to be defective by OMS inspectors will be cut out and tested in the method described in section 8.H of this manual. 8.G) Visual Inspection Completed welds must be visually inspected and marked as acceptable by OMS inspectors before the joint coating is applied. It will not be deemed satisfactory unless it meets the standards of acceptability and testing requirements as defined in API standard 1104 for welding of pipelines. 8.H) Destructive Tests of Field Welds Contractors will be responsible to cut out any welds as required by Oasis and deliver the sample for testing and examination, and re-weld the pipe. OMS will not require the contractor to cut out more than one non defective weld per welder without reimbursing contractor, 52 Construction Guidelines

53 Section 4 regardless of whether the weld was cut out because of the results of nondestructive testing methods (other than radiographic), visual inspection or other reasons. Coupons cut from test welds shall be pulled for tensile strength by an OMS approved pulling machine, furnished by contractor. Welds may be further tested by cutting additional coupons for bend tests and nickbreak tests and the ductility and grain structure of the welded metal examined. Contractors will replace all defective welds and one non-defective weld per welder at their expense. A record of the results of each test shall be jointly signed by an Oasis representative and the contractor. 8.I) Weld Identification Oasis shall assign a specific number to each contractor welder. It shall be the duty of each welder to personally affix such number with a permanent waterproof felt or paint marker, adjacent to each weld on which he works for future identification. In the event any welder leaves the project, his number will be voided and not duplicated when another welder is utilized. If radiographic or physical tests indicate the production of defective welds, the welder responsible shall be disqualified from further welding on the project. Should two or more welders participate in making the defective welds, the contractor, welding foreman and OMS inspector shall determine which welder was responsible for the defective work. 8.J) Replacement of Test Welds or Rejected Welds When welding the line together at places where welds have been removed, if possible, one weld shall be made after moving the line back into position; otherwise two welds shall be made by installing a spool with the minimum length of 1½ times the pipe diameter. 8.K) Repair of Weld Defects Weld defects, other than cracks, may be repaired if the weld was not previously repaired if authorized by an OMS inspector. Such defects shall be removed by grinding to clean, sound metal before re-welding and shown by radiographic inspection to be free of defects before acceptance. Should laminations, split end or longitudinal seam defects be discovered in the pipe, the full joint containing the defect shall be removed from the line. 8.L) Standard of Acceptability Minimum acceptable standards for penetration, fusion, burned-through areas, slag inclusion, gas pockets, discontinuities and undercutting shall be in accordance with API standard 1104, and ASME code. 8.M) Arc Burns Contractor shall prevent arc burns. Arc burns, where they occur, shall be cut out at contractor s expense. 8.N) Preheating & Stress Relieving 8.M.1) General Practices The welding procedure shall specify the preheating and stress relieving practices to be followed when materials or weather conditions make either or both necessary. Version

54 8.O) Preheating When the weld procedures and/or carbon content or the carbon equivalent of the pipe requires preheating, or the ambient temperature is 40 F or less, the weld zone shall be preheated to an appropriate uniform temperature. The hot pass shall be made no longer than five minutes after the stringer bead and before the weld joint is cooled to below 200 F. The preheating temperature shall be accurately tested to assure that the by Oasis and shall be accomplished in accordance with the instructions in ASME b 31.8 and the Oasis welding inspector. Butt welds on weld-end valves shall not be stress relieved and in no case shall cold expanded pipe be stress relieved. Oasis will pay for stress relief Boring A) Equipment Requirements Directional boring equipment must have a rig of sufficient capacity to Diagram 4.5A required temperature is obtained prior to and maintained during the welding operation. OMS will pay for preheating required during cold weather. Preheating required by weld procedures will not be paid by Oasis. 8.P) Stress Relief Stress relieving may be designated perform the bore and pull back the pipe, a boring fluid mixing and delivery system of sufficient capacity to successfully complete the crossing, a guidance system to accurately guide boring operations and trained and competent personnel to operate the system. All equipment shall be in good, safe operating condition with sufficient supplies, materials and spare parts on 54 Construction Guidelines

55 Section 4 hand to maintain the system in good working order for the duration of this project. B) Boring System Mud motors shall be of adequate power to turn the required boring tools. It is required that the boring profile is supplied electronically, with operator s Boring rigs must be grounded during boring and pullback operations. 1. Boring Machine The directional boring machine shall consist of a hydraulically powered system to rotate, push and pull hollow drill pipe into the ground at a variable angle while delivering a pressurized fluid mixture to a guidable drill (bore) head. The machine shall be anchored to the ground to withstand the pulling, pushing and rotating pressure required to complete the crossing. The hydraulic power system shall be self-contained with sufficient pressure and volume to power boring operations. Hydraulic system shall be free of leaks. Rigs shall have a system to monitor and record maximum pullback pressure during pullback operations. Boring rigs must be grounded during boring and pullback operations. Sufficient spares shall be kept on hand for any breakdowns, which can be reasonably anticipated. 1.A) Bore Head The bore head shall be guided by changing it s rotation and shall provide the necessary cutting surfaces and boring fluid jets. signature and supplied upon invoice. 1.B) Guidance System The Guidance System shall be of a proven type and shall be set up and operated by personnel trained and experienced with this system. The operator shall be aware of any magnetic anomalies and shall consider such influences in the operation of the guidance system if using a magnetic system. 2. Boring Fluid (Mud) System 2.A) Mixing System A self-contained, closed, boring fluid mixing system shall be of sufficient size to mix and deliver boring fluid composed of Bentonite clay, potable water and appropriate additives. Mixing system shall be able to molecularly shear individual Bentonite particles from the dry powder to avoid clumping and ensure thorough mixing. Mixing system shall continually agitate the boring fluid during boring operations. 2.B) Boring Fluids Version

56 Drilling fluid shall be composed of clean water and an appropriate additive. Water shall be from a clean source with a ph of Water of a lower ph or with excessive calcium shall be treated with the appropriate amount of sodium carbonate or equal. Water and additives shall be mixed thoroughly and be absent of any clumps or clods. No hazardous additives may be used. Boring fluid shall be maintained at a viscosity sufficient to suspend cuttings and maintain the integrity of bore wall. 3. Delivery System The mud pumping system shall have the drill pipe. Connections between the pump and drill pipe shall be relatively leak-free. If fluid is anticipated to leave the ROW, it is recommended that contractors utilize containment methods. Used boring fluid and boring fluid spilled during boring operations shall be contained and properly disposed of. Berms constructed a minimum of 1 foot high, shall be maintained around boring equipment, boring fluid mixing system, entry and exit pits, and boring fluid recycling system (if used) to prevent spills into the surrounding environment. Pumps and or vacuum truck(s) of sufficient size shall be in place to convey excess boring fluid from containment Diagram 4.5B a gallon per minute (GPM) capacity equal to the hole size and be capable of delivering the boring fluid at a constant minimum pressure of the same. The delivery system shall have filters in line to prevent solids from being pumped into areas to storage facilities. 4. Pipe Rollers Pipe rollers, if required, shall be of sufficient size to fully support the weight 56 Construction Guidelines

OASIS PETROLEUM NORTH AMERICA LLC OASIS WELL SERVICES LLC. Contractor Environmental, Health and Safety (EHS) Requirements

OASIS PETROLEUM NORTH AMERICA LLC OASIS WELL SERVICES LLC. Contractor Environmental, Health and Safety (EHS) Requirements March 8, 2012 OASIS PETROLEUM NORTH AMERICA LLC OASIS WELL SERVICES LLC Contractor Environmental, Health and Safety (EHS) Requirements March 2012 March 8, 2012 OASIS PETROLEUM NORTH AMERICA LLC OASIS WELL

More information

XXVI. Contractor Safety & Environmental Guidelines (For General Contractors and Sub-Contractors)

XXVI. Contractor Safety & Environmental Guidelines (For General Contractors and Sub-Contractors) XXVI. Contractor Safety & Environmental Guidelines (For General Contractors and Sub-Contractors) 1. PURPOSE 1.1 This procedure highlights minimum safe working practices required for all contractors working

More information

Site Specific Safety Plans (SSSP)

Site Specific Safety Plans (SSSP) 1.0 SCOPE/PURPOSE 1.1 The guidelines in this document provide a minimum framework for the development of a Site- Specific Safety Plan. They are not meant to supersede or replace regulatory requirements,

More information

MMM MASONRY, INC. Employee Safety Guidelines

MMM MASONRY, INC. Employee Safety Guidelines MMM MASONRY, INC. Employee Safety Guidelines This manual represents common hazards associated with masonry construction and is no way intended to replace the OSHA 29CFR 1926 Safety Standards. It is the

More information

Roles & Responsibilities

Roles & Responsibilities Roles & Responsibilities Table of Contents Roles and Responsibilities... 2 Corporate Management, Total Energy Services Inc... 2 President/ CEO... 2 VP Legal & General Counsel... 2 Vice President, Operations...

More information

Rocky Top Materials, Inc.

Rocky Top Materials, Inc. Rocky Top Materials, Inc. 2707 John Deere Dr. Knoxville, TN 37917 (865) 522-0060 1806 Middlecreek Rd. Pigeon Forge, TN 37863 (865) 453-3723 Disclaimer: This document contains brief descriptions of Rocky

More information

Environmental, Health and Safety Policy for Contractors

Environmental, Health and Safety Policy for Contractors Environmental, Health and Safety Policy for Contractors The attached policy is a tool to help contractors understand and comply with RBC's Environmental, Health and Safety rules. The information that follows

More information

2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS

2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS 2014 SAFETY ECELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below

More information

GUELPH WATER RECLAMATION HEALTH, SAFETY AND SECTION GUELPH, ON. EMERGENCY PROCEDURES PAGE 1 PROJECT NO

GUELPH WATER RECLAMATION HEALTH, SAFETY AND SECTION GUELPH, ON. EMERGENCY PROCEDURES PAGE 1 PROJECT NO GUELPH, ON. EMERGENCY PROCEDURES PAGE 1 DIVISION 01 - GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS.1 The Instructions to Bidders, the General Conditions of CCDC 2-1994, Supplementary

More information

2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT

2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT 2014 SAFETY ECELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below Average 1 =

More information

Contractor EHS Program Attachments

Contractor EHS Program Attachments Contractor EHS Program Attachments Contractor Environmental Health & Safety Program Safety Work Permit Attachments Attachment 1- Contractor Safety Work Permit The Contractor Safety Work Permit Checklist

More information

SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS)

SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS) Title: Subcontractor Control Document Effective Date: 2/3/2012 Control Number: THG_0007 Revision Number: 1 Date: 10/6/2015 Annual Review Completed: 5/13/2015 CONTENTS SUBCONTRACTOR SAFETY, HEALTH, AND

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy Policy statement Brunk is committed to meeting our health and safety goals for all processes, and to maintaining a safe and healthy workplace. It is Brunk s policy to provide a

More information

2013 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT

2013 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT 2013 SAFETY ECELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below Average 1 =

More information

CHEMICAL CONTRACTORS DC WATER CONTRACTOR SAFETY PROGRAM CONTRACT PROVISIONS FOR CHEMICAL DELIVERIES 1. RESPONSIBILITY FOR COMPLIANCE

CHEMICAL CONTRACTORS DC WATER CONTRACTOR SAFETY PROGRAM CONTRACT PROVISIONS FOR CHEMICAL DELIVERIES 1. RESPONSIBILITY FOR COMPLIANCE ATTACHMENT D: SAFETY PLAN REQUIREMENTS FOR CHEMICAL CONTRACTORS 1. RESPONSIBILITY FOR COMPLIANCE DC WATER CONTRACTOR SAFETY PROGRAM CONTRACT PROVISIONS FOR CHEMICAL DELIVERIES A. The contractor shall comply

More information

ENVIRONMENT, HEALTH AND SAFETY (EHS) REQUIREMENTS FOR SERVICE PROVIDERS

ENVIRONMENT, HEALTH AND SAFETY (EHS) REQUIREMENTS FOR SERVICE PROVIDERS Page: 1 of 6 ENVIRONMENT, HEALTH AND SAFETY (EHS) REQUIREMENTS FOR SERVICE PROVIDERS Seller is required to provide a safe and healthy job site for its employees, subcontractors, Buyer's employees, and

More information

It is the goal of Hyperion safety to provide all of your needs from one source. From Onsite personnel, to

It is the goal of Hyperion safety to provide all of your needs from one source. From Onsite personnel, to Capabilities & Services Journey to a Safer Tomorrow It is the goal of Hyperion safety to provide all of your needs from one source. From Onsite personnel, to equipment, to auditing, to SEMS compliance,

More information

Effective Date: 10-January Table of Contents

Effective Date: 10-January Table of Contents Version: 3 Page: 1 of 8 Table of Contents 1.0 Introduction... 2 1.1 Purpose... 2 1.2 Scope... 2 1.3 Definitions... 2 1.4 Responsibilities... 2 Environmental Health and Safety Office (EHSO) and Emory Healthcare

More information

Personal Protective Equipment (PPE) Safety Program

Personal Protective Equipment (PPE) Safety Program Personal Protective Equipment (PPE) Safety Program ENVIRONMENTAL HEALTH & SAFETY pg. 1 Table of Contents A. Introduction And Purpose... 4 B. Background... 4 C. Policy... 4 D. Personal Protective Equipment

More information

Ras Al Khaima Investment Authority LLC

Ras Al Khaima Investment Authority LLC HSE Manual Ras Al Khaima Investment Authority LLC 00/00/2017 1 Contents 1. Definitions... 3 2. Purpose... 3 3. Scope... 4 4. Health and Safety Policy Statement of Intent... 4 5. HSE Rules... 7 6. HSE system

More information

This document sets out the rules applicable to all contract companies and their personnel when working on a CF Fertilisers UK Limited (CF) site.

This document sets out the rules applicable to all contract companies and their personnel when working on a CF Fertilisers UK Limited (CF) site. CONTRACTOR EHS REQUIREMENTS FOR ON-SITE WORK Issued by:: EHS Page No: Issue No: Issue Date: Authorised By: Review date: 1 of 8 3 July 2016 N Cook July 2020 1. INTRODUCTION This document sets out the rules

More information

HAZARD COMMUNICATION PROGRAM YOUR-RIGHT-KNOW CFR

HAZARD COMMUNICATION PROGRAM YOUR-RIGHT-KNOW CFR HAZARD COMMUNICATION PROGRAM YOUR-RIGHT-KNOW CFR 29 1910.1200 0 TABLE OF CONTENTS OUR COMMITMENT...1 PURPOSE...2 INTRODUCTION...2 RESPONSIBILITIES...2 Management, Shipping / Receiving, Safety Representative,

More information

Employee Safety Training Program

Employee Safety Training Program Employee Safety Training Program Line of Business: Workers Compensation, General Liability Risk Control Strategy/Key Issues: Employee training to improve job safety knowledge and reduce the number and

More information

St Francis School District Code of Safe Practices

St Francis School District Code of Safe Practices St Francis School District Code of Safe Practices POLICY: The Board of Education directs that all reasonable efforts be made to ensure a safe learning and working environment for the students and employees

More information

1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY

1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY 1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY Purpose and Applicability The purpose of this Program is to ensure that Imhoff Custom Services Inc. employees who operate aerial or scissor lifts have the

More information

Project Safety Orientation and Procedures

Project Safety Orientation and Procedures www.oakmaninc.com Project Safety Orientation and Procedures Compliance with Project Procedures Oakman believes that sites under our control must be as safe as we can make them not only for our employees,

More information

CAL/OSHA ELECTRICAL HIGH VOLTAGE

CAL/OSHA ELECTRICAL HIGH VOLTAGE Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to electrical exposure to high voltage for employees and contractors

More information

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities CONTRACTOR SAFETY PROGRAM PURPOSE: The Contractor Safety Program (CSP) establishes that contractors are required to work in compliance with legislation, regulations and the Town of Caledon health and safety

More information

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No PART 1 GENERAL 1.1 RELATED DOCUMENTS REQUIREMENTS COMMON TO ALL WORK CATEGORIES 1. Drawings and general provisions of the Contract, including General Special Conditions and other Division 1 Specification

More information

SUBCONTRACTOR MANAGEMENT PLAN

SUBCONTRACTOR MANAGEMENT PLAN SUBCONTRACTOR MANAGEMENT PLAN Purpose The purpose of this program is to improve subcontractor health, safety and environmental performance and establish a standard for pre-qualification, evaluation/selection

More information

Cover Page / Revision Status

Cover Page / Revision Status EFFECTIVE DATE: April 4, 2011 REVISION: 1 Page 1 of 18 Cover Page / Revision Status Rev Date Description 0 4/4/11 Original Issue signed 1 4/4/14 Revisions to contractor roles and responsibilities. Revisions

More information

I. Introduction/Welcome to MAPP

I. Introduction/Welcome to MAPP I. Introduction/Welcome to MAPP II. Company Policy HSE POLICY It is the commitment of MAPP to perform ALL work in the safest manner possible, while maintaining the highest level of construction practices.

More information

FORKLIFT AND INDUSTRIAL TRUCKS SAFETY PROGRAM

FORKLIFT AND INDUSTRIAL TRUCKS SAFETY PROGRAM TRUCKS SAFETY 1. PURPOSE Establish requirements and procedures for the safe operation and use of Powered Industrial Trucks. 2. SCOPE To all D&D TECH SYSTEMS, INC. employees who operate a Powered Industrial

More information

SECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1

SECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1 SECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1 It is our company s policy to perform its work in the safest manner possible, consistent with safe work practices, and according to all governing laws

More information

SUBCONTRACTOR MANAGEMENT PLAN

SUBCONTRACTOR MANAGEMENT PLAN Doc : SMP Revision. 0 Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 10 Purpose The purpose of this program is to improve subcontractor health, safety and environmental

More information

Contractor / Subcontractors Work Plan

Contractor / Subcontractors Work Plan Document: FMW-585 Revision: 8 Date: January 11. 2013 EMS CONTROL PROCEDURE REV: 8 Page 1 of 20 REV DATE DETAILS Page Para. DESCRIPTION OF CHANGE 0 01/19/2007 All All Original Issue 1 02/22/2007 2 All visitors,

More information

Chemical Hygiene Plan

Chemical Hygiene Plan Chemical Hygiene Plan RIM of the World Unified School District 27315 North Bay Road Blue Jay, CA 92352 (909) 336-4100 July 2016 Safety and Risk Management Department RIM of the World Unified School District

More information

Excavation Monitoring and Observation

Excavation Monitoring and Observation Purpose Reference Appendices Related Toolbox Topics This document contains items to consider when developing a process to monitor or observe excavation activity after a one-call ticket has been analyzed

More information

HEALTH AND SAFETY MANUAL

HEALTH AND SAFETY MANUAL 1 Purpose/Scope: HEALTH AND SAFETY MANUAL Title: Powered Industrial Trucks, (Forklifts) Approved by: Greg Savoy Rev. 4/1/08 The purpose of this program is to establish requirements for the safe operation

More information

GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM

GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM NAHB Builder s Show Orlando, Florida February 2008 Leon Rogers President Construction Management Associates, LLC PO Box 867 Thayne, WY 83127 (801) 310-0035

More information

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision 1. Intent This program has been developed to reduce the risk of physical injury or property

More information

INTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol

INTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol INTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol For The International Cyanide Management Code www.cyanidecode.org December 2016 The International Cyanide Management

More information

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name:

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name: Appendix C Hazard Assessment and Trench Entry and Authorization Form for regularly scheduled and emergency trenching activities Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

Scaffolding. Safety Guide. STOP! Before you climb

Scaffolding. Safety Guide. STOP! Before you climb Scaffolding Safety Guide Printed FEB 2015 rebr. AUG 2016 Contents Safety Guide Disclaimer... 1 Safety Guide Objectives... 2 Roles & Responsibilities of Workplace Parties Employers, Supervisors, Workers...

More information

TITLE: CONTRACTOR SAFETY. Safety Procedures and Policies. Issuing Authority: Multi-Color Corporation, Page Number: 1 of 5. Date Effective: 4/1/2011

TITLE: CONTRACTOR SAFETY. Safety Procedures and Policies. Issuing Authority: Multi-Color Corporation, Page Number: 1 of 5. Date Effective: 4/1/2011 Page Number: 1 of 5 1.0 SCOPE Safety in the plant is concerned with more than just the Multi-Color associate. All outside contractors must also follow specific guidelines and rules for safe conduct while

More information

SUBCONTRACTOR MANAGEMENT

SUBCONTRACTOR MANAGEMENT Doc : Revision. 0 Preparation: Safety Mgr Authority: Director Issuing Dept: Safety Page: Page 1 of 9 Purpose The purpose of this program is to ensure that ANC Foster continues to improve subcontractor

More information

1.0 GENERAL REQUIREMENTS: 1.1 Scope of work:

1.0 GENERAL REQUIREMENTS: 1.1 Scope of work: Page 6 of 20 1.0 GENERAL REQUIREMENTS: 1.1 Scope of work: 1.1.1 Work includes, but is not limited to, providing all labor, consumable materials (rags, etc), tools, equipment, service trucks, man-lifts,

More information

Contractor EHS Program Attachments

Contractor EHS Program Attachments Procedure: HS210 DONNELLEY FINANCIAL SOLUTIONS - Version: 3.3 Att Page 1 of 21 Contractor Environmental Health & Safety Program Attachments Date:12/04/2009 Contractor EHS Program Attachments Download:

More information

STANDARD OPERATING PROCEDURES-Water Transfer

STANDARD OPERATING PROCEDURES-Water Transfer SOP WT-16 (MAR 2014) STANDARD OPERATING PROCEDURES-Water Transfer Large Diameter Poly Operations Section 1.0 Introduction and Background Rockwater Energy Solutions, Inc. (and all its affiliated and subsidiary

More information

SAMPLE PAGES. Construction Safety and Health Program. [Company name]

SAMPLE PAGES. Construction Safety and Health Program. [Company name] The safety and health of our employees is our top priority. Everyone goes home safe and healthy every day. Construction Safety and Health Program [Company name] [Date Authorized] [Version} 0 Contents Mission

More information

BAY CITIES PAVING & GRADING, INC

BAY CITIES PAVING & GRADING, INC BAY CITIES PAVING & GRADING, INC 1450 CIVIC CT., BLDG. B # 400, CONCORD, CA 94520 925-687-6666 FX: 925-687-2122 CODE OF SAFE PRACTICES EMPLOYEE RESPONSIBILITIES SAFETY STATEMENT SAFETY POLICY STATEMENT

More information

THE UNIVERSITY OF THE WEST INDIES Mona Campus Human Resource Management Division (HRMD) SECTION I GENERAL SAFETY

THE UNIVERSITY OF THE WEST INDIES Mona Campus Human Resource Management Division (HRMD) SECTION I GENERAL SAFETY EOHS 01-016 Housekeeping Introduction Purpose Attention to general cleanliness, storage and housekeeping can prevent numerous accidents. This policy covers items not discussed in other areas and is not

More information

MVDC F041 Safety Inspection Checklist

MVDC F041 Safety Inspection Checklist MVDC F041 Safety Inspection Checklist JOB TITLE: DEPARTMENT: JOB NO.: DATE: LEGEND 1 Satisfactory 2 Requires Improvement 3 Non Existent 4 Not Applicable EMERGENCY PREPAREDNESS Emergency procedure is posted

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY SECTION 1. GENERAL POLICY STATEMENT: Director Responsible for Safety: A.C. Appleton The Director responsible for safety will ensure the adoption and maintenance of proper standards of safety, health and

More information

JOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised:

JOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised: Table of Contents 1.0 Applicability...2 2.0 Scope...2 3.0 Definitions...2 4.0 Core Information and Requirements...2 5.0 Roles and Responsibilities...6 6.0 Goals, Objectives and Performance Measures...7

More information

Document Revision Change Table Revision Number

Document Revision Change Table Revision Number Beaumont Site Procedure No.: BMEHS-002.025 Reviewed: 01/17 Page: 1 of 7 Document Revision Change Table Revision Number Revision Description Revised By Revision Date Rev. 03 Considered as starting document

More information

WHITMAN COLLEGE TRENCHING AND SHORING PLAN

WHITMAN COLLEGE TRENCHING AND SHORING PLAN Purpose: WHITMAN COLLEGE TRENCHING AND SHORING PLAN This is a statement of official college policy to establish the process for compliance with safety standards as stated in the Washington State Administrative

More information

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS All gas yard lines shall be installed, repaired or replaced in accordance with the standards and specifications herein and in accordance with the rules and regulations as set forth in the city s OQ, and

More information

3.0 Crane Heavy Lift Service General Requirements

3.0 Crane Heavy Lift Service General Requirements 3.0 Crane Heavy Lift Service General Requirements 3.1 Scope of Work: Under the direction of the GPA Representative, contractor s work includes, but is not limited to, providing supervision, materials (if

More information

HAZARD IDENTIFICATION AND ASSESSMENT

HAZARD IDENTIFICATION AND ASSESSMENT Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose To provide guidelines for identifying, assessing and controlling workplace hazards; To ensure the potential hazards

More information

OUTLAW AUTOMATION INC. Safety Management System

OUTLAW AUTOMATION INC. Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 Purpose The purpose of this program is to provide employees general information for working on owner client or other

More information

Team Building Volunteer Manual

Team Building Volunteer Manual Team Building Volunteer Manual 2018 Edition Welcome to Habitat for Humanity Manitoba! Thank you for choosing to volunteer your time with Habitat for Humanity Manitoba! As a new or returning volunteer to

More information

SAFETY RULES AND ENFORCEMENT

SAFETY RULES AND ENFORCEMENT SAFETY RULES AND ENFORCEMENT Steingass Mechanical Contracting, Inc. 754 Progress Drive Medina, Ohio 44256 (330) 725-6090 SAFETY RULES AND ENFORCEMENT Effective incident prevention includes eliminating

More information

HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd

HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd Company Trading Address 242 Fort Austin Avenue Crownhill Plymouth PL6 5NZ Tel: 01752 657227 Fax: 01752 657227 Email: enquiries@jmc-sw.com

More information

Brian Moore. All Contractors. Regarding: Contractor Safety Introduction Letter and Packet. To Whom It May Concern:

Brian Moore. All Contractors. Regarding: Contractor Safety Introduction Letter and Packet. To Whom It May Concern: To: All Contractors Regarding: Contractor Safety Introduction Letter and Packet To Whom It May Concern: Platte River Power Authority (Platte River) and the Safety Department are pleased that you are interested

More information

Fall Protection Plan for Construction

Fall Protection Plan for Construction Safety & Health Program 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 Fall Protection Plan for Construction OSHA currently regulates fall protection for construction

More information

EM385 Construction Safety and Health Certification Course Section 14 Material Handling, Storage, and Disposal

EM385 Construction Safety and Health Certification Course Section 14 Material Handling, Storage, and Disposal EM385 Construction Safety and Health Certification Course Section 14 Material Handling, Storage, and Disposal OSHAcademy Course 502 Study Guide EM 385 SAFETY AND HEALTH CERTIFICATION COURSE - SECTION 14

More information

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10 Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors Northeast Utilities Safety 12/10 How Electric Utilities Work Plan the Work & Work the Plan! Agenda Introduction

More information

Written Safety and Health Program

Written Safety and Health Program Written Safety and Health Program For XYZ Company Required for all Hawaii Businesses with 25 or More Employees Incorporates Provisions of Hawaii Administrative Rules Title 12, Subtitle 8, Part 2, Chapter

More information

STANDARD PRACTICE INSTRUCTION

STANDARD PRACTICE INSTRUCTION STANDARD PRACTICE INSTRUCTION DATE: March 1, 2001 SUBJECT: Scaffolding Safety Program. REGULATORY STANDARDS: 29 CFR 1910.28 Safety Requirements For Scaffolding. 29 CFR 1910.29 Manually Propelled Mobile

More information

MAINTENANCE WORKER 1 JOB DESCRIPTION

MAINTENANCE WORKER 1 JOB DESCRIPTION MAINTENANCE WORKER 1 JOB DESCRIPTION GENERAL DESCRIPTION Under supervision, an employee of this classification performs semi-skilled, skilled, and manual labor including operation of dump trucks, semi-tractor

More information

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Plumbing - 220000 Without limiting the application of all of the Contract Documents to the Subcontract,

More information

Reliant Holdings Ltd Safety Management System

Reliant Holdings Ltd Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to falls from elevated work areas and ensure employees

More information

Safety & Environmental Orientation Program for Contractors

Safety & Environmental Orientation Program for Contractors Transmission Group Safety & Environmental Orientation Program for Contractors Applies To Eversource Connecticut, Western Massachusetts, and New Hampshire 1 Agenda Introduction ES Contractor Work Rules

More information

Injury & Illness Prevention Program

Injury & Illness Prevention Program Injury & Illness Prevention Program Be Safe! All employees are to ensure that safe and healthful conditions and practices are provided and followed within the area under their control. POLICY OBJECTIVES

More information

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep):

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep): ABN 39 137 318 873 Unit 2, 36 Lidco St Arndell Park NSW 2148 QAC swms2 Phone: 1300 121 544 Fax 1300 078 877 Safe Work Method Statement SWMS No: 1 Revision Date: 14/4/16 Approved by (Snr Management Rep):

More information

Radiation Safety Manual

Radiation Safety Manual University of California, Merced Environment, Health and Safety Radiation Safety Manual Approved by: Signature: Title: Date: TABLE OF CONTENTS 1. ORGANIZATION AND RESPONSIBILITIES 1.1 POLICY 1.2 RADIATION

More information

MICHIGAN DEPARTMENT OF NATURAL RESOURCES DRAFT FINAL Forest Certification Work Instruction

MICHIGAN DEPARTMENT OF NATURAL RESOURCES DRAFT FINAL Forest Certification Work Instruction MICHIGAN DEPARTMENT OF NATURAL RESOURCES DRAFT FINAL Forest Certification Work Instruction Date of Draft Document: Effective Date: 6-29-07 Revision Number: 3 Supersedes Version Dated: February 7, 2006

More information

Risk Control at United Fire Group

Risk Control at United Fire Group INTRODUCTION work can be a very hazardous exposure to employees and other contractors on construction job sites. is one of the most hazardous construction operations. The most feared hazard is excavation

More information

Employees receive OSHA Safety training - on-demand any time and at their own pace.

Employees receive OSHA Safety training - on-demand any time and at their own pace. OSHA Safety Evolve e-learning delivers online courses to ensure your employees have the knowledge and skills to work safely and protect your organization from reportable injuries and lost worktime at a

More information

Most Commonly Misunderstood Standards for Oil and Gas Industry

Most Commonly Misunderstood Standards for Oil and Gas Industry Most Commonly Misunderstood Standards for Oil and Gas Industry Presented by: Dale Robinson HR Safety Consulting, LLC Erie, Colorado 80516 www.hrsafety.com Like us on Facebook at: HR Safety Consulting,

More information

Safe Management of Contractors Policy

Safe Management of Contractors Policy Safe Management of Contractors Policy Stour Federation Stour Federation Safe Management of Contractors, Page 1 1.! INTRODUCTION 1.1! Shipston-on-Stour Primary School and Acorns Primary School accept the

More information

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment.

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment. Fall Protection Plan for Construction OSHA currently regulates fall protection for construction under Part 1926, Subpart M. The standards for regulating fall protection systems and procedures are intended

More information

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 1.0 PURPOSE To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 2.0 BACKGROUND Excavation activities are highly dangerous and thus require adequate planning

More information

192GasCatalog.

192GasCatalog. 192GasCatalog www.energyu.org www.midwestenergy.org 192-Abnormal Operating Conditions... 4 192-0101 Characteristics and Hazards of Natural Gas... 4 192-0201 Gas Detection and Alarm System Maintenance...

More information

240- POWERED INDUSTRIAL TRUCKS

240- POWERED INDUSTRIAL TRUCKS 240.1 PURPOSE A. To establish safe operation and use of Powered Industrial Trucks (PIT s). 240.2 SCOPE A. This program applies to all Central New Mexico Community College (CNM) employees who operate a

More information

TABLE OF CONTENTS. NiCon Terminal HS&E

TABLE OF CONTENTS. NiCon Terminal HS&E This Terminal Safety Plan outlines many of the safety policies and processes utilized at the NiCon Terminal. Additional safety rules and policies may be introduced or utilized by ARB Midstream, or the

More information

MATERIAL HANDLING, STORAGE, AND DISPOSAL

MATERIAL HANDLING, STORAGE, AND DISPOSAL SECTION 14 MATERIAL HANDLING, STORAGE, AND DISPOSAL 14.A MATERIAL HANDLING 14.A.01 Employees shall be trained in and shall use safe lifting techniques. 14.A.02 Requirements for PPE are covered in Section

More information

Guidelines for Transloading Polymeric Methylene Diphenyl Diisocyanate (pmdi)

Guidelines for Transloading Polymeric Methylene Diphenyl Diisocyanate (pmdi) Guidelines for Transloading Polymeric Methylene Diphenyl Diisocyanate (pmdi) Table of Contents AX-409 July 2015 Introduction... 1 Facility Considerations... 2 Facility Management Considerations... 2 Security

More information

HEALTH & SAFETY POLICY

HEALTH & SAFETY POLICY 1. Policy Statement CONTENTS 1. Policy Statement 2. Responsibilities 3. In Practice 3.1 Risk Assessments 3.2 COSHH 3.3 PPE 3.4 Safety Training 3.5 Accident Procedure 3.6 Emergency Procedure 3.7 Site Audits

More information

HEALTH AND SAFETY CONTRACT BETWEEN EMPLOYER AND MANDATORY (CONTRACTOR) SECTION 37(2) OF THE OHS ACT, ACT 85 OF 1993

HEALTH AND SAFETY CONTRACT BETWEEN EMPLOYER AND MANDATORY (CONTRACTOR) SECTION 37(2) OF THE OHS ACT, ACT 85 OF 1993 P a g e 1 SUBJECT ISSUED BY APPROVED BY CONTRACT CONTRACT BETWEEN EMPLOYER AND MANDATORY SAFETY MANAGER: SUN CITY RESORT DIRECTOR OF OPERATIONS PAGE 1 OF 15 EFFECTIVE: REVISION NO: 1 HEALTH AND SAFETY

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

ECCS Information Form

ECCS Information Form ECCS Information Form Date: EXHIBIT A Company Name: Form Completed By: Address: E-Mail Address: City, State and Zip Code Federal Tax ID #: Company Contact: List Work Codes Here: (Refer to Type of Work

More information

M.B. Power Services (Essex) Ltd

M.B. Power Services (Essex) Ltd M.B. Power Services (Essex) Ltd HEALTH & SAFETY POLICY 1 POLICY STATEMENT The company recognises that under the Health & Safety at Work Act 1974 the Company has a legal duty to ensure so far as is reasonably

More information

Contractor and Supplier Expectations

Contractor and Supplier Expectations Contractor and Supplier Expectations GUI/1548 Issue 15 Page 1 of 10 16 September 2016 Contents 1. INTRODUCTION AND SCOPE 3 2. RICARDO ENERGY & ENVIRONMENT POLICIES 3 3. SUSTAINABILITY 4 4. MANAGEMENT OF

More information

Safety Approach. September 2016

Safety Approach. September 2016 Safety Approach The San Francisco Public Utilities Commission (SFPUC) Construction Safety Approach applies to all personnel and companies contracted to work on any Project related to SFPUC Capital Improvement

More information

Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017

Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017 Marshall Municipal Utilities EXCAVATIONS AND TRENCHING Effective August 1, 2011 Revised August 17, 2017 POLICY This policy applies to all open excavations and trenches; including those excavations and

More information

Scaffolding Procedures

Scaffolding Procedures Procedures Purpose It is the purpose of this company in issuing these procedures to further ensure a safe workplace based on the following formal, written procedures for scaffold work. Application This

More information

SUBCONTRACTOR SAFETY PRE-QUALIFICATION FORM

SUBCONTRACTOR SAFETY PRE-QUALIFICATION FORM SUBCONTRACTOR SAFETY PRE-QUALIFICATION FORM GENERAL INFORMATION 1. Subcontractor Information Subcontractor Name: Street Address: Telephone Number: Fax Number: City: Website Address: State: Zip Code: 2.

More information