1.0 EXECUTIVE SUMMARY

Size: px
Start display at page:

Download "1.0 EXECUTIVE SUMMARY"

Transcription

1 1.0 EXECUTIVE SUMMARY 1.1 Campus Program Summary There are five (5) projects in pre-design and programming; four (4) are in design; and five (5) in construction. A summary of the Trade-Tech construction projects is given below: Projects in Construction Phase Projected Cost (Million) 1. "A" Building Restoration and Modernization $ Learning Assistance Center / Library Renovation $ Campus-Wide Information Technology Upgrade $ Campus-Wide Improvements Phase 3 $ East Parking Structure $ Total Projected Project Cost $ A-Building Restoration and Modernization project is 99% complete. The contractor is working on final punchlist items and revisions of Operation and Maintenance and Warranty manuals scheduled to be completed by January 30, Notice-of-Completion is expected to go to the Board for Approval in April The Learning Assistance Center work has progressed to 95% complete. Construction team continues working to resolve issues in an effort to meet schedule milestones. The substantial completion date is targeted for mid-february CPM is working with the Campus to coordinate FF&E procurement and staff move-in schedules. This building is on track to be occupied in June The upgrade of the Campus-Wide Information Technology systems is in progress. Deployment of the wireless network and emergency notification systems is approximately 90% complete. All critical buildings are operational. Redundant fiber network has been completed. Storage and Disaster Recovery systems are 85% complete; deployment and failover testing is scheduled for Spring Break 2013, at which point all components of the project will be complete. The Campus-Wide Improvements Phase 3 design-build project consists of fourteen (14) subprojects, eight (8) of which are non-dsa. The Notice to Proceed was issued to KPRS Construction Services on August 23, 2011 and is 40% complete. Substantial Completion is projected on September 1, The East Parking Structure design-build project is under contract to Bernard s Brothers, Inc. The Notice to proceed was issued on November 15, Construction for this Gold LEED project started in September The contractor is now working on foundations. Completion of construction is projected on or before fall Page 1 of 5

2 1.2 Program Highlights / Key Milestones This section is intended to provide program highlights and key milestones relative to each active project. Pre-Design / Program Phase Upgrade West Campus Main Electrical Distribution System This project will provide a new electrical distribution system on the west side campus. The CPM will recommend to the Program Manager that this project be bundled with other related site infrastructure projects. A meeting was held with LACCD Executive Director of Facilities on December 18, 2012 to discuss the planned projects, as well as project delivery method. North Quad Site Development / Grand Avenue Enhancement / Blue Line Station Extension The programming architect has completed the development of a landscape master plan which was adopted by the College. The plan identified dedicated open spaces, pedestrian walkways, landscape plans and planting palette, site furniture and site lighting. The consultant futher identified a Phase 1 scope of work which could be implemented within the budget available. The Phase 1 scope is one of the projects proposed to be bundled with the other site infrastructure projects that was discussed in the December 18, 2012 meeting mentioned above. The LACCD Director s approval is expected in mid-. Design Phase ADA Transition and Barrier Removal The Architect of Record, PBWS Architects, continues to incorporate final pre-dsa review comments, including District Auto CAD Standards and structural elements for Maintenance and Operations requirements. Final construction documents are anticipated to be submitted to DSA in February Performing Arts Center (work for seismic upgrade and building weather closure) Construction documents are recently complete and are being reviewed by Campus and CPM. Architect s cost estimate is being reviewed by CPM. East Campus Substation and Recycle Center The East Campus Substation and Recycle Center has achieved 100% design development level. The design will be submitted to the LACCD Board of Trustees for approval on January 30, The final design package is scheduled to be submitted to DSA in April 2013, including coordination with LADWP design. Page 2 of 5

3 DSA Review Phase Construction Technology Building (CTB) This Gold LEED design-build project is under contract to Bernard s Brothers, Inc. The Notice to proceed was issued on November 15, The 95% Construction Document design package is expected to be approved and released by DSA on or before March 15, The CTB Increment 1 work started on December 17, 2012, with the start of the balance of abatement and demolition of existing structures. Earthwork and grading will start following completion of the demolition. Structural construction work is projected to start in March Final completion of the project is scheduled for the winter Construction Phase East Parking Structure This Gold LEED design-build project is under contract to Bernard s Brothers, Inc. The The East Parking Structure started construction in September The contractor is working on foundations in Areas 3 and 4. Level 1 column work and masonry work are in progress. DWP U-Permit #1 work continues with the electrical duct bank on 23rd Street. Completion of construction is projected on or before fall A Building Restoration and Modernization This Silver LEED project is under contract to USS Cal Builders, Inc. and 99% complete. The contractor is working on final punchlist items and revisions of Operation and Maintenance and Warranty manuals scheduled to be completed by January 30, Notice-of-Completion is expected to go to the Board for Approval in April Learning Assistance Center / Library This Silver LEED project is under contract to Suffolk Construction. The work has progressed to 95% complete. Construction team continues working to resolve issues in an effort to meet schedule milestones. The substantial completion is forecast for mid- February Contractor is behind the original schedule by about three weeks. CPM is working with FF&E and the Campus to coordinate furniture procurement and staff move-in schedules. This building is on track to be occupied in June Campus-Wide Information Technology Upgrade The upgrade of the Campus-Wide Information Technology Upgrade project is in progress. Deployment of the wireless network and emergency notification systems is approximately 90% complete. All critical buildings are operational. Redundant fiber network has been completed. Storage and disaster recovery systems are 85% complete. Deployment and failover testing is scheduled for Spring Break 2013, at which point all components of the project will be complete. Campus-Wide Improvements Phase 3 This design-build project is under contract to KPRS Construction Services and is 40% complete. Final completion is projected in March Following is the status of subprojects: Page 3 of 5

4 Completed Non-DSA Projects o Waterproofing at Building F Ramp o South LRC Parking Lot o Room A-100 Splicing o Locking WAP Devices o IDF Remediation Non-DSA Projects in Construction o Cabling/Conduit installation for wireless access points to be completed in January 2013 o Cabling/Conduit installation for IP speakers to be completed in o Security System Upgrades are expected to be completed in o Fiber pull work to begin approximately winter break Projects submitted for DSA review o East Campus Entrance - Approved o Building D Catwalk Approved, construction to start 01/9/13 o Fire Lane Approved, construction to start summer 2013 o Building G Exhaust Approved, construction to start summer 2013 o Welding Shop Remodel Approved, construction to start summer 2013 o Campus Wide Signage Submitted for approval Contract Close-out Phase Child Development Center This Silver LEED design-bid-build project is under contract to Morillo Brothers, Inc. The building is completed and occupied as of September The Settlement and Mutual Release Agreement for the Contractor s Claim was executed in September Projects in Moratorium Culinary Arts A single building will be designed to include the Culinary Arts and Fashion Arts. PBWS Architects was selected and approved by the Board to develop programming and design critera for the new building. Programming is expected to be completed in April Site feasibility studies are currently underway. Fashion and Fine Arts Building (aka) Design and Media Arts The Design and Media Arts building is the only Trade Tech project remaining in moratorium, however it will be released upon completion with programming and validation with the District criteria. PBWS Architects is proceeding with programming concurrent the new Culinary Building. Page 4 of 5

5 1.4 Look Ahead (next 90 days) The following events are scheduled or targeted to occur in the next 90 days Final completion of the Silver LEED A Building Restoration and Modernization project is projected in early April Metal siding, curtain wall systems, hardscape around building, and interior finishes for the Learning Assistance Center project will be completed. The following Non-DSA subprojects under Campus-Wide Improvements Phase 3 are projected to start construction: - Building D Catwalk to begin construction in - Building G Exhaust to start construction in June 2013 Construction work will continue on the East Parking Structure. Construction on Increment 1 at the CTB will continue. Structural foundation work at the CTB will start in March Solicitation of bids for a design architect for the Grand Avenue Enhancement and Blue Line Extension landscaping. Continue programming at the Culinary building Initiate architectural work on the demolition for Building C, E and R Issue task order to architect for North Quad design Start campus signage work Page 5 of 5

Perimeter Site Improvements

Perimeter Site Improvements Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff

More information

Manage Deliverables - Construction Step 6 February 2015

Manage Deliverables - Construction Step 6 February 2015 Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection

More information

Monthly Progress Report November 1, 2011

Monthly Progress Report November 1, 2011 LOS ANGELES MISSION COLLEGE PROPOSITION A/AA BOND PROGRAM & PROPOSITION J BOND PROGRAM Monthly Progress Report November 1, 2011 Health & PE Fitness Center Lobby Page 1 of 14 THIS PAGE IS LEFT INTENTIONALLY

More information

M $336M .73 S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS A BETTER WAY TO BUILD. YEARS OF CONSTRUCTION SERVICES DESIGN-BUILD PROJECTS

M $336M .73 S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS A BETTER WAY TO BUILD. YEARS OF CONSTRUCTION SERVICES DESIGN-BUILD PROJECTS A BETTER WAY TO BUILD. S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS Our team of construction professionals has more than 30 years of building experience in New England. We pride ourselves on the personal

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

Master RFI List: March 22, 2013 Version # 1, 2 & 3

Master RFI List: March 22, 2013 Version # 1, 2 & 3 Master RFI List: March 22, 2013 Version # 1, 2 & 3 1. Can the City confirm the completion and occupancy dates for the Main Street Garage (February 2003?) and Transit Center Garage facilities? Main Street

More information

Projects Currently in Planning, Design and Construction. April 12, 2017

Projects Currently in Planning, Design and Construction. April 12, 2017 Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

East Los Angeles College Project Priority List Occupancy Date

East Los Angeles College Project Priority List Occupancy Date East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media

More information

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018 Question & Answer: #1 The RFP calls for a survey of the building to gain a comprehensive understanding of the existing building, utilities, building systems, occupancies and all existing conditions as

More information

LIFE OF A CAPITAL PROJECT

LIFE OF A CAPITAL PROJECT LIFE OF A CAPITAL PROJECT CAPITAL ASSET STRATEGIES (CAS) ARCHITECTS AND ENGINEERS (A&E) 5/4/2017 EARLY STEPS OF A MAJOR CAPITAL PROJECT (>$750,000) Scoping & Feasibility Project sponsor and campus leadership

More information

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation

More information

Office of Planning, Design and Construction. Capital Program Update May 10, 2017

Office of Planning, Design and Construction. Capital Program Update May 10, 2017 Office of Planning, Design and Construction Capital Program Update May 10, 2017 Projects Under Construction Translational Research Center Translational Research Center Phase I Site work Status: Completed

More information

Facilities Management Project Delivery Model - Process Map - v

Facilities Management Project Delivery Model - Process Map - v Project Delivery Model - Process Map - v8.0-2016-05-25 Overview PLANNING DESIGN IMPLEMENTATION CLOSE OUT Project Identification Initiation Page 2 Project Planning Page 3 Schematic Design / Design Development

More information

Office of Planning, Design and Construction. Capital Program Update April 10, 2017

Office of Planning, Design and Construction. Capital Program Update April 10, 2017 Office of Planning, Design and Construction Capital Program Update April 10, 2017 Projects Under Construction Translational Research Center Translational Research Center Phase I Site work Completed - June

More information

JASPER SHARED SCHOOL FACILITY

JASPER SHARED SCHOOL FACILITY JASPER SHARED SCHOOL FACILITY A BRIDGING PERSPECTIVE Robert Rabinovitch M.Arch., Architect, AAA, SAA, MRAIC History Jasper Junior / Senior High School Originally constructed in 1952 with additions in 1958,

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

RFQ WEB Advertisement

RFQ WEB Advertisement 165 Capitol Avenue, Hartford, CT 06106 Selection Type: Request for Qualifications (RFQ) Web Advertisement Construction Manager at Risk Adv. No.: Web Advertisement Date: July 18, 2008 General Statement:

More information

MANHATTAN COLLEGE STUDENT COMMONS

MANHATTAN COLLEGE STUDENT COMMONS MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2 OMAHA BASEBALL STADIUM May 21, 2009 Report No. 2 METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

Project Brief. Royal Columbian Hospital Redevelopment Project Phase One

Project Brief. Royal Columbian Hospital Redevelopment Project Phase One Royal Columbian Hospital Redevelopment Project Phase One Page i TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Purpose of this... 1 2 THE BUSINESS OPPORTUNITY... 2 3 FRASER HEALTH AUTHORITY... 4 4 THE PROJECT...

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Office. RdM s confidence and apparent interest in our business operation proved to be real. They became knowledgable

Office. RdM s confidence and apparent interest in our business operation proved to be real. They became knowledgable RdM s confidence and apparent interest in our business operation proved to be real. Office They became knowledgable about how our people interacted internally and made educated alternative suggestions

More information

Annual Announcement (January 1 to December 31, 2017)

Annual Announcement (January 1 to December 31, 2017) Annual Announcement (January 1 to December 31, 2017) This annual announcement is intended to result in the identification of persons and firms which are interested in pursuing contracts to perform the

More information

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California.

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California. REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE SPARTAN COMPLEX SEISMIC UPGRADE PROJECT SAN JOSE STATE UNIVERSITY ONE WASHINGTON SQUARE, SAN JOSE, CA 95192-0010 The Trustees of

More information

EJ Industrial Spine BOA Nomination Study

EJ Industrial Spine BOA Nomination Study A. Selecting Priority Sites Section V. Redevelopment of Priority Sites Section IV of this Nomination Study presents a summary of the analyses of the Study Area and market conditions affecting the E-J BOA

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES 1 of 15 CS & ASSOCIATES EXPERIENCE & BACKGROUND Established in 2003 by Charla Curtis, Former LCP Director for LAUSD Certified MBE/

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services...

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services... EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services...A-1 B. Pre-Design and Start-Up Services...A-3 1. Project Initiation...A-3 2. Development of Architectural Program...A-4

More information

The Columbus Regional Airport Authority (CRAA) hereby issues addenda to the subject solicitation:

The Columbus Regional Airport Authority (CRAA) hereby issues addenda to the subject solicitation: February 13, 2015 NOTICE OF ADDENDUM ADDENDUM #4 Subject: Date Due: Wireless System Design and Replacement; Request For Proposals (RFP) # FIT-2015-001 February 23, 2015 at 2:00 PM EDT Dear Sir or Madam:

More information

University of Illinois Business Instructional Facility LEED Gold Design. University of Illinois. University of Illinois

University of Illinois Business Instructional Facility LEED Gold Design. University of Illinois. University of Illinois Keys to success: Sustainable design strategies included early. Clear and early benchmarking choice. Integrated design process. Consensus building. Keys to success: Sustainable design strategies considered

More information

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN. CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS AUBURN. GARDEN OF MEMORY AUBURN MEMORIAL STUDENT AFFAIRS HOLCOMBE NORTON PARTNERS LANDSCAPE SERVICES The Auburn Memorial wall includes excerpts from the Auburn

More information

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No. SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall

More information

FACILITIES DESIGN STANDARDS

FACILITIES DESIGN STANDARDS FACILITIES DESIGN STANDARDS 7th Edition June 21, 2016 Use only the most current copy of these Design Standards. Most current Edition including revisions can be found at the MnSCU Facilities website. http://www.finance.mnscu.edu/facilities/design-construction/resources.html

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

STEP TWO, Tradewinds Park North Equestrian Farm Site Improvements R P2

STEP TWO, Tradewinds Park North Equestrian Farm Site Improvements R P2 1- Project Team Design Solution: A) Provide a DESIGN SOLUTION that addresses the vision OVERALL CONCEPT PLANNING AND BASE PROGRAM SCOPE OF WORK for the Project. Specifically describe how the Proposal addresses

More information

Code Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617)

Code Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) Code Requirements for Existing Buildings R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS) was established in 1945 and currently

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Why Do I Need A Project Manager / Owner s Representative For My New Library Project?

Why Do I Need A Project Manager / Owner s Representative For My New Library Project? Why Do I Need A Project Manager / Owner s Representative For My New Library Project? 111 SW Columbia Street Suite 830 Portland, OR 97201 Tel: 503-225-1120 Fax: 503-224-3226 www.hillintl.com A Project Manager/Owner

More information

Addendum #02 New County Office Building Responses to RFP Questions

Addendum #02 New County Office Building Responses to RFP Questions Sam Lin Manager Project Development Unit 1402 Maple Street Redwood City, CA 94063 650-369-4766 September 22, 2017 slin@smcgov.org Addendum #02 New County Office Building Responses to RFP Questions To All

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

Annual Announcement (January 1 to December 31, 2018)

Annual Announcement (January 1 to December 31, 2018) Annual Announcement (January 1 to December 31, 2018) This annual announcement is intended to result in the identification of persons and firms which are interested in pursuing contracts to perform the

More information

Report For Class D Construction Cost Estimate

Report For Class D Construction Cost Estimate Report For Class D Construction Cost Estimate Douglas McNeill Director Jon Gilford Senior Cost Manager Turner & Townsend 170 Laurier Avenue West Suite 604 Ottawa Ontario K1P 5V5 t: +1 (613) 221 9560 e:

More information

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-

More information

APPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects

APPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects PROVINCE OF NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND INFRASTRUCTURE RENEWAL DTIR Document DC350 APPENDICES DESIGN REQUIREMENTS Appendix A Performance Criteria for Design Projects 2010 EDITION Printed

More information

Science Technology Engineering and Mathematics (STEM) Initiative

Science Technology Engineering and Mathematics (STEM) Initiative DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and

More information

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register

More information

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents

More information

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017 UCSF Mission Bay & Dogpatch Construction Community Meeting Agenda Welcome Project Communications Construction Context Project Updates Minnesota Housing Center for Vision Neuroscience Precision Cancer Medicine

More information

POSITION DESCRIPTION June 16, 2017

POSITION DESCRIPTION June 16, 2017 POSITION DESCRIPTION June 16, 2017 Common Name: Classification: Team / Section: Bureau / Division: ROOFING / BUILDING ENVELOPE PROJECT MANAGER ENGINEERING SPECIALIST MANAGEMENT Project Delivery Services

More information

CAMBRIDGE PUBLIC LIBRARY

CAMBRIDGE PUBLIC LIBRARY PROJECT Cambridge, MA SIZE Total: 103,900 sqft Addition: 76,700 sqft Renovation: 27,200 sqft CLIENT City of Cambridge ARCHITECT WILLIAM RAWN ASSOCIATES ASSOCIATE ARCHITECT ANN BEHA ARCHITECTS LANDSCAPE

More information

Box Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments

Box Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments Box Clever Consulting Executive Summary Project Report July 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 05/08/17 Strand Plaza - Liverpool Status Report @ End of

More information

Design Guidelines & Standards Manual

Design Guidelines & Standards Manual Updated: 10/31/2011 Volumes I-III Divisions 1-48 SAN DIEGO COMMUNITY COLLEGE DISTRICT Design Guidelines & Standards Manual CITY COLLEGE MESA COLLEGE MIRAMAR COLLEGE CONTINUING EDUCATION Campus Facilities

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

Project Delivery Method

Project Delivery Method Project Delivery Method Presenters San Diego Community College District Facilities Management Lance Lareau District Architect UC Berkeley graduate 30 years of architecture experience 2 nd generation architect

More information

Managing Schedule Change

Managing Schedule Change Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change

More information

ARCHITECTURAL EXPANSION JOINT PRE-INSTALLATION INSPECTION

ARCHITECTURAL EXPANSION JOINT PRE-INSTALLATION INSPECTION Date Project Name Location (city/state) Project Address Installer: Architect /Engineering Firm: General Contractor: Your Name: Contact Person: Contact Person: Phone: Phone: Phone: Mobile: Mobile: Mobile

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

Arlington Independent School District Board of Trustees Communication

Arlington Independent School District Board of Trustees Communication Arlington Independent School District Board of Trustees Communication Meeting Date: September 21, 2017 Consent Item Subject: Bids Purpose: To provide the Board of Trustees the opportunity to review the

More information

Building Information Modeling (BIM) Execution Plan

Building Information Modeling (BIM) Execution Plan 10/19/2017 for [Stanford Project Name] [Stanford Project Number] Developed by [Primary A/E] TABLE OF CONTENTS USE OF THE BIM EXECUTION PLAN... 3 1. PROJECT INFORMATION... 3 2. PROJECT SCHEDULE AND MILESTONES...

More information

Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits

Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits 1 Cornell Rolling Counter Fire Doors Earning LEED v4 Credits Cornell Rolling Counter Fire Doors can provide a significant

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

Attachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #

Attachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone # UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial

More information

CALGreen Building Codes Mandatory Provisions Overview

CALGreen Building Codes Mandatory Provisions Overview CALGreen Building Codes Mandatory Provisions Overview Summary provided courtesy of Green Building in Alameda County www.buildgreennow.org CALGreen Title 24, Part 11 (Green Building Standards) Developed

More information

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017 1107 E. Madison Street Student Housing Project Monthly Update May 12, 2017 Anticipated Completion: Fall 2018 About the Project: This newly constructed building will be ten stories providing eight floors

More information

The designer shall also submit additional information required by the University as described and underlined below.

The designer shall also submit additional information required by the University as described and underlined below. I. Structural Engineering Submissions The designer shall submit all information required by the State Construction Office (SCO) as described in the State Construction Manual Chapter 300 - Project Design

More information

Consolidating Systems for a Greener Future:

Consolidating Systems for a Greener Future: FEATURE Consolidating Systems for a Greener Future: Trinity University s thermal utility upgrade Bradley A. Pankow, PE, Principal Engineer and Project Manager, Stanley Consultants; and Jesse Cabrera, PE,

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

SECTION ALUMINUM WINDOWS

SECTION ALUMINUM WINDOWS SECTION 08520 ALUMINUM WINDOWS PART 1 - GENERAL 1.01 SUMMARY A. Section includes: 1. Storefront systems and aluminum framed glass doors. 2. Hardware, fasteners, accessories, filler pieces, etc., required

More information

Section SoundPly LR M25 Acoustic Ceiling Panels

Section SoundPly LR M25 Acoustic Ceiling Panels Section 095126 Acoustic Ceiling Panels PART 1 GENERAL 1.1 RELATED DOCUMENTS 1.2 SUMMARY A. Drawings and general conditions of the Contract, including General and Supplementary Conditions and Division 1

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Creative Performing Media Arts Middle School

Creative Performing Media Arts Middle School Dawne St Kilkee St Enelra Pl Creative Performing Media Arts Middle School 5050 Conrad Ave. San Diego, CA 92117 Sub-district: A Cluster: Madison Year School Opened: 2002 Grades: 6-8 Arlene Pl 3 2 Conrad

More information

Aviation Capital Construction Program Update

Aviation Capital Construction Program Update Aviation Capital Construction Program Update 2012 Completed Projects 2013 Active Projects Bern Seals Program Manager Parsons Management Consultants April 2013 0 Discussion Agenda Program Safety Performance

More information

building new horizons

building new horizons building new horizons www.tektondevelopment.com UNIQUE INSIGHT SMARTER CONSTRUCTION Tekton Development has been a leader in delivering quality construction projects throughout New Jersey and Eastern Pennsylvania.

More information

ARCHITECTURE & PLANNING INTRODUCTIONS

ARCHITECTURE & PLANNING INTRODUCTIONS YOO ARCHITECTURE & PLANNING INTRODUCTIONS Page 1 INTRODUCTION YOO is a world leading branded design company founded by the world s most celebrated designer, Philippe Starck and international property entrepreneur

More information

Ongoing and Future Project Work. Construction Management

Ongoing and Future Project Work. Construction Management Ongoing and Future Project Work New Broward County Courthouse Tower 1,000 Car Courthouse Garage Midrise Building Renovations 714,000 square foot, 20-story Civil/Family Courthouse replacing 1950 s era

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

FUTURE BOND PROGRAM PROPOSED PROJECTS Summary Report. September 2013

FUTURE BOND PROGRAM PROPOSED PROJECTS Summary Report. September 2013 Project Summary and Total Project Cost NEW CONSTRUCTION PROJECTS A. Campus Center Replacement $ 29,474,691 B. East Campus Classroom and Office Building(s) $ 34,674,804 C. Wake Center Replacement $ 40,051,128

More information

GREEN BUILDINGS Risks and Rewards

GREEN BUILDINGS Risks and Rewards GREEN BUILDINGS Risks and Rewards Mark Lucuik, P.Eng., LEED AP, Morrison Hershfield October 14, 2010 Agenda Green Buildings LEED Intro Risks 2 What is a Green Building? Radical Design? Natural Materials?

More information

What happened to Division 17? and what is CLA? A Strategic Plan for Communications, Life Safety and Building Automation Systems

What happened to Division 17? and what is CLA? A Strategic Plan for Communications, Life Safety and Building Automation Systems What happened to Division 17? and what is CLA? A Strategic Plan for Communications, Life Safety and Building Automation Systems Discussion Points History of MasterFormat and CLA CLA Consultant What BICSI

More information

DESIGN DEVELOPMENT PHASE

DESIGN DEVELOPMENT PHASE UNIVERSITY OF MICHIGAN DESIGN DELIVERABLES FEBRUARY 2012 As part of the deliverables for formal UM review at each of the major phases of design listed below, the Design Professional shall submit this "Design

More information

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E.

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E. The courthouse exterior. Courtesy of NLA/HLM Architects. United States Courthouse Sacramento, Robert D. McCartney, S.E. CA Modern Steel Construction / November 2001 Public entrances to courtrooms occur

More information

ACEC/MA 15th Annual State Markets Conference

ACEC/MA 15th Annual State Markets Conference University of Massachusetts Building Authority ACEC/MA 15th Annual State Markets Conference April 6, 2017 1 University of Massachusetts Building Authority General Overview 2 Designer Procurement Process

More information

Construction Project Briefing

Construction Project Briefing Construction Project Briefing August 12, 2009 CHICAGO TRANSIT AUTHORITY Today s Presentation Brown Line Capacity Expansion Project Subway Escalators Project Dearborn Subway Tie Replacement Project Systemwide

More information

All Plan Holders 3/3/

All Plan Holders 3/3/ All Plan Holders 3/3/2017 14-044 Marina Middle School Window Replacement and Seismic Retrofit 5 Window Replacement and Seismic Retrofit 11 DSA No. 01-116273 San Francisco Unified School District 16 SFUSD

More information

HQ Building Renovation. Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO

HQ Building Renovation. Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO HQ Building Renovation Mark Focht, President Nancy Somerville, EVP Michael O Brien, CFO Agenda Roll Call Introduction Presentation of Design Concepts and Cost Estimate Financing Options and Recommendation

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

SLC Terminal Redevelopment Program. Salt Lake City International Airport

SLC Terminal Redevelopment Program. Salt Lake City International Airport SLC Terminal Redevelopment Program Salt Lake City International Airport Terminal Redevelopment Program Goals and Expectations Address Seismic Risk Provide Right-Sized Facilities Solve Operational Problems

More information

Management. Construction. Development. WE PROVIDE A complete roster of building services to streamline the construction process

Management. Construction. Development. WE PROVIDE A complete roster of building services to streamline the construction process WE ARE: We are a family-owned construction company providing construction services to general contractors and real estate owners throughout the San Francisco Bay Area. Founded in 2001, Argo Construction

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

APPENDIX 6 (not yet reviewed by UCCS) STRUCTURAL ANALYSIS/VIBRATION CRITERIA

APPENDIX 6 (not yet reviewed by UCCS) STRUCTURAL ANALYSIS/VIBRATION CRITERIA APPENDIX 6 (not yet reviewed by UCCS) STRUCTURAL ANALYSIS/VIBRATION CRITERIA GENERAL The purpose of this standard is to identify structural submittal requirements, as well as identify vibration design

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5 EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services... A-2 B. Architectural Programming... A-5 1. Project Initiation... A-5 C. Design Services... A-6 1. Schematic Design Phase...

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS DEPARTMENT SUITE 209S - LOGAN OFFICE CENTER ONE HARBORSIDE DRIVE EAST BOSTON, MASSACHUSETTS 02128-2909 REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT

More information