October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:
|
|
- Wilfred Price
- 6 years ago
- Views:
Transcription
1 October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents Oct. 18 th from AH and FSB Will go to the January 2018 RUSO for final project close-out +- $117K withheld from AH contract. Smaller projects continue by Alpha and Housing DINING FACILITY: Start Date: Jan Completion: Fall 2019 Size: TBD Total Project Budget: $19,000,000 Contractor: Lingo Construction (CMR) Architect: ADG Architects Client/ADG/Lingo/AES (Team) bi- weekly meetings continue, next is Nov. 1 st ADG/Lingo presented scope revisions, size, and costs at Team meeting October 18 th Planning of kitchen/food services area is on-going to tighten up the space, program, equipment list and costs Project schedule will be revised when scope and costs are finalized but occupancy and operations will likely be pushed to October/November 2019 Discussion to not begin construction until after NCUR April 4-7, 2018 due to heavy use of HFH to allow for construction on site for late April, 2018 PERFORMING ARTS CENTER: Start Date: TBD Completion: TBD Size: TBD Total Project Budget: TBD Contractor: TBD Architect: City of Edmond with Hornbeek Blatt Steering Committee met twice this past week to review the Consultant Team s feasibility assessment. The team found that there is a need for a 600 to 1000 seat facility. o A 250 seat theater and school of Music is included in both scenarios. Discussions were centered around: o The building program, both shared and dedicated spaces o Potential sites o Business plan 11/28 Presentation to UCO Cabinet: 8:00am 9:30am 1
2 CAMPUS MASTER PLAN: Start Date: Dec Completion: October 2017 Size: NA Total Project Budget: $250,000 Architects: Rees Associates Met with Provost Barthell and Assoc. Provost Simmons (Oct 2) Met with Kevin F (Oct 3) to update and review status Meeting with President (Nov 1 st at 2 pm) Public meetings scheduled mid-november Final meeting to present to UPC (Nov. 10, 2017) 3 campus maps essentially will define proposals for campus growth to include: o Projects completed and or under construction o Project in planning with proposed next identified projects and; o Potential projects as defined in the Capital Master Plan (Legislative Long Range Planning Commission report) Final report completion December 2017 for potential January 26, 2018 RUSO SOUTH CENTRAL PLANT: Start Date: Jul Completion: Early Fall 2017 Size: 6,500 sq ft Total Project Budget: $18,500,000 Contractor: Timberlake Construction & Johnson Controls Engineer: Robert Piland (JCI holds contract) Three major components: (Work for all three is currently underway) $3M building to house the plant equipment - start date: 11/15/16 completion: Fall 17 Work is complete. (excluding minor details to be provided by JCI) $12M chiller plant equipment and controls - start date: 2/24/17 completion: Fall 17 Installation work inside the plant is substantially complete. Testing, balancing, and automation of the system will continue until end of the year. Site repair work and sodding are underway. $3.5M underground piping - Clean-up is scheduled to be complete by Nov. 15 th Final connections to Health & Phys. Ed. Building and Math and Computer Science are underway and will be complete no later than Dec. 31 Mitchell Hall Theater connection to take place spring of NOTE: Remaining Balance of funds will be directed towards the addition of a Central Plant connection north of Ayers, for use by: New Dining Facility, Hamilton Field House, New North Hamilton Annex, & Wantland Stadium. 2
3 STEM TEACHING & RESEARCH CENTER: Start Date: Jan Completion: Fall 2018 Size: 55,000 sq ft Total Project Budget: $24,000,000 Contractor: Lippert Brothers Architect: Elliott + Associates Structural Steel work complete. Mechanical, Electrical, Plumbing, Roofing, Framing, and Masonry work are all underway. AV/IT, Furniture, and Electronic Door Access meetings are on-going. (procurement will occur Spring Semester) Prior to Thanksgiving, Lippert will provide updated schedule. Overall the project is on schedule to meet substantial completion date. LIBERAL ARTS ADDITION: (KT/TD) Start Date: Fall 2017 Completion: Summer 2019 Size: 55,000 sqft Total Project Budget: $18,350,000 Contractor: Lippert Brothers Architect: Beck Design 100% review documents to AEE/AHJ on Oct. 23 rd Project to advertise for bid Oct. 26 th Bid opening Nov. 16 th Site Mobilization, Thanksgiving break Ground breaking ceremony Nov. 29 th Open for classes Fall of 2019 Numerous trees will be relocated to south side of Business over Thanksgiving break. SPORTS PERFORMANCE CENTER: (KT/RH) Start Date: Apr Completion: Fall 2018 Size: 41,000 sq ft Total Project Budget: $14,000,000 Precast concrete panels installation and structural steel work are underway. AV/IT, and Electronic Door Access meetings are on-going as well. (procurement will occur Spring Semester) Studio Architecture is developing options for furniture and equipment; will work with Athletic Department and A&E Services to determine preferred selections. Project is on schedule to meet or beat contractual completion date of Move in to follow, approx. 4-6 weeks. 3
4 NORTH HAMILTON ANNEX: Start Date: Summer 2018 Completion: Fall 2019 Size: 26,000 sqft Total Project Budget: $10,500,000 Design work underway JE Dunn provided schedule: o 03/20/18 100% Bid documents o 03/23/18 04/31/18 Bid and Contract o 05/01/18 to 06/29/18 Building Demo o 07/09/18 Construction Start o Fall 19 Construction Complete TEMPORARY WRESTLING/ HITTING FACILITY Start Date: Summer 2017 Completion: Spring 2018 Size: 8,000 sqft Total Project Budget: TBD JE Dunn provided schedule: o 09/15/17 100% Bid documents o Bids received o 11/01/17 Construction Start o Spring 18 Construction Complete BASEBALL FACILITY Start Date: Fall 2017 End Date: Spring 2018 Total project budget: $2,500,000 Updated cost proposal for phase one expected back from vendor early next week. Phase one work will include new field turf playing surface and outfield wall system. The work is expected to be complete by early spring for the upcoming season. Phase two to include dugouts, press box and locker room. Work to begin early summer. 4
5 TRANSPORTATION AND PARKING: Start Date: Jan. 17 Completion: August 20, 2017 and Late July 2018 Size: NA Total Project Budget TBE Contractor: TBD Architect/Engineer: Dewberry Design/Wallace Engineering Lot 10 Reconfiguration, LOT 14, 15 (Visitor and Event Parking) o Dewberry will begin design modifications for Lot 10 in early Oct for completion January 2018 o Renovations may be done summer 2018 and summer 2019 pending extent of changes o New request from T&P for an engineered review of existing Parking Lot conditions to begin for integration into Parking Committee HFH SEATING REPAIRS Start Date: Spring 2018 End Date: Summer 2018 Total Cost: $200,000 Received quotes from Hussey and Irwin seating vendors to replace North/South seats. Existing units in good condition will be used to replace damaged seats at East/West. HOH GREENHOUSE FABRICATION Start Date: Fall 2017 End Date: Fall 2017 Total Cost: $45,000 New electrical and plumbing services to the building were installed last week. The existing fence was removed and reinstalled last week as required. New concrete foundations for the greenhouse are being poured this week. 5
Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues
February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationStephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018
Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations
More informationGrossmont-Cuyamaca Community College District Facilities Construction Update
Grossmont-Cuyamaca Community College District Facilities Construction Update September 13, 2016 Presented by Penny McGrew Program Manager Gafcon, Inc. Bond Program Update Agenda Districtwide Energy Conservation
More informationBOARD OF TRUSTEES OCTOBER 13, 2014
Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationJanuary 1, 2009 March 31, 2009
January 1, 2009 March 31, 2009 1 G.O. Bond Project Status As of March 31, 2009 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center Remodel
More informationProgram Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement
Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:
More informationUniversity of North Florida BOARD OF TRUSTEES. CAMPUS PLANNING, DESIGN & CONSTRUCTION CAPITAL PROJECTS UPDATE September 27, 2013
Projects included in this report: 1. Science & Humanities Building (Biology) 2. Osprey Café Dining Facility 3. Housing Club House and Pool Facility 4. Greek Village 5. Chick-Fil-A 6. Student Assembly Center
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL
More informationFacilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017
Facilities Maintenance & Operations Update Presidents Executive Cabinet March 6, 2017 1 Update Proposition 39 Year 4: March 6 March 31 Will complete all exterior lighting upgrades to LED Aquatic Center
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As
More informationKRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent
KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent 8353 University Boulevard, Moon Township, PA 15108 Thesis Proposal THIRD REVISION 3/19/2010 Table of Contents Executive
More informationProgram Update. Chino Health Science Parking Lot
Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016
FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements
More informationMONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13
PROPOSITION R PROGRAM UPDATE MONTHLY EXECUTIVE UPDATE MARCH 21, 2013 1 CENTRAL PLANT BOILERS--- COMPRESSORS--- CONDENSERS--- PIPING--- COMMISSIONING PREPARATIONS 2 Central Plant Accomplished in March:
More informationLOVEJOY Independent School District
Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $
More informationREGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS
AUGUST 1, 2018 Contact: John Nash REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS Actions Requested: Consider recommending to the Board approval of the: 1. Project Description
More informationGrossmont-Cuyamaca Community College District Facilities Construction Update
Grossmont-Cuyamaca Community College District Facilities Construction Update April 17, 2018 Presented by Fred Parker Program Manager Gafcon, Inc. Agenda Grossmont College Update Cuyamaca College Update
More informationPIERCE HALL RENOVATION
PIERCE HALL RENOVATION October 2017 Update CNAS Presenters: John White A.V.C, Campus Planning, Capital Asset Strategies (CAS) Jocelyne Nguema Sr. Director of Space Management, Capital Asset Strategies
More informationProjects Currently in Planning, Design and Construction. April 12, 2017
Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space
More informationRequest for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018
Request for Proposal for GC/CM Consultant Services Ferndale School District Secondary High School GC/CM Program October 19, 2018 The Ferndale School District is requesting proposals for project management,
More informationCONSTRUCTION UPDATE. April 2017 THIS IS PROGRESS. THIS IS AUBURN.
CONSTRUCTION UPDATE April THIS IS AUBURN. RISK MANAGEMENT AND SAFETY ADMINISTRATIVE BUILDING RISK MANAGEMENT AND SAFETY SEAY SEAY & LITCHFIELD ARCHITECTS CAM BUILDERS Entrance to the Risk Management and
More informationFacilities Planning & Management
Facilities Planning & Management 1100 North Grand Avenue Walnut, CA 91789 909-274-4850 www.mtsac.edu CONSTRUCTION QUARTERLY UPDATE 9/1/2016 PROJECT MANAGER: Gary Gidcumb / Fernan Siocon September 1, 2016
More informationSchool of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014.
School of Business Project #26290 Overall Project Cost: $26,700,000.00 Architect: Urbahn Scheduled Completion Date: 10/2014 Contractor: N/A Description: This project will construct a new academic building
More informationInstructional Science Facility Phase I
Instructional Science Facility Phase I University of Wisconsin La Crosse Campus August 26, 2015 UWL Science Lab Building Phase 1 1 Project Schedule Timeline July Aug Sept Oct Nov Dec Jan Feb Mar Apr May
More informationPROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project
More informationJuly 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationCapital Project Recommendations Presented to the Board of Education 9/23/2014
Capital Project Recommendations Presented to the Board of Education 9/23/2014 The administration has been working to identify a division of the proposed $15M in capital projects between the athletic field
More informationPROJECT # University of South Carolina, Aiken USCA Convocation Center Shed Aiken, South Carolina ADDENDUM NUMBER
University of South Carolina, Aiken PROJECT #10010.01 SECTION 00911 - ADDENDUM NUMBER 2 PARTICULARS 1.01 DATE: April 10, 2012 1.02 PROJECT: USC AIKEN CONVOCATION CENTER SHED 1.03 STATE PROJECT NUMBER:
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018
FACILITIES COMMITTEE MEETING APRIL 17, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure Johnson Student Center Johnson Demolition Science Center & Building J Demolition
More informationMOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS
MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade
More informationJune 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As
More informationBUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION
I. PURPOSE BUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION To ensure the proper process to request and obtain approval for all renovation or new construction projects within Bucknell
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationColumbia University School of International + Public Affairs Center on Global Energy Policy Project Construction Logistics.
Columbia University School of International + Public Affairs Center on Global Energy Policy Project Construction Logistics February 18, 2015 PRESENTATION SUMMARY OPENING REMARKS + INTRODUCTIONS ABOUT THE
More informationCONSTRUCTION UPDATE November 2018
CONSTRUCTION UPDATE November 2018 The project modified Mell Street starting at Thach Avenue and ending at the Library Service Drive by creating a concourse for pedestrians and bicyclists. Additional improvements
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationMerritt Island High School
Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry
More informationAPPA Chicago August 2015
Facilities Planning, Design & Construction University of North Texas Integrated University Facilities Project Management Process APPA Chicago August 2015 UNT Factoids: 36,000+ students 172 Buildings including
More informationAuburn University Construction Project April
Small Animal Teaching Hospital Phase I: Construction Cost: $8.8 million. Phase I consists of (1) constructing an addition to the Overton-Rudd Auditorium to expand classroom and lecture hall capacity, (2)
More informationACEC/MA 15th Annual State Markets Conference
University of Massachusetts Building Authority ACEC/MA 15th Annual State Markets Conference April 6, 2017 1 University of Massachusetts Building Authority General Overview 2 Designer Procurement Process
More informationRenovations & Addition Carroll County, Kentucky BG RTA 1233 CONTRACT DATE: March 24, 2014 CONTRACT FOR: General Construction
CHANGE ORDER DATE: 7/25/2014 CO #: 04 (FOUR) TO: Marrillia Design and Construction 259 West Short Street, Suite 325 Lexington, KY 40507 PROJECT: Carroll County Middle School Renovations & Addition Carroll
More informationPROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min)
PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min) 1. Commissioning is ongoing and will be completed by September 30, 2014. 2. Graphics for the EMS is complete. CPT to coordinate training
More informationJuly 1 September 30, 2008
July 1 September 30, 2008 1 G.O. Bond Project Status As of September 30, 2008 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center Remodel
More informationFacility Improvements
CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation
More informationCONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE JUNE THIS IS AUBURN. WOODFIELD DRIVE EXTENSION FACILITIES MANAGEMENT ARCHITECT: GOODWYN, MILLS, CAWOOD D&J ENTERPRISES $1.4 APRIL Woodfield Drive entrance from South Donahue Drive.
More informationFACILITIES Summer Projects. September 8, 2015 Board Meeting
FACILITIES 2015 Summer Projects September 8, 2015 Board Meeting On January 27, 2015 the Laguna Beach Unified School District Board of Education approved a 10-year facilities plan. The plan identified numerous
More informationPortsmouth Middle School Additional Funding Request
City Council Work Session Portsmouth Middle School Additional Funding Request Monday March 18, 2013 Project Background School Board selected Parrott Avenue site after lengthy, comprehensive and public
More informationCONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013
April 2013 AUM Projects AU Montgomery New Residence Hall AU Projects AU Recreation and Wellness Center Biggio Drive Parking Facility Biodiversity Learning Center CONSTRUCTION UPDATE AU Montgomery New Residence
More informationFrost Technical Center
Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 13462» Total Man Hours on Project: 268272» Crafts On Project This Week: 17» OSHA Recordable Rate: 0 June 5, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East
More informationBasic renewal/restoration and safety projects
Basic renewal/restoration and safety projects Board Update September 9, 2013 Bond Team Support Team Agenda Program Management Goals Program Budget Status 2013 Project Updates Labor Distribution Study 2014
More informationCapital Improvement Program Monthly Status Report
Projects Upgrades in Multipurpose Building 1300 In order to meet the needs of the building s three distinct uses administrative gatherings, recreational program space, and as a general venue and event
More informationOhlone Community College District
Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More information*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.
SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial
More informationPROJECT UPDATES. Capital Planning and Space Management Office April 2015
PROJECT UPDATES Capital Planning and Space Management Office April 2015 2 Completed Projects Stockton - Chan Family Hall Renovation 3 Chan Family Hall Renovation Audio-visual and security camera work in
More informationHinsdale Township High School District 86 Referendum Project Listing April 2, Approved
Hinsdale Township High School District 86 Referendum Project Listing April 2, 2019 - Approved 1-12-2019 Project Category and Description Central South Total Security Replace Intercom System Install a completely
More informationNew Hall High School Project Summary Report to the Board of Education June 3, 2015
New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete
More informationBusiness Affairs Committee Dobo Recovery Update. February 7, 2019
Business Affairs Committee Dobo Recovery Update February 7, 2019 Dobo Hall Recovery Efforts and Phasing Page 2 Dobo Hall, a 110,000 GSF laboratory facility, was significantly damaged by Hurricane Florence.
More informationMarch 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT
March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationBronx Community College. Five-Year Capital Plan FY through FY
Five-Year Capital Plan FY 2019-20 through FY 2023-24 Projects in priority order / costs in $ thousands Project Name FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 (B) Campus-Wide Fire Alarm Replacement DC
More informationSECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN
SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation
More informationHealth Life Safety Survey and Master Facilities Plan
Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master
More informationUNCW Board of Trustees. Facilities Update. October 27, 2016
UNCW Board of Trustees Facilities Update October 27, 2016 Hurricane Matthew Page 2 UNCW Allied Health Facility Page 3 Budget: $66M Status: Advance Planning in Progress Designer: EYP Architects Advance
More informationFY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT
FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-
More informationSuburbia, USA. Image Courtesy of The Whiting-Turner Contracting Company
Image Courtesy of The Whiting-Turner Contracting Company Penn State AE Senior Capstone Project Nicholas J. Kline Construction Option Advisor Mr. Ray Sowers 3 Water Drainage 2 Exterior 3 Water Drainage
More informationCORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting
CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening
More informationPHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016
PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 1 ACTIVE PROJECTS Santa Ana College Chavez Hall Renovation Temporary Village Phase 2 Santiago Canyon College Orange Education Center
More informationAPSU PROJECT REPORT. Client. Athletics REMAINING BUDGET STATUS. Client. Athletics
APSU PROJECT REPORT 373/003112018 Softball Field Improvements Athletics Rufus Johnson Installation of new foundation, ADA compliant stands and press box for the softball field. CONTRACTED PAID 01Approval\Planning
More informationAnnual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011
Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Annual Report TABLE OF CONTENTS
More informationAndover Schools Facilities Update
Town Facilitlies Garage Andover Schools Facilities Update Andover High School Finance Committee May 9, 2018 West Middle School Collins Center Andover High School Facility Study Committee and Andover School
More informationCultural Facilities: Capital Needs Inventory and Priorities. Arts, Culture and Libraries Committee October 17, 2016
Cultural Facilities: Capital Needs Inventory and Priorities Arts, Culture and Libraries Committee October 17, 2016 Purpose To provide an overview of the buildings managed through the Office of Cultural
More informationMARCH 23 FACILITIES MASTER PLANNING AND OVERSIGHT COMMITTEE Included Materials
Building for Tomorrow s Leaders LACCD Program Management 515 S. Flower Street, Suite 900 Los Angeles, California 90071 www.build-laccd.org 213.593 8000 tel 866.817.1051 fax MARCH 23 FACILITIES MASTER PLANNING
More informationInvitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:
RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:
More informationVoorhees Replacement Facility Schedule Summary Classic WBS Layout 29-Sep-09 13:50 Activity Name Original Start Finish Duration Voorhees Replacement F 1136 17-Nov-06 31-Mar-11 Schematic Design 87 17-Nov-06
More informationDerby Hall. Herrick Archives Number 025 A. IDENTIFICATION & LOCATION
1 of 8 11/18/2008 2:44 PM Herrick Archives Number 025 A. IDENTIFICATION & LOCATION 1. Name 2. Location 1. 1 Officially named "" by Board of Trustees on August 8, 1929, in memory of Samuel Carroll Derby.
More informationUniversity of North Florida BOARD OF TRUSTEES. CAMPUS PLANNING, DESIGN & CONSTRUCTION CAPITAL PROJECTS UPDATE January 18, 2011
Projects included in this report: 1. Founders Hall Renovations 2. Student Wellness and Sports Education Center 3. Science and Humanities Building (Biology) 4. Building 1 Renovations 5. Building 15 First
More informationJMU Capital Projects SWaM Outreach Event Presentations
JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom
More informationLong Term School Funding Program Measure M Component: Citizen s Oversight Committee Report
Moreno Valley Unified School District Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report November 19, 2015 District Long Term School Funding Program Revenue Sources
More informationJackson Miracle Building Plan Outreach Roundtable. February 14, 2017
Jackson Miracle Building Plan Outreach Roundtable February 14, 2017 $1.8 billion Expanded Footprint Improved Patient Experience World-Class Facilities Innovative, Leading-Edge Care A Stronger, More Competitive
More informationPlanned Procurement Opportunities Report. August 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationPlanned Procurement Opportunities Report. August 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationPROJECT UPDATE August 28, 2014
PROJECT UPDATE August 28, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT
More informationState College Area School District Memorial Field Phase 2 Update
State College Area School District Memorial Field Phase 2 Update The State College Area School District Is continuing renovations to its primary outdoor sporting venue, known as Memorial Field. The Design
More informationLANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent
RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural
More informationPROPOSITION R Citizen s Bond Oversight Committee
PROPOSITION R Citizen s Bond Oversight Committee June 15, 2011 Southwestern Community College District 900 Otay Lakes Road, Room L246 Chula Vista, CA 91910 Proposition R AGENDA 1. Call to Order / Roll
More informationPlanned Procurement Opportunities Report. September 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationNorth Allegheny School District
North Allegheny School District January 18, 2017 Preparing all students for success in a changing world NAI was last renovated in 1997 Money was set aside during recent bond issue for renovations to occur
More informationMONTHLY PROGRESS REPORT
MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project 395795» Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East
More informationSemi-Annual Report. January 1, 2012 June 30, 2012
Semi-Annual Report January 1, 2012 June 30, 2012 G.O. Bond Project Status As of June 30, 2012 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student
More informationOrange Education Center Project Update. Board of Trustees Meeting February 25, 2019
Orange Education Center Project Update Board of Trustees Meeting February 25, 2019 1 ORANGE EDUCATION CENTER 2 Topics 1. Need for Adult Education (AE) in Orange 2. Location of AE Center 3. Fiscal Feasibility
More informationBoynton High School & Blackford Site
Boynton High School & Blackford Site Balance (E- D) 980075 Blackford Campus Repairs (Asphalt, Plaster, Complete 100% 07/16/18 10/05/18 $725,367.67 $735,233.50 $352,463.56 -$9,865.83 $382,769.94 4 980066
More informationOctober 1, 2008 December 31, 2008
October 1, 2008 December 31, 2008 1 G.O. Bond Project Status As of December 31, 2008 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center
More informationFacilities Services Newsletter Summer 2012
Facilities Services Newsletter Summer 2012 Facilities Services Spring & Summer Project Update Commencement Completed! Reunion Completed! Language School Setups Completed! Hepburn Water Service - Completed!
More information