CONTRACTOR AND EQUIPMENT ARRIVE ON-SITE

Size: px
Start display at page:

Download "CONTRACTOR AND EQUIPMENT ARRIVE ON-SITE"

Transcription

1 Lesson 5 Inspector CONTRACTOR AND EQUIPMENT ARRIVE ON-SITE Drilled Shaft Installation Plan 5-1 Version 1-1/15 5-1

2 Learning Outcomes Identify and understand the Role and Duties of the Inspector Verify and Inspect On-site Equipment Verify Protection of Existing Structures is implemented Identify the applicable 455 Specifications 5-2 Version 1-1/15 5-2

3 Inspector s Role What is the Inspector s Role? To serve as a representative of the State and ensure the work is performed in accordance with the approved plans and specifications. 5-3 Version 1-1/15 5-3

4 Inspector s Role To know the specifications, both the State Standard Specifications and the job Plans and Specifications. To record and document activity relative to the Plans and Specifications. Raise a red flag soon enough to make a difference if work is performed outside of those specifications. Keep the Project Administrator Informed. Call the Project Administrator if judgment is needed to interpret a Specification. 5-4 Version 1-1/15 5-4

5 Inspector s Role Remember that you are the Department s Representative Do not delay or interfere with the Contractor unnecessarily Remember the Goal- Constructing a project in accordance with the approved documents 5-5 Version 1-1/15 5-5

6 Inspector s Role Keep the Project Administrator Informed Notify the Project Administrator soon enough that appropriate decisions or Corrective Actions can be made or implemented in a timely fashion to reduce the impact to the project schedule, cost or quality. 5-6 Version 1-1/15 5-6

7 Inspector s Role KNOW THE PLANS KNOW THE SPECIFICATIONS 5-7 Version 1-1/15 5-7

8 Inspector s Responsibilities Be a Recorder Make accurate and unbiased observations Document events: complete & consistent Perform your duties promptly Be a Reporter Complete reports & forms accurately Keep forms and diary up-to-date Keep Project Administrator informed 5-8 Version 1-1/15 5-8

9 Communication & Coordination With Project Administrator If interpretation of specifications is required, contact the Project Administrator If work is performed outside of the plans or specifications, contact the Project Administrator For work or items requiring Approval, contact the Project Administrator Talk to Project Administrator daily Contact PA soon enough to make a difference and to minimize impacts to cost or schedule 5-9 Version 1-1/15 5-9

10 CPAM Miscellaneous Shafts Miscellaneous Drilled Shafts To improve the quality of miscellaneous drilled shafts installation, DCEs shall obtain technical support from the District Geotechnical Office on drilled shaft projects involving mast arms, cantilever signs, overhead truss signs, high mast light poles or other miscellaneous structures shown in the Contract Documents. This process includes review of Drilled Shaft Installation Plans, conduct at the earliest predrill/pre-concrete pour meetings, as required for quality assurance checks and inspector assistance etc. Project Administrators shall notify the District Geotechnical Offices of the construction schedules of the miscellaneous drilled shafts for the projects so they can schedule time to assist Version 1-1/

11 Communication & Coordination Pre-Drilling Meeting Review the approved Drilled Shaft Installation Plan, and have any questions answered Discuss applicable Special Provisions Discuss administrative issues Discuss and resolve any conflicts. Discuss any special site considerations 5-11 Version 1-1/

12 Communication & Coordination With Contractor Remember, you are a team Do Not direct the Contractor in their work If you observe potential non-conformance, notify the Contractor, in advance, to avoid the situation occurring Avoid delaying Contractor 5-12 Version 1-1/

13 Inspector s Role on Drilled Shafts Check Drilled Shaft Installation Plan Verify Contractor Equip. Verify hole location Verify template Verify setup for plumbness, etc. Record Pilot Holes Verify proper steel size, length, etc. Verify proper ties Verify proper spacers and intervals Verify CSL Tubes Verify anchors placement plate alignment Monitor concrete volumes Prepare Concrete Placement Log CONTRACTOR SET UP SHAFT EXCAVATION AND CLEANING PLACING STEEL CONCRETING OPERATION POST INSTALLATION Verify testing of Slurry Identify Soils & Rock Prepare Excavation Logs Verify Shaft Depth Perform Shaft Inspection Prepare Shaft Inspection Log Verify hole cleanliness Document casing use, type, length Verify Const. Tolerance compliance Verify pay quantities Verify integrity testing Complete required forms Check CSL tubes 5-13 Version 1-1/

14 Assemble Your Toolbox Casey 5-14 Version 1-1/

15 Tools Checklist Checklists Prevent Forgetting 5-15 Version 1-1/

16 Checklist The Drilled Shaft Inspector s Checklist can assist you in performing you duties Version 1-1/

17 Project Document Check COMPONENT Plan Revisions CHECK Always check for revised sheets to see if there are any changes that affect the shaft construction. Key Sheet Does Project ID No., location, etc. agree with the information you were provided? Summary of Pay Items Do the pay quantities and items agree? 5-17 Version 1-1/

18 Project Document Check COMPONENT Utilities CHECK Does there appear to be any conflicts with production or test shafts? If so, are there provisions for addressing these conflicts? Traffic Control Does there appear to be any conflicts with production or test shafts? Does the sequence of shaft installation conflict? If so, are there provisions for addressing these conflicts? 5-18 Version 1-1/

19 Structural Plan Sheet Check STRUCTURAL PLANS General Notes CHECK Compare with the Drilled Shaft Data Table. Do any Notes contain changes to the specifications or specification applications? General Plan & Elevation Does the number of bent/piers or shaft locations match the Drilled Shaft Data Table? Do the elevations shown compare favorably with the Drilled Shaft Data Table? 5-19 Version 1-1/

20 Structural Plan Sheet Check STRUCTURAL PLANS Rpt. of Borings Foundation Layout CHECK Are water tables/piezometric levels shown? Do the boring(s) extend beyond the proposed bottom of shaft elevations? Does the foundation layout match the Drilled Shaft Installation Plan relating to number, sequencing, elevations, etc.? 5-20 Version 1-1/

21 Learning Outcome What is the Inspector s Role? As a Recorder and Reporter, the Inspector s duties include what? 5-21 Version 1-1/

22 Learning Outcome When should the Inspector contact the Project Administrator? It is enough for the inspector to know the Standard Specifications. True or False? 5-22 Version 1-1/

23 Contractor & Equipment Arrive 5-23 Version 1-1/

24 Inspector s Checklist 5-24 When the Contractor and their equipment arrive on-site, there are a variety of items that you, the I nspector, are responsible for c hecking and verifying. From ver ifying the equipment on-site matches that in the a pproved Drilled Shaft Installation Plan t o assessing Contractor compliance with any required Protection of Existing Structures, the Inspector is quite busy. Version 1-1/

25 Verify Equipment Can use Drilled Shaft Installation Plan submittal to verify equipment Need to check & document augers, bits, buckets, etc. -Type -Size - Condition 5-25 The Contractor has to provide det ailed information on their equipment in the Drilled Shaf t installation Plan. Version 1-1/

26 Verify Equipment Check diameter of bits Check condition of auger and teeth Length Diameter Determine length of tool Cutting teeth 5-26 Though we cannot and do not want to tell the Contractor what type of bit to use, they have provided the information on their equipment in t he Drilled Shaft Installation Plan. The Inspector should verify that the augers and bits are as detailed in the plan, especially paying attention to the diameters, condition and length of the tools. Bits should be checked for missing or broken teeth, and types on site. Augers checked for broken or missing cutting blades, damaged flights, etc. It is important to measure the height of these tools as you will need this information when determining depths. Version 1-1/

27 Verify Equipment Is the equipment in good shape? Bent kelly 5-27 The Inspector typically does not have the authority to reject the Contractor s tools, however, it is the Inspector s responsibility to document the condition of the equipment and tools. The Inspector must document all of the tools, as q uestions may arise at a later time concerning drilling difficulties, etc. Document any changing of or repairing of tools, such as changing teeth on a bit, etc. Version 1-1/

28 Verify Equipment Bucket Template Auger Bit 5-28 Version 1-1/

29 Verify Equipment 5-29 Section 400 of the Standard Specifications states that tremies are to be a minimum of 10 inches in diameter. Version 1-1/

30 Verify Equipment 5-30 Version 1-1/

31 Verify Equipment 5-31 Version 1-1/

32 Verify Equipment Contractor was trying to use this bent casing. Cutting off bent part so they could use Casings can be bent or deformed at the tip during installation into hard strata. Contractor then has difficulty removing the drilling tool from the hole making it difficult to remove the cuttings. The auger will catch on the bent portion of the casing. Version 1-1/

33 Casing Casings: Ensure that casings are metal, of ample strength to withstand handling and driving stresses and the pressure of concrete and of the surrounding earth materials, and that they are smooth and water tight. Ensure that the inside diameter of casing is not less than the specified size of shaft except as provided below. The Department will not allow extra compensation for concrete required to fill an oversize casing or oversize excavation Version 1-1/

34 Protection of Existing Struct Protection of Existing Structures: When the Plans require excavation or foundation construction operations in close proximity to existing structures, take all reasonable precautions to prevent damage to such structures. The requirements described herein apply to all types of structures (on or off the right-of-way) that may be adversely affected by foundation construction operations (including phase construction) due to vibrations, ground loss, ground heave, or dewatering. Protect utilities as described inthe applicable provisions of Section Version 1-1/

35 Protection of Existing Struct Protection of Existing Structures: Continued Survey and monitor structures for settlement in a manner approved by the Engineer, recording elevations to foot. Employ a qualified Specialty Engineer to inspect and document the condition of structures prior to and after construction of excavations and foundation construction. Inspect and monitor the following structures: (1) shown in the plans. (2) within a distance of ten shaft diameters or the estimated depth of excavation, whichever is greater. (3) within a distance of three times the depth of excavation for the footing Version 1-1/

36 Protection of Existing Struct Protection of Existing Structures: (Continued) Take elevation; (1) before beginning construction, (2) daily during the driving of any casings, piling, or sheeting, (3) weekly for two weeks after stopping driving, (4) during excavation, (5) during blasting, (6) or as directed by the Engineer. Notify the Engineer of any movements detected and immediately take any remedial measures required to prevent damage to the existing structures Version 1-1/

37 Protection of Existing Struct. Distance from Shaft to be monitored and Surveyed (pre and post-construction) D D = 10 Shaft diameters OR Depth of Excavation 5-37 Version 1-1/

38 Protection of Existing Struct Protection of Existing Structures: (Continued) The Department will make the necessary arrangements to provide right-of-way entry to the existing structures. Adequately document the condition of the structures and all existing cracks with descriptions and pictures. Prepare two reports documenting the condition of the structures: one report before beginning foundation construction operations and a second report after completing foundation construction operations. The Department will take ownership of both reports. Do not perform pre-driving and post-driving surveys of the condition of bridges owned by the Department except when shown in the Contract Documents Version 1-1/

39 Protection of Existing Struct. When shown in the Contract Documents, employ a qualified Specialty Engineer to monitor and record vibration levels during the driving of casings, piling, sheeting, or blasting operations. Provide vibration monitoring equipment capable of detecting velocities of 0.1 in/s or less. Upon detecting settlement or heave of foot, vibration levels reaching 0.5 in/s, levels otherwise shown in the Contract Documents, or damage to the structure, immediately stop the source of vibrations, backfill any open drilled shaft excavations, and contact the Engineer for instructions Version 1-1/

40 Learning Outcome The Contractor is preparing to install a 48 in. drilled shaft to a depth of 90 ft. Answer the following. 1. Structures within what distance must be monitored by the Contractor? Within a distance of ten shaft diameters....or the estimated depth of excavation, 5-40 Version 1-1/

41 Excavation Excavation: Complete all excavation of the foundations prior to installing piles or shafts unless otherwise authorized by the Engineer Version 1-1/

42 Abutment (End Bent) Fill Abutment (End Bent) Fill: Place and compact the fill before installing end-bent piling/shafts, except when: (1) driving specified test piling in end bents or, (2) the plans show uncased piles through proprietary retaining wall fills. When installing piles/shafts or casing prior to placing fill, take necessary precautions to prevent displacement of piles/shafts during placing and compacting fill materials within 15 feet of the piles/shafts or casing. Reference and check the position of the piles/shafts or casing at three approximately equal intervals during construction of the embankment Version 1-1/

43 Abutment (End Bent) Fill Abutment (End Bent) Fill: (Continued) Provide permanent casings installed prior to placement of the fill, for all drilled shafts through mechanically stabilized fills (for example, behind proprietary retaining walls) for shafts installed after fill placement. Install temporary casings through the completed conventional fill when permanent casings are not required. Provide permanent casings, if required, before the fill is placed extending a sufficient distance into the existing ground to provide stability to the casings during construction of the abutment fill Version 1-1/

44 Cofferdams 5-44 A Cofferdam is a closed t emporary wall, typically built with steel sheet piles and wh ich allows the protected area to be dewatered and be constructed in the dry. In FDOT projects cofferdams are used to construct pier fo undations for bridges and in spec ial drainage structure construction. The foll owing slides illustrate a cof ferdam installed for the construction of a bridge p ier. Even t hough is mostly temporary, in some cases the cofferdam is left in place as it is not practical or cannot be removed. Version 1-1/

45 Cofferdams 5-45 Version 1-1/

46 Cofferdams 5-46 Version 1-1/

47 Cofferdams Cofferdams: Construct cofferdams as detailed in the plans. When cofferdams are not detailed in the plans, employ a Specialty Engineer to design cofferdams, and to sign and seal the plans and specification requirements. Send the designs to the Engineer for his records before beginning construction. Provide a qualified diver and a safety diver to inspect the conditions of the foundation enclosure or cofferdam when the Contract Documents require a seal for construction Version 1-1/

48 Cofferdams Cofferdams:Continued. Equip these divers with suitable voice communications, and have them inspect the foundation enclosure and cofferdam periphery including each sheeting indentation and around each piling or drilled shaft to ensure that no layers of mud or other undesirable materials were left above the bottom of seal elevation during the excavation process. Also have the divers check to make sure the surfaces of the piles or drilled shafts are sufficiently clean to allow bond of the concrete down to the minimum bottom of seal elevation Version 1-1/

49 Learning Outcomes Identify and understand the Role and Duties of the Inspector Verify and Inspect On-site Equipment Verify Protection of Existing Structures is implemented Identify the applicable 455 Specifications 5-49 Version 1-1/

50 Questions? ANY QUESTIONS? 5-50 Version 1-1/

51

52 Drilled Shaft Reinforcement/Spacers Log Drilled Shaft fluid/slurry testing log

53 Lesson 5-Contractor & Equipment Arrive On-Site DRILLED SHAFT INSPECTOR S CHECKLIST The following is a general checklist to follow when consulting a Drilled Shaft. The answer to each of these should be yes unless plans, specification or specific approval has been given otherwise. CONSULT WITH RESPONSIBLE ENGINEER FOR YOUR SPECIFIC PROJECT RESPONSIBILITIES. EARLY REQUIREMENTS YES NO NA 1. Do you have a copy of the Plans including latest revisions & located relevant items (ex. Drilled Shaft Data Table)? 2. Do you have and have you reviewed the accepted Drilled Shaft Installation Plan submitted by Contractor ( ? 3. Is a Shaft Inspection device (SID) to be used? 4. Do you have the supplemental specifications for this project? 5. Does the contractor have an approved Concrete Mix Design and do you have a copy ( )? 6. Has the contractor provided the required Slump Loss Test for their mix design ( )? 7. Are Pilot Holes required ( )? a. If Yes, how many, what depths. And where? b. What type of sampling (Cores versus SPT)? c. Do you have samples? Does the Engineer have results? d. Do you have revised/confirmed tip elevations based on Pilot Holes? 8. If cores are required at the bottom of the shaft, does the Contract have the correct coring equipment ( )? 9. Are Load tests required (455-2)? 10. Have you scheduled or attended a Pre-Installation meeting with the PA/Geotechnical Engineer? PRE-INSTALLATION REQUIREMENTS 11. Has the Contract met the requirements of , Protection of Existing Structures? 12. Has the site preparation been completed for footings/excavations/abutments in accordance with & ? 13. Have the requirements of vibrations of Freshly Placed Concrete been met? 14. If a Cofferdam is required, does the Contractor have a qualified diver and safety diver for inspections in accordance with , cofferdams? 15. If underwater diving is required, are the divers equipped with voice communications, per , Cofferdams? 16. Does the contractor have the equipment indicated in the Drilled Shaft Installation Plan on-site ? 17. If casing is to be used, does it meet the requirements of , Casing? 18. If the Contractor plans on using a pre-mix slurry, do they have the equipment to mix it? 19. Does the contractor have the equipment indicated in the Drilled Shaft Installation Plan on-site ? 20. If casing is to be used, does it meet the requirements of , Casing? 21. If using polymer, has the Contractor provided the required data ( )? TEST HOLE/TEST SHAFTS 22. Is this a Miscellaneous Shaft? If so, no separate Test Hole required (455-18, Test Holes)? 23. Has the Contractor located the Test Hole away from the production shafts ore as indicated in the Plans (455-18, Test Holes) or is it at permanent locations? 24. If OD casing used, what is the additional depth required ( , Casing)? 25. Has the Contractor performed a successful Test Hole, per Plan requirements and , Test Holes? 26. If not, has the Contractor revised their technique and/or equipment (and the revision approved) to successfully construct the Test Holes? 27. Was the Test Hole cutoff a minimum of 2 ft. below the groundline, per , Test Holes? SHAFT CONSTRUCTION - EXCAVATION 28. Is the shaft being constructed in the correct plan location and within tolerance (455-20, Construction Tolerances)? 29. Does the Contractor have a bench mark so the shaft can be construction and inspected in the proper elevations? 30. Is the template required ( , Templates) and has the Contractor met the requirements? 31. Is the Contractor using a surface casing as a minimum to meet Section , General Methods and Equipment? 32. If mineral slurry is being used, does the Contractor have a CTQP qualified technician to test the slurry and report the results in accordance with , Slurry? 33. Are the proper type and number of tests being performed per , or ? 34. If being used, is the slurry level being properly maintained (a minimum of 4ft above the highest piezometric head) in accordance with , Slurry? Version 1.0-1/

54 Lesson 5-Contractor & Equipment Arrive On-Site DRILLED SHAFT INSPECTOR S CHECKLIST Page 2 SHAFT CONSTRUCTION EXAVATION (Continued) YES NO NA 35. Do you have the required drilled Shaft Forms? 36. Are you filling out the Shaft Excavation Form, as the excavation proceeds? 37. Is the shaft to the proper depth ( , Depth)? 38. Was the shaft over drilled & extra reinforcement placed ( )? Was this authorized? 39. Is the shaft being excavated within the allowable axial tolerances ( ), Dimensions and Alignment)? 40. If slurry is being used, is the Contractor taking the required slurry tests in accordance with Fluid in the Excavation at the Time of Concrete Placement? (Applies to ALL shafts) 41. If so, are the test results within the allowable limits per or ? 42. Does the shaft excavation meet the 36 hour time limit per ? 43. If the shaft was not excavated within the applicable time limit, has the shaft been overreamed in accordance with ? 44. If using mineral slurry, has it been in contact with the bottom 5 ft. of the shaft for over 12 hours ( )? 45. If yes, has the bottom 5 ft of the shaft been overreamed per ? 46. Does the shaft bottom meet the requirements of or ? 47. Have you completed the proper Shaft Inspection Forms? REINFORCING CAGE 48. Are the correct number and size of bars being used per the Plans? 49. Is the cage properly tied in accordance with , Cage Construction and Placement? 50. If the cage was spliced, was it performed in accordance with , Splicing Cage? 51. Are the proper number of bottom spacers and side spacers being used ( , Support, Alignment and Tolerance)? 52. Are the CSL tubes, the correct diameter, steel, spaced, aligned and secured inside the cage per , Cross-Hole Sonic Logging Tubes? 53. Do the CSL tubes extend from the bottom of the shaft to the minimum of 30 inches above the top of the shaft, ground or water surface, whichever is higher ( , Cross-Hole Sonic Logging Tubes)? 54. Was a simulated or mock CSL probe inserted and run down each CSL to check for serviceability ( , Cross- Hole Sonic Logging Tubes)? 55. Are the CSL tubes sealed, watertight, and filled with clean potable water prior to concreting ( , Cross-Hole Sonic Logging Tubes)? 56. Is the cage secured from settling and/or rising (during concrete placement)? (Elevation check) CONCRETE PLACEMENT 57. Does the tremie or pump meet the requirements of , & Tremies and Pumps? 58. Is the tremie or pump line sealed and watertight? 59. Immediately prior to concrete placement, was the slurry tested per , Fluid in the Hole at time of Concrete Placement? 60. Is the tremie/pump line maintained in the concrete with a head above it? 61. Did you complete the concrete placement forms and the concrete curves? Does the placement curve appear OK? 62. Project Administrator notified of concrete curves with irregularities? 63. Did the Contractor overflow the shaft until good concrete flowed? 64. Was the concrete placed within the time allowed by the Slump Loss Test ( )? POST INSTALLATION 65. Did you check the CSL tubes following concrete placement to ensure they are still full of water ( , Cross-Hole Sonic Logging Tubes)? 66. If in open water, is the shaft protected for 7 days or until strength of 2,500 psi has been achieved ( , Curing)? 67. Is all casing removed to the proper elevation per Forms? 68. Does the drilled shaft meet the construction tolerances (455-20, Construction Tolerances)? 69. Have you filled out the Drilled Shaft Construction and Pay Summary form? Version 1.0-1/15

55

56

57

58

59

60

61

62

63

64

65

66

CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS

CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS 2006 LADOTD ENGINEERING CONFERENCE Kim Martindale Garlington, P.E. Pavement & Geotechnical Services February 13, 2007

More information

Lesson 4 INSPECTOR S ROLE

Lesson 4 INSPECTOR S ROLE Lesson 4 INSPECTOR S ROLE 4-1 Version 1.0-1/15 4-1 Learning Outcomes Identify and understand the Role and Duties of the Inspector Assemble Your Tool Box Identify and Understand Pay Items/Quantities Perform

More information

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division

More information

Implementation of this Special Provision requires a complete understanding of the following documents:

Implementation of this Special Provision requires a complete understanding of the following documents: VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR Quality Assurance/Quality Control (QA/QC) for the Construction of Deep Foundation Systems for Design-Build and PPTA Contracts November 10, 2009

More information

RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS

RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS Chris Nickel, P.E. LA DOTD Pavement & Geotechnical Services 2011 Louisiana Engineering Conference TOPIC OUTLINE Driven Piles Definitions and Data table

More information

SHAFT EXCAVATION AND CLEANING

SHAFT EXCAVATION AND CLEANING Lesson 6 SHAFT EXCAVATION AND CLEANING 6-1 Version 1-1/15 6-1 Learning Outcomes Perform inspection of drilled shaft excavations for compliance to plans, tolerances and cleanliness. Perform visual field

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Lesson 3 Construction Documents Transcript. Welcome to the Pile Driving Inspector Course. This is Lesson 3 Construction Documents.

Lesson 3 Construction Documents Transcript. Welcome to the Pile Driving Inspector Course. This is Lesson 3 Construction Documents. Lesson 3 Construction Documents Transcript Welcome to the Pile Driving Inspector Course. This is Lesson 3 Construction Documents. To begin, select the start button or press Shift+N on your keyboard. In

More information

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015 SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015 Note: This sample specification contains recommended or typical quantities in parenthesis, in the format (quantity); the specifying

More information

5.0 DRILLED SHAFTS. Table of Contents

5.0 DRILLED SHAFTS. Table of Contents 5.0 DRILLED SHAFTS Table of Contents 5.0 DRILLED SHAFTS...1 5.4.1 General...1 5.4.2 Bid Items:...2 5.4.3 Equipment:...3 5.4.4 Materials:...5 5.4.5 Investigative Core Hole:...6 5.4.6 Drilling (Excavation):...6

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures Preferred QC/QA Procedures The Federal Highway Administration (FHWA) has provided QC/QA guidance for this technology as noted below. The reference document also contains information about construction

More information

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates LA Transportation Conference: 10 Jan 2011 Drilled Shaft Foundations For Two Mississippi River Bridges in Louisiana Dan Brown and Associates Projects John James Audubon Bridge, St. Francisville New Construction

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR DRILLED SHAFT FOUNDATIONS

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR DRILLED SHAFT FOUNDATIONS 516-3(a-s) 09 OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR DRILLED SHAFT FOUNDATIONS These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2009

More information

Non-Destructive Testing of Drilled Shafts Current Practice and New Method

Non-Destructive Testing of Drilled Shafts Current Practice and New Method Non-Destructive Testing of Drilled Shafts Current Practice and New Method George Piscsalko PE, Pile Dynamics, Inc., Cleveland, Ohio, USA Garland Likins PE, Pile Dynamics, Inc., Cleveland, Ohio, USA Benjamin

More information

WELCOME TO THE PILE DRIVING INSPECTOR COURSE

WELCOME TO THE PILE DRIVING INSPECTOR COURSE Lesson 1 WELCOME TO THE PILE DRIVING INSPECTOR COURSE 1-1 Welcome to the Pile Driving Inspector Course. This is a course designed to assist students to understand the specifications and inspection practices

More information

STRUCTURES SPECIFICATIONS FOR BRIDGE CONSTRUCTION ISSUES. John Westphal, P.E. State Construction Office January 2017

STRUCTURES SPECIFICATIONS FOR BRIDGE CONSTRUCTION ISSUES. John Westphal, P.E. State Construction Office January 2017 STRUCTURES SPECIFICATIONS FOR BRIDGE CONSTRUCTION ISSUES John Westphal, P.E. State Construction Office January 2017 Introduction Discuss Defective Materials, as defined within the Specifications Recent

More information

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , & TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3 Contents 1. Introduction 3 2. Selection of Pile Type 3 3. Soil Report / Boreholes 3 4. Obstructions 3 5. Design and Installation of Piling Mat 3 6. Permit to Dig 4 7. Setting out 4 8. Water 5 9. Attendant

More information

Using Thermal Integrity Profiling to Confirm the Structural Integrity of foundation applications

Using Thermal Integrity Profiling to Confirm the Structural Integrity of foundation applications Using Thermal Integrity Profiling to Confirm the Structural Integrity of foundation applications Authors: 1. George Piscsalko, PE, Pile Dynamics, Inc., 30725 Aurora Road, Solon, Ohio, USA, gpiscsalko@pile.com;

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,

More information

ENGINEERING DIRECTIVE

ENGINEERING DIRECTIVE Number: E-95-001 Date: 2/2/95 ENGINEERING DIRECTIVE Ross B. Dindio (Signature on Original) CHIEF ENGINEER The purpose of this engineering directive is to formally notify ALL Department engineering personnel

More information

ODOT Design & Construction Requirements for MSE Walls

ODOT Design & Construction Requirements for MSE Walls ODOT Design & Construction Requirements for MSE Walls Peter Narsavage, P.E. Foundation Engineering Coordinator Ohio Department of Transportation Office of Structural Engineering 2006 Ohio Transportation

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London PIANC UK Seminar Design Developments and Specification for Steel Duncan Nicholson Arup Fellow 9/3/17 ICE London Contents 1. Design Issues 2. SPERWall Edition 3 (2016) 1. Steel Sheet Piles (Section 14)

More information

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch MSE WALLS CASE STUDIES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch COMMON RETAINING WALL TYPES CONCRETE BLOCK MSE TEMPORARY EARTH SPREAD FOOTING Gabions Drilled Shaft Soil Nail Tiedback

More information

Specifications for the Construction of Secant and Tangent Pile Wall Systems using Drilled Shafts

Specifications for the Construction of Secant and Tangent Pile Wall Systems using Drilled Shafts 1.0 GENERAL Specifications for the Construction of Secant and Tangent Pile Wall Systems using Drilled Shafts This document establishes the recommended construction specifications for the installation of

More information

DEPARTMENT OF TRANSPORTATION

DEPARTMENT OF TRANSPORTATION Gregory A. Whirley Commissioner September 6, 2013 DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VIRGINIA 23219-2000 Order No.: B43 Route: 340 Project: (NFO)0340-093-127, B609, C501 FHWA:

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter. STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer

More information

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION Supplemental Specification 901-S-803-1 LFRD Driven Pile Specifications. DATE: May 24, 2010 OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION SUBJECT: LRFD Driven Pile Specifications

More information

SECTION DUCTILE IRON PILES

SECTION DUCTILE IRON PILES SECTION 31 66 13 DUCTILE IRON PILES PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS A. Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. B.

More information

SCOPE OF WORK FOR PILING JOB

SCOPE OF WORK FOR PILING JOB SCOPE OF WORK FOR PILING JOB 1.0 PURPOSE This document defines the scope of works and specific requirements for the tank pad construction including pile foundation system for the proposed tanks at Wadala

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

HANDHOLES, PULLING VAULTS AND JUNCTION BOXES

HANDHOLES, PULLING VAULTS AND JUNCTION BOXES Handholes and pulling vaults perform several important functions: Provide drainage for the conduit system so that freezing water does not damage the conduit or wires. Provide a location for bending the

More information

Our Tour Stops. A Foundation Engineering gtrip down the Mississippi River. Dan Brown, P.E. Dan Brown and Associates 9/6/2010.

Our Tour Stops. A Foundation Engineering gtrip down the Mississippi River. Dan Brown, P.E. Dan Brown and Associates 9/6/2010. A Foundation Engineering gtrip down the Mississippi River Dan Brown, P.E. Dan Brown and Associates Our Tour Stops I 35W Minneapolis US U.S. 61 Bridge, Hastings, MN New Mississippi River Bridge (I 70),

More information

Temporary Structures. Cofferdams TOKYO INSTITUTE OF TECHNOLOGY ATCE-II ADVANCED TOPICS IN CIVIL ENGINEERING DEPARTMENT OF CIVIL ENGINEERING

Temporary Structures. Cofferdams TOKYO INSTITUTE OF TECHNOLOGY ATCE-II ADVANCED TOPICS IN CIVIL ENGINEERING DEPARTMENT OF CIVIL ENGINEERING TOKYO INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING ATCE-II ADVANCED TOPICS IN CIVIL ENGINEERING Second Semester 2005 Professor Kamran M. Nemati Temporary Structures Cofferdams ATCE-II ADVANCED

More information

CHAPTER 5 PILE DRIVING

CHAPTER 5 PILE DRIVING SDDOT Standard Specifications Section 510 CHAPTER 5 PILE DRIVING PILE DRIVING CHECKLIST U:\op\inspection list Structures Manual, Chapter 5 Pages 5-54 to 5-96 USE IT, LEARN IT, KNOW IT!!!!! PILE TYPES:

More information

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE Karsten Beckhaus (1), Martin Larisch (2), Habib Alehossein (3,4) (1) BAUER Spezialtiefbau GmbH, Deutschland (2) Keller Australia Pty Ltd, Australia (3)

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

Recent Advances in the Selection and Use of Drilled Foundations

Recent Advances in the Selection and Use of Drilled Foundations Recent Advances in the Selection and Use of Drilled Foundations Dan Brown, P.E., Ph.D. Dan Brown and Associates Overview Micropiles Continuous Flight Auger Piles Drilled Displacement Piles Drilled Shafts

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

A. Product Data shall be provided for each type of product indicated.

A. Product Data shall be provided for each type of product indicated. 32 31 13 CHAIN LINK FENCES AND GATES SECTION 1 GENERAL 1.1 SUMMARY This Section includes the following: 1. Chain Link Fences 2. Gates for Chain Link Fences. See electrical specifications for electrical

More information

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2) Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course. SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721

More information

CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING

CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING CEMENT EVALUATION OBJECTIVES Is the material behind the pipe a solid or liquid - Solids can t be fixed

More information

Temporary Shoring. Specifications, Applications, & Best Practices. Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer

Temporary Shoring. Specifications, Applications, & Best Practices. Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer Temporary Shoring Specifications, Applications, & Best Practices Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer Temporary Shoring Specifications, Applications, & Best Practices Temporary

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

Scope of Services EXHIBIT "A" Business Development Initiative (BDI) Contract Districtwide Materials Testing / Geotechnical Support FM

Scope of Services EXHIBIT A Business Development Initiative (BDI) Contract Districtwide Materials Testing / Geotechnical Support FM EXHIBIT "A" Business Development Initiative (BDI) Contract Districtwide Materials Testing / Geotechnical Support Scope of Services FM 25073033201 FM 25073033201- BDI Contract 7052017 1 TABLE OF CONTENTS

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-34 73 13 (April 2008) Change 1-11/14 -------------------------- Preparing Activity: USACE Superseding UFGS-34 73 13 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more. TECHNOLOGY Diaphragm walls Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

Bi-Directional Static Load Testing of Driven Piles

Bi-Directional Static Load Testing of Driven Piles Bi-Directional Static Load Testing of Driven Piles Paul J. Bullock, PhD Fugro Consultants Inc. Loadtest Bi-Directional Osterberg Cell Testing Specialized jack in pile uses bearing to mobilize side shear

More information

Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LIGHTING AND SIGNS

Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LIGHTING AND SIGNS Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 FOUNDATION SYSTEM SECTION 10 CONTENTS INTRODUCTION... 10-3 PRODUCT BENEFITS... 10-3 RECOMMENDED FACTORS of SAFETY for DESIGN...

More information

Structural and Geotechnical Issues Impacting The Dalles Spillwall Construction and Bay 1 Erosion Repair

Structural and Geotechnical Issues Impacting The Dalles Spillwall Construction and Bay 1 Erosion Repair Structural and Geotechnical Issues Impacting The Dalles Spillwall Construction and Bay 1 Erosion Repair Jeffrey M. Ament, PE U.S. Army Corps of Engineers, Portland District (503) 808-4950 Jeffrey.M.Ament@usace.army.mil

More information

Witness & Hold Inspection Plan. I-595 Corridor Roadway Improvement Project

Witness & Hold Inspection Plan. I-595 Corridor Roadway Improvement Project Witness & Hold Inspection Plan I-595 Corridor Roadway Improvement Project Revision 6 March 2013 I-595 Corridor Roadway Improvements QUALITY PROCEDURES Procedure No.QP-07 Revision #6 PROCEDURE FOR WITNESS

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information

Over the last decade, drilled and postgrouted micropile foundations have

Over the last decade, drilled and postgrouted micropile foundations have Seismic Design of Micropile Foundation Systems Leo Panian, S.E., and Mike Korolyk, S.E. Over the last decade, drilled and postgrouted micropile foundations have come to be increasingly relied on for resisting

More information

JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106.

JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106. JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106. There are notes in the plans regarding driving the test pile without the use of a follower. The

More information

Construction Procedures

Construction Procedures Construction Procedures 2014 Rev. 1.6 1 Introduction This manual presents the methods and procedures necessary for the proper erection of a LOCK+LOAD retaining wall. problems later during the service life

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

2016 Port of San Francisco Building Code

2016 Port of San Francisco Building Code PORT CODE PROCEDURE NO. : DATE : December 5, 2012 SUBJECT : Permit Process; Inspection TITLE : Special Inspection and Structural Observation Procedures PURPOSE : The purpose of this Port Code Procedure

More information

METHOD STATEMENT for INSTALLATION OF MICROPILE

METHOD STATEMENT for INSTALLATION OF MICROPILE METHOD STATEMENT for INSTALLATION OF MICROPILE A. MATERIAL TO BE USED 1. Grout Grout shall be mixed from Ordinary Portland Cement and clean water free from harmful substances. Usage of other cement which

More information

Geotechnical Specification and Construction Update

Geotechnical Specification and Construction Update Geotechnical Specification and Construction Update Steve Slomski, P.E. Office of Construction Administration Topics 2016 C&MS Revisions Supplemental Specifications & Supplements Revisions & Additions Construction

More information

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT CHAPTER Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 19 By Dr. Ibrahim

More information

WOOD POLE SPAN WIRE SIGNAL SYSTEMS

WOOD POLE SPAN WIRE SIGNAL SYSTEMS 7 A wood pole span wire traffic control signal system differs from a mast arm steel pole traffic control signal system in that it uses wood poles and span wires to place the signal indications in the driver

More information

SECTION GRAVEL PACKED WATER WELL

SECTION GRAVEL PACKED WATER WELL SECTION 02520 GRAVEL PACKED WATER WELL PART 1 GENERAL 1.01 SECTION INCLUDES A. Gravel packed water well includes drilling, installing, cleaning, developing, testing, videoing, abandoning, and site clean

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM SECTION 32 32 23 SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM PART 1: GENERAL 1.01 Scope Work includes furnishing all materials, labor, equipment, and supervision to install a Stonebridge segmental

More information

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated: SECTION 04220 CONCRETE UNIT MASONRY PART 1 - GENERAL 1.01 SCOPE: A. The CONTRACTOR shall furnish all labor, materials and equipment necessary for the masonry construction as shown on the drawings or as

More information

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966 SINCE 1966 Introduction Geotechnical Systems Australia (GSA) was founded in March 1987 to design, manufacture and distribute geotechnical instrumentation for the geotechnical and mining industries. Now

More information

Schnabel Foundation Company

Schnabel Foundation Company Micropiles for Roadway Support, Bridge Abutments and Metal Signal Poles on US-158 from US-17B to East of Pasquotank River, in Elizabeth City, NC Schnabel Foundation Company Presenter: Stephen Dimino, P.E.

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

ROOF MOUNT KIT OWNERS MANUAL

ROOF MOUNT KIT OWNERS MANUAL ROOF MOUNT KIT OWNERS MANUAL Made in the USA by: Primus Wind Power, Inc. 938 Quail St. Lakewood, CO 80215 Phone: (303) 242-5820 www.primuswindpower.com AIR is a trademark of Primus Wind Power, Inc. ROOF

More information

SITE INVESTIGATION. Foundation Engineering

SITE INVESTIGATION. Foundation Engineering SITE INVESTIGATION Assist. Prof. Berrak TEYMUR Foundation Engineering Analysis Design Construction As a foundation engineer, you need to consider geotechnical/structural issues (involves geology, subsurface

More information

C. Installers licensed by the Geopier Foundation Company, Inc. (www.geopier.com) will be accepted as approved installer.

C. Installers licensed by the Geopier Foundation Company, Inc. (www.geopier.com) will be accepted as approved installer. SPECIFICATION FOR RAMMED AGGREGATE PIER SYSTEMS AND RIGID INCLUSION FOUNDATION PART 1: GENERAL REQUIREMENTS 1.01 Description Work shall consist of designing, furnishing and installing Rammed Aggregate

More information

THE USE OF SELF-CONSOLIDATING CONCRETE FOR DRILLED SHAFT CONSTRUCTION: PRELIMINARY OBSERVATIONS FROM THE LUMBER RIVER BRIDGE FIELD TRIALS

THE USE OF SELF-CONSOLIDATING CONCRETE FOR DRILLED SHAFT CONSTRUCTION: PRELIMINARY OBSERVATIONS FROM THE LUMBER RIVER BRIDGE FIELD TRIALS 1 THE USE OF SELF-CONSOLIDATING CONCRETE FOR DRILLED SHAFT CONSTRUCTION: PRELIMINARY OBSERVATIONS FROM THE LUMBER RIVER BRIDGE FIELD TRIALS Dan Brown 1, Joe Bailey 2, Anton Schindler 3 ABSTRACT: Several

More information

SECTION PILING

SECTION PILING 02300-1 of 16 SECTION 02300 PILING 02300.01 GENERAL A. Description Piling shall include, but not necessarily be limited to, the manufacturing, furnishing, treating, painting, coating, driving, jetting,

More information

Bureau of Materials Materials Approval Procedures

Bureau of Materials Materials Approval Procedures Bureau of Materials Materials Approval Procedures MAP Number: 116-15 Effective Date: April 1, 2015 Approved By: Eileen Sheehy PROCEDURE FOR APPROVAL OF MECHANICALLY STABILIZED EARTH (MSE) RETAINING WALL

More information

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation)

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) PART 1 GENERAL SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) 1.01 SCOPE This specification includes the materials and procedures required for the internal sealing of the frame-chimney

More information

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT Tracy Brettmann, P.E., D.GE, Vice President, A. H. Beck Foundation Company, Houston, Texas, (713) 413-3800, tracy.brettmann@ahbeck.com

More information

Uwall UNIVERSAL CONSTRUCTION MANUAL

Uwall UNIVERSAL CONSTRUCTION MANUAL Uwall UNIVERSAL Retaining Wall System CONSTRUCTION MANUAL TM President s Letter CSI is a leader in its industry supplying precast infrastructure products throughout New England and beyond since 1972, developing

More information

THE PILE DRIVING SYSTEM

THE PILE DRIVING SYSTEM Version 1.0-1/2015 Page 2-1 Lesson 2 THE PILE DRIVING SYSTEM 2-1 Version 1.0-1/2015 Page 2-2 Learning Outcomes Identify Pile Installation Equipment and Tools Identify various pile types Use Pile Driving

More information