1 Questions / Answers from BUILD Meeting with Congregation on September 18, 2016 The mission of the Church is to make Disciples of Jesus Christ for the transformation of the world. With that mission as our focus and being one body in Christ, the Building Committee, along with our Architect and Builder, met with the congregation on Sunday evening, September 18 to present a new vision of our proposed architectural plan for the new church building. After the presentation of this proposed new plan, we collected questions from the congregation and are providing them to you here, along with the answers to these questions. Please note that the questions we received cover many different topics, and many of our members were asking the same question. Additionally, as more of our members study this plan, more questions have been submitted. We are providing answers to these questions with the information that we know at this time. Please note that we are still in a phase of developing the details around the proposed plan and will continue to keep the congregation informed as more details are worked out. Our intent is to ensure we can provide as much information to our congregation as possible before the Church Conference on October 23 rd, where we will vote on whether or not to proceed with this plan. General / Miscellaneous 1. Continuing prayer that God s will and way be done through each one of you in the Building Ministry and in your personal lives. JAM Thank you and continue to pray. 2. Please make the presentation slides available to download. The full presentation is available on the church website. The site plans and basic drawings are available in the Marion Methodist and on posters throughout the church. 3. Why not allow live questioning? (9/18/16) Time did not allow. To allow everyone the opportunity to be heard. There will be the opportunity to ask verbal questions at the Church Conference on October 23 rd. 4. Aren t we the communication church? Or are we the church? We have made every attempt to be completely transparent throughout this process via , Marion Methodist, church announcements, mailings, Facebook, etc. A public forum does not allow everyone the opportunity to speak, thereby to allow communication from everyone, written communication has been most effective. 5. Call DB Acoustics in Marion for AV Thank you for the referral. We are considering a number of AV firms who will all have the opportunity to bid on the building project. 6. What impact might the current discussions regarding human sexuality have on the building if the UMC decides to split? It is our intention to move the building project forward in a loving, caring way in the midst of this ongoing conversation. 7. Will church offices move in the future? The What s Next Committee recommended that we leave the church offices in the Carnegie building for the foreseeable future. 8. Sweat equity, will we have the option to paint education rooms (not sanctuary)? This is a possibility that is unplanned at this time. 9. Interior view? Interior finishes? (2x) These decisions have not been made at this time. We will begin to make these decisions once the building project has been approved.

2 10. Taking stained glass windows? How will the existing stained glass windows be incorporated? Will they be reused? Are they going to be used and where? (7x) While the stained glass windows are important to us, it may not be economically feasible to take the ones we want. The moving of the stained glass windows is not included in the building project. If funds beyond the current project were raised specifically for the stained glass windows, the proposed plan would be to have the windows on the east side of the building, external in frames with specialized lighting. The Memorial Committee has identified 5 windows and has prioritized them as follows 1. Jesus window in the sanctuary 2. Moses window in the sanctuary 3. Peace window in the sanctuary Commandments window in the chapel 5. Rose window in the sanctuary 11. Will there be a dedicated space for Barbecue Grilling located to minimize potential harm from grease on the concrete and a safe distance from the building? We hope that the church congregation will make ample use of the outdoor space available while being considerate of the property and membership. 12. Does the plan allow for dumpsters that can be locked and secured at a discrete location with regard to the main entrance? The proposal does include an enclosure for the dumpster which will have the opportunity to be secured. The current plan is to locate the dumpster on the west side of the building. 13. Does the plan include accommodation for the security aspects of the building and our congregation including internal and external video monitoring, remote access, controlled access, and motion sensors? While security is a viable concern, we have not discussed technology or security in any depth at this point but we expect to in the future. 14. How do we execute a wedding? Education classrooms will continue to be available for dressing / staging rooms. These classrooms have close access to restrooms. 15. How do we execute VBS? What does that look like? With greatest creativity as we have always planned. The ample outdoor and fellowship space will be a tremendous asset during VBS. 16. How do we execute a funeral? Access, viewing, etc. The space currently designed will be much more effective in this ministry than our current space. Budgetary 17. Are landscaping features included? Included in budget? (2x) Yes. 18. Will we be selling out parcels for residential (condo) development? No, this is not in our plans. 19. How much money do we have pledged? Currently as of 9/26 we have received $2.57 million in donations for the BUILD Campaign. We have over $600,000 remaining from the successful BELIEVE Campaign. By investing our donations, we have earned approximately $110,000 to date. When these dollars are added to the purchase of the land and our previous commitment to the construction of REC Drive, we have raised over $4 million dollars to support the vision of our building project. The next phase of our capital campaign will begin in early 2017 as the BUILD Campaign completes in March.

3 20. Is snow removal in the budget? The Trustees are beginning to forecast the operational costs for our new building and snow removal will be included. 21. Cost: 9.1 million. The figure of 9.1 million was mentioned was that for everything that we saw tonight? Our builder made an error in reporting. The current bid for everything shown is $9.8 million. 22. Who will own this building? First United Methodist Church of Marion will own the building and hold it in a sacred trust for The Iowa Conference of the United Methodist Church. 23. How do we handle weekly offerings? Security do we need a safe? Our plan is to continue with our present practice to immediately deposit offerings at Farmers State Bank following services. Church Interior: Rooms / Facilities 24. Where is: Choir room, library room, children s library, music, bell choir room puppets, fellowship hall? Dining area? Storage of bell and choir equipment? (Asked 8x) Choir, Bells, Music, Puppets all will rehearse in the sanctuary There is no designated library or children s library room Fellowship hall / dining are in the Narthex Bell storage will be in special tables that are planned for the chancel Choir robes storage in chancel storage area. 25. Where is Youth/ 4:12 space? (Asked 2 x) 4:12 will meet in the sanctuary 26. Where will the choir be? Choir will rehearse and perform in the sanctuary/chancel 27. Glow room is there one? Where? Not planned at this time 28. Music/puppet ministries practice? See 21 above 29. Black out windows for puppets? Will the sanctuary windows be able to be covered to completely darken it? Plans are for power shades on the sanctuary windows 30. How many classrooms do we have/need? There are 10 classrooms, plus two rooms for the nursery, in the current plan. 31. Is the number of classrooms sufficient for both children s and adult classes simultaneously? If not, what is the plan for adult education space? Plans are to design educational opportunities around available space and plan for future expansion. In addition, adult education is currently moving to offsite venues in small groups. 32. Will the walls in the education area dividing the classrooms (particularly on the west and east) be permanent or are they transitional/moveable to allow flexibility to the rooms and be able to make them larger? All walls are fixed. There are currently no provisions for moveable walls in the classrooms. 33. Is the center core of the education wing wide enough to be the right size for a basketball court if that wing is expandable and we need a multi-purpose room? The width of the building is 120 feet. Future expansion would need to take this dimension into consideration. 34. Is there space provided on either side or in back of platform for people to wait to go on stage during (example) plays and puppets? Yes, on both sides

4 35. Will the gathering space have portable walls for smaller events? No, not included at this time 36. Are the squares shown on the drawing in the narthex poles? Pillars in narthex? (Asked 2x) Yes, these are necessary design elements to support the roof structure, provide drainage and access to power in the narthex. 37. Will there be a communion prep station? Yes, the kitchen will be used for this purpose. 38. Administrative offices? Pastor and staff office space? (Asked 2x) Administrative offices will remain in the Carnegie building; however, there will be an administrative space in the new building. 39. Not enough storage? How does 995 sq. f.t of storage space that is proposed compare to storage space in our current building? Currently more storage. (Asked 3x) Yes, we are aware that planned storage space is significantly less than current storage space. 40. Windowless rooms current more storage No, classrooms are not intended as storage spaces. 41. Will there be any basement space under the church? (Asked 3x) No, the entire building is at the same elevation (i.e. the floor is flat throughout). 42. Will there be a storm shelter? Yes, there will be designated shelter space. 43. Distance (feet) from sanctuary to kitchen? (Size of narthex) The Narthex will be 50 x 120, approximately 6,000 sq. ft. Church Interior: Furnishings 44. Pews or chairs? (Asked 3x) Chairs 45. With windows in sanctuary, will there still be AV screens? Yes, the windows will be equipped with shades to allow effective projection onto screens. 46. Do we have TV s in narthex with seating area just outside of sanctuary for cry room space for parents to soothe fussy babies? We will have TVs in the narthex area. We will explore options for cry room space. 47. How does the size of the gathering space compare to the current fellowship hall? How many could it seat for meals? Dinner tables? What is seating capacity for gathering area for meals and how does it compare to current fellowship hall? (Asked 3x) The Narthex area is a little more than twice as large as the current Fellowship Hall. Depending on the setup and types of tables, the capacity will vary but the maximum capacity for seating would be approximately Do we have space planned in women s bathroom for a couch (breast feeding) and changing tables in both men and women s restrooms? Is the ladies restroom larger than what we have now? How many stalls? (Asked 2x) Space is not currently reserved for a couch in the restroom, but there should be changing stations in both the men s and women s restrooms. We will explore options for a breastfeeding area. The restroom areas will meet code requirements and be handicap accessible. We anticipate having a total of 7 women s stalls and two family restrooms along with 4 men s stalls and 3 urinals. 49. As long as we are building new restrooms, we must look at gender neutral ones. We currently have plans for two restrooms that anyone can use.

5 Church Exterior / Parking / Streets 50. Inclement weather for getting someone in a wheelchair no overhead protection from the weather. (Asked 18x) Entry canopy is not included in the budget for Phase 1 at this time, however, depending on financing and construction costs, a canopy could be a consideration for Phase 1 or included in a future phase parking spots? Yet it seats 1,000? Parking for 500 people -- sanctuary holds 1,000. What is the average worship service size (current) vs. projected and will 256 spaces be adequate? Parking needs to support 500 plus parking spaces. (Asked 5x) The amount of parking is determined based on the maximum capacity of the sanctuary (1000 people). Overflow parking may be available on grassy areas if capacity of the planned parking lot is exceeded. The sanctuary capacity of our current building is approximately 400 people. 52. The number of handicapped parking spaces mandated by city code will probably be insufficient for this congregation!!!?? If additional handicap spaces are needed, we could use temporary handicap parking space signs. 53. Parking lot lighting/security Exterior lighting/security is included. 54. Will there be signage on Highway 13? There is no signage currently included in this phase of project. The building front will be visible from Hwy Who pays for streets? (REC Drive & 35 th St) We pay for the streets and the cost is part of the current budget. This is a shared cost with the City and a portion will be paid back when the other half of the streets develop. 56. Is the only way to access the church on Highway 13? Entrance from 35 th Ave.? (Asked 2x) Initially the only access will be from Hwy 13 onto Rec Drive. There will not be access to or from 35 th Ave. 57. Expansion to the south would road need moved to do this? No. Expansion is planned to the south already and the road should not need to be moved. 58. Drives concrete or asphalt? Are ALL of the driveways and parking concrete? (Asked 2x) Concrete is currently planned, but may change depending on material costs at the time of construction. 59. Garages for equipment snow removal, etc. mowers janitorial equipment storage? Planning for an out building? (Asked 3x) This is not currently included in this phase of the project. We anticipate evaluating options for church members to construct an outbuilding on the property. Janitorial equipment storage is included in the new building. 60. Is it a flat roof? Is the shaped roof going to cause more damage of pressure of the center roofing? Too much flat roof and issues? Is the flat roof a cause for concern snow accumulation, leaking, etc. Concerned about the flat roof design. Roof is too flat over classrooms, future maintenance? Flat roof in Iowa solar possible? (Asked 7x) The roof will include sloping to allow for drainage of water. The roof will be designed to adequately handle snow load and drifting in the winter. The roofing materials should allow for relatively low maintenance. Solar panels are not included in this phase of the project. 61. What material will be used for the exterior of the building any brick/stone? What kind of material on building? Is the exterior concrete? (Asked 4x) The exterior is precast concrete. We are evaluating different potential finishes of the concrete.

6 62. Can the visual or curb appeal be improved? Options to improve curb appeal will be ongoing and can be addressed with landscaping, decorative features, or other items. 63. Will the steeple and cross be lit? We are evaluating lighting options for the steeple and cross. 64. The spire could be more inspiring. The feature was designed by the architect. 65. Are solar and geothermal energy being used? Not at this time. 66. Will there be an earth berm along Highway 13 to attenuate noise from the traffic? Highway noise can be very loud, and even a short berm can help. A berm along property boundaries, including Hwy 13, is being evaluated. 67. Rear entrance/exit trash deliveries FLY access to kitchen coolers etc. Means and methods for building access for various activities will be an ongoing discussion with project stakeholders. 68. For ice and snow management around the entrances have heated sidewalks at entry points been considered? Heating of sidewalks is not included. Supplemental questions 69. Is there a janitor room, mop sink, equipment storage, paper supply storage? There is a janitor closet with mop sink that connects to the kitchen and the educational hallway. 70. Will on-site offices be included in the building? See 38 above 71. Will access to restrooms be possible without walking on carpet (can a restroom be accessed from outside without crossing carpet?) The Narthex is not carpeted and restrooms are accessible directly from the Narthex 72. Will there be a family restroom / Handicapped Restroom? Four of six restrooms are handicapped accessible and there are two family restrooms at the back of the sanctuary, also accessible from the Narthex. Children s restrooms are not handicap accessible. 73. Natural lighting control? Yes, see 29 above 74. Will the building design be such that the tech team will not be an intrusive part of the worship experience? The tech team will have dedicated space at the back of the sanctuary 75. Will the interior of the building provide controlled access to different areas? Education space is set up with access doors to keep it separate from the Narthex 76. Will there be ramps on both sides to get up to the Chancel? Access to the Chancel is planned as a ramp on one side only and four sets of steps. 77. Will the kitchen design provide dedicated space for the steam table? Yes 78. Will there be steps up to the Chancel in the center of the stage? Yes 79. Where will money come from to pay interest on principle for new church? It will be paid by congregational giving, either through the general budget or through a debt elimination campaign. 80. Where will UMW keep their program materials? Not known at this time.

Presbyterian Church of the Cross

Presbyterian Church of the Cross Presbyterian Church of the Cross Go Now in Peace! Facilities Expansion Task Force (FETF) Status Briefing to PCOC Congregation FETF Members: Mike Howland, Moderator; Marshall Zieman, Staff Chuck Baddley,

More information

THE BUILDING PLAN October 7th, 2012

THE BUILDING PLAN October 7th, 2012 THE BUILDING PLAN October 7th, 2012 Summary Outline of Strategic Building Plan Introduction: The Strategic Building Plan is the final component, and one of the top priorities of the Church s Vision Plan.

More information

Yorkshire United Methodist Church

Yorkshire United Methodist Church Yorkshire United Methodist Church Yorkshire United Methodist Church York, PA This project provided one exciting challenge after another. With a finite budget to adhere to, the original budget was maintained

More information

Yorkshire United Methodist Church

Yorkshire United Methodist Church Yorkshire United Methodist Church Yorkshire United Methodist Church York, PA This project provided Poole Construction with one exciting challenge after another. With a finite budget to adhere to, Poole

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

Phase II Fellowship Hall

Phase II Fellowship Hall Phase II Floor Plan for Fellowship Hall Kitchen First United Methodist Church NE 419 First Street Gainesville, Florida Serving Area R E S T R O O M s Fellowship Hall Storage Room Chapel Phase II Fellowship

More information

STORY TITLE Story Subtitle or summary

STORY TITLE Story Subtitle or summary Story Subtitle or summary STORY TITLE Story Subtitle or summary GOOD SHEPHERD LUTHERAN CHURCH: LONG RANGE IMPROVEMENT PLAN EXECUTIVE SUMMARY: INTRODUCTION/BACKGROUND Good Shepherd Lutheran Church (GSLC)

More information

Introduction. Priorities and Phasing

Introduction. Priorities and Phasing Introduction The Long Range Planning Committee has prayerfully and carefully assembled this Master Plan as a result of its mission to identify and address the future needs and goals of our church under

More information

FACILITIES COMMITTEE UPDATE MAY 1, Shippensburg First Church of God

FACILITIES COMMITTEE UPDATE MAY 1, Shippensburg First Church of God FACILITIES COMMITTEE UPDATE MAY 1, 2016 Shippensburg First Church of God Committee Members / Purpose Members Larry Bistline Denny Fleagle George Fritz Wayne Gruver Karen Marr Jeanette Roberts Pastor Jim

More information

Corsicana High School

Corsicana High School Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156 FOR SALE 8800 Miller Dr (SW 56 Street) Miami, FL 33156 Completely 12,820 SF 1.87 Acres Presented exclusively by Dimitri Kiosseff of Brown Harris Stevens BHSMiami.com NEW YORK CITY THE HAMPTONS PALM BEA

More information

2016 BUDGET ITEM CONSIDERATIONS 6/4/2015 1

2016 BUDGET ITEM CONSIDERATIONS 6/4/2015 1 2016 BUDGET ITEM CONSIDERATIONS 1 2016 BUDGET ITEM CONSIDERATIONS Replace Wooden Siding on Sanctuary with Vinyl Siding Current siding is plywood with 2x2s nailed to it. It is rotting and some areas need

More information

Park Hill Christian Church. Ministry Support Administrator Job Description and Contract. Adopted December 2016

Park Hill Christian Church. Ministry Support Administrator Job Description and Contract. Adopted December 2016 Park Hill Christian Church Ministry Support Administrator Job Description and Contract Adopted December 2016 If interested in the position described below, please, email Rev. Robert Fugarino at rfugarino@parkhillcc.org,

More information

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING

More information

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION 02001 Bus Traffic. Separation between bus traffic, regular vehicular flow, service traffic and pedestrian traffic. Bus traffic must have adequate

More information

University of New Mexico Environmental Services Design & Development Standard Requirements

University of New Mexico Environmental Services Design & Development Standard Requirements University of New Mexico Environmental Services Design & Development Standard Requirements Please review the following standards to be considered on all construction specifications. Your consideration

More information

With Illustrated Guidelines for Implementation

With Illustrated Guidelines for Implementation MESA COUNTY INDUSTRIAL DEVELOPMENT DESIGN STANDARDS HANDBOOK With Illustrated Guidelines for Implementation November 14, 2011 1 INDEX A. Purpose... 1 B. Applicability... 1 C. Design Standards... 2 1. Site

More information

SUGGESTED GUIDELINES Design Review Board

SUGGESTED GUIDELINES Design Review Board SUGGESTED GUIDELINES Design Review Board The Suggested Design Guidelines for Downtown Holland have been created to provide direction to those seeking approval for a private improvement project falling

More information

Architect and Engineer: Friar Associates inc.

Architect and Engineer: Friar Associates inc. Architect and Engineer: Friar Associates inc. BACKGROUND In June, after soliciting and interviewing several professional firms, Friar Associates was hired to perform an Existing Conditions Survey and Facilities

More information

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for

More information

Trinity Lutheran Church Strategic Plan Report. as of December 2017

Trinity Lutheran Church Strategic Plan Report. as of December 2017 Trinity Lutheran Church Strategic Plan Report as of December 2017 January 2018 Education Committee Goal #1: Strengthening relationships small group ministry Strategy: Create and sustain small group ministries

More information

LUFacilities Policy Service Level Agreement v1.1

LUFacilities Policy Service Level Agreement v1.1 PURPOSE The Service Level Agreement (SLA) for University provides a detailed list of services offered by the LU Department. The SLA identifies which services are funded by the approved Lehigh University

More information

SUGGESTED GUIDELINES Design Review Board

SUGGESTED GUIDELINES Design Review Board SUGGESTED GUIDELINES Design Review Board The Suggested Design Guidelines for Downtown Holland have been created to provide direction to those seeking approval for a private improvement project falling

More information

260,000 SF Building Profile

260,000 SF Building Profile Expanding Your Development & Investment Perspectives 260,000 SF Building Profile Precast & Brick Exterior Finish 245,000 SF Production/Warehouse 7,500 SF Office & 7,500 SF Mezzanine 50 x 50 Bays, 24 Clear

More information

The Report: Priority 1 thru 5 $ 2,124,417 Lifecycle Years 1 thru 3 ½ $ 384,097 New Construction $ 2,451,568 Less Redlined Items $ 43,534

The Report: Priority 1 thru 5 $ 2,124,417 Lifecycle Years 1 thru 3 ½ $ 384,097 New Construction $ 2,451,568 Less Redlined Items $ 43,534 Building Condition Assessment Facilities Feasibility Study 106 - Sam Houston Elementary Educational Needs $ 2,451,568 Safety & Security Needs $ 588,049 Exterior Needs $ 622,503 Interior Needs $ 703,790

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

Expanding Your Development & Investment Perspectives 159,000 SF Building Profile

Expanding Your Development & Investment Perspectives 159,000 SF Building Profile Expanding Your Development & Investment Perspectives 159,000 SF Building Profile Metal & EIFS Exterior Finish 150,000 SF Production/Warehouse 4,500 SF Office & 4,500 SF Mezzanine 50 x 50 Bays, 24 Clear

More information

Myrtle Grove United Methodist Church, Board of Trustees, Project List

Myrtle Grove United Methodist Church, Board of Trustees, Project List Bring in local roofing company to repair roofing areas above the kitchen and fellowship hall. Replace all old polybutylene plumbing pipe & connectors with PEX water line & connectors throughout the Education

More information

Branson Events Center. Real Estate Sales Brochure

Branson Events Center. Real Estate Sales Brochure Branson Events Center Real Estate Sales Brochure Pertinent Information Address: 2527 State Highway 248, Branson, Missouri Sales Price: $6,000,000 Property: Live Entertainment Center with 113,118 sq. ft.

More information

Timberglen Recreation Center Summary

Timberglen Recreation Center Summary Timberglen Recreation Center Summary Address Building Purpose 3810 Timberglen Road Dallas, TX 75287 Recreation Center Original Year of Construction 2003 Building Area 15,000 SF Inspection Date August 2,

More information

HOST A REMOTE ISSACHAR SUMMIT

HOST A REMOTE ISSACHAR SUMMIT HOST A REMOTE ISSACHAR SUMMIT Livestream Guide How-Tos & Helpful Guidelines 1 TABLE OF CONTENTS Introduction 3 Invite Gather a Community 4 Setup Setting the Stage 6 Implementation Starting the Conversation

More information

INSPIRED. by Collaboration

INSPIRED. by Collaboration Close collaboration between structural engineers and architects results in an expressive structural steel-enhanced ethereal experience for a new church in suburban Kansas City. INSPIRED by Collaboration

More information

AMENDMENT TO REQUEST FOR PROPOSALS Janitorial Services UAF Chukchi Campus

AMENDMENT TO REQUEST FOR PROPOSALS Janitorial Services UAF Chukchi Campus 103 Administrative Services Center 3295 College Road Phone (907) 474-7315 Fax (907) 474-7720 Procurement & Contract Services PO Box 757940, Fairbanks, Alaska 99775-7940, www.uaf.edu/procurement/ AMENDMENT

More information

(d) Metal buildings used for industrial uses are not exempt from additional landscape standards as required in Section (e).

(d) Metal buildings used for industrial uses are not exempt from additional landscape standards as required in Section (e). 5.22. Non-Residential and Multifamily Design Standards. 5.22-1 Applicability of Non-Residential Design Standards. All non-residential and multifamily buildings, with the exception of those described in

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls

More information

Facilities Feasibility Study Frederick Douglass HS Condition Assessment

Facilities Feasibility Study Frederick Douglass HS Condition Assessment Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

HIDDEN VALLEY ELEMENTARY SCHOOL

HIDDEN VALLEY ELEMENTARY SCHOOL SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802

More information

Country Club Historic District Architecture Review Committee

Country Club Historic District Architecture Review Committee Country Club Historic District Architecture Review Committee Project: 378 Lafayette St November 8, 018 Dear Landmark Preservation, Our committee would recommend the project @ 378 Lafayette, Rear Addition,

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior

More information

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department. City of Goshen Instructions for Residential Permit Application Why do you need a building permit? Your home is a large investment, and if your construction project does not comply with the codes adopted

More information

Manchester-Shortsville Central School District Red Jacket Excellence Every Student, Every Class, Every Day WHY NOT DO A CAPITAL PROJECT?

Manchester-Shortsville Central School District Red Jacket Excellence Every Student, Every Class, Every Day WHY NOT DO A CAPITAL PROJECT? Manchester-Shortsville Central School District Red Jacket Excellence Every Student, Every Class, Every Day WHY NOT DO A CAPITAL PROJECT? That is the real question. Manchester-Shortsville Central School

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

EXISTING CONDITIONS BTA PROJECT NO: 1722

EXISTING CONDITIONS BTA PROJECT NO: 1722 1 CAROLINE STREET PUTNAM STREET 3 2 PROJECT SITE LOCATION PLAN 1. INTERSECTION OF CAROLINE ST AND PUTNAM ST - LOOKING SOUTHEAST 2. PUTNAM ST - LOOKING NORTHEAST 3. CAROLINE ST - LOOKING WEST EXISTING CONDITIONS

More information

SITE PLAN AND ARCHITECTURAL REVIEW APPLICATION

SITE PLAN AND ARCHITECTURAL REVIEW APPLICATION SITE PLAN AND ARCHITECTURAL REVIEW APPLICATION CITY OF GENEVA, NEW YORK The purpose of the site plan and architectural review process is to secure compliance with the City s Zoning Ordinance and to promote

More information

HERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School

HERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has

More information

PROPERTY INFORMATION

PROPERTY INFORMATION PROPERTY INFORMATION INTRODUCTION The release of Stage 3 at River Terraces features prime semi-elevated sections offering close proximity to the Ngaruawahia Golf Course, Waikato River, Te Awa Cycleway,

More information

Bethlehem Lutheran Church

Bethlehem Lutheran Church BUILDING MASTER PLAN PROPOSAL Accessibility Maintenance Community Bethlehem Lutheran Church Bethlehem Lutheran Church Revised Property Development Plans This new year brings us to a time when The Property

More information

r e s i d e n t i a l o u t s i d e v i l l a g e c e n t e r

r e s i d e n t i a l o u t s i d e v i l l a g e c e n t e r N e w A l b a n y, O h i o r e s i d e n t i a l o u t s i d e v i l l a g e c e n t e r D e s i g n G u i d e l i n e s & R e q u i r e m e n t s s e c t i o n 5 I. Overview This section applies to all

More information

PC 10 05, Request for conditional use permit and and text amendment construct construct new North Education Education Center, Center, 5530 Zealand

PC 10 05, Request for conditional use permit and and text amendment construct construct new North Education Education Center, Center, 5530 Zealand PC 10 05, 05, Request for conditional use permit and text amendment to construct new North Education Center, 5530 Zealand Ave N Planning Commission October 5, 2010 General Information Planning Case: 10-05

More information

Lake Highlands North Recreation Center Summary

Lake Highlands North Recreation Center Summary Lake Highlands North Recreation Center Summary Address Building Purpose 9940 White Rock Trail Dallas, TX 75238 Recreation Center Original Year of Construction 1971 Building Area 33,036 SF Inspection Date

More information

VISION PLANNING TEAM REPORT February 2017 VISION PLANNING TEAM. John Greven Scott Ife Michelle Mills Carol Moffitt Stan Harvey (Facilitator)

VISION PLANNING TEAM REPORT February 2017 VISION PLANNING TEAM. John Greven Scott Ife Michelle Mills Carol Moffitt Stan Harvey (Facilitator) VISION PLANNING TEAM REPORT February 2017 VISION PLANNING TEAM John Greven Scott Ife Michelle Mills Carol Moffitt Stan Harvey (Facilitator) Table of Contents Executive Summary... 2 1. Findings... 3 2.

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

CARPORTS Carports, regardless of size, shape, or construction material are not approved.

CARPORTS Carports, regardless of size, shape, or construction material are not approved. The following list summarizes some of the design elements that the Architectural Review Committee (ARC) and the Board of Directors (BOD) may require. Also required is compliance with all deed restrictions

More information

EMPLOLYMENT APPLICATION P.O. BOX 3810 BUTTE, MT

EMPLOLYMENT APPLICATION P.O. BOX 3810 BUTTE, MT APPLICANT INFORMATION P.O. BOX 3810 BUTTE, MT 59701 406-494-3310 Last Name First M.I. Street of Birth City State ZIP Phone Available Position Applied for Social Security No. E-mail Desired Salary Are you

More information

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING Multi family housing is an increasingly popular form of infill development in Shaker Heights because of the city s built out

More information

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1 GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept

More information

Trinity Episcopal Church Saint Louis. South Parish Hall Renovation campaign

Trinity Episcopal Church Saint Louis. South Parish Hall Renovation campaign Trinity Episcopal Church Saint Louis South Parish Hall Renovation 2012 2013 campaign OVERVIEW The South Parish Hall ( SPH ) at Trinity Episcopal Church in St. Louis Central West End is essential to the

More information

Discipleship Pastor Job Description

Discipleship Pastor Job Description Individual: Accountable to: Johnathan Sublet, Lead Pastor FLSA Classification: Exempt Supervises: Work schedule: Flexible (1 day off Mon-Fri), must be available for ministry work outside of 8 AM 5 AM,

More information

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies

More information

Architectural and Design Guidelines

Architectural and Design Guidelines Architectural and Design Guidelines The Preserve at Parkside Manor- Architectural Review Committee (ARC) The following architectural changes require approval by application to the ARC unless otherwise

More information

2017 City of Ortonville Northridge Study

2017 City of Ortonville Northridge Study 2017 City of Ortonville Northridge Study HASSLEN CONSTRUCTION AND RICE STROMGREN ARCHITECTS / STUDY / Page 1 CONTENTS Existing City Facilities Executive Summary 3 Location of Facilities 4 City Hall/Community

More information

Wildwood Home Owners Association Architectural Review Board Guidelines

Wildwood Home Owners Association Architectural Review Board Guidelines Wildwood Home Owners Association Architectural Review Board Guidelines A. STATEMENT OF OBJECTIVES : 1. It is the intention of Wildwood Home Owners Association, through this review board, to provide the

More information

Phase 1: Preliminary Study

Phase 1: Preliminary Study Phase 1: Preliminary Study September 2013, Scott Simons Architects was hired to conduct a preliminary study. They were asked to determine: 1. Could the library be expanded onsite 2. Was it necessary to

More information

Initial Design & Size

Initial Design & Size Want to Save time and money on your next building project? Careful planning will help you to anticipate problems, make the right decisions, and to speed construction. If you don t know the answers to all

More information

Quality specifications for my home

Quality specifications for my home Quality specifications for my home by 7 Benefits of a dospuntos home 2 Quality specifications Casa Banderas 01 02 Outside: Before you go in: Façades Your home will have a ceramic brick façade finished

More information

DESIGN REVIEW BOARD AGENDA Wednesday, June 14, 2017, 6:30 p.m. Council Chambers, 209 S. Main Street, 2 nd Floor

DESIGN REVIEW BOARD AGENDA Wednesday, June 14, 2017, 6:30 p.m. Council Chambers, 209 S. Main Street, 2 nd Floor City Hall, 209 S. Main Street Marysville, Ohio 43040 1641 (937) 645 7350 FAX (937) 645 7352 www.marysvilleohio.org DESIGN REVIEW BOARD AGENDA Wednesday, June 14, 2017, 6:30 p.m. Council Chambers, 209 S.

More information

Civic Center Renovation News

Civic Center Renovation News Civic Center Renovation News February 15, 2015 Virginia Avery of Wells, ME was the first guest to enter the newly renovated Civic Center at the Maine Home, Remodeling and Garden Show! She was presented

More information

STAGE 9 ARCHITECTURAL GUIDELINES. TAMANI COMMUNITIES #200, Ave SE, Calgary, AB, T2Z 3X1

STAGE 9 ARCHITECTURAL GUIDELINES. TAMANI COMMUNITIES #200, Ave SE, Calgary, AB, T2Z 3X1 STAGE 9 ARCHITECTURAL GUIDELINES TAMANI COMMUNITIES #200, 3132 118 Ave SE, Calgary, AB, T2Z 3X1 T: 403.723.8446 F: 403.212.0161 E: Info@tamanicommunities.com Edgewater Estates - Stage 9 Architectural Guidelines

More information

Commercial Remodel Permit

Commercial Remodel Permit Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each

More information

Laurel School Upper Campus Building Features

Laurel School Upper Campus Building Features Laurel School Upper Campus Building Features INTRODUCTION Laurel School Upper Campus is tucked into the Willows neighborhood in Menlo Park surrounded by residential housing on all sides. The oddly shaped

More information

HANDBOOK FOR SESSION COMMITTEE MODERATORS

HANDBOOK FOR SESSION COMMITTEE MODERATORS HANDBOOK FOR SESSION COMMITTEE MODERATORS Frank Walmsley 1996 Permission is given to use all or part of this document for local church use provided acknowledgement is given to the author. Table of Contents

More information

NC State University Design and Construction Guidelines Division 00 Planning & Design Space Planning

NC State University Design and Construction Guidelines Division 00 Planning & Design Space Planning 1.0 Purpose A. These guidelines provide requirements for the Designer and Contractor to follow related to space planning. 2.0 General Requirements A. Single Occupant Toilet Room Each new or renovated building

More information

CITY OF CEDARBURG. August 3, 2015

CITY OF CEDARBURG. August 3, 2015 CITY OF CEDARBURG PLAN COMMISSION PLN20150803-1 A regular meeting of the Plan Commission of the City of Cedarburg was held on Monday, at Cedarburg City Hall, W63 N645 Washington Avenue, second floor, Council

More information

The Foundation House. Commercial Exterior. Project cost: $442,620.18

The Foundation House. Commercial Exterior. Project cost: $442,620.18 The Foundation House Commercial Exterior Project cost: $442,620.18 Farm Foundation House The Foundation is dedicated to the conservation of the valley and furthering education and preservation. The Foundation

More information

SLOT HOME STRATEGY OVERVIEW

SLOT HOME STRATEGY OVERVIEW ALLEY ALLEY ALLEY SLOT HOME STRATEGY OVERVIEW In recent years, slot homes have been constructed in many neighborhoods throughout Denver, resulting in a new development pattern that can detract from the

More information

AGE-FRIENDLY CHICAGO BUSINESS INITIATIVE HAVE YOU MADE YOUR BUSINESS AGE-FRIENDLY?

AGE-FRIENDLY CHICAGO BUSINESS INITIATIVE HAVE YOU MADE YOUR BUSINESS AGE-FRIENDLY? AGE-FRIENDLY CHICAGO BUSINESS INITIATIVE HAVE YOU MADE YOUR BUSINESS AGE-FRIENDLY? DID YOU KNOW THAT 2013 424,077 2020 498,308 498,308 70% $ $ There are more than 400,000 adults age 60 and older in Chicago

More information

Design Meeting #1 - Minutes

Design Meeting #1 - Minutes 3201 Stanley Street, Stevens Point, WI 54481, 715-345-5000, www.elliswi.com Design Meeting #1 - Minutes Holy Spirit Catholic Parish Addition and Remodeling Church Lower Level September 12, 2018 Attendees

More information

Checklist. Open House & Home Tour THE HOUSE. Flooring. Walls

Checklist. Open House & Home Tour THE HOUSE. Flooring. Walls THE HOUSE Address: Listing Price: Property Tax: Style: Number of Floors: Square Footage: Number of Bedrooms: Bathrooms Appliances Included: Outdoor Space? Yes No Enough Closet Space? Yes No Enough Storage

More information

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved Hinsdale Township High School District 86 Referendum Project Listing April 2, 2019 - Approved 1-12-2019 Project Category and Description Central South Total Security Replace Intercom System Install a completely

More information

FRAMING INSPECTION GENERAL

FRAMING INSPECTION GENERAL FRAMING INSPECTION GENERAL 20 FRAMING INSPECTION GENERAL Tips Check habitable rooms for minimum light, ventilation and sanitation requirements. Check that stair framing meets headroom, width, and rise

More information

TOWN OF BRUNSWICK, MAINE

TOWN OF BRUNSWICK, MAINE TOWN OF BRUNSWICK, MAINE INCORPORATED 1739 DEPARTMENT OF PLANNING AND DEVELOPMENT 85 UNION STREET, SUITE 216 BRUNSWICK, ME 04011 ANNA M. BREINICH, FAICP PHONE: 207-725-6660 DIRECTOR OF PLANNING & DEVELOPMENT

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Exhibit A Library Shell Construction

Exhibit A Library Shell Construction Exhibit A Library Shell Construction Library Component Building Requirements Approximately 15,000-17,000 square feet plus 900 square feet for mechanical room and additional space on roof for installation

More information

EXHIBIT "B-1" DESIGN GUIDELINES SUBDIVISION DESIGN GUIDELINES FOR MELTON RIDGE

EXHIBIT B-1 DESIGN GUIDELINES SUBDIVISION DESIGN GUIDELINES FOR MELTON RIDGE EXHIBIT "B-1" DESIGN GUIDELINES SUBDIVISION DESIGN GUIDELINES FOR MELTON RIDGE DESIGN GUIDELINES SUBDIVISION DESIGN GUIDELINES FOR MELTON RIDGE These Subdivision Design Guidelines are designed specifically

More information

EXCLUSIVELY AVAILABLE!! PRICE: $1,600,000. LKY Advisor s, LLC. Property Description

EXCLUSIVELY AVAILABLE!! PRICE: $1,600,000. LKY Advisor s, LLC. Property Description Former Bank HQ & Data Center w/ Drive-Thru LOCATION: 2031 W. Camelback Rd., Phoenix, AZ 85015 Property Description Building Size: +/- 16,503 SF Lot Size: +/- 43,560 SF Zoning: C-2 (City of Phoenix) 2014

More information

MINUTES OF A REGULAR VOTING MEETING OF THE FAIRFIELD PLANNING COMMISSION OCTOBER 10, 2018

MINUTES OF A REGULAR VOTING MEETING OF THE FAIRFIELD PLANNING COMMISSION OCTOBER 10, 2018 Page 1 of 6 MINUTES OF A REGULAR VOTING MEETING OF THE FAIRFIELD PLANNING COMMISSION OCTOBER 10, 2018 Scott Lepsky called the Regular Meeting of the Fairfield Planning Commission to order. Members present:

More information

BUILDING/FACILITY ACCESSIBILITY CHECKLIST. Lessee. Lessor

BUILDING/FACILITY ACCESSIBILITY CHECKLIST. Lessee. Lessor BUILDING/FACILITY ACCESSIBILITY CHECKLIST Location: Type of Building or Project 1. Is this a newly constructed building? Yes No a. Year plans were approved b. Year built 2. Is this an addition? Yes No

More information

ARCHITECTURAL REVIEW CHECKLIST ARCHITECTURAL REVIEW SUBMITTAL REQUIREMENTS SINGLE MODEL

ARCHITECTURAL REVIEW CHECKLIST ARCHITECTURAL REVIEW SUBMITTAL REQUIREMENTS SINGLE MODEL 9500 Civic Center Drive Thornton, CO 80229 CITY DEVELOPMENT DEPARTMENT ARCHITECTURAL REVIEW CHECKLIST 303-538-7295 Single-Family Detached and Single-Family Attached Homes developmentsubmittals@cityofthornton.net

More information

Public and Institutional Development

Public and Institutional Development Public and Institutional Development Facts to Know INTRODUCTION: In the City of Commerce City, there is one Public zone district, as follows: PUBLIC: Public Zone District Each zone district in Commerce

More information

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project: RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:

More information

SMOKY RIDGE HOMEOWNERS ASSOCIATION ARCHITECTURAL CONTROL COMMITTEE (ACC) GUIDELINES EFFECTIVE DATE: April 22, 2019

SMOKY RIDGE HOMEOWNERS ASSOCIATION ARCHITECTURAL CONTROL COMMITTEE (ACC) GUIDELINES EFFECTIVE DATE: April 22, 2019 SMOKY RIDGE HOMEOWNERS ASSOCIATION ARCHITECTURAL CONTROL COMMITTEE (ACC) EFFECTIVE DATE: April 22, 2019 The Process Defined 1. The completed Architectural Improvement Request Form and all supporting documentation

More information

COMMERCIAL BUILDING PERMIT APPLICATION

COMMERCIAL BUILDING PERMIT APPLICATION COMMERCIAL BUILDING PERMIT APPLICATION Permit No.: Date: PART 1 OWNER/APPLICANT INFORMATION Name Email Address Business Name Address Home/Business Phone Cell Phone PART 2 PROPERTY INFORMATION Street Address

More information

Worship Center. Seating in the Worship Center consists of one mile of pews made in New Holland, Pa.

Worship Center. Seating in the Worship Center consists of one mile of pews made in New Holland, Pa. FACT SHEET NEW CAMPUS INTERESTING FACTS Inside Features Worship Center The Worship Center is built on the second floor the same level of the sky bridge connecting to the Horner Family Center and Parking

More information

Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications

Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications Supplemental Information Requested of Staff from Review Panel Bishop Place Economic Hardship Applications During the review of the application materials submitted with the Bishop Place Economic Hardship

More information

2. House Designs. SAL Review

2. House Designs. SAL Review 2. House Designs 1 Roof has a minimum of 6:12 pitch 2 Minimum roof overhang is 2 feet 3 Roof design must incorporate dormers or gables to the 4 Long slopes of unbroken roof line will not be accepted 5