1 SAFETY FACT SHEETS Working near underground services Safety Non Negotiable G-HS-ST Working near underground services

2 Safety Non-Negotiables (SNN) Zinfra Group is committed to providing a safe workplace in line with our number one company value Health, Safety and the Environment. To bring this value to life, our strategy is to directly manage critical hazards through Safety Non- Negotiables (SNN s) and systematically manage other safety risks. All employees and vendors (whether suppliers, subcontractors or consultants) need to consistently apply the relevant controls stipulated on these SNN s across all Zinfra Group controlled sites. Any deviation from these SNN s will require a documented risk assessment with approval of the direct manager and HSEQ manager.

3 Definition Working near underground services Work conducted in the vicinity of potential services (e.g. electricity, water, gas and telecommunications) installed below ground.

4 Working near underground services - examples Work that may involve work near underground services includes: Installation, repair or maintenance of underground services Building / structure foundations Excavating ground materials Boring and directional drilling

5 Item 1: Must have and follow the Safe Work Method Statement Do you understand the hazards and risks with the work? The most significant risk of working near underground services is a Fatality. This may occur by: Electrocution Fire Explosion Injection/pressure What Safe Work Method Statement (SWMS) are relevant? Are all the controls in the SWMS in place? Is there anything unsafe that should be raised with your supervisor?

6 Item 2 : Follow all issued permit conditions and asset owner requirements Each asset owner may have different requirements when excavating near their underground services, therefore this information must be obtained and all requirements or permit conditions (if issued) followed. An excavation permit must be used when excavating deeper than 300mm. All required information such as technical specifications; drawings etc. must be attached with the Permit and available on site.

7 Item 3 : Only start work with asset owner/dial Before You Dig plans Prior to excavating, the depth and location of existing known services must be identified. Asset owners who are not members of the Dial Before You Dig service should be contacted directly, this may include private asset owners. Asset owners may also need to be contacted if a site survey indicates that there may be additional services not indicated on the Dial Before You Dig plans. All information gathered regarding the location of services must be provided to the site operator and the spotter.

8 Item 4: Use a trained spotter A trained spotter must be used when operating plant near underground services. The spotter should: Have all service location information. Assist with visually locating underground or covered services; Warn of any other unsafe conditions; Be positioned at a suitable location to effectively observe the work; Be able to immediately and effectively communicate with the operator; Not observe more than one work activity at a time; Have the authority to suspend the work at any time.

9 Item 5: Carry out a site survey to locate and mark the services Prior to any excavation work, any Dial Before You Dig plans must be confirmed as accurate and services marked out on site. A walk around the site along the length of the proposed excavation/trench and around nearby corners should be conducted to check service location and potentially idenfity additional services not located on the Dial Before You Dig/asset owner plans. Once identified using these devices, care should be taken to mark the location of the underground asset on the ground s surface.

10 Item 6: Visually confirm and record the depth and location of services at regular interval using non-destructive digging methods when services are within the excavation area Non-destructive digging methods must be used when services are within the excavation area. Pot-holing at each service crossing and at regular spacing along services should be completed. The amount of pot-holing should be determined as part of the risk assessment for the works e.g. the greater number of services, the shorter the interval of potholing.

11 Item 7: Provide all service location information to the site operator and spotter All information gathered regarding the location of services must be provided to the site operator and the spotter.

12 Item 8: Protect all exposed high risk services with a physical protection when damage may occur When high risk services are exposed, temporary physical barriers or guards must be installed to provide an additional layer of protection. If operating mechanical plant (excavating), using powered hand tools or moving loads in close proximity to a high risk service and there is a risk of damage, the temporary barrier must be placed and secured during that work. High Risk Services include: High pressure gas services, mains and pipelines Low, high and extra high voltage electricity cables

13 Item 9: Follow the approved drilling profile during drilling works For all boring activities, the drilling profile must be determined prior to the works and followed during the bore itself. The approved drilling profile will be part of the construction or design specifications.

14 Item 10: When using mechanical excavation methods maintain a minimum clearance of 300mm from services crossing the excavation The clearance distances for mechanical excavation will depend on the type of service and asset owner requirements. These distances should be obtained prior to the works and the requirements or permit conditions (if issued) followed. Where an underground service crosses or intersects the excavation a minimum clearance of 300 mm must be maintained.

15 Item 11: Seek written approval before proceeding with any changes in the scope of works Any potential changes to the scope of works or the drilling profile must be approved by an authorised person; this may include the design manager, engineer or client.

SAFETY FACT SHEETS. Working with and around High Risk Plant Safety Non Negotiable. G-HS-ST Working with and around High Risk Plant

SAFETY FACT SHEETS. Working with and around High Risk Plant Safety Non Negotiable. G-HS-ST Working with and around High Risk Plant SAFETY FACT SHEETS Working with and around High Risk Plant Safety Non Negotiable G-HS-ST-00741 Working with and around High Risk Plant Safety Non-Negotiables (SNN) Zinfra Group is committed to providing

More information

SAFETY FACT SHEETS. Working in or near Traffic Safety Non Negotiable. G-HS-ST Working in or near Traffic. G-HS-FS Version:1

SAFETY FACT SHEETS. Working in or near Traffic Safety Non Negotiable. G-HS-ST Working in or near Traffic. G-HS-FS Version:1 SAFETY FACT SHEETS Working in or near Traffic Safety Non Negotiable G-HS-ST-00737 Working in or near Traffic Safety Non-Negotiables (SNN) Zinfra Group is committed to providing a safe workplace in line

More information

WORK IN THE VICINITY OF UNDERGROUND ASSETS

WORK IN THE VICINITY OF UNDERGROUND ASSETS CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF UNDERGROUND ASSETS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD

More information

Contractor s Guide to Applying for Permit to Dig/Excavate

Contractor s Guide to Applying for Permit to Dig/Excavate Contractor s Guide to Applying for Permit to Dig/Excavate Page 1 of 15 Contractor s Guide to Applying for Permit to Dig/Excavate Contents Purpose... 3 Inclusion Group... 3 1. Pre commencement worksite

More information

Using earthmoving equipment near overhead electrical assets

Using earthmoving equipment near overhead electrical assets A handbook for workplaces Using earthmoving equipment near overhead electrical assets Edition No. 1 December 2009 On 18 June 2017, the Occupational Health and Safety Regulations 2017 (OHS Regulations 2017)

More information

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ML&P ELECTRICAL FACILITY CLEARANCE REQUIREMENTS FOR CONSTRUCTION OR MAINTENANCE NEAR ELECTRICAL FACILITIES July 31, 2014 MUNICIPAL LIGHT & POWER ELECTRICAL

More information

Worksite Safety Update Promoting safety in road construction

Worksite Safety Update Promoting safety in road construction Worksite Safety Update Promoting safety in road construction No 122 August 2012 In this Edition: Work Near Overhead and Underground Utility Services Page 1 The Regional Rail Link Experience Page 9 This

More information

Excavation Monitoring and Observation

Excavation Monitoring and Observation Purpose Reference Appendices Related Toolbox Topics This document contains items to consider when developing a process to monitor or observe excavation activity after a one-call ticket has been analyzed

More information

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS.

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. Date of issue 27/01/2017 Date of next review 29/01/2018 Page 1 V4 18/07/2018 CONTENTS CONTENTS... 2 WORKING SAFELY...

More information

The Essential First Step.

The Essential First Step. The Essential First Step. Australia s national referral service for information on infrastructure networks. Dial Before You Dig Dial Before You Dig is a not for profit organisation that delivers a vital

More information

Apply for Permit to Dig/Excavate

Apply for Permit to Dig/Excavate Apply for Permit to Dig/Excavate Title: Apply for Permit to Dig/Excavate (Guide) Date Published: 23/03/2018 Page 1 Apply for Permit to Dig/Excavate 1 Introduction 3 1.1 Purpose 3 1.2 Inclusion Group 3

More information

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2 Purpose This procedure provides guidance to the Diocese of Maitland Newcastle (DoMN), principal contractors and other persons conducting a business or undertaking (PCBU) who commission or carry out construction,

More information

Veriforce TG CCT 607OP. Training Guide

Veriforce TG CCT 607OP. Training Guide Training Guide Directions: This training guide is to be used by a Veriforce Authorized Evaluator/Trainer and Trainee during on-thejob training (OJT) or prior to an evaluation as a resource. (S) Indicates

More information

SAFE WORKPLACE PROCEDURE No. 222 WORKING NEAR OVERHEAD & UNDERGROUND SERVICES

SAFE WORKPLACE PROCEDURE No. 222 WORKING NEAR OVERHEAD & UNDERGROUND SERVICES SAFE WORKPLACE PROCEDURE No. 222 WORKING NEAR OVERHEAD & UNDERGROUND SERVICES 1. PURPOSE This procedure is intended to assist Southern Rural Water (SRW) to meet its Occupational Health and Safety obligations

More information

Excavation/Floor Penetration Permit

Excavation/Floor Penetration Permit 1. General Details* (to be completed by Applicant) PR Number: (Or Work Request No.) Proposed Start Date: Building: Level: Room: Proposed End Date: Description of Works: Disruption to building users/rmit

More information

SITE - HEALTH & SAFETY COLD EYE S REVIEW

SITE - HEALTH & SAFETY COLD EYE S REVIEW SITE - HEALTH & SAFETY COLD EYE S REVIEW NOVEMBER 2016 BENCHMARK AGAINST WHAT DOES GOOD HS LOOK LIKE Steve McFadden: HSE Strategic & Technical advisor SUMMARY SM Consulting was asked to undertake a site

More information

Field Instruction. All Horizon Power workers who work in and around excavations.

Field Instruction. All Horizon Power workers who work in and around excavations. 6.4 Excavation work and directional drilling Purpose This instruction provides the minimum requirements for: All Horizon Power workers who work in and around excavations. All Horizon Power workers who

More information

Site Rules. Regulation Excavations Page 1 of Excavations

Site Rules. Regulation Excavations Page 1 of Excavations Page 1 of 11 2. Contents: 1. Introduction 2. Organizational aspects 3. Risk inventory and evaluation 4. Safety aspects of pit and trench digging 5. in the vicinity of cables 6. in the vicinity of pipelines

More information

Ensure your own actions reduce risks to health and safety

Ensure your own actions reduce risks to health and safety Ensure your own actions reduce risks to health and safety UNIT SM 1 Area of competence This unit is designed to demonstrate competence in following the health and safety duties required in the workplace

More information

Policy Statement. Objective. Context. References and Supporting Documentation. Policy Statement

Policy Statement. Objective. Context. References and Supporting Documentation. Policy Statement Policy Statement Subject Guidelines for Placement of Power Poles Within Road Reserves in Built-Up Areas Approved by Robert Rogerson Signature & Date Distribution Standards and Policy Manager Authorised

More information

Application for Permit for Installation of Utilities or Placing Underground Construction

Application for Permit for Installation of Utilities or Placing Underground Construction Application for Permit for Installation of Utilities or Placing Underground Construction City of Hanover, MN / cityhall@ci.hanover.mn.us City of Hanover Permit No. Applicant is responsible for all locations

More information

PRO Ground Disturbance

PRO Ground Disturbance MS&L Procedure PRO-4.5-0001-1-03 Ground Disturbance Version: 3 Authorised by: Tom Angliss & Owen Quake Authorisation Date: 21/11/2017 This document has been approved for release and changed as per the

More information

APPENDIX D DIRECTIONAL BORING GUIDELINES

APPENDIX D DIRECTIONAL BORING GUIDELINES The City of Winnipeg Appendix D Bid Opportunity No. 180 163-2016 Page 1 of 1 Template Version: C420150806 - RW APPENDIX D DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional Boring

More information

APPENDIX D C DIRECTIONAL BORING GUIDELINES

APPENDIX D C DIRECTIONAL BORING GUIDELINES The City of Winnipeg Appendix C D Bid Opportunity No. 19-2015 18 2015 Page 1 of 1 Template Version: C420150116 - RW APPENDIX D C DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional

More information

WORKING NEAR HORIZON POWERS UNDERGROUND & OVERHEAD ELECTRICAL NETWORK

WORKING NEAR HORIZON POWERS UNDERGROUND & OVERHEAD ELECTRICAL NETWORK WORKING NEAR HORIZON POWERS UNDERGROUND & OVERHEAD ELECTRICAL NETWORK Horizon Power 2018 Prepared by Field Practices Safety and Health Corporate Services & Company Secretary DOCUMENT CONTROL Document Owner

More information

HSEQ GUIDELINE FOR WORK

HSEQ GUIDELINE FOR WORK HSEQ GUIDELINE FOR WORK IN VICINITY OF ADDC ASSETS Effective Date : 01/09/2013 Procedure #: GL.GN.06 Issue: 01 Revision: 0 Page 2 of 12 Approved by: Managing Director TABLE OF CONTENTS Contents AMENDMENTS

More information

Interim Guideline for Excavating in the Proximity of Underground Distribution Lines

Interim Guideline for Excavating in the Proximity of Underground Distribution Lines Interim Guideline for Excavating in the Proximity of Version 2.0 Ontario Regulation 22/04 Electrical Distribution Safety Issue date: January 9, 2019 Legal Disclaimer. This document contains GUIDELINES

More information

Damage to Underground Infrastructure British Columbia, Ontario and Quebec

Damage to Underground Infrastructure British Columbia, Ontario and Quebec Damage to Underground Infrastructure, and and Highlights Data collection The Common Ground Alliance (CGA) created the Damage Information Reporting Tool (DIRT) in 2003. DIRT is an online database used to

More information

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings G U I D E L I N E S F O R L A N D O W N E R S, D E V E L O P E R S A N D C O N T R A C T O R S T A B L E O F C O N T E N T S 1 Introduction 2 Office Locations/Map 3 General Requirements 4 Structures and

More information

Overhead Power Lines. Corporate Safety Policy Overhead Power Lines. (Cont.)

Overhead Power Lines. Corporate Safety Policy Overhead Power Lines. (Cont.) Corporate Safety Policy Overhead Power Lines Last Modified: JAN 2013 1 of 6 Overhead Power Lines I Purpose To provide procedures, for working on overhead power lines or in their vicinity on COMPANY sites,

More information

Adopt Best Safety Practices & Prevent Cable Damages BEWARE BEFORE YOU DIG!

Adopt Best Safety Practices & Prevent Cable Damages BEWARE BEFORE YOU DIG! Adopt Best Safety Practices & Prevent Cable Damages BEWARE BEFORE YOU DIG! Index Always remember 991 Statistics Cable faults Cable damages Things you need to know before starting excavation, digging Before

More information

Guidelines for Scaffolding near Service Lines. Version 1 March 2014

Guidelines for Scaffolding near Service Lines. Version 1 March 2014 Guidelines for Scaffolding near Service Lines Version 1 March 2014 Erecting, dismantling and use of scaffold near service lines This guideline has been developed to provide guidance for the erection, dismantling

More information

SS 576 : 2012 KEY REQUIREMENTS AND APPLICABLE LEGISLATION. Presented by : Er Joseph Michael

SS 576 : 2012 KEY REQUIREMENTS AND APPLICABLE LEGISLATION. Presented by : Er Joseph Michael SS 576 : 2012 KEY REQUIREMENTS AND APPLICABLE LEGISLATION Presented by : Er Joseph Michael Part 1 - Key Requirements of SS 576 : 2012 Identification of Key Stakeholders The Key Stakeholders are defined

More information

Work Health & Safety Procedure

Work Health & Safety Procedure 1 PURPOSE This procedure explains the process for qualification of Contractors at Port of Newcastle (PON). It outlines the responsibilities for PON Representatives and Contractors. It also provides a system

More information

Permit Manager Training Guide Apply for Permit to Isolate High Voltage

Permit Manager Training Guide Apply for Permit to Isolate High Voltage Permit Manager Training Guide Apply for Permit to Isolate High Voltage Details of revisions Level Details Date Initial 01 Creation of initial document for use 06-01-17 J.O S 02 Revisions from Permit Workshops

More information

FCX Department of Occupational Health and Safety. Contents. Open-Hole Policy

FCX Department of Occupational Health and Safety. Contents. Open-Hole Policy FCX Department of Occupational Health and Safety Open-Hole Policy Approval Date: 12/09/13 Original Date: 03/30/09 SOP # FCX-01 Revision # 6 Supersedes X High Medium Task Risk Low NA Contents 1.0 Policy...2

More information

Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice)

Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice) Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice) Version 3 June 2014 Authorised by Arrium Safety Council TOOL75.WHS.COP.001 Critical Elements from the Code

More information

21-Jul-17. Buried Services. Presentation Title: Insert > Header & Footer / 1

21-Jul-17. Buried Services. Presentation Title: Insert > Header & Footer / 1 21-Jul-17 Buried Services Presentation Title: Insert > Header & Footer / 1 Buried Service strikes At present we are averaging one buried services strike a month. This level of activity is likely to result

More information

SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland

SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland April 2015 Contents Page Acknowledgements... 4 1. Preface... 5 1.1 Introduction... 5 1.3

More information

Information Brochure. Requirements for working in the vicinity of TransGrid Underground Cables

Information Brochure. Requirements for working in the vicinity of TransGrid Underground Cables Requirements for working in the vicinity of TransGrid Underground Cables Contents 1. Introduction 1 2. Definitions 2 Terminology used on Route Plans 2 3. Working in the vicinity of underground power cables

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height

More information

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES

More information

INTERSOL BP Remediation Management. Mary Heyes HSSE Manager, Europe, Middle East & Africa

INTERSOL BP Remediation Management. Mary Heyes HSSE Manager, Europe, Middle East & Africa INTERSOL 2007 BP Remediation Management HSSE Management in Europe: Experience at Contaminated Sites Mary Heyes HSSE Manager, Europe, Middle East & Africa Remediation Management Rationale A centralised

More information

Ground Disturbance or Surface Penetration

Ground Disturbance or Surface Penetration PURPOSE To define the minimum requirements for managing the health and safety risks associated with ground disturbance or surface penetration activities. Where: Ground disturbance involves digging, excavation,

More information

香港電燈有限公司 THE HONGKONG ELECTRIC CO., LTD. ************************************

香港電燈有限公司 THE HONGKONG ELECTRIC CO., LTD. ************************************ Page 1 of 7 Revision Date: 08/2010 香港電燈有限公司 THE HONGKONG ELECTRIC CO., LTD. ************************************ GENERAL PRACTICE ON EXECUTION OF EXCAVATION AND CONSTRUCTION WORK NEAR UNDERGROUND ELECTRICITY

More information

[ insert name of contractor ] Date: [ ] [ insert address of contractor ] Co. Registration No.: [ ] Our Ref:

[ insert name of contractor ] Date: [ ] [ insert address of contractor ] Co. Registration No.: [ ] Our Ref: [ insert name of contractor ] Date: [ ] [ insert address of contractor ] Co. Registration No.: [ ] Your Ref: [ ] Our Ref: [ ] Dear Sir REQUIREMENTS FOR EARTHWORKS AT [ insert location ] (Site Meeting Date:

More information

BEHAVIOUR ON SAFE SITES

BEHAVIOUR ON SAFE SITES Page: 1 of 8 P932 (a) Introduction: Black & Veatch has set a target of achieving ZERO incidents and injuries across all of its business operations. At B&V, we believe that zero incidents and injuries are

More information

REFURBISHMENT DEMOLITION

REFURBISHMENT DEMOLITION CONTRACTOR WHS HAZARD STANDARD REFURBISHMENT DEMOLITION EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Setting national standards for utilities coordination and protection SCIRT leads the way

Setting national standards for utilities coordination and protection SCIRT leads the way Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

Ohio Utilities Protection Service Safety Presentation

Ohio Utilities Protection Service Safety Presentation Ohio Utilities Protection Service 2014 Safety Presentation Ohio Utilities Protection Service is the call before you dig notification center for the state of Ohio. O.U.P.S. is the communication link between

More information

Know Recognize Respond PIPELINE SAFETY IN YOUR COMMUNITY PARA UNA COPIA EN ESPAÑOL POR FAVOR VISITE

Know Recognize Respond PIPELINE SAFETY IN YOUR COMMUNITY PARA UNA COPIA EN ESPAÑOL POR FAVOR VISITE PIPELINE SAFETY IN YOUR COMMUNITY PARA UNA COPIA EN ESPAÑOL POR FAVOR VISITE WWW.VALERO.COM Know Recognize Respond Pipeline Purpose and Reliability Valero knows that being a good operator also means being

More information

NZQA registered unit standard version 1 Page 1 of 5. Identify and inspect road safety barrier systems on Infrastructure Works sites

NZQA registered unit standard version 1 Page 1 of 5. Identify and inspect road safety barrier systems on Infrastructure Works sites Page 1 of 5 Title Identify and inspect road safety barrier systems on Infrastructure Works sites Level 4 Credits 10 Purpose People credited with this unit standard are able to: identify and explain road

More information

BILL AS INTRODUCED H Page 1 of 8. Subject: Utilities; underground; damage prevention system; hot water and

BILL AS INTRODUCED H Page 1 of 8. Subject: Utilities; underground; damage prevention system; hot water and BILL AS INTRODUCED H. 0 Page of 0 H. Introduced by Representative Sibilia of Dover Referred to Committee on Date: Subject: Utilities; underground; damage prevention system; hot water and steam facilities

More information

CONTRACTOR WHS HAZARD STANDARD MOBILE POWERED PLANT EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD MOBILE POWERED PLANT EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD MOBILE POWERED PLANT EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

ESSENTIAL STANDARD no.1. Excavations

ESSENTIAL STANDARD no.1. Excavations ESSENTIAL STANDARD no.1 Excavations KEY MESSAGES Ensure that public safety and the safety of those doing the work is the number one priority. Plan to use the best/correct method. For example, where space

More information

Safe Work Method Statement

Safe Work Method Statement Safe Work Method Statement 01 WHAT IS A SWMS? A SWMS is a document that sets out the high risk construction work activities to be carried out at a workplace, the hazards arising from these activities and

More information

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10

Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors. Northeast Utilities Safety 12/10 Safety & Environmental Orientation Program for Northeast Utilities Transmission Contractors Northeast Utilities Safety 12/10 How Electric Utilities Work Plan the Work & Work the Plan! Agenda Introduction

More information

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation.

Duty holders under the OHS Act and OHS Regulations should use the Code together with this legislation. 1 PREFACE This Compliance Code (Code) provides practical guidance for those who have duties or obligations in relation to demolition sites under the Occupational Health and Safety Act 2004 (OHS Act) and

More information

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 1.0 PURPOSE To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 2.0 BACKGROUND Excavation activities are highly dangerous and thus require adequate planning

More information

GUIDE FOR UNDERTAKING WORK NEAR UNDERGROUND ASSETS

GUIDE FOR UNDERTAKING WORK NEAR UNDERGROUND ASSETS CONSTRUCTION AND UTILITIES JULY 2004 GUIDE FOR UNDERTAKING WORK NEAR UNDERGROUND ASSETS A GUIDE TO THE NO GO ZONES WorkSafe s expectations for safe work practice. On 18 June 2017, the Occupational Health

More information

Safe Work Method Statement (SWMS) for Painting projects

Safe Work Method Statement (SWMS) for Painting projects Safe Work Method Statement (SWMS) for Painting projects This SWMS is a site specific statement that must be prepared before any high risk construction work is commenced. Painting company: Address: Principle

More information

To Loughborough University Facilities Management (FM) Health and Safety Policy

To Loughborough University Facilities Management (FM) Health and Safety Policy Annex DD To Loughborough University Facilities Management (FM) Health and Safety Policy Work involving excavations Purpose According to the Occupational Safety and Health Administration (OSHA), the fatality

More information

CONSTRUCTION CLIENT INDUCTION CARDS

CONSTRUCTION CLIENT INDUCTION CARDS CONSTRUCTION CLIENT INDUCTION CARDS CAUTION! TRADE ON SITE BUSINESS NAME: SITE CONTACT: BUSINESS NUMBER: SITE NUMBER: SITE HAZARDS CONTROLS REQUIRED Everyone must be inducted to this worksite tidy & walkways

More information

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities CONTRACTOR SAFETY PROGRAM PURPOSE: The Contractor Safety Program (CSP) establishes that contractors are required to work in compliance with legislation, regulations and the Town of Caledon health and safety

More information

1 HB By Representative Greer. 4 RFD: Transportation, Utilities and Infrastructure. 5 First Read: 03-MAR-15. Page 0

1 HB By Representative Greer. 4 RFD: Transportation, Utilities and Infrastructure. 5 First Read: 03-MAR-15. Page 0 1 HB62 2 164367-2 3 By Representative Greer 4 RFD: Transportation, Utilities and Infrastructure 5 First Read: 03-MAR-15 Page 0 1 2 ENROLLED, An Act, 3 To amend Section 37-15-2 of the Code of Alabama 4

More information

EXCAVATION PROCEDURE

EXCAVATION PROCEDURE TABLE OF CONTENTS 1 PREFACE... 3 2 OBJECTIVE... 3 3 SCOPE... 3 4 RELATED DOCUMENTS... 3 5 PURPOSE... 3 6 PPA EXCAVATION PERMIT FORM... 4 6.1 THE EXCAVATION PERMIT FORM.... 4 6.2 WHERE TO OBTAIN THE EXCAVATION

More information

ELECTROMAGNETIC ENERGY

ELECTROMAGNETIC ENERGY CONTRACTOR WHS HAZARD STANDARD ELECTROMAGNETIC ENERGY EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Pipeline Safety Information for Schools

Pipeline Safety Information for Schools Pipeline Safety Information for Schools Application of this information can help: Determine the presence of nearby pipelines Aide in the recognition and response of a pipeline leak Provide advance planning

More information

OWA Vendor Pre-Qualification System

OWA Vendor Pre-Qualification System OWA Vendor Pre-Qualification System March 2008 Vendor s Name An OWA Vendor is defined as any individual or company hired to provide services or supplies under contract to the OWA. The steps of the OWA

More information

Partner Update MITA. Doug Needham, P.E. Michigan Infrastructure & Transportation Association Vice President of Industry Relations

Partner Update MITA. Doug Needham, P.E. Michigan Infrastructure & Transportation Association Vice President of Industry Relations Partner Update MITA Doug Needham, P.E. Michigan Infrastructure & Transportation Association Vice President of Industry Relations Work Zone Safety Industry group formed with a goal to increase safety in

More information

TECHNICAL PROCEDURE TABLE OF CONTENTS

TECHNICAL PROCEDURE TABLE OF CONTENTS TECHNICAL PROCEDURE No. Page DATE: 07/3/5 CATEGORY UNDERGROUND STRUCTURES SUBJECT OF SMUD s UNDERGROUND TRANSMISSION TABLE OF CONTENTS PURPOSE... 2 2 REFERENCES... 2 3 MINIMUM REQUIREMENTS... 2 4 RELATED

More information

Client Assessment of Requirements to make Particular Safety & Health Appointments

Client Assessment of Requirements to make Particular Safety & Health Appointments Client Assessment of Requirements to make Particular Safety & Health Appointments > Contents Form 1...... Client Checklist - Does the project involve Construction Work? Form 2...... Client Checklist -

More information

Welcome to the MOL Explosives Blitz webinar

Welcome to the MOL Explosives Blitz webinar Welcome to the MOL Explosives Blitz webinar Thank you for joining us! We will be getting started at 10:00 a.m. EST To access the audio portion of this webinar, please phone: 1. 866. 613. 5223 Access code:

More information

Excavations. OSHA (Revised)

Excavations. OSHA (Revised) Excavations OSHA 2226 2002 (Revised) Contents Introduction... 1 What is the difference between an excavation and a trench?... 1 What are the dangers of trenching and excavation operations?... 1 OSHA s

More information

District No.: Applicant: Type of Work:

District No.: Applicant: Type of Work: Fee: Permit No.: District No.: Applicant: Type of Work: FOR DEPARTMENT USE ONLY APPLICATION AND ANNUAL PERMIT FOR TELECOMMUNICATION OCCUPANCY OF NEVADA DEPARTMENT OF TRANSPORTATION RIGHT-OF-WAY (Under

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT COMPANY DETAILS: Company Name Address CLIENT DETAILS: Principal contractor Contact name Phone no. Mobile: Phone no. Mobile: Works manager Contact no.: Project/owner name Work activity Scope of work covered

More information

Knowing what s below will help protect you, your family and your neighbors

Knowing what s below will help protect you, your family and your neighbors About EQT Corporation EQT Corporation is an integrated energy company with emphasis on Appalachian area natural gas production, gathering, transmission, and distribution. EQT is the general partner and

More information

Iron Ore Company of Canada Health, Safety & Environment

Iron Ore Company of Canada Health, Safety & Environment Barricading 1 PURPOSE To protect personnel by preventing or controlling access to hazards in work areas by the installation and maintenance of barricades, demarcation and restricting access. This work

More information

RESOLUTION NO COL Excavation/TrenchingPolicy ADOPTING THE CAYUGA COUNTY EXCAVATION/TRENCHING SAFETY POLICY FOR COUNTY EMPLOYEES.

RESOLUTION NO COL Excavation/TrenchingPolicy ADOPTING THE CAYUGA COUNTY EXCAVATION/TRENCHING SAFETY POLICY FOR COUNTY EMPLOYEES. RESOLUTION NO. 414-13 11-26-13 COL Excavation/TrenchingPolicy ADOPTING THE CAYUGA COUNTY EXCAVATION/TRENCHING SAFETY POLICY FOR COUNTY EMPLOYEES. BY: Hon. George Fearon, Chairman Government Operations

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

OUTLAW AUTOMATION INC. Safety Management System

OUTLAW AUTOMATION INC. Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 Purpose The purpose of this program is to provide employees general information for working on owner client or other

More information

Appendix 4A - SWMS Description

Appendix 4A - SWMS Description SAFE WORK METHOD STATEMENT (SWMS) Duty holders A person conducting a business or undertaking (PCBU) carrying out any high risk work in connection with a construction project is required to have a detailed

More information

Guidance on Avoiding Danger from Underground Electricity Cables based on HSE Document HS(G)47

Guidance on Avoiding Danger from Underground Electricity Cables based on HSE Document HS(G)47 Guidance on Avoiding Danger from Underground Electricity Cables based on HSE Document HS(G)47 This information is provided as guidance only to be used in conjunction with Safe Digging Practices in the

More information

PROPERTY SERVICES OPERATING PROCEDURE

PROPERTY SERVICES OPERATING PROCEDURE This is a internal document and is only applicable to the internal operations of the RMIT. OPERATING PROCEDURE INTENT The Permit to Work (PTW) procedure is a formal written system used to control certain

More information

Transmission Line Worker

Transmission Line Worker COMPETENCY-BASED OCCUPATIONAL FRAMEWORK FOR REGISTERED APPRENTICESHIP Transmission Line Worker ONET Code: 49-9051 RAPIDS Code: 0282 Created: February 2018 Updated: This project has been funded, either

More information

INDUCTION INFORMATION

INDUCTION INFORMATION INDUCTION INFORMATION The following pages are a guide to help you induct any clients or visitors. They list the common hazards found on most sites. You can also use the QR code on your Hazard Board to

More information

GUIDELINES FOR PROPERTY DEVELOPMENT

GUIDELINES FOR PROPERTY DEVELOPMENT FOR PROPERTY DEVELOPMENT TABLE OF CONTENTS SPECIAL THANKS 1 GUIDELINES FOR PROPERTY DEVELOPMENT 3 GUIDELINES FOR CROSSING PIPELINES, GAS TRANSMISSION LINES, MAINS AND SERVICE CONNECTIONS 5 GUIDELINES FOR

More information

The Miss Utility process begins when a locate request is received by the Virginia Utility Protection Service, more commonly known as Miss Utility.

The Miss Utility process begins when a locate request is received by the Virginia Utility Protection Service, more commonly known as Miss Utility. The Miss Utility process begins when a locate request is received by the Virginia Utility Protection Service, more commonly known as Miss Utility. A normal ticket takes 48-hours to clear starting at 7:00

More information

Safe Management of Contractors Policy

Safe Management of Contractors Policy Safe Management of Contractors Policy Stour Federation Stour Federation Safe Management of Contractors, Page 1 1.! INTRODUCTION 1.1! Shipston-on-Stour Primary School and Acorns Primary School accept the

More information

Client Requirements to make Particular Safety & Health Appointments

Client Requirements to make Particular Safety & Health Appointments Client Requirements to make Particular Safety & Health Appointments REVISED IN ACCORDANCE WITH THE SAFETY HEALTH AND WELFARE AT WORK (CONSTRUCTION) REGULATIONS 2013. > Contents Form 1...... Client Checklist

More information

Excavation General Awareness Safety Training Presentation Red Willow Production Co.

Excavation General Awareness Safety Training Presentation Red Willow Production Co. Excavation General Awareness Safety Training Presentation Red Willow Production Co. Learning Objectives Understand the purpose of our Excavation SOP - to protect employees and contractors when working

More information

NZQA registered unit standard version 3 Page 1 of 5

NZQA registered unit standard version 3 Page 1 of 5 Page 1 of 5 Title Operate the drill rig for horizontal directional drilling Level 3 Credits 15 Purpose People credited with this unit standard are able to: care for and maintain horizontal directional

More information

Work involving excavations

Work involving excavations Annex DD To Loughborough University Facilities Management (FM) Health and Safety Policy Work involving excavations All persons who carry out or work in excavations have a duty to :- Comply with the Safety

More information

Corporate Policy and Procedure

Corporate Policy and Procedure Corporate Policy and Procedure POLICY CATEGORY AUTHORITY RELATED POLICIES APPROVED BY Safety Management When Outside Contractors are Retained (Contractor Safety Management Program) (the Policy ) Health

More information

1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY

1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY 1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY Purpose and Applicability The purpose of this Program is to ensure that Imhoff Custom Services Inc. employees who operate aerial or scissor lifts have the

More information

GUIDELINES FOR PROPERTY DEVELOPMENT

GUIDELINES FOR PROPERTY DEVELOPMENT F O R P R O P E R T Y D E V E L O P M E N T A N A M E R I C A N P E T R O L E U M I N S T I T U T E P U B L I C A T I O N FOR PROPERTY DEVELOPMENT TABLE OF CONTENTS SPECIAL THANKS 1 FOR PROPERTY DEVELOPMENT

More information

INVESTIGATION RESULTS

INVESTIGATION RESULTS September 13, 2011 Burt Fleischer, R.E.A., R.E.P. Director, Environmental Affairs Hilmar Cheese Company 9001 N. Lander Avenue Hilmar, CA 95324 Subject: Revised Work Plan for Supply Well IN 1 Destruction

More information

Excavation and Trenching

Excavation and Trenching Excavation and Trenching Excavation and trenching are among the most hazardous construction operations. The Occupational Safety and Health Administration s (OSHA) Excavation standards, 29 Code of Federal

More information

The anglo american Safety way. Safety Management System Standards

The anglo american Safety way. Safety Management System Standards The anglo american Safety way Safety Management System Standards 2 The Anglo American Safety Way CONTENTS Introduction 04 Anglo American Safety Framework 05 Safety in anglo american 06 Monitoring and review

More information

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock 1/16 Management of Rolling Stock Revision Date Comments 1 January 2011 Procedure developed to support SMS and legislative requirements. 2 February 2012 Reviewed with RISSB Standards and change of titles

More information