Valuing our Water Resource Together Construction Site Erosion and Sediment Management

Size: px
Start display at page:

Download "Valuing our Water Resource Together Construction Site Erosion and Sediment Management"

Transcription

1 Valuing our Water Resource Together Construction Site Erosion and Sediment Management Presenters Andrea Beard Engineer 1 City of Oregon, Department of Public Service Beatrice Miringu, MSc Senior Environmental Specialist City of Toledo, Division of Environmental Services 1

2 Overall Goal: To protect our water resources Ensure proper implementation of the Stormwater Pollution Prevention Plan (SWPPP) and the Erosion and Sediment Control Plan (ESC). Identify and address specific issues that minimize soil erosion and sediment migration from a construction site. 1

3 Why do we need Teamwork? To promote open dialogue on expected compliance with social and economic considerations. To share specific and unique site characteristics. To respond to identified issues in a timely, effective and relevant manner. Discuss regulatory requirements. 3

4 Three Phases of Construction Activities I-Pre-construction SWPPP Notice of Intent (NOI) Pre-construction meeting and notifications II-Active construction Structural and non-structural BMP application Temporary stabilization III-Post-construction Final stabilization Removal of BMPs File for Notice of Termination (NOT) 4

5 Inspector s Mission Establishing whether the applicable BMPs are properly installed, effective and functional. Identifying specific areas of non-compliance. Initiating conversation on identified issues. Monitoring achievement of agreed upon compliance time schedule. 5

6 Strategies for Achieving Compliance Provide opportunities for meaningful, professional and technical dialogue. Discuss site managers and superintendents in BMP management strategies. Document compliance where storm water deficiencies are observed. Follow appropriate sequence of activities. 6

7 Pre-Construction Meeting Note: The pre-construction meeting requirements depend on project complexity and jurisdiction. Possible items of discussion: Compliance For Construction Site Construction Site Enforcement Procedure Inspectors Contact Information Pre-Construction Data Form 7

8 SWPPP Document on site Review construction plan on site to ensure that BMPs installation are as approved. Ensure on site plans are updated when adjustments are made during implementation. Review construction site data sheets/log/reports. 8

9 Critical Inspection Areas All disturbed areas Site entrances/exits Inlets and curb cuts Discharge points Equipments (leaking) Housekeeping Off site storage areas 9

10 Issue Illicit Discharge Dewatering operation over dirt pile. Discharge water was conveying sediment into the unprotected catch basin. Possible solutions Screen at the end of pipe Dewatering bag Sediment trap 10

11 Issue- Poor Housekeeping 11

12 Issue-Inadequate/Absence of BMPs No sediment filters Lack of construction entrance Immediate action required 12

13 Issue-Inadequate/Absence of BMPs 13

14 Getting To Compliance Collect information showing where the specific construction site fails to satisfy NPDES requirements Document site conditions that are non-compliant Discuss compliance requirements 14

15 End of Active Construction Phase Keep track of areas that will remain inactive for extended period and during winter. Achieve 70% of vegetation cover Have inlet protection in place until final stabilization is archived. Remove remnants BMPs at the end of the projects. 15

16 Example of Achieved Compliance 2/8/ /4/

17 Start communicating early Lessons Learned Be willing to learn Continuous monitoring of BMPS Acknowledge the other s position Maximize joint effort on inspections Demonstrate commitment to teamwork 17

18 Challenges Focusing on issues of mutual benefit Building trust Being consistent Turnover - both for site supervisors and agency inspectors 18

19 Speakers Contact Information Beatrice Miringu City of Toledo, Div. of Environmental Services 348 S. Erie St. Toledo, OH Office (419) Andrea Beard City of Oregon, Department of Public Service 5330 Seaman Road Oregon, Ohio Office (419)

Section 4: Managing the Construction Site

Section 4: Managing the Construction Site Section 4: Managing the Construction Site 4.1 Mobilization 33 4.1.1 Posting the SWPPP 33 4.1.2 Initial installation of BMP s 33 4.1.3 Mobilization Checklist for Initial Installation 34 4.2 Maintaining

More information

Watershed Enforcement Environmental Services (ESD)

Watershed Enforcement Environmental Services (ESD) Watershed Enforcement Environmental Services (ESD) Construction Inspector Training 2009 Presented by: Watershed Enforcement Outline Overview of Watershed Enforcement Program Role of Watershed Enforcement

More information

VILLAGE OF HODGKINS STORM WATER MANAGEMENT PLAN (MS4) NPDES PERMIT No. ILR400356

VILLAGE OF HODGKINS STORM WATER MANAGEMENT PLAN (MS4) NPDES PERMIT No. ILR400356 VILLAGE OF HODGKINS STORM WATER MANAGEMENT PLAN (MS4) NPDES PERMIT No. ILR400356 The Village of Hodgkins in compliance with the Illinois Environmental Protection Agency (IEPA) and the Metropolitan Water

More information

AGENDA. Speaker. November Highways Division, Oahu District

AGENDA. Speaker. November Highways Division, Oahu District Speaker Richard Price, P.E., LEED AP, CSM EA Engineering, Science, and Technology, Inc. Stormwater Program Manager rprice@eaest.com Introduction to DOT Storm Water Program Highways Division, Oahu District

More information

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum LOUISIANA URBAN STORMWATER COALITION EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum SWPPP NOTIFICATION SIGN Post sign at entrance of site or areas where the public can easily access.

More information

Construction site inspections are conducted for all projects that receive an approved site plan and proceed to construction.

Construction site inspections are conducted for all projects that receive an approved site plan and proceed to construction. Standard Operating Procedures for implementation of the Stormwater, Erosion and Sedimentation Inspection Program for Construction Sites Discharging Stormwater to the MS4 Construction site inspections are

More information

2010 California Green Building Standards Code. Residential and Non-Residential Development

2010 California Green Building Standards Code. Residential and Non-Residential Development 2010 California Green Building Standards Code Residential and Non-Residential Development Stormwater Management (Site Development) Requirements Engineering, Surveying & Permit Services Department 2700

More information

Single Family Residential Construction Erosion/Sediment Control Standards

Single Family Residential Construction Erosion/Sediment Control Standards Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended

More information

Performance Standards Compliance Checklist

Performance Standards Compliance Checklist Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each

More information

Module 1: Construction Site Erosion Control

Module 1: Construction Site Erosion Control Module 1: Construction Site Erosion Control Problems and Regulations Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Problems Associated with Erosion

More information

Storm Water and SPCC Plan Best Management Practices Presented To: 2015 IMAA Winter Workshops February 2, 3 & 4, 2015

Storm Water and SPCC Plan Best Management Practices Presented To: 2015 IMAA Winter Workshops February 2, 3 & 4, 2015 Storm Water and SPCC Plan Best Management Practices Presented To: 2015 IMAA Winter Workshops February 2, 3 & 4, 2015 Mack Overton, VP Industrial Services KERAMIDA, Inc. Stormwater Rule Purpose is to limit

More information

City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017

City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017 City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017 Why is Water Quality Important? Water has always been important to Minnesota and is a key part of our history, culture, economy

More information

LAND DISTURBANCE PERMIT

LAND DISTURBANCE PERMIT SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone

More information

York County STORMWATER LUNCH & LEARN

York County STORMWATER LUNCH & LEARN York County STORMWATER LUNCH & LEARN TOPICS Points of Exposure SWPPP's NOT's Construction Sequence Permanent BMP's Basin Details Major and Minor Modifications Construction Buffers Stabilization Questions

More information

The Stormwater Management Plan

The Stormwater Management Plan Introduction The University of Alabama has been issued a National Pollutant Discharge Elimination System (NPDES) permit for stormwater discharges from regulated small municipal separate storm sewer systems

More information

The Future of ODOT s Erosion and Sediment Control Specification SS832

The Future of ODOT s Erosion and Sediment Control Specification SS832 The Future of ODOT s Erosion and Sediment Control Specification SS832 Hans Gucker, P.E., CPESC ODOT Office of Construction Administration Construction Hydraulic Engineer MS4 AUDIT FINDINGS 2013-2016 Ohio

More information

Stormwater Pollution Prevention Plan Engineering Department Requirements

Stormwater Pollution Prevention Plan Engineering Department Requirements Stormwater Pollution Prevention Plan Engineering Department Requirements The following are the stormwater pollution prevention plan requirements for the above referenced project. If you have any questions

More information

Construction Site Inspections

Construction Site Inspections Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some

More information

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until

More information

Good Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions

Good Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions September 18, 2018 Good Housekeeping Phones Weather related emergencies Breaks and facilities Introductions Goals and Objectives 1. Plan Review Process 2. Land Disturbance Permitting 3. Erosion and Sediment

More information

Tracking Contractor Compliance for Stormwater in Ohio

Tracking Contractor Compliance for Stormwater in Ohio Tracking Contractor Compliance for Stormwater in Ohio Hans Gucker, P.E., CPESC ODOT Office of Construction Administration Construction Hydraulic Engineer BRIEF HISTORY Prior to 2004 ODOT prepared all Stormwater

More information

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required.

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required. Overview of Section 9 9.0 The GESC Permit Section provides a description of the Small Utility GESC Permit Program. Step 1. Determine if a GESC Permit is Applicable and if a Project Specific GESC Plan is

More information

Minnesota Pollution Control Agency requires that the City of Brainerd develop written procedures for

Minnesota Pollution Control Agency requires that the City of Brainerd develop written procedures for I. INTRODUCTION The owns and operates an MS4 ( Municipal Separate Storm Sewer System). The Minnesota Pollution Control Agency requires that the develop written procedures for the purpose of eliminating

More information

APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS

APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS City of Bradenton January 2017 1 INTRODUCTION This appendix to the City of Bradenton Department of Public Works and Utilities Utility Specifications

More information

Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702

Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702 Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702 November 2011 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PURPOSE... 1 3.0

More information

Erosion and Sediment Control Manual Table of Contents

Erosion and Sediment Control Manual Table of Contents Erosion and Sediment Control Manual Table of Contents Introduction... 2 Requirements Based on Size of the Construction Site... 3 Flow Chart Illustrating the Responsibilities of a Construction Site... 5

More information

Construction Site Runoff (CSR) Permit Application Permit Fee $150.00

Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Site Address or Lot and Subdivision: Applicant Name: Applicant s E-Mail: Applicant s Address: Telephone: (office) City, State, ZIP (cell)

More information

STORMWATER MANAGEMENT PLAN City of Overland Park, Kansas

STORMWATER MANAGEMENT PLAN City of Overland Park, Kansas STORMWATER MANAGEMENT PLAN 2014 2019 City of Overland Park, Kansas Table of Contents Introduction...1 Plan Management...3 Minimum Control Measures...4 Public Education and Outreach...5 Public Involvement

More information

Construction Site Runoff Inspections and Enforcement

Construction Site Runoff Inspections and Enforcement Construction Site Runoff Inspections and Enforcement Stormwater Program 12/01/11 Table of Contents Introduction... 1 Purpose of Document... 1 Definition of Terms... 1 Compliance and Inspections... 3 Site

More information

Regulatory Requirements

Regulatory Requirements 7B-1 Design Manual Chapter 7 - Erosion and Sediment Control 7B - Regulatory Requirements Regulatory Requirements A. National Pollutant Discharge Elimination System (NPDES) The Clean Water Act established

More information

CHAPTER 5. NPDES PHASE II EVALUATION

CHAPTER 5. NPDES PHASE II EVALUATION CHAPTER 5. NPDES PHASE II EVALUATION A Stormwater Management Program for Medford was developed and submitted to the DEQ to meet requirements of the NPDES Phase II program. Phase II regulations require

More information

For a complete list of all BMP categories, see Stormwater: Best Management Practices Index.

For a complete list of all BMP categories, see Stormwater: Best Management Practices Index. Stormwater: General Inspection Checklist Department: Environmental Protection Program: Stormwater This inspection checklist can be used by Stormwater Division or Environmental Services Coordinator to Conduct

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000

More information

Stormwater CGP. CGP Regulatory Overview. CGP Regulatory Overview

Stormwater CGP. CGP Regulatory Overview. CGP Regulatory Overview Stormwater CGP Stormwater Construction General Permit CGP-2013 Stormwater Construction General Permit (CGP) Pima Association of Governments 2013 Seminar on Stormwater Prepared by Chris Henninger Stormwater

More information

STORMWATER POLLUTION PREVENTION PLAN (SWP3)

STORMWATER POLLUTION PREVENTION PLAN (SWP3) City of Moore, Oklahoma Community Development Department 301 North Broadway Moore, Oklahoma 73160 STORMWATER POLLUTION PREVENTION PLAN (SWP3) The SWP3 is a written narrative describing the site, potential

More information

Appendix A: SWPPP Template Instructions

Appendix A: SWPPP Template Instructions Appendix A: SWPPP Template Instructions To help you develop the narrative section of your construction site SWPPP, EPA has created this electronic SWPPP template. The template is designed to help guide

More information

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000

More information

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

Construction Site Erosion Control and Phase II of the Stormwater Permit Program Construction Site Erosion Control and Phase II of the Stormwater Permit Program Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Some Features of Phase

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

CHAPPAQUA CENTRAL SCHOOL DISTRICT 66 ROARING BROOK ROAD CHAPPAQUA, NY GUIDELINE AND PROCEDURES DOCUMENT FOR STORMWATER BEST MANAGEMENT PRACTICES

CHAPPAQUA CENTRAL SCHOOL DISTRICT 66 ROARING BROOK ROAD CHAPPAQUA, NY GUIDELINE AND PROCEDURES DOCUMENT FOR STORMWATER BEST MANAGEMENT PRACTICES SWMP MS4 SPDES PERMIT NYR20A516 CHAPPAQUA CENTRAL SCHOOL DISTRICT 66 ROARING BROOK ROAD CHAPPAQUA, NY 10514 GUIDELINE AND PROCEDURES DOCUMENT FOR STORMWATER BEST MANAGEMENT PRACTICES APRIL 2018 CFE CONSULTING

More information

SWPPP Inspection Procedures and Form 247 Instructions

SWPPP Inspection Procedures and Form 247 Instructions SWPPP Inspection Procedures and Form 247 Instructions 1. Pre-Construction Conference a. A stormwater pollution pre-construction conference shall be held prior to beginning work on each project. b. The

More information

City of Fairmont Storm Water Pollution Prevention Plan Annual Public Meeting. June 11, 2018

City of Fairmont Storm Water Pollution Prevention Plan Annual Public Meeting. June 11, 2018 City of Fairmont Storm Water Pollution Prevention Plan Annual Public Meeting June 11, 2018 Why is Water Quality Important? Water has always been important to Minnesota and is a key part of our history,

More information

Lesson s Learned and BMPs A Consultant s Perspective. February 13, 2013 Melanie Niday, PG Short Elliott Hendrickson, Inc.

Lesson s Learned and BMPs A Consultant s Perspective. February 13, 2013 Melanie Niday, PG Short Elliott Hendrickson, Inc. Lesson s Learned and BMPs A Consultant s Perspective February 13, 2013 Melanie Niday, PG Short Elliott Hendrickson, Inc. In the Beginning Solid Waste In the Beginning Solid Waste In the Beginning Solid

More information

BMP FACT SHEET DF-1 HOA Annual Self-Certification Report

BMP FACT SHEET DF-1 HOA Annual Self-Certification Report PURPOSE: Public and privately owned and maintained stormwater conveyance systems collect and transport urban runoff and storm water that may contain certain pollutants. These pollutants may accumulate

More information

WAKULLA SITE PLANNING

WAKULLA SITE PLANNING WAKULLA CIVIL SURVEYING SITE PLANNING TRAFFIC CONTROL PLAN WAKULLA ARRAN ROAD WIDENING & RESURFACING UTILITY CONTACT LIST NO. DATE: APPR. REVISION: DATE: CIVIL SURVEYING SITE PLANNING GENERAL NOTES WAKULLA

More information

2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS

2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS 2. Section 2 TW O SECTIONTWO 2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS Unless specifically exempted, all Development Construction Projects will be required

More information

ANNUAL FACILITY INSPECTION REPORT. April 1, March 31, 2014 NPDES PERMIT FOR STORM WATER DISCHARGES FROM MUNICIPAL SEPARATE STORM SEWER SYSTEMS

ANNUAL FACILITY INSPECTION REPORT. April 1, March 31, 2014 NPDES PERMIT FOR STORM WATER DISCHARGES FROM MUNICIPAL SEPARATE STORM SEWER SYSTEMS ANNUAL FACILITY INSPECTION REPORT April 1, 2013 - March 31, 2014 NPDES PERMIT FOR STORM WATER DISCHARGES FROM MUNICIPAL SEPARATE STORM SEWER SYSTEMS Submitted to ILLINOIS ENVIRONMENTAL PROTECTION AGENCY

More information

Erosion Control State Standards Sampling of Material Innovations

Erosion Control State Standards Sampling of Material Innovations Erosion Control State Standards Sampling of Material Innovations Greg Halverson Brock White Company Geosynthetics Product Manager 32 nd Annual North Central Local Roads Conference Rapid City, SD - October

More information

CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre

CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre Approved by: City of Camarillo Stormwater Program Manager Date: CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre Project Name: Project #: Project Location:

More information

A. Each Contractor shall comply with the requirements outlined in these documents.

A. Each Contractor shall comply with the requirements outlined in these documents. Section 000700 Stormwater Management Plan for Aurora Public Schools PART 1 GENERAL 1.0 DESCRIPTION A. Each Contractor shall comply with the requirements outlined in these documents. PART 2 PRODUCTS Not

More information

Stormwater Management at Municipal Solid Waste Landfills

Stormwater Management at Municipal Solid Waste Landfills Stormwater Management at Municipal Solid Waste Landfills Permit Coverage Municipal Solid Waste Landfills are covered under one of the following National Pollutant Discharge Elimination System (NPDES) types

More information

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for

More information

OPERATION & MAINTENANCE

OPERATION & MAINTENANCE Grate Inlet Filter OPERATION & MAINTENANCE Bio Clean Environmental Services, Inc. 398 Via El Centro Oceanside, CA 92058 www.biocleanenvironmental.com p: 760.433.7640 f: 760.433.3176 OPERATION & MAINTENANCE

More information

Division of Water Quality (701)

Division of Water Quality (701) Division of Water Quality (701) 328-5210 stormwater@nd.gov March April 2018 1 Construction Permit Permit #: NDR10-0000 Reissued April 1, 2015 Expires March 31, 2020 2 Discharges Covered Stormwater Discharges

More information

1. INSPECTOR NAME/ TITLE 2. CONTACT PHONE NUMBER 3. CONTACT ADDRESS 4. DATE/TIME OF INSPECTION 5. OTHER ATTENDANTS ACCOMPANYING INSPECTOR

1. INSPECTOR NAME/ TITLE 2. CONTACT PHONE NUMBER 3. CONTACT  ADDRESS 4. DATE/TIME OF INSPECTION 5. OTHER ATTENDANTS ACCOMPANYING INSPECTOR : The Best Management Practices Plan (BMPP) shall be completed annually by the Port Authority, tenants or contractors for all activities that potentially impact stormwater at JFK airport. The will be used

More information

Illinois EPA MS4/ILR10 permit overview & changes

Illinois EPA MS4/ILR10 permit overview & changes Illinois EPA MS4/ILR10 permit overview & changes Stasi Brown, CPESC Resource Analyst Kane-DuPage Soil & Water Conservation District Questions We Hope To Answer: Requirements of an MS4 & ILR10 permits how

More information

SCDOT & the NPDES Program

SCDOT & the NPDES Program SCDOT & the NPDES Program Presentation Outline Introduction and Overview Permitting Storm Water Management and Planning What is the NPDES Program? National Pollutant Discharge Elimination System Controls

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

Common Plan SWPPP for

Common Plan SWPPP for Stormwater Pollution Prevention Plan Template (SWPPP) (This SWPPP Template is for the Only, and does NOT address SWPPP requirements found in the CGP.) Common Plan SWPPP for Date 1. Project Information

More information

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE STORM WATER POLLUTION PREVENTION PLAN TEMPLATE Cover Page Certifications Project, Owner, Operator, SWPPP Preparer, Date, Project Dates Signed by RIDOT (Owner) and CONTRACTOR (as Operator) of Contents Introduction

More information

Storm Water Pollution Prevention Training 2016

Storm Water Pollution Prevention Training 2016 Storm Water Pollution Prevention Training 2016 For the Employees of the City of Lynn Haven Fl. Presented by Lisa Fowler ECO Consulting Group, LLC What is Storm Water? Storm water is water flowing over

More information

Page 2. Highway Construction Environmental Best Management Practices and Lessons Learned

Page 2. Highway Construction Environmental Best Management Practices and Lessons Learned Page 1 Page 2 Highway Construction Environmental Best Management Practices and Lessons Learned Page 3 OUTLINE 1. Project Overview 2. Erosion and Sediment Control Planning 3. Collaboration, Communication,

More information

Module 4 Regulatory requirements for Land Disturbing Activities

Module 4 Regulatory requirements for Land Disturbing Activities Module 4 Regulatory requirements for Land Disturbing Activities MODULE 4 REGULATORY REQUIREMENTS FOR A LDA Module 4a Overview MODULE 4A REGULATORY REQUIREMENTS FOR A LDA ESC Regulations Overview 1990 First

More information

EDMONDS COMMUNITY COLLEGE STORMWATER MANAGEMENT PROGRAM

EDMONDS COMMUNITY COLLEGE STORMWATER MANAGEMENT PROGRAM Update: 3-13-2017 Original Document: Sept 2009 EDMONDS COMMUNITY COLLEGE STORMWATER MANAGEMENT PROGRAM Western Washington Phase II Municipal Stormwater Permit Number (WAR04-5715) Table of Contents Introduction...

More information

Construction Phasing Bad

Construction Phasing Bad Construction Entrances Construction Phasing Remove mud and dirt from the tires of construction vehicles before they enter a paved roadway. Propoerly size entrance BMP's for all anticipated vehicles. Make

More information

LAUSD SWPPP Training. Presented By: Joe Zucker

LAUSD SWPPP Training. Presented By: Joe Zucker LAUSD SWPPP Training Contractor SWPPP & Reporting Requirements Presented By: Joe Zucker May 28, 2009 SWPPP Procedures & Policies LAUSD LAUSD Contracts Hall & Foreman to Prepare SWPPP LAUSD File Notice

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

October 2016 CDRPC Workshop

October 2016 CDRPC Workshop The New Blue Book NYS Standards and Specifications for Erosion and Sediment Control Dated July 2016 October 2016 CDRPC Workshop Blue Book Update Overview Reorganization of standard to reflect recommended

More information

Blue Book Update Overview

Blue Book Update Overview The New Blue Book NYS Standards and Specifications for Erosion and Sediment Control Dated July 2016 October 2016 CDRPC Workshop Blue Book Update Overview Reorganization of standard to reflect recommended

More information

Stormwater Construction General Permit CGP-2013

Stormwater Construction General Permit CGP-2013 Stormwater Construction General Permit CGP-2013 Stormwater Construction General Permit (CGP) Stormwater Outreach for Regional Municipalities MS4 Statewide Summit June 18, 2013 Prepared by Chris Henninger

More information

Storm Water Pollution Prevention Plan (SWP3) Checklist

Storm Water Pollution Prevention Plan (SWP3) Checklist . Summit Soil and Water Conservation District Storm Water Pollution Prevention Plan (SWP3) Checklist Modified from the Ohio EPA SWP3 Checklist (Revised January 2017) SITE NAME: REVIEWER: DATE RECEIVED:

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW3 June 2015 SW3.01 Purpose The purpose of this Chapter is to outline the minimum drawing and submittal requirements for proposed stormwater improvements.

More information

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP) Elements of the Storm Water Management Plan Storm Water Pollution Prevention Plan (SWPPP) Small Construction Site Storm Water Management Rodney Hendrick Water Quality Specialist LSU Ag Center Plan Requirements

More information

SUDAS Revision Submittal Form

SUDAS Revision Submittal Form SUDAS Revision Submittal Form Status Date: As of 3/15/2018 Topic: General Permit No. 2 updates Manual: Design Manual Location: Sections 7A-1 and 7B-1 Requested Revision: Section 7A-1 (General Information),

More information

Checklist Stormwater Pollution Prevention Plan (SWPPP)

Checklist Stormwater Pollution Prevention Plan (SWPPP) Checklist Stormwater Pollution Prevention Plan (SWPPP) Project: Reviewed: 1. Site Evaluation and Design Development A. Collect Site Information Existing soils information Existing runoff water quality

More information

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering) Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating

More information

CHAPTER 6 - How to Prepare a SWPPP

CHAPTER 6 - How to Prepare a SWPPP All construction sites which disturb an area of 1 acre or more, currently need a UPDES permit from the State of Utah. As a condition of the permit, a Stormwater Pollution Prevention Plan (SWPPP) must be

More information

Construction Stormwater Compliance: Are You Covered Under the EPA s New 2017 Construction General Permit?

Construction Stormwater Compliance: Are You Covered Under the EPA s New 2017 Construction General Permit? Construction Stormwater Compliance: Are You Covered Under the EPA s New 2017 Construction General Permit? Presented by: Jennifer Hildebrand Environmental Compliance Group Manager WSB and Associates, Inc.

More information

New Administration Building

New Administration Building New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180

More information

Stormwater Management - Basic Overview for Municipal Employees

Stormwater Management - Basic Overview for Municipal Employees Stormwater Management - Basic Overview for Municipal Employees October 13 th, 2011 Scott D. Cook Environmental Program Specialist 2 NYSDEC - Region 7 Syracuse Division of Water 315-426-7502 sdcook@gw.dec.state.ny.us

More information

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from

More information

The Future of SS832. Hans Gucker, P.E., CPESC, ODOT Scott Lines, Storm Water Simplified Ltd. Tom Simon, Storm Water Simplified Ltd.

The Future of SS832. Hans Gucker, P.E., CPESC, ODOT Scott Lines, Storm Water Simplified Ltd. Tom Simon, Storm Water Simplified Ltd. The Future of SS832 Hans Gucker, P.E., CPESC, ODOT Scott Lines, Storm Water Simplified Ltd. Tom Simon, Storm Water Simplified Ltd. SS832 Evolving Ohio EPA MS4 Permit Audit Findings Dec. 2013 to Jan. 2017

More information

APPENDIX A EXCERPTS FROM THE PERMIT

APPENDIX A EXCERPTS FROM THE PERMIT APPENDIX A EXCERPTS FROM THE PERMIT NPDES CAS004001-45 - Order No. 01-182 F. PUBLIC AGENCY ACTIVITIES PROGRAM Each Permittee shall implement a Public Agency program to minimize storm water pollution impacts

More information

Tina R. Evans, PE, CISEC HydroDynamics Incorporated Parker, CO HDI

Tina R. Evans, PE, CISEC HydroDynamics Incorporated Parker, CO HDI Tina R. Evans, PE, CISEC HydroDynamics Incorporated Parker, CO 303-841-0377 PREPARING FOR THE START OF CONSTRUCTION Environmental Regulatory Tasks Remain compliant Steps to Consider Know the Rules and

More information

PART 3 STORM WATER TECHNICAL MANUAL

PART 3 STORM WATER TECHNICAL MANUAL PART 3 STORM WATER TECHNICAL MANUAL A. INTRODUCTION The Storm Water Technical Manual contains requirements for land development and construction activities, as well as design criteria and guidelines for

More information

Drainage System Maintenance

Drainage System Maintenance Drainage System Maintenance GH-50 OBJECTIVES Ensure functionality of storm drain system through maintenance and monitoring General Overview Operational Protocols General Practices Limitations Specific

More information

LOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE

LOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE TITLE: NUMBER: ISSUER: Storm Water Discharges Associated with Construction and Land Disturbance Activities REF-6286.0 John Sterritt, Director Enrique G. Boull t, Chief Operating Officer Office of the Chief

More information

CITY OF FRIENDSWOOD DOCUMENT TPDES REQUIREMENTS

CITY OF FRIENDSWOOD DOCUMENT TPDES REQUIREMENTS DOCUMENT 01410 PART I: GENERAL 1.1 GENERAL A. Documentation to be prepared and signed by the Contractor before conducting construction operations, in accordance with the Texas Pollutant Discharge Elimination

More information

SECTION 11 PART I STORMWATER QUALITY PROTECTION Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES

SECTION 11 PART I STORMWATER QUALITY PROTECTION Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES SECTION 11 PART I STORMWATER QUALITY PROTECTION CONTENTS Page 11-1 Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES 11-2 Stormwater Pollution Prevention Plan (SWPPP) 11-3 11-3 Erosion and Sediment

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

City of Evanston STORMWATER MANAGEMENT PLAN February 2018

City of Evanston STORMWATER MANAGEMENT PLAN February 2018 City of Evanston STORMWATER MANAGEMENT PLAN February 2018 1 1.0 Table of Contents 2.0 INTRODUCTION...3 2.1 SMP STRUCTURE... 3 2.2 AREA SUBJECT TO THE PLAN... 3 2.3 SMP DEVELOPMENT... 3 2.4 ANNUAL REPORTING...

More information

SECTION EROSION AND SEDIMENTATION CONTROL

SECTION EROSION AND SEDIMENTATION CONTROL SECTION 02160 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Contractor shall be held to have read all Bidding Requirements; all of the General Conditions and Supplementary

More information

Home Remodeling Projects

Home Remodeling Projects Should your project require a Standard Urban Stormwater Mitigation Plan (SUSMP), please see the City of Pomona s Standard Urban Stormwater Mitigation Plan (SUSMP) Pamphlet Best Management Practices For

More information

Stormwater Management Practices and Design Manual. Clemson University

Stormwater Management Practices and Design Manual. Clemson University Stormwater Management Practices and Design Manual Clemson University Clemson University Facilities February 2017 This Stormwater Management Practices and Design Manual (Manual) is issued by Clemson University

More information

TOWN OF BETHLEHEM SWPPP APPLICATION REVIEW CHECKLIST

TOWN OF BETHLEHEM SWPPP APPLICATION REVIEW CHECKLIST TOWN OF BETHLEHEM SWPPP APPLICATION REVIEW CHECKLIST Instructions: This form must be included with an initial submittal of a Site Plan or Subdivision Application. Use the column to indicate if the SWPPP

More information

Governor s Environmental Advisory Council 2007 Non-point Source Pollution Initiative Management Practices Survey EROSION AND SEDIMENT CONTROL COMPILED

Governor s Environmental Advisory Council 2007 Non-point Source Pollution Initiative Management Practices Survey EROSION AND SEDIMENT CONTROL COMPILED Governor s Environmental Advisory Council 2007 Non-point Source Pollution Initiative Management Practices Survey EROSION AND SEDIMENT CONTROL COMPILED Best Practice(s) Observed Worst Practice(s) Observed

More information

MCM#6 Pollution Prevention/Good Housekeeping for Municipal Operations. Licking County MS

MCM#6 Pollution Prevention/Good Housekeeping for Municipal Operations. Licking County MS MCM#6 Pollution Prevention/Good Housekeeping for Municipal Operations Licking County MS4 12 14 2016 1 Why are we here? Heath is an MS4 Community MS4 = Municipal Separate Storm Sewer System SWMP Storm Water