FINAL Hazardous Building Materials Assessment 801 Low Level Road, North Vancouver, BC

Size: px
Start display at page:

Download "FINAL Hazardous Building Materials Assessment 801 Low Level Road, North Vancouver, BC"

Transcription

1 Hazardous Building Materials Assessment 801 Low Level Road, North Vancouver, BC Prepared for: PCL Constructors Westcoast Inc. # Wireless Way Richmond, BC, V6V 3B9 Attention: Chad McPhee Project Manager October 7, 2016 PWL File: 13371H Pinchin West Ltd.

2 Issued to: Contact: Issued on: PWL File: Issuing Office: Primary PWL Contact: Chad McPhee Project Manager October 7, H-01 Suite 200, Commerce Parkway, Richmond, BC V6V 2V4 Hien Nguyen, Project Manager, Author: Larissa Braun Neville, BA Project Coordinator Reviewer: John Holland, PEng, CEng, LEED AP (BD&C), FEC President Reviewer: Hussien Jaffer, B ASc, CIH, CRSP Operations Manager hjaffer@pinchinwest.com 2016 Pinchin West Ltd. Page i

3 EXECUTIVE SUMMARY (Client) retained Pinchin West Ltd. (PWL) to conduct a hazardous building materials assessment of Cargill Grain Terminal located at 801 Low Level Road, North Vancouver, BC. PWL performed the assessment on September 21, The objective of the assessment was to identify specified hazardous building materials in preparation for facility Electrical Infrastructure upgrades and demolition of the Substation Switch Yard. The results of this assessment are intended for use with a properly developed scope of work and performance specification. The assessed area was limited to the Substation Switch Yard, including the Basement Vaults (Rooms 808, 809) and detached Emergency Generator Room 806. PDC Rooms 1, 2, 3/4 and 19 MCCs (Electrical Vaults) were previously assessed in PWL report Hazardous Building Materials Assessment 801 Low Level Road, North Vancouver, BC dated August 30, 2016, PWL File: 13371H, submitted under separate cover. The purpose of this report is to augment the findings of the PWL August 30, 2016 report to include previously inaccessible project areas as well as to include hazardous materials as required by the Vancouver Fraser Port Authority Project & Environmental Review demolition permit application within all identified project areas. SUMMARY OF FINDINGS Asbestos: Asbestos-containing materials (ACM) were confirmed to be present as follows: Black fibre duct conduits associated 60kV feeder cables within the concrete slab of the Substation Switch Yard Putty/firestopping (grey, hard) associated 60kV feeder cable penetrations and grounding cable penetrations within the concrete slab of the Substation Switch Yard Mastic/tar (black) on the concrete foundation and duct bank at the Exterior wall of Substation Switch Yard Basement Vault (Room 809) Asbestos-containing materials (ACM) are suspected to be present as follows: Black fibre duct conduits associated 60kV feeder cables within the concrete foundation and duct banks of the Substation Switch Yard Vault (Room 808) Putty/firestopping (grey, hard) associated 60kV feeder cable penetrations and grounding cable penetrations within the concrete foundation and duct banks of the Substation Switch Yard Vault (Room 808) 2016 Pinchin West Ltd. Page i

4 Lead: Lead was confirmed present in select paints/surface coatings throughout the assessed area (more details in findings) and is present in an emergency light battery within the Emergency Generator Room 806. Lead may be present within 60kV electrical feeder cables. Silica: Crystalline silica is present in concrete, mortar, masonry, ceramics, etc. Mercury: Mercury vapour is present in fluorescent lamps. Polychlorinated Biphenyls (PCBs): PCBs may be present in light ballasts within the Emergency Generator Room 806. PCBs may be present in oils associated with 60kV feeder cables and equipment in the Substation Switch Yard. PCB containing oil is present (>0.5 <50 ppm) in Transformers (East and West, within PCD 3/4) associated with 60kV feeder cables. Ozone depleting Substances: Equipment containing ozone depleting substances was not observed within the assessed areas. Mould: Mould-impacted materials were not observed within the assessed areas. Heavy Metals: Copper encased and woven copper secondary electrical cables were observed throughout the assessed areas. Needles and Sharps: Needles and sharps were not observed within the assessed areas. Radioactive Materials: Radioactive materials may be present in fire ionizing detection systems within the assessed areas. Flammable materials: A canister of heavy duty lubricant was observed in MCC 123, and a canister of enamel/paint was observed within MCC 13. Explosive Materials: Explosive materials may be present within the assessed areas, due to the airborne grain dust typically present within a Grain Terminal Facility. Household Chemicals: Cleaning agents and solutions were observed within PDC 3/4. Animal Carcasses and Animal Droppings: Animal carcasses and animal droppings were observed throughout the Cargill Grain Terminal, adjacent to assessed areas. An animal carcass (bird) was observed within the fenced enclosure of the Substation Switch Yard Pinchin West Ltd. Page ii

5 SUMMARY OF RECOMMENDATIONS The following is a summary of significant recommendations; refer to the body of the report for detailed recommendations. 1. Remove and properly dispose of asbestos-containing materials prior to demolition or if disturbed by the planned renovation work. 2. Remove and properly dispose of PCB ballasts, and oils in transformers and other electrical equipment, and mercury-containing items prior to demolition or if disturbed by the planned renovation work. 3. Follow appropriate safe work procedures when handling or disturbing lead, copper, silica, and animal carcasses and droppings. 4. Relocate for proper storage or remove and properly dispose of all household chemicals and flammable materials if disturbed by the planned renovation work. 5. Follow all Cargill Safe Work Procedures and protocols for work in and around the Terminal. All demolition and renovation contractors should pay particular attention to the procedures and protocols to prevent grain dust explosions and/or fires. Please refer to Section 4.0 of this report for detailed recommendations regarding administrative, renovation or demolition activities. This Executive Summary is subject to the same standard limitations as contained in the report and must be read in conjunction with the entire report Pinchin West Ltd. Page iii

6 TABLE OF CONTENTS 1.0 INTRODUCTION AND SCOPE Scope of Assessment BACKGROUND INFORMATION Existing Reports Inaccessible Locations FINDINGS Asbestos Lead Silica Mercury Polychlorinated Biphenyls Ozone Depleting Substances in Building Equipment Mould Needles and Sharps Radioactive Materials Animal Carcasses and Droppings Heavy Metals Explosive Materials Flammable Materials Household Chemicals RECOMMENDATIONS General Building Demolition or Renovation Work LIMITATIONS REFERENCES APPENDICES APPENDIX I APPENDIX II-A APPENDIX II-B APPENDIX III APPENDIX IV Drawings Asbestos Analytical Certificates Lead Analytical Certificates Methodology Photographs 2016 Pinchin West Ltd. Page iv

7 1.0 INTRODUCTION AND SCOPE (Client) retained Pinchin West Ltd. (PWL) to conduct a hazardous building materials assessment of Cargill Grain Terminal, located at 801 Low Level Road, North Vancouver, BC. Larissa Braun Neville, BA, Project Coordinator performed the assessment on September 21, The surveyor was accompanied by Cargill Electrical Supervisor, Ron Ludwig during the assessment. The building was occupied at the time of the assessment. The objective of the assessment was to identify specified hazardous building materials in preparation for Electrical Infrastructure upgrades throughout the facility and demolition of the Substation Switch Yard. This assessment is intended to be used for pre-construction purposes only, and may not provide sufficient detail for long term management of hazardous materials as required by Health and Safety regulations. The results of this assessment are intended for use with a properly developed scope of work and performance specification. 1.1 Scope of Assessment The assessment was performed to establish the location and type of specified hazardous building materials incorporated in the structure(s) and its finishes. The assessed area was limited to the Substation Switch Yard, including the Basement Vaults (Rooms 808, 809) and detached Emergency Generator Room (806). PDC Rooms 1, 2, 3/4 and 19 MCCs (Electrical Vaults) were previously assessed in PWL report Hazardous Building Materials Assessment 801 Low Level Road, North Vancouver, BC dated August 30, 2016, PWL File: 13371H, submitted under separate cover. The purpose of this report is to augment the findings of PWL August 30, 2016 report to include previously inaccessible project areas as well as include hazardous materials as required by the Vancouver Fraser Port Authority Project & Environmental Review demolition permit application within all identified project areas. For the purpose of the assessment and this report, hazardous building materials are defined as follows: Asbestos Lead Silica Mercury Polychlorinated Biphenyls (PCBs) Ozone Depleting Substances Mould 2016 Pinchin West Ltd. Page 1 of 14

8 Additional hazardous materials included within the assessment, as required by the Vancouver Fraser Port Authority are as follows: Animal Carcasses and Droppings Household Chemicals Heavy Metals Needles and Sharps Radioactive Materials Flammable Materials Explosive Materials 2.0 BACKGROUND INFORMATION Building Description Item Building Use Details Grain Terminal Total Area of Assessed (Square Feet) Approximately 8,000 Year of Construction 1968 Structure Exterior Cladding HVAC Roof Flooring Interior Walls Ceilings Structural steel, reinforced concrete Reinforced concrete, concrete block Not applicable EPDM Concrete Concrete, masonry Concrete 2.1 Existing Reports PWL was provided and asked to rely upon the following existing report: Cargill Limited 2016 Transformer Oil Sampling and Analysis dated June 7, 2016, File: C , by Magna IV Engineering 2016 Pinchin West Ltd. Page 2 of 14

9 2.2 Inaccessible Locations The following rooms or areas of the building were not accessible to the surveyor: Area or Room Substation Switch Yard Basement Vault (Room 808, Loc. 20) Reason Access panel rusted closed 3.0 FINDINGS 3.1 Asbestos Suspect Building Materials Not Found The following types of building materials may historically contain asbestos but were not observed in the assessed areas and are not discussed in the report findings: Spray-applied fireproofing or thermal insulation Texture finishes (acoustic/decorative) Duct insulation Mechanical insulation Acoustic ceiling tiles Plaster Drywall joint compound Asbestos cement products Vinyl sheet flooring Vinyl floor tiles and mastic Thermal Systems Insulation (TSI) Pipe Insulation Non-asbestos textile cloth insulation was observed on pipes within Emergency Generator Room 806 (Loc. 21) Pinchin West Ltd. Page 3 of 14

10 Non-asbestos textile insulation associated with the Emergency Generator Vermiculite Loose fill vermiculite is not present in the assessed areas. Demolition of masonry block walls of the Emergency Generator Room 806 (Loc. 21) was not performed due to limitations on scope; vermiculite may be present within these cavities Firestopping, Sealants, Caulking, and Putty Firestopping/putty, containing chrysotile asbestos, is present at conduit penetrations associated with the 60kV feeder cables and grounding cables of the Substation Switch Yard (Loc. 18, sample S hard grey putty). Firestopping/putty, containing chrysotile asbestos, is suspected to be present at conduit penetrations associated with 60kV feeder cables and grounding cables within the inaccessible Substation Switch Yard Basement Vault Room 808 (Loc. 20). Firestopping/putty present at conduit penetrations associated with cut-off cables in the Substation Switch Yard Basement Vault Room 809 (Loc. 19, sample S soft grey putty) was determined to be nonasbestos Pinchin West Ltd. Page 4 of 14

11 Hard grey asbestos-containing putty (firestop) associated with cable penetrations in the Substation Switch Yard concrete slab Other Building Materials Black fibre duct conduits associated with 60kV feeder cables, located within the concrete slab of the Substation Switch Yard (Loc. 18) were sampled (S0024 and S0025) and determined to be asbestoscontaining. Black fibre duct conduits associated with 60kV feeder cables, suspected to be asbestos-containing, are suspected to be present within the concrete foundation of the Substation Switch Yard Basement Vault Room 808 (Loc. 20) and within underground duct runs beneath the train tracks leading into the facility. Black rubberized conduits associated with grounding cables, located within the concrete slab of the Substation Switch Yard were sampled and determined to be non-asbestos. Black mastic/tar on the Exterior concrete wall and duct run of the Substation Switch Yard Basement Vault Room 809 (Loc. 19) was sampled (S0029) and determined to be asbestos-containing. The vibration damper at the vent connection of the Emergency Generator (Room 806) was visually identified as non-asbestos rubber / vinyl material. The black tar material seeping through the concrete wall of MCC 20 (Loc. 10), from an unidentified source, was sampled and determined to be non-asbestos Pinchin West Ltd. Page 5 of 14

12 Asbestos-containing black fibre duct conduits associated with 60kV feeder cables in the Substation Switch Yard concrete slab. Asbestos-containing black mastic/tar on the Exterior concrete wall and duct run of the Substation Switch Yard Basement Vault Room Presumed Asbestos Materials A number of materials which might contain asbestos were not sampled during the assessment due to limitations in scope and methodology. Where present, these materials must be presumed to be an asbestos material and are best sampled during project planning and preparation of contract documents for their removal. Materials presumed to contain asbestos are listed in the Methodology. 3.2 Lead Paints and Surface Coatings A total of 10 paint samples were collected from interior and exterior painted finishes. The following table summarizes the analytical results for paints sampled and their locations. Sample Number L0023 L0024 L0025 L0026 Colour, Substrate Description Green and silver paint (composite) on metal Circuit Breaker housing Brown paint (red primer undercoat) on metal Circuit Breaker control housing Off-white paint (red primer undercoat) on metal BC Hydro meter housing Silver paint (red primer undercoat) on metal railings Locations Lead (%) Substation Switch Yard 0.74 Substation Switch Yard 2.6 Substation Switch Yard 0.49 Substation Switch Yard Pinchin West Ltd. Page 6 of 14

13 Sample Number L0027 Colour, Substrate Description White paint (red undercoat) on metal lamp posts Locations Lead (%) Substation Switch Yard 0.56 L0028 Yellow paint on concrete Substation Switch Yard basement Vault (room 809) <0.006 L0029 Silver paint (red primer undercoat) on metal door and frames Substation Switch Yard Basement Vaults (rooms 808, 809) 0.34 L0030 L0031 L0032 Silver paint on Generator exhaust pipes Green paint (red primer undercoat) on metal Generator Beige paint on Exterior concrete block walls and metal doors Emergency Generator Room Emergency Generator Room Emergency Generator Room Paints containing elevated levels of lead are flaking/peeling in the following areas on the following items: White paint on lamp posts, Substation Switch Yard Silver paint and red primer on metal railings, Substation Switch Yard Silver paint on Generator exhaust pipes, Emergency Generator Room 806 Beige paint on Exterior concrete block walls and metal doors, Emergency Generator Room 806 Flaking silver lead paint, Emergency Generator Room 806 Flaking beige lead paint, Emergency Generator Room 806 Exterior 2016 Pinchin West Ltd. Page 7 of 14

14 Appendix II-B presents the lead testing results Lead Products and Applications Lead-containing batteries are present in emergency lighting present in the Emergency Generator Room 806 (Loc. 21) Presumed Lead Materials Lead may be present in a number of materials which were not assessed and/or sampled. The following materials, where found, should be considered to contain lead. electrical components, including wiring connectors, grounding conductors, and solder 60kV electric feeder cables 3.3 Silica Crystalline silica is a presumed component of the following materials where present in the building: poured or pre-cast concrete masonry and mortar ceramic materials in high temperature equipment 3.4 Mercury Lamps Mercury vapour is present in fluorescent lamps where present in the assessed area Mercury-Containing Devices Mercury-containing devices were not found during the assessment. 3.5 Polychlorinated Biphenyls Lighting Ballasts The Emergency Generator Room 806 (Loc. 21) has not been comprehensively re-lamped with new energy efficient light ballasts and lamps, and as such, a percentage of light ballasts may be pre-1980 and contain PCBs Transformers PCB containing oil is present (>0.5 <50 ppm) within East and West Transformers of PCD 3/4 (Loc. 9) Pinchin West Ltd. Page 8 of 14

15 The dielectric fluid within the Oil Circuit Breaker at the Substation Switch Yard is presumed to be PCB free based on the Magna IV 2016 report. The dielectric fluid within the oil tanks supplying 60kV feeder cables of the Substation Switch Yard is pre and may contain PCBs. The dielectric fluid within the BC Hydro metering equipment at the Substation Switch Yard is pre-1980 and may contain PCBs. PCB containing oils may be present within BC Hydro metering equipment. PCB containing oils may be present within barrels supplying 60kV feeder cables Presumed PCB Materials oil impregnated cables and potheads voltage regulators 3.6 Ozone Depleting Substances in Building Equipment Equipment containing ozone depleting substances is not present. 3.7 Mould Visible mould growth is not present. 3.8 Needles and Sharps Needles and sharps were not observed within the assessed areas. 3.9 Radioactive Materials Radioactive materials may be present in ionizing fire detection systems within the assessed areas Pinchin West Ltd. Page 9 of 14

16 3.10 Animal Carcasses and Droppings Animal carcasses and droppings are present throughout the Grain Terminal facility, adjacent to the assessed areas. A carcass (bird) was observed within the fence enclosure of the Substation Switch Yard Heavy Metals Processes using heavy metals were not observed in the assessed areas. Copper encased, insulated woven copper wire secondary electrical conduits are present throughout the assessed areas Explosive Materials Explosive materials may be present within the assessed areas, due to airborne grain dust typically present within a Grain Terminal Facility Flammable Materials A canister (< 350g) of heavy duty lubricant was observed in MCC 1/2/3 (Loc. 7), and a canister (< 350g) of enamel/paint was observed within MCC 13 (Loc. 11) Household Chemicals Cleaning agents and solutions (2 bottles, < 500 g) were observed within PDC 3/4 (Loc. 9). 4.0 RECOMMENDATIONS 4.1 General 1. Prepare plans and performance specifications for hazardous material removal required for the planned work. The specifications should include the scope of work, safe work practices, personal protective equipment, respiratory protection, and disposal of waste materials. 2. Investigate any items excluded from the scope of work of this report. Ideally this investigation will be performed as part of the development of the specifications, or at a minimum immediately prior to commencing renovations when the areas are no longer occupied. Specifically the following materials/areas need to be investigated: Susbstation Switch Yard Basement Vault Room 808 due to no access at the time of this assessment. Oil containing electrical equipment, when de-energized 3. Provide this report and the detailed plans and specifications to the contractor prior to bidding or commencing work Pinchin West Ltd. Page 10 of 14

17 4. Retain a qualified consultant to specify, inspect and verify the successful removal of hazardous materials. 5. Update the asbestos inventory upon completion of the abatement and removal of asbestos-containing materials. 4.2 Building Demolition or Renovation Work The following recommendations are made regarding demolition or renovation involving the hazardous materials identified Asbestos Remove all asbestos-containing materials (ACM) prior to renovation, alteration, maintenance or demolition work if ACM may be disturbed by the work. If the identified ACM will not be removed prior to commencement of the work, disturbance of ACM must follow the appropriate asbestos precautions for the classification of work being performed. Asbestos-containing materials must be disposed of at a landfill approved to accept asbestos waste Lead Construction disturbance of lead in paint and coatings (or other materials) may result in over-exposure to lead dust or fumes. The need for work procedures, engineering controls and personal protective equipment will need to be assessed on a project-by-project basis and must comply with provincial standards or guidelines. Performing an exposure assessment during work that disturbs lead in paints and coatings may be able to alleviate the use of some of the precautions specified by these standards or guidelines. Items painted with paints containing elevated levels of lead may be a hazardous waste. Test lead-painted materials for leachable lead and other metals prior to disposal. Well adhered paints containing elevated levels of lead on metal substrates do not require leachable lead analysis as the materials can be recycled with the paint intact. Lead-containing items (lead-acid batteries, lead cables) should be recycled when taken out of service or prior to building demolition Silica Construction disturbance of silica-containing products may result in excessive exposures to airborne silica, especially if performed indoors and dry. Cutting, grinding, drilling or demolition of materials 2016 Pinchin West Ltd. Page 11 of 14

18 containing silica should be completed only with proper respiratory protection and other worker safety precautions that comply with provincial standards or guidelines Mercury Do not break lamps. Recycle and reclaim mercury from fluorescent lamps when taken out of service PCBs When light fixtures are removed, examine light ballasts for PCB content. If ballasts are not clearly labelled as non-pcb, or are suspected to contain PCBs; package and ship ballasts for destruction at a federally permitted facility. Liquid in electrical equipment and cables should be sampled immediately for classification purposes. PCB liquids are a hazardous waste. When PCB containing electrical equipment has been decommissioned package and ship for destruction at a federally permitted facility Mould No mould was observed; if mould is uncovered inside wall cavities during hand demolition, use appropriate precautions and protect workers using methods that comply with provincial guidelines Radioactive Materials Reclaim radioactive materials from fire detection systems when taken out of service. Use appropriate precautions and protect workers using methods that comply with provincial and federal guidelines Animal Carcasses and Droppings Disturbance and clean-up of animal carcasses and droppings should be conducted only with proper precautions, protecting workers using methods that comply with Regulation 6.34 of the Occupational Health and Safety Regulations Heavy Metals Copper items (copper jacketing and copper cables) should be recycled when taken out of service or prior to building demolition Flammable Materials Handling of controlled products, including flammable materials should be conducted following appropriate worker safety precautions that comply with provincial standards or guidelines Pinchin West Ltd. Page 12 of 14

19 Explosive Materials Follow all Cargill Safe Work Procedures and protocols for work in and around the Terminal. All demolition and renovation contractors should pay particular attention to the developed procedures and protocols to prevent grain dust explosions and/or fires. 5.0 LIMITATIONS Specific limitations related to the legal and financial and limitations to the scope of the current work are outlined in our proposal, the attached Methodology and the Authorization to Proceed which accompanied the proposal. The work performed by PWL was conducted in accordance with generally accepted engineering or scientific practices current in this geographical area at the time the work was performed. No warranty is either expressed or implied by furnishing written reports or findings. The Client acknowledges that subsurface and concealed conditions may vary from those encountered or inspected. PWL can only comment on the environmental conditions observed on the date(s) the survey is performed. The work is limited to those materials or areas of concern identified by the Client or outlined in our proposal. Other areas of concern may exist but were not investigated within the scope of this assignment. PWL makes no other representations whatsoever, including those concerning the legal significance of its findings or as to other legal matters touched on in this report, including, but not limited to, ownership of any property, or the application of any law to the facts set forth herein. With respect to regulatory compliance issue, regulatory statutes are subject to interpretation and these interpretations may change over time. PWL accepts no responsibility for consequential financial effects on transactions or property values, or requirements for follow-up actions and costs. The liability of PWL or our officers, directors, shareholders or staff will be limited to the lesser of the fees paid or actual damages incurred by the Client. PWL will not be responsible for any consequential or indirect damages. PWL will only be liable for damages resulting from the negligence of PWL. PWL will not be liable for any losses or damage if the Client has failed, within a period of two years following the date upon which the claim is discovered (Claim Period), to commence legal proceedings against PWL to recover such losses or damage unless the laws of the jurisdiction which governs the Claim Period which is applicable to such claim provides that the applicable Claim Period is greater than two years and cannot be abridged by the contract between the Client and PWL, in which case the Claim Period shall be deemed to be extended by the shortest additional period which results in this provision being legally enforceable. Information provided by PWL is intended for Client use only. PWL will not provide results or information to any party unless disclosure by PWL is required by law. Any use by a third party of reports or documents 2016 Pinchin West Ltd. Page 13 of 14

20 authored by PWL or any reliance by a third party on or decisions made by a third party based on the findings described in said documents, is the sole responsibility of such third parties. PWL accepts no responsibility for damages suffered by any third party as a result of decisions made or actions conducted. No other warranties are implied or expressed. 6.0 REFERENCES The following legislation and documents were referenced in completing the assessment and this report: 1. Occupational Health and Safety Regulation, B.C. Reg. 296/97, WorkSafe BC. 2. Safe Work Practices for Handling Asbestos, WorkSafe BC, 2012 Edition. 3. Hazardous Waste Regulation, B.C. Reg. 261/2006, BC Ministry of Environment. 4. Ozone Depleting Substances and Other Halocarbons Regulation, B.C. Reg. 220/2006, Environmental Management Act. 5. PCB Regulations, SOR/ , Canadian Environmental Protection Act. 6. Lead-Containing Paint and Coatings, Preventing Exposure in the Construction Industry, WorkSafe BC, June Transportation of Dangerous Goods Regulations SOR/ , Transportation of Dangerous Goods Act. 8. Mould Guidelines for the Canadian Construction Industry, Standard Construction Document CCA , Canadian Construction Association. 9. A Hantavirus Risk Control Program for Employers and Workers, WorkSafe BC, 2006 Edition H-01r01.docx Template: Master Report for Hazardous Materials Assessment Report (Pre-Construction), Haz, February 1, Pinchin West Ltd. Page 14 of 14

21 APPENDIX I Drawings

22

23

24

25 APPENDIX II-A Asbestos Analytical Certificates

26 Bulk Asbestos Analysis By Polarized Light Microscopy EPA Method: 600/R-93/116 and 600/M LAB # Customer: Project: Pinchin West Ltd. Suite 200, Commerce Parkway Richmond, BC V6V 2V4 Cargill EDP Attn: Larissa Braun Neville Hien Nguyen Lab Order ID: Analysis ID: _PLM Date Received: 9/22/2016 Date Reported: 9/23/2016 Sample ID Lab Sample ID Description Lab Notes Asbestos Fibrous Components Non-Fibrous Components Attributes Treatment S0024 BFD Condiut - East Feeder Cable, into concrete slab / Substation track level 0.6% Chrysotile 94.4% Cellulose 5% Other Black Non Fibrous Homogeneous PLM_1 Teased, Crushed S0025 BFD Condiut - West Feeder Cable, into concrete slab / Substation track level 0.6% Chrysotile 94.4% Cellulose 5% Other Black Non Fibrous Homogeneous PLM_2 Teased, Crushed S0026 Putty/firestop (hard, grey) at West Feeder Cable / Substation track level 10% Chrysotile 90% Other Tan Non Fibrous Homogeneous PLM_3 Crushed, Dissolved S0027 Rubberized conduit (black) - grounding cables, into concrete slab / Substation trac None Detected 100% Other Black Non Fibrous Homogeneous PLM_4 Ashed, Crushed S0028 Putty/firestop (soft, grey) - Sub switch basement (West, LPT2) None Detected 10% Cellulose 90% Other Gray, Black Non Fibrous Homogeneous PLM_5 Crushed, Dissolved S0029 Mastic/sealant on concrete at duct bank / Substation, below track level 10% Chrysotile 90% Other Black Non Fibrous Homogeneous PLM_6 Crushed, Dissolved S0030 Tar/mastic seeping thru concrete (unknown origin) / MCC 20 None Detected 100% Other Black Non Fibrous Homogeneous PLM_7 Dissolved Disclaimer: Due to the nature of the EPA 600 method, asbestos may not be detected in samples containing low levels of asbestos. We strongly recommend that analysis of floor tiles, vermiculite, and/or heterogeneous soil samples be conducted by TEM for confirmation of None Detected by PLM. This report relates only to the samples tested and may not be reproduced, except in full, without the written approval of SAI. This report may not be used by the client to claim product endorsement by NVLAP or any other agency of the U.S. government. Analytical uncertainty available upon request. Scientific Analytical Institute participates in the NVLAP Proficiency Testing program. Unless otherwise noted blank sample correction was not performed. Estimated MDL is 0.1%. Heather Davide (7) P-F-002 r15 1/15/2018 Analyst Approved Signatory Scientific Analytical Institute, Inc Dundas Dr. Greensboro, NC (336) Page 1 of 1

27 APPENDIX II-B Lead Analytical Certificates

28 Analysis for Lead Concentration in Paint Chips by Flame Atomic Absorption Spectroscopy EPA SW B/6010C/7420 Customer: Project: Pinchin West Ltd. Suite 200, Commerce Parkway Richmond, BC V6V 2V4 Cargill EDP Attn: Larissa Braun Neville Hien Nguyen Lab Order ID: Analysis ID: _PBP Date Received: 9/22/2016 Date Reported: 9/23/2016 Sample ID Description Mass Concentration Concentration Lab Sample ID Lab Notes (g) (ppm) (% by weight) L PBP_1 Green and silver (composite) on metal CB and support steel / Substation track level % L PBP_2 Brown (red primer undercoat) on CB metal control housing / Substation track level % L PBP_3 Off-white (red primer undercoat) on metal BCH meter housing / Substation track level % L PBP_4 Silver (red primer undercoat) on metal railings / Substation track level % L PBP_5 White (red undercoat) on metal lamp posts / Substation track level % L PBP_6 Yellow on concrete / West Sub basement switch room (LPT2) < 58 < 0.006% L PBP_7 Silver (red primer undercoat) on metal door / West Sub basement switch room (LPT2) % L PBP_8 Silver on generator exhaust / 806 Emg. Generator % L PBP_9 Green (red primer undercoat) on generator / 806 Emg. Generator % L PBP_10 Beige on exterior concrete block walls and metal doors / 806 Emg. Generator % Unless otherwise noted blank sample correction was not performed on analytical results. Scientific Analytical Institute participates in the AIHA ELPAT program. ELPAT Laboratory ID: This report relates only to the samples tested and may not be reproduced, except in full, without the written approval of SAI. Analytical uncertainty available upon request. The quality control samples run with the samples in this report have passed all EPA required specifications unless otherwise noted. RL: (Report Limit for an undiluted 50ml sample is 4µg Total Pb). Taylor Davis (10) L-F-021 r15 3/28/2014 pbrpt_4.0.01_pbp001 Analyst Laboratory Director Scientific Analytical Institute, Inc Dundas Dr. Greensboro, NC (336) Page 1 of 1

29 APPENDIX III Methodology

30 Cargill Grain Terminal, Methodology Document 1.0 GENERAL PWL conducts a room-by-room survey (rooms, corridors, service areas, exterior, etc.) to identify the hazardous building materials as defined by the scope of work. All work is conducted in accordance with our own internal Standard Operating Procedures. Information regarding the location and condition of hazardous building materials encountered and visually estimated quantities are recorded. The locations of any samples collected are recorded on small-scale plans. As-built drawings and previous reports are referenced where provided. 1.1 Scope Limitations The assessment excludes the following: Articles belonging to the owner, tenant or occupant (e.g. stored items, furniture, appliances, etc.); Underground materials or equipment (e.g. vessels, drums, underground storage tanks, pipes, etc.); Building envelope, structural components, inaccessible or concealed materials or other items where sampling may cause consequential damage to the property. Energized systems (e.g. internal boiler components, elevators, mechanical or electrical components); Controlled products (e.g. stored chemicals, operational or process-related substances); and Materials not typically associated with construction (e.g. settled dust, spills, residual contamination from prior spills, etc.). In occupied facilities, PWL only undertakes non-intrusive testing. Concealed spaces such as those above solid ceilings and within shafts and pipe chases are accessed via existing access panels only. PWL does not conduct demolition of walls, solid ceilings, structural items, interior finishes or exterior building finishes, to determine the presence of concealed materials. 1.2 Asbestos PWL conducts an inspection for the presence of friable and non-friable asbestos-containing materials (ACM). A friable material is a material that when dry can be crumbled, pulverized or powdered by hand pressure Pinchin Ltd. Page 1 of 5

31 Cargill Grain Terminal, Methodology Document A separate set of samples is collected of each type of homogenous material suspected to contain asbestos. A homogenous material is defined by the US EPA as material that is uniform in texture and appearance, was installed at one time, and is unlikely to consist of more than one type or formulation of material. The homogeneous materials are determined by visual examination and available information on the phases of construction and prior renovations. PWL collects samples at a rate that is in compliance with the requirements of local regulations and guidelines. The sampling strategy is also based on known ban dates and phase out dates of the use of asbestos; sampling of certain building materials is not conducted after specific construction dates. In addition, to be conservative, several years past these dates are added to account for some uncertainty in the exact start/finish date of construction and associated usage of ACM. In some cases, manufactured products such as asbestos cement pipe are visually identified without sample confirmation. PWL undertakes sampling of roofing felts at the client s request. A temporary repair is made with asphaltbased mastic and fibreglass mesh. A more permanent repair is required if the roofing or the building is to remain in use for any extended period of time. PWL is not responsible or liable for leaks or water damage caused by sampling and or repair. Flooring mastic/adhesive and leveling compounds are only sampled and analyzed if present on the underside of flooring samples (vinyl floor tile and vinyl sheet flooring). If present, the following materials are presumed to be asbestos-containing and are best sampled immediately prior to commencing renovation/disturbance: roofing, felts and tar concrete floor levelling compound elevator and lift brakes electrical components or wiring within control centers, breakers, motors or lights, insulation on wiring refractory materials and insulations in boilers, incinerators and stacks insulation under metal clad boilers and vessels vermiculite in concrete block wall cavities fibre reinforced paints and coatings mechanical packing, ropes and gaskets fire resistant doors or metal clad finishes 2016 Pinchin Ltd. Page 2 of 5

32 Cargill Grain Terminal, Methodology Document exterior cladding PWL submits the bulk samples to a NVLAP accredited laboratory for analysis. The analysis is performed in accordance with Test Method EPA/600/R-93/116: Method for the Determination of Asbestos in Bulk Building Materials, July In British Columbia an ACM is defined as materials containing 0.5% asbestos by weight, or any amount of asbestos for vermiculite insulation. The asbestos analysis is completed using a stop positive approach. Only one result meeting the above regulated criteria is required to determine that a material is asbestos-containing, but all samples must be analyzed to conclusively determine that a material is non-asbestos. The laboratory stops analyzing samples from a homogeneous material once a result equal to or greater than the regulated criteria is detected in any of the samples of that material. All samples of a homogeneous material are analyzed if no asbestos is detected. In some cases, all samples are analyzed in the sample set regardless of result. Where building materials are described in the report as non-asbestos, this means that either no asbestos was detected by the analytical method utilized in any of the multiple samples or, if detected, it is below the lower limit of an asbestos-containing material in the applicable regulation. 1.3 Lead PWL collects samples of distinctive paint finishes and surface coatings present in more than a limited application, where removal of the paint is possible. PWL collects samples by scraping the painted finish to include base and covering applications. Drawings included show sample locations. Analysis for lead in paints or surface coatings is performed at an accredited laboratory in accordance with EPA Method No. 3050B/Method No. 7420; flame atomic absorption. For this report, all paints containing lead at a concentration of 0.009% or greater are discussed. Paint and surface coatings are evaluated for condition such as flaking, chipping or chalking. Other lead building products (e.g. batteries, lead sheeting, flashing) are identified by visual observation only. 1.4 Silica PWL identifies building materials suspected of containing crystalline silica (e.g. concrete, cement, tile, brick, masonry, mortar) by knowledge of current and historic applications and visual inspection only. PWL does not perform sampling of these materials for laboratory analysis of crystalline silica content Pinchin Ltd. Page 3 of 5

33 Cargill Grain Terminal, Methodology Document 1.5 Mercury Building materials/products/equipment (e.g. thermostats, barometers, pressure gauges, light tubes), suspected to contain mercury are identified by visual inspection only. Dismantling of equipment suspected of containing mercury is not performed. Sampling of these materials for laboratory analysis of mercury content is not performed. Mercury spills or damaged mercury-containing equipment are recorded where observed. 1.6 Polychlorinated Biphenyls PWL determines the potential for light ballasts and oil containing electrical equipment to contain PCBs based on the age of the building, a review of maintenance records and examination of labels or nameplates on equipment, where present and accessible. The information is compared to known ban dates of PCBs and Environment Canada publications. PWL records spills or leakage of suspect PCB-containing fluids where observed or identified in historical documents. PWL samples exterior caulking or sealants for PCBs based on the date of construction or installation. Caulking installed after 1985 is presumed to be free of PCBs and hence not sampled. If sampled, analysis for PCBs is performed using an ASTM test method appropriate to the sample matrix at an accredited laboratory. 1.7 Ozone Depleting Substances (ODS) PWL determines the potential presence of ODS (chlorofluorocarbon, hydrochlorofluorocarbon, hydrofluorocarbon, halon, etc.) in air conditioning units, chillers, commercial coolers and fire suppression systems by visual inspection of manufactures labels or plates, maintenance records, or log books, etc. Domestic type equipment such as window mounted and small central air conditioners, refrigerators, and freezers are not evaluated for the presence of ODS. 1.8 Visible Mould PWL identifies the presence of mould if visibly present in a significant quantity on exposed building surfaces. If any mould growth is concealed within wall cavities it is not addressed in this assessment. 1.9 Stored Chemicals (Explosive Materials, Flammable Materials, Household Chemicals) A visual inspection is conducted to identify any stored chemicals (solvents, cleaners, paints, compressed gas, etc.). Quantities and contents were inventoried where possible Pinchin Ltd. Page 4 of 5

34 Cargill Grain Terminal, Methodology Document 1.10 Animal Carcasses and Droppings PWL identifies the presence of animal droppings and carcasses if visibly present in a significant quantity on exposed building surfaces. If any animal droppings and carcasses are concealed within wall cavities it is not addressed in this assessment. Locations were inventoried where possible Needles and Sharps PWL conducts a visual inspection to identify visible needles and or sharps. Locations were inventoried where possible Radioactive Materials PWL conducts a visual inspection to identify equipment that may contain radioactive materials Heavy Metals PWL conducts a visual inspection to identify equipment and materials, as well as industrial processes that contain or use heavy metals. Master Template: Methodology Document for Hazardous Building Materials Pre-Construction, HAZ, February 1, Pinchin Ltd. Page 5 of 5

35 APPENDIX IV Photographs

36 Cargill Grain Terminal, Appendix IV Lead-containing paints (brown, green and silver) on the Oil Circuit Breaker in the Substation Switch Yard. Lead-containing paints in poor condition on lamp posts and railings in the Substation Switch Yard Pinchin West Ltd. Page 1 of 2

37 Cargill Grain Terminal, Appendix IV Non-asbestos tar/mastic (unknown origin) within MCC 20. Canister of enamel/paint within MCC H-01r01_Photo Appendix.docx Template: Master Photo Appendix, HazMat, February 10, Pinchin West Ltd. Page 2 of 2

Asbestos Assessment East Facilities Services 97 Railside Road, Toronto, Ontario

Asbestos Assessment East Facilities Services 97 Railside Road, Toronto, Ontario Asbestos Assessment East Facilities Services 97 Railside Road, Toronto, Ontario Prepared for: Toronto Catholic District School Board 80 Sheppard Avenue East Toronto, Ontario, M2N 6E8 Attention: Kathleen

More information

Hazardous Building Materials Assessment 20 Westgate Street, Winnipeg, Manitoba

Hazardous Building Materials Assessment 20 Westgate Street, Winnipeg, Manitoba Hazardous Building Materials Assessment 20 Westgate Street, Winnipeg, Manitoba Prepared for: 4th Floor, 185 King Street Winnipeg, MB R3B 1J1 Attention: Ryan Mathews February 10, 2017 Pinchin File: 200012.004

More information

Hazardous Building Materials Assessment St. Louis Elementary School 75 Allen Street Waterloo, Ontario

Hazardous Building Materials Assessment St. Louis Elementary School 75 Allen Street Waterloo, Ontario St. Louis Elementary School 75 Allen Street Waterloo, Ontario Prepared for: City of Waterloo 500 Parkside Drive Waterloo, Ontario Attention: Jean Starchuk 79146 October 31, 2012 Pinchin Environmental Ltd.

More information

Hazardous Building Materials Assessment 240 Manor Road East, Toronto, Ontario

Hazardous Building Materials Assessment 240 Manor Road East, Toronto, Ontario 1 of 54 Hazardous Building Materials Assessment 240 Manor Road East, Toronto, Ontario Prepared for: City of Toronto 55 John Street, 2nd Floor Toronto, Ontario Attention: Sara Reid Environmental Project

More information

ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: C-CORE BUILDING MEMORIAL UNIVERSITY OF NEWFOUNDLAND

ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: C-CORE BUILDING MEMORIAL UNIVERSITY OF NEWFOUNDLAND ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: C-CORE BUILDING MEMORIAL UNIVERSITY OF NEWFOUNDLAND Prepared for: Memorial University of Newfoundland St. John s, NL Pinchin LeBlanc Environmental

More information

PRE-RENOVATION SURVEY FOR DESIGNATED SUBSTANCES. Good Neighbours Club Community Centre 170 Jarvis Street Toronto, Ontario

PRE-RENOVATION SURVEY FOR DESIGNATED SUBSTANCES. Good Neighbours Club Community Centre 170 Jarvis Street Toronto, Ontario PRE-RENOVATION SURVEY FOR DESIGNATED SUBSTANCES Good Neighbours Club Community Centre 170 Jarvis Street Toronto, Ontario Presented to: Sara Reid Environmental Coordinator City of Toronto Facility Management

More information

HAZARDOUS BUILDING MATERIALS SURVEY

HAZARDOUS BUILDING MATERIALS SURVEY HAZARDOUS BUILDING MATERIALS SURVEY Renovation Project Areas Social Services 178 Charlotte Street Peterborough, Ontario K9J 8S1 Presented to: City of Peterborough 500 George Street North Peterborough,

More information

FINAL Hazardous Building Materials Assessment Chebucto Road, Halifax, Nova Scotia

FINAL Hazardous Building Materials Assessment Chebucto Road, Halifax, Nova Scotia FINAL Hazardous Building Materials Assessment 6374-6376 Chebucto Road, Halifax, Nova Scotia Prepared for: Green Stem Housing Co-operative 2437 Davison Street Halifax, Nova Scotia B3K 4K9 Attn: Scott Coleman

More information

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Physical Plant Division Engineering and Architectural Services Department

More information

Pre-demolition Hazardous Building Materials Survey Report

Pre-demolition Hazardous Building Materials Survey Report Pre-demolition Hazardous Building Materials Survey Report 607 Cliff Avenue Enderby, BC Prepared for: City of Enderby PO Box 400, 619 Cliff Avenue Enderby, BC V0E 1V0 Attention: Mr. Tate Bengtson Chief

More information

PROJECT NO REPORT TO CITY OF STRATFORD ASBESTOS CONTAINING MATERIALS SURVEY ROW HOUSES STRATFORD, ONTARIO CONDUCTED BY:

PROJECT NO REPORT TO CITY OF STRATFORD ASBESTOS CONTAINING MATERIALS SURVEY ROW HOUSES STRATFORD, ONTARIO CONDUCTED BY: PROJECT NO. 1197 REPORT TO CITY OF STRATFORD ON ASBESTOS CONTAINING MATERIALS SURVEY ROW HOUSES STRATFORD, ONTARIO CONDUCTED BY: 1099 KINGSTON ROAD, SUITE 260 PICKERING, ONTARIO L1V 1B5 Tel: (416) 410-4333

More information

ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: COUGHLAN COLLEGE MEMORIAL UNIVERSITY OF NEWFOUNDLAND

ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: COUGHLAN COLLEGE MEMORIAL UNIVERSITY OF NEWFOUNDLAND ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: COUGHLAN COLLEGE MEMORIAL UNIVERSITY OF NEWFOUNDLAND Prepared for: Memorial University of Newfoundland St. John s, NL Pinchin LeBlanc Environmental

More information

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for Michigan State University Engineering and Architectural Services Physical Plant Building, Room 101 East Lansing, Michigan 48824-1326 at Michigan

More information

FINAL Hazardous Building Materials Assessment Windsor Street, Halifax, Nova Scotia

FINAL Hazardous Building Materials Assessment Windsor Street, Halifax, Nova Scotia FINAL Hazardous Building Materials Assessment 2547-2549 Windsor Street, Halifax, Nova Scotia Prepared for: Green Stem Housing Co-operative 2347 Davison Street Halifax, Nova Scotia B3K 2K9 Attn: Scott Coleman

More information

ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: QUEEN ELIZABETH II LIBRARY MEMORIAL UNIVERSITY OF NEWFOUNDLAND

ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: QUEEN ELIZABETH II LIBRARY MEMORIAL UNIVERSITY OF NEWFOUNDLAND ASBESTOS AND LEAD PAINT BUILDING MATERIALS SURVEY FOR: QUEEN ELIZABETH II LIBRARY MEMORIAL UNIVERSITY OF NEWFOUNDLAND Prepared for: Memorial University of Newfoundland St. John s, NL Pinchin LeBlanc Environmental

More information

FINAL Hazardous Building Materials Assessment Windsor Street, Halifax, Nova Scotia

FINAL Hazardous Building Materials Assessment Windsor Street, Halifax, Nova Scotia FINAL Hazardous Building Materials Assessment 2551-2553 Windsor Street, Halifax, Nova Scotia Prepared for: Green Stem Housing Co-operative 2437 Davison Street, Halifax, Nova Scotia Halifax, Nova Scotia

More information

ASBESTOS ASSESSMENT Curtis House Memorial University of Newfoundland St. John s, NL

ASBESTOS ASSESSMENT Curtis House Memorial University of Newfoundland St. John s, NL Project #: 13916 ASBESTOS ASSESSMENT Curtis House Memorial University of Newfoundland St. John s, NL Prepared for: Sheila Miller Director, Department of Health and Safety Memorial University of Newfoundland

More information

PRE-DEMOLITION HAZARDOUS BUILDING MATERIALS SURVEY

PRE-DEMOLITION HAZARDOUS BUILDING MATERIALS SURVEY PRE-DEMOLITION HAZARDOUS BUILDING MATERIALS SURVEY Residential Property 1533 Sherbrooke Street Peterborough, Ontario K9K 0E6 Presented to: City of Peterborough 500 George Street North Peterborough, Ontario

More information

City of Saskatoon Staff Development Center Asbestos Survey Report

City of Saskatoon Staff Development Center Asbestos Survey Report City of Saskatoon Staff Development Center Asbestos Survey Report December 2015 Prepared For: City of Saskatoon Infrastructure Services Facilities Branch Staff Development Center 116 Avenue W South, Saskatoon

More information

DESIGNATED SUBSTANCES REPORT

DESIGNATED SUBSTANCES REPORT Replacement of Hangers Doors Ottawa, Ontario Page 1 of 4 PART 1 GENERAL 1.1 Regulatory Requirements.1 The following Designated Substances Report (DSR) was prepared in order to meet the owners or engineer

More information

REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development

REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development Hazardous Materials Survey of 1710 East Kent Ave, Vancouver, BC Sampling Date: 2017-02-24 and 2017-03-10 Address: 1710 East Kent Ave,

More information

Pre-Demolition Hazardous Building Materials Survey

Pre-Demolition Hazardous Building Materials Survey Pre-Demolition Hazardous Building Materials Survey Commercial and Residential Property 212 and 210 Street East Peterborough, Ontario K9L 2A3 Presented to: City of Peterborough 500 George Street North Peterborough,

More information

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for Michigan State University Engineering and Architectural Services Physical Plant Building, Room 101 East Lansing, Michigan 48824-1326 at Michigan

More information

POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT. for

POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT. for POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT for Michigan State University Engineering and Architectural Services Physical Plant Division East Lansing, Michigan 48823 at the Owen Graduate

More information

Asbestos Inventory Survey of James Anderson Learning Centre, Avenue, Langley (Formerly Langley Fundamental Middle School)

Asbestos Inventory Survey of James Anderson Learning Centre, Avenue, Langley (Formerly Langley Fundamental Middle School) October 31, 2016 200753 AIS R1 James Anderson Learning Centre School District #35 (Langley) 20260 64 th Avenue Langley, BC V2Y 1N3 E mail: Attention: Reference: KWagner@sd35.bc.ca Karen Wagner Asbestos

More information

Asbestos Assessment St. Joseph s College Catholic Secondary School 74 Wellesley Street West, Toronto, Ontario

Asbestos Assessment St. Joseph s College Catholic Secondary School 74 Wellesley Street West, Toronto, Ontario Asbestos Assessment St. Joseph s College Catholic Secondary School 74 Wellesley Street West, Toronto, Ontario Prepared for: Toronto Catholic District School Board 80 Sheppard Avenue East Toronto, Ontario,

More information

REASSESSMENT SURVEY OF ASBESTOS - CONTAINING MATERIALS ANNE HATHAWAY DAYCARE CENTRE 103 Bruce Street Stratford, Ontario

REASSESSMENT SURVEY OF ASBESTOS - CONTAINING MATERIALS ANNE HATHAWAY DAYCARE CENTRE 103 Bruce Street Stratford, Ontario REASSESSMENT SURVEY OF ASBESTOS - CONTAINING MATERIALS ANNE HATHAWAY DAYCARE CENTRE 103 Bruce Street Stratford, Ontario June 30 th, 2014 Prepared for: Debbie Kindler - Supervisor 103 Bruce Street Stratford,

More information

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for. SSOE, Inc Wilshire Drive Suite 260 Troy, Michigan 48084

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for. SSOE, Inc Wilshire Drive Suite 260 Troy, Michigan 48084 POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for SSOE, Inc. 1050 Wilshire Drive Suite 260 Troy, Michigan 48084 at Michigan State University Physics Astronomy Building (Now Psychology) East

More information

ASBESTOS INSPECTION REPORT 3801 HARNEY STREET OMAHA, NEBRASKA 68132

ASBESTOS INSPECTION REPORT 3801 HARNEY STREET OMAHA, NEBRASKA 68132 ASBESTOS INSPECTION REPORT 3801 HARNEY STREET OMAHA, NEBRASKA 68132 Prepared For: Women s Center for Advancement 222 South 29 th Street Omaha, Nebraska 68131 June 20, 2016 Prepared By: New Horizons Enterprises,

More information

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for. Barton Malow/Clark MSU Spartan Stadium 58 Shaw Lane East Lansing, Michigan

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for. Barton Malow/Clark MSU Spartan Stadium 58 Shaw Lane East Lansing, Michigan POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for Barton Malow/Clark MSU Spartan Stadium 58 Shaw Lane East Lansing, Michigan 48824-1215 at Michigan State University I.M. West Building East

More information

Michigan State University

Michigan State University Michigan State University ASBESTOS BUILDING INSPECTION REPORT Botany Field Lab (Plant Pathology) Building Number 452 Inspection conducted by Zach Hansmann Office of Environmental Health and Safety 150

More information

Designated Substance Sampling, 1631 Queen Street East, Toronto, ON

Designated Substance Sampling, 1631 Queen Street East, Toronto, ON April 27, 2018 Meaghan Aldcroft Environmental Coordinator City of Toronto, Corporate Services Facilities Management Metro Hall, 55 John Street Toronto ON, M5V 3C6 Re: Designated Substance Sampling, 1631

More information

LIMITED ASBESTOS ASSESSMENT

LIMITED ASBESTOS ASSESSMENT LIMITED ASBESTOS ASSESSMENT FORMER DORAN MILL SITE 404 POLKVILLE ROAD SHELBY, NORTH CAROLINA 28150 ECS PROJECT NO. 49:4683 FOR CLEVELAND COUNTY ECONOMIC DEVELOPMENT JUNE 30, 2017 June 30, 2017 Mr. Matt

More information

ASBESTOS SURVEY. Old Detective s Building Wadesboro, NC INSPECTED &PREPARED BY:

ASBESTOS SURVEY. Old Detective s Building Wadesboro, NC INSPECTED &PREPARED BY: ASBESTOS SURVEY Old Detective s Building Wadesboro, NC PREPARED FOR: Alex Sewell Town Manager Town of Wadesboro 124 E. Wade Street Wadesboro, NC Date of Inspection September 28, 2016 Date of Report October

More information

Hazardous Building Materials Assessment Report

Hazardous Building Materials Assessment Report Hazardous Building Materials Assessment Report Berwick House 1375 Nicola Street Vancouver, BC Prepared for: Colliers International 15 th Floor, 200 Granville Street Vancouver, BC. V6C 2R6 Attention: Cristina

More information

Limited Asbestos Demolition Survey

Limited Asbestos Demolition Survey Limited Asbestos Demolition Survey Limited Asbestos Demolition Survey Former Fire Station Facility 25 to 45 S. Orlando Avenue Cocoa Beach, Florida Client: City of Cocoa Beach Public Works Department 1600

More information

InAIR Environmental Ltd.

InAIR Environmental Ltd. InAIR Environmental Ltd. Final Report Limited Designated Substances Survey Algonquin College, Building J Dental Clinic Ottawa, Ontario Survey Performed: February 2014 Prepared for: Mr. Len Tremblay P.Eng.,

More information

ASBESTOS ASSESSMENT Cartier Court Memorial University of Newfoundland St. John s, NL

ASBESTOS ASSESSMENT Cartier Court Memorial University of Newfoundland St. John s, NL Project #: 13916 ASBESTOS ASSESSMENT Cartier Court Memorial University of Newfoundland St. John s, NL Prepared for: Sheila Miller Director, Department of Health and Safety Memorial University of Newfoundland

More information

202 Pitt Street, Cornwall, ON Designated Substances Survey APPENDIX E. Pinchin Report (2006, 2008 & 2009)

202 Pitt Street, Cornwall, ON Designated Substances Survey APPENDIX E. Pinchin Report (2006, 2008 & 2009) 202 Pitt Street, Cornwall, ON Designated Substances Survey Final Report APPENDIX E Pinchin Report (2006, 2008 & 2009) January 2012 GENIVAR INC. Environmental Investigation Pitt St. & Second St. Cornwall,

More information

ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823

ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 at the Demonstration Hall Building #57 East Lansing, Michigan

More information

ANNUAL SURVEY FOR DESIGNATED SUBSTANCES AND HAZARDOUS MATERIALS

ANNUAL SURVEY FOR DESIGNATED SUBSTANCES AND HAZARDOUS MATERIALS ANNUAL SURVEY FOR DESIGNATED SUBSTANCES AND HAZARDOUS MATERIALS East York Civic Centre 850 Coxwell Avenue Toronto, Ontario Presented to: Sara Reid City of Toronto Corporate Services Facilities Management

More information

FM USC Work Order. Description HAZMAT SURVEY-100 Site. Assigned To Crew Start Date Due date Request Date. Building. Priority 5.

FM USC Work Order. Description HAZMAT SURVEY-100 Site. Assigned To Crew Start Date Due date Request Date. Building. Priority 5. FM00361888 Description HAZMAT SURVEY-100 Site COLUMBIA Building Floor 100 07 COKER LIFE SCIENCES Room: Equipment Assigned To Crew Start Date Due date Request Date USC Work Order JPROVENCE HAZMAT Priority

More information

ST. LUKE CATHOLIC ELEMENTARY SCHOOL

ST. LUKE CATHOLIC ELEMENTARY SCHOOL ST. LUKE CATHOLIC ELEMENTARY SCHOOL Final 2017 ACM Re-Assessment Report Project Location: 345 Albright Road Hamilton, ON Prepared for: Hamilton Wentworth Catholic District School Board 57 Stuart Street

More information

Asbestos Inventory Survey of Glenwood Elementary, Avenue, Langley, BC

Asbestos Inventory Survey of Glenwood Elementary, Avenue, Langley, BC October 25, 2016 200753 AIS R1 Glenwood Elementary School District #35 (Langley) 20260 64 th Avenue Langley, BC V2Y 1N3 E mail: Attention: Reference: KWagner@sd35.bc.ca Karen Wagner Asbestos Inventory

More information

202 Pitt Street, Cornwall, ON Designated Substances Survey APPENDIX E. Pinchin Report (2006, 2008 & 2009)

202 Pitt Street, Cornwall, ON Designated Substances Survey APPENDIX E. Pinchin Report (2006, 2008 & 2009) 202 Pitt Street, Cornwall, ON Designated Substances Survey Final Report APPENDIX E Pinchin Report (2006, 2008 & 2009) January 2012 GENIVAR INC. Environmental Investigation Pitt St. & Second St. Cornwall,

More information

REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development

REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development Hazardous Materials Survey Of: 1305 West 70 th Avenue MARPOLE PLACE Building Code: 2035 Address: 1305 West 70 th Avenue, Vancouver,

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823

ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 at the Dairy Cattle Teaching and Research Center Building

More information

July 13, 2011 TTL Project No NESHAP Asbestos and Limited Hazardous Materials Survey Report 500 North Congress Street Ypsilanti, Michigan

July 13, 2011 TTL Project No NESHAP Asbestos and Limited Hazardous Materials Survey Report 500 North Congress Street Ypsilanti, Michigan July 13, 2011 TTL Project No. 7615.02 Ms. Paula Boase Downriver Community Conference Brownfield Consortium 15100 Northline Road Southgate, Michigan 48195 Dear Ms. Boase: NESHAP Asbestos and Limited Hazardous

More information

Ontario Inc. March 10, Jardin Des Sapins Orleans, ON

Ontario Inc. March 10, Jardin Des Sapins Orleans, ON 2150 Thurston Drive, Suite 203 Ottawa, Ontario K1G 5T9 Tel.: (613) 748-1415 or 1-877-378-3745 Fax: (613) 748-1356 E-Mail: ottawa@dstgroup.com 2357976 Ontario Inc. March 10, 2014 1698 Jardin Des Sapins

More information

Project & Environmental Review. Guidelines Demolition. May 2016

Project & Environmental Review. Guidelines Demolition. May 2016 Project & Environmental Review Guidelines Demolition May 2016 TABLE OF CONTENTS 1. Introduction... 3 2. Objectives... 3 3. Applicability and Building Permits... 3 4. Guidelines for Preparing a Project

More information

October 8, Coulson Group 4890 Cherry Creek Rd Port Alberni, BC V9Y 8E9

October 8, Coulson Group 4890 Cherry Creek Rd Port Alberni, BC V9Y 8E9 October 8, 213 Coulson Group 489 Cherry Creek Rd Port Alberni, BC V9Y 8E9 Attention: Re: Mr. Britt Coulson Zellers Building, Port Alberni, BC (PHH ARC) conducted air monitoring for lead during the removal

More information

Hazardous Materials Inspection Services Seekonk Public Library, Seekonk, MA

Hazardous Materials Inspection Services Seekonk Public Library, Seekonk, MA January 10, 2017 Mr. Christopher Blessen Principal Tappe & Associates 6 Edgerly Place Boston, MA 02116 Reference: Hazardous Materials Inspection Services Seekonk Public Library, Seekonk, MA Dear Mr. Blessen:

More information

The following non-friable asbestos products were identified at the site:

The following non-friable asbestos products were identified at the site: April 27, 2018 Ms. Jessica Kenney Boulder Housing Partners 4800 Broadway Street Boulder, Colorado 80304 RE: Limited Asbestos-Containing Building Materials Survey Canyon Point Apartments First Floor 700

More information

Asbestos Assessment Campbellford / Seymour Community Centre 313 County Road 38 Campbellford, Ontario

Asbestos Assessment Campbellford / Seymour Community Centre 313 County Road 38 Campbellford, Ontario Asbestos Assessment Campbellford / Seymour Community Centre 313 County Road 38 Campbellford, Ontario Prepared for: Municipality of Trent Hills P. O. Box 1030, 66 Front Street South Campbellford, Ontario,

More information

ASBESTOS REINSPECTION SURVEY REPORT GENERAL SERVICES ADMINISTRATION AUBURN ADMINISTRATION BUILDING BUILDING WA0811KA AUBURN, WASHINGTON

ASBESTOS REINSPECTION SURVEY REPORT GENERAL SERVICES ADMINISTRATION AUBURN ADMINISTRATION BUILDING BUILDING WA0811KA AUBURN, WASHINGTON ASBESTOS REINSPECTION SURVEY REPORT GENERAL SERVICES ADMINISTRATION AUBURN ADMINISTRATION BUILDING BUILDING WA0811KA AUBURN, WASHINGTON May 23, 2007 Prepared for: Mr. Ron Smith GSA 400-15 th Street SW

More information

ASBESTOS SURVEY WARNER ROBINS HOUSING AUTHORITY PROJECT SITE GA06P WARNER ROBINS, GEORGIA. December 28, 2005

ASBESTOS SURVEY WARNER ROBINS HOUSING AUTHORITY PROJECT SITE GA06P WARNER ROBINS, GEORGIA. December 28, 2005 ASBESTOS SURVEY WARNER ROBINS HOUSING AUTHORITY PROJECT SITE GA06P160003 WARNER ROBINS, GEORGIA Prepared for: Warner Robins Housing Authority Ms. Charles Alexander Prepared by: Holley Consultants, Inc.

More information

MICHIGAN STATE UNIVERSITY

MICHIGAN STATE UNIVERSITY ASBESTOS SURVEY REPORT MICHIGAN STATE UNIVERSITY CENTER FOR INTEGRATIVE PLANT SYSTEMS EAST LANSING, MICHIGAN Prepared By: TEK Environmental & Consulting Services, Inc. 9670 Chilson Commons Circle Suite

More information

APPENDIX I. DST Hazardous Material Assessment. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX I

APPENDIX I. DST Hazardous Material Assessment. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX I APPENDIX I DST Hazardous Material Assessment APPENDIX I G3 Terminal Vancouver Port Metro Vancouver Project Permit Application DST Consulting Engineers Inc. Unit B 4125 McConnell Drive Burnaby, British

More information

Asbestos Elevator Industry Workshop November 25, 2015

Asbestos Elevator Industry Workshop November 25, 2015 Asbestos Elevator Industry Workshop November 25, 2015 BOB SWING CONTACT INFO EMAIL: Bob.Swing@ThyssenKrupp.com Phone: 604-499-5714 SOME ASBESTOS-CONTAINING MATERIALS Cement Pipes Cement Wallboard Cement

More information

FINAL Asbestos Management Program University of Windsor 401 Sunset Avenue, Windsor, Ontario

FINAL Asbestos Management Program University of Windsor 401 Sunset Avenue, Windsor, Ontario FINAL Asbestos Management Program University of Windsor 401 Sunset Avenue, Windsor, Ontario Prepared for: University of Windsor 401 Sunset Avenue Windsor, Ontario, N9B 3P4 Attn: Danny A. Castellan, P.Eng.

More information

NORWELL PUBLIC LIBRARY 64 South St, Norwell, MA 02061

NORWELL PUBLIC LIBRARY 64 South St, Norwell, MA 02061 INSPECTION REPORT FOR HAZARDOUS BUILDING MATERIALS NORWELL PUBLIC LIBRARY 64 South St, Norwell, MA 02061 Prepared For: Mr. Rick Pomroy Pomroy Associates LLC Village Place 448 Turnpike Street, Suite 1-1

More information

Designated Substances Survey Guelph Greyhound Station 141 Macdonell Street Guelph, Ontario

Designated Substances Survey Guelph Greyhound Station 141 Macdonell Street Guelph, Ontario Designated Substances Survey Guelph Greyhound Station 141 Macdonell Street Guelph, Ontario Prepared By: R.J. Burnside & Associates Limited 292 Speedvale Avenue West Unit 7 Guelph ON N1H 1C4 July 2010 File

More information

SUBPART 56-5 PHASE IA: ASBESTOS SURVEY PLANNING AND DESIGN

SUBPART 56-5 PHASE IA: ASBESTOS SURVEY PLANNING AND DESIGN SUBPART 56-5 PHASE IA: ASBESTOS SURVEY PLANNING AND DESIGN 56-5.1 Asbestos Survey Requirements for Building/Structure Demolition, Renovation, Remodeling and Repair (a) (b) Asbestos Survey Required. An

More information

REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development

REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development REAL ESTATE & FACILITIES MANAGEMENT Facilities Planning & Development Hazardous Materials Survey Of: MARPOLE PLACE ELEVATOR / MECHANICAL ROOMS Sampling Date: 2016/01/15 Building Code: 2035 Address: 1305

More information

Roseville OFFICE* 1911 Douglas Blvd, ste * Roseville, CA Phone (916) * Fax (916) *

Roseville OFFICE* 1911 Douglas Blvd, ste * Roseville, CA Phone (916) * Fax (916) * Roseville OFFICE* 1911 Douglas Blvd, ste 85-349* Roseville, CA 95661 Phone (916) 628-0050 * Fax (916) 781-6837 * www.hazmanage.com Camino Union Elementary School District Maintenance Building Demolition

More information

ETERNAL MEMORIALS ASBESTOS SURVEY REPORT

ETERNAL MEMORIALS ASBESTOS SURVEY REPORT ETERNAL MEMORIALS ASBESTOS SURVEY REPORT February 2014 Prepared For: City of Saskatoon Infrastructure Services Department 1101 Avenue P North, Saskatoon SK, Canada S7L 7K6 Attn: Brent Anderson Prepared

More information

REPORT. Asbestos-Containing Building Materials Assessment Report - Nutana Lawn Bowling Storage Garage CITY OF SASKATOON.

REPORT. Asbestos-Containing Building Materials Assessment Report - Nutana Lawn Bowling Storage Garage CITY OF SASKATOON. CITY OF SASKATOON Asbestos-Containing Building Materials Assessment Report - Nutana Lawn Bowling Storage Garage REPORT Submitted to: The City of Saskatoon 1101 Avenue P North Saskatoon, SK S7L 7K6 Report

More information

FINAL REPORT. Asbestos-Containing Building Material Assessment. Toronto Catholic District School Board

FINAL REPORT. Asbestos-Containing Building Material Assessment. Toronto Catholic District School Board FINAL REPORT Asbestos-Containing Building Material Assessment Toronto Catholic District School Board Corpus Christi Catholic School 4 Edgewood Avenue Toronto, Ontario PROJECT NO. 05760 PROJECT NO. 05760

More information

TRANSIT REPAIR TERMINAL NORTH BUILDING ASBESTOS SURVEY REPORT

TRANSIT REPAIR TERMINAL NORTH BUILDING ASBESTOS SURVEY REPORT TRANSIT REPAIR TERMINAL NORTH BUILDING ASBESTOS SURVEY REPORT April 2014 Prepared For: City of Saskatoon Infrastructure Services Department 1101 Avenue P North, Saskatoon SK, Canada S7L 7K6 Attn: Brent

More information

Investigation Remediation Citation Drive, Suite 100 Compliance Restoration Brighton, MI 48116

Investigation Remediation Citation Drive, Suite 100 Compliance Restoration Brighton, MI 48116 Investigation Remediation 10448 Citation Drive, Suite 100 Compliance Restoration Brighton, MI 48116 Mailing Address: P.O. Box 2160 Brighton, MI 48116-2160 800 395-ASTI Fax: 810.225.3800 www.asti-env.com

More information

1.0 Executive Summary

1.0 Executive Summary & Hazardous Materials Inspection 1.0 Executive Summary [Client] contracted with Parks Environmental Consulting, Inc. (Parks) to perform an inspection and sampling for asbestos-containing materials (ACM)

More information

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 Issued 6/1/95 Revised 11/08/2004; 3/6/06 Please direct any questions or comments about the applicability of this document to Luigi

More information

Hazardous Materials G

Hazardous Materials G Hazardous Materials G Needham Public Schools- Mitchell and Hillside HAZARDOUS MATERIALS HAZARDOUS MATERIALS Introduction: Universal Environmental Consultants (UEC) has been providing comprehensive asbestos

More information

HAZARDOUS AND REGULATED MATERIALS PRE-DEMOLITION ASSESSMENT REPORT

HAZARDOUS AND REGULATED MATERIALS PRE-DEMOLITION ASSESSMENT REPORT P E A K E N V I R O N M E N T A L LT D. 951 Pinewood Place West Kelowna, BC V1Z 3G7 e-mail: info@peakenvironmental.ca Toll Free 1-877-518-7325 (PEAK) HAZARDOUS AND REGULATED MATERIALS PRE-DEMOLITION ASSESSMENT

More information

AHERA/NESHAP ASBESTOS INSPECTION REPORT. CLIENT: City of Florence 324 West Evans Street Florence, SC (843)

AHERA/NESHAP ASBESTOS INSPECTION REPORT. CLIENT: City of Florence 324 West Evans Street Florence, SC (843) AHERA/NESHAP ASBESTOS INSPECTION REPORT CLIENT: City of Florence 324 West Evans Street Florence, SC 29501-3430 (843) 665-3173 LOCATION: 558 N. Alexander Street Florence, SC 29501 DATE OF INSPECTION: September

More information

FINAL REPORT. Asbestos-Containing Building Material Assessment

FINAL REPORT. Asbestos-Containing Building Material Assessment FINAL REPORT Asbestos-Containing Building Material Assessment Toronto Catholic District School Board St. Maurice Catholic School, 45 Kingsview Boulevard Etobicoke, Ontario PROJECT NO. 1025760 PROJECT NO.

More information

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22 Page 1 of 22 Asbestos Survey Project Summary Pursuant to your request; Environmental, Inc., has performed an Asbestos Building Survey on 8/13/2014 and limited to the above referenced location. The Interior/Exterior/Roof

More information

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278 PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278 PREPARED FOR: Mr. Roberto Aguirre City of San Francisco DPW, SAR, BCM 1680 Mission Street San Francisco, California PREPARED

More information

TRANSIT STORAGE & ADMINISTRATION BUILDING ASBESTOS SURVEY REPORT

TRANSIT STORAGE & ADMINISTRATION BUILDING ASBESTOS SURVEY REPORT TRANSIT STORAGE & ADMINISTRATION BUILDING ASBESTOS SURVEY REPORT April 2014 Prepared For: City of Saskatoon Infrastructure Services Department 1101 Avenue P North, Saskatoon SK, Canada S7L 7K6 Attn: Brent

More information

REFURBISHMENT ASBESTOS SURVEY REPORT

REFURBISHMENT ASBESTOS SURVEY REPORT Survey Reference B-50239 Client Lead Surveyor Assistant Surveyor Regal Theatre Tony Osborne N/A Start Date 13 June 2012 Completion Date 26 June 2012 Reviewed By Jon House REFURBISHMENT ASBESTOS SURVEY

More information

November 12, Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California

November 12, Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California November 12, 2014 Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California 95993-2240 RE: Pre-Renovation Asbestos Survey Report 5862 Rupert Avenue, Marysville, California

More information

FINAL REPORT. Asbestos-Containing Building Material Assessment. Toronto Catholic District School Board

FINAL REPORT. Asbestos-Containing Building Material Assessment. Toronto Catholic District School Board FINAL REPORT Asbestos-Containing Building Material Assessment Toronto Catholic District School Board Santa Maria Catholic School, 25 Avon Avenue Toronto, Ontario PROJECT NO. 1025760 PROJECT NO. 1025760

More information

INVITATION TO TENDER ITT NO. PS KITSILANO ARENA CHILLER REPLACEMENT AMENDMENT No. 1

INVITATION TO TENDER ITT NO. PS KITSILANO ARENA CHILLER REPLACEMENT AMENDMENT No. 1 FINANCE, RISK, & SUPPLY CHAIN MANAGEMENT Supply Chain Management June 6, 2018 INVITATION TO TENDER ITT NO. PS20180875 KITSILANO ARENA CHILLER REPLACEMENT AMENDMENT No. 1 RE: PART C SCHEDULE C HAZARDOUS

More information

LIMITED AHERA/NESHAP ASBESTOS INSPECTION AND LEAD PAINT CHIP REPORT 309 E STREET ANDERSON, SC

LIMITED AHERA/NESHAP ASBESTOS INSPECTION AND LEAD PAINT CHIP REPORT 309 E STREET ANDERSON, SC LIMITED AHERA/NESHAP ASBESTOS INSPECTION AND LEAD PAINT CHIP REPORT 309 E STREET ANDERSON, SC CLIENT: City of Anderson Department of Economic and Community Development 401 South Main Street Anderson, SC

More information

AHERA/NESHAP ASBESTOS INSPECTION REPORT 460 FEWELL STREET ROCK HILL, SC. CLIENT: City of Rock Hill P.O. Box Rock Hill, SC 29731

AHERA/NESHAP ASBESTOS INSPECTION REPORT 460 FEWELL STREET ROCK HILL, SC. CLIENT: City of Rock Hill P.O. Box Rock Hill, SC 29731 AHERA/NESHAP ASBESTOS INSPECTION REPORT 460 FEWELL STREET ROCK HILL, SC CLIENT: City of Rock Hill P.O. Box 11706 Rock Hill, SC 29731 LOCATION: 460 Fewell Street Rock Hill, SC 29730 DATE OF INSPECTION:

More information

ASBESTOS AND LEAD-BASED PAINT SURVEY 697 Cook Avenue St. Paul, Minnesota. Prepared for:

ASBESTOS AND LEAD-BASED PAINT SURVEY 697 Cook Avenue St. Paul, Minnesota. Prepared for: ASBESTOS AND LEAD-BASED PAINT SURVEY 697 Cook Avenue St. Paul, Minnesota Prepared for: City of St. Paul Department of Planning and Economic Development 1100 City Hall Annex 25 West 4 th Street St. Paul,

More information

Work Type Definition

Work Type Definition Work Type Definition Page 1-6 details the work type definition. In order to become pre-qualified for this work type, please see the Work Type Submittal Requirements on pages 7-8. I. Description A. Work

More information

Hikone. Sincerely, Enclosures

Hikone. Sincerely, Enclosures August 8, 2013 Mr. Richard Higgins Norstar Development USA, L.P. 733 Broadway Albany, New York 12207 Re: Asbestos Containing Material Survey Hikone 2702 2760 Hikone Road, Ann Arbor, Michigan ERG Project

More information

FINAL REPORT. Asbestos-Containing Building Material Assessment

FINAL REPORT. Asbestos-Containing Building Material Assessment FINAL REPORT Asbestos-Containing Building Material Assessment Toronto Catholic District School Board Nativity of Our Lord Catholic School 35 Saffron Crescent Etobicoke, Ontario PROJECT NO. 1025760 PROJECT

More information

Asbestos Procedures. Asbestos Abatement and Repair

Asbestos Procedures. Asbestos Abatement and Repair Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see for a list of known asbestos containing materials located on the Olympia campus. Where

More information

Limited Asbestos-Containing Materials Inspection Platt Road Ann Arbor, Michigan. Ann Arbor Housing Commission.

Limited Asbestos-Containing Materials Inspection Platt Road Ann Arbor, Michigan. Ann Arbor Housing Commission. Limited Asbestos-Containing Materials Inspection 3451-3457 Platt Road Ann Arbor, Michigan Ann Arbor Housing Commission November 11, 2013 Limited Asbestos-Containing Materials Inspection 3451-3457 Platt

More information

Cosmo Senior Center Asbestos Survey Report

Cosmo Senior Center Asbestos Survey Report Cosmo Senior Center Asbestos Survey Report February 2015 Prepared For: City of Saskatoon Infrastructure Services - Facilities Branch 3130 Laurier Drive, Saskatoon, SK. Attn: Brent Anderson Prepared By:

More information

LIMITED AHERA/NESHAP ASBESTOS INSPECTION AND LEAD PAINT CHIP REPORT 805 BEACHWOOD AVE. ANDERSON, SC

LIMITED AHERA/NESHAP ASBESTOS INSPECTION AND LEAD PAINT CHIP REPORT 805 BEACHWOOD AVE. ANDERSON, SC LIMITED AHERA/NESHAP ASBESTOS INSPECTION AND LEAD PAINT CHIP REPORT 805 BEACHWOOD AVE. ANDERSON, SC CLIENT: City of Anderson Department of Economic and Community Development 401 South Main Street Anderson,

More information

EVALUATION ON PROJECT Prepared for: Carson. City, Nevada

EVALUATION ON PROJECT Prepared for: Carson. City, Nevada HAZARDOUS MATERIALS EVALUATION STRUCTURAL DEMOLITIO ON PROJECT 162-04-501-0033 1111 DESERT LANE LAS VEGAS, NEVADA Prepared for: Nevada Department of Transportation 1263 South Stewart Street Carson City,

More information

Asbestos Inventory and Condition Assessment

Asbestos Inventory and Condition Assessment Prepared for: School District 85 - Vancouver Island North PO Box 90 Port Hardy, British Columbia V0N 2P0 Asbestos Inventory and Condition Assessment NWest Project Number: 30639 V.1.0 Prepared by: 201-415

More information

WHY SHOULD PROJECT OWNERS PROVIDE A LIST OF DESIGNATED SUBSTANCES?

WHY SHOULD PROJECT OWNERS PROVIDE A LIST OF DESIGNATED SUBSTANCES? In Ontario, section 30 of the Occupational Health and Safety Act requires that a project owner identify designated substances on the project and provide a list to prospective constructors as part of the

More information

AHERA/NESHAP ASBESTOS INSPECTION REPORT. CLIENT: City of Florence 324 West Evans Street Florence, SC (843)

AHERA/NESHAP ASBESTOS INSPECTION REPORT. CLIENT: City of Florence 324 West Evans Street Florence, SC (843) AHERA/NESHAP ASBESTOS INSPECTION REPORT CLIENT: City of Florence 324 West Evans Street Florence, SC 29501-3430 (843) 665-3173 LOCATION: 814 Gladstone Street Florence, SC 29501 DATE OF INSPECTION: September

More information

Asbestos Assessment Report Residential Structure 1530 W Bramlett Road Greenville, South Carolina S&ME Project No Phase 49

Asbestos Assessment Report Residential Structure 1530 W Bramlett Road Greenville, South Carolina S&ME Project No Phase 49 Attachment B Asbestos Assessment Report Residential Structure 1530 W Bramlett Road Greenville, South Carolina S&ME Project No. 4226-18-003 Phase 49 Asbestos Identified Asbestos Design Required Asbestos

More information

Asbestos Inventory and Condition Assessment

Asbestos Inventory and Condition Assessment Prepared for: School District 85 - Vancouver Island North PO Box 9 Port Hardy, British Columbia VN 2P Asbestos Inventory and Condition Assessment NWest Project Number: 314 V.1. Prepared by: 21-415 Gorge

More information