1 Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow BOIS D ARC LAKE Texas Water Conservation Association March 7, 2019 Tom Kula, NTMWD Executive Director Mike Rickman, NTMWD Deputy Director Operations & Maintenance
2 OVERVIEW Growing population Existing & Future Supplies Conservation Reuse New Reservoir Bois d Arc Lake & Related Projects Permitting Mitigation Construction Progress and Timeline Keys to Success Questions 2
3 Water Essential for Economic Growth Water supply infrastructure is the driving force of community and business vitality NTMWD Total Population Served: Historical and Projected Year Population Served 32,000 60, , ,000 1,700,000 2,500,000 3,700,000 Legacy West - Plano The Star - Frisco Watters Creek Convention Center Allen Craig Ranch - McKinney
4 Existing & Planned Raw Water Supplies Existing: Lavon Lake Lake Texoma Lake Tawakoni Chapman Lake Reuse/Wetland In Progress: Bois d Arc Lake
5 WATER SUPPLY PLANNING: FUTURE SOURCES Conservation and Reuse = 21% New Sources, Reservoirs = 25% New Reservoirs, 25% Current Supplies, 22% Chart represents NTMWD supplies in 2060 Source: 2016 Region C Water Plan Conservation & Reuse, 21% Connect Existing Supplies, 32% 5
6 BOIS CLICK D ARC TO EDIT LAKE MASTER TITLE STYLE Decade+ of planning, permitting Surface Area: 16,641 acres Supply: Firm Yield of 108 MGD Average/Max Depth: 22/70 ft Lake Elevation: 534 ft mean sea level (MSL) Owner & operator: NTMWD Cost Estimate: $1.6B Construction began May 2018 Impoundment expected Fall 2020 Water delivery expected Spring 2022 First major reservoir to be constructed in Texas in nearly 30 years
7 Bois d Arc Lake: Key Components & Related Infrastructure 1. Dam and intake structure for reservoir mile raw water pipeline 3. $50 million road projects 4. Mitigation area (over 17,000 acres) 5. New water treatment plant, pump station, terminal storage reservoir mile treated water pipeline 7
8 PLANNING AND PERMITTING TIMELINE December 2006 June 2008 State Water Rights Permit Application USACE Section 404 Permit Application February 2015 June 2015 USACE Issues Draft Environmental Impact Statement State Water Rights Permit Received Anticipating 404 Permit in Jan 2016 July 2015 USACE Requires HGM methodology for Mitigation Delay in expected 404 permit March 2017 USACE Issues Revised Draft Environmental Impact Statement November 2017 Feb 2018 USACE Issues Final Environmental Impact Statement USACE Section 404 Permit Received 8
9 CLICK TO EDIT MASTER TITLE STYLE AQUATIC AND TERRESTRIAL MITIGATION Environmental mitigation on more than 17,000 acres Largest permitteeresponsible ecological mitigation project in nation Over 8,500 acres of wetland restoration and enhancement Planting approx. 5 million trees Restoring or enhancing over 3,200 acres of native grasslands; 2,600 acres of forests Improving over 70 miles of local streams 9
10 RIVERBY CLICK TO RANCH EDIT MASTER MITIGATION TITLE SITE STYLE Trees Delivered and Stacked January 2019 Tree Planting Crew February 2019 Over 1.23 million trees planted to date (As of March 1)
11 CLICK PERMITTING TO EDIT REFORM MASTER RECOMMENDATIONS TITLE STYLE STREAMLINE PERMITTING Unnecessary delays from changeover in people, policies, concepts and procedures process should only take 2-3 years STATUTE OF LIMITATIONS TO PERMIT CHALLENGES Should be shortened to 180 days vs. 5+ years to avoid further delays of litigation FEDERAL FUNDING FOR SUPPLY PROJECTS Water supply lowest priority and lowest funded program of USACE need Congress to approve more funding and resources ESTABLISHING PURPOSE & NEED Population and demand projections developed/approved by state should be sufficient USE OF BEST AVAILABLE INFORMATION Applicants shouldn t be required to develop new or updated information late in permitting process recommend statutory deadline. Applicant and agencies should have binding agreement on impact assessment methods required for evaluation. COMPENSATORY MITIGATION Environmental benefits of supply projects should be considered as offsets to impacts
12 BOIS D ARC LAKE PROGRAM COMPONENTS Major Components include several projects; projects were separated by type of work/infrastructure: CMAR 1 Dam and Reservoir Clearing/Terminal Storage Reservoir Program Component 2 Full Service Provider Mitigation Project CMAR 3 Leonard Water Treatment Plant and Pump Stations CMAR 4 Roads and Bridges CMAR 5 Raw Water and Treated Water pipelines 12
13 CLICK TO EDIT MASTER TITLE STYLE CMAR 1 DAM & TERMINAL STORAGE RESERVOIR (TSR) Goal: By December 2020: Begin impounding water Complete terminal storage reservoir at Leonard WTP Foundation Excavation for the Dam Footprint August 2018 Scope: Dam and Clearing Intake Tower 210 MG (420 MG ultimate) terminal storage reservoir Lake Bonham Dam Improvements
14 BOIS CLICK D ARC TO EDIT LAKE MASTER DAM AND TITLE RESERVOIR STYLE Dam Embankment February mile long, 90-ft tall dam
15 BOIS CLICK D ARC TO EDIT LAKE MASTER DAM AND TITLE RESERVOIR STYLE Intake Tower Slab Pour January 2019 Excavating the Intake Tower Conduit January 2019 Slab = 1,100 cubic yards of concrete Two 78-inch pipes from Intake Tower to Pump Station
16 CLICK TO EDIT MASTER TITLE STYLE CMAR 3 WATER TREATMENT PLANT & PUMP STATIONS Goal: Complete and operational by First Quarter of 2022 Raw Water Pump Station Excavation February 2019 Scope: Raw Water Pump Station (RWPS) at the dam (90 MGD 236 MGD ultimate) 70 MGD Leonard Water Treatment Plant (LWTP) (280 MGD ultimate) High Service Pump Station (HSPS) at WTP site (90 MGD 330 MGD ultimate)
17 LEONARD CLICK TO EDIT WATER MASTER TREATMENT TITLE STYLE PLANT SITE AND RAW WATER PS December 2018 Looking North Raw Water Pump Station January 2019 Phase 1 = 210 MG terminal storage reservoir and 90 MGD high service pump station 9 pumps in a football field-sized building
18 CMAR CLICK 4 TO ROAD EDIT IMPROVEMENTS MASTER TITLE STYLE & BOAT RAMPS Goal: Before impoundment, complete: FM 897 Improvements Fannin County Road improvements Boat ramps FM 897 Columns and Bent Caps February 2019 Scope: FM miles of new FM roadway 1.3 miles of new bridge County roads Improvements at 9 locations Bridge, culvert, and roadway embankment Bridge/culvert demolition at 5 additional locations
19 CMAR CLICK 5 TO RAW EDIT AND MASTER TREATED TITLE WATER STYLEPIPELINES Approximately 35 miles of raw water pipeline and 25 miles of treated water pipeline
20 CLICK TO EDIT MASTER TITLE STYLE TIMELINE TO WATER DELIVERY IN
21 KEYS CLICK TO SUCCESS EDIT MASTER TITLE STYLE Reservoirs are an absolute necessity and we ve stayed focused on: PROTECTING ENVIRONMENT SMART DEVELOPMENT PROVIDING ESSENTIAL SERVICES TO NORTH TEXANS WATER IS LIFE Build relationships with state and federal agencies early Assemble dream team get right resources/expertise Get support from elected officials keep informed along the way Funded entire $1.6B project with low interest SWIFT funding from TWDB saving ~ $230 million Follow our progress at 21
22 QUESTIONS? FOLLOW
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow BOIS D ARC RESERVOIR
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow BOIS D ARC RESERVOIR Robert McCarthy, Permitting Manager Jeff McKito, Public Relations Specialist Greater Texoma Association
More informationENSURING REGIONAL PROSPERITY
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow ENSURING REGIONAL PROSPERITY Society of American Military Engineers: Infrastructure Forum R.J. Muraski, Assistant Deputy Director,
More informationNTMWD ESSENTIAL SERVICES, PROJECTS
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow NTMWD ESSENTIAL SERVICES, PROJECTS Society of American Military Engineers (SAME) Dallas Post September 17, 2018 Tom Kula, NTMWD
More informationLOWER BOIS D ARC CREEK RESERVOIR PROGRAM. NTMWD & Freese and Nichols August 29, 2017 LBCR Program Contractor Involvement Workshop
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow LOWER BOIS D ARC CREEK RESERVOIR PROGRAM NTMWD & Freese and Nichols August 29, 2017 LBCR Program Contractor Involvement Workshop
More informationWATER TREATMENT PLANT TOUR
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow WATER TREATMENT PLANT TOUR Tom Kula, Executive Director Billy George, Assistant Deputy Director Water August 11, 2017 Member
More informationCity Council Work Session Handouts. July 21, I. Review and Discuss North Texas Municipal Water District Water Supply Plan and Projects
City Council Work Session Handouts July 21, 2014 I. Review and Discuss North Texas Municipal Water District Water Supply Plan and Projects II. Review and Discuss the Richardson Hospital Authority Dissolution
More informationNorth Texas Municipal Water District Regional Service Through Unity Meeting Our Region s Needs Today and Tomorrow
North Texas Municipal Water District Regional Service Through Unity Meeting Our Region s Needs Today and Tomorrow Lower Bois d Arc Creek Reservoir Update Tom Kula, Executive Director Mike Rickman, Deputy
More informationSister Grove Regional Water Resource Recovery Facility
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow Sister Grove Regional Water Resource Recovery Facility New Hope City Council June 26, 2018 AGENDA North Texas Municipal Water
More informationNTMWD WATER AND WASTEWATER PROJECTS, COST FORECASTS
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow NTMWD WATER AND WASTEWATER PROJECTS, COST FORECASTS Tom Kula, Executive Director June 27, 2017 Forney City Council OUR CLICK
More informationNorth Texas Municipal Water District Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow
North Texas Municipal Water District Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow Water Committee Meeting March 23, 2016 Agenda I. CALL TO ORDER II. ACTION ITEMS A. Consider
More informationGlades Reservoir Environmental Impact Statement (EIS)
Glades Reservoir Environmental Impact Statement (EIS) Permit Application #SAS-2007-00388 Public Scoping Meeting Proposed Operational Plan/Scenarios March 2012 Glades Reservoir Environmental Impact Statement
More informationLAKE PALO PINTO STORAGE RESTORATION
Palo Pinto County MWD No. 1 and City of Mineral Wells Joint Meeting Cory Shockley, P.E. November 8, 2018 LAKE PALO PINTO STORAGE RESTORATION TURKEY PEAK PROJECT 2014 HDR, Inc., all rights reserved. History
More informationNORTH TEXAS MUNICIPAL WATER DISTRICT EAST FORK RAW WATER SUPPLY PROJECT
NORTH TEXAS MUNICIPAL WATER DISTRICT EAST FORK RAW WATER SUPPLY PROJECT Denise Hickey Agenda NTMWD Background Water Planning East Fork Raw Water Supply Project Overview Benefits Nature Center NTMWD BACKGROUND
More informationThe Path to 2060: Dallas Water Plan Update Reuse Partnership with North Texas Municipal Water District
The Path to 2060: Dallas Water Plan Update Reuse Partnership with North Texas Municipal Water District The State s 16 Regional Planning areas are identified by the letters A to P. Dallas is in Region C.
More informationCity of Dallas Drought Update. Dallas Water Utilities February 1, 2012
City of Dallas Drought Update Dallas Water Utilities February 1, 2012 Purpose This briefing provides an overview of the ongoing drought weather conditions and its impact on Dallas water supply and other
More informationWater Conservation Awareness and Education Programs May 12, 2016
North Texas Municipal Water District Regional Service Through Unity Meeting Our Region s Needs Today and Tomorrow Water Conservation Awareness and Education Programs May 12, 2016 Agenda I. NTMWD Background
More informationRegion C Water Planning Group Meeting. TRA Central Wastewater Treatment Plant April 25, 2005
Region C Water Planning Group Meeting TRA Central Wastewater Treatment Plant April 25, 2005 1 Agenda Action Items Additional Wholesale Water Providers Action on Unique Stream Segments Action on Policy
More informationWater Supply in North Texas: Where Does (and Where Will) it Come From?
Water Supply in North Texas: Where Does (and Where Will) it Come From? Alan H. Plummer, Jr., P.E., BCEE Ellen T. McDonald, Ph.D., P.E. Alan Plummer Associates, Inc. April 3, 2013 Where does your water
More informationPublic Hearing on. Region C Water Plan. May 25, 2010
Public Hearing on 2011 Initially Prepared Region C Water Plan May 25, 2010 Introduction The Regional Water Planning Process 2011 Region C Water Plan Plans for Major Providers Regional Water Planning Process
More informationFrequently Asked Questions: Wholesale Water Rates and Water Supply Contract
11-17-15 North Texas Municipal Water District (NTMWD) Frequently Asked Questions: Wholesale Water Rates and Water Supply Contract What is the role of the NTMWD in providing water to the region? The North
More informationANNUAL REPORT WASTEWATER SERVICES WATER SERVICES SOLID WASTE SERVICES MORE THAN WATER
2016-2017 ANNUAL REPORT WATER SERVICES WASTEWATER SERVICES SOLID WASTE SERVICES MORE THAN WATER ANNUAL REPORT 2017 WATER IS ESSENTIAL FOR LIFE, BUT IT TAKES MUCH MORE THAN WATER TO KEEP IT FLOWING TO NEARLY
More informationAPPENDIX I WATER SUPPLY AVAILABLE TO REGION C
APPENDIX I WATER SUPPLY AVAILABLE TO REGION C APPENDIX I WATER SUPPLY AVAILABLE TO REGION C Table I.1 shows the overall water supply available to Region C. Table I.2 shows the overall water supply available
More informationTexas Water Plan and Region C Water Plan. UTA Water Systems Design Class March 26, 2009
Texas Water Plan and Region C Water Plan Tom Gooch Freese and Nichols UTA Water Systems Design Class March 26, 2009 Introduction Who Am I Tom Gooch tcg@freese.com 817/735-7314 7314 Vice President, Freese
More informationPublic Notice of a Proposed Amendment of the 2001 Region C Water Plan
TO: FROM: RE: Each mayor of a municipality with a population of 1,000 or more or which is a county seat that is located in whole or in part in the Region C water planning area; Each county judge of a county
More informationAPPENDIX I WATER SUPPLY AVAILABLE TO REGION C DRAFT
APPENDIX I WATER SUPPLY AVAILABLE TO REGION C APPENDIX I WATER SUPPLY AVAILABLE TO REGION C Table I-1 shows the overall water supply available to Region C. Table I-2 shows the overall water supply available
More informationDELIVERING SAFE WATER FOR 60+ YEARS
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow DELIVERING SAFE WATER FOR 60+ YEARS Tom Kula, Executive Director Billy George, Assistant Deputy Director of Water Frisco City
More informationAPPENDIX I WATER SUPPLY AVAILABLE TO REGION C
APPENDIX I WATER SUPPLY AVAILABLE TO REGION C APPENDIX I WATER SUPPLY AVAILABLE TO REGION C Table I.1 shows the overall water supply available to Region C. Table I.2 shows the overall water supply available
More informationas it Affects North Texas and Water for Energy in North Texas
Texas Water Plan as it Affects North Texas and Water for Energy in North Texas Tom Gooch Freese and Nichols Geological Society of America March 16, 2009 Introduction Who Am I Tom Gooch tcg@freese.com 817/735-7314
More informationBreckenridge Second Water Treatment Plant. Public Open House. April 11, HDR, all rights reserved.
Breckenridge Second Water Treatment Plant Public Open House April 11, 2018 2015 HDR, all rights reserved. Why Build a Second Water Treatment Plant? Future Tarn WTP Refurbishment: o Allows existing Tarn
More informationInstream Flow Study for the Proposed Lower Bois d Arc Creek Reservoir, Texas
450,000 400,000 350,000 300,000 250,000 200,000 150,000 Instream Flow Study for the Proposed Lower Bois d Arc Creek Reservoir, Texas 100,000 50,000 0 Jan-48 Jan-51 Jan-54 Jan-57 Jan-60 Jan-63 Jan-66 Jan-69
More informationFORWARD. Questions regarding this water conservation plan should be addressed to the following:
Water Conservation Plan FORWARD This Water Conservation Plan was prepared by Freese and Nichols for the North Texas Municipal Water District (NTMWD), pursuant to Texas Commission on Environmental Quality
More information8.3 Somervell County Water Supply Project
8.3 Somervell County Water Supply Project 8.3.1 Description of Option The Somervell County Water District (SCWD) completed the first part of their surface water supply system in October 2011. Previously,
More informationFloodplain Jurisdiction 6/9/2014. Texas Floodplain Management Association May 29, 2014
Texas Floodplain Management Association May 29, 2014 Loretta E Mokry, PWS Craig T. Maske, P.E., CFM Alan Plummer Associates, Inc. Who really owns the floodplain? What do I have to do to use/develop the
More informationDRAFT. TO: Stephanie Griffin, P.E. PROJECT: Region C Water Supply Plan Freese and Nichols, Inc.
1320 South University, Suite 300 Fort Worth, Texas 76107-5764 Phone: 817.806.1700 Fax: 817.870.2536 DATE: September 15, 2008 PROJECT #: 0312-034-01 Memo TO: Stephanie Griffin, P.E. PROJECT: Region C Water
More information7.1 Introduction. 7.2 Consistency with the Protection of Water Resources
7. Description of How the Regional Water Plan is Consistent with Long-Term Protection of the State s Water Resources, Agricultural Resources, and Natural Resources 7.1 Introduction The development of viable
More informationIAFSM 2010 Annual Conference. City of Rockford Keith Creek Greenway Flood Mitigation Project
IAFSM 2010 Annual Conference City of Rockford Keith Creek Greenway Flood Mitigation Project March 10, 2010 Introduction Problem Overview 1890 s Building of homes along Keith Creek 1920 s Home construction
More informationVICINITY MAP AND SITE MAP. Page 1 of 9
INTRODUCTION... 2 1. Background Information of West Bottom Ash Pond (BAP)... 2 1.1 Facility Location Description...2 1.2 Description of West BAP CCR Unit...2 1.2.1 Embankment Configuration...2 1.2.2 Construction
More informationThe Evolution of the City of Asheville Water System. Presented by Leslie Carreiro and Bill Hart
The Evolution of the City of Asheville Water System Presented by Leslie Carreiro and Bill Hart First City of Asheville Water System Asheville Water System Prior to 1883 Beaucatcher Reservoir -5 Million
More informationSan Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis
San Antonio Water System enhancement. This recommendation was based on limited water quality data provided by SAWS and using a free-water surface constructed wetland with approximately 112 acres of wetted
More informationImplementing the Second Stage Short-Term Drought Response Strategy GMP No. 3 Garney Companies and Pepper Lawson. June 25, 2015
Implementing the Second Stage Short-Term Drought Response Strategy GMP No. 3 Garney Companies and Pepper Lawson June 25, 2015 DROUGHT IS REAL Lake Fort Phantom Hill Was 47% capacity in May, 2013 Now 43%
More informationFISH AND WILDLIFE MITIGATION AND ENHANCEMENT PLAN
NISP FISH AND WILDLIFE MITIGATION AND ENHANCEMENT PLAN Colorado Parks and Wildlife Commission June 9, 2017 NISP Northern Integrated Supply Project A Better Poudre River A new regional water supply project
More informationKlamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR
Klamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR Agenda Time 1:00pm 2:00pm 3:00pm Item Presentation on Design-Build RFQ 1. Room Safety 2. Project Background
More informationTOLEDO BEND PROJECT FERC NO DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES
TOLEDO BEND PROJECT FERC NO. 2305 DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES May 2011 Copyright 2011.Sabine River Authority of Texas and Sabine River
More information7.6 Lake Aquilla Storage Reallocation
Management of Existing Supplies Lake Aquilla Storage Reallocation 7.6 Lake Aquilla Storage Reallocation 7.6.1 Description of Option Figure 7.6-1 is an aerial map of Lake Aquilla showing the water surface
More informationDESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS
DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano, P.E. May 29, 2014 PROJECT BACKGROUND Integrated Pipeline Project 149 miles of pipeline 3 booster
More informationDraft Environmental Impact Statement Lake Ralph Hall Regional Water Supply Reservoir Project Volume II
US Army Corps of Engineers Fort Worth District October 2018 Draft Environmental Impact Statement Lake Ralph Hall Regional Water Supply Reservoir Project Volume II Lake Ralph Hall Volume II- Appendices
More information3. Analysis of Water Supply Currently Available to Region C
3. Analysis of Water Supply Currently Available to Region C This section gives an overall summary of the water supplies available to Region C. Appendix I includes further details on the development of
More informationINTEGRATED PROJECT DELIVERY. proactive & collaborative approach
INTEGRATED PROJECT DELIVERY proactive & collaborative approach AT GARNEY, A PROACTIVE AND COLLABORATIVE APPROACH IS IN OUR DNA. For more than 10 years, integrated project delivery methods have accounted
More informationNORTH TEXAS MUNICIPAL WATER DISTRICT WATER CONSERVATION AND DROUGHT CONTINGENCY AND WATER EMERGENCY RESPONSE PLAN MARCH 2008.
NORTH TEXAS MUNICIPAL WATER DISTRICT THIS DOCUMENT WAS ORIGINALLY SIGNED, SEALED AND DATED BY: AUTHORIZED BY: STEPHANIE W. GRIFFIN, P.E. TEXAS NO.: 88504 ON DATE: MARCH 31, 2008 THIS ELECTRONIC FILE IS
More informationStevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets
Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority
More informationAPPENDIX A CALCULATION OF NET PRESENT VALUE OF WATER SUPPLY PACKAGES. Total Capital Total Annual O&M Net Present Value ($) ($ per year) ($ Millions)
APPENDIX A CALCULATION OF NET PRESENT VALUE OF WATER SUPPLY PACKAGES Package Package 1 - Recycled Water + Emergency Supply + WTP Expansion Total Capital Total Annual O&M Net Present Value ($) ($ per year)
More informationTarrant Regional Water District Receives ISI Envision Silver Award
FOR IMMEDIATE RELEASE: Tarrant Regional Water District Receives ISI Envision Silver Award WASHINGTON, D.C. - (September 24, 2014) -The Institute for Sustainable Infrastructure (ISI) announced today that
More informationNorth Texas Municipal Water District Regional Service Through Unity Meeting Our Region s Needs Today and Tomorrow
North Texas Municipal Water District Regional Service Through Unity Meeting Our Region s Needs Today and Tomorrow Communications Committee Discussion April 27, 2016 Public Relations & Water Educators AGENDA
More informationRegion C Water Planning Group (RCWPG) Public Notice of Possible Amendments of the 2001 Region C Water Plan PUBLIC NOTICE
TO: FROM: RE: Mayors of municipalities with a population of 1000 or more or which is a county seat and that is located in whole or in part in the Region C Regional Water Planning Area; County Judges of
More informationMill Creek (HHEI)
Section 401 OEPA Water Quality Certification Application TRU-534-24.32 Transportation Improvements Project PID 23967 2-Aug-12 401 Table A Streams Affected by the Proposed Project Stream STA Description
More informationDRAFT MASTER PLAN RICHFIELD HERITAGE PRESERVE. Environmental OCTOBER 2016
DRAFT MASTER PLAN RICHFIELD HERITAGE PRESERVE OCTOBER 2016 Environmental DesignGroup STREETSBORO RD SITE BROADVIEW ROAD RICHFIELD HERITAGE PRESERVE 336 ACRES CLEAN OHIO CLEAN OHIO OVIATT RD RECAP FEBRUARY
More informationFigure 1 Demands on Lake Athens
Table 1 Projected Demands for Athens MWA and Lake Athens Water User Group Demand on Lake Athens 2010 2020 2030 2040 2050 2060 Comments City of Athens 2,326 2,832 3,431 4,111 5,003 6,108 Henderson Co. Irrigation
More informationTitle XVI Recycled Water Feasibility Study. RMCSD Board Meeting June 19, 2013
Title XVI Recycled Water Feasibility Study RMCSD Board Meeting Study Purpose Click to edit Master title style 1. Determine which developments are most cost-effective for recycled water service (e.g., leverage
More informationTexas-Sized Challenges
Aerial view of the City of Austin s Water Treatment Plant No. 4 in northwest Austin near the intersection of RM 620 and Bullick Hollow Road. cover story Delivering Water Provides Texas-Sized Challenges
More informationReuse Texas Style: Status of Potable Reuse Initiatives in the Lone Star State. Ellen McDonald, Ph.D., P.E. Alan Plummer Associates, Inc.
Reuse Texas Style: Status of Potable Reuse Initiatives in the Lone Star State July 25, 2014 Ellen McDonald, Ph.D., P.E. Alan Plummer Associates, Inc. Acknowledgments City of Brownwood David Harris, Director
More informationPEACE RIVER MANASOTA REGIONAL WATER SUPPLY AUTHORITY BOARD OF DIRECTORS MEETING December 5, 2018 ROUTINE STATUS REPORTS ITEM 1
PEACE RIVER MANASOTA REGIONAL WATER SUPPLY AUTHORITY BOARD OF DIRECTORS MEETING December 5, 218 ROUTINE STATUS REPORTS ITEM 1 Hydrologic Conditions Report MEMORANDUM Project: Hydrologic Conditions Report
More information8.4 West Central Brazos Water Distribution System
8.4 West Central Brazos Water Distribution System 8.4.1 Description of Option The West Central Brazos Water Distribution System (WCBWDS) is a relatively unused system that could potentially provide raw
More information3. Analysis of Water Supply Currently Available to Region C
3. Analysis of Water Supply Currently Available to Region C This section gives an overall summary of the water supplies available to Region C. Appendix I includes further details on the development of
More informationA World of Solutions
Project Goals Engineering, Economics, & Environmental Principles Minimization of execution risks Construction industry s highest standards Cost savings vs. conventional methods Consistency with Master
More informationREGION C WATER PLANNING GROUP
REGION C WATER PLANNING GROUP Senate Bill One Fifth Round of Regional Water Planning - Texas Water Development Board Board Members Jody Puckett, Chair Russell Laughlin, Vice-Chair Kevin Ward, Secretary
More informationHolly Swartz and Jason Shirey
Chapter 105 General Permits for Stream and Wetland Impacts DEP Ch. 105 CONTACTS FOR BERKS COUNTY: Holly Swartz and Jason Shirey What DEP Regulates Under Chapter 105 Waters of the Commonwealth, which includes
More informationDALLAS WATER UTILITIES LONG RANGE PLANNING FOR SUSTAINABILITY
DALLAS WATER UTILITIES LONG RANGE PLANNING FOR SUSTAINABILITY Albert H. Halff 2015 Water Resources Workshop Dallas Post of the Society of American Military Engineers July 20, 2015 Maggiano's Little Italy,
More informationWater Conservation Plan Allen, Texas. Gail Donaldson Water Conservation Manager November 22, 2013
Water Conservation Plan Allen, Texas Gail Donaldson Water Conservation Manager November 22, 2013 ALLEN, TEXAS Population: 87,157 Median Age: 33.5 Avg. Household Income: $106,563 27.11 Sq. Miles Average
More informationBattling Texas Worst One-Year Drought: Drought Planning and Response in the Lone Star State
Battling Texas Worst One-Year Drought: Drought Planning and Response in the Lone Star State Rachel A. Ickert, P.E. 1, Thomas C. Gooch, P.E. 2, Amy D. Kaarlela, P.H. 3, Nicholas Lester, P.E. 4 1 Project
More informationNTMWD REGIONAL WASTEWATER SYSTEM
Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow NTMWD REGIONAL WASTEWATER SYSTEM Tour of South Mesquite Regional Wastewater Treatment Plant November 28, 2017 REGIONAL WASTEWATER
More informationC43 West Basin Storage Reservoir. Hendry County Commission January 22, 2019
C43 West Basin Storage Reservoir Hendry County Commission January 22, 2019 Project Location SFWMD Trailer Compound C-43 Reservoir Townsend Canal Perimeter Dam Appox. 6 Mi C-43 Reservoir Separator Dam Perimeter
More informationSabine River Authority of Texas Summary Report MtBE Contamination in Lake Tawakoni from Gasoline Pipeline Rupture 5. TREATMENT AND REMEDIATION
5. TREATMENT AND REMEDIATION Explorer is responsible for the treatment and remediation of areas contaminated by the gasoline spill, including the reservoir. Explorer has worked cooperatively with SRA to
More information4. Present Activities and Roles
4. Present Activities and Roles The present missions, authorities, activities and roles of the various agencies involved with flood protection, floodplain management and flood-damage reduction are identified
More informationCape Fear River Water Supply Evaluation
Cape Fear River Water Supply Evaluation March 30, 2016 Division of Water Resources Cape Fear River WaterSupply Evaluation Todays goal: Review the Draft Cape Fear River Water Supply Evaluation Review the
More informationFAST TRACK RELIEF TO MIDLAND S EMERGENCY THIRST
FAST TRACK RELIEF TO MIDLAND S EMERGENCY THIRST Todd Larson, Director of Commercial & Risk Management Black & Veatch Water, Design Build Americas Presented to Texas Association of Clean Water Agencies
More informationCoping With an Increase in Energy Usage. Cynthia Lane American Water Works Association
Coping With an Increase in Energy Usage at Drinking Water Facilities Cynthia Lane American Water Works Association September 15, 2009 Today s Presentation Energy usage at drinking water utilities Data
More informationFormer cornfield, Bear Creek Wetland Mitigation Bank, LaGrange, North Carolina
Former cornfield, Bear Creek Wetland Mitigation Bank, LaGrange, North Carolina Environmental Mitigation Banking & Stream and Wetland Restoration RESTORATION SYSTEMS. LLC 1101 HAYNES STREET. SUITE 211 RALEIGH.
More informationMEMORANDUM. Supplemental Reservoir Screening Study July 23, 2010 Page 2 of 12
Supplemental Reservoir Screening Study July 23, 2010 Page 2 of 12 MEMORANDUM must be pumped from the main stem of the river when available to obtain the desired reservoir yield. The diversion pumping rate
More informationIcicle Creek Water Resource Management Strategy
Icicle Creek Water Resource Management Strategy January 14, 2015 Mike Kaputa Director Chelan County Department of Natural Resources Dan Haller, PE Water Resources Engineer Aspect Consulting Background
More informationProject Name: St. Johns River/Taylor Creek Reservoir
Project Name: St. Johns River/Taylor Creek Reservoir Project Location: Osceola and Orange counties Project Number: 126 Project Type: Surface Water Description of project: The proposed St. Johns River/Taylor
More informationIDEM Wetlands and Streams Regulatory Overview. An overview of IDEM permitting for work in Waters of the State
IDEM Wetlands and Streams Regulatory Overview An overview of IDEM permitting for work in Waters of the State Who Has Jurisdiction? Adjacent wetland: USACE & IDEM Stream > 1 sq. mile drainage: IDNR, USACE
More informationWatershed Response to Water Storage. 8/1/2012 Paul Wymar Scientist Chippewa River Watershed Project
Watershed Response to Water Storage 8/1/2012 Paul Wymar Scientist Chippewa River Watershed Project Chippewa River Watershed 1.3 Million Acres Largest tributary watershed in the Minnesota River Basin 7
More information10497 Town and Country Way, Suite 600 Houston, Texas fax
TECHNICAL MEMORANDUM 1497 Town and Country Way, Suite 6 Houston, Texas 7724 713-6-68 fax 713-6-681 www.freese.com TO: Jace Houston David Parkhill, P.E. CC: Davies Mtundu FROM: Jason D. Afinowicz, P.E.
More informationTexas Groundwater Summit
Guadalupe-Blanco River Authority Mid-Basin Water Supply Projects Texas Groundwater Summit James Lee Murphy, Esq. Executive Manager for Water Resources & Utility Operations Guadalupe-Blanco River Authority
More informationHis Worship Mayor Don Darling and Members of Common Council. SUBJECT: Project Performance Update Safe, Clean Drinking Water Project
COUNCIL REPORT M&C No. 2016-214 Report Date August 12, 2016 Meeting Date August 22, 2016 Service Area Saint John Water His Worship Mayor Don Darling and Members of Common Council SUBJECT: Project Performance
More informationPUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS
ISSUE DATE: December 15, 2015 EXPIRATION DATE: January 15, 2016 PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS Availability of Draft Environmental Assessment and Draft Finding of No Significant Impact REPLY
More information7 Management of Existing Supplies
7 Management of Existing Supplies 7.1 Lake Belton to Lake Stillhouse Hollow Pipeline 7.1.1 Description of Option A pipeline is proposed to connect Lake Belton to Lake Stillhouse Hollow (Figure 7.1-1) to
More informationSection 2. Mono Basin Operations
Section 2 Mono Basin Section 2 Mono Basin Compliance with State Water Resources Control Board Decision 1631 and Order Nos. 98-05 and 98-07 May 2014 Los Angeles Department of Water and Power Table of
More information7.9 Lake Whitney Reallocation
7.9 Lake Whitney Reallocation 7.9.1 Description of Option Lake Whitney is a major impoundment located on the Brazos River approximately 30 miles north of the City of Waco in Hill and Bosque Counties. The
More informationEXISTING EID WATER SUPPLY SOURCES
EXISTING EID WATER SUPPLY SOURCES FOLSOM RESERVOIR Folsom Reservoir is located at the west end of El Dorado County, at the confluence of the North and South Forks of the American River. EID treats water
More informationPublic Scoping Meetings
Public Scoping Meetings GRASS VALLEY Wednesday, March 9, 2016 6:00 8:00 p.m. Holiday Inn Express 121 Bank Street Grass Valley, CA 95945 AUBURN Thursday, March 10, 2016 6:00 8:00 p.m. Forest Lake Christian
More informationGregory J. Eldridge, P.E. Vice President Haley and Ward, Inc.
Gregory J. Eldridge, P.E. Vice President Haley and Ward, Inc. July 2012 Howe Street Water Supply Site There are 5 wells located at the Howe Street site All 5 wells are gravel packed wells with at least
More informationSW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN
SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN BACKGROUND INFORMATION Project SWIM? Aquatic Control? Exotic Control? Mitigation Bank? Type No No No No Mitigation Restoration and enhancement Type
More informationChehalis Basin Strategy Programmatic SEPA Draft EIS
Chehalis Basin Strategy Programmatic SEPA Draft EIS History of Flooding I-5 closed in 1990, 1996, 2007, 2009 Five largest flood events occurred since 1986 2 History of Habitat Degradation Harvest has been
More informationFlorida Department of Environmental Protection
Florida Department of Environmental Protection Noticed General Permit for Dredging of Public Navigation Channel and Canal Infrastructure by the West Coast Inland Navigation District within Lee County Background
More informationSweet Creek Road Retaining Wall Replacement. Mapleton, OR
Sweet Creek Road Retaining Wall Replacement Mapleton, OR Technical Information Project Completion Date: April 30, 2013 Project Location: Mapleton, OR Size of Project: 15,000 SF, 870 CY Concrete Strength
More informationNORTH TEXAS MUNICIPAL WATER DISTRICT
NORTH TEXAS MUNICIPAL WATER DISTRICT WATER CONSERVATION AND DROUGHT CONTINGENCY PLAN AUGUST 2004 REVISED APRIL 2006 Prepared for: Stephanie W. Griffin, P.E. NORTH TEXAS MUNICIPAL WATER DISTRICT Thomas
More informationGlades Reservoir Draft Environmental Impact Statement
Glades Reservoir Draft Environmental Impact Statement Chapter 4 Environmental Consequences October 2015 4 ENVIRONMENTAL CONSEQUENCES 4.1 INTRODUCTION 4-1 4.1.1 Types and Definitions of Impacts 4-1 4.1.2
More informationHydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the
Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) Photo Credit: Bakersfield.com This summary was produced by the Hydropower Reform Coalition KERN RIVER, CA KERN
More information