CHAPTER 5 EXISTING FACILITIES

Size: px
Start display at page:

Download "CHAPTER 5 EXISTING FACILITIES"

Transcription

1 CHAPTER 5 EXISTING FACILITIES INTRODUCTION The District s original wastewater collection system was constructed and brought on-line in 1970 and Additional sewer facilities have been constructed within the District over the past 40 years. The District has agreements with Everett and AWWD that provide for the treatment and disposal of all wastewater generated within the District. The majority of the wastewater collected in the District flows to the City of Everett s Wastewater Pollution Control Facility (WPCF), located approximately six miles to the north of the District boundary. The District s remaining wastewater flows through the Alderwood Water and Wastewater District s (AWWD) sewer system before continuing on to the King County Department of Natural Resources (KCDNR) for treatment. The District also has an agreement with Snohomish County and Everett for the conveyance of leachate from the Cathcart Landfill to Everett for treatment. Copies of these agreements are located in Appendix B. EXISTING WASTEWATER COLLECTION SYSTEM The District s wastewater collection system consists of 22 sewage lift stations, approximately 13.1 miles of force main, and 155 miles of gravity sewer line. A schematic representation of the District s lift stations and force mains is shown in Figure 5-1. SEWAGE LIFT STATIONS An inventory of the District s sewage lift stations is presented in Table 5-1. The three lift stations with the highest capacity are Lift Station No. 2, Pioneer Trails, and Lift Station No. 3. The drainage basin areas for each lift station, as well as the areas that drain to Everett or AWWD by gravity, are shown in Figure 5-2. FORCE MAINS An inventory of the District s force mains, sorted by pipe diameter, is presented in Table 5-2. A summary of the force main for each sewage lift station is presented in Table 5-3. Silver Lake Water & Sewer District 5-1 Wastewater Comprehensive Plan April 2011

2 TABLE 5-1 Inventory of Sewage Lift Stations Year Station Station Serial Pump No. of Capacity (2) TDH (3) Motor Impeller Surge Relief Auxiliary No. Lift Station (1) On-Line Type No. Model Pumps (gpm) (ft) Power (hp) Size (inch) Valve Power (4) th Street 2003 Vacuum Lift V 6D3B 2 1, No 60 kw th Street 2007 Vacuum Lift N 6D3B No 75 kw 3 Creekside 2001 Vacuum Lift F 4C3B No 80 kw 4 Glacier Peak 2011 Submersible TBD No None 5 Highlands East 2001 Vacuum Lift W 4D4B No 100 kw 6 Highlands I 1997 Vacuum Lift C3B No 65 kw 7 Highlands II 1999 Vacuum Lift C3B No 60 kw 8 Lift Station No Wet Pit/Dry Pit V 8D4C 3 3, (5) Yes 300 kw 9 Lift Station No Wet Pit/Dry Pit D4C 3 2, (5) No 175 kw 10 Lift Station No Vacuum Lift B4A No 40 kw 11 Lowell Larimer No Vacuum Lift K 4D4B Yes 215 kw Lowell Larimer No Vacuum Lift V 4C3B No 47 kw 13 Pioneer Trails 1987 Wet Pit/Dry Pit D4D 2 2, (5).625 No 175 kw 14 Silver Firs 1994 Wet Pit/Dry Pit D No 60 kw 15 Sector Wet Pit/Dry Pit D5 3 1, (5) Yes 450 kw 16 The Point 2011 Vacuum Lift TBD 4D4B No 80 kw 17 Thomas Lake 2000 Vacuum Lift C3B 3 1, No 80 kw 18 Valmont 2011 Vacuum Lift W 4C3B No 60 kw 19 Waldenwood 1999 Wet Pit/Dry Pit D5 2 1, (5) Yes 300 kw 20 Windsong Terrace 1988 Vacuum Lift B2D No 30 kw 21 Woodlands East 2005 Vacuum Lift V 4C2B No 35 kw 22 Woodlands North 1979 Wet Pit/Dry Pit C 4D No 60 kw (1) The location of each sewage lift station is shown in Figure 5-3. (2) Capacity is based on testing performed at startup. (3) Total Dynamic Head. (4) Size. (5) Variable Frequency Drive (VFD). 5-2 Silver Lake Water & Sewer District April 2011 Wastewater Comprehensive Plan

3

4 23 ³ SCALE 1 = 3,000' LEGEND: SILVER LAKE WATER DISTRICT BOUNDARY STUDY AREA 180TH STREET 164TH STREET CREEKSIDE GLACIER PEAK HIGHLANDS EAST HIGHLANDS HIGHLANDS II LIFT STATION NO. 2 LIFT STATION NO. 3 LIFT STATION NO. 4 LOWELL LARIMER NO. 1 LOWELL LARIMER NO. 2 PIONEER TRAILS SILVER FIRS NEW SECTOR 7 THE POINT THOMAS LAKE VALMONT WALDEN WOOD WINDSONG TERRACE WOODLANDS EAST WOODLANDS NORTH EVERETT GRAVITY ALDERWOOD GRAVITY LITTLE BEAR CREEK GRAVITY SILVER LAKE WATER & SEWER DISTRICT WASTEWATER COMPREHENSIVE PLAN FIGURE 5-2 DRAINAGE BASINS

5 TABLE 5-2 Inventory of Force Mains (1) Pipe Diameter Length (LF) Length (Miles) , , , , , , Total (LF) 69, (1) District-owned force mains are Ductile Iron, Cast Iron, or HDPE. The length and capacity of each force main is provided in Table 5-3, with the capacity as calculated for a maximum velocity of 8 feet per second. The location of each force main is shown in Figure 5-3. TABLE 5-3 Inventory of Lift Station Force Mains (1) Lift Station (Force Main Source) Diameter (inches) Length (LF) Capacity (2) (gpm) 164 th Street 10 PVC 5,933 1, th Street 8 D.I. 8 O.D. DR11 HDPE 74 2,465 1, Creekside 6 D.I. 3, Glacier Peak 4 O.D. HDPE Highlands East 8 D.I. 5,550 1,253 Highlands I 6 D.I. 2, Highlands II 6 D.I. 2, Lift Station No. 2 Lift Station No. 3 (5) 18 O.D. HDPE 16 (3) D.I. 10 (4) C.I ,600 1,196 4,136 5,013 1, D.I. D.I. 10 D.I. 2,250 4,000 3,700 5,013 2,820 1,958 Lift Station No. 4 8 D.I ,253 Lowell Larimer No. 1 8 D.I. 8 O.D HDPE 1, , Silver Lake Water & Sewer District 5-3 Wastewater Comprehensive Plan April 2011

6 TABLE 5-3 (continued) Inventory of Lift Station Force Mains (1) Lift Station (Force Main Source) Diameter (inches) Length (LF) Capacity (2) (gpm) Lowell Larimer No. 2 8 D.I ,253 Pioneer Trails 10 D.I. (6) 1,058 1,958 The Point 6 C.I. 2, New Sector 7 D.I./ O.D. HDPE 5,200 2,075 Silver Firs 8 D.I. 1,0 1,253 Thomas Lake D.I. (6) 10 O.D. HDPE 4,760 1,850 2,820 1,475 Valmont 6 D.I. 1, Waldenwood East 10 D.I. 8 D.I. 3,414 3,970 1,958 1,253 Windsong Terrace 6 D.I. 2, Woodlands East 6 C.I Woodlands North 4 C.I. 1, (1) Through May, (2) Capacity based on maximum velocity of eight feet per second (8 fps). (3) 16-inch FM from Lift Station No. 2 and 10-inch FM from Waldenwood Lift Station run parallel for 3,414 LF and can be shared. (4) This section of 10-inch FM coming from Lift Station No. 2 is normally closed. (5) Two force mains (10-inch and -inch) flow from Lift Station No. 3. The 10-inch FM can be opened to convey flows to Lift Station No. 2. The -inch increases in size to a 16-inch and conveys flows to Pioneer Trails Lift Station. (6) -inch FM from Thomas Lake and 10-inch FM from Pioneer Trails run parallel for 958 lf and can be shared. GRAVITY MAINS An inventory of the District s gravity sewer lines, sorted by pipe diameter and pipe material, is presented in Table 5-4. All concrete sewer lines were installed prior to 1980, while all PVC and D.I. sewer line has been installed from 1980 to the present. The 8-inch gravity sewers collect sewage flows within residential areas. Gravity sewers larger than 8-inch collect sewage flows from smaller pipes and convey the flow to lift stations or larger trunk lines. The data in Table 5-4 was taken from the District GIS Database/Map. The database indicates 61,386 lineal feet of pipe of unknown diameter and/or material. The City of Everett South End Interceptor (30- and 36-inch pipes) are owned and maintained by Everett, and therefore these are not counted in the District s inventory. 5-4 Silver Lake Water & Sewer District April 2011 Wastewater System Comprehensive Plan

7 RE EN SCALE 1 = 3,000' LOWEL L 9 LAR IME R 15 4 '' CATHCART LANDFILL NO. LIFT STATION TH STREET 180TH STREET CREEKSIDE GLACIER PEAK HIGHLANDS EAST HIGHLANDS HIGHLANDS II LIFT STATION NO. 2 LIFT STATION NO. 3 LIFT STATION NO. 4 LOWELL LARIMER NO. 1 LOWELL LARIMER NO. 2 PIONEER TRAILS SILVER FIRS NEW SECTOR NO. 7 THE POINT THOMAS LAKE VALMONT WALDENWOOD WINDSONG TERRACE WOODLANDS EAST WOODLANDS NORTH LEGEND FORCE MAIN STUDY AREA GRAVITYSEWER SILVER LAKE WATER & SEWER DISTRICT CATHCART LANDFILL SR REE K 10 LIFT STATION EVERETT SOUTH END INTERCEPTOR MIL LC 164TH 15 '' '' SR SE AT T ND 10 6 '' 15 I-5 8TH 13 BOTHELL EVERETT LE I-5 6 MARSH IL L H 6 36 LL MA 19TH EV ER G T RET EVE ³ SECOND PARCELS 110 SILVER LAKE WATER & SEWER DISTRICT WASTEWATER COMPREHENSIVE PLAN FIGURE 5-3 EXISTING FORCE MAINS AND MAJOR GRAVITY LINES 2 180TH

8 TABLE 5-4 Inventory of Gravity Mains (1) Pipe Diameter Pipe Material (2) Length (LF) Length (Miles) 24 D.I D.I D.I. 3, D.I D.I D.I. 4, D.I. 14, D.I. 50, D.I. Subtotal 75, PVC 7, PVC PVC 6, PVC 20, PVC, PVC 519, PVC Subtotal 567, CONC CONC 7, CONC 1, CONC 3, CONC 96, Concrete Subtotal 108, Unknown Unknown 64,207.2 Total 816, (1) Data based on District GIS Database/Map. (2) D.I. = Ductile Iron; PVC Poly Vinyl Chloride; CONC = Concrete. DISTRICT SEWER AGREEMENTS All wastewater collected within the District is transported for treatment to either Everett or KCDNR via the Alderwood Water & Wastewater District (AWWD). Interlocal sewer service agreements have been established with Everett and AWWD for disposal of wastewater collected within the District. The District also maintains an interlocal agreement with Cross Valley Water District to provide sewer service within areas along Lowell Larimer Road. The District has an agreement with Snohomish County and Everett for the conveyance of leachate from the Cathcart Landfill, located in the eastern portion of the District s service area. Figure 5-4 illustrates the regional sewer system relative to the District. Figure 5-5 illustrates the service agreement areas. Silver Lake Water & Sewer District 5-5 Wastewater Comprehensive Plan April 2011

9 CITY OF EVERETT AGREEMENT In 1982, the District entered into the existing sewer agreement with Everett. The 1982 agreement rescinded the two prior agreements of 1970 and 1974, which established a cost sharing arrangement based on the number and type of connections within the District. The cost sharing arrangement is now based upon the District s required capacity within components of Everett s sewer system, including interceptor lines and Water Pollution Control Facility (WPCF). The agreement was amended in 1991, as the District purchased additional capacity within Everett s wastewater facilities. Under the agreement the District shares in the capital cost of facilities based on the percentage of the facility capacity required to service the District s wastewater flow. These improvement contributions cease when the WPCF reaches a capacity of 40.4 mgd, maximum winter month flow. A summary of the District s purchased capacity in Everett s wastewater system covered in the agreement, including the share of construction costs incurred by the District, is presented in Table 5-5. The District s purchased capacities are for Peak Wet Weather Flow for conveyance and headworks; and Maximum Month Flow for the WPCF. Flow definitions are presented in Chapter 4. The agreement with Everett does not specify wastewater characterization requirements for the wastewater delivered by the District. Therefore, the District is not required to conduct any sampling for wastewater characterization parameters within its collection system. As part of the agreement with Everett, the District pays a wastewater disposal operation and maintenance charge. This charge is based on the number of connections within the District that ultimately discharge to the Everett system. A copy of the 1982 agreement, as well as the 1991 amendment, between the District and Everett is included in Appendix B. The purchased capacities in Everett facilities were based on the populations and land use zonings in the District s 1988 Sewerage System General Comprehensive Plan Update. 5-6 Silver Lake Water & Sewer District April 2011 Wastewater System Comprehensive Plan

10 24 TRUNK C LAKE STEVENS ³ 17TH ST. INTERCEPTOR (TRUNK D) TRUNK A SOUTHEND INTERCEPTOR SWPCF S WWTP POSSESSION SOUND MUKILTEO BEACH INTERCEPTOR 30 SOUTHWEST INTERCEPTOR MEMORIAL STADIUM INTERCEPTOR 24 SUMMIT AVE. INTERCEPTOR 36 2 CENTRAL INTERCEPTOR 5 30 SNOHOMISH RIVER SWWTP UV SILVER LAKE SOUTHEND INTERCEPTOR S WWTP S S WWTP - WASTEWATER TREATMENT PLANT WPCF - WATER POLUTION CONTROL FACILITY LEGEND: INTERCEPTORS WATER LAKE STEVENS SEWER DISTRICT MUKILTEO WATER & WASTEWATER DISTRICT SILVER LAKE WATER & SEWER DISTRICT S WWTP UV 525 CITY LIMITS OF EVERETT CITY LIMITS OF SNOHOMISH ALDERWOOD WATER AND WASTEWATER DISTRICT CROSS VALLEY WATER DISTRICT SILVER LAKE WATER & SEWER DISTRICT S WWTP UV 99 UV 9 UV 522 REGIONAL SEWERS FIGURE M:\SLWD\08564 WW COMP PLAN\Figures\FIGURE 5-4.mxd

11 ³ SR 99 35TH AVENUE SE 100TH STREET SE LO W EL L LA RI M ER RO AD SCALE 1 = 3,000' 8TH SR TH STREET SE LL HI AD SR 9 132ND STREET SE E TL T A SE RO LEGEND H IL L R O AD I-5 slwd-bndry-2011.dwg Polyline STUDY AREA AWWD AGREEMENT AREA CATHCART AGREEMENT AREA CVWD AGREEMENT AREA EVERETT AGREEMENT AREA EVERETT & ALDERWOOD AGREEMENT AREAS SE AT T LE NOTE: EVERETT AGREEMENT AREA ALSO INCLUDES ALL AREAS WITHIN THE SILVER LAKE WATER & SEWER DISTRICT BOUNDARY AND CROSS VALLEY WATER DISTRICT AGREEMENT AREA. 35TH AVENUE SE 164TH STREET SE SILVER LAKE WATER & SEWER DISTRICT WASTEWATER COMPREHENSIVE PLAN FIGURE 5-5 SEWER AGREEMENT AREAS 180TH STREET SE M:\SLWD\08564 WW Comp Plan\GIS\FIGURES\FIGURE

12 TABLE 5-5 District Purchased Capacity in Everett Sewer Facilities District Purchased Capacity Total Facility Capacity District Portion of Cost (3) Everett Facility South End Interceptor (1) South End Extension 11,500 gpm 16,000 gpm 72% To Southwest Interceptor 11,500 gpm 32,000 gpm 36% Northern Segment 11,500 gpm 45,000 gpm 26% Everett Treatment Facilities Headworks (1) 11,500 gpm 80,000 gpm 14% WPCF (2) 6.6 mgd 40.4 mgd 16% (1) Capacity for Peak Hour Flow. (2) Capacity for Maximum Month Flow. (3) District portion of cost is the percentage of the total facility capacity purchased by the District. ALDERWOOD WATER AND WASTEWATER DISTRICT AGREEMENT In 1978, the District entered into an agreement with the AWWD. Subsequent agreements and amendments were superseded by an agreement signed in July of 2006 and updated in Connections in the southwest and southern portion of the District have been designated to discharge through the AWWD sewer system to the King County wastewater treatment facilities. The area covered in the agreement is shown in Figure 5-5. The agreement specifies that the District constructs and maintains sewer system facilities within the area in accordance with all King County regulations and conditions of the agreement between AWWD and the County. For the area designated in the agreement, the District pays AWWD a sewage disposal charge based upon the number of connections, and a sewer connection charge for any new developments. Individual connections are responsible to King County for their treatment impacts at the time service is provided. According to the agreement, the wastewater discharged by the District may be limited by the capacity of the AWWD system. The District is not allowed to surcharge any component of AWWD s wastewater collection facilities. As part of the agreement AWWD is to provide sufficient capacity in downstream facilities to handle the peak flow from the District area designated in the agreement and shown in Figure 5-5. A copy of the agreement between AWWD and the District is included in Appendix B. Provisions of the agreement allow for AWWD sewer flows to enter District facilities prior being discharged back to AWWD for transmission to KCDNR. These areas are shown in Figure 5-5, and include areas that drain to the District s 180 th Street Lift Station Silver Lake Water & Sewer District 5-7 Wastewater Comprehensive Plan April 2011

13 and the District s North Creek Sewer Interceptor, which is aligned in Main Street in Mill Creek. CROSS VALLEY WATER DISTRICT AGREEMENT In 1994 the District entered into an interlocal agreement with the Cross Valley Water District (CVWD) to provide sewer service to an undeveloped area along Lowell-Larimer Road. This agreement was subsequently updated in 2001, 2007, and again in The area covered in the agreement is shown in Figure 5-5. A copy of the agreement between CVWD and the District is included in Appendix B. This area is located outside of the District boundary. However, it is anticipated that the District will provide sewer service in this area for the foreseeable future. Although outside of the District boundary, future flows from this CVWD Agreement Area are projected through build-out. For the District to provide sewer service within the study area directly east of the existing agreement area, an amended agreement would need to be negotiated between the District and CVWD. SNOHOMISH COUNTY CATHCART LANDFILL AGREEMENT In 1989, the District entered into an agreement with Snohomish County and the City of Everett for the disposal of leachate from the 587-acre Cathcart Landfill site. The Cathcart Landfill (now closed) is located in the southeast portion of the study area and pumps wastewater to a manhole which drains to the District s Lift Station No. 3. This agreement was amended in April The landfill location is shown on Figure 5-5. Leachate from the landfill undergoes a pre-treatment process in a lagoon prior to discharging to the District s sewer system. The agreement allows a maximum of 100 gallons per minute (144,000 gallons per day) to be pumped into the District, with a maximum off-peak rate of 400 gpm allowed. The volume of leachate pumped from Cathcart is monitored by Snohomish County, and shall at no time exceed 144,000 gallons per day. A copy of the agreement between the District, Snohomish County and the City of Everett is also included in Appendix B. Snohomish County has surplussed much of the approximately 330 acres of the area adjacent to the Carthcart Landfill for schools, parks, and future private development. The area in question is within the District s current service area boundary. If residential housing is constructed consistent with the densities allowed in that region of Snohomish County, the impact could be as many as 803 additional dwelling units, plus commercial development. The Plan will address the impacts of the land use changes for the undeveloped portion of Snohomish County land adjacent to the Cathcart Landfill. As part of the agreement with Snohomish County, wastewater from the landfill must meet the wastewater characterization requirements as specified in the Industrial Waste 5-8 Silver Lake Water & Sewer District April 2011 Wastewater System Comprehensive Plan

14 Discharge Permit (IWDP) for the Cathcart Landfill. Snohomish County monitors the parameters of BOD, TSS, ph, oils and grease, total organic carbon, and total metals. The Maximum Contaminant Levels (MCLs) are specified in the IWDP. A copy of the IWDP for the Cathcart Landfill is included in Appendix E. Silver Lake Water & Sewer District 5-9 Wastewater Comprehensive Plan April 2011

CHAPTER 4 SYSTEM DESIGN CRITERIA

CHAPTER 4 SYSTEM DESIGN CRITERIA INTRODUCTION CHAPTER 4 SYSTEM DESIGN CRITERIA Adequate design of the District s wastewater conveyance facilities requires the determination of the quantity of wastewater from contributing sources. The

More information

CHAPTER 8 CAPITAL IMPROVEMENT PLAN

CHAPTER 8 CAPITAL IMPROVEMENT PLAN INTRODUCTION CHAPTER 8 CAPITAL IMPROVEMENT PLAN This chapter presents a 10-year Capital Improvement Plan (CIP). Wastewater capital improvements have been scheduled and prioritized on the basis of growth,

More information

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL INTRODUCTION The District developed a hydraulic model of the sanitary sewer system as part the 2000 Wastewater Comprehensive Plan. The output from this model

More information

Chapter 5 Existing Wastewater Facilities

Chapter 5 Existing Wastewater Facilities Chapter 5 Existing Wastewater Facilities \\7348101\TOC.doc CHAPTER 5 Existing Wastewater Facilities 5.1 INTRODUCTION Lacey s wastewater utility serves over 21,000 acres (33 square miles) of residential

More information

CHAPTER 8 CAPITAL IMPROVEMENT PLAN

CHAPTER 8 CAPITAL IMPROVEMENT PLAN INTRODUCTION CHAPTER 8 CAPITAL IMPROVEMENT PLAN This chapter presents 6-, 10-, and 20-year Capital Improvement Plans (CIPs) in accordance with the requirements of WAC 26-290. Water system capital improvements

More information

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan 4 Capacity Analysis The capacity analysis used the calibrated dry weather and wet weather wastewater collection system model to evaluate

More information

PRELIMINARY WASTEWATER CAPACITY STUDY

PRELIMINARY WASTEWATER CAPACITY STUDY PRELIMINARY WASTEWATER CAPACITY STUDY Tentative Tract Map No. 18955 CITY OF HESPERIA Prepared for: HESPERIA VENTURES I, LLC 10410 Roberts Road Calimesa, CA 92320 Tel (714) 785 2381 Mr. John Ohanian Prepared

More information

4 EXISTING FACILITIES EVALUATION

4 EXISTING FACILITIES EVALUATION 4 EXISTING FACILITIES EVALUATION The City is served by a combination of wastewater collection, conveyance, and treatment systems. The City owns and operates the collection system that collects wastewater

More information

2010 Utility Plan Amendment Boxelder Sanitation District

2010 Utility Plan Amendment Boxelder Sanitation District 2010 Utility Plan Amendment Boxelder Sanitation District For inclusion of the Harmony Ridge Development November 7, 2014 1612 Specht Point Rd. Ste. 105 Fort Collins, Colorado 80525-9770 p 970.484.7477

More information

Chapter 7: Sanitary Sewer Plan. Introduction. Metropolitan Council Coordination

Chapter 7: Sanitary Sewer Plan. Introduction. Metropolitan Council Coordination Chapter 7: Sanitary Sewer Plan Introduction The 2030 Sanitary Sewer Plan was prepared for two primary reasons. The first purpose is to provide recommendations and guidance to the City of Lino Lakes by

More information

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY EXECUTIVE SUMMARY EXECUTIVE SUMMARY INTRODUCTION AND BACKGROUND The Village of Algonquin, located along the Fox River in McHenry County, provides wastewater collection and treatment services to the entire

More information

Executive Summary. Introduction

Executive Summary. Introduction Executive Summary Introduction The City of Terre Haute has developed a (CSO LTCP), which describes the measures they will take to reduce the combined sewer overflows and improve water quality in the Wabash

More information

CHAPTER 8: SANITARY SEWER

CHAPTER 8: SANITARY SEWER CHAPTER 8: SANITARY SEWER 8.1 EXECUTIVE SUMMARY The Metropolitan Land Planning Act (amended 1995) requires local governments to prepare comprehensive plans and submit them to the Metropolitan Council (MCES)

More information

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS 2.1. General Requirements Sanitary sewers are to be provided solely for the removal of sanitary waste. Under no circumstances shall any roof drains,

More information

TABLE OF CONTENTS. INTRODUCTION... 1 BACKGROUND... 2 EXISTING SANITARY SEWER SYSTEM... 2 Public Collection Systems... 2

TABLE OF CONTENTS. INTRODUCTION... 1 BACKGROUND... 2 EXISTING SANITARY SEWER SYSTEM... 2 Public Collection Systems... 2 TABLE OF CONTENTS INTRODUCTION... 1 BACKGROUND... 2 EXISTING SANITARY SEWER SYSTEM... 2 Public Collection Systems... 2 Individual Sewage Treatment Systems... 5 Private Treatment Plant... 7 FORECASTS...

More information

Page Intentionally Left Blank

Page Intentionally Left Blank Page Intentionally Left Blank Julie Avenue and Hoeschler Drive Lift Stations Evaluation City of Sparta TABLE OF CONTENTS Page CHAPTER 1 GENERAL INFORMATION... 1 1.1 Scope of Lift Station Evaluation...

More information

CHAPTER 7 CAPITAL IMPROVEMENT PLAN

CHAPTER 7 CAPITAL IMPROVEMENT PLAN 7.1 INTRODUCTION CHAPTER 7 CAPITAL IMPROVEMENT PLAN This Chapter presents the District s Capital Improvement Plan (CIP) in accordance with the requirements of WAC 173-240. Wastewater capital improvements

More information

CHAPTER VI EXISTING AND FUTURE POPULATION PROJECTIONS

CHAPTER VI EXISTING AND FUTURE POPULATION PROJECTIONS COMPREHENSIVE SEWER PLAN CHAPTER VI EXISTING AND FUTURE POPULATION PROJECTIONS 6.1 POPULATION 6.1.1 General Current and future population projections for areas that include the Alderwood Service Area have

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

CHAPTER 4 DESIGN CRITERIA

CHAPTER 4 DESIGN CRITERIA CHAPTER 4 DESIGN CRITERIA 4.1 INTRODUCTION This chapter summarizes the basic design criteria necessary to develop options and sizing estimates for the components of centralized wastewater collection systems.

More information

STEERING COMMITTEE MEETING #6

STEERING COMMITTEE MEETING #6 STEERING COMMITTEE MEETING #6 August 7 th, 2017 Topic: Infrastructure (Sewer & Water, Transportation follow up) 6:00 p.m. Transportation follow up Follow up issues map Transportation plan strategies table

More information

Wastewater Collection. (Sewer Alternatives)

Wastewater Collection. (Sewer Alternatives) Wastewater Collection (Sewer Alternatives) Sewer Basics Collection and transport of wastewater from each home/building to the point where treatment occurs. Wastewater Characterization Solids Liquids Pipe

More information

Chapter 8-Sanitary Sewer

Chapter 8-Sanitary Sewer Chapter -Sanitary Sewer Executive Summary Background The Metropolitan Land Planning Act (amended 1995) requires local governments to prepare comprehensive plans and submit them to the Metropolitan Council

More information

Technical Memorandum No. 1

Technical Memorandum No. 1 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Serving the Public Protecting the Environment Technical Memorandum No. 1 Multi-Jurisdictional Use Facilities Capital Cost Allocation DRAFT April 17, 2013

More information

4. CONVEYANCE SYSTEM

4. CONVEYANCE SYSTEM 4. CONVEYANCE SYSTEM 4.1. Background... 1 4.2. Existing Conveyance System... 1 4.3. Current Conveyance Deficiencies for Centralized Treatment... 4 4.4. Existing Facility Condition Assessment... 5 CONVEYANCE

More information

CITY OF MANTECA 2012 WASTEWATER COLLECTION SYSTEM MASTER PLAN UPDATE

CITY OF MANTECA 2012 WASTEWATER COLLECTION SYSTEM MASTER PLAN UPDATE CITY OF MANTECA 2012 WASTEWATER COLLECTION SYSTEM MASTER PLAN UPDATE Executive Summary The City of Manteca (City) desires to update the 2006 Wastewater Collection System Master Plan (2006 Master Plan)

More information

Connection to the Lower Northwest Interceptor

Connection to the Lower Northwest Interceptor TABLE OF CONTENTS City of West Sacramento - Wastewater Master Plan and Connection to the Lower Northwest Interceptor 1. INTRODUCTION...1-1 1.1 Background...1-1 1.2 General Description of the Study Area...1-2

More information

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Sanitation District No. 1 of Northern Kentucky Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Ohio WEA Collection Systems Workshop May 5, 2011 Sanitation District No. 1

More information

Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility

Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility Michael Sanders, P.E., Kleinfelder Collection Systems Specialty Conference NEWEA September 12, 2016 Presentation

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

b) Ensure provision of sufficient potable water to meet anticipated University needs and to reuse water for irrigation purposes.

b) Ensure provision of sufficient potable water to meet anticipated University needs and to reuse water for irrigation purposes. 9.0 GENERAL INFRASTRUCTURE ELEMENT The purpose of this element is to ensure adequate provision of public facilities and services required to meet the future needs of the University, including the following:

More information

Chapter 6 Collection System

Chapter 6 Collection System Chapter 6 Collection System 6.1 Introduction Collection System The following chapter details the evaluation process and findings for the City s existing sewer collection system. Generally the existing

More information

3.9 times the average 3.8 times the average 3.6 times the average

3.9 times the average 3.8 times the average 3.6 times the average ARTICLE VI DESIGN OF SANITARY SEWERS M'RSMIN. VOL.281 JA 2 4 2001 IMAGE; Section 601 Determination of the Amount of Sewage for Sanitary Sewers A. MSD Design Standards for estimating sanitary sewage flow

More information

TOWN OF LONDONDERRY, NEW HAMPSHIRE WASTEWATER FACILITIES PLAN UPDATE TABLE OF CONTENTS

TOWN OF LONDONDERRY, NEW HAMPSHIRE WASTEWATER FACILITIES PLAN UPDATE TABLE OF CONTENTS 6%34(6%4(2 )%&+-+4+(3 1-%/ 51 %4( :=>?;9 406/ 0) -0/ 0/ (227! /(6 *%.13*+2(,8A #""$ TOWN OF LONDONDERRY, NEW HAMPSHIRE WASTEWATER FACILITIES PLAN UPDATE TABLE OF CONTENTS SECTION DESCRIPTION PAGE ES

More information

MUNICIPAL WASTEWATER PUMP STATION DESIGN PROBLEMS AND SOLUTIONS Jeff Chapin, P.E. Dewberry 8401 Arlington Boulevard Fairfax, VA 22032

MUNICIPAL WASTEWATER PUMP STATION DESIGN PROBLEMS AND SOLUTIONS Jeff Chapin, P.E. Dewberry 8401 Arlington Boulevard Fairfax, VA 22032 MUNICIPAL WASTEWATER PUMP STATION DESIGN PROBLEMS AND SOLUTIONS Jeff Chapin, P.E. Dewberry 8401 Arlington Boulevard Fairfax, VA 22032 ABSTRACT The growth of the Northern Virginia Area around Washington

More information

ODUCTION ANITARY SEWER

ODUCTION ANITARY SEWER INTRODUCTION SANITARY SEWER Why Plan? 10 A Plan for the Community of Hastings 10 Metropolitan Council Oversight 11 Plan Organization 12 Previous Visioning and Planning 14 2040 Engagement Topics & Consensus

More information

CENTRAL KITSAP COUNTY WASTEWATER FACILITY PLAN ADDENDUM

CENTRAL KITSAP COUNTY WASTEWATER FACILITY PLAN ADDENDUM CENTRAL KITSAP COUNTY WASTEWATER FACILITY PLAN ADDENDUM Prepared for Kitsap County Department of Public works May 2013 Prepared by: TABLE OF CONTENTS CHAPTER 1: INTRODUCTION 1.1 Purpose of Addendum...

More information

Leachate Management Plan

Leachate Management Plan Leachate Management Plan LEACHATE MANAGEMENT PLAN Chesapeake Energy Center Ash Landfill Permit #440 Submitted To: Dominion Chesapeake Energy Center 2701 Vepco Street Chesapeake, Virginia 23323 Submitted

More information

Section 5 - Inflow and Infiltration Analysis

Section 5 - Inflow and Infiltration Analysis Section 5 - Inflow and Infiltration Analysis 5.1 Introduction The section presents a comprehensive review of the historical flow metering data collected for the sewer collection system in the Towns of

More information

2. System Description

2. System Description 2. System Description This chapter provides a general overview of the water system, including information on the District s management, water service area, history, wholesale customers and adjacent purveyors.

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES

CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES Santa Clarita Valley Joint Sewerage System SCVJSS Conveyance System Solids Processing and Biosolids Management CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES

More information

Appendix J Effluent Pump Station

Appendix J Effluent Pump Station Appendix J Effluent Pump Station TECHNICAL MEMORANDUM Salmon Creek Treatment Plant Effluent Pump Station Hydraulics and Phasing Analysis for the Phase 5A Project Columbia River Outfall and Effluent Pipeline

More information

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Community Services Department (CSD) standards for: INDEX Designing Gravity Sewer Collection Facilities ( Sewer Design

More information

DRAFT DRAFT 04/18/ COMPREHENSIVE PLAN MINNETRISTA COMPREHENSIVE SANITARY SEWER PLAN HENNEPIN COUNTY MINNETRISTA MINNESOTA APRIL 17, 2017

DRAFT DRAFT 04/18/ COMPREHENSIVE PLAN MINNETRISTA COMPREHENSIVE SANITARY SEWER PLAN HENNEPIN COUNTY MINNETRISTA MINNESOTA APRIL 17, 2017 DRAFT 2040 COMPREHENSIVE PLAN MINNETRISTA COMPREHENSIVE SANITARY SEWER PLAN HENNEPIN COUNTY MINNETRISTA MINNESOTA APRIL 17, 2017 Prepared for: City of Minnetrista 7701 County Road 110W Minnetrista, MN

More information

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Department of Water Resource s (DWR) standards for: Designing Gravity Sewer Collection Facilities ( Sewer Design Standards

More information

Sanitary Sewer 101. Jan. 12, 2016 Keith Fisher, P.E. Director of Public Works

Sanitary Sewer 101. Jan. 12, 2016 Keith Fisher, P.E. Director of Public Works Sanitary Sewer 101 Jan. 12, 2016 Keith Fisher, P.E. Director of Public Works What We Will Cover -What is Sanitary Sewer? -Components -History -What types of systems are there? -What types of materials

More information

Wastewater Master Facility Report. (Project Name) (Project Basin Location)

Wastewater Master Facility Report. (Project Name) (Project Basin Location) Wastewater Master Facility Report For (Project Name) (Project Basin Location) The Wastewater Master Facility Report for (Project name) dated (Date); located in the (Basin Name) Basin has been completed

More information

EX. 24" G RAV ITY PRO P. GRAVITY S FISHER PARK PUM P STAT IO N EX. PUMP STATION TO BE REMO VED PRO P. F.M. PRO P. S.W. M AST ER PUM P STAT IO N RHODES

EX. 24 G RAV ITY PRO P. GRAVITY S FISHER PARK PUM P STAT IO N EX. PUMP STATION TO BE REMO VED PRO P. F.M. PRO P. S.W. M AST ER PUM P STAT IO N RHODES EX. 24" G RAV ITY PRO P. GRAVITY S FISHER PARK PUM P STAT IO N EX. PUMP STATION TO BE REMO VED PRO P. F.M. PRO P. S.W. M AST ER PUM P STAT IO N RHODES CREEK PRO P. GRAVITY THOM PSO N DRIVE PUM P STAT IO

More information

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System INSTRUCTIONS: This form shall be completed and submitted (in duplicate)

More information

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Attachment 1 Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Sanitary Sewer System Master Plan Summary Points - City s sanitary system

More information

CHAPTER 9: SANITARY SEWER INTRODUCTION FORECASTS CHAPTER 9: SANITARY SEWER 9-1

CHAPTER 9: SANITARY SEWER INTRODUCTION FORECASTS CHAPTER 9: SANITARY SEWER 9-1 CHAPTER 9: SANITARY SEWER INTRODUCTION The Metropolitan Land Planning Act (amended 1995) requires local governments to prepare comprehensive plans and submit them to the Metropolitan Council to determine

More information

WASTEWATER REGIONALIZATION PLAN FOR NORTHERN TOOELE VALLEY

WASTEWATER REGIONALIZATION PLAN FOR NORTHERN TOOELE VALLEY WASTEWATER REGIONALIZATION PLAN FOR NORTHERN TOOELE VALLEY HAL Project No.: 283.02.100 Final report March 2017 TABLE OF CONTENTS TABLE OF CONTENTS... i CHAPTER 1 - INTRODUCTION... 1-1 BACKGROUND... 1-1

More information

Section 7 Design Criteria Irrigation and Drainage Facilities

Section 7 Design Criteria Irrigation and Drainage Facilities Section 7 Design Criteria Irrigation and Drainage Facilities 7.1 Background The Irrigation and Drainage system is comprised of the Coachella Branch of the All-American Canal (Coachella Canal), Protective

More information

Water and Wastewater Impact Fee Analysis Capital Improvement Plan City of Lockhart February 2017

Water and Wastewater Impact Fee Analysis Capital Improvement Plan City of Lockhart February 2017 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 ANALYSIS OF WATER & WASTEWATER SYSTEMS... 1 2.1 Present Water Demands... 1 2.2 Water Supply... 3 2.3 Water Treatment Plant... 4 2.4 Storage, High-Service Pumps,

More information

Chapter 8: Water Supply & Sanitary Systems

Chapter 8: Water Supply & Sanitary Systems Chapter 8: Water Supply & Sanitary Systems Manage, Treat & Reserve Comprehensive Plan 2040 2 8. WATER SUPPLY & SANITARY SYSTEM INTRODUCTION This chapter of the City of Lauderdale s 2040 Comprehensive Plan

More information

Background Where did CSO systems begin? Combined Sewer Overflow (CSO) Control. Background. Background. Background

Background Where did CSO systems begin? Combined Sewer Overflow (CSO) Control. Background. Background. Background Background Where did CSO systems begin? Combined Overflow (CSO) Control Eric Bergstrom HDR Engineering Background System Development Before About 196 House Background System Development After 196 Building

More information

Final - Preliminary Design Report Interstate 10 and Indian Avenue Area Sewer System. Prepared for

Final - Preliminary Design Report Interstate 10 and Indian Avenue Area Sewer System. Prepared for Final - reliminary Design Report Interstate 10 and Indian Avenue Area Sewer System repared for Mission Springs Water District July 2012 Mission Springs Water District I-10 & Indian Area Sewer System DR

More information

Decentralized Wastewater Systems

Decentralized Wastewater Systems Decentralized Wastewater Systems Decentralized and Traditional Wastewater Treatment Systems Mark Gross, Ph.D., P.E. Training Manager Orenco Systems, Inc. Decentralized Overview 3/3/2010 #1 Some Aspects

More information

Chapter 9 Sanitary Sewers

Chapter 9 Sanitary Sewers Chapter 9 Sanitary Sewers I:\AD\030\U30\U30009.docx 4-8-16 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow 9-1 9.4 Facility Design

More information

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility: Oklahoma Department of Environmental Quality Water Quality Division Phone: 405-702-8100 Construction Permitting Section 707 N. Robinson, OKC, OK 73102-6010 P.O. Box 1677, OKC, OK 73101-1677 Sanitary Sewer

More information

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM I. General Information A. Agency Name B. Agency Address

More information

VISTA TECHNOLOGY CAMPUS

VISTA TECHNOLOGY CAMPUS ENGINEER S REPORT PUBLIC SEWER EXTENSION TO SERVE THE PROPOSED VISTA TECHNOLOGY CAMPUS TOWN OF BETHLEHEM & TOWN OF NEW SCOTLAND ALBANY COUNTY, NEW YORK August 22, 2007 Revised December 31, 2007 Revised

More information

SUPPLEMENTAL MECHANICAL CORRECTION SHEET FOR SEWAGE EJECTORS AND SUMP PUMPS 2011 LAPC

SUPPLEMENTAL MECHANICAL CORRECTION SHEET FOR SEWAGE EJECTORS AND SUMP PUMPS 2011 LAPC SUPPLEMENTAL MECHANICAL CORRECTION SHEET FOR SEWAGE EJECTORS AND SUMP PUMPS 2011 LAPC This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the

More information

Appendix B Addendum 1 - Revisions to the Operation and Training Plan (dated November 2015) for the Indian River County Class I Landfill

Appendix B Addendum 1 - Revisions to the Operation and Training Plan (dated November 2015) for the Indian River County Class I Landfill Appendix B Addendum 1 - Revisions to the Operation and Training Plan (dated November 2015) for the Indian River County Class I Landfill The IRC Landfill 20-year Construction/Operation Permit Nos. 0128769-022-SC

More information

CHAPTER SEVEN: UTILITIES

CHAPTER SEVEN: UTILITIES CHAPTER SEVEN: UTILITIES 7.1 Introduction The Water Works Board of the City of Auburn (AWWB) is the primary potable water service provider for the City of Auburn (City) and Auburn University. There are

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

West Bountiful City. Water System Capital Facilities Plan

West Bountiful City. Water System Capital Facilities Plan Water System Capital Facilities Plan August 2008 TABLE OF CONTENTS 1.0 Executive Summary... 1 2.0 Definition of Terms and Abbreviations... 2 3.0 Introduction... 3 3.1 Background...3 3.2 Scope of Investigation...3

More information

Capital Improvement Plan Update:

Capital Improvement Plan Update: Board of Supervisors Meeting Carson City Public Works Department Capital Improvement Plan Update: Wastewater Collection, Treatment and Reuse March 14, 2013 Topics of Discussion Regionalization Existing

More information

KINGSTON WASTEWATER FACILITIES PLAN UPDATE ADDENDUM

KINGSTON WASTEWATER FACILITIES PLAN UPDATE ADDENDUM KINGSTON WASTEWATER FACILITIES PLAN UPDATE ADDENDUM May 2013 Prepared for Kitsap County Department of Public Works Prepared By: KITSAP COUNTY KINGSTON WASTEWATER FACILITY PLAN UPDATE ADDENDUM TABLE OF

More information

Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES

Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES A. GENERAL 1. The following water system design guidelines are based on Federal, State and local health requirements and the Hilton Head No. 1 Public

More information

WASTEWATER INTRODUCTION ENVIRONMENTAL SETTING

WASTEWATER INTRODUCTION ENVIRONMENTAL SETTING 3.14.4 WASTEWATER INTRODUCTION This section of the Draft EIR describes the wastewater disposal conditions in the area surrounding the project site. The analysis focuses on potential impacts to wastewater

More information

Design Criteria for Greenland WRF Pipelines: Water, Reclaimed Water and Sanitary Sewer Force mains Jacksonville, FL

Design Criteria for Greenland WRF Pipelines: Water, Reclaimed Water and Sanitary Sewer Force mains Jacksonville, FL Design Criteria for Greenland WRF Pipelines: Water, Reclaimed Water and Sanitary Sewer Force mains Jacksonville, FL PREPARED FOR: JEA PREPARED BY: FOUR WATERS ENGINEERING, INC. DATE: FRIDAY, DECEMBER 21,

More information

City of Hudson. Wastewater Treatment Plant Improvements. Columbia County, New York. Facility Plan. Delaware Engineering, P.C.

City of Hudson. Wastewater Treatment Plant Improvements. Columbia County, New York. Facility Plan. Delaware Engineering, P.C. City of Hudson Columbia County, New York Wastewater Treatment Plant Improvements Facility Plan Prepared By: Delaware Engineering, P.C. 28 Madison Avenue Extension Albany, New York 12203 (Phone) 518-452-1290

More information

CITY OF TOPPENISH General Sewer Plan DRAFT FOR AGENCY REVIEW

CITY OF TOPPENISH General Sewer Plan DRAFT FOR AGENCY REVIEW CITY OF TOPPENISH General Sewer Plan DRAFT FOR AGENCY REVIEW G&O #15039 JUNE 2017 CITY OF TOPPENISH YAKIMA COUNTY WASHINGTON GENERAL SEWER PLAN G&O#l5039 JUNE 2017 Gray & Oshor.n.e~ l.n.c. CONSUL TING

More information

City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012

City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 Project made possible by US Dept. of HUD Regional Substantiality Planning Grant and ND Energy Development Infrastructure and

More information

ALDERWOOD WATER & WASTEWATER DISTRICT LYNNWOOD, WASHINGTON WATER QUALITY COLIFORM AND D/DBP MONITORING PLAN

ALDERWOOD WATER & WASTEWATER DISTRICT LYNNWOOD, WASHINGTON WATER QUALITY COLIFORM AND D/DBP MONITORING PLAN ALDERWOOD WATER & WASTEWATER DISTRICT LYNNWOOD, WASHINGTON WATER QUALITY COLIFORM AND D/DBP MONITORING PLAN Prepared: March 2002 Updated: July 2009 ALDERWOOD WATER & WASTEWATER DISTRICT WATER QUALITY MONITORING

More information

Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview

Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview August 11, 2014 Let s Look at the Numbers Water System 2 - Raw Water Sources Clinton Reservoir Kansas River 2 - Water Treatment

More information

Technical Memorandum - Final

Technical Memorandum - Final Technical Memorandum Final Water andenvironment Subject: Tuscany Meadows Offsite Sewerage Impacts Evaluation Prepared For: Patricia Chapman, DDSD Prepared by: Chris van Lienden, RMC Reviewed by: Gisa Ju,

More information

South thdearborn Regional lsewer District

South thdearborn Regional lsewer District Travis Miller, OKI South thdearborn Regional lsewer District i t Original wastewater treatment plant built in the late 1970 s with major expansion in 1997 98. 98 The Lawrenceburg Distillery (LDI) uses

More information

3.1 Wastewater Treatment Plants The City of Victoria has two (2) wastewater treatment plants: Victoria Regional WWTP and Odem Street WWTP.

3.1 Wastewater Treatment Plants The City of Victoria has two (2) wastewater treatment plants: Victoria Regional WWTP and Odem Street WWTP. 1. INTRODUCTION AND SCOPE This study is an update to the City of Victoria's Master Wastewater Plan prepared in 2009 by Urban Engineering and Water and Wastewater Treatment Plant Capacity Assessment prepared

More information

AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE

AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE PLAN SUMMARY AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE The Pennsylvania Sewage Facilities Act (Act 537) was enacted by the Pennsylvania

More information

Medford Comprehensive Plan Chapter 8 Public Facilities

Medford Comprehensive Plan Chapter 8 Public Facilities Medford Comprehensive Plan Chapter 8 Public Facilities Amd Pub. Fac. Element, Ord. No. 2003-134, April 17, 2003; Amd Parks, Recreation and Leisure Services Section, Ord. No. 2010-240, November 4, 2010;

More information

City of Palmdale Sewer Master Plan Final Report

City of Palmdale Sewer Master Plan Final Report City of Palmdale Sewer Master Plan Final Report Prepared by: Water andenvironment In Association with: Larson Consulting September, 2009 City of Palmdale Sewer Master Plan FINAL Table of Contents ES-1

More information

Here is a description of the City of Delphos collection system in its entirety and provide

Here is a description of the City of Delphos collection system in its entirety and provide CITY OF DELPHOS 24793 Pohlman Rd DELPHOS OH 45833 419-692-0991 PHONE Annual Report The City of Delphos is required to provide an Annual Report to the public in accordance with Ohio Environmental Protection

More information

MEMORANDUM. The general findings of the assessment are as follows:

MEMORANDUM. The general findings of the assessment are as follows: November 28, 2006 MEMORANDUM Project No.: 030009-002-01 To: From: Re: WRIA 31 Planning Unit Steve Germiat, LHG, CGWP, and Timothy J. Flynn, LHG, CWGP Evaluation of Winterizing Existing River Pump/Conveyance

More information

Consent Decree Appendix 1. Control Measures and Performance Criteria

Consent Decree Appendix 1. Control Measures and Performance Criteria Case: 1:10-cv-02895-DCN Doc #: 2-2 Filed: 12/22/10 1 of 6. PageID #: 82 United States and State of Ohio v. Northeast Ohio Regional Sewer District Consent Decree Appendix 1 Control Measures and Performance

More information

Request for Proposals for Professional Engineering Services for the Front Street Pump Station Upgrade

Request for Proposals for Professional Engineering Services for the Front Street Pump Station Upgrade Request for Proposals for Professional Engineering Services for the Front Street Pump Station Upgrade May 11, 2015 Capital Region Water Administrative Offices 212 Locust Street, Suite 302 Harrisburg, PA

More information

PLANNING FOR THE FUTURE: A REGIONAL MASTER PLAN APPROACH WITH THE OPPORTUNITY TO MINIMIZE FUTURE OPERATION AND MAINTENANCE CONCERNS

PLANNING FOR THE FUTURE: A REGIONAL MASTER PLAN APPROACH WITH THE OPPORTUNITY TO MINIMIZE FUTURE OPERATION AND MAINTENANCE CONCERNS PLANNING FOR THE FUTURE: A REGIONAL MASTER PLAN APPROACH WITH THE OPPORTUNITY TO MINIMIZE FUTURE OPERATION AND MAINTENANCE CONCERNS ABSTRACT Robert Skip Notte*, PE, LEED AP, Dewberry, snotte@dewberry.com

More information

NTMWD REGIONAL WASTEWATER SYSTEM

NTMWD REGIONAL WASTEWATER SYSTEM Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow NTMWD REGIONAL WASTEWATER SYSTEM Tour of South Mesquite Regional Wastewater Treatment Plant November 28, 2017 REGIONAL WASTEWATER

More information

Sewer Facilities 102. Hampstead Sewer Service Area. Carroll County Water & Sewer Master Plan. Current Conditions

Sewer Facilities 102. Hampstead Sewer Service Area. Carroll County Water & Sewer Master Plan. Current Conditions Sewer Facilities 102 Hampstead Sewer Service Area Current Conditions Carroll County owns and operates the public sewer system that serves both the Town of Hampstead and adjoining areas in the county. The

More information

ILLINOIS ENVIRONMENTAL PROTECTION AGENCY

ILLINOIS ENVIRONMENTAL PROTECTION AGENCY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY 1021 NORTH GRAND AVENUE EAST, P.O. Box 19276, SPRINGFIELD, ILLh~OIS 62794-9276 (217) 782-3397 BRUCE RAUNER, GOVERNOR LISA BONNETT, DIRECTOR Project Summary and

More information

CEE 371 May 14, 2009 Final Exam

CEE 371 May 14, 2009 Final Exam CEE 371 May 14, 2009 Final Exam Closed Book, two sheets of notes allowed Please answer questions 3, 6 and 7. In addition, answer either question 1 or 2, and answer either question 4 or 5. The total potential

More information

AUGUST 30, 2016 DRAFT WATER SYSTEM PLAN TEXT AND TABLES BYWATER BAY WATER SYSTEM WITH SHINE PLAT

AUGUST 30, 2016 DRAFT WATER SYSTEM PLAN TEXT AND TABLES BYWATER BAY WATER SYSTEM WITH SHINE PLAT AUGUST 30, 2016 DRAFT WATER SYSTEM PLAN TEXT AND TABLES BYWATER BAY WATER SYSTEM WITH SHINE PLAT 1. SYSTEM OVERVIEW The Bywater Bay Water System (DOH Water System ID number 02043P) is located in eastern

More information

AUGUST 30, 2016 DRAFT WATER SYSTEM PLAN TEXT AND TABLES BYWATER BAY WATER SYSTEM WITHOUT SHINE PLAT

AUGUST 30, 2016 DRAFT WATER SYSTEM PLAN TEXT AND TABLES BYWATER BAY WATER SYSTEM WITHOUT SHINE PLAT AUGUST 30, 2016 DRAFT WATER SYSTEM PLAN TEXT AND TABLES BYWATER BAY WATER SYSTEM WITHOUT SHINE PLAT 1. SYSTEM OVERVIEW The Bywater Bay Water System (DOH Water System ID number 02043P) is located in eastern

More information

Joshua H. Reynolds, P.E.

Joshua H. Reynolds, P.E. Joshua H. Reynolds, P.E. Education B.S., Civil Engineering, California Polytechnic University, San Luis Obispo, CA Professional Registrations Professional Engineer - Civil, California, No. C65400 Professional

More information

BOROUGH OF ALBURTIS SEWER DEPARTMENT

BOROUGH OF ALBURTIS SEWER DEPARTMENT BOROUGH OF ALBURTIS SEWER DEPARTMENT Capacity, Management, Operations, and Maintenance Program for Sewers Borough of Alburtis Lehigh Co., Pennsylvania February 2018 Prepared for: BOROUGH OF ALBURTIS 260

More information

Introduction. Purpose

Introduction. Purpose Introduction This Master Plan update includes updating the text of the Utilities Section of the current Master Plan and adding a report concerning telecommunications. Each element examines the existing

More information

2015 BASELINE ASSESSMENT A REPORT CARD FOR ROADS, WATER, SEWER, AND STORMWATER APPENDIX

2015 BASELINE ASSESSMENT A REPORT CARD FOR ROADS, WATER, SEWER, AND STORMWATER APPENDIX 2015 BASELINE ASSESSMENT A REPORT CARD FOR ROADS, WATER, SEWER, AND STORMWATER APPENDIX FEBRUARY, 2015 GRADING SCALE Classification Description Value A Exceptional: Fit for the future The infrastructure

More information

Has a median household income that is 80 percent or less than the statewide median household income.

Has a median household income that is 80 percent or less than the statewide median household income. C. Disadvantaged Unincorporated Communities Assessment 1. Context SB 244 (Wolk, 2011) requires cities and counties to address the infrastructure and service needs of unincorporated disadvantaged communities

More information