Pembina Nisku Oil Project. Three Well Exploration Program

Size: px
Start display at page:

Download "Pembina Nisku Oil Project. Three Well Exploration Program"

Transcription

1 Pembina Nisku Oil Project Three Well Exploration Program

2 Communication Public Notifications For Each Well: To: A. i. Seasonal residents, owner of vacant residences and residences under construction, vacant shop/residence and vacant serviced lot inside the Emergency Planning Zone (EPZ) ii. Industrial Operators, Grazing Lease/allotment user, and the cultivation permit user B. Permanent residents and owners of businesses inside the EPZ Notice of Commencement of: Sour Drilling Operations Sour Completions and Testing including a Flaring Notice Sour Workover/Servicing A. One week prior to entering the FIRST sour formation (by mail) One week prior to entering the NISKU formation (by mail) B. Within 96 hours (4 days) prior to entering the FIRST sour formation (by hand) Within 96 hours (4 days) prior to entering the Nisku formation (by hand) Public Communication: At the commencement of Sour Operations, the Acting Public Protection Branch Director will be available daily from 4:30 to 5:30pm at the junction of Range Road 72 and Township Road 500 to provide information about Shelter-In-Place, evacuation, ignition and /or the well.

3 Drilling Safety is our Priority Use of best equipment and qualified personnel. In Accordance with AER Directives & Industry Recommended Practices (IRPs). Critical Drilling of 4 Days per well AER Approved drilling program AER Conducted rig inspections Prior to Drilling out the Intermediate Casing On-site safety equipment plus mobile air monitoring

4 Completion Safety First Well Control Equipment in place at all times In Accordance with AER Directives & IRPs Critical Completion of 4 Days per well Safety equipment on-site plus mobile air monitoring

5 Planned Testing: Planned Testing and Flaring Will follow AER D60 for Flaring and IRP Vol #4 for Testing and Handling of Fluids Flow Test of 72 Hours (3 Days) per well followed by 9 days of shut-in. Using a 30.5 meter (100 ft) Flare Stack Limited to 100x10³m³ (3.5 Mmscf) of Total Gas Volume per well Flaring Notification Radius of 3.0 kms Any exceedances of the AAAQO will result in cessation of testing and flaring operations until dispersion conditions improve.

6 Development Plan Development plan will depend on reservoir and fluid characteristics. Sinopec Crossfire Battery is closest but complex. Pipeline and on-site facility will require separate licencing process and approval.

7 Flare Dispersion Modelling, Pembina Sour Oil Project, Bashaw Oil Corp. David Chadder Senior Project Director/Principal November 16, I CANADA I CHINA I HONG KONG I INDIA I SINGAPORE I UK I USA

8 AER Directive 60 Requirements, Temporary Flaring Purpose of Directive 60 Alberta Energy Regulator (AER) Directive 60 (D60) outlines the strict requirements for sour crude oil wells among other facilities. Aligned with other AB government regulators. Must comply with Alberta Environment and Parks Alberta Ambient Air Quality Objectives and Guidelines (AAAQO) for SO 2. Developed in consultation with the Clean Air Strategic Alliance (CASA); multi-stakeholder group that advises AB government on air quality policies to eliminate or reduce the potential impacts of flaring and address public safety concerns and environmental impacts. Conditions That Require a Temporary Flaring/Incineration Permit Bashaw must obtain temporary flaring permits to flare sour gas (>5 per cent sour gas) from each of the three proposed critical sour wells.

9 AER Directive 60 Requirements, Temporary Flaring Temporary and Well Test Flaring Dispersion Modelling Equipment design and/or the operating procedures, or both, must address all modelled predictions that exceed the AAAQO (0.172 ppm), excluding predicted values that meet the AER risk-based criteria. Flaring safely combusts H 2 S to less hazardous SO 2 Risk-based criteria for temporary events allow limited exclusion of predicted ambient air quality results based on their magnitude and frequency of occurrence. Model predictions up to ppm (900 μg/m 3 ) will be considered by the AER; however, actual measured exceedances of the AAAQO are never permitted.

10 Bashaw Proposed Flaring Plan Total volume to be flared at each well is 100 e 3 m 3 of sour gas Flaring would be conducted for 3 consecutive days per well times 3 wells or 9 days in total Cumulative Effects Multiple well test flaring/incinerating must not occur within 20 km of each other unless a licensee (Bashaw) can demonstrate that cumulative emissions from flaring can meet the AAAQO for SO 2.

11 Air Quality Management System Source Standards Dispersion Modelling Ambient Guidelines Source Monitoring A dispersion model provides a fundamental link between emissions and air quality changes by simulating transport, dispersion and deposition mechanisms. Ambient Monitoring

12 Local wind conditions, wind rose Wind rose plots the originating wind direction, where a greater lobe length indicates more commonly occurring wind direction

13 Predicted SO 2 concentrations for the Bashaw Pembina Project Scenario Maximum Average Low Sour Gas Flow Rate (10 3 m 3 /d) Maximum Predicted Hourly Average SO 2 Concentration in ppm (μg/m 3 ) (974) (935) (397) 99.9 th Percentile Predicted 1-hour SO 2 Concentration in ppm (μg/m 3 ) (562) (536) 0.99 (259) 99 th Percentile Predicted 1-hour SO 2 Concentration in ppm (μg/m 3 ) (421) (398) 0.65 (169) AER Risk-Based Criteria met? YES YES YES The AER flaring model calculates the predicted SO 2 concentrations over 43,800 hours of meteorological conditions and selects the maximum value that occurs once

14 Pembina Sentinel Air Monitoring Network Pennwest 592 Pennwest 447 Rocky Rapids Store 486 Bashaw Well Site Bellatrix 448

15 Example of Mobile Ambient Air Quality Monitoring Units for Downwind Surveillance

16 Summary of AER D60 Requirements, Flare Modelling Bashaw must obtain a flaring permit for each of their three proposed wells. Bashaw is able to secure AER flaring permits for temporary and separate well testing on the three wells without an air quality management plan. Four ambient air quality monitoring stations operated by the Pembina Sentinel Air Monitoring Network will continuously measure H 2 S and SO 2 within 5 km of the proposed surface well locations Bashaw will retain a 3rd party contractor to undertake downwind ambient air quality monitoring while they are working in the sour zones. Downwind surveillance will use public roads on both sides of the river, based on measured winds. Any measured 1-hour SO 2 concentrations in excess of the AAAQO will be communicated back to the well-site. Flaring operations will stop for a minimum one hour period until dispersion conditions improve (minimum 30-minutes).

17 Flare Dispersion Modelling, Pembina Sour Oil Project QUESTIONS? (403) ext 6228

18 Maximum predicted 1-hour SO 2 concentration contours based on AERMOD modelling for the maximum flow rate ( m 3 /d)

19 Pseudo-Parameters (flame derived), AER Flare Model Scenario Maximum Average Low Sour Gas Flow Rate (10 3 m 3 /d) H 2 S Content (%) Net Heating Value (MJ/m 3 ) SO 2 Emission Rate (g/s) Stack Height (m) 30.5 Stack Diameter (m) Scenario Maximum Average Low Sour Gas Flow Rate (10 3 m 3 /d) Effective Height (m) Pseudo-Exit Diameter (m) Pseudo-Exit Velocity (m/s) Estimated Exit Temperature (K) 1, , , Assumed Ambient Air Temperature (K)

20 EMERGENCY RESPONSE PLANNING ASHAW et al 102 PEMBINA (W5M) BASHAW et al PEMBINA (W5M) BASHAW et al 102 PEMBINA (W5M) SITE-SPECIFIC SUPPLEMENTAL SECTION Drilling, Completions and Testing and Workover/Servicing Operations Russ Brown Bissett Resource Consultants Ltd

21 ALBERTA ENERGY REGULATOR (AER) DIRECTIVE 71 Alberta Energy Regulator (AER) Directive 71 - Emergency Preparedness and Response Requirements for the Petroleum Industry. The purpose of emergency preparedness and response is to establish a decision framework and action plan so that the licensee can quickly and effectively respond to an emergency. (AER - D71, Section 1.5). The AER strongly supports the use of the Incident Command System (ICS) as a means of ensuring consistent command and communication among all parties. (AER - D71, Section 2.1.4). Section 4.3 of D71 recognises that those residing on deadend roads beyond the EPZ where occupants are required to egress through the EPZ must be included in the ERP.

22 ALBERTA ENERGY REGULATOR (AER) DIRECTIVE 71 Section 1.3. Licensees have a responsibility to ensure that they are fully prepared and capable of responding to any level of emergency. Emergency preparedness and response includes all activities done prior to an emergency so that designated personnel are ready and able to respond quickly and appropriately, as well as those activities that take place during the incident. This includes activities such as: identifying hazards, preparing and maintaining ERPs and response procedures, ensuring that the ERPs identify sufficient resources and equipment for use by response personnel during an emergency, and designating response personnel and ensuring that they are suitably equipped to carry out their duties through training, drills, and exercises.

23 EMERGENCY PLANNING ZONE: An emergency planning zone (EPZ) is a geographical area surrounding a well, pipeline, or facility containing hazardous product that requires specific emergency response planning by the licensee (AER - D71, Section 3.1).

24 INITIAL ISOLATION ZONE: The initial isolation zone (IIZ) defines an area in close proximity to a continuous hazardous release where indoor sheltering may provide temporary protection due to the proximity of the release. For H 2 S releases under poor dispersion conditions, the IIZ is defined and calculated using the ERCBH2S model and is very useful for planning purposes. The IIZ does not have to be drawn on the ERP map; however, IIZ information from the ERCBH2S model should be readily available to aid responders in protecting the public. (AER - D71, Section 3.4).

25 PUBLIC PROTECTION MEASURES (AER - D71, SECTION 5.2). Sheltering indoors (Shelter-In-Place): is a viable public protection measure in circumstances when: there is insufficient time or warning to safely evacuate the public that may be at risk, residents are waiting for evacuation assistance, the release will be of limited size and/or duration, the location of a release has not been identified, or the public would be at higher risk if evacuated.

26 AER - PUBLIC PROTECTION MEASURES FOR PLANNING AND RESPONSE ZONES DECISION TREE (AER DIRECTIVE 71 SECTION 14.3)

27 QUESTIONS?

28 THANK YOU

Revised edition November 18, 2008, including errata of November Emergency Preparedness and Response Requirements for the Petroleum Industry

Revised edition November 18, 2008, including errata of November Emergency Preparedness and Response Requirements for the Petroleum Industry Directive 071 Revised edition November 18, 2008, including errata of November 2009 Emergency Preparedness and Response Requirements for the Petroleum Industry The Energy Resources Conservation Board (ERCB/Board)

More information

Upstream Petroleum Industry Flaring, Incinerating, and Venting

Upstream Petroleum Industry Flaring, Incinerating, and Venting Directive 060 Release date: March 12, 2018 Effective date: March 29, 2018 Replaces previous edition issued March 22, 2016 Upstream Petroleum Industry Flaring, Incinerating, and Venting The Alberta Energy

More information

Industry, Trade Petroleum Ellice Avenue

Industry, Trade Petroleum Ellice Avenue Manitoba Industry, Trade Petroleum 360-1395 Ellice Avenue and Mines Winnipeg MB R3G 3P2 CANADA Phone: (204) 945-6577 Fax: (204) 945-0586 February 15, 2002 INFORMATIONAL NOTICE 02-1 INTERIM GUIDELINES FOR

More information

Air Quality Assessment Of the Grizzly Oil Sands ULC Algar Lake SAGD Project

Air Quality Assessment Of the Grizzly Oil Sands ULC Algar Lake SAGD Project Air Quality Assessment Of the Prepared for: Prepared by: Millennium EMS Solutions Ltd. January 21 File #7-99 Suite 28 427 98 Street Edmonton AB Canada T6E 5R7 Tel: 78.496.948 Fax: 78.496.949 Email: info@mems.ca

More information

Future Odour Enforcement and Role of Regulation in Alberta

Future Odour Enforcement and Role of Regulation in Alberta Future Odour Enforcement and Role of Regulation in Alberta David S. Chadder Senior Project Director/Principal CPANS/AWMA Annual Conference May 26 27, 2015 WWW.RWDI.COM I CANADA I CHINA I HONG KONG I INDIA

More information

E29. Emergency management area Hazardous facilities and infrastructure

E29. Emergency management area Hazardous facilities and infrastructure E29. Emergency management area Hazardous facilities and infrastructure E29.1. Background For the purposes of this section, the identified hazardous facilities and infrastructure are the Wiri Oil Terminal,

More information

SemCAMS Area Project Description

SemCAMS Area Project Description REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory

More information

Tips to Improve Model Results

Tips to Improve Model Results Tips to Improve Model Results 2019 Missouri Air Compliance Seminar Joseph Stolle, PE, Senior Environmental Engineer Wendy Vit, PE, Senior Environmental Engineer March 7, 2019 What is an Air Model? Used

More information

INTERIM DIRECTIVE ID 91-3

INTERIM DIRECTIVE ID 91-3 ID 91-03: Heavy Oil/Oil Sands Operations Page 1 of INTERIM DIRECTIVE ID 91-3 28 March 1991 To: All Oil and Gas Operators All In Situ Oil Sands Operators All Drilling and Servicing Contractors HEAVY OIL/OIL

More information

Appendix 1-A Well Testing

Appendix 1-A Well Testing Appendix 1-A Well Testing FLOW TESTING PURPOSE Flow testing is used to determine the performance of oil and gas wells and their economic potential. Various tests will be done to determine the amount of

More information

Directive DRAFT

Directive DRAFT Directive 060 - DRAFT Release date: Effective date: Replaces previous edition issued Upstream Petroleum Industry Flaring, Incinerating, and Venting The Alberta Energy Regulator approved this directive

More information

Annual Monitoring Network Plan for the North Carolina Division of Air Quality. Volume 1 Addendum 2

Annual Monitoring Network Plan for the North Carolina Division of Air Quality. Volume 1 Addendum 2 2016-2017 Annual Monitoring Network Plan for the North Carolina Division of Air Quality Volume 1 Addendum 2 December 28, 2016 North Carolina Division of Air Quality A Division of the North Carolina Department

More information

Parsons Creek Aggregates Limestone Quarry Project Clarification Questions of Supplemental Information Request 3 Responses

Parsons Creek Aggregates Limestone Quarry Project Clarification Questions of Supplemental Information Request 3 Responses November 19, 212 Susan Whittaker Pat Marriott, P. Eng. Natural Resources Conservation Board District Approvals Manager, Northern Region 4 th Floor, Sterling Place and 994 16 Street Camille Almeida Edmonton,

More information

LOCAL AIR QUALITY. Our Service

LOCAL AIR QUALITY. Our Service Supporting decision making with expertly gathered source/monitoring data, comprehensive modeling and user-friendly client-site software Meeting local air quality goals can be challenging as solutions become

More information

Application of the AERMOD modeling system for air pollution dispersion in the South Pars oilfield

Application of the AERMOD modeling system for air pollution dispersion in the South Pars oilfield First International Symposium on Urban Development: Koya as a Case Study 339 Application of the AERMOD modeling system for air pollution dispersion in the South Pars oilfield 1,2 1,2 3 M. Rouhi, H. Moradi

More information

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS)

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) 101050.22.RP.0001 A Environmental Impact Statement 15 th April 2005 APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) S:\Projects\190900\101050

More information

Comparison of Two Dispersion Models: A Bulk Petroleum Storage Terminal Case Study

Comparison of Two Dispersion Models: A Bulk Petroleum Storage Terminal Case Study Comparison of Two Dispersion Models: A Bulk Petroleum Storage Terminal Case Study Prepared By: Anthony J. Schroeder BREEZE SOFTWARE 12770 Merit Drive Suite 900 Dallas, TX 75251 +1 (972) 661-8881 breeze-software.com

More information

Analysis of SO 2 Modeling Issues for Ameren Power Plants in the Greater St. Louis Area

Analysis of SO 2 Modeling Issues for Ameren Power Plants in the Greater St. Louis Area Analysis of SO 2 Modeling Issues for Ameren Power Plants in the Greater St. Louis Area Prepared by AECOM August 19, 2014 1. Introduction In 2010, the United States Environmental Protection Agency (EPA)

More information

TECHNICAL BULLETIN. METHODOLOGY FOR MODELLING ASSESSMENTS OF CONTAMINANTS WITH 10-MINUTE AVERAGE STANDARDS AND GUIDELINES under O. Reg.

TECHNICAL BULLETIN. METHODOLOGY FOR MODELLING ASSESSMENTS OF CONTAMINANTS WITH 10-MINUTE AVERAGE STANDARDS AND GUIDELINES under O. Reg. TECHNICAL BULLETIN Standards Development Branch April 2008 METHODOLOGY FOR MODELLING ASSESSMENTS OF CONTAMINANTS WITH 10-MINUTE AVERAGE STANDARDS AND GUIDELINES under O. Reg. 419/05 EXECUTIVE SUMMARY This

More information

Arab Journal of Nuclear Sciences and Applications

Arab Journal of Nuclear Sciences and Applications Arab J. Nucl. Sci. Appl, Vol 51, 2, 68-81 (2018) Arab Journal of Nuclear Sciences and Applications ISSN 1110-0451 Web site: ajnsa.journals.ekb.eg (ESNSA) Environmental Impact of Conventional Power Plant

More information

Shell Canada Limited. Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No

Shell Canada Limited. Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No Shell Canada Limited Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No. 1769924 January 22, 2014 Good (morning/afternoon) Panel Members, AER staff, members

More information

9 INCIDENT AND EMERGENCY MANAGEMENT 9.2 EMERGENCY MANAGEMENT

9 INCIDENT AND EMERGENCY MANAGEMENT 9.2 EMERGENCY MANAGEMENT 9 INCIDENT AND EMERGENCY MANAGEMENT 9.2 EMERGENCY MANAGEMENT TABLE OF CONTENTS 9.2.1 Purpose... 2 9.2.2 The Need for Emergency Management... 2 9.2.3 Responding to an Emergency... 3 9.2.4 Responsibilities

More information

David Heinold AECOM Chelmsford, MA. Ambient Air Modeling Workshop NCASI Southern Regional Meeting Savannah, Georgia

David Heinold AECOM Chelmsford, MA. Ambient Air Modeling Workshop NCASI Southern Regional Meeting Savannah, Georgia David Heinold AECOM Chelmsford, MA Ambient Air Modeling Workshop NCASI Southern Regional Meeting Savannah, Georgia June 9, 2014 Acknowledgement The contents of this presentation is based on work conducted

More information

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 The following is an outline of the Safe Working Requirements for all Companies, staff and any other persons for this event. Please note that the terms Company

More information

Ketch Resources Ltd.

Ketch Resources Ltd. Decision 2005-129 Review of Well Licence No. 0313083 and Application for Associated Battery and Pipeline Pembina Field December 1, 2005 ALBERTA ENERGY AND UTILITIES BOARD Decision 2005-129:, Review of

More information

PREPARED BY: Demos Dracoulides. CAPE TOWN PO Box 60034, 7439 Table View, Cape Tel: Fax:

PREPARED BY: Demos Dracoulides. CAPE TOWN PO Box 60034, 7439 Table View, Cape Tel: Fax: Relocation of Acacia and Port Rex Gas Turbines to Ankerlig Power Station Air Quality Impact Assessment Summary Report PREPARED BY: Demos Dracoulides CAPE TOWN PO Box 60034, 7439 Table View, Cape Tel: 021

More information

Under Section 113 of the Environmental Protection and Enhancement Act

Under Section 113 of the Environmental Protection and Enhancement Act Order Made at Slave lake, in the Province of Alberta, on July 13, 2018 ALBERTA ENERGY REGULATOR Under Section 113 of the Environmental Protection and Enhancement Act Under Section 29 of the Pipeline Act

More information

SAMPLE APPROVAL ABC REGULATOR. ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT R.S.A. 2000, c.e-12, as amended. January 02, 2018.

SAMPLE APPROVAL ABC REGULATOR. ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT R.S.A. 2000, c.e-12, as amended. January 02, 2018. SAMPLE APPROVAL ABC REGULATOR ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT R.S.A. 2000, c.e-12, as amended. APPROVAL NO.: APPLICATION NO.: EFFECTIVE DATE: EXPIRY DATE: APPROVAL HOLDER: 000-00-00 99-999

More information

Appendix 9-C Cumulative PM-10 Emissions Inventories (PSD/Major Sources and Local Sources)

Appendix 9-C Cumulative PM-10 Emissions Inventories (PSD/Major Sources and Local Sources) Appendix 9-C Cumulative PM-10 Emissions Inventories (PSD/Major Sources and Local Sources) 9.0 Air Quality Multi-source PSD PM 10 Modeling Inventory Development A multi-source modeling emissions inventory

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 22706-D01-2017 Spring 2017 Comprehensive Sound Survey at Receptors R and S August 25, 2017 Alberta Utilities Commission Decision 22706-D01-2017 Proceeding 22706 Application 22706-A001 August 25,

More information

CIAC TRANSPORTATION EMERGENCY RESPONSE STANDARD

CIAC TRANSPORTATION EMERGENCY RESPONSE STANDARD Part 1 - Introduction The Senior Executive of each CIAC member company makes a formal commitment to take preventative action to protect health and the environment and to engage business partners to ensure

More information

Incident Reporting Requirements

Incident Reporting Requirements Incident Reporting Requirements Directive PNG014 December 2016 Version 2.0 Governing Legislation: Acts: The Oil and Gas Conservation Act The Pipelines Act, 1998 Regulations: The Oil and Gas Conservation

More information

EXAMPLE AIR QUALITY ANALYSIS CHECKLIST a

EXAMPLE AIR QUALITY ANALYSIS CHECKLIST a EXAMPLE AIR QUALITY ANALYSIS CHECKLIST a 1. Source location map(s) showing location with respect to:! Urban areas b! PSD Class I areas! Nonattainment areas b! Topographic features (terrain, lakes, river

More information

Drilling Inside Municipal Boundaries What are the Issues?

Drilling Inside Municipal Boundaries What are the Issues? Drilling Inside Municipal Boundaries What are the Issues? SACPA October 3, 2013 Goldenkey Penny Project Reference S Presenters S David Hill S Tim Robillard S Representatives of Goldenkey s Penny Project

More information

APPENDIX III. Air Quality Modelling of NO X and PM 10 (2007) RFI Report (Dec 2007)

APPENDIX III. Air Quality Modelling of NO X and PM 10 (2007) RFI Report (Dec 2007) APPENDIX III Air Quality Modelling of NO X and PM 10 (2007) RFI Report (Dec 2007) 17 EPA Export 25-07-2013:22:32:47 Platin IPPC Licence Application Air Quality Modelling of NOx and PM (2007) EPA Export

More information

Brandon Generating Station Unit 5 Environmental Impact Statement

Brandon Generating Station Unit 5 Environmental Impact Statement 0.3 µg/m 3 respectively are negligible, and less than 0.2 µg/m 3 at the nearest residence east of Unit 5. Therefore, fugitive dust emissions from the Brandon G.S. alone would not be sufficient to account

More information

Air Quality Monitoring

Air Quality Monitoring Air Quality Monitoring in the vicinity of a CNRL well blowout February 25, 2010 to March 9, 2010 Summary report Overview All monitoring sites were downwind of the Canadian Natural Resources Limited (CNRL)

More information

NOVA Chemicals Redwater Lateral Upgrade. Project Information Document and Confirmation of Non-objection

NOVA Chemicals Redwater Lateral Upgrade. Project Information Document and Confirmation of Non-objection NOVA Chemicals Redwater Lateral Upgrade Project Information Document and Confirmation of Non-objection December 20, 2016 NOVA Chemicals Redwater Lateral Upgrade 2 Contents Project Necessity... 3 Project

More information

Integrated IT Technology for HazMat Incidents Decision Support

Integrated IT Technology for HazMat Incidents Decision Support Integrated IT Technology for HazMat Incidents Decision Support 8th INTERNATIONAL CONFERENCE FOR FIRE BRIGADES IN THE HIGH HAZARD INDUSTRY 10 th 11 th November 2015 Danubius Hotel Helia, Budapest Eric Quatreville

More information

Directive 039: Revised Program to Reduce Benzene Emissions from Glycol Dehydrators

Directive 039: Revised Program to Reduce Benzene Emissions from Glycol Dehydrators Directive 039 Directive 039: Revised Program to Reduce Benzene Emissions from Glycol Dehydrators January 22, 2013 Effective June 17, 2013, the Energy Resources Conservation Board (ERCB) has been succeeded

More information

Example Airshed. Sample 2018 Annual Ambient Air Quality Monitoring Report

Example Airshed. Sample 2018 Annual Ambient Air Quality Monitoring Report Example Airshed Sample 2018 Annual Ambient Air Quality Monitoring Report 29 March 2019 DISCLAIMER: This sample annual report is provided as guidance only. The structure, look and layout of monthly and

More information

EnviroTech Dispersion Modelling to Address Air Quality during Remediation of Hydrocarbon Impacted Soils

EnviroTech Dispersion Modelling to Address Air Quality during Remediation of Hydrocarbon Impacted Soils EnviroTech 2018 Dispersion Modelling to Address Air Quality during Remediation of Hydrocarbon Impacted Soils Presented by: Cody Halleran, B.Sc., E.P. & Pippa Cookson-Hills, M.Sc. THE PROBLEM Excavation

More information

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT 6 J:\Jobs\42626220\07 Deliverables\EIS\FINAL for Public Release\6. Values and Management of Impacts\6-8 Air Quality\06 08 Air Quality (Section 6.8) FINAL PUBLIC track.doc GLNG Project - Environmental Impact

More information

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2 Summary of LAE ONTARIO 1. Requiring SPC approval: LO SEW 3 LO FUEL 2 2. Information (editorial, revised, new): LO G 1 (revised) LO NGS 1 (revised) LO G 2 (revised) LO SEW 2 (revised) LO G 6 (revised) LO

More information

Air Quality Assessment of the Pengrowth Lindbergh SAGD Project

Air Quality Assessment of the Pengrowth Lindbergh SAGD Project Air Quality Assessment of the Pengrowth Lindbergh SAGD Project Prepared for: Pengrowth Energy Corporation Prepared by: Millennium EMS Solutions Ltd. Suite 217, 811 14 th Street NW Calgary, Alberta T2N

More information

BEST OPERATING PRACTICES: Hydraulic Fracturing

BEST OPERATING PRACTICES: Hydraulic Fracturing BEST OPERATING PRACTICES: Hydraulic Fracturing OBJECTIVE The West Central Stakeholders (WCS) group is committed to sharing information and creating understanding about oil and gas development in Clearwater

More information

Use of EMVAP to Evaluate 1-hour NAAQS Compliance with Long-term Emission Rates

Use of EMVAP to Evaluate 1-hour NAAQS Compliance with Long-term Emission Rates Use of EMVAP to Evaluate 1-hour NAAQS Compliance with Long-term Emission Rates Bob Paine, AECOM and Dr. Eladio Knipping, EPRI Presentation to EPA RSL Workshop May 20, 2014 Outline of Presentation Emission

More information

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION 1 Contents Introduction 3 Delegation to the NEB 3 Assessments and regulatory guidance 4 Provincial requirements

More information

RELOCATION, RE-ENTRY, AND RETURN - DECISION MAKING. Demonstrate the capability to develop decisions on relocation, re-entry, and return.

RELOCATION, RE-ENTRY, AND RETURN - DECISION MAKING. Demonstrate the capability to develop decisions on relocation, re-entry, and return. OBJECTIVE 28: RELOCATION, RE-ENTRY, AND RETURN - DECISION MAKING OBJECTIVE Demonstrate the capability to develop decisions on relocation, re-entry, and return. INTENT This objective is derived from -0654

More information

Update of Saskatchewan Upstream Oil & Gas Industry Regulations

Update of Saskatchewan Upstream Oil & Gas Industry Regulations Update of Saskatchewan Upstream Oil & Gas Industry Regulations Ministry of the Economy SESSA March 19, 2012 Directive S-10 DirectiveS S 10 10provides enforceable regulatory requirements for reducing flaring

More information

Introduction to Pipeline Quantitative Risk Assessment

Introduction to Pipeline Quantitative Risk Assessment Introduction to Pipeline Quantitative Risk Assessment 66 th Canadian Chemical Engineering Conference October 18 th, 2016 Presented by Sam Sanati, P.Eng, FS Eng. 30 January 2017 1 Pipeline Incident, 2008

More information

Information Brochure. Proposed EOR Development Project. The Company CO 2. EOR recovers as much oil as primary or secondary recovery.

Information Brochure. Proposed EOR Development Project. The Company CO 2. EOR recovers as much oil as primary or secondary recovery. Information Brochure Proposed EOR Development Project Enhance Energy Inc. ( Enhance ) has prepared this project information brochure to provide landowners, the public, government agencies, and other interested

More information

Keep Your Company Moving After A Disaster With A Business Continuity Plan (BCP)

Keep Your Company Moving After A Disaster With A Business Continuity Plan (BCP) Keep Your Company Moving After A Disaster With A Business Continuity Plan (BCP) HR Benefits Payroll gnapartners.com It only takes one major interruption to its business operations for a company to recognize

More information

Single-Source Impacts on Secondary PM 2.5 Formation A Case Study

Single-Source Impacts on Secondary PM 2.5 Formation A Case Study Single-Source Impacts on Secondary PM 2.5 Formation A Case Study Midwest Environmental Compliance Conference Joe Stolle, PE, Senior Environmental Engineer Wendy Vit, PE, Senior Environmental Engineer May

More information

EMERGENCY OPERATIONS PLANNING AND CONTINUITY OF OPERATIONS

EMERGENCY OPERATIONS PLANNING AND CONTINUITY OF OPERATIONS EMERGENCY OPERATIONS PLANNING AND CONTINUITY OF OPERATIONS County Commissioner Clerks/Engineers Administrative Professional Association Winter Conference - Columbus Convention Center Emergency Management

More information

Isopleths of Maximum Predicted Hourly Average Ground-level NO 2

Isopleths of Maximum Predicted Hourly Average Ground-level NO 2 400 100 PEACE RIVER 80 60 40 0 TOWN OF PEACE RIVER UTM-NAD83-Z11 (metres) LEGEND Source - Baseline Plant Fenceline MAXIMUMS Time Average: 1-hour AAAQO: 400 µg/m³ Modelled: 122 µg/m³ Background: 23.7 µg/m³

More information

The Alberta Energy Regulator (AER) has approved this directive on February 17, 2016.

The Alberta Energy Regulator (AER) has approved this directive on February 17, 2016. Directive 007 Release date: February 17, 2016 Effective date: February 17, 2016 Replaces previous edition issued February 25, 2015 Volumetric and Infrastructure Requirements The Alberta Energy Regulator

More information

Suspension Requirements for Wells

Suspension Requirements for Wells Directive 01 Suspension Requirements for Wells July 24, 2007 Effective January 1, 2008, the Alberta Energy and Utilities Board (EUB) has been realigned into two separate regulatory bodies, the Energy Resources

More information

Saskatchewan Upstream Flaring and Incineration Requirements

Saskatchewan Upstream Flaring and Incineration Requirements Saskatchewan Upstream Flaring and Incineration Requirements Directive S-20 November 2015 Revision 1.0 Governing Legislation: Act: The Oil and Gas Conservation Act Regulation: The Oil and Gas Conservation

More information

O I L SPILL RES PO NSE TRA INING SERVICE S

O I L SPILL RES PO NSE TRA INING SERVICE S O I L SPILL RES PO NSE TRA INING SERVICE S OIL SPILL RESPONSE TRAINING SERVICES The International Convention on Oil Pollution Preparedness, Response and Cooperation (OPRC 1990) sets the international framework

More information

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Dispersion Modeling Approach to Assess the Odour Impact from an Industrial Source at Residential Buildings in Urban Areas

Dispersion Modeling Approach to Assess the Odour Impact from an Industrial Source at Residential Buildings in Urban Areas Dispersion Modeling Approach to Assess the Odour Impact from an Industrial Source at Residential Buildings in Urban Areas Attilio Poli Envirosolutions & Consulting, Singapore Better Air Quality 2012 Hong

More information

Flaring in Canada: Overview and Strategic Considerations Part 1 January 16, 2017

Flaring in Canada: Overview and Strategic Considerations Part 1 January 16, 2017 Cap-Op Energy Inc. Suite 610, 600 6 Ave SW Calgary, AB T2P 0S5 403.457.1029 www.capopenergy.com Flaring in Canada: Overview and Strategic Considerations Part 1 January 16, 2017 January 2017 Page 1 of 44

More information

City of Edmonton Oil and Gas Facilities Policy Review Implementation Plan

City of Edmonton Oil and Gas Facilities Policy Review Implementation Plan City of Edmonton Oil and Gas Facilities Policy Review Implementation Plan Approved by Council January 30, 2008 Table of Contents 1.0 Roles and Responsibilities 1.1.1 Oil and Gas Liaison Officer 1.1.2 Internal

More information

Technical Backgrounder on Multi-Source Air Dispersion Modelling

Technical Backgrounder on Multi-Source Air Dispersion Modelling Technical Backgrounder on Multi-Source Air Dispersion Modelling DRAFT FOR DISCUSSION ONLY NOVEMBER, 2017 Page 1/29 Table of Contents 1 Multi-source Air Dispersion Modelling - Overview... 3 2 Selection

More information

DRAKS INTERIOR DOOR SYSTEMS LTD STATEMENT OF INTENT

DRAKS INTERIOR DOOR SYSTEMS LTD STATEMENT OF INTENT DRAKS INTERIOR DOOR SYSTEMS LTD STATEMENT OF INTENT The management of Draks Interior Door Systems Ltd looks upon the promotion of Health and Safety measures as a mutual objective for themselves and their

More information

Company Y Facility Z. Sample January 2019 Monthly Industrial Air Monitoring Report. EPEA Approval Number

Company Y Facility Z. Sample January 2019 Monthly Industrial Air Monitoring Report. EPEA Approval Number Company Y Facility Z Sample January 219 Monthly Industrial Air Monitoring Report EPEA Approval Number -- 15 February 219 Sample January 219 Monthly Industrial Air Monitoring Report Page 1 of 4 DISCLAIMER:

More information

DORIN LAND AND OILFIELD MANAGEMENT INC Ave, Edmonton Alberta, Canada T6E 0C5 Telephone (780) Fax (780)

DORIN LAND AND OILFIELD MANAGEMENT INC Ave, Edmonton Alberta, Canada T6E 0C5 Telephone (780) Fax (780) May 1, 015 Penn West Petroleum Ltd. c/o Bennett Jones LLP Suite 00 Penn West Plaza Calgary, Alberta, TP 1K VIA E-MAIL DORIN LAND AND OILFIELD MANAGEMENT INC. 9760 60 Ave, Edmonton Alberta, Canada T6E 0C5

More information

POLICY NUMBER: C515. City Council Energy Resources Conservation Board

POLICY NUMBER: C515. City Council Energy Resources Conservation Board CITY POLICY POLICY NUMBER: C515 REFERENCE: ADOPTED BY: Municipal Government Act, R.S.A. 2000 City Council Energy Resources Conservation Board 30 January 2008 Oil and Gas Conservation Regulations; Energy

More information

Pipeline Application

Pipeline Application Pipeline Application Sales Gas Pipeline From 11-30-001-25 W1M to 14-19-001-25 W1M Southwestern Manitoba Manitoba Innovation, Energy and Mines Petroleum Branch Date: June 5, 2013 Table of Contents 1. Introduction...

More information

Policy Work Health and Safety (WHS) RCPA Introduction WHS legislation

Policy Work Health and Safety (WHS) RCPA Introduction WHS legislation Policy Subject: Work Health and Safety (WHS) Approval Date: July 2011, December 2014 Review Date: July 2018 Review By: Board of Directors Number: 1/2011 The Royal College of Pathologists of Australasia

More information

Millipore Thermal Oxidiser Emissions Dispersion Modelling Impact Assessment

Millipore Thermal Oxidiser Emissions Dispersion Modelling Impact Assessment Millipore Thermal Oxidiser Emissions Dispersion Modelling Impact Assessment Issue No 2 45078628 EPA Export 25-07-2013:19:52:54 Project Title: Report Title: Millipore Thermal Oxidiser Emissions Project

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,

More information

ST Field Surveillance and Operations Branch Field Operations Provincial Summary 2012

ST Field Surveillance and Operations Branch Field Operations Provincial Summary 2012 ST57-2013 Field Surveillance and Operations Branch Field Operations Provincial Summary 2012 ACKNOWLEDGEMENTS Thank you to the following Energy Resources Conservation Board staff who contributed to this

More information

Released by EHP under the

Released by EHP under the Tara Air Emission Data Collation Response to the Queensland Health Action Plan Report drafted by the Department of Environment and Heritage Protection Page 15-185 File B Page 1 of 18 Contents 1. Introduction...

More information

LINN COUNTY PUBLIC HEALTH DEPARTMENT

LINN COUNTY PUBLIC HEALTH DEPARTMENT LINN COUNTY PUBLIC HEALTH DEPARTMENT Air Quality Division M E M O R A N D U M DATE: MARCH 13, 2009 TO: FROM: RE: CC: TONY DAUGHERTY PM2.5 PREDICTED MODELING IMPACTS OF OUTDOOR WOOD BOILERS INTRODUCTION

More information

WELL CONTROL AND SPILL RESPONSE PLANNING

WELL CONTROL AND SPILL RESPONSE PLANNING Scotian Basin Exploration Program WELL CONTROL AND SPILL RESPONSE PLANNING BP s Scotian Basin Exploration Program involves drilling an initial well on Exploration Licence (EL) 2434 in 2777 metres water

More information

AERMOD Modeling of PM2.5 Impacts of the Proposed Highwood Generating Station

AERMOD Modeling of PM2.5 Impacts of the Proposed Highwood Generating Station AERMOD Modeling of PM2.5 Impacts of the Proposed Highwood Generating Station September 10, 2007 Prepared for Montana Environmental Information Center and Citizens for Clean Energy Prepared by Khanh T.

More information

IN THE MATTER of a CONTRAVENTION. of the OIL AND GAS ACTIVITIES ACT. [SBC 2008] Chapter 36. Before. The BC OIL & GAS COMMISSION. Case File

IN THE MATTER of a CONTRAVENTION. of the OIL AND GAS ACTIVITIES ACT. [SBC 2008] Chapter 36. Before. The BC OIL & GAS COMMISSION. Case File IN THE MATTER of a CONTRAVENTION of the OIL AND GAS ACTIVITIES ACT [SBC 2008] Chapter 36 before The BC OIL & GAS COMMISSION Case File 2017-061 BETWEEN The BC Oil & Gas Commission AND Pavilion Energy Corporation

More information

AERMOD Modeling of SO2 Impacts of the Luminant Martin Lake Coal Plant

AERMOD Modeling of SO2 Impacts of the Luminant Martin Lake Coal Plant AERMOD Modeling of SO2 Impacts of the Luminant Martin Lake Coal Plant Final Report June 2011 Prepared for Sierra Club San Francisco, California Prepared by Mr. Khanh T. Tran Principal AMI Environmental

More information

Gunlake Quarry. Air Quality Management Plan

Gunlake Quarry. Air Quality Management Plan Gunlake Quarry Air Quality Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Air Quality Criteria 3 2.1 Impact Assessment Criteria 4 2.2 Sources

More information

We did. Have you tested your environmental unit lately? Jeff Blanchard, Spectra Energy Sheri Gilmour, Stantec Consulting Ltd.

We did. Have you tested your environmental unit lately? Jeff Blanchard, Spectra Energy Sheri Gilmour, Stantec Consulting Ltd. REMTECH 2016 FAIRMONT BANFF SPRINGS OCTOBER 12-14, 2016 Have you tested your environmental unit lately? We did. Jeff Blanchard, Spectra Energy Sheri Gilmour, Stantec Consulting Ltd. RemTech 2016 October

More information

Annual Monitoring Network Plan for the North Carolina Division of Air Quality. Volume 1 Addendum

Annual Monitoring Network Plan for the North Carolina Division of Air Quality. Volume 1 Addendum 2016-2017 Annual Monitoring Network Plan for the North Carolina Division of Air Quality Volume 1 Addendum September 1, 2016 North Carolina Division of Air Quality A Division of the North Carolina Department

More information

Pembina NGL Corporation

Pembina NGL Corporation Decision 22928-D01-2018 45-Megawatt Cogeneration Power Plant, Alteration to Scoria 318S Substation and Amendment to the Redwater Industrial System Designation January 9, 2018 Alberta Utilities Commission

More information

Initiated by PHMSA, NTSB accident report, Congress, petition for rulemaking, inspector general, etc. Advance notice of proposed rulemaking (ANPRM)

Initiated by PHMSA, NTSB accident report, Congress, petition for rulemaking, inspector general, etc. Advance notice of proposed rulemaking (ANPRM) How a regulation is made Initiated by PHMSA, NTSB accident report, Congress, petition for rulemaking, inspector general, etc. Advance notice of proposed rulemaking (ANPRM) Public comments and possible

More information

Emergency Preparedness & Response Training

Emergency Preparedness & Response Training J U N E 2 7, 2 0 13 Emergency Preparedness & Response Training Terry McGivern Manager, Emergency Response Planning & System Security Union Gas Training & Assessment Programs 1. About Union Gas & Emergency

More information

ELECTROMAGNETIC ENERGY

ELECTROMAGNETIC ENERGY CONTRACTOR WHS HAZARD STANDARD ELECTROMAGNETIC ENERGY EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

WasteMINZ Webinar 22 February 2018

WasteMINZ Webinar 22 February 2018 WasteMINZ Webinar 22 February 2018 Dr Doug Boddy Senior Air Quality Scientist Pattle Delamore Partners Ltd Auckland doug.boddy@pdp.co.nz Ph +64 9 529 5858 Mob +64 21 977 810 https://www.linkedin.com/in/doug-boddy-b279615/

More information

Major Event Response Reporting April 15, 2018

Major Event Response Reporting April 15, 2018 Major Event Response Reporting April 15, 2018 1 PRIOR TO THE MAJOR EVENT 1.0 Did the distributor have any prior warning that the Major Event would occur? Yes. From April 11, 2018 to April 15, 2018, Toronto

More information

AIR AND ODOUR EMISSIONS ASSESSMENT OF OPERATIONAL SHUTDOWN STACK RELEASE

AIR AND ODOUR EMISSIONS ASSESSMENT OF OPERATIONAL SHUTDOWN STACK RELEASE AIR AND ODOUR EMISSIONS ASSESSMENT OF OPERATIONAL SHUTDOWN STACK RELEASE CLEAN HARBORS CANADA INC. CORUNNA, ONTARIO DISCLAIMER: SOME FORMATTING CHANGES MAY HAVE OCCURRED WHEN THE ORIGINAL DOCUMENT WAS

More information

OWNER USER INTEGRITY MANAGEMENT SYSTEM WRITTEN DESCRIPTION CHECKLIST AB-512(b)

OWNER USER INTEGRITY MANAGEMENT SYSTEM WRITTEN DESCRIPTION CHECKLIST AB-512(b) Company Name: Written Description of QMS Title and Rev. Status: Person who is responsible for preparing the owner s QMS written description: Name: Title: Telephone No.: ( ) Fax No.: ( ) Cell No.: ( ) E-Mail:

More information

Integrated ESIA Greece Annex Ambient Air Quality

Integrated ESIA Greece Annex Ambient Air Quality Page 2 of 9 TABLE OF CONTENTS 1 INTRODUCTION 3 2 RELEVANT LEGISLATION AND STANDARDS 4 3 METHODOLOGY 5 3.1 Selection of Sample Points 5 3.2 Sampling Methodology and Samples Analysis 7 4 RESULTS 8 5 LIMITATIONS

More information

Inspection Program. Inspection Training

Inspection Program. Inspection Training General Inspection 1 Table of Contents Inspection Program... 3 Inspection Training... 3 Inspection Responsibility... 4 Management Tours and Inspection... 4 Health, Safety and Environment Tours and Inspections...

More information

Planning or Diagnostic Tool. Air Plume Modeling. Michael Gemelli, Lockheed-Martin/REAC, Edison, NJ. Keith Ocheski, Lockheed-Martin/REAC, Edison, NJ

Planning or Diagnostic Tool. Air Plume Modeling. Michael Gemelli, Lockheed-Martin/REAC, Edison, NJ. Keith Ocheski, Lockheed-Martin/REAC, Edison, NJ Air Plume Modeling Planning or Diagnostic Tool Rod Turpin, US EPA-ERT, Edison, NJ Greg De Angelis, US EPA Region II, Edison, NJ Paul Groulx, US EPA Region I, Boston, MA And Keith Ocheski, Lockheed-Martin/REAC,

More information

WG1 discussion topic: Model s fitness-for-purpose in the context of exceedance modelling

WG1 discussion topic: Model s fitness-for-purpose in the context of exceedance modelling WG1 discussion topic: Model s fitness-for-purpose in the context of exceedance modelling Jenny Stocker & Kate Johnson FAIRMODE Technical Meeting June 2017 Athens Greece Contents Context Specific questions:

More information

Combined Cycle Gas Turbine Power Plant Project at Fort George, Mauritius

Combined Cycle Gas Turbine Power Plant Project at Fort George, Mauritius Combined Cycle Gas Turbine Power Plant Project at Fort George, Mauritius CONTENTS Chapter Description Page 1 NON-TECHNICAL SUMMARY 17 1 INTRODUCTION 18 2 PROPOSED PROJECT IN FORT GEORGE 18 3 METHODOLOGY

More information

Proposed Heartland Cavern Lateral Pipeline and Meter Station. Public Information Document

Proposed Heartland Cavern Lateral Pipeline and Meter Station. Public Information Document Proposed Heartland Cavern Lateral Pipeline and Meter Station Public Information Document April 16, 2015 Proposed Heartland Cavern Lateral Pipeline and Meter Station Project 2 Contents Project Necessity...

More information

The Health & Safety Policy

The Health & Safety Policy The Health & Safety Policy April 2014 Issue: 3 Page 1 of 16 Review Date: April 2015 Introduction This document sets out the Health & Safety arrangements for Astra Signs Ltd and represents our commitment

More information

Pipeline Regulatory Framework in Alberta

Pipeline Regulatory Framework in Alberta Pipeline Regulatory Framework in Alberta Outline Energy Context Regulatory Jurisdiction About the Alberta Energy Regulator (AER) AER Initiatives Canada In World Context 4 4 Canada In World Context cont

More information

PIPELINE EMERGENCY RESPONSE GUIDELINES

PIPELINE EMERGENCY RESPONSE GUIDELINES PIPELINE EMERGENCY RESPONSE GUIDELINES FOR SCHOOLS In the event of an actual or suspected pipeline release call 911 and Kinder Morgan Canada at 1.888.876.6711 If you see someone working or digging near

More information