Korea Nuclear Power Plants and Technology

Size: px
Start display at page:

Download "Korea Nuclear Power Plants and Technology"

Transcription

1 Presentation 5 Session 2 Korea Nuclear Power Plants and Technology Byung Jin LEE, Ph.D KEPCO Engineering & Construction Company Biography Majoring in Nuclear Engineering, Byung Jin Lee received his Ph.D. degree from KAIST in Korea. He has an experience of 30 years in nuclear power plant design, starting his career at Korea Atomic Energy Research Institute and now working at KEPCO-E&C. He participated in the development of OPR1000, APR1400 and APR+ reactors, and is now working on a future advanced nuclear reactor development project. Abstract This presentation will start with a brief history of Korea s nuclear technology self-reliance and followup efforts for evolution. Key design features of APR1400 will be introduced together with major enhancements to avoid or cope with severe accidents like that occurred in Fukushima. The KEPCO Engineering & Construction Inc (KEPCO E&C) was founded in 1975 with the goal of accomplishing self-reliance in power plant engineering technology. The company focuses on reactor technology and design as well as technology support for the NPPs in operation. KEPCO E&C, with over 4,000 employees in total of which 1,800 are involved in the company s nuclear business. KEPCO A&E has designed 22 nuclear power plants. In 2009, KEPCO E&C participated in the bid to win a nuclear power plant project in Barakah, UAE, for the first exportation of Korean-model nuclear power plant, and are performing A/E (Architect Engineering) and NSSS (Nuclear Steam Supply System) Design for the four APR1400 being constructed at Barakah. In addition, from 2016, KEPCO E&C is participating in the engineering of a SMART nuclear power plant, which is a small to mid-sized nuclear power plant, to export to Saudi Arabia. ANA2017 Conference, Sydney, 6 Oct

2 ANA2017 Conference, Sydney, NSW 06 October 2017 LEE, Byung Jin This document is the property of KEPCO E&C and the use of this information is strictly prohibited without the permission of KEPCO E&C

3 Contents 1 Korean Nuclear Technology Development 2 Key Design Features of APR Countermeasures for Severe Accidents 4 Summary 1

4 Korean Nuclear Technology Development 2

5 Our Nuclear Reactors Today & Tomorrow Technology Self-Reliance Design Standardization Improvements Innovations 5 th Phase : Gen IV 1 st Phase : Gen II Turn-key base 600 MWe 2 nd Phase : Gen II Standardization (KSNP) Optimization (OPR1000) 3 rd Phase : Gen III Evolutionary PWRs - APR SMART(100MWe) 4 th Phase : Gen III + Evolutionary PWRs - APR + (1500MWe) with improved Economics and Safety - ipower Revolutionary - SFR : U recycle and waste minimization - VHTR : Hydrogen production 1970s 1980s 1990s 2000s 2010s 2020s 2030s 3

6 Strategy for Large NPP Developments Unending Improvements to Stay Competitive Optimization to improve economics Based on experience of steady constructions and operation over 40 years Advanced Design to enhance safety and operational flexibility Up-to-date Safety Requirements (Korea, USA, IAEA, UAE) Utility Requirements (domestic & world-wide: KURD, EPRI URD, EUR) Flexible Response to Market Demands Diversifying Portfolio APR1400 / EU-APR / US-APR APR+ APR1000 ipower Diversifying Applications Electricity, Desalination US-APR Future NPPs ipower APR+ APR1400 OPR1000 APR1000 EU-APR 4

7 Extensive Validation Testing for ADFs 5

8 Design Verifications for International Market EUR Certification of EU-APR US NRC Design Certification of US-APR 6

9 Key Design Features of APR1400 7

10 Design Goals SAFETY Core Damage Frequency Containment Failure Frequency Seismic Design Basis Occupational Radiation Exposure < 10-5 /RY < 10-6 /RY 0.3 g < 1 Man Sv/RY Gen-III NPP PERFORMANCE / ECONOMY Thermal Margin > 10 % Plant Availability > 90 % Unplanned Trip < 0.8/RY Plant Capacity (Gross) 1,455 MWe Plant Lifetime 60 Years Refueling Cycle 18 Months Construction Period 48 Months (N th unit) 8

11 Plant Layout Economics Twin-unit arrangement & Compound building shared by two units Seismic resistance Common basemat for containment and auxiliary building Physical Separation Four-quadrant arrangement of safety systems 9

12 Reactor Coolant System 10

13 Safety Systems SIP SIP SIT SIT RWST SIT SIT RCP RCP LPSIP RCP RCP IRWST S/G RV S/G HPSIP S/G RV S/G CONTAINMENT RCP RCP HPSIP RCP RCP SIT Sump SIT LPSIP SIP SIT SIT SIP CONTAINMENT 11

14 Human-Machine Interface System 12

15 Countermeasures for Severe Accidents 13

16 Prevention & Mitigation of Severe Accident 14

17 Protection from External Hazards * EF : Enhanced Fujita scale of Tornado 15

18 Post-Fukushima Safety Enhancements 16

19 Summary 17

20 Korean Nuclear Technology - Safe and Reliable Proven and improved through accumulated experience of steady constructions and operation of 40 years APR1400, Evolutionary ALWR Advanced design features for safety and operational flexibility Reinforced design for severe accident mitigation Complying with global standards of Korea, USA, UAE, EU and IAEA One and only Gen-III NPP now in operation Five (5) more units under construction in Korea, and 4 units in the UAE Our innovation continues. APR+ ipower 18

21 Thank You! 19

APR1400 Safe, Reliable Technology

APR1400 Safe, Reliable Technology APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

Managing the supply chain: Challenges and Overcoming in Korean nuclear industry

Managing the supply chain: Challenges and Overcoming in Korean nuclear industry Managing the supply chain: Challenges and Overcoming in Korean nuclear industry TM on Topical Issues in the Development of Nuclear Power Infrastructure 4-7 February 2014, Vienna, Austria International

More information

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford Post-Fukushima Action Plan in Korea WNU-SI 2011, August 11 Christ Church, Oxford Contents Korean nuclear overview BK Kim Government action plan BS Jeong Post-Fukushima action plan MK Jo Nuclear Power Plants

More information

Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C

Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C Int. Conf. on Topical Issues in Nuclear Installation Safety, Vienna Austria, 6~9 Jun. 2017 Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C Contents 1. Introduction

More information

Small Modular Reactors: A Call for Action

Small Modular Reactors: A Call for Action Small Modular Reactors: A Call for Action Overview of Five SMR Designs by Dr. Regis A. Matzie Executive Consultant Adapted May 2015 for the Hoover Institution's Reinventing Nuclear Power project from a

More information

Post-Fukushima Assessment of the AP1000 Plant

Post-Fukushima Assessment of the AP1000 Plant ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,

More information

Advances in Small Modular Reactor Design and Technology Development for Near-term Deployment

Advances in Small Modular Reactor Design and Technology Development for Near-term Deployment ESI-CIL Nuclear Governance Project Conference Series Small Modular Nuclear Reactors: The Outlook for Deployment Jen Tanglin Hotel, Singapore, 8 th November 2017 Advances in Small Modular Reactor Design

More information

NEW POWER REACTOR DESIGNS

NEW POWER REACTOR DESIGNS NUCLEAR ENERGY RENAISSANCE: ADDRESSING THE CHALLENGES OF CLIMATE CHANGE AND SUSTAINABILITY NCSR DEMOKRITOS Athens May 8, 2008 NEW POWER REACTOR DESIGNS Dimitrios Cokinos Brookhaven National Laboratory

More information

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,

More information

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods

More information

Role of Nuclear Cogeneration in a Low Carbon Energy Future?

Role of Nuclear Cogeneration in a Low Carbon Energy Future? Role of Nuclear Cogeneration in a Low Carbon Energy Future? Dr. Henri PAILLERE Senior Nuclear Analyst, Nuclear Development Division henri.paillere@oecd.org NC2I Conference, Brussels, 14-15 September 2015

More information

Rosatom Global Development, International Cooperation Perspective

Rosatom Global Development, International Cooperation Perspective ROSATOM STATE ATOMIC ENERGY CORPORATION ROSATOM Rosatom Global Development, International Cooperation Perspective Atomex-Europe 013 Forum Nikolay Drozdov Director, International Business State Corporation

More information

Westinghouse AP1000. Reactor

Westinghouse AP1000. Reactor Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment

More information

Nuclear Businesses. Sept 10, Session 3 NEA/MDEP Conference on the New Reactor Design Activities

Nuclear Businesses. Sept 10, Session 3 NEA/MDEP Conference on the New Reactor Design Activities Nuclear Businesses Sept 10, 2009 Session 3 NEA/MDEP Conference on the New Reactor Design Activities Sang Jin, Kim sangjinkim@doosan.com Doosan Heavy Industries and Construction Co., Ltd. Fully Integrated

More information

Westinghouse SMR & Nuclear Fuel Overview

Westinghouse SMR & Nuclear Fuel Overview Westinghouse SMR & Nuclear Fuel Overview Carlos Leipner, Westinghouse VP Latin America Presented at LAS-ANS July 2014 Rio de Janeiro, Brasil 2014 Westinghouse Electric Company LLC, All Rights Reserved.

More information

Westinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant

Westinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant Westinghouse s plant for the Nuclear Renaissance : AP000 Fernando Naredo Milan, January 30, 006 AP000 Advanced Passive Plant Designed to compete with other sources in deregulated power markets - Two loop,

More information

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW Gabriel Georgescu, Patricia Dupuy and Francois Corenwinder Institute for Radiological Protection

More information

Jordan s Nuclear Energy Programme

Jordan s Nuclear Energy Programme Technical Meeting on the Country Nuclear Power Profiles Jordan s Nuclear Energy Programme Yasmin Majali 10-13 May 2016 0 Jordan s Country Profile Total Area: 89,213 Km 2 Sea Port: Aqaba Coastline: 26 Km

More information

The Nuclear Safety Authority (ASN - Autorité de Sûreté Nucléaire),

The Nuclear Safety Authority (ASN - Autorité de Sûreté Nucléaire), REPUBLIQUE FRANÇAISE ASN Resolution 2014-DC-0406 of 21 th January 2014 instructing Electricité de France - Société Anonyme (EDF-SA) to comply with additional prescriptions applicable to the Gravelines

More information

IAEA Generic Review for UK HSE of New Reactor Designs against IAEA Safety Standards EPR

IAEA Generic Review for UK HSE of New Reactor Designs against IAEA Safety Standards EPR IAEA Generic Review for UK HSE of New Reactor Designs against IAEA Safety Standards EPR IAEA Generic Review for UK HSE of New Reactor Designs against IAEA Safety Standards EPR 3.1 3.7 Graded Approach 3.2

More information

Controlled management of a severe accident

Controlled management of a severe accident July 2015 Considerations concerning the strategy of corium retention in the reactor vessel Foreword Third-generation nuclear reactors are characterised by consideration during design of core meltdown accidents.

More information

Country Presentation. Ukraine

Country Presentation. Ukraine Country Presentation. Ukraine 25th Meeting of the IAEA Technical Working Group on Nuclear Power Plant Instrumеntation and Control (TWG -NPPIC) May 27-29, 2015,, Austria Vladimir Sklyar, RPC Radiy TOP5

More information

NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview

NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview NPP Simulators Workshop for Education - Passive PWR NPP & Simulator Overview Wilson Lam (wilson@cti-simulation.com) CTI Simulation International Corp. www.cti-simulation.com Sponsored by IAEA Modified

More information

UAE Selects Korea Electric Power Corp. Team as Prime Contractor for Peaceful Nuclear Power Program

UAE Selects Korea Electric Power Corp. Team as Prime Contractor for Peaceful Nuclear Power Program UAE Selects Korea Electric Power Corp. Team as Prime Contractor for Peaceful Nuclear Power Program 27/12/2009 - WAM - Emirates News Agency http://www.wam.ae/servlet/satellite?c=page&cid=1135099399988&pagename=

More information

LBLOCA AND DVI LINE BREAK TESTS WITH THE ATLAS INTEGRAL FACILITY

LBLOCA AND DVI LINE BREAK TESTS WITH THE ATLAS INTEGRAL FACILITY LBLOCA AND DVI LINE BREAK TESTS WITH THE ATLAS INTEGRAL FACILITY WON-PIL BAEK *, YEON-SIK KIM and KI-YONG CHOI Thermal Hydraulics Safety Research Division, Korea Atomic Energy Research Institute 1045 Daedeokdaero,

More information

Regulatory Issues and Challenges in Preparing for the Regulation of New Reactor Siting: Malaysia s Experience

Regulatory Issues and Challenges in Preparing for the Regulation of New Reactor Siting: Malaysia s Experience Regulatory Issues and Challenges in Preparing for the Regulation of New Reactor Siting: Malaysia s Experience Azlina Mohammad Jais a,b a Atomic Energy Licensing Board (AELB) Malaysia b Universiti Kebangsaan

More information

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants 2016 OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants The company is certified according to three management systems: Certificate stn en iso 9001:2008 Quality management system

More information

Current Status and Future Challenges of Innovative Reactors Development in Japan

Current Status and Future Challenges of Innovative Reactors Development in Japan Innovation for Cool Earth Forum 2017, Tokyo, Japan, October 4-5, 2017 Current Status and Future Challenges of Innovative Reactors Development in Japan 5 October, 2017 Yutaka Sagayama Assistant to the President

More information

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 Tim Beville Office of Nuclear Energy U.S. Department of Energy Administration

More information

27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs

27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 27 June 2013 Warsaw, Poland Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 1 Procurement for New Nuclear Programs Nuclear power programs risk and opportunity Supplier

More information

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC 3.10.2016 ČEZ, a. s. Meeting at IAEA Vienna Overview of topics ČEZ nuclear fleet (basic features) Systematic measures targeted to improve

More information

Belgian Stress Test Nuclear Power Plants (BEST)

Belgian Stress Test Nuclear Power Plants (BEST) Belgian Stress Test Nuclear Power Plants (BEST) 2013-08-26 TM IAEA: Belgian Stress Tests Stress Test Specifications Technical scope Initiating events Earthquake Flooding Other extreme natural events (extreme

More information

SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND

SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND Risto Sairanen Radiation and Nuclear Safety Authority (STUK) Nuclear Reactor Regulation P.O.Box 14, FI-00881

More information

Next and Last Generation of Nuclear Power Plants Paul Howarth

Next and Last Generation of Nuclear Power Plants Paul Howarth Next and Last Generation of Nuclear Power Plants Paul Howarth Exec Director, Dalton Nuclear Institute IMechE Branch Meeting Jan 2009 Order of Service Introduction to status of advanced systems The 3 contending

More information

Egyptian Nuclear Power Plant Program History and Status

Egyptian Nuclear Power Plant Program History and Status Egyptian Nuclear Power Plant Program History and Status Nuclear Power Plant Authority (NPPA) WorleyParsons Nuclear Services 1 Egyptian Nuclear Program History Milestones Establishment of Atomic Energy

More information

Countermeasures for the Falsification of Quality Verification Documents

Countermeasures for the Falsification of Quality Verification Documents Technical Meeting on Procurement Activities and on Counterfeit, Fraudulent and Substandard Items: Experiences and Lessons Learned, IAEA Headquarters, Vienna, Austria, 8-11 September 2014 Countermeasures

More information

FRANCE LWR activities

FRANCE LWR activities FRANCE LWR activities Norbert NICAISE with contributions from AREVA-NP ASN French Nuclear Safety Authority, IRSN French Institute for Radiation Protection and Nuclear Safety (TSO of ASN), CEA French Atomic

More information

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION 18th International Conference on Structural Mechanics in Reactor Technology (SMiRT 18) Beijing, China, August 7-12, 2005 SMiRT18-A01-2 DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA

More information

Small Modular Reactor Materials R&D Program Materials Coordination Webinar

Small Modular Reactor Materials R&D Program Materials Coordination Webinar Small Modular Reactor Materials R&D Program Materials Coordination Webinar William Corwin Office of Advanced Reactor Technologies U.S. Department of Energy August 2012 SMRs Are Strong Contenders to Augment

More information

FBNR Nuclear Reactor for Developing Countries

FBNR Nuclear Reactor for Developing Countries The first Arab conferfence on the prospects of nuclear Power for electricity generation and sea water desalination Hammamet Tunisia 23-25 June 2010 FBNR Nuclear Reactor for Developing Countries An innovative

More information

Non-Electric Applications of Nuclear Energy

Non-Electric Applications of Nuclear Energy Non-Electric Applications of Nuclear Energy I. Khamis Nuclear Power Technology Development Section Department of Nuclear Energy Contents Introduction An overview of current experience on nonelectric applications

More information

NEWCOMER STATES AND FINNISH SAFEGUARDS SUPPORT PROGRAMME TO THE IAEA

NEWCOMER STATES AND FINNISH SAFEGUARDS SUPPORT PROGRAMME TO THE IAEA NEWCOMER STATES AND FINNISH SAFEGUARDS SUPPORT PROGRAMME TO THE IAEA Elina Martikka 1, Tapani Honkamaa 1, Marko Hämäläinen 1, Tommi Lamminpää 2, Päivi Tuulensuu 2. 1 STUK, Helsinki, Finland, 2 TVO, Olkiluoto,

More information

EDF & the nuclear renewal : the Flamanville 3 model. Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division

EDF & the nuclear renewal : the Flamanville 3 model. Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division EDF & the nuclear renewal : the Flamanville 3 model Jean-Claude Prenez Director for International Projects EDF Nuclear Engineering Division Varna, 27-29 May 2009 Contents 1.The french context and EDF nuclear

More information

Applicability of PSA Level 2 in the Design of Nuclear Power Plants

Applicability of PSA Level 2 in the Design of Nuclear Power Plants Applicability of PSA Level 2 in the Design of Nuclear Power Plants Estelle C. SAUVAGE a, Gerben DIRKSEN b, and Thierry COYE de BRUNELLIS c a AREVA-NP SAS, Paris, France b AREVA-NP Gmbh, Erlangen, Germany

More information

Nuclear Power Development in Europe: Rosatom perspective

Nuclear Power Development in Europe: Rosatom perspective ROSATOM Nuclear Power Development in Europe: Rosatom perspective Alexey Kalinin Head, International Business, Rosatom CEO, Rusatom Overseas Platts 7 th Annual European Nuclear Conference June 25-26, 2012

More information

Technical Note OPTIMIZATION OF THE PARAMETERS OF FEEDWATER CONTROL SYSTEM FOR OPR1000 NUCLEAR POWER PLANTS

Technical Note OPTIMIZATION OF THE PARAMETERS OF FEEDWATER CONTROL SYSTEM FOR OPR1000 NUCLEAR POWER PLANTS Technical Note OPTIMIZATION OF THE PARAMETERS OF FEEDWATER CONTROL SYSTEM FOR OPR1000 NUCLEAR POWER PLANTS UNG SOO KIM *, IN HO SONG, JONG JOO SOHN and EUN KEE KIM Safety Analysis Department, KEPCO Engineering

More information

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA OKTOBER 3-6, 2016 1 ANPP * ANPP is located in the western part of Ararat valley 30 km west of Yerevan close to

More information

Updating on NPP Life Management, Long Term Operation and post-fukushima Issues in Spain

Updating on NPP Life Management, Long Term Operation and post-fukushima Issues in Spain IAEA Technical Working Group on Life Management of Nuclear Power Plants (TWG-LMNPP) Vienna, February 22-24, 2017 Updating on NPP Life Management, Long Term Operation and post-fukushima Issues in Spain

More information

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) 1.3.2016 Prof.Dr. Böck Technical University Vienna Atominstitut Stadionallee 2, 1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at

More information

IAEA HONG-KONG IAEA APPROACH ON NUCLEAR POWER INTRODUCTION

IAEA HONG-KONG IAEA APPROACH ON NUCLEAR POWER INTRODUCTION HONG-KONG APPROACH ON NUCLEAR POWER INTRODUCTION February, 2014 International Atomic Energy Agency V. NKONG-NJOCK INTRODUCTION International Atomic Energy Agency WORLD CHALLENGES - NUCLEAR OPPORTUNITIES

More information

Harmonized EUR revision E requirements corresponding to currently available technical solutions

Harmonized EUR revision E requirements corresponding to currently available technical solutions Harmonized EUR revision E requirements corresponding to currently available technical solutions Csilla TOTH - EUR Steering Committee MVM Paks II Ltd., Hungary, Technical Director IAEA International Conference

More information

Lessons from Fukushima

Lessons from Fukushima Lessons from Fukushima October 11, 2011 The Institute of Energy Economics, Japan Masakazu Toyoda, Chairman & CEO, Outline : Lessons from Fukushima 1. One NPP accident could stop other plants as well 2.

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

The risk of reactor pressure vessel material degradation Doel-3/Tihange-2

The risk of reactor pressure vessel material degradation Doel-3/Tihange-2 The risk of reactor pressure vessel material degradation Doel-3/Tihange-2 Ilse Tweer NURIS 2015, Vienna, 16-17 April 2015 Reactor pressure vessel structural integrity The reactor pressure vessel (RPV)

More information

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

U.S. and South Korean Cooperation in the World Nuclear Energy Market: Major Policy Considerations

U.S. and South Korean Cooperation in the World Nuclear Energy Market: Major Policy Considerations U.S. and South Korean Cooperation in the World Nuclear Energy Market: Major Policy Considerations Mark Holt Specialist in Energy Policy January 21, 2010 Congressional Research Service CRS Report for Congress

More information

Global Perspectives on SMRs Developing Countries Expectations

Global Perspectives on SMRs Developing Countries Expectations Global Perspectives on SMRs Developing Countries Expectations Dr Atam Rao Head Nuclear Power Technology Development Jun 18, 2010 The 4 th Annual Asia-Pacific Nuclear Energy Forum on Small and Medium Reactors

More information

Small Reactors. Cindy Klotz Facilitator Black & Veatch

Small Reactors. Cindy Klotz Facilitator Black & Veatch Small Reactors Cindy Klotz Facilitator Black & Veatch Small Modular Reactors Mark Gake, P.E. Nuclear Chief Engineer, Black & Veatch July 23, 2013 Agenda What is an SMR? SMR Advantages SMR Designs in Development

More information

Swedish action plan. for nuclear power plants

Swedish action plan. for nuclear power plants Swedish action plan for nuclear power plants Response to ENSREG s request December 2012 Page 2 (48) Abstract Following the severe accidents which started in the Fukushima Dai-ichi nuclear power plant,

More information

Ageing Management and Long Term Operation of Nuclear Power Plants

Ageing Management and Long Term Operation of Nuclear Power Plants Ageing Management and Long Term Operation of Nuclear Power Plants Senior Regulators Meeting 17 September 2015 Jan BENS AGENDA Belgian Nuclear Reactor Sites LTO Legal Framework LTO Regulatory Framework

More information

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as

More information

THE NECESSITY FOR NUCLEAR POWER

THE NECESSITY FOR NUCLEAR POWER THE NECESSITY FOR NUCLEAR POWER THE NECESSITY FOR NUCLEAR POWER Geoffrey Greenhalgh Graham & Trotman Limited First published in 1980 by Graham and Trotman Limited Bond Street House 14 Clifford Street London

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

APPROACH TO PRACTICAL ELIMINATION IN FINLAND

APPROACH TO PRACTICAL ELIMINATION IN FINLAND M-L. JÄRVINEN et al. APPROACH TO PRACTICAL ELIMINATION IN FINLAND M-L. JÄRVINEN Radiation and Nuclear Safety Authority (STUK) Helsinki, Finland Email: marja-leena.jarvinen@stuk.fi N. Lahtinen Radiation

More information

Ensuring Spent Fuel Pool Safety

Ensuring Spent Fuel Pool Safety Ensuring Spent Fuel Pool Safety Michael Weber Deputy Executive Director for Operations U.S. Nuclear Regulatory Commission American Nuclear Society Meeting June 28, 2011 1 Insights from Fukushima Nuclear

More information

High Temperature Gas-Cooled Reactors Now More Than Ever!

High Temperature Gas-Cooled Reactors Now More Than Ever! High Temperature Gas-Cooled Reactors Now More Than Ever! Dr. Finis SOUTHWORTH Chief Technology Officer AREVA Inc. On behalf of the NGNP Industrial Alliance, LLC Washington DC Section ANS Rockville, MD

More information

LIFE CYCLE MANAGEMENT OF LOVIISA NPP

LIFE CYCLE MANAGEMENT OF LOVIISA NPP LIFE CYCLE MANAGEMENT OF LOVIISA NPP Presentation at International Scientific Forum Intellectual design. Complex Engineering Product Life Cycle Management (PLM), Nizhny Novgorod, Russia, June 15th, 2011.

More information

P Boiling Water Reactor Vessel and Internals Program (BWRVIP)

P Boiling Water Reactor Vessel and Internals Program (BWRVIP) 2018 Research Portfolio P41.01.03 - Boiling Water Reactor Vessel and Internals Program (BWRVIP) Program Description As boiling water reactors (BWRs) age, various types of materials degradation mechanisms

More information

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear

More information

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director Simposyum Siting of New Nuclear Power Plants and Irradiated Fuel Facilities Buenos Aires Argentina 24-28 June 2013 Panel Fukushima Daiichi s Impact in Nuclear Power Programs Worldwide Brazilian Operator

More information

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT Z.K. Jankovsky The Ohio State University Columbus, USA Email: jankovsky.3@osu.edu

More information

SMALL MODULAR REACTORS: CONTOURS OF PROLIFERATION/SECURIT Y RISKS

SMALL MODULAR REACTORS: CONTOURS OF PROLIFERATION/SECURIT Y RISKS SMALL MODULAR REACTORS: CONTOURS OF PROLIFERATION/SECURIT Y RISKS Sharon Squassoni Director, Proliferation Prevention Program Center for Strategic & International Studies Platts 4 th Annual Small Modular

More information

Small Modular Reactors & waste management issues

Small Modular Reactors & waste management issues Small Modular Reactors & waste management issues 8 th May 2014, Bucharest International Framework For Nuclear Energy Cooperation Infrastructure development working group meeting Dan Mathers Business Leader

More information

NuScale SMR Technology

NuScale SMR Technology NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by

More information

Advanced Reactors Mission, History and Perspectives

Advanced Reactors Mission, History and Perspectives wwwinlgov Advanced Reactors Mission, History and Perspectives Phillip Finck, PhD Idaho National Laboratory Senior Scientific Advisor June 17, 2016 A Brief History 1942 CP1 First Controlled Chain Reaction

More information

EPR of Korea and International Assistance

EPR of Korea and International Assistance EPR of Korea and International Assistance Seung-Young Jeong, Ph.D k504jsy@kins.re.kr Korea Institute of Nuclear Safety (KINS) I. Nuclear Emergency Preparedness and Response of Korea 1 Status of Nuclear

More information

FOLLOW-UP TO THE FRENCH NUCLEAR POWER PLANT STRESS TESTS UPDATE OF THE ACTION PLAN OF THE FRENCH NUCLEAR SAFETY AUTHORITY (ASN) DECEMBER 2017

FOLLOW-UP TO THE FRENCH NUCLEAR POWER PLANT STRESS TESTS UPDATE OF THE ACTION PLAN OF THE FRENCH NUCLEAR SAFETY AUTHORITY (ASN) DECEMBER 2017 43 FOLLOW-UP TO THE FRENCH NUCLEAR POWER PLANT STRESS TESTS UPDATE OF THE ACTION PLAN OF THE FRENCH NUCLEAR SAFETY AUTHORITY (ASN) DECEMBER 2017 UPDATED NATIONAL ACTION PLAN OF THE FRENCH NUCLEAR SAFETY

More information

German Energy Policy: Reactions after the Fukushima Accident ( Energiewende )

German Energy Policy: Reactions after the Fukushima Accident ( Energiewende ) German Energy Policy: Reactions after the Fukushima Accident ( Energiewende ) - Energiewende & Nuclear Phase-out (NPo) - Energy consume & Energy mix - Consequences of the NPo - Self-imposed goals & EC-goals

More information

Small Scale Nuclear Power: an Option for Alaska? Gwen Holdmann, Director

Small Scale Nuclear Power: an Option for Alaska? Gwen Holdmann, Director Small Scale Nuclear Power: an Option for Alaska? Gwen Holdmann, Director Alaska Center for Energy and Power University of Alaska History Overview of of Nuclear Presentation Energy What is nuclear energy?

More information

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA Integrity Study of Spent PWR Fuel under Dry Storage Conditions 14236 Jongwon Choi *, Young-Chul Choi *, Dong-Hak Kook * * Korea Atomic Energy Research Institute ABSTRACT Technical issues related to long-term

More information

Contribution of Industry to NPP Performances

Contribution of Industry to NPP Performances Nuclear power : Performance and long term operation Contribution of Industry to NPP Performances Dominique MOUILLOT CEO ONET Technologies WIN France Chairperson Contribution of Industry to NPP Performances

More information

Design Safety Considerations for Water-cooled Small Modular Reactors As reported in IAEA-TECDOC-1785, published in March 2016

Design Safety Considerations for Water-cooled Small Modular Reactors As reported in IAEA-TECDOC-1785, published in March 2016 International Conference on Topical Issues in Nuclear Installation Safety, Safety Demonstration of Advanced Water Cooled Nuclear Power Plants 6 9 June 2017 Design Safety Considerations for Water-cooled

More information

Small Modular Reactors

Small Modular Reactors Small Modular Reactors Nuclear Institute Joint Nuclear Energy CDT Event, York University, 24 May 2017 Kevin Hesketh Senior Research Fellow Scope To highlight generic design issues from SMRs But not to

More information

DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM. Yujie DONG INET, Tsinghua University, China January 24, 2018

DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM. Yujie DONG INET, Tsinghua University, China January 24, 2018 DESIGN, SAFETY FEATURES & PROGRESS OF HTR-PM Yujie DONG INET, Tsinghua University, China January 24, 2018 Meet the Presenter Dr. Dong is a Professor in Nuclear Engineering at the Tsinghua University, Beijing,

More information

Nuclear Power Economics and Markets

Nuclear Power Economics and Markets Nuclear Power Economics and Markets IBC - Decommissioning of Nuclear Reactors & Materials 29 30 September 2014; Miami, Florida Edward Kee Disclaimer The NECG slides that follow are not a complete record

More information

OSART Good Practices OPERATIONAL EXPERIENCE FEEDBACK Utilization and dissemination of operating experience

OSART Good Practices OPERATIONAL EXPERIENCE FEEDBACK Utilization and dissemination of operating experience OSART Good Practices OPERATIONAL EXPERIENCE FEEDBACK Utilization and dissemination of operating experience St. Laurent, France Mission Date; 27 Nov.-14 Dec., 2006 Operational experience during outages

More information

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES JOON-EON YANG Integrated Safety Assessment Division, Korea Atomic Energy Research Institute, Daedeok-daero 989-111,

More information

Developing Competencies for Nuclear Safe Operation. October 2015

Developing Competencies for Nuclear Safe Operation. October 2015 Developing Competencies for Nuclear Safe Operation October 2015 Content 1. Introduction to Tecnatom Group 2. Relevant Current Activities in Training 3. The Elements in Developing Competencies for Safe

More information

Thermal Hydraulic Simulations of the Angra 2 PWR

Thermal Hydraulic Simulations of the Angra 2 PWR Thermal Hydraulic Simulations of the Angra 2 PWR Javier González-Mantecón, Antonella Lombardi Costa, Maria Auxiliadora Fortini Veloso, Claubia Pereira, Patrícia Amélia de Lima Reis, Adolfo Romero Hamers,

More information

Risks of Nuclear Ageing

Risks of Nuclear Ageing Risks of Nuclear Ageing Technical characteristics of ageing processes and their possible impacts on nuclear safety in Spain S. Mohr, S. Kurth Greenpeace, Valencia, November 2014 Age of European NPPs (grid

More information

ICEM DEVELOPMENT OF THE ENVI SIMULATOR TO ESTIMATE KOREAN SNF FLOW AND ITS COST

ICEM DEVELOPMENT OF THE ENVI SIMULATOR TO ESTIMATE KOREAN SNF FLOW AND ITS COST Proceedings of the 12 th International Conference on Environmental Remediation And Radioactive Waste Management ICEM 2009 October 11-15, 2009, Liverpool, England, UK ICEM 2009 16060 DEVELOPMENT OF THE

More information

Corporate Presentation 2017

Corporate Presentation 2017 2017 1 Company Milestones COMPANY FOUNDATION ZORITA NPP PROGRAM STARTS DEVELOPMENT OF SPANISH NPP PROGRAM TECHNOLOGICAL INDEPENDENCE ACHIEVED TECNATOM AS INTERNATIONAL GROUP 1957 1962 70 s 80 s 2010 s

More information

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT DESIGN ASSESSMENT AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT 10/2016 Stephen J Walls, EDF Energy Nuclear New Build 1 Olivier Bard, EDF HINKLEY POINT C (HPC) 2 HPC Financial Investment

More information

COUPLING A HYDROGEN PRODUCTION PROCESS TO A NUCLEAR REACTOR

COUPLING A HYDROGEN PRODUCTION PROCESS TO A NUCLEAR REACTOR COUPLING A HYDROGEN PRODUCTION PROCESS TO A NUCLEAR REACTOR P. Anzieu, P. Aujollet, D. Barbier, A. Bassi, F. Bertrand, A. Le Duigou, J. Leybros, G. Rodriguez CEA, France NEA 3 rd Meeting on Nuclear Production

More information

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis Verification of the Code Against SCDAP/RELAP5 for Severe Accident Analysis Jennifer Johnson COLBERT 1* and Karen VIEROW 2 1 School of Nuclear Engineering, Purdue University, West Lafayette, Indiana 47907-2017,

More information

RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING

RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Science and Technology Journal of BgNS, Vol. 8, 1, September 2003, ISSN 1310-8727 RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Pavlin P. Groudev, Rositsa V. Gencheva,

More information