Decision Criteria from Estimated Financial Impacts IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005

Size: px
Start display at page:

Download "Decision Criteria from Estimated Financial Impacts IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005"

Transcription

1 Decision Criteria from Estimated Financial Impacts 2005 IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005

2 Resource Option Workshops 1st meeting (Dec 7) Introduction / Process of input / feedback 2nd meeting (March 8 and 9) Sessions on: Financial Demand Side Management Environmental Attributes Planning Criteria 3rd meeting (May 27) Provide opportunity to ask clarifying questions on Draft ROR before providing comments Meetings have also been held with various Resource Proponents to review technologies May 31/June 1, 2005 Page 2

3 UEC/UCC & Portfolios May 31/June 1, 2005 Page 3

4 Objectives Ensure consistent representation of projects IPP projects vs. BC Hydro projects IPP #1 vs. IPP#2 IPP technology #1 vs. IPP technology #2 Compare resources based on their cost Simplify the economic analysis Use a simplified, transparent approach to greatest extent possible Avoid undue precision, recognizing degree of uncertainty in calculations May 31/June 1, 2005 Page 4

5 Issues and Where we landed Discount rate / Pre-tax vs. post-tax approaches Project vs. contract life Corporate overhead Provincial transfers Subsidies Gas and electricity price Real pre-tax discount rates of 6 & 8% Project life Excluded Included as costs Excluded Representative values used UEC/UCC s calculated for ROR; portfolio analysis will use range of current forecasts May 31/June 1, 2005 Page 5

6 ROR Summary for Small Hydro - Supply Curves UEC - Sigma Inventory UEC - RFEI and submitted by IPPs UEC - Knight Piesold database UEC - Bundles $115 $105 Unit Energy Cost ($/MWh in 2005$) $95 $85 $75 $65 $55 $45 $35 $ Average Annual Energy (GWh) May 31/June 1, 2005 Page 6

7 ROR Summary for Large Hydro Generic large hydro potential is represented by the only project currently under investigation, Peace River Site C: 900 MW with average annual energy of 4600 GWh Unit energy cost of $42.5/MW (based on 3 units operating after 9 years. Energy Resource Smart opportunities provide 300 GWh: Example projects include redevelopment of existing facilities and turbine upgrades. These projects generally do not proceed if the unit energy cost is above $55/MW. May 31/June 1, 2005 Page 7

8 ROR Summary for Biomass Biomass Supply Curve (for the three bundles) May 31/June 1, 2005 Page 8

9 ROR Summary for Geothermal Projects: Generic geothermal potential is represented by the South Meager Geothermal Project, as it is the only project currently verifying the resource potential: Initial phase is 100 MW with average annual energy of 800 GWh. The report calculates the unit energy cost at $47/MW, but Western Geopower Corp. indicates the UEC may be closer to $55/MW. Potential for a second phase of 100 MW for a total of 200 MW. May 31/June 1, 2005 Page 9

10 ROR Summary for Wind Supply curves: Wind Resource Option Energy Supply Curves by Region 175 Unit Energy Cost ($/MWh) North Coast - Offshore North Coast - Onshore Peace Region Vancouver Island Average Annual Energy (GWh) May 31/June 1, 2005 Page 10

11 ROR Summary for Natural Gas Projects Generic 47 MW SCGT Generic 500 MW CCGT Generic 250 MW CCGT Generic 60 MW CCGT Generic 10 MW gas cogen Capacity/Energy Average Unit Cost of Energy* ($/MWh) Primarily capacity $ 115 Both capacity and energy Both capacity and energy Both capacity and energy Both capacity and energy $ 56 $ 59 $ 71 $ 68 * Costs are at-site costs and before transmission, losses and environmental attributes are considered May 31/June 1, 2005 Page 11

12 ROR Summary for Coal Projects: 500MW supercritical single unit plant: $1.06B capital includes allowances for transmission interconnection, water supply, mitigation/compensation O&M: $11/kWh; Fuel: $11/MWh based on mine-mouth generation plant UEC: 8% 250MW IGCC single unit plant: gasify coal as fuel for combined cycle GT capital cost 15% over supercritical and variable O&M 50% higher UEC: $51/MWh@6%; $58/MWh@ 8% May 31/June 1, 2005 Page 12

13 ROR Summary for DSM Energy Efficiency Supply Curve May 31/June 1, 2005 Page 13

14 ROR Summary Conclusions Energy Supply Curves for Generic Bundles 175 Unit Energy Cost ($/MWh) Average Annual Energy (GWh) Small and Micro Hydro Medium Hydro Large Hydro Power Smart Natural Gas (Resource Smart) Natural Gas Coal Wind Geothermal Biomass Resource availability of coal and natural gas is not a constraint for generation within the province during the planning period. May 31/June 1, 2005 Page 14

15 ROR Summary Conclusions Energy Supply Curves for Capacity and Future Resource Options 175 Unit Energy Cost ($/MWh) Solar Unit Energy Cost is $697/MWh for the first 104 GWh and $1565/MWh for the next 280 GWh. Fuel Cell Supply Curve is not shown due to a very small average annual energy of 51 GWh and a unit energy cost up to $107/MW. Large Hydro: Future Coal: Future Geothermal: Future Wave: Future Tidal: Future Solar: Net Metering Average Annual Energy (GWh) Resource availability of coal is not a constraint for generation within the province during the planning period. May 31/June 1, 2005 Page 15

16 Accuracy of Estimates Commission suggested range of +/- 35% for specific projects Greater for generic resources Range captured in Cost Uncertainty Low = -10% to +20% Medium = -10% to +40% High = -10% to +60% Generally agreed to by project proponents Subject to further review with Commission May 31/June 1, 2005 Page 16

17 How to translate nominal post-tax discount rate to real pre-tax discount rate Assumptions: 18.73% effective tax rate (based on capital structure, debt cost, debt repayment schedule and CCA available and used) 2.0% annual inflation rate At 6.95% nominal post-tax discount rate 6.95%/( ) = 8.55% nominal pre-tax discount rate; and ( )/ = 6.42% real pre-tax discount rate May 31/June 1, 2005 Page 17

18 Comparison of Unit Energy Cost using pre-tax and post-tax calculation methods Example: small hydro project with capital cost of $40M Effective tax rate Nominal Post-tax discount rate Real Pretax discount rate Debt repayment year Energy Project life Capability year GWh/yr UEC $/MWh Post-tax after tax 12% ROE 18.73% 6.95% $56 Pre-tax simplified approach 6.42% $52 Post-tax tax 15% ROE 20.09% 7.48% $60 Pre-tax simplified approach 7.21% $56 6% pretax real = 50$/MWh 8% pretax real = 59$/MWh May 31/June 1, 2005 Page 18

19 Annualized capital cost calculation Mathematical formula = (A*i)/(1-1/(1+i)^n) where A is the capital cost including IDC in real $ i is the real pre-tax discount rate n is the project life Can use Payment Function in Excel: PMT( rate =i, number of periods = n, present value =A) May 31/June 1, 2005 Page 19

PIEPC Meeting #1. Resource Options 3:30-5:00

PIEPC Meeting #1. Resource Options 3:30-5:00 PIEPC Meeting #1 Resource Options 3:30-5:00 Agenda for Resource Options Resource Types Proposed method to development generic resource blocks Review attributes 3/30/05 Page 2 Changes in Energy Planning

More information

2005 Integrated Electricity Plan

2005 Integrated Electricity Plan 2005 Integrated Electricity Plan Regional Workshops Round 1 Kitimat February 22, 2005 Workshop Objectives To provide a forum to learn, share and express regional preferences about future energy options

More information

Name: Wayne Peppard Organization: Allied Hydro Council Date: October 10, Subject: AHC Site C Technical Presentation

Name: Wayne Peppard Organization: Allied Hydro Council Date: October 10, Subject: AHC Site C Technical Presentation Name: Wayne Peppard Organization: Allied Hydro Council Date: October 10, 2017 24-2 Subject: AHC Site C Technical Presentation British Columbia Utilities Commission Suite 410, 900 Howe Street Vancouver,

More information

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005 2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability

More information

2008 LTAP Resource Options Update. Results Session December 4, 2007

2008 LTAP Resource Options Update. Results Session December 4, 2007 2008 LTAP Resource Options Update Results Session December 4, 2007 AGENDA 9:00 Welcome 9:10 Context Setting 9:30 ROU Results Biomass Natural Gas Coal 10:15 Coffee Break 10:30 ROU Results continued Geothermal

More information

2005 Integrated Electricity Plan Modelling Approach IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005

2005 Integrated Electricity Plan Modelling Approach IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005 2005 Integrated Electricity Plan Modelling Approach 2005 IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005 IEP Road Map Part 2 Key Input Assumptions Part 1 Planning Objectives and Principles

More information

RESOURCE OPTIONS UPDATE RESULTS SUMMARY. October 2016

RESOURCE OPTIONS UPDATE RESULTS SUMMARY. October 2016 RESOURCE OPTIONS UPDATE RESULTS SUMMARY October 2016 BACKGROUND & OBJECTIVES This slide deck summarizes the process and results of the Resource Options Update that BC Hydro undertook in 2014 2015. The

More information

Canada-China Clean Energy Initiative & Annual Workshop

Canada-China Clean Energy Initiative & Annual Workshop The 2060 Project: Energy Pathways for BC and Canada Estimating an Idealized Carbon Tax Via Dispatch Protocols Amy Sopinka Ariane Ouellette Lawrence Pitt June 18 th, 2014 Canada-China Clean Energy Initiative

More information

Review of BC Hydro s Alternatives Assessment Methodology

Review of BC Hydro s Alternatives Assessment Methodology Review of BC Hydro s Alternatives Assessment Methodology Prepared for BC Hydro September 23, 2014 AUTHORS Rachel Wilson Bruce Biewald David White 485 Massachusetts Avenue, Suite 2 Cambridge, Massachusetts

More information

2005 Integrated Electricity Plan

2005 Integrated Electricity Plan 2005 Integrated Electricity Plan Regional Workshops Round 1 Victoria February 25, 2005 Introductions. Please introduce yourself. Name Affiliation, if any Identify 1 interest area regarding the Integrated

More information

2005 Integrated Electricity Planning (IEP) Regional Information Sessions Fall 2005

2005 Integrated Electricity Planning (IEP) Regional Information Sessions Fall 2005 2005 Integrated Electricity Planning (IEP) Regional Information Sessions Fall 2005 Introduction and Agenda What is an Integrated Electricity Plan and why are we doing one? How are we getting input on the

More information

BCUC INQUIRY RESPECTING SITE C A-26

BCUC INQUIRY RESPECTING SITE C A-26 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 November 16, 2017 BCUC

More information

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans ENTERGY GULF STATES LOUISIANA, L.L.C. & ENTERGY LOUISIANA, LLC LPSC DOCKET NO. I-33014 DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans This version

More information

INVITATION TO ATTEND AN INFORMATION SESSION ABOUT BC HYDRO S 2004 INTEGRATED ELECTRICITY PLAN REVISED DATE: DEC. 9 REVISED LOCATION: BAYSHORE HOTEL

INVITATION TO ATTEND AN INFORMATION SESSION ABOUT BC HYDRO S 2004 INTEGRATED ELECTRICITY PLAN REVISED DATE: DEC. 9 REVISED LOCATION: BAYSHORE HOTEL INVITATION TO ATTEND AN INFORMATION SESSION ABOUT BC HYDRO S 2004 INTEGRATED ELECTRICITY PLAN REVISED DATE: DEC. 9 REVISED LOCATION: BAYSHORE HOTEL IPPBC members are invited to attend an information session

More information

Generation Technology Assessment & Production Cost Analysis

Generation Technology Assessment & Production Cost Analysis SPO Planning Analysis Generation Technology Assessment & Production Cost Analysis EAI Stakeholder Meeting July 31, 212 Technology Life Cycle Technology Deployment Over Time Conceptual Research & Development

More information

Energy Supply Costs. BCUC Workshop

Energy Supply Costs. BCUC Workshop Energy Supply Costs BCUC Workshop 15 January 2004 Outline Electricity Planning/Supply Requirements Context Approach to Planning for New Supply Cost Versus Risk Management Projected Electricity Demand/Supply

More information

2015 PWP Power IRP Update Exhibit 7

2015 PWP Power IRP Update Exhibit 7 2015 PWP Power IRP Update Exhibit 7 Key Assumptions and Analysis Progress Toward 2012 IRP Recommendations Recommendation Target Status Renewable Energy: RPS Renewable Energy: Local Solar 40% by 2020; Meet/exceed

More information

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE March 12, 2015 THE INTEGRATED RESOURCE PLAN Every 3-5 years BC Hydro develops a flexible, long-term strategic plan

More information

Meeting held November 8, 2005 at the Coast Bastion Inn in Nanaimo Page 1 of 6

Meeting held November 8, 2005 at the Coast Bastion Inn in Nanaimo Page 1 of 6 Meeting Date and Location November 8, 2005 Coast Bastion Inn 11 Bastion Street, Nanaimo, B.C. 6:30 p.m. 8:30 p.m. Attendees and Interests Name Interest/Organization J. R. Young Gabriola Ratepayers Ed Thompson

More information

2011 IRP Public Input Meeting. December 15, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. December 15, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting December 15, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda 2011 IRP schedule update and next steps Resource portfolio development status Supply Side Resources

More information

Integrated Electricity Plan (IEP) 2005 Technical Resource Option Workshop #3 Review of Resource Options Report - May 27, 2005 Final Meeting Notes

Integrated Electricity Plan (IEP) 2005 Technical Resource Option Workshop #3 Review of Resource Options Report - May 27, 2005 Final Meeting Notes ATTENDEES (in alphabetical order by organization of person) Name Juergen Puetter TJ Schur Don Timlick Paul Kan Ron Sanderson Rama Vinnakota Nick Andrews Ron Zeilstra Adam Lewis David Newlands Peter Besenovsky

More information

at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning

at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning Integrated t Resource Planning at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning Today s agenda 1. Our system 2. Integrated Resource Plan 3. Looking forward Our system Generation

More information

Regional IEP Meeting 2nd round. Fall 2005

Regional IEP Meeting 2nd round. Fall 2005 Regional IEP Meeting 2nd round Fall 2005 Introduction and Agenda Why are we doing an Integrated Electricity Plan (IEP)? 15 min What has BC Hydro heard in the process? 30 min Five key questions for long-term

More information

ENTERGY NEW ORLEANS 2015 IRP RENEWABLES TECHNICAL CONFERENCE

ENTERGY NEW ORLEANS 2015 IRP RENEWABLES TECHNICAL CONFERENCE ENTERGY NEW ORLEANS 2015 IRP RENEWABLES TECHNICAL CONFERENCE Technology, Cost and Regulation of CO 2 SEPTEMBER 22, 2014 Note: All IRP materials presented here are marked preliminary subject to change prior

More information

2.1 Discuss the accuracy of BC Hydro load forecasts and what appear to be significant variations between forecast and actual loads.

2.1 Discuss the accuracy of BC Hydro load forecasts and what appear to be significant variations between forecast and actual loads. REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 1 TO: BRITISH COLUMBIA HYDRO & POWER AUTHORITY DATE: June 5, 2006 PROJECT NO: 3698419 APPLICATION NAME: BCH 2006

More information

FortisBC Resource Planning Community Stakeholder Workshop

FortisBC Resource Planning Community Stakeholder Workshop FortisBC Resource Planning Community Stakeholder Workshop Long Term Resource Planning October 2015 Workshop Objectives 1. Obtain feedback on Long Term Resource Planning issues 2. Provide a better understanding

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 8

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 8 TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 8 From: Date: Subject: Staff February 20, 2009 Council Meeting Report on Florida Renewable Energy Potential

More information

Changing energy infrastructure and the potential role of new forms of energy storage

Changing energy infrastructure and the potential role of new forms of energy storage Changing energy infrastructure and the potential role of new forms of energy storage Mike Colechin 2013 Energy Technologies Institute LLP The information in this document is the property of Energy Technologies

More information

Solar Specifications Progress Report. Solar Subgroup Lead Jeremy Webb

Solar Specifications Progress Report. Solar Subgroup Lead Jeremy Webb Solar Specifications Progress Report Solar Subgroup Lead Jeremy Webb Progress to date 7 th Session of the EGRC May: Work begins on establishing the Solar Subgroup August: Solar Subgroup established and

More information

INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID

INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID CEYLON ELECTRICITY BOARD INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID 2018-2028 Dr. H.M Wijekoon Chief Engineer (Transmission Planning) Randika Wijekoon Electrical Engineer (Generation

More information

Watt About Energy in the Northwest

Watt About Energy in the Northwest Watt About Energy in the Northwest WSU Whatcom County Carbon Masters Course Nancy Hirsh NW Energy Coalition November 3, 2011 Nancy@nwenergy.org nwenergy.org Turn of the Century Extraction economy Timber

More information

New Jersey s Clean Energy Program

New Jersey s Clean Energy Program New Jersey s Clean Energy Program Municipal Technical Training Fundamentals June 11 & 25, 2008 Mark Valori Renewable Energy Technical Director Market Management Team Agenda Presentation Overview Usage

More information

Renewable Energy Economics and Technology Status - Program 84

Renewable Energy Economics and Technology Status - Program 84 Renewable Energy Economics and Technology Status - Program 84 Program Description Program Overview Renewable energy is fundamentally changing the electricity industry's strategic landscape. Active industry

More information

ECONOMICS OF ELECTRICITY GENERATION

ECONOMICS OF ELECTRICITY GENERATION ECONOMICS OF ELECTRICITY GENERATION dr. Péter Kaderják Director, REKK NARUC Training on Tariff Development and Utility Regulation May 7-11, 2007, Baku, Azerbaijan OUTLINE Costs of generation Demand for

More information

JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES

JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES ENERGY TRANSPARENCY 2013 ALI IZADI 20 JUNE 2013 /// Energy / / Transparency, Tokyo, / / 20 / June / / 2013 / / / 1 JAPAN ELECTRICITY CONSUMPTION INTENSITY

More information

Impact of Regional Greenhouse Gas Initiative and Renewable Portfolio Standards on Power System Planning

Impact of Regional Greenhouse Gas Initiative and Renewable Portfolio Standards on Power System Planning Impact of Regional Greenhouse Gas Initiative and Renewable Portfolio Standards on Power System Planning Panel on Impacts of GHG Programs and Markets on the Power Industry PESGM2006 Montreal June 21, 2006

More information

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013 GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 213 FACT PACK GUY TURNER HEAD OF ECONOMICS AND COMMODITIES APRIL 22, 213 PRESENTATION TITLE, DAY MONTH YEAR 1 INTRODUCTION This year s Global Renewable Energy Market

More information

Energy-Environment Relationship: How Much Does Environmental Regulation Affect Investment in Energy Infrastructure?

Energy-Environment Relationship: How Much Does Environmental Regulation Affect Investment in Energy Infrastructure? Energy-Environment Relationship: How Much Does Environmental Regulation Affect Investment in Energy Infrastructure? Marji Philips PSEG Energy Resources & Trade LLC 973-430-6893 Marji.philips@pseg.com I

More information

Resource Options Update Technical Engagement Summary

Resource Options Update Technical Engagement Summary Resource Options Update Technical Engagement Summary 2014 2015 1.0 Overview of the Engagement Process A key input into BC Hydro s long-term planning process is our inventory of electricity generation options

More information

MTEP18 Futures. Planning Advisory Committee June 14, 2017

MTEP18 Futures. Planning Advisory Committee June 14, 2017 MTEP18 Futures Planning Advisory Committee June 14, 2017 Overview Objective: Present final MTEP18 Futures and an overview of stakeholder feedback Key Takeaways: Four Futures to be used in MTEP18 to consider

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project June 2015 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286 TABLE

More information

Using PLEXOS to Validate TIMES

Using PLEXOS to Validate TIMES Using PLEXOS to Validate TIMES Paul Deane and Alessandro Chiodi Sustainable Energy Research Group, Environmental Research Institute University College Cork, Cork, Ireland ETSAP workshop, Cork, Ireland

More information

PacifiCorp s 2017 Integrated Resource Plan Update. Public Utility Commission of Oregon Public Meeting - July 3, 2018

PacifiCorp s 2017 Integrated Resource Plan Update. Public Utility Commission of Oregon Public Meeting - July 3, 2018 PacifiCorp s 2017 Integrated Resource Plan Update Public Utility Commission of Oregon Public Meeting - July 3, 2018 2017 IRP Update Highlights Energy Vision 2020 projects updated with the latest cost-and-performance

More information

Nuclear Powers Illinois. Reliable Energy, Jobs, and Clean Air for Illinois

Nuclear Powers Illinois. Reliable Energy, Jobs, and Clean Air for Illinois Nuclear Powers Illinois Reliable Energy, Jobs, and Clean Air for Illinois About Exelon Generation Competitive Energy Sales Transmission and Delivery One of the largest U.S. competitive power generators

More information

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008 ALL ISLAND GRID STUDY STUDY OVERVIEW January 2008 1 Study Overview The All Island Grid Study is the first comprehensive assessment of the ability of the electrical power system and, as part of that, the

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project March 2018 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286

More information

Integrated Resource Plan First Nations Workshop. March 7, 2011 Coast Canadian Inn Kamloops B.C.

Integrated Resource Plan First Nations Workshop. March 7, 2011 Coast Canadian Inn Kamloops B.C. Integrated Resource Plan First Nations Workshop March 7, 2011 Coast Canadian Inn Kamloops B.C. Welcome & Introductory Remarks Dan George INDEPENDENT/NEUTRAL FACILITATOR The role of Four Directions Management

More information

Towards a sustainable Romanian energy sector: Roadmap to RES in 2030 Deloitte Romania, June 2018

Towards a sustainable Romanian energy sector: Roadmap to RES in 2030 Deloitte Romania, June 2018 Towards a sustainable Romanian energy sector: Roadmap to RES in 2030 Deloitte Romania, June 2018 Content Background 03 1. Development scenarios 04 2. Impact & benefits 09 Key messages 12 2 Background Romania

More information

Heat and the Smart Energy System

Heat and the Smart Energy System Heat and the Smart Energy System Jeff Douglas Energy Technologies Institute Heat and the Smart Energy System 1. Why is Heat Important? 2. Meeting National Emissions Targets 3. Developing Power Networks

More information

Clean Flexible Power using H2 Storage

Clean Flexible Power using H2 Storage Clean Flexible Power using H2 Storage Den Gammer, New Energy Forum, 17/07/14 2013 Energy Technologies Institute LLP The information in this document is the property of Energy Technologies Institute LLP

More information

CCA is a public-private mix

CCA is a public-private mix Community Choice Aggregation in Marin CCA is a public-private mix IOU CCA (investor-owned utility/pg&e) Public Utility (municipal utility like SMUD) IOU Purchases Power IOU Maintains Transmission Lines

More information

Energy Technology Roadmaps: Data Analysis and Modelling. Energy technology roadmaps

Energy Technology Roadmaps: Data Analysis and Modelling. Energy technology roadmaps Energy Technology Roadmaps: Data Analysis and Modelling Overview Energy Technology Perspectives 2012 and Roadmap goals Data and analysis activities Baseline data Analysis of future scenarios for energy

More information

UK Future Energy Scenarios. Richard Smith Future Transmission Networks Manager

UK Future Energy Scenarios. Richard Smith Future Transmission Networks Manager UK Future Energy Scenarios Richard Smith Future Transmission Networks Manager January 2012 Cautionary Statement This presentation contains certain statements that are neither reported financial results

More information

Southern California Edison Approach to Renewable Integration June 7, 2011

Southern California Edison Approach to Renewable Integration June 7, 2011 Southern California Edison Approach to Renewable Integration June 7, 2011 Page: 0 SCE s 2010 Resource Mix Natural Gas All Resources 100% = 75 billion kwh/yr Renewable Resources 100% = 14.5 billion kwh/yr

More information

Proposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman

Proposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman Proposed Work Plan for Seventh Plan Development October 2, 2014 GRAC Tom Eckman Council s Analytical Process Flow Load Forecast Model Load Forecast Range (without efficiency) Regional Portfolio Model Data

More information

L A Z A R D ' S L E V E L I Z E D C O S T O F E N E R G Y A N A L Y S I S V E R S I O N 7. 0

L A Z A R D ' S L E V E L I Z E D C O S T O F E N E R G Y A N A L Y S I S V E R S I O N 7. 0 C O N F I D E N T I A L A U G U S T 2 0 1 3 L A Z A R D ' S L E V E L I Z E D C O S T O F E N E R G Y A N A L Y S I S V E R S I O N 7. 0 Introduction Lazard s Levelized Cost of Energy Analysis ( LCOE )

More information

Methodology for calculating subsidies to renewables

Methodology for calculating subsidies to renewables 1 Introduction Each of the World Energy Outlook scenarios envisages growth in the use of renewable energy sources over the Outlook period. World Energy Outlook 2012 includes estimates of the subsidies

More information

INTEGRATED RESOURCE PLAN TECHNICAL ADVISORY COMMITTEE MEETING #5 DAY 2

INTEGRATED RESOURCE PLAN TECHNICAL ADVISORY COMMITTEE MEETING #5 DAY 2 INTEGRATED RESOURCE PLAN TECHNICAL ADVISORY COMMITTEE MEETING #5 DAY 2 Preliminary Analysis and Results for TAC Input February 28 & 29, 2012 IRP TAC MTG #5: February 28 & 29, 2012 Preliminary Analysis

More information

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY 1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY Prof. Michael W. Golay Nuclear Engineering Dept. 1 Energy Supply, Demand, and Storage Planning The Example of Electricity PRESENTATION

More information

Additional Information on the IRP Study. City Commission Meeting 12/6/06

Additional Information on the IRP Study. City Commission Meeting 12/6/06 Additional Information on the IRP Study City Commission Meeting 12/6/06 Today s Presentation Review of IGCC information Financial Analysis of IRP Cases Summary of Additional Study Issues Options for Study

More information

Electricity Technology Options Assessment Guide (ETOAG)

Electricity Technology Options Assessment Guide (ETOAG) Electricity Technology Options Assessment Guide (ETOAG) ETOAG Report World Bank Washington D.C. June 2012 CHUBU ELECTRIC POWER CO. INC. ECONOMIC CONSULTING ASSOCIATES LIMITED Outline 1. Background 2. Purpose

More information

INTEGRATED ELECTRICITY PLAN

INTEGRATED ELECTRICITY PLAN January 2000 INTEGRATED ELECTRICITY PLAN An Update to the 1995 IEP Table of Contents Executive Summary I Chapter 1: Introduction 1 1.1 SCOPE 1 1.2 PLANNING CONTEXT AND RECENT DEVELOPMENTS 1 1.2.1 Electricity

More information

Procurement Under GHG Regulation

Procurement Under GHG Regulation Procurement Under GHG Regulation Pedro J. Pizarro Senior Vice President, Power Procurement Southern California Edison IEP Annual Meeting September 25, 2007 Existing GHG-Related Procurement Rules Loading

More information

UK Generation. BAML lunch - 29 th March Alison Kay Commercial Director Transmission

UK Generation. BAML lunch - 29 th March Alison Kay Commercial Director Transmission UK Generation BAML lunch - 29 th March 2012 Alison Kay Commercial Director Transmission Cautionary statement This presentation contains certain statements that are neither reported financial results nor

More information

CAISO s Plan for Integration of Renewable Resources

CAISO s Plan for Integration of Renewable Resources CAISO s Plan for Integration of Renewable Resources July 21, 2008 CEC 33% Renewables Workshop Presented by David Hawkins Program Tracks 2008-9 CAISO Work Plan Track 1 - Develop Operational Tools Wind and

More information

New England States Committee on Electricity

New England States Committee on Electricity Renewable and Clean Mechanisms 2.0 Study Phase I: Scenario Analysis Winter 2017 New England States Committee on Electricity Overview Context Analytical Approach and Modeling Assumptions Scenario Analysis

More information

Integrated Energy Challenge

Integrated Energy Challenge Integrated Energy Challenge Energy System Overview Transition Challenges 9 December 214 Jeff Douglas Energy Technologies Institute 214 Energy Technologies Institute LLP The information in this document

More information

BC Hydro Renewable Generation Market Competitiveness Report

BC Hydro Renewable Generation Market Competitiveness Report BUILDING A WORLD OF DIFFERENCE BC Hydro FINAL REPORT B&V Project Number: 172047 July 2011 Black & Veatch Corporation 11401 Lamar Avenue Overland Park, Kansas 66211 Tel: (913) 458 2000 www.bv.com Table

More information

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005 2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005 2005 IEP Objectives Means Objectives Ends (Fundamental) Objectives Agenda Items No net imports

More information

INTEGRATED RESOURCE PLAN TECHNICAL ADVISORY COMMITTEE MEETING #7. September 23, 2013

INTEGRATED RESOURCE PLAN TECHNICAL ADVISORY COMMITTEE MEETING #7. September 23, 2013 INTEGRATED RESOURCE PLAN TECHNICAL ADVISORY COMMITTEE MEETING #7 September 23, 2013 1 TAC MEETING OBJECTIVES To introduce the draft plan, provide clarifications and promote understanding in preparation

More information

TECHNICAL AND ECONOMIC ANALYSIS OF THE EUROPEAN ELECTRICITY SYSTEM WITH 60% RES EDF R&D

TECHNICAL AND ECONOMIC ANALYSIS OF THE EUROPEAN ELECTRICITY SYSTEM WITH 60% RES EDF R&D TECHNICAL AND ECONOMIC ANALYSIS OF THE EUROPEAN ELECTRICITY SYSTEM WITH 60% RES EDF R&D Strasbourg, 13 Septembre 2016 1 The study: how can we integrate «a lot of RES» in power systems? 60 % RES (generation)

More information

Financing Future Power Supply October 4, 2004 Peter Kind

Financing Future Power Supply October 4, 2004 Peter Kind CPUC Installed Capacity Conference Financing Future Power Supply October 4, 2004 Peter Kind Key Questions What are we doing to address fuel diversity/energy independence? Do Least Cost Plans result in

More information

100% Renewable Electricity Generation in France?

100% Renewable Electricity Generation in France? 100% Renewable Electricity Generation in France? Key lessons Decarbonisation Workshop, Berlin Christopher Andrey 9 November 2015 www.artelys.com AGENDA 1. The research question 2. The French context 3.

More information

Trends in Clean Energy Investment

Trends in Clean Energy Investment Trends in Clean Energy Investment Madrid 31 st January 212 Guy Turner Director, Bloomberg New Energy Finance /// MICHAEL / / / LIEBREICH / / / SUMMIT / / / KEYNOTE, / / / 5 / APRIL / / 211 / / / 1 CONTENTS

More information

Cost of Service and Public Policy. Ted Kury Director of Energy Studies, PURC

Cost of Service and Public Policy. Ted Kury Director of Energy Studies, PURC Cost of Service and Public Policy Ted Kury Director of Energy Studies, PURC ted.kury@warrington.ufl.edu Session Overview Improving Utility Sector Performance Costs to Provide Service Uniform System of

More information

September 13, Dr. Harry Swain Joint Review Panel Chair. Mr. James S. Mattison Joint Review Panel Member

September 13, Dr. Harry Swain Joint Review Panel Chair. Mr. James S. Mattison Joint Review Panel Member September 13, 2013 Dr. Harry Swain Joint Review Panel Chair Mr. James S. Mattison Joint Review Panel Member Ms. Jocelyne Beaudet Joint Review Panel Member In c/o Ms. Courtney Trevis Panel Co-Manager Canadian

More information

ENO 2015 IRP PUBLIC TECHNICAL CONFERENCE MAY 12, 2016

ENO 2015 IRP PUBLIC TECHNICAL CONFERENCE MAY 12, 2016 ENO 2015 IRP PUBLIC TECHNICAL CONFERENCE MAY 12, 2016 C ONFERENCE OBJECTIVES Development of the 2015 IRP Process Recap ENO s resource needs IRP Scope and Objectives Overview of Final ENO 2015 IRP Primary

More information

CLEAN ENERGY FINANCING OVERVIEW

CLEAN ENERGY FINANCING OVERVIEW CLEAN ENERGY FINANCING OVERVIEW NATIONAL ACADEMY OF SCIENCES WORKSHOP ETHAN ZINDLER 25 JULY 2013 NATIONAL ACADEMY OF SCIENCES, 25 JULY 2013 1 COPYRIGHT AND DISCLAIMER This publication is the copyright

More information

Dominica Geothermal Project and Interconnection with Neighbouring Islands

Dominica Geothermal Project and Interconnection with Neighbouring Islands A E T S Application Européenne de Technologies et de Services Dominica Geothermal Project and Interconnection with Neighbouring Islands Assessment and Cost-Benefit Analysis March 2006 Contents 1 Project

More information

DATA, BENCHMARKING AND RATIONALE

DATA, BENCHMARKING AND RATIONALE DATA, BENCHMARKING AND RATIONALE BC Hydro relies on various data sources for relevant and accurate reporting of its Performance Measures. This includes, but is not limited to, internal financial records,

More information

100% Fossil Free Electricity. June 27, 2018

100% Fossil Free Electricity. June 27, 2018 100% Fossil Free Electricity June 27, 2018 Current Washington Emissions Levels 100 90 +7% 80 70 60 50-82% 40 30 20 10 0 1990 2013 2050 (goal) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

More information

The Future of Electricity: A Market with Costs of Zero? Marginal

The Future of Electricity: A Market with Costs of Zero? Marginal The Future of Electricity: A Market with Costs of Zero? Marginal Richard Green, IAEE European Conference, 217 1 Supply /MWh Marginal Cost Nuclear CCGT OCGT GW 2 Demand and Supply Prices reflect Marginal

More information

China s Efforts in Controlling GHG Emissions in Power Industry

China s Efforts in Controlling GHG Emissions in Power Industry UNFCCC SB in-session workshop on mitigation China s Efforts in Controlling GHG Emissions in Power Industry Energy Research Institute National Development and Reform Commission 15 May, 2007, Bonn Outline

More information

NY s New 50% Renewable Energy Standard

NY s New 50% Renewable Energy Standard NY s New 50% Renewable Energy Standard What will it take to get there? Scenic Hudson, March 27, 2018 1 Electricity Mix in NY: 2014 Snapshot; 25.9% renewables Wind 2.4% Solid Waste 1.3% Solar 0.4% Biomass

More information

L.D. Carter For USCSC

L.D. Carter For USCSC L.D. Carter For USCSC Why was a review needed? How was the analysis framed? What sources of information were used? What is the answer? What factors could significantly change the answer? What is the industry

More information

2017 IRP Update. Proposed Long Term Resource Strategy Proposed Conservation

2017 IRP Update. Proposed Long Term Resource Strategy Proposed Conservation 2017 IRP Update Proposed Long Term Resource Strategy Proposed Conservation + 10-Year Potential Estimate + 2018/2019 Conservation Target Proposed Action Plan Commission Briefing October 2, 2017 Pre-Decisional

More information

Observations on US Renewable Energy Trends

Observations on US Renewable Energy Trends Observations on US Renewable Energy Trends Ryan Pletka 32 nd IAEE Conference June 22 2009 Copyright 2009 Black & Veatch Holding Company Agenda Where are we at? Where are we going? Challenges to getting

More information

2017 Long-term Outlook. Information Session July 25, 2017

2017 Long-term Outlook. Information Session July 25, 2017 2017 Long-term Outlook Information Session July 25, 2017 0 Welcome Overview of 2017 Long-term Outlook (2017 LTO) Questions will be answered at the end of the presentation Please use microphone when asking

More information

2016 Integrated Resource Plan Executive Summary

2016 Integrated Resource Plan Executive Summary 2016 Integrated Resource Plan Executive Summary The electric industry is in the midst of unprecedented change. Customer needs and the way energy is consumed continues to evolve. Technologies are rapidly

More information

NYISO s Integrating Public Policy Project

NYISO s Integrating Public Policy Project NYISO s Integrating Public Policy Project Phase 2: Study Description and Assumption Review Dr. Nicole Bouchez & Mike Swider MIWG Krey Blvd, Rensselaer February 16, 2017 2000-2017 New York Independent System

More information

Integrated Resource Plan. Chapter 7. Consultation

Integrated Resource Plan. Chapter 7. Consultation Chapter Consultation Table of Contents. Overview of IRP Consultation... -. Consultation Process Design and Description... -.. Public and Stakeholder Consultation Process Design and Description... -.. First

More information

Electric Utility Regulation, Energy Needs and Emerging Issues. Florida Energy Systems Consortium Summit

Electric Utility Regulation, Energy Needs and Emerging Issues. Florida Energy Systems Consortium Summit Electric Utility Regulation, Energy Needs and Emerging Issues Presentation to the: Florida Energy Systems Consortium Summit Mark Futrell Office of Strategic Analysis and Governmental Affairs Florida Public

More information

BC Hydro Price Forecast

BC Hydro Price Forecast BC Hydro Price Forecast Natural Gas and Electricity Price Forecast Scenarios Quick Links: Introduction Gas Price Scenarios Electricity Price Forecast Components Electricity Price Scenarios 1. Introduction

More information

Levelized Cost of New Generation Resources in the Annual Energy Outlook 2012

Levelized Cost of New Generation Resources in the Annual Energy Outlook 2012 July 2012 Levelized Cost of New Generation Resources in the Annual Energy Outlook 2012 This paper presents average levelized costs for generating technologies that are brought on line in 2017 1 as represented

More information

i

i i ii iii 1 2 Figure ES-1: 11000 10000 9000 Overnight Costs (2008$/KW) 8000 7000 6000 5000 4000 3000 GREAT BANDWAGON MARKET Wall Street and Independent Analysts Utilities NUCLEAR RENNAISANCE 2000 1000 Early

More information

BC Hydro Vancouver, British Columbia. BC Hydro 2008 Resource Options Update Gas-fired Combustion Turbine Power Plant Costs and Performance Updates

BC Hydro Vancouver, British Columbia. BC Hydro 2008 Resource Options Update Gas-fired Combustion Turbine Power Plant Costs and Performance Updates BC Hydro Vancouver, British Columbia BC Hydro 2008 Resource Options Update Gas-fired Combustion Turbine Power Plant Costs and Performance Updates 28 February 2008 Prepared by: D. Bruce, P.Eng. Reviewed

More information

Michael Thorpe Managing Director Infrastructure and Utilities

Michael Thorpe Managing Director Infrastructure and Utilities Michael Thorpe Managing Director Infrastructure and Utilities INTRODUCTION RENEWABLES IN THE UK RENEWABLES / GAS GENERATION IN THE US OPTIMISING THE OUTCOME Introduction Coming together is a beginning;

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

Reliability Modeling: Demand, Outage, Intermittent Generation, & Import

Reliability Modeling: Demand, Outage, Intermittent Generation, & Import Reliability Modeling: Demand, Outage, Intermittent Generation, & Import Adequacy and Demand Curve Workgroup November 15, 2017 Draft for Discussion Outline Reliability modeling updates Question to WG Members:

More information

Generation Technology Options in a Carbon- Constrained World

Generation Technology Options in a Carbon- Constrained World Generation Technology Options in a Carbon- Constrained World Prepared by the Energy Technology Assessment Center (Reference: EPRI Report 1022782) Levelized Cost of Electricity Analysis Objectives Provide

More information