Portsmouth Middle School Additional Funding Request

Similar documents
RAYMOND EDUCATION CAMPUS

STUART-HOBSON MIDDLE SCHOOL

PLUMMER ELEMENTARY SCHOOL

LASALLE - BACKUS EDUCATION CAMPUS

Facility Improvements

4.1.3 Project Manual

LECKIE ELEMENTARY SCHOOL

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

BALLOU SENIOR HIGH SCHOOL

SEATON ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

MAURY ELEMENTARY SCHOOL

SHEPHERD ELEMENTARY SCHOOL

Update on FCPS Construction/Renovation Projects. July 2016

Appendix J - Custom Uniformat for EDU Migration

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DAVIS ELEMENTARY SCHOOL

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

POWELL ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

NALLE ELEMENTARY SCHOOL

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

Project Manual Index of Specifications Shenandoah Schools Concession Building

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Board Work Session Feasibility Study. January 9, 2017

LOVEJOY Independent School District

90% Draft - NOT FINAL. A Presentation For: the architectural studio. By Principals: George Moore & Curt Santee October 28th 2014

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN

FACILITY COMPONENTS - MIDDLE SCHOOL

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

BOYERTOWN AREA SENIOR HIGH SCHOOL

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT

Corsicana High School

CEFPI Monthly Meeting

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

ADDENDUM 2 - JULY 14, 2015

PATTERSON ELEMENTARY SCHOOL

Biddeford School Department

Nevada Joint Union HSD Facilities Improvement Plan - DRAFT ITEM NO. ITEM DESCRIPTION AREA (SF) PROJECT COST $/SF

BOND CONSTRUCTION UPDATE

NYC Department of Education

School Assessment Report

New Ringgold Middle School. Project Slideshow August 26, 2017

FACILITIES LIFE CYCLE ANALYSIS

NOYES EDUCATION CAMPUS

Architectural Inspection Site Structures

WATKINS ELEMENTARY SCHOOL

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

Frost Technical Center

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE

Al Behrman Elementary School

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

Update on FCPS Construction/Renovation Projects. June 2016

Belington Elementary School Grades PK 5

Greenwich High School Music Instructional Space & Auditorium Building Committee Report for the quarter ending June 30, 2010 July 6, 2010

School Assessment Report

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

Health Life Safety Survey and Master Facilities Plan

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT

School Assessment Report

LLANO ISD SCHOOL BOARD MEETING. January 2016

Building Excellence IV Capital Levy Projects Under Construction

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

COOLIDGE SENIOR HIGH SCHOOL

School Assessment Report

Minuteman Regional Vocational Technical School

James Lick High School

Hampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects

2019 Construction

Lincoln Akerman School Hampton Falls, NH

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

BARNARD ELEMENTARY SCHOOL

NEW MIDDLE SCHOOL PROJECT

KEY ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Merritt Island High School

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

Table of Contents Chapter 1 INTRODUCTION Chapter 2 DEFINITIONS Chapter 3 DELIVERABLES Chapter 4 BASIS OF DESIGN

Collins Middle School

Stevens High School Pre Bond Presentation Claremont, NH

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Lake Highlands North Recreation Center Summary

Chino Valley Unified School District Monthly Construction Update

Mount Vernon Elementary School Grades PK 5

MCER Study for Little Powder K-8

Independence Adult Center

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

FACILITY COMPONENTS - ELEMENTARY SCHOOL

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

Transcription:

City Council Work Session Portsmouth Middle School Additional Funding Request Monday March 18, 2013

Project Background School Board selected Parrott Avenue site after lengthy, comprehensive and public evaluation JCJ completed conceptual and schematic designs to meet our middle school education program now and in the future Costs to renovate and build estimated at $40.8 million program, design and cost fully approved by State DOE City Council approved $37.5 million in August, 2009 JBC launched in October, 2009

Accomplishments Built multi-use synthetic turf field at Portsmouth High School Removed decaying Wentworth School building and reused site for Alumni Wentworth softball field Re-graded and improved parking lot for Portsmouth Public Library/Portsmouth Middle School shared use Corrected drainage problems in Parrott Avenue area; coordinated water management with accelerated sewerseparation project Managed construction of new Youth Recreation Facility replacing outdated Connie Bean Center Completed new classroom and media center wing; 7 th and 8 th grades moved-in September, 2012

Portsmouth High School Synthetic Turf Field

Alumni Wentworth Softball Field

Portsmouth Middle School

Portsmouth Middle School

Portsmouth Middle School

Portsmouth Middle School

Portsmouth Middle School

Cost Overview Project the last to be approved by State State approved $40.8 million project with 40% reimbursement (and an additional 3% if school is NHCHPS certified) JBC tasked to complete project for $37.5 million challenging but believed doable Subsequent events have proven the $40.8 million estimate was accurate Completion of project building Phases 2 and 3 estimated at an additional $2.9 million Requesting up to $3.3 million to allow for contingencies

View from Parrott Avenue

Construction Phasing Phase 3 Phase 2 Phase 1

Value Management - PreBid Building Area Previous Study - January 2007 179,000 sq. ft. Initial Program April 2008 154,945 sq. ft. Approved Program Nov 2008 129,765 sq. ft. Modifications Teams - Delete (3) Conference Rooms KIDS Program - Combine Daily Living Center with Classroom Physical Education - Combine Team Rooms with Locker Rooms - Replace Weight Room with Health Classroom Performing Arts - Replace Auditorium with Stage and Bleachers in Student Commons - Reduce Size of Band Room - Combine Choral with Stage (acoustic partition) - Combine Technology Studio with General Music - Delete Ensemble and Reduce Number of Practice Rooms Foreign Language - Incorporate Kitchenette into Classroom Visual Arts - Combine Digital Media Studio with 2D Studio Building Grossing Factor - 35% for Circulation and Wall Construction

Previous Assumptions Depressed construction market Date Area (sf) Budget Cost/SF Const. Conting. Owner Conting. Escalation 11 18 2008 129,765 $40.8 m 140 reno 180 new 5% $1.2 m 5% $1.7 m 4.5% $2.9 m 8 10 2009 129,765 $37.5 m 130 reno 170 new 5% $1.2 m 2.5% $.7 m 3.75% $2.6 m Change (6 7%) ($1.4 m) $0 ($1.0 m) ($.3 m)

Value Management Pre Bid Project scope reductions that maintain academic program totaling $1,077,900 include, but not limited to: Delete irrigation system Delete 1930 building brick repointing Delete interior sun shelves Change proscenium opening partition Modify mechanical system piping and fittings Reduce generator size to meet building demand Modify fire protection design Delete fire pump; not code required Define Add Alternates: Air Cooler Chiller Custom Ornamental Light Fixtures Vegetative Roof Material & Pavers Add Exterior Brick at Band Room, Stage, Kitchen and Boiler Room

Value Management Post Bid Project scope reductions that maintain academic program totaling $919,800 include, but not limited to: No Add Alternates accepted Change brick paver manufacturer and banding pattern Delete Courtyard rain cistern Change exterior brick manufacturer Delete roof railings where not code required Change snow guard manufacturer Delete exterior sun shades Change gymnasium operable partition to operable curtain Miscellaneous interior door and hardware modifications Miscellaneous interior finish modifications Miscellaneous plumbing fixture modifications Miscellaneous electrical wiring modifications

Value Management During Construction Project scope reductions that maintain academic program totaling $140,000 include, but not limited to: Delete sign at Alumni Wentworth Field Reduce number of snow guards Delete roof stair Modify roof sheathing Delete metal roof panels Delete catwalk in attic Delete interior storefront Reduce the number of fabric wrapped panels Delete perimeter fence replacement

Total Cost Reduction Summary Project scope reductions that maintain academic program totaling $2,857,700 include: Value Management Pre Bid $1,077,900 Value Management Post Bid $919,800 Value Management During Construction $140,000 Furniture, Furnishings & Equipment Reduction $527,000 Public Art Allowance Reduction $115,000 Builder s Risk Transfer $78,000

Additional Costs Phase 1 Temporary Heat Issue Utility company delayed permanent gas service Phase 2 Structural Issues Clay tile verses brick in existing walls Lead paint on existing structural steel Unsuitable steel bearing conditions Fire stair redesign; additional columns Phase 2 Existing Pier/Soil Issues Excavation uncovered deteriorated concrete Remediation plan/redesign caused delay

Phase 2 Structural Steel Issues

Phase 2 Structural Steel Issues

Phase 2 Structural Steel Issues

Phase 2 Structural Steel Issues

Phase 2 Existing Pier/Soil Issue

Phase 2 Existing Pier/Soil Issue

Phase 3 Current Condition

Phase 3 Complete

Phase 3 Student Commons

Phase 3 Student Commons

Phase 3 Student Commons

Phase 3 Student Commons

Completed Project

City Council Work Session Thank you!