Lean Production Performance Metrics
|
|
- Austin May
- 6 years ago
- Views:
Transcription
1 Lean Production Performance Metrics Course in Operations Management Prof. Sergio Cavalieri Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 1 HOW TO SELECT THE RIGHT INDICATORS HOW TO SELECT THE RIGHT INDICATORS? FACTORY OBJECTIVES LOGISTICS PLANNING MAINTENANCE PRODUCTION OBJECTIVES OBJECTIVES OBJECTIVES OBJECTIVES PRODUCTION PLANT OBJECTIVES PRODUCTION METRICS Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 2 1
2 MAIN PRODUCTION METRICS - - PRODUCTION YIELD - OVERALL YIELD - TECHNOLOGICAL RATE - SET-UP TIME - PARTS PER MILLION Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 3 DEFINITION BASE TIME: ALLOTTED TIME TO WORK/ASSEMBLE AN ITEM. THIS TIME REMAINS FIXED FOR THE ENTIRE REFERENCE PERIOD. CYCLE TIME: TIME ALLOTTED TO WORK/ASSEMBLE AN ITEM AS A RESULT OF AN IMPROVEMENT ACTIVITY. THIS TIME CAN BE CHANGED MORE THAN ONCE IN THE SAME REFERENCE PERIOD. Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 4 2
3 GOOD ITEMS * BASE TIME WORKING HOURS TYPOLOGIES: DIRECT DEPARTMENTAL TOTAL PLANT GLOBAL Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 5 DIRECT = GOOD ITEMS * BASE TIME WORKING HOURS OF DIRECT PERSONNEL MONITORS THE EFFICIENCY OF DIRECT LABOUR AND POSTS THE RESULTS ACHIEVED THROUGH THE CONTINUOUS IMPROVEMENT PROCESS SINGLE MACHINE SINGLE DEPARTMENT WHOLE PLANT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 6 3
4 DEPARTMENTAL GOOD ITEMS * BASE TIME = WORKING HOURS OF DIRECT + INDIRECT PERSONNEL MONITORS THE EFFICIENCY OF THE DEPARTMENT WORKFORCE AND POSTS THE RESULTS ACHIEVED THROUGH THE CONTINUOUS IMPROVEMENT PROCESS SINGLE DEPARTMENT E.G. forklift operators, supervisors, etc. Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 7 TOTAL PLANT = GOOD ITEMS * BASE TIME WORKING HOURS OF DIRECT + INDIRECT DEPARTMENTAL PERSONNEL + INDIRECT PLANT PERSONNEL MONITORS THE EFFICIENCY OF THE FACTORY WORKFORCE AND POSTS THE RESULTS ACHIEVED THROUGH THE CONTINUOUS IMPROVEMENT PROCESS WHOLE PLANT E.G. Quality control personnel, warehouse personnel, maintenance personnel,. Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 8 4
5 GLOBAL PRODUCTIVTY = GOOD ITEMS * BASE TIME WORKING HOURS OF DIRECT + INDIRECT DEPARTMENTAL PERSONNEL + INDIRECT PLANT PERSONNEL + WHITE COLLARS MONITORS THE EFFICIENCY OF THE OVERALL PLANT WORKFORCE AND POSTS THE RESULTS ACHIEVED THROUGH THE CONTINUOUS IMPROVEMENT PROCESS WHOLE PLANT E.G. personnel employed in offices (logistics, R&D, engineering, ) Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 9 PRODUTTIVITA' GLOBALE Produttività Reale Produttività Budget Produttività Reale progressiva Produttività Budget progressiva MONTHLY RESULTS ARE COMPARED WITH THE BUDGET OBJECTIVES TO VERIFY ANY DEVIATIONS dic-02 GEN FEB MAR APR MAG GIU LUG AGO SET OTT NOV DIC Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 10 5
6 MAIN SOURCES OF LACK OF GLOBAL CAN BE: LACK OF DIRECT IMPACT OF INDIRECT PERSONNEL OPERATING IN THE PRODUCTION DEPARTMENTS IMPACT OF WHITE COLLARS IMPACT OF MAINTENANCE PERSONNEL IMPACT OF QUALITY PERSONNEL IMPACT OF WAREHOUSE AND MATERIAL HANDLING PERSONNEL OTHERS (SECURITY, CLEANING STAFF, ETC..) Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 11 PARETO'S FAILURE OF CAUSES OF GLOBAL : graphical representation using histograms of the % weight of each hour because of lack of global productivity on hours of global presence. Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 12 6
7 PRODUCTION YIELD P.Y. = PRODUCTION YIELD GOOD ITEMS * CYCLE TIME WORKING HOURS PLANNED BREAKS MONITORS THE CORRECT MANAGEMENT OF EQUIPMENT THROUGH THE INVOLVEMENT OF OPERATORS SINGLE PLANT WHOLE DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 13 PRODUCTION YIELD THEORETICAL PRODUCTION: (WORKING HOURS PLANNED BREAKS) / CYCLE TIME EFFECTIVE PRODUCTION: CUMULATIVE NUMBER OF GOOD PRODUCED ITEMS YIELD: EFFECTIVE PRODUCTION / THEORETICAL PRODUCTION Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 14 7
8 PRODUCTION YIELD EVERY GROUP OF OPERATORS COMPUTES THE PY AT THE END OF EACH SHIFT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 15 OVERALL YIELD O.Y.= OVERALL YIELD GOOD ITEMS * CYCLE TIME PLANT TOTAL OPENED HOURS TYPOLOGIES: OVERALL YIELD 24 HOURS OVERALL YIELD PLANNED HOURS Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 16 8
9 OVERALL YIELD OVERALL YIELD 24 HOURS = GOOD ITEMS * CYCLE TIME 24 HOURS MONITORS THE RATE OF USE OF EQUIPMENT SINGLE MACHINE WHOLE DEPARTMENT DAILY MONTHLY ON YEARLY BASE Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 17 OVERALL YIELD 24 HOURS Overall Yield April 2000 Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 18 9
10 OVERALL YIELD 24 HOURS MAIN SOURCES OF MISSED YIELD: 1. MISSED PLANNING 2. WEEKLY SUSPENSION 3. NATIONAL HOLIDAYS AND/OR COMPANY S CLOSURE 4. PLANNED MAINTENANCE 5. PLANNED PRODUCTION STOPS 6. SET UPS 7. BREAKDOWNS 8. PRODUCTION INEFFICIENCIES 9. MISSING OPERATOR 10.MISSING MATERIAL 11.OTHERS Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 19 OVERALL YIELD 24 HOURS CAUSES of FAILURE PARETO 24 HOURS: graphical representation using histograms of % weight of the hours of each cause on OVERALL number of hours Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 20 10
11 OVERALL YIELD PLANNED HOURS OVERALL YIELD PLANNED HOURS = GOOD ITEMS X CYCLE TIME OVERALL PLANNED HOURS OBIETTIVO: MONITORS THE RATE OF EFFICIENCY OF EQUIPMENT SINGLE MACHINE WHOLE DEPARTMENT DAILY MONTHLY ON YEARLY BASE Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 21 OVERALL YIELD PLANNED HOURS MAIN SOURCES OF MISSED YIELD: 1. PLANNED STOPS 2. SET UPS 3. BREAKDOWNS 4. PRODUCTION INEFFICIENCIES 5. MISSING OPERATOR 6. MISSING MATERIAL 7. OTHERS Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 22 11
12 OVERALL YIELD PLANNED HOURS CAUSES of FAILURE PARETO PLANNED HOURS: graphical representation using histograms of % weight of the hours of each cause on PLANNED number of hours Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 23 TECHNOLOGICAL RATE TECHNOLOGICAL RATE ASSIGNED TIME BEFORE IMPROVEMENT ACTIONS ASSIGNED TIMES AFTER IMPROVEMENT ACTIONS MONITORS THE DEGREE OF OPTIMIZATION OF A PRODUCTION PROCESS RELATED TO A MACHINE OR TO A PRODUCTION DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 24 12
13 TECHNOLOGICAL RATE TECHNOLOGICAL RATE MACHINE = GOOD ITEMS X BASE TIME GOOD ITEMS X CYCLE TIME MONITORS THE DEGREE OF OPTIMIZATION OF TECHNICAL INSTALLATIONS SINGLE MACHINE DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 25 TECHNOLOGICAL RATE TECHNOLOGICAL RATE PERSONNEL = GOOD ITEMS X BASE TIME X PERFORMANCE RATE GOOD ITEMS X CYCLE TIME X PERFORMANCE RATE MONITORS THE DEGREE OF ORGANIZATIONAL AND TECHNICAL OPTIMIZATION OF ASSEMBLY LINES SINGLE LINE ASSEMBLY DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 26 13
14 SET-UP TIME SET-UP TIME= SET-UP HOURS NUMBER OF SET-UPS TRACKS THE AVERAGE SET-UP TIME AND THE DEGREE OF FLEXIBILITY OF INSTALLATIONS SINGLE MACHINE WHOLE DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 27 P.P.M. = PARTS PER MILLION PPM SCRAPPED ITEMS X MILLION PRODUCED ITEMS MONITORS THE QUALITY PERFORMANCE AT ALL LEVELS OF THE PRODUCTION PROCESS FROM SUPPLIER UP TO THE END CUSTOMER, PASSING THROUGH ALL STAGES OF THE PRODUCTION PROCESS SINGLE MACHINE WHOLE DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 28 14
15 GAINS ACHIEVED THROUGH INDUSTRIAL OPTIMISATION GAINED PERSONNEL HOURS = DIRECT X HOURS OF DIRECT PERSONNEL MONITORS THE GAIN OBTAINED BY OPTIMIZATION IN ASSEMBLY DEPARTMENTS SINGLE ASSEMBLY LINE ASSEMBLY DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 29 GAINS ACHIEVED THROUGH INDUSTRIAL OPTIMISATION GAINED EQUIVALENT = MACHINE HOURS PLANTS X HOURS OF PLANNED HOURS MONITORS THE GAIN OBTAINED THROUGH INDUSTRIAL OPTIMIZATION OF MACHINING DEPARTMENTS SINGLE MACHINE WHOLE DEPARTMENT Università degli Studi di Bergamo 2011 Pof. Sergio Cavalieri 30 15
Administration Division Public Works Department Anchorage: Performance. Value. Results.
Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,
More information/ OBJECTIVE: INNOVATION
/ OBJECTIVE: INNOVATION CALEFFI GROUP FACTS AND FIGURES 2 CALEFFI GROUP FACTS AND FIGURES CALEFFI WORLDWIDE 3 THE NEW RESEARCH CENTER - HISTORY 2006 - APRIL DESIGN 2006 - DECEMBER START OFFICIAL OPENING
More informationATM safety management: reactive and proactive indicators Forecasting and monitoring ATM overall safety performance
Giulio Di Gravio 1, Maurizio Mancini 2, Riccardo Patriarca 1, Francesco Costantino 1 1 Department of Mechanical and Aerospace Engineering 2 ENAV s.p.a. Operations Directorate Fourth SESAR Innovation Days
More informationStrategies for energy efficiency improvement in residential and office buildings: their role at building and country scale
The Future Role of Energy Storage in South Eastern Europe Enlargement and Integration Action Workshop Strategies for energy efficiency improvement in residential and office buildings: their role at building
More informationThe Energy Balance: a tool for energy planning
CLIMACT Regions Project The Energy Balance: a tool for energy planning Conference on Climate Change Observatories of Greenhouse Gases and Action Plans Valencia, 1 March 2012 Eng. Alex Sorokin Interenergy
More informationUpdate on Life Cycle Costing (LCC) project. Ugo Pretato Elia Rillo Studio Fieschi & soci S.r.l. GPP Advisory Group meeting Amsterdam, 20 April 2016
Update on Life Cycle Costing (LCC) project Ugo Pretato Elia Rillo Studio Fieschi & soci S.r.l. GPP Advisory Group meeting Amsterdam, 2 April 216 Summary Introduction Project timeline Methodology Direct
More informationGeneral Manager Roundtable Lean Production
Lean Production 1 No. Time Topic Participants description Tuesday, 1 08:30 09:00 2 09:00 09:10 3 09:10 09:40 4 09:40 10:30 5 10:30 11:30 6 11:30 12:00 Arrival, Registration, Networking Welcome and program
More informationPractical solutions to address F-gas challenges. Alvise Case Francesco Mastrapasqua
2 Practical solutions to address F-gas challenges Alvise Case Francesco Mastrapasqua «The preferred local partner for customized products and refrigeration system solutions. The ultimate technology and
More informationCILT Certified Procurement Professional. Contents are subject to change. For the latest updates visit
CILT Certified Procurement Professional Page 1 of 7 Why Attend Procurement is at the heart of the supply chain function as the purchasing department can spend up to 70% of a company's money. In this course,
More informationCertified Purchasing Professional. Contents are subject to change. For the latest updates visit
Certified Purchasing Professional Page 1 of 7 Why Attend Purchasing is at the heart of the supply chain function as the purchasing department can spend up to 70% of a company's money. In this course, we
More informationTurnaround leadership with the Wernau way. Armin Schwab Vice President Plant Manager Bosch Thermotechnology
Turnaround leadership with the Wernau way Armin Schwab Vice President Plant Manager Bosch Thermotechnology The initial condition High performance environment Todays journey... Leading the change Bosch
More informationMetrics for Diagnostic Purposes. Steven Kaplan Global MES Administrator
Metrics for Diagnostic Purposes Steven Kaplan Global MES Administrator www.mesa.org 2008 North American Plant-to-Enterprise Conference September 21-23, Orlando, FL The following Strategic Initiatives of
More informationThe Total Business Excellence Model
The Total Business Excellence Model www.melbournesnorth.com.au www.melbournesnorth.com.au ISBN: 978-0-9803944-2-9 Copyright 2008 Melbourne s Northern Economic Wedge Inc trading as NORTH Link/NIETL Disclaimer
More informationProduction Planning & Control BMM4823. Aggregate Planning. by Dr. Ahmad Nasser Mohd Rose
Production Planning & Control BMM4823 Aggregate Planning by Dr. Ahmad Nasser Mohd Rose nasser@ump.edu.my Chapter Description Aims To understand the importance of aggregate planning in production planning
More informationITALIAN HEALTH AND BEAUTY PHARMACY RETAIL CHANNEL. A Trade Business Intelligence model for marketing and sales, based on a channel analytic census.
ITALIAN HEALTH AND BEAUTY PHARMACY RETAIL CHANNEL A Trade Business Intelligence model for marketing and sales, based on a channel analytic census. M&T Partner Consulting The Bold Filosophy Project Development
More informationQuantification of Machine Performance Through Overall Equipment Effectiveness
2015 International Symposium on Technology Management and Emerging Technologies (ISTMET), August 25-27, 2015, Langkawi, Kedah, Malaysia Quantification of Machine Performance Through Overall Equipment Effectiveness
More informationJOB DESCRIPTION. This position is a hands on line position with additional leadership and process requirements. The optimal breakdown of hours is:
JOB DESCRIPTION General Information: Job Title Fabrication Lead Hand Department Operations Reports To Operations Manager Direct Reports Punch Press Operators, Fabrication Workers, Assigned Temporary Staff
More informationMobility: Improve productivity and efficiency
Mobility: Improve productivity and efficiency Sergio G. Cortez & Jack Tobin GPDIS_2012.ppt 1 Surge in Mobile App Usage Worldwide $52b WW apps market in 2016 44b Mobile app downloads by 2016 41 Average
More informationSUPPLY CHAIN EXCELLENCE IN WIDEX. June 2016
SUPPLY CHAIN EXCELLENCE IN WIDEX June 2016 AGENDA 1. Presentation of Widex 2. The first year Creating a solid base 3. The second year Stabilizing the performance 4. The next steps Unleashing the competitive
More informationMATERIALS AND SUPPLIES INVENTORY
Filed: August, 0 EB-0-0 Exhibit D Schedule Page of MATERIALS AND SUPPLIES INVENTORY.0 STRATEGY Hydro One Distribution is committed to optimizing materials and supplies inventory in support of our customer
More informationENVIRONMENTAL and SOCIAL RESPONSIBILITY MANAGEMENT SYSTEM REPORT
ENVIRONMENTAL and SOCIAL RESPONSIBILITY MANAGEMENT SYSTEM REPORT ELEXES is actively engaged to act in line with Corporate Social Responsibility principles and value and is committed to apply those valued
More informationMANAGEMENT OF MANUFACTURING SYSTEMS GBAT9102
MANAGEMENT OF MANUFACTURING SYSTEMS GBAT9102 SUPERVISED OPEN-BOOK EXAMINATION Time Allowed: 2 Hours Reading Time: 10 Minutes INSTRUCTIONS 1. This is a supervised open-book examination. Course study guide,
More informationIllinois Institute of Technology [IPRO 306]
Goals > Progress > Results Outline Sloan Valve World s leading manufacture of water-efficient solutions Headquarter: Franklin Park, Illinois Founded in 1906 Facilities in Michigan, Massachusetts, Pennsylvania,
More informationRenewables investment boost in a global uncertain context
Renewables investment boost in a global uncertain context 31/3/217 Claudio Machetti 1 Technology cost reduction Cost evolution for selected technologies 28-216 12 Index 28 = 1 8 6 4 2 Upstream oil & gas
More informationAQUA th September 2015, ROME
AQUA 2015 15 th September 2015, ROME Low velocity areas' influence on contaminant persistence: a field study (Milan, Italy) Alberti Luca 1, Colombo Loris 1, Francani Vincenzo 1 1 Politecnico di Milano,
More informationImproving Material Handling Efficiency in a Ginning Machine Manufacturing Company
Improving Material Handling Efficiency in a Ginning Machine Manufacturing Company A. P. Bahale 1, Dr.S.S.Deshmukh 2 P.G. Student, Department of Mechanical engineering, PRMIT&R, Badnera, India 1 Associate
More informationPROJECT PLANNING AND SCHEDULING
PROJECT PLANNING AND SCHEDULING AFTAB HAMEED MEMON Office: E6-003A, Makmal Kej. Bangunan Jab. Kej. Bangunan & Peminaan, FKAAS Contact No. 014-2527620 E-mail: ah78memon@hotmail.com Introduction to Project
More informationAnalyzing pro-poor value chains- Study of post-rainy season sorghum in Maharashtra state of India
Analyzing pro-poor value chains- Study of post-rainy season sorghum in Maharashtra state of India Basavaraj G, Parthasarathy Rao P, Sachin More and Pokharkar V G Workshop Global value chains for food and
More informationJOB DESCRIPTION. Finished Wine & Packaging Manager Finished Wine & Packaging Department
JOB DESCRIPTION POSITION TITLE DEPARTMENT REPORTS TO ROLES REPORTING DIRECT KEY RELATIONSHIPS Finished Wine & Packaging Manager Finished Wine & Packaging Department Operations Manager Commercial Winemaker,
More informationLean Cost Management at MarquipWardUnited: Lessons Learned & Corporate Insight: Part I
Lean Cost Management at MarquipWardUnited: Lessons Learned & Corporate Insight: Part I Jerry Solomon Vice President of Operations MarquipWardUnited - Hunt Valley Bill Stabler Group Vice President, Finance
More informationJOB DESCRIPTION. This position is a hands on line position with additional leadership and process requirements. The optimal breakdown of hours is:
JOB DESCRIPTION General Information: Job Title Warehouse Lead Hand Department Operations Reports To Operations Manager Direct Reports Warehouse Packer, Specialty Packer, Outbound Quality Control Clerk,
More informationCIP Routine/Small Purchasing Team Close-out
CIP Routine/Small Purchasing Team Close-out Define Ken Koebel Control Measure January 26, 2011 Improve Analyze Cross Functional Team 2 Charter / Business Case Define Measure Routine purchasing (orders
More informationDriving organizational improvement
Driving organizational improvement Context Top 10 Critical Success Factors Results NB Government 10 Critical success factors 1. Have an executive champion 2. Demonstrate what is possible Wave 3 Departments
More informationCommunication on Progress May, 2017
Communication on Progress May, 2017 Introduction Tvilum is Europe s leading supplier of practical, environmentally friendly furniture, designed for you and your home. Tvilum is a Danish company that produces
More informationForest Fires in Italy Analysys of data in 2011 Campaign
Forest Fires in Italy Analysys of data in 2011 Campaign 27 th Meeting at JRC-Ispra 10 th -11 th november 2011 PREAMBLE: Forest fires in Italy in long-term period 1970-2010 ABOUT THE ITALIAN FORESTS INVENTORY
More informationAPPENDIX VI Guidelines for a Complete Written Program
APPENDIX VI! Guidelines for a Complete Written Program! FSEP Audit Scope Worksheet! FSEP Audit Worksheet! Corrective Action Request (CAR) Guidelines! FSEP Corrective Action Request Form! FSEP CAR Tracking
More informationMAINTENANCE CREDIT CARD PROCEDURES (MTC-P004)
1.0 SCOPE: 1.1 This procedure applies to Maintenance Department and its preparation and processing of Credit Cards. This procedure will be used for verification of purchases listed on monthly Credit Card
More informationTraffic Department Anchorage: Performance. Value. Results.
Traffic Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements.
More informationClimate change impacts on water resources in the Upper Po basin
limate change impacts on water resources in the Upper Po basin Giovanni Ravazzani, Marco Mancini, hiara orbari, Alessandro eppi, Laura Boscarello, Giulia Ercolani Department of ivil and Environmental Engineering
More informationWebinar: Justifying a Paperless Solution Building a Compelling Business Case
Pharma&Biotech Webinar: Justifying a Paperless Solution Building a Compelling Business Case Jeremy Tanner / Lonza Wayne Inc., Wayne, PA 19087 / April 2017 Lonza Lonza Informatics Lonza Informatics empowers
More informationUnderstanding Process Variation Lean Six Sigma Green Belt Session #3 Handout
Understanding Process Variation Lean Six Sigma Green Belt Session #3 Handout Purpose-Agenda-Limit (P-A-L) Page 1 Purpose Learning Objectives Understand why cycle time is a driver of customer satisfaction
More informationDepartment of Industrial Engieering
Department of Industrial Engieering Operations Analysis Assistant Prof. Abed Schokry Analysis techniques Between operations Multi Activity charts Project scheduling Flow diagrams and process charts Location
More informationUnderstanding Inventory Fundamentals
CHAPTER SEVEN Understanding Inventory Fundamentals McGraw-Hill/Irwin Copyright 2011 by the McGraw-Hill Companies, Inc. All rights reserved. Where We Are Now Relationships Sustainability Globalization Organizational
More informationCOST ACCOUNTING QUESTION ONE
QUESTION ONE COST ACCOUNTING a) Briefly explain the term limiting factor A limiting factor is a binding constraint upon the organization. It prevents indefinite expansion or unlimited profits. It may be
More informationNational Institute of Technology Calicut Department of Mechanical Engineering PRODUCTION PLANNING (AGGREGATE PLANNING)
PRODUCTION PLANNING (AGGREGATE PLANNING) Concerned with the overall operations of an organisation over a specified time horizon Determines the efficient way of responding (allocating resources) to market
More informationAcceptable level of safety performance (ALoSP) GAJAH ANNUAL REPORT
Acceptable level of safety performance (ALoSP) GAJAH ANNUAL REPORT 2015 1 CONTENTS Definitions Why measure safety performance? Safety performance indicators Alert level Selecting the target SPI data template
More informationFactory Modeling. The Priority Enterprise Management System. Contents
The Priority Enterprise Management System Factory Modeling Contents Introduction...2 Parts...3 Bills of Materials and Revisions...3 Engineering Change Orders (ECO)...4 Part Routings...4 s...5 Work Cells...5
More informationPlanning Production Capacity Optimisation with Rough Cut Capacity Planning
SOCIAL SCIENCES & HUMANITIES Journal homepage: http://www.pertanika.upm.edu.my/ Planning Production Capacity Optimisation with Rough Cut Capacity Planning Sarjono, H.*, Kusuma, V., Hamali, S. and Mulyono
More informationChapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories. Omar Maguiña Rivero
Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories Learning Objectives At the end of the class the student will be able to: 1. Describe the production budget process
More information2012 Pathology Quality Objectives and Quality Indicators Cumulative Report
Introduction A quality management system provides the integration of organisational structure, processes, procedures and resources needed to fulfil the quality policy and thus meet the needs and requirements
More informationOverheads/Job and Batch Costing. RST Ltd. has two production departments Machining and Finishing. There are three service
CA R. K. Mehta Overheads/Job and Batch Costing CA Past Years Exam Question Question : 1 Nov, 2006 RST Ltd. has two production departments Machining and Finishing. There are three service departments Human
More informationBRANDED GOODS CONFERENCE. September,
BRANDED GOODS CONFERENCE September, 15 2016 THE BRAND FACTS 69.3 million turnover in FY 2015-16, up 3.1% 3.88 million net profit in FY 2015-16 37% generated by DOS, 63% by wholesale 100 free-standing stores
More informationQUALITY COST ANALYSIS IN AN INDUSTRY
QUALITY COST ANALYSIS IN AN INDUSTRY L. Emmanual *, V.K. Kannan, L. Ragunath Department of Mechanical Engineering, M. Kumarasamy College of Engineering, Karur, India. Corresponding author mail: * emmanuall.mech@mkce.ac.in
More informationUK SERIAL PURCHASING Location: Fradley
UK SERIAL PURCHASING Location: Fradley The Serial Purchasing function is responsible for purchasing activity linked to current programs in production. You will have the opportunity to gain an insight into
More informationUsing Lean Thinking to Increase Productivity in Maintenance and Warehousing Activities Presenter: Jason Sadovia
Using Lean Thinking to Increase Productivity in Maintenance and Warehousing Activities Presenter: Jason Sadovia For Audio: Phone: 1-888-296-6500 Code:738859# November 25, 2009 Agenda What is Lean? What
More informationAGGREGATE PLANNING PROBLEMS
AGGREGATE PLANNING PROBLEMS Problem 1. ABC Corporation has developed a forecast for a group of items that has the following seasonal demand pattern. Quarter Demand Cumulative Demand 1 22 22 2 17 39 3 4
More informationCustomized smart factory solutions for smartphone, smartwatch, and tablet.
Customized smart factory solutions for smartphone, smartwatch, and tablet. by in-tech Customized smart factory solutions for production More efficiency, transparency, and productivity in machinery with
More informationKey Performance Indicator (KPI) Visualization Tools for Lean Manufacturing Facilities
Key Performance Indicator (KPI) Visualization Tools for Lean Manufacturing Facilities As a production process becomes more complex, the availability and exchange of information become more critical to
More informationTraffic Division Public Works Department Anchorage: Performance. Value. Results.
Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the
More informationBHPBilliton Iron Ore Port Sweating the assets. September 2003
BHPBilliton Iron Ore Port Sweating the assets September 2003 Port Hedland Ports Operations Nelson Point 240 hectares Approx 400 employees 3 car dumpers 4 reclaimers 6 stackers 2 berths Finucane Island
More informationDial-in Number: Access code: # Go to: Use the JOIN A SESSION button Enter the Access Code:
Dial-in Number: 209 647-1075 Access code: 1013004# Go to: http://www.gatherplace.net Use the JOIN A SESSION button Enter the Access Code: 8285433 This presentation may appear different on your computer
More informationWork Breakdown Structure & Schedules
A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a project. Resources are identified for each item within the WBS that facilitates budgeting as well as assignment of responsibilities.
More informationHow to Get Started with Quality Performance Management
How to Get Started with Quality Performance Management In an effort to catch quality nonconformances earlier and reduce cost, companies are focused on collecting as much performance data as possible. This
More informationContinuous Improvement Toolkit. Graphical Analysis. Continuous Improvement Toolkit.
Continuous Improvement Toolkit Graphical Analysis The Continuous Improvement Map Managing Risk FMEA Understanding Performance Check Sheets Data Collection PDPC RAID Log* Risk Assessment* Fault Tree Analysis
More informationCSU Project Management Certificate Program
CSU Project Management Certificate Program Project Quality Management Instructor: Ric Rothschild, PMP Contact Info: ric.rothschild@comcast.net 303-664-1117 1 Project Quality Management Agenda Introduction
More informationMTP_Paper 9_Syllabus 2016_June 2018_Set 1
Paper - 9 : OPERATIONS MANAGEMENT & STRATEGIC MANAGEMENT Academics Department, The Institute of Cost Accounts of India (Statutory Body under an Act of Parliament) Page 1 Paper 9 : Operation Management
More informationCertified Maintenance Planner. Contents are subject to change. For the latest updates visit
Certified Maintenance Planner Page 1 of 7 Why Attend The critical objectives of the maintenance planning and scheduling section are to ensure assets availability and reliability at the lowest cost. The
More informationAmbient Air Quality in Nova Scotia
Ambient Air Quality in Nova Scotia Science Forum on Air Quality March 8, 2006 Fran Di Cesare, Data Manager Air Quality Branch, Nova Scotia Environment and Labour What is the quality of the air in Nova
More informationEGVillage model in the Municipality of Castelnuovo Rangone
WP3 act 3.5 Development of the EGVillage structure on the basis of an operative model by MILD HOME NoE 1 EGVillage model in the Municipality of Castelnuovo Rangone Activity 3.5. Output O.3.5.04 Date: December
More informationProject vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,
Project vs Operation PROJECTS OPERATIONS Temporary Ongoing Unique Repetitive Closes after attaining the objectives Objective is to sustain business Prototyping the new car model Assembly line production
More informationCustomer Pay. A Government / Industry Partnership. Presented to the NDIA/DSCC Land & Maritime Symposium By Ed Peters President AM General Defense
Customer Pay A Government / Industry Partnership Presented to the NDIA/DSCC Land & Maritime Symposium By Ed Peters President AM General Defense HMMWV Products HUMMER H1 HUMMER H2 6.5 Liter Business Units
More informationProject Quality Management
1 Project Quality Management Unit 8 Eng.elsaka09@gmail.com Project Quality Management Includes the processes and activities of the performing organization that determine quality policies, objectives, and
More informationINSERT BLACK & WHITE PICTURE. Purchasing Input Perfect Storm February 2016
INSERT BLACK & WHITE PICTURE Purchasing Input Perfect Storm February 2016 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Dec-14 Jan-15 Feb-15 Mar-15
More informationThe Thinking Approach LEAN CONCEPTS , IL Holdings, LLC All rights reserved 1
The Thinking Approach LEAN CONCEPTS All rights reserved 1 Tools to Drive Kaizen Activity CREATING A LEAN TRANSFORMATION All rights reserved 2 IMPLEMENTATION PLANNING MILESTONES: 1. Setting targets quantify
More informationMgtOp 340 Professor Munson Washington State University Sample Exam for Exam 2
MgtOp 340 Professor Munson Washington State University Sample Exam for Exam 2 Multiple Choice 1. Suppose that the annual EOQ cost (setup plus inventory holding) for a product stored in a warehouse is $10,000.
More informationUsing Software and Submeters to Manage Energy
Dan Ellis Product Manager Power Management Products Eaton s Cutler-Hammer business Introduction To be economically competitive in today s global marketplace, it is necessary to reduce the cost of production
More informationAgenda. 1. Background 2. Lean Path 3. Lean Accounting Role 4. Lessons Learned 5. Next Steps 6. Questions / Answers
Agenda 1. Background 2. Lean Path 3. Lean Accounting Role 4. Lessons Learned 5. Next Steps 6. Questions / Answers 1 Facility Overview 65,000 sq. ft. 35,000 Air-Conditioned Mfg. 25,000 Warehouse 5,000 Office
More informationOVERALL SAFETY MANAGEMENT OF MAINTENANCE WORK
OVERALL SAFETY MANAGEMENT OF MAINTENANCE WORK 1. Case metadata Country/ies of origin: Finland Year of publication by agency: N/A Sector: C23.5.1 - Manufacture of cement Keywords: EU-OSHA Thesaurus: Building
More informationImprovement in Customer Order Fulfillment of Power Tool Motor Housing
, pp. 215-220 Krishi Sanskriti Publications http://www.krishisanskriti.org/jbaer.html Improvement in Customer Order Fulfillment of Power Tool Motor Housing Seenivasan K 1, Ganapathi. K.N 2 and Raghavendra
More informationOperations Management
17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William
More informationCase Study GTECH increases efficiencies in gaming machine manufacturing
Case Study GTECH increases efficiencies in gaming machine manufacturing SHOPFLOOR-ONLINE TM from Lighthouse Systems enhances product component traceability, quality check information visibility, and line
More informationIntroduction The role of the warehouse Role of the warehouse manager 36. List of figures xi List of tables xv Acknowledgements xvii
CONTENTS List of figures xi List of tables xv Acknowledgements xvii Introduction 1 01 The role of the warehouse 5 Introduction 5 Types of warehouse operation 7 Why do we hold stock? 12 Warehouse location
More informationQuality Workforce at Affordable Rates LABOUR
Quality Workforce at Affordable Rates 0508 4 LABOUR Background At Labour Enterprises we take pride in providing skilled and experienced personnel to a wide range of industries. We believe that happy workers
More informationCHAPTER 3 FLOW, SPACE, AND ACTIVITY RELATIONSHIPS. In determining the requirement of a facility, three important consideration are: Flow
1 CHAPTER 3 FLOW, SPACE, AND ACTIVITY RELATIONSHIPS Asst.Prof.Dr.BusabaPhruksaphanrat IE333 Industrial Plant Design Introduction 2 In determining the requirement of a facility, three important consideration
More informationUmoja Cluster 4 Course Catalogue
Umoja Cluster 4 Course Catalogue 1 Course Curriculum Summary No. of Courses Training (hours) Total Curricula 72 596.5 1 Courses 18 37 2 Courses 5 10 3 Courses 49 549.5 2 Course Curriculum Summary No. of
More information2. Standard costs imply a) Predetermined cost for a period b) Incurred cost c) Conversion cost d) Incremental cost
QUESTION BANK PAPER: COST ACCOUNTING COURSE: B.Com (Semester IV) MCQs 1. The basic objective of cost accounting is a) Recording of cost b) Reporting of cost c) Cost control d) EarningProfit 2. Standard
More informationDevelopment of an effective maintenance concept for enhancement of competitive advantage: a case study of East African Portland Cement Company
Development of an effective maintenance concept for enhancement of competitive advantage: a case study of East African Portland Cement Company Japheth Ombogo East African Portland Cement Kenya Abstract
More informationCELLULAR MANUFACTURING - THE HEART OF LEAN MANUFACTURING
Advances in Production Engineering & Management 3 (2008) 4, 171-180 ISSN 1854-6250 Scientific paper CELLULAR MANUFACTURING - THE HEART OF LEAN MANUFACTURING Shishir Bhat.B.N Research Scholar, Dept. of
More information1) Does the facility have a NYC DCA License for Parking? NYCEDC does not have a DCA License for Parking.
BWMM Revenue Control Project # 6348/ Contract #001 Questions & Answers Date 1/15/2016 1) Does the facility have a NYC DCA License for Parking? NYCEDC does not have a DCA License for Parking. 2) What is
More informationSupplier Keynote Joseph F. Jahn
Supplier Keynote Joseph F. Jahn President and CEO, Vaupell, Inc. Joseph Jahn is a senior executive with over 36 years in the plastics industry. Mr. Jahn s background leading to general management responsibilities
More informationOnline Course Manual By Craig Pence. Module 12
Online Course Manual By Craig Pence Copyright Notice. Each module of the course manual may be viewed online, saved to disk, or printed (each is composed of 10 to 15 printed pages of text) by students enrolled
More informationEnergy Management in Plastics Processing
Energy Management in Plastics Processing Dr Robin Kent Tangram Technology Ltd. This is where we work: This is how long we have been doing this: The new words: Global warming. Greenhouse effect. Carbon
More informationManaging Hiring Volatility & Costs with On-Demand Recruitment
Company Overview This medical device company (hereby referred to as the company ) develops, manufactures, and markets products that simplify, automate, and innovate complex biomedical testing. More than
More informationRecalculation of Seasonal Adjustment Factors
January 1985 Effective with data for January 1985, seasonal adjustment factors have been recalculated to reflect 1984 price movement patterns for stage-of-processing (SOP) and commodity groupings. This
More informationPosition elimination letter
Position elimination letter Apr 20, 2018. Sample termination eliminated. Nov 4, 2008. Example: Due to a change in business operations, the X department and every job in it will be eliminated. Your position
More informationHow to Implement Supplier Relationship Management
THE EUROPEAN INSTITUTE O F P U R C H A S I N G M A N A G E M E N T How to Implement Supplier Relationship Management The 10th EIPM Purchasing Conference Archamps, December 1st, 2005 Page 1 Today s Programme
More informationInspection Process Flow Development for a Warehouse
Minnesota State University, Mankato Cornerstone: A Collection of Scholarly and Creative Works for Minnesota State University, Mankato All Theses, Dissertations, and Other Capstone Projects Theses, Dissertations,
More informationUS Imported Beef Market A Weekly Update
US Imported Beef Market A Weekly Update Prepared Exclusively for Meat & Livestock Australia - Sydney Volume XVII, Issue 48 December 1, 2017 Prepared by: Steiner Consulting Group SteinerConsulting.com 800-526-4612
More informationDevelopment of Material Handling System in a Manufacturing Company
Development of Material Handling System in a Manufacturing Company P. Sunderam 1, E.Viswanathan 2 Assistant Professor, Karpagam College of Engineering, Coimbatore, India 1,2 ABSTRACT: In the last several
More informationWoking. q business confidence report
Woking q1 business confidence report Woking q1 report headlines saw a new record in company registrations in Woking when compared to any previous. was a record quarter for company registrations in Woking
More information