SAGD Optimization under Uncertainty

Size: px
Start display at page:

Download "SAGD Optimization under Uncertainty"

Transcription

1 WHOC SAGD Optimization under Uncertainty J. GOSSUIN & P. NACCACHE Schlumberger SIS, Abingdon, UK W. BAILEY & B.COUËT Schlumberger-Doll Research, Cambridge, MA, USA This paper has been selected for presentation and/or publication in the proceedings for the 2011 World Heavy Oil Congress [WHOC11]. The authors of this material have been cleared by all interested companies/employers/clients to authorize dmg events (Canada) Ltd., the congress producer, to make this material available to the attendees of WHOC11 and other relevant industry personnel. Abstract A means to optimize a SAGD process in the presence of reservoir uncertainty is presented. While various methods for optimizing a SAGD model have been presented, these all applied to discrete models where uncertainty was not explicitly considered in the course of the analysis. Studies utilizing a sensitivity analysis on reservoir simulations have been used but these mostly only identify which parameters impact the desired outcome, an assumption that does not consider their distribution as an explicit part of the computation. This work presents a consistent and operationally realizable method for SAGD optimization that can consider any number of uncertainties (and their distribution) subject to sufficient computational capacity. We present results on a SAGD model where 3 different (and equi-probable) geological models are possible. We map the results into a graphical construct based on the well-known Efficient Frontier that permits the decision maker to make an operational decision given their own (often very specific) risk tolerance (their degree of risk aversion). The Efficient Frontier provides the necessary operational input to allow the asset holder to maximize their recovery (or NPV) when faced with genuine and real reservoir uncertainty. Finally, we show how we can obtain better strategies, with confidence, and the potential of such a workflow to help select a production pattern. Introduction The substantial amount of energy required to produce the necessary steam in Steam Assisted Gravity Drainage (SAGD) results in it being a costly process, thereby motivating the need to examine methods to make the most efficient use of resources and improve subsequent project economics. Numerous studies aimed at optimizing a SAGD process have been published (Yang et al., 2007, Piña et al., 2008, among many others), most of which involve some form of sensitivity analysis where one parameter is varied while others are kept constant. The best value for this parameter is then kept fixed while the next variable is investigated, and so on. This method is not only time consuming but is liable to miss optimal combinations of parameters due to their likely interaction. To improve upon such an analysis, dedicated optimization algorithms have been successfully applied to a single SAGD simulation model (Card et al., 2006, Gossuin et al., 2010). However, such schemas are deterministic in nature, as they are bound by the fundamental assumption that the model being optimized is actually the right one. This might not be necessarily applicable to fields with heterogeneities, which have been shown, particularly with the presence of shale close to either well bore, to drastically influence SAGD production (Chen et al., 2007). Some authors (e.g., Yeten et al., 2002) have considered optimization under uncertainty but did so using deterministic optimizations. In essence, the "optimum" result presented was the mean of the optima obtained from individual deterministic runs. The problem with this approach is that the final result becomes unrealizable as one cannot tell which combination of unique control variables is to be used to obtain this mean value. In other words, it is not practically possible to actually realize this optimum. The scheme proposed here corrects this limitation by furnishing the actual unique combination of controls necessary to achieve the stated optimum - and to do so with an associated degree of confidence. The aim of this article is to 1

2 explain this in detail and to demonstrate an optimization with geological uncertainty such that the results have real operational meaning and can be applied in practical operational settings. The uncertainty in our example is in the form of three different but equi-probable geological realizations. As will be discussed in more detail later, while we still need to run simulations for each of these realizations it is in the processing of the results from these runs that we can extract meaningful results and the analysis provides a summary that can incorporate the decision makers own particular value (or degree) of risk tolerance. We first outline preparatory work necessary to identify the key control variables. This is followed by a description of the proposed optimization under uncertainty scheme and its application to an example. To demonstrate its utility, we compare and discuss the results against their deterministic counterparts to validate the proposed approach. Problem Description The overarching objective of this work is to maximize the net present value (NPV) of a SAGD process at the end of ten years of production. The well pair is 500m each and completed in a 25m thick sandstone reservoir unit. Reservoir Grid: The volume modeled is a m rectangular domain. To enable a more rapid solution, only half of the reservoir (divided along the plane containing the well) is simulated, i.e., we assume symmetrical property distributions either side of the wells. The grid itself consists of cells, each 50m long (in the direction of the wells), 5m wide (perpendicular to the wells) and 1m thick. These dimensions were selected to balance run time and accuracy and were also based on prior work by Gossuin et al. (2010). Three equi-probable geological realizations of porosity and permeability were geostatistically generated with average porosity of around 26% and permeability of 5500 md. Their properties are described in Table 1 and illustrated in Figures 1, 2 and 3. Grid 1 (shown in Figure 1) has a large thickness pay zone situated in the bottom part of the reservoir with quality generally decreasing as depth increases. Grid 2 (shown in Figure 2) has more homogeneous properties with some variations of quality along the well direction. Grid 3 (shown in Figure 3) has a large thickness pay zone roughly in the middle of the reservoir with slightly decreased quality at the top and bottom of the reservoir. We need to stress that these geological representations were deemed reasonable for the problem at hand. If a problem requires a larger number of realizations, the optimization framework proposed here can accommodate such requirements seamlessly. However, one must be mindful that the more uncertainties one introduces into a problem, the longer the computation time required per trial will be. Reservoir & Fluids: The oil is an Orinoco heavy oil with a viscosity of 6450 cp at reservoir conditions (51.2 C, 70 bars) and summarized in Table 2. A viscosity versus temperature curve is shown in Figure 4. Economic Parameters: The objective function, F, defined for our optimization is the after-tax NPV of the field at the end of a 10-year production period. The suitability of this singlevalued objective function for our optimization was demonstrated by Gossuin et al. (2010). The economic parameters used are outlined in Table 3. Costs are divided into energy- and non-energy-dependent terms with discounting performed continuously and an allowance made for oil and gas price drift in time. Preparatory Optimization Steps Before embarking on any major optimization (with uncertainty or otherwise), it is highly beneficial to conduct a set of preparatory tasks (steps 0 to 4) to properly identify the most important control variables and to ensure the most efficient and effective optimization possible. Such preparatory tasks associated with a deterministic optimization have been covered in detail by Gossuin et al., A rapid proxy is used to identify the most important (impactful) set of control parameters and their practical lowerand upper bounds. For this study, the proxy was chosen to be a 2D model representing the volume directly perpendicular to the wells. The 2D model porosity and permeabilities are chosen to be homogeneous and equal to the average of the 3D three grids properties. However, the inclusion of uncertainty requires the introduction of a new, initial step, denoted as "Step 0". Our modified preparatory steps are as follows: Step 0: Identify Key Uncertainties. This may be simple (both the nature of the uncertainty and its distributional form are known) or much more involved, necessitating considerable analysis to properly identify and enumerate (i.e., describe its distribution, its probability density function). Once these uncertainties have been identified (and their distributions agreed upon), they should be applied in step 3 below to better understand how uncertainty impacts our control variables. In our case, we have established 3 equi-probable grids, each with symmetric heterogeneity. Step 1: List the possible control variable (CV) candidates to focus on practical, operational variables that can be realistically optimized for. These should be accorded a crude ranking based on engineering judgment and experience. This step identified the following initial set of CVs: Wells positions in the vertical plane (k-index) The injector bottom hole pressure (BHPINJ) The BHP of the producer (BHPPROD): Steam trap temperature (STEMP) Furthermore, we sub-divide the 10-year forecast period into a number of separate time periods (not necessarily of equal duration). Step 2: Proxy sensitivity. This step utilizes a straightforward sensitivity analysis to provide a preliminary ranking of the control variables according to their impact, being mindful that the more CVs one selects, the longer the optimization will take to converge to a solution. From an initial parameter set (see Table 4), we chose to subdivide the forecast into five fixed time periods to cover the 10- year (3650-day) production, resulting in a new initial set comprising 17 CVs. These are: 2, for each well position, 5 for the BHP of the injector (one for each time period), 5 for the BHP of the producer (again, one per time period) and 5 separate values for the stream trap temperature (again, one per period). Time periods at the beginning are chosen to be shorter while the steam chamber is being established. We then conducted a sensitivity analysis to establish an approximate ranking of the 17 initial CVs. We should stress here that the criticism leveled earlier against single-parameter sensitivity analysis applies only to its use as an optimization tool. It has a valid and important role in this parameter reduction step. The difference between the lowest and highest NPV obtained from this simple sensitivity analysis is shown as a tornado plot in Figure 5, which illustrates parameters by decreasing order of influence. Note that the producer BHP (BHPPROD) has little effect on the final result (probably because the producer well is under steam trap control for most of the ten years). This lack of impact was confirmed later in our 3D validation analysis. 2

3 Step 3: 3D sensitivity: this step is recommended, but can be optional if computer resources or time are limited. Information forthcoming from step 2 are now validated on the full 3D model to validate our candidate CVs. To achieve this, similar sensitivities were run on each of the 3D grids. In terms of their relative ranking, the results obtained are very similar and are shown in Figure 6. Well location and injector BHP (BHPINJ) remain the most influential parameters. While 3D grids and 2D proxy share similar behavior, there does appear to be a major difference in the impact of well position. The best values from a sensitivity analysis for a 2D homogeneous model suggest that the wells should be separated as much possible with the injector in the upper layer and the producer at the bottom. However, the introduction of heterogeneity in the 3D model results in a much more complex response, as shown in Figure 7 (injector location) and Figure 8 (producer location). These two figures demonstrate the substantial impact on NPV not only from well location but also between the 3 grids, due to the 3D reservoir heterogeneity. Step 4: Control Variable Reduction. We must exercise caution in eliminating control parameters without some additional confirmation otherwise we may lose fidelity. The ranking obtained from the sensitivity analysis is used to guide parameter reduction, not specify it. A limited set of control variables is selected by testing different optimizations of the proxy. Note that we tested the best number of time sub-divisions using our proxy simulations, being mindful that the more subdivisions there are, the more CVs will be created. In other words, we needed to strike a balance between increased resolution (and hopefully better optima) and run time. The results are shown in Table 5, which confirms that the best balance is obtained with a 5-period sub-division (as was originally suggested by Gossuin et al., 2010). With the producer BHP having little effect, as mentioned above, and with the steam injection rate (STRATE) being ultimately dominated by BHPINJ, as seen in Figures 5 and 6, the final selection of CVs, confirmed using our 3D model, is shown in Table 6(a) with 11 controls being carried through into our full 3D optimization study. Note that we are now letting the duration of the time periods to become variable. Table 6(b) provides their initial values and their lower and upper bounds. As stated above, Period 5 is simply the time remaining between 3650 days and the sum of periods 1 to 4. The initial guesses stated in Table 6(b) are the resulting optimum values obtained from optimizing the 2D proxy with the selected control variables. They will be used in the following part as the initial (starting) values of any 3D optimization. The idea is to provide the full 3D model with the best starting value given the state of knowledge at the time. Optimization Under uncertainty Our discussion so far has been focused solely on the preparatory work and some sensitivity studies and validation. The following covers the treatment of uncertainty. To do this in a systematic manner, we first outline the nature of the objective function under investigation - which is pivotal to our proper understanding and interpretation of the results. We follow by results of our optimization runs for the SAGD model considered. This includes a description of the Efficient Frontier and how it pertains to an operational strategy, given the definition of the chosen uncertainty. We also include a discussion on the results obtained. We should also stress that the following discussion does not apply to just our problem (defined by 3 equi-probable uncertainties). Rather, the nature of the solution allows any number of uncertainties to be incorporated into the analysis given that there is sufficient computational resource to solve them in a timely manner. Objective Function When optimizing under uncertainty, it is necessary in each trial to simulate the three geological grid realizations separately - but each with identical operating conditions. The results from each realization are combined into a single representative objective function to be optimized. One could, of course, simply consider the average over the three results for the objective function. However, taking the mean of these three separate simulations is just one of a spectrum of possible outcomes. Rather, a more general form of the objective function, F, can be used that takes into account the decision makers own particular risk-aversion, which we define as a risk aversion factor, λ. This concept was originally described by Couët et al. (2004) and is written as: F = μ λσ, where μ is the average of the cumulative NPV obtained from the three runs and σ their standard deviation. The higher the value of μ, the higher the objective function will be, but accordingly, the higher the dispersion σ between the results, the lower the objective function will be. One can relate the riskaversion factor, λ, to the confidence levels typically used in standard probability distributions. It is possible to compute the probability that a realized gain, X, will be greater than F, i.e., to say with what confidence (in percent) one can be certain that X will be greater than F. If we assume that the individual gains in NPV of the various individual scenarios follow a normal (Gaussian) distribution, selecting λ = 0, 1 or 2 means that the corresponding NPV gain is to be maximized at a 50%, 84% or 98% confidence level, respectively, or that one has 50%, 84% or 98% certainty to obtain more than the corresponding F. A different optimization process will be run for each of these three values of λ. In other words, if we wish to optimize about the mean (i.e., λ = 0) then this corresponds to a risk-neutral stance towards the objective function, i.e., there is a 50% chance that the actual value realized will be higher or lower than the value of F found from optimization (assuming, of course, that the reservoir model is a fair and representative proxy of the actual asset). If λ = 1.0, then one is taking a more risk-averse position towards the outcome as this translates to an 84% likelihood that the actual realized value will be higher than that provided by the optimization of F. As the value of F computed is correspondingly smaller (by a value of 1 σ), the degree of confidence attributed to the result is higher. The larger the given value of λ, the smaller will be our value of F but with a corresponding increase in likelihood that that value or more will actually be realized. Our optimization process involves a sequential optimization starting with risk-aversion constant, λ = 0 (i.e., an optimization about the mean, our risk-neutral scenario). Using the best values of this run as the starting vector, a second optimization is conducted, this time with λ = 1. This, in turn, is followed by a third (and final) optimization run with λ = 2, this time starting with the optimum values obtained from the previous run. The reader should note that separate optimizations for each value of λ are necessary as λ determines the objective function F being considered. There is no strict requirement to restart the next λ run with the best (optimum) values from the previous. However, 3

4 doing this accelerates convergence as initial control parameters are likely to be closer to the optimum than using initial estimate starting values. Results are described and discussed in the following section. Results and Discussion Before describing the results of optimizing with uncertainty, we first present the results of deterministic optimizations performed individually over each grid in turn, hence separate results for each grid. Mean of the Optima (Unrealizable): We conducted three separate deterministic optimizations, one separate, distinct optimization for each grid, and the results are shown in Table 7. This shows a significant percentage gain for Grid 3, while Grids 1 & 2 have gains of around 19% over their respective baselines. The baselines are defined as the results of the 3D cases ran with the strategy obtained by proxy optimization. Using the approach suggested by some authors (e.g., Yeten et al., 2002), the average over these optima is around $13 million. The problem with such a value, however, is that it is not realizable as there is no single unique operational policy to achieve this value. Indeed, what are the corresponding values of the control variables associated with this mean value? The answer does not come out of the analysis. The mean of optima value is merely an indicator of potential upside with no associated operating control settings. In other words, such a value is not physically realizable but rather an indicator that upside exists. Optimum of the Mean (Realizable): To address this practical consideration of no corresponding control parameters, we conduct our optimization for the objective function defined earlier over a set of risk aversion factors (λ = 0, 1 and 2). The results shown in Table 8 are presented according to each risk aversion value (λ) and its associated degree of confidence (C.I.). Table 8 may be referred to as a 'decision table' as the decision maker can simply look-up their personal preference for risk and read-off the corresponding value of F (for which we have an associated set of controls). Recall that the objective function in the optimization is defined as F = μ λσ, meaning that as we increase our risk aversion (i.e., λ increases) the value of F correspondingly reduces, as can be seen in Table 8. While the value of F may reduce as λ increases, the degree of confidence associated with that value also increases. Thus, for λ = 2, we can translate the optimum value as "there is a 98% certainty that we will get $ (or more)" if we implemented the operational policies suggested. The gain stated in Table 8 relates to F and its corresponding initial value set for that particular λ. The initial set of control variables for a λ run is chosen to be the best set from the previous run and demonstrate the practical benefit of starting from a good initial value as the number of iterations is also reduced. Also note from Table 8 how the gain for successive λ reduces - once again due to the improved initial value. For λ = 0, the initial set of control variables was chosen as the optimum set from the 2D proxy optimization. So what are these policies? Recall from the earlier discussion that each trial comprises 3 separate simulations (realizations) - one for each of our uncertain grids but with identical control variables. Thus each and every value of F computed during the optimization is associated with a unique set of values for the control variables. We can represent all possible outcomes (both optimal and sub-optimal) in the form of the Efficient Frontier. The Efficient Frontier Representing the results for all trials in a succinct and meaningful manner is achieved through an Efficient Frontier (EF) (Couët et al and Bailey et al. 2005). The EF is the leftmost limit (shown as a green line) made from the various iterates in the optimization on the plot of μ against σ, shown in Figure 9. This plot provides all the information decision makers will need to adopt an operational policy that is in concert with their own degree of risk tolerance. Each point on the plot (labeled "Sample Point" with a blue circular marker) corresponds to a unique set of control variables. A sub-optimal operation would be one involving a point that is not on the frontier. This is because any such point corresponds to a nonoptimal combination of standard deviation (risk) and its mean value. Points on the frontier itself represent the optimum combination of risk (as defined by standard deviation) and reward (the mean value). No set of points can lie above the frontier as this space is non-realizable. A rational decision maker will first select their own value of risk aversion - say 84% certainty of achieving an outcome (i.e., λ = 1). Then, using the EF, locate the point on the frontier corresponding to that particular value of risk aversion. This point will have associated with it a unique set of corresponding control variables that represents the policy the decision maker should adopt in order to obtain their desired value. For this example (λ = 1), the optimum value of F is $ (see Table 8) that is attainable with a prescribed set of control variables. Thus we can say that we have an 84% likelihood of achieving $ or more from our asset given that the uncertainty is reasonably defined by the 3 equi-probable grids (discussed earlier). The EF is a flexible construct in that any number of uncertainties may be folded into its representation. For example, if we have 20 separate geostatistical grids then - subject to a lot more computation - we may still represent the results of all these in this simple 2D plot. If we have more than one uncertainty, say grids and PVT properties, these too may be folded seamlessly into the construct. One is really only restricted by the almost exponential computational cost required to perform the computation as the number of realizations per trial increases by the product of their sampling points. For example, say we have 3 separate uncertainties, each sampled with 3 points, then each trial of our optimization will require 27 separate simulation runs (27 realizations), which could, however, be evaluated concurrently on a computer cluster, for example. Obtaining better strategies with confidence For a risk-tolerating user (λ = 0), cumulative NPV has been improved for each grid by between 64% and 115% if we compare with our original SAGD cases (see Table 9). These large benefits are due to the fact that cumulative oil produced has increased between 23% and 57% while steam oil ratio has been divided by two. Using different time periods was instrumental into obtaining such a strategy: it enables the creation and evaluation of flexible combinations. The fact that the duration of the periods is itself a variable gives the optimizer more latitude to achieve higher values. Yet, this kind of approach greatly complicates the problem, making it even more complex to interpret by successive sensitivity alone. Using the approach described above enables us to tackle a complex problem with numerous control variables while at the same time obtaining a unified solution valid over the uncertainty studied. Had we used a deterministic approach for each of the grids, we 4

5 would have risked obtaining inconsistent results and proposing a sub-optimal policy. Referring again to the Efficient Frontier in Figure 9, we know each and every value for BHPINJ, PERIOD, POSINJ and POSPROD for every point indicated. For deterministic runs, we do not have a single set of values for the three grids and it is only with proper dealing of the uncertainty that we may make the optimal choice. In other words, when faced with real and quantified uncertainty, performing the optimization in the manner discussed here will produce results that are indeed optimal, given the uncertainty, but with the caveat that the objective function is not a single number but it also includes a percentile describing the confidence of its value. Table 11 shows the values for all control variables for our optimizations with uncertainty (various λs) and without (the 3 individual grids). Figure 10 presents the results for the BHPINJs. The left-hand plot (bounded in green) shows the results using optimization under uncertainty for each λ. The right-hand plot (bounded in red) was generated from individual deterministic optimizations for each grid. Although it appears that the results of optimizing individual grid produce almost identical values of BHPINJ per time period, when combined under one uncertainty, one can definitely conclude that the BHPINJ takes alternatively a high value of 80 and 20 bars from the first to the fourth period and stays low in the last period. The similarity between deterministic and uncertainty runs illustrates the fact that the uncertainty chosen might not have much impact on the optimization for the BHPINJ. Figure 11 shows the duration of each forecast time period, denoted 'TIME'). We notice that the left-hand (green bounded) plots (optimization with uncertainty) are markedly different from those established from individual optimizations. This clearly indicates the dangers of drawing conclusions from deterministic results alone. These periods relate to alternating injection and non-injection of steam, the duration of which is clearly sensitive to the presence of our uncertainty. Finally, Figure 12 shows producer and injector completion locations (POSPROD and POSINJ, respectively). There is good agreement at all confidence levels between these locations for the optimization with uncertainty results (the green-bounded, left-hand plot). The core operational strategy behind the improvement obtained relies on a discontinuous steam injection pattern: following a short period of injection, injection is stopped for several years and depressurization ensues. Injection starts afterwards again at a rate higher than what is achieved in the continuous steam injection case. The injector BHP limit is either at its lowest 20 bars or at its maximum (82 bars) for the 3D simulations. Why is this strategy of alternation of aggressive injection and non injection more efficient than continuous injection? The original problem shows the steam channels reaching the producer quickly, which leads the necessary steam trap control to choke the wells. Shutting the injector lets the steam chamber dissipate partially inside the reservoir, spreading its heat. The producer well switches then from being constrained by the steam presence to a bottom hole pressure control and is able to produce much more, as displayed in Figure 13. The ensuing depressurization is what enables the injector well to reach such higher rates of steam injection afterwards, as showed in Figure 14. At the end of this injection period, more steam has been introduced inside the reservoir than in the base case, as showed in Figure 15. The cost of the steam injected reduces temporarily the overall economics of the field, but the investment is recovered during the remaining time, as displayed in Figure 16. Great care was taken to ensure that this strategy was not a direct consequence of the approach chosen. Two optimizations under uncertainties, described in Table 10, were run: one to test the possible improvements with a tighter control of the producer well, and another one for the five period constraints. In that last case, the injector well is either injecting at 82 bars or shut and the duration of its injection or soaking period is optimized. A similar strategy of two successions of injection/depressurization periods was obtained in both cases with only marginal benefits. The robustness provided by the uncertainty handling combined with the ability of optimization to explore complex problems makes it possible to really assess the potential of production processes. Compared to cold production, using a base SAGD strategy would improve oil recovery by more than 100%. Yet, the strategy we obtained after optimization is one where we interrupt steam injection. That leaves opened the possibility that another thermal pattern like Cyclic Steam Stimulation may be more adapted for such a field and economic conditions. Conclusion Optimization with uncertainty has been applied successfully to a SAGD process. The uncertainty in this example was fairly benign, comprising of three heterogeneous and equi-probable grids. However, the scheme can accommodate any number of uncertainties subject to sufficient computational power. Optimization is performed on a simple utility function (involving the mean, standard deviation and risk aversion factor) that considers the specific risk tolerance of the decision maker. A set of preparatory steps necessary to reduce the number of control variables is also suggested and resulted in a reduction from 17 to 11 for the number of controls deemed significant to the example discussed here. The optimum operating strategy forthcoming prevents premature steam channels that can choke production by alternating periods of depressurization and injection. Using a mathematical optimization approach enables one to handle more complex problems that simple sensitivity analysis can address. Trying to tackle such problem manually could force, for example, the imposition of constant operating parameters over the life of the field. References Bailey, W.J., Couët, B., and Wilkinson, D., Framework for Field Optimization to Maximize Asset Value, SPE PA, SPE Reservoir Engineering J., 8, 1, February 2005, pp Card, C., Chakrabarty, N., Gates, I., and Kovscek, A. R. Automated Global Optimization of Commercial SAGD Operations, Petroleum Society Chen, Q., Gerritsen, M. G., and Kovscek, A. R. Effects of Reservoir Heterogeneities on the Steam-Assisted Gravity-Drainage Process, SPE Couët, B., Bailey, W.J., and Wilkinson, D., Reservoir Optimization Tool for Risk and Decision Analysis, Proceedings of the 9 th European Conference on the Mathematics of Oil Recovery, Cannes, France, August 30 - September 2, Gossuin, J., Bailey, W.J., Couët, B., and Naccache, P., Steam-Assisted Gravity Drainage Optimization for Extra Heavy Oil, Proceedings of the 12 th European Conference on the Mathematics of Oil Recovery, Oxford, UK, September 6-8,

6 Piña, J.A.R., Bashbush, J.L. and Fernandez, E.A.: "Applicability and Optimization of SAGD in the Eastern Venezuelan Reservoirs. SPE MS Yang, C., Card, C. and Nghiem, L. Economic Optimization and Uncertainty Assessment of Commercial SAGD Operations, paper , Canadian International Petroleum Conference, Calgary, Alberta, June 12-14, Yeten, B., Durlofsky, L.J., and Aziz, K.: Optimization of Smart Control, SPE

7 Table 1 Properties of the three grids selected for porosity, permeability and fluid in place. Grid 1 Grid 2 Grid 3 Average Porosity (%) Min. Porosity (%) Max. Porosity (%) Porosity, std. Dev (%) Average Permeability (md) Min. Permeability (md) Max. Permeability (md) Permeability, std. Dev (md) Fluid in place (Mrm3) Table 2 Reservoir and fluid properties Reservoir temperature 51.2 C Reservoir Pressure 70 bars Viscosity 6300 cp API degree 10.1 Reservoir Thickness 25 m Reservoir Width 225 Molar percentage light component 0.18 Table 3 Economic Parameters Parameter Value Non Energy-Dependent Terms Costs Water treatment $0.28 /stb (water) Water injection cost $2.43 /stb (water) CO2 cost $0.43 /stb (water injected) Oil production costs $4.13 /stb (oil) Oil upgrade costs $3.07 /stb (oil) Electricity $0.05 /kw hr Prices Gas Price $10.0 /Mscf Oil Price $75.0 /stb (oil) Drift Oil price 4.0% per annum Cost drift 2.0% per annum Discount rate 4.0% per annum Energy-Dependent Terms Water injection cost $0.29 /stb (water) Oil production costs $1.18 /stb (oil) Oil upgrade costs $0.60 /stb (oil) Taxes and Royalties Oil Royalties 5.6% Tax rate 33.8% Table 4 Values used during sensitivity and optimization. POSINJ is the location of the injector (from the top of the reservoir). POSPROD is the corresponding location of the producer. With the last digit representing the specific production periods, TIME, BHPINJ, BHPPROD, and STRATE indicate the duration of the forecast, the injector and the producer bottom hole pressures, and the steam injection rate, respectively. Note that TIME5 is computed such that the total production period equals 10 years. Base Min. Max. value Value Value Units POSINJ m POSPROD m Production period 1 TIME Days BHPINJ Bars BHPPROD Bars STRATE Sm3/day Production period 2 TIME Days BHPINJ Bars BHPPROD Bars STRATE Sm3/day Production period 3 TIME Days BHPINJ Bars BHPPROD Bars STRATE Sm3/day Production period 4 TIME Days BHPINJ Bars BHPPROD Bars STRATE Sm3/day Production period 5 TIME Days BHPINJ Bars BHPPROD Bars STRATE Sm3/day Table 5 Results of optimization of the proxy for different numbers of time periods being used. Number of periods Number of CVs Iterations Final NPV ($millions) 3 Flexible Periods Flexible Periods Flexible Periods Flexible Periods Fixed periods

8 Table 6 Table (a) (top) defines the control parameters identified. Table (b) (bottom) shows their initial guesses and bounds. CV Type Notation Units 1 Position of Producer POSPROD k-layer 2 Position of injector POSINJ k-layer 3 Period 1 Duration TIME1 Days 4 Period 2 Duration TIME2 Days 5 Period 3 Duration TIME3 Days 6 Period 4 Duration TIME4 Days 7 Injector BHP (for Period 1) BHPINJ1 Bars 8 Injector BHP (for Period 2) BHPINJ2 Bars 9 Injector BHP (for Period 3) BHPINJ3 Bars 10 Injector BHP (for Period 4) BHPINJ4 Bars 11 Injector BHP (for Period 5) BHPINJ5 Bars Notation Initial Guess Lower Upper POSPROD POSINJ TIME TIME TIME TIME BHPINJ BHPINJ BHPINJ BHPINJ BHPINJ Figure 1: Grid 1 porosity. High quality area in the bottom, but the upper part of the reservoir has lower porosity. Figure 2: Grid 2 porosity. More homogeneous overall, with the presence of a reduced permeability layer. Table 7 Results of deterministic optimization for the three equi probable grids. The baseline for 3D optimizations is not the original SAGD strategy, but the optimal strategy obtained from the proxy model. Grid 1 Grid 2 Grid 3 Baseline NPV ( 10 6 ) $9.698 $12.63 $8.793 Optimum NPV ( 10 6 ) $11.7 $14.95 $12.6 Gain (over baseline) 19.7% 18.4% 41.4% Trials Mean of Optima $ Figure 3: Grid 3 porosity. Quality of the reservoir is lower at the bottom and at the top but very good in the middle. Table 8 Results of optimization with uncertainty. The percentage gain shown relates to the gain in F against the initial value set for that λ optimization. For λ = 0, the initial set is chosen as the optimum of the 2D optimization. For subsequent λs, the initial set is the optimum of the previous λ optimization. Gain Trials λ C.I. F μ σ US$ 10 6 US$ 10 6 US$ % $12.81 $12.81 $ % % $11.65 $12.81 $ % % $10.54 $12.69 $ % 26 Figure 4: Viscosity vs. temperature of the fluid considered using a semi logarithmic scale. Viscosity can be reduced by several orders of magnitude by increasing the temperature. 8

9 Figure 5: 2D sensitivity results: what is displayed here is the difference between the lowest and highest cumulative NPV after ten years for each parameter. Figure 8: Cumulative NPV vs. producer position for the 2D proxy (purple) and the three 3D grids. Figure 6: Tornado plot obtained for a 3D model (Grid 2). The ranking is very similar to the 2D model with well positions and injector BHP being the most influential parameters. Figure 9: Efficient Frontier. Each blue point represents the outcome of a unique set of control parameters applied equally to all 3 grids. The frontier (shown in green) represents the best possible pair of (μ,σ) attainable and for each pair corresponds a set of control variables. The value of λ increases from right to left along the frontier. Points below the frontier are sub optimal. Figure 7: Cumulative NPV vs. injector position for the 2D proxy (purple) and the three 3D grids. The 2D proxy exhibits a somewhat linear behavior favoring the top positions, whereas heterogeneous grids have more complex variations. 9

10 Figure 10: Results of BHPINJ (injector bottom hole pressure) for the 5 periods of the forecast. The left hand plot (bounded in green) shows the values obtained from optimization under uncertainty for each of the three λ values. The right hand plot (bounded in red) shows optimum BHPINJ, but obtained with deterministic optimization (each grid optimized separately). The legend applies to both plots. Table 11 tabulates all the results shown here. Figure 11: Results of Period. The left plot (bounded in green) shows the values obtained from optimization under uncertainty for each of the three values of λ while the right hand plot (bounded in red) shows the same parameter but with deterministic optimization (each grid optimized separately). The legend applies to both plots. Table 11 tabulates all the results shown here. Figure 12: Position of Producer (blue) and injector (red). Left plot (bounded in green) shows the values obtained from optimization under uncertainty for each of the three values of λ while the right hand plot (bounded in red) shows the same parameter but with deterministic optimization (each grid optimized separately). The legend applies to both plots. Table 11 tabulates all the results shown here. 10

11 Table 9 Summary of main optimization results comparing the economics of the base SAGD case (constant operating pressure) for each grid versus the optimized results (chosen with λ = 0), followed by the cumulative oil produced and the final cumulative steam oil ratio. Cumulative NPV ($millions) Cumulative oil produced (Msm3) Steam oil ratio Grid 1 Base SAGD Final result Grid 2 Base SAGD Final result Grid 3 Base SAGD Final result Table 10 Cumulative NPV ($ millions) for the different optimization approaches: In the second row, the producer BHP limit is setup as the BHP of the injector minus a variable difference of pressure. In the third one, the control variables chosen are the well position and the duration of the periods where the injector is opened or shut. Only marginal additional benefits are obtained. Figure 14: Steam injection rate for base case (green) vs. optimized case (red) of the Grid 3. The optimized case can reach a much higher injection case than the base SAGD case. Grid1 Grid2 Grid3 Original approach (lambda=0) Pressure differential approach Cyclic (Inj, soak, Inj, soak, Inj ) Figure 15: Cumulative steam injected vs. simulated time for the optimized case (red) and the base case (Green), Grid 1. Figure 9: Cumulative oil produced of Grid 1 for the base SAGD case (green), the optimized case (red) and a cold production case (black). 11

12 Figure 16: Cumulative NPV ($) of Grid 2 for the base SAGD case (green), the optimized case (red) and a cold production case (black). Table 11 Control variable results for optimization with and without uncertainty. Optimization under uncertainty results (shown under the group heading "With Uncertainty") are shown for their respective values of risk aversion (λ). Deterministic optimization results (shown under the group heading "Deterministic Optima") are shown for each of the 3 grids. We observe that while there is little difference in values for bottom hole injection well pressure, much more pronounced differences exist for the durations of each period and also for well completion location. With Uncertainty Deterministic Optima λ=0 λ=1 λ=2 Grid 1 Grid 2 Grid 3 Injector Bottom Hole Pressure (bars) BHPINJ1 (applied over TIME1) BHPINJ2 (applied over TIME2) BHPINJ3 (applied over TIME3) BHPINJ4 (applied over TIME4) BHPINJ5 (applied over TIME5) Duration of Each Period (days) TIME TIME TIME TIME TIME5 (derived) Completion Layer of Well (k-index) POSPROD (production well location) POSINJ (injection well location)

Horizontal Well Spacing and Hydraulic Fracturing Design Optimization: A Case Study on Utica-Point Pleasant Shale Play

Horizontal Well Spacing and Hydraulic Fracturing Design Optimization: A Case Study on Utica-Point Pleasant Shale Play URTeC: 2459851 Horizontal Well Spacing and Hydraulic Fracturing Design Optimization: A Case Study on Utica-Point Pleasant Shale Play Alireza Shahkarami*, Saint Francis University; Guochang Wang*, Saint

More information

Analysis Fraction Flow of Water versus Cumulative Oil Recoveries Using Buckley Leverett Method

Analysis Fraction Flow of Water versus Cumulative Oil Recoveries Using Buckley Leverett Method Analysis Fraction Flow of Water versus Cumulative Oil Recoveries Using Buckley Leverett Method Reza Cheraghi Kootiani, and Ariffin Bin Samsuri International Science Index, Physical and Mathematical Sciences

More information

Thermal Recovery Status and Development Prospect for Heavy Oil in China

Thermal Recovery Status and Development Prospect for Heavy Oil in China UNITAR Centre for Heavy Crude and Tar Sands 1998 1 No.1998.198 Thermal Recovery Status and Development Prospect for Heavy Oil in China Liu Wenzhang Research Institute of Petroleum Exploration and Development,

More information

Operating Conditions Optimization of Steam Injection in Enhanced Oil Recovery Using Duelist Algorithm

Operating Conditions Optimization of Steam Injection in Enhanced Oil Recovery Using Duelist Algorithm Operating Conditions Optimization of Steam Injection in Enhanced Oil Recovery Using Duelist Algorithm Totok R. Biyanto, Sonny Irawan, Hiskia J. Ginting, Matradji, Ya umar, A. I. Fitri 1 Abstract Steam

More information

Development of Surrogate Reservoir Models (SRM) For Fast Track Analysis of Complex Reservoirs

Development of Surrogate Reservoir Models (SRM) For Fast Track Analysis of Complex Reservoirs Development of Surrogate Reservoir Models (SRM) For Fast Track Analysis of Complex Reservoirs Shahab D. Mohaghegh, WVU & ISI Modavi, A., Hafez, H. Haajizadeh, M., Kenawy, M., and Guruswamy, S., Abu Dhabi

More information

7. Gaining Insight. 1. Deterministic evaluation Sensitivity analysis Tornado diagrams

7. Gaining Insight. 1. Deterministic evaluation Sensitivity analysis Tornado diagrams R.E.Marks 2001 Lecture 5-1 7. Gaining Insight The product of any analysis should be new insights which clarify a course of action. There are several tools to generate these new insights into the problem.

More information

USING A LARGE RESERVOIR MODEL IN THE PROBABILISTIC ASSESSMENT OF FIELD MANAGEMENT STRATEGIES

USING A LARGE RESERVOIR MODEL IN THE PROBABILISTIC ASSESSMENT OF FIELD MANAGEMENT STRATEGIES PROCEEDINGS, Twenty-Seventh Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, January 28-30, 2002 SGP-TR-171 USING A LARGE RESERVOIR MODEL IN THE PROBABILISTIC ASSESSMENT

More information

Screening of Major Chemical Reactions in In-Situ Combustion Process for Bitumen Production from Oil Sands Reservoirs

Screening of Major Chemical Reactions in In-Situ Combustion Process for Bitumen Production from Oil Sands Reservoirs International Journal of Petroleum and Petrochemical Engineering (IJPPE) Volume 3, Issue 4, 217, PP 82-92 ISSN 2454-798 (Online) DOI: http://dx.doi.org/1.2431/2454-798.348 www.arcjournals.org Screening

More information

Application of the Power Law Loss-Ratio Method of Decline Analysis

Application of the Power Law Loss-Ratio Method of Decline Analysis PAPER 2009-159 Application of the Loss-Ratio Method of Decline Analysis R. MCNEIL, O. JEJE, A. RENAUD Fekete Associates Inc. This paper is accepted for the Proceedings of the Canadian International Petroleum

More information

Steam Injection. Dr. Helmy Sayyouh Petroleum Engineering Cairo University

Steam Injection. Dr. Helmy Sayyouh Petroleum Engineering Cairo University Steam Injection Dr. Helmy Sayyouh Petroleum Engineering Cairo University 1 Increasing Temperature Lowers Viscosity... Fig. 11-1 2 Single-Parameter Viscosity Correlation Fig. 11-5 Two-parameter correlation

More information

Appraising the Performance of Cyclic Production Scheme through Reservoir Simulation, a Case Study Tariq Al-Zahrani, Saudi Aramco

Appraising the Performance of Cyclic Production Scheme through Reservoir Simulation, a Case Study Tariq Al-Zahrani, Saudi Aramco SPE 152151 Appraising the Performance of Cyclic Production Scheme through Reservoir Simulation, a Case Study Tariq Al-Zahrani, Saudi Aramco Copyright 2012, Society of Petroleum Engineers This paper was

More information

Optimal Field Development and Control Yields Accelerated, More Reliable, Production: A Case Study

Optimal Field Development and Control Yields Accelerated, More Reliable, Production: A Case Study Optimal Field Development and Control Yields Accelerated, More Reliable, Production: A Case Study Morteza Haghighat, Khafiz Muradov, David Davies Institute of Petroleum Engineering, Heriot-Watt University,

More information

Optimization of Polymer Flooding and Comparison with Infill Well Drilling

Optimization of Polymer Flooding and Comparison with Infill Well Drilling International Journal of Petroleum and Petrochemical Engineering (IJPPE) Volume 1, Issue 1, June 2015, PP 20-30 www.arcjournals.org Optimization of Polymer Flooding and Comparison with Infill Well Drilling

More information

SPE Abstract. Introduction

SPE Abstract. Introduction SPE 149944 Succesful Application of Metal PCP Rechnology to Maximize Oil Recovery in SAGD Process R. Arystanbay, SPE, W. Bae, SPE, Huy X. Nguyen, SPE, Sejong University; S. Ryou, SPE, W. Lee, T. Jang,

More information

Ph.D. Defense: Resource Allocation Optimization in the Smart Grid and High-performance Computing Tim Hansen

Ph.D. Defense: Resource Allocation Optimization in the Smart Grid and High-performance Computing Tim Hansen Ph.D. Defense: Resource Allocation Optimization in the Smart Grid and High-performance Computing Tim Hansen Department of Electrical and Computer Engineering Colorado State University Fort Collins, Colorado,

More information

Preference Elicitation for Group Decisions

Preference Elicitation for Group Decisions Preference Elicitation for Group Decisions Lihi Naamani-Dery 1, Inon Golan 2, Meir Kalech 2, and Lior Rokach 1 1 Telekom Innovation Laboratories at Ben-Gurion University, Israel 2 Ben Gurion University,

More information

THE LEAD PROFILE AND OTHER NON-PARAMETRIC TOOLS TO EVALUATE SURVEY SERIES AS LEADING INDICATORS

THE LEAD PROFILE AND OTHER NON-PARAMETRIC TOOLS TO EVALUATE SURVEY SERIES AS LEADING INDICATORS THE LEAD PROFILE AND OTHER NON-PARAMETRIC TOOLS TO EVALUATE SURVEY SERIES AS LEADING INDICATORS Anirvan Banerji New York 24th CIRET Conference Wellington, New Zealand March 17-20, 1999 Geoffrey H. Moore,

More information

US climate change impacts from the PAGE2002 integrated assessment model used in the Stern report

US climate change impacts from the PAGE2002 integrated assessment model used in the Stern report Page 1 of 54 16 November 27 US climate change impacts from the PAGE22 integrated assessment model used in the Stern report Chris Hope & Stephan Alberth Judge Business School, University of Cambridge, UK

More information

Getting Started with Risk in ISO 9001:2015

Getting Started with Risk in ISO 9001:2015 Getting Started with Risk in ISO 9001:2015 Executive Summary The ISO 9001:2015 standard places a great deal of emphasis on using risk to drive processes and make decisions. The old mindset of using corrective

More information

ReservoirSimulationModelsImpactonProductionForecastsandPerformanceofShaleVolatileOilReservoirs

ReservoirSimulationModelsImpactonProductionForecastsandPerformanceofShaleVolatileOilReservoirs Global Journal of Researches in Engineering: J General Engineering Volume 16 Issue 4 Version 1.0 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals Inc. (USA) Online

More information

TECHNICAL PAPER. Decision & Risk Analysis. By: Justin Mao-Jones. Consultant The Merrick Consultancy

TECHNICAL PAPER. Decision & Risk Analysis. By: Justin Mao-Jones. Consultant The Merrick Consultancy TECHNICAL PAPER Decision & Risk Analysis By: Justin Mao-Jones Consultant The Merrick Consultancy Merrick & Company 2450 S. Peoria Street Aurora, CO 80014-5475 Tel: 303-751-0741 Fax: 303-751-2581 www.merrick.com

More information

DEVELOPMENT OPTIMIZATION OF A MARGINAL OIL FIELD

DEVELOPMENT OPTIMIZATION OF A MARGINAL OIL FIELD DEVELOPMENT OPTIMIZATION OF A MARGINAL OIL FIELD Ana Sofia Canelhas Castanho ASTRACT This thesis intends to demonstrate the development of a Marginal Field in onshore Brazil, by maximizing the use of available

More information

EVALUATION OF WATER AND GAS INJECTION IN A CARBONATE RESERVOIR

EVALUATION OF WATER AND GAS INJECTION IN A CARBONATE RESERVOIR SCA-53 1/ EVALUATION OF WATER AND GAS INJECTION IN A CARBONATE RESERVOIR P.R. Nurafza 1, M.J. Blunt and M.R. Fassihi 3 1, - Department of Earth Science and Engineering, Imperial College, London SW7 AZ,

More information

Numerical Simulation Study of Field Scale SAGD and ES-SAGD Processes Investigating the Effect of Relative Permeabilities

Numerical Simulation Study of Field Scale SAGD and ES-SAGD Processes Investigating the Effect of Relative Permeabilities Energy and Environment Research; Vol. 3, No. ; 3 ISSN 97-59 E-ISSN 97-577 Published by Canadian Center of Science and Education Numerical Simulation Study of Field Scale SAGD and ES-SAGD Processes Investigating

More information

Dynamic Simulation and Supply Chain Management

Dynamic Simulation and Supply Chain Management Dynamic Simulation and Supply Chain Management White Paper Abstract This paper briefly discusses how dynamic computer simulation can be applied within the field of supply chain management to diagnose problems

More information

Forecasting Revenues in Ancillary Markets

Forecasting Revenues in Ancillary Markets Forecasting Revenues in Ancillary Markets Ajay Patel and Eddie Solares Forecasting Revenues in Ancillary Markets 1 Summary Most companies use an expected value formula to forecast revenues from a sales

More information

Automated Energy Distribution In Smart Grids

Automated Energy Distribution In Smart Grids Automated Energy Distribution In Smart Grids John Yu Stanford University Michael Chun Stanford University Abstract We design and implement a software controller that can distribute energy in a power grid.

More information

Review: Simple schedule risk modelling with Safran Risk

Review: Simple schedule risk modelling with Safran Risk Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative

More information

Strategic Design of Robust Global Supply Chains: Two Case Studies from the Paper Industry

Strategic Design of Robust Global Supply Chains: Two Case Studies from the Paper Industry Strategic Design of Robust Global Supply Chains: Two Case Studies from the Paper Industry T. Santoso, M. Goetschalckx, S. Ahmed, A. Shapiro Abstract To remain competitive in today's competitive global

More information

Simplify APC Tuning and Configuration

Simplify APC Tuning and Configuration WHITE PAPER Simplify APC Tuning and Configuration Advanced Process Control Tushar Singh, APC Product Marketing, Aspen Technology, Inc. Lucas Reis, APC Product Management, Aspen Technology, Inc. Introduction

More information

Production/Injection Optimization Using Numerical Modeling at Ribeira Grande, São Miguel, Azores, Portugal

Production/Injection Optimization Using Numerical Modeling at Ribeira Grande, São Miguel, Azores, Portugal Proceedings World Geothermal Congress 21 Bali, Indonesia, 25-29 April 21 Production/Injection Optimization Using Numerical Modeling at Ribeira Grande, São Miguel, Azores, Portugal Minh Pham 1, Chris Klein

More information

Towards maximum utilization of CO2 storage resources

Towards maximum utilization of CO2 storage resources Towards maximum utilization of CO2 storage resources Per Bergmo, Dag Wessel Berg, Alv Arne Grimstad NORDICCS Conference contribution D 6.1.1407 (7) October 2014 Summary If large scale CCS is to be realised

More information

Power Generation Asset Optimization: Optimal Generating Strategies in Volatile Markets (Case Study) Presented at POWER-GEN 2001 Las Vegas, Nevada

Power Generation Asset Optimization: Optimal Generating Strategies in Volatile Markets (Case Study) Presented at POWER-GEN 2001 Las Vegas, Nevada Power Generation Asset Optimization: Optimal Generating Strategies in Volatile Markets (Case Study) Presented at POWER-GEN 2001 Las Vegas, Nevada Presented By: Jason Kram, Power Costs, Inc. Scott Stallard,

More information

Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency -

Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency - Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency - Nov-29, 2017 JAPEX (Japan Petroleum Exploration Co., Ltd) Canada Oil Sands Project Dept. Tanetomo (Tom) Izumi Japan

More information

ATTACHMENT 12: CDISCO Description and Sensitivity to Input Parameters

ATTACHMENT 12: CDISCO Description and Sensitivity to Input Parameters ATTACHMENT 12: CDISCO Description and Sensitivity to Input Parameters INTRODUCTION The A11. ISCO Spreadsheet Design Tool (a.k.a. Conceptual Design for ISCO or CDISCO) was developed with support from ESTCP

More information

Tutorial Segmentation and Classification

Tutorial Segmentation and Classification MARKETING ENGINEERING FOR EXCEL TUTORIAL VERSION v171025 Tutorial Segmentation and Classification Marketing Engineering for Excel is a Microsoft Excel add-in. The software runs from within Microsoft Excel

More information

Geothermal reservoir simulation of hot sedimentary aquifer system using FEFLOW

Geothermal reservoir simulation of hot sedimentary aquifer system using FEFLOW IOP Conference Series: Earth and Environmental Science PAPER OPEN ACCESS Geothermal reservoir simulation of hot sedimentary aquifer system using FEFLOW To cite this article: Hardi Nur Hidayat and Maximillian

More information

Online Student Guide Types of Control Charts

Online Student Guide Types of Control Charts Online Student Guide Types of Control Charts OpusWorks 2016, All Rights Reserved 1 Table of Contents LEARNING OBJECTIVES... 4 INTRODUCTION... 4 DETECTION VS. PREVENTION... 5 CONTROL CHART UTILIZATION...

More information

Standardization of the Evaluation Criteria on Petroleum Resources

Standardization of the Evaluation Criteria on Petroleum Resources Standardization of the Evaluation Criteria on Petroleum Resources Standardization of Korean Petroleum Resources Classification and Definition (Unofficial Report) Contents I. Introduction 1. Significance

More information

PRICE FORECASTS FOR POWER AND CERTIFICATE MARKETS

PRICE FORECASTS FOR POWER AND CERTIFICATE MARKETS PRICE FORECASTS FOR POWER AND CERTIFICATE MARKETS FEBRUARY 2015 EDITION THEMA offers long term price forecasts for the Nordic and German power markets as well as the market for electricity certificates

More information

Analysis of Shear Wall Transfer Beam Structure LEI KA HOU

Analysis of Shear Wall Transfer Beam Structure LEI KA HOU Analysis of Shear Wall Transfer Beam Structure by LEI KA HOU Final Year Project report submitted in partial fulfillment of the requirement of the Degree of Bachelor of Science in Civil Engineering 2013-2014

More information

The Efficient Allocation of Individuals to Positions

The Efficient Allocation of Individuals to Positions The Efficient Allocation of Individuals to Positions by Aanund Hylland and Richard Zeckhauser Presented by Debreu Team: Justina Adamanti, Liz Malm, Yuqing Hu, Krish Ray Hylland and Zeckhauser consider

More information

Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios

Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios Peerapat Vithayasrichareon 1, Iain MacGill 1,2, and Fushuan Wen 1,2 1 School of Electrical Engineering and Telecommunications

More information

Energy Efficiency Impact Study

Energy Efficiency Impact Study Energy Efficiency Impact Study for the Preferred Resources Pilot February, 2016 For further information, contact PreferredResources@sce.com 2 1. Executive Summary Southern California Edison (SCE) is interested

More information

Near well simulation of extra-heavy oil production using SAGD

Near well simulation of extra-heavy oil production using SAGD Near well simulation of extra-heavy oil production using SAGD 1 Kou Guandong 1 Britt Halvorsen 1 Department of Technology, Telemark University College, Norway Abstract Steam-Assisted Gravity Drainage (SAGD)

More information

Container packing problem for stochastic inventory and optimal ordering through integer programming

Container packing problem for stochastic inventory and optimal ordering through integer programming 20th International Congress on Modelling and Simulation, Adelaide, Australia, 1 6 December 2013 www.mssanz.org.au/modsim2013 Container packing problem for stochastic inventory and optimal ordering through

More information

The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture. Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April

The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture. Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April 13 2013 Motivation Province of Alberta targets a 2050 GHG emissions

More information

CHAPTER 2. Objectives of Groundwater Modelling

CHAPTER 2. Objectives of Groundwater Modelling CHAPTER 2 Objectives of Groundwater Modelling In the last two decades mathematical modelling techniques have increasingly proved their value in furthering the understanding of groundwater systems and,

More information

CONTINUOUS RESERVOIR SIMULATION INCORPORATING UNCERTAINTY QUANTIFICATION AND REAL-TIME DATA. A Thesis JAY CUTHBERT HOLMES

CONTINUOUS RESERVOIR SIMULATION INCORPORATING UNCERTAINTY QUANTIFICATION AND REAL-TIME DATA. A Thesis JAY CUTHBERT HOLMES CONTINUOUS RESERVOIR SIMULATION INCORPORATING UNCERTAINTY QUANTIFICATION AND REAL-TIME DATA A Thesis by JAY CUTHBERT HOLMES Submitted to the Office of Graduate Studies of Texas A&M University in partial

More information

Econometría 2: Análisis de series de Tiempo

Econometría 2: Análisis de series de Tiempo Econometría 2: Análisis de series de Tiempo Karoll GOMEZ kgomezp@unal.edu.co http://karollgomez.wordpress.com Primer semestre 2016 I. Introduction Content: 1. General overview 2. Times-Series vs Cross-section

More information

Sawtooth Software. Sample Size Issues for Conjoint Analysis Studies RESEARCH PAPER SERIES. Bryan Orme, Sawtooth Software, Inc.

Sawtooth Software. Sample Size Issues for Conjoint Analysis Studies RESEARCH PAPER SERIES. Bryan Orme, Sawtooth Software, Inc. Sawtooth Software RESEARCH PAPER SERIES Sample Size Issues for Conjoint Analysis Studies Bryan Orme, Sawtooth Software, Inc. 1998 Copyright 1998-2001, Sawtooth Software, Inc. 530 W. Fir St. Sequim, WA

More information

Simulation-Based Analysis and Optimisation of Planning Policies over the Product Life Cycle within the Entire Supply Chain

Simulation-Based Analysis and Optimisation of Planning Policies over the Product Life Cycle within the Entire Supply Chain From the SelectedWorks of Liana Napalkova June, 2009 Simulation-Based Analysis and Optimisation of Planning Policies over the Product Life Cycle within the Entire Supply Chain Galina Merkuryeva Liana Napalkova

More information

Limitations of Using Uniform Heat Flux Assumptions in Sizing Vertical Borehole Heat Exchanger Fields

Limitations of Using Uniform Heat Flux Assumptions in Sizing Vertical Borehole Heat Exchanger Fields Limitations of Using Uniform Heat Flux Assumptions in Sizing Vertical Borehole Heat Exchanger Fields Veera Malayappan 1, Jeffrey D. Spitler 2 1,2 Mechanical and Aerospace Engineering, Oklahoma State University

More information

The Lazy Man s Guide to 80 x 50 in NYC Laurie Kerr, FAIA, LEED AP Urban Green Council, Policy Director

The Lazy Man s Guide to 80 x 50 in NYC Laurie Kerr, FAIA, LEED AP Urban Green Council, Policy Director The Lazy Man s Guide to 80 x 50 in NYC Laurie Kerr, FAIA, LEED AP Urban Green Council, Policy Director ABSTRACT The Lazy Man methodology was developed to help New York City establish its high level strategies

More information

IMPERIAL COLLEGE LONDON. Department of Earth Science and Engineering. Centre for Petroleum Studies

IMPERIAL COLLEGE LONDON. Department of Earth Science and Engineering. Centre for Petroleum Studies IMPERIAL COLLEGE LONDON Department of Earth Science and Engineering Centre for Petroleum Studies Evaluation of the Design of Liner Deployed Inflow/Outflow Control Devices for SAGD Wells By Elena Spronk

More information

OPERATING SYSTEMS. Systems and Models. CS 3502 Spring Chapter 03

OPERATING SYSTEMS. Systems and Models. CS 3502 Spring Chapter 03 OPERATING SYSTEMS CS 3502 Spring 2018 Systems and Models Chapter 03 Systems and Models A system is the part of the real world under study. It is composed of a set of entities interacting among themselves

More information

Decision Analysis Applied to Small Satellite Risk Management

Decision Analysis Applied to Small Satellite Risk Management AIAA SciTech Forum 5-9 January 2015, Kissimmee, Florida 53rd AIAA Aerospace Sciences Meeting AIAA 2015-1863 Decision Analysis Applied to Small Satellite Risk Management Katharine Brumbaugh Gamble * and

More information

Jian-Yang Yuan Osum Oil Sands Corp. Richard McFarlane Alberta Research Council Inc.

Jian-Yang Yuan Osum Oil Sands Corp. Richard McFarlane Alberta Research Council Inc. Steam Circulation Strategies for SAGD Start-Up Jian-Yang Yuan Osum Oil Sands Corp. Richard McFarlane Alberta Research Council Inc. Objective Evaluate impact of operation parameters on SAGD start-up using

More information

Designing with LRFD for Wood by Robert J. Taylor, Ph.D., P.Eng., M.ASCE, Assoc. AIA

Designing with LRFD for Wood by Robert J. Taylor, Ph.D., P.Eng., M.ASCE, Assoc. AIA Designing with LRFD for Wood by Robert J. Taylor, Ph.D., P.Eng., M.ASCE, Assoc. AIA Many engineers (especially seasoned engineers) ask, "Why should I switch from allowable stress design (ASD) to LRFD design

More information

Risk Analysis Overview

Risk Analysis Overview Risk Analysis Overview What Is Risk? Uncertainty about a situation can often indicate risk, which is the possibility of loss, damage, or any other undesirable event. Most people desire low risk, which

More information

An experimental study of permeability determination in the lab

An experimental study of permeability determination in the lab Petroleum and Mineral Resources 221 An experimental study of permeability determination in the lab E. Lock, M. Ghasemi, M. Mostofi & V. Rasouli Department of Petroleum Engineering, Curtin University, Australia

More information

The Effect of Different Carbon Dioxide Injection Modes on Oil Recovery

The Effect of Different Carbon Dioxide Injection Modes on Oil Recovery 66 The Effect of Different Carbon Dioxide Injection Modes on Oil Recovery Faiza M. Nasir and Yeap Y. Chong Abstract This paper presents a study of the effect of various CO 2 injection modes on miscible

More information

CAPROCK INTEGRITY FOCUS Analyzing How To Utilize Technical Testing Methodologies To Ensure Caprock Integrity. Tuesday, May 24 th, 2011

CAPROCK INTEGRITY FOCUS Analyzing How To Utilize Technical Testing Methodologies To Ensure Caprock Integrity. Tuesday, May 24 th, 2011 CAPROCK INTEGRITY FOCUS Analyzing How To Utilize Technical Testing Methodologies To Ensure Caprock Integrity Tuesday, May 24 th, 2011 Forward-Looking Information and Advisories This presentation contains

More information

Understanding Type-well Curve Complexities & Analytic Techniques

Understanding Type-well Curve Complexities & Analytic Techniques Understanding Type-well Curve Complexities & Analytic Techniques Reservoir, Evaluation and Production Optimization Luncheon SPE - Calgary Section Dec. 1 st, 2015 Introduction Thank you SPE Disclaimer and

More information

Harbingers of Failure: Online Appendix

Harbingers of Failure: Online Appendix Harbingers of Failure: Online Appendix Eric Anderson Northwestern University Kellogg School of Management Song Lin MIT Sloan School of Management Duncan Simester MIT Sloan School of Management Catherine

More information

A RANKING AND PRIORITIZING METHOD FOR BRIDGE MANAGEMENT

A RANKING AND PRIORITIZING METHOD FOR BRIDGE MANAGEMENT A RANKING AND PRIORITIZING METHOD FOR BRIDGE MANAGEMENT Saleh Abu Dabous and Sabah Alkass Department of Building, Civil and Environmental Engineering, Concordia University, Rm: EV-6139 1455 de Maisonneuve,

More information

A New Method for Efficient Global Optimization of Large Systems Using Sub-models HEEDS COMPOSE demonstrated on a crash optimization problem

A New Method for Efficient Global Optimization of Large Systems Using Sub-models HEEDS COMPOSE demonstrated on a crash optimization problem 12 th International LS-DYNA Users Conference Optimization(2) A New Method for Efficient Global Optimization of Large Systems Using Sub-models HEEDS demonstrated on a crash optimization problem Nate Chase,

More information

Permeability, Flow Rate, and Hydraulic Conductivity Determination for Variant Pressures and Grain Size Distributions

Permeability, Flow Rate, and Hydraulic Conductivity Determination for Variant Pressures and Grain Size Distributions Permeability, Flow Rate, and Hydraulic Conductivity Determination for Variant Pressures and Grain Size Distributions Nick Desiderio, npd5050@psu.edu, February 18, 2014 Abstract Carbon capture and storage

More information

A Comparative Field-Scale Simulation Study on Feasibility of SAGD and ES-SAGD Processes in Naturally Fractured Bitumen Reservoirs

A Comparative Field-Scale Simulation Study on Feasibility of SAGD and ES-SAGD Processes in Naturally Fractured Bitumen Reservoirs Energy and Environment Research; Vol. 3, No. 1; 2013 ISSN 1927-0569 E-ISSN 1927-0577 Published by Canadian Center of Science and Education A Comparative Field-Scale Simulation Study on Feasibility of SAGD

More information

Practical Implications of Increased Liquefaction Vulnerability

Practical Implications of Increased Liquefaction Vulnerability REPORT Practical Implications of Increased Liquefaction Vulnerability Prepared for Chapman Tripp acting on behalf of the Earthquake Commission (EQC) Prepared by Date Job Number 52010.140.v1.0 Distribution:

More information

Oil Production Efficiency Of Marginal Fields In The Phitsanulok Basin By Simulation Model

Oil Production Efficiency Of Marginal Fields In The Phitsanulok Basin By Simulation Model International journal of scientific and technical research in engineering (IJSTRE) www.ijstre.com Volume 2 Issue 4 ǁ April 2017. Oil Production Efficiency Of Marginal Fields In The Phitsanulok Basin By

More information

Reservoir Engineering

Reservoir Engineering Reservoir Engineering How much oil is in place? How much oil is recoverable? How can I maximize oil recovery? Under economic constraints Origin of Petroleum Where are the resources? Traps Dome trap Fault

More information

Capacity Dilemma: Economic Scale Size versus. Demand Fulfillment

Capacity Dilemma: Economic Scale Size versus. Demand Fulfillment Capacity Dilemma: Economic Scale Size versus Demand Fulfillment Chia-Yen Lee (cylee@mail.ncku.edu.tw) Institute of Manufacturing Information and Systems, National Cheng Kung University Abstract A firm

More information

Course Catalog. Calgary, Alberta Canada

Course Catalog. Calgary, Alberta Canada Course Catalog Calgary, Alberta Canada October 2012 through March 2013 Table of Contents Training Calendar (October 2012 - March 2013)... 3 Training Course Flowchart... 5 Introduction to IMEX/Builder/Results...

More information

THE GUIDE TO SPSS. David Le

THE GUIDE TO SPSS. David Le THE GUIDE TO SPSS David Le June 2013 1 Table of Contents Introduction... 3 How to Use this Guide... 3 Frequency Reports... 4 Key Definitions... 4 Example 1: Frequency report using a categorical variable

More information

THE ITERATIVE ENGAGEMENT MODEL A CALCULATED RISK AND A WHOLE LOT OF REWARD. By Mikhail Papovsky CEO, Abraic, Inc.

THE ITERATIVE ENGAGEMENT MODEL A CALCULATED RISK AND A WHOLE LOT OF REWARD. By Mikhail Papovsky CEO, Abraic, Inc. THE ITERATIVE ENGAGEMENT MODEL A CALCULATED RISK AND A WHOLE LOT OF REWARD By Mikhail Papovsky CEO, Abraic, Inc. Fall 2016 1 The traditional vendor engagement model is flawed. Technology initiatives are

More information

MANAGERIAL ECONOMICS WILEY A JOHN WILEY & SONS, INC., PUBLICATION. A Mathematical Approach

MANAGERIAL ECONOMICS WILEY A JOHN WILEY & SONS, INC., PUBLICATION. A Mathematical Approach MANAGERIAL ECONOMICS A Mathematical Approach M. J. ALHABEEB L. JOE MOFFITT Isenberg School of Management University of Massachusetts Amherst, MA, USA WILEY A JOHN WILEY & SONS, INC., PUBLICATION PREFACE

More information

Transportation Optimization: Is This the Next Step?

Transportation Optimization: Is This the Next Step? Transportation Optimization: Is This the Next Step? By Irista, An HK Systems Company Cost reduction through effective transportation management remains a high priority for most organizations. The challenges

More information

Challenges for Japanese companies to grow in the expanding global technology frontier

Challenges for Japanese companies to grow in the expanding global technology frontier Mizuho Economic Outlook & Analysis May 10, 2016 Challenges for Japanese companies to grow in the expanding global technology frontier < Summary > Over the past decade, the productivity of Japanese companies

More information

Determining Optimum Redesign Plans for Avionics Based on Electronic Part Obsolescence Forecasts

Determining Optimum Redesign Plans for Avionics Based on Electronic Part Obsolescence Forecasts 02WAC-150 Determining Optimum Redesign Plans for Avionics Based on Electronic Part Obsolescence Forecasts P. Singh and P. Sandborn University of Maryland, College Park, MD D. Lorenson Honeywell International,

More information

TIMEBOXING PLANNING: BUFFERED MOSCOW RULES

TIMEBOXING PLANNING: BUFFERED MOSCOW RULES TIMEBOXING PLANNING: BUFFERED MOSCOW RULES EDUARDO MIRANDA, INSTITUTE FOR SOFTWARE RESEARCH, CARNEGIE MELLON UNIVERSITY, SEPTEMBER 2011 ABSTRACT Time boxing is a management technique which prioritizes

More information

1) Operating costs, such as fuel and labour. 2) Maintenance costs, such as overhaul of engines and spraying.

1) Operating costs, such as fuel and labour. 2) Maintenance costs, such as overhaul of engines and spraying. NUMBER ONE QUESTIONS Boni Wahome, a financial analyst at Green City Bus Company Ltd. is examining the behavior of the company s monthly transportation costs for budgeting purposes. The transportation costs

More information

THE RTM-LIGHT MANUFACTURING PROCESS: EXPERIMENTATION AND MODELLING

THE RTM-LIGHT MANUFACTURING PROCESS: EXPERIMENTATION AND MODELLING THE RTM-LIGHT MANUFACTURING PROCESS: EXPERIMENTATION AND MODELLING O. Maclaren 1, J.M. Gan 2, C.M.D. Hickey 2, S. Bickerton 2, P.A. Kelly 1 1 Department of Engineering Science, 2 Centre for Advanced Composite

More information

Computation and analysis of temperature distribution in the crosssection

Computation and analysis of temperature distribution in the crosssection Computation and analysis of temperature distribution in the crosssection of the weld Vee John Inge Asperheim, Bjørnar Grande, Leif Markegård, ELVA Induksjon a.s James E. Buser, ELVA Induction inc. Patrick

More information

Similarity Assessment of Biosimilars. The Past, Present and Future State. Joseph Glajch, Ph.D and Jim Anderson, Ph.D Jan 28, 2016

Similarity Assessment of Biosimilars. The Past, Present and Future State. Joseph Glajch, Ph.D and Jim Anderson, Ph.D Jan 28, 2016 Similarity Assessment of Biosimilars. The Past, Present and Future State Joseph Glajch, Ph.D and Jim Anderson, Ph.D Jan 28, 2016 Disclaimer The views and opinions expressed in the following PowerPoint

More information

Optimization of Chemical Flooding in a Mixed-Wet Dolomite Reservoir

Optimization of Chemical Flooding in a Mixed-Wet Dolomite Reservoir SPE 100082 Optimization of Chemical Flooding in a Mixed-Wet Dolomite Reservoir Glen A. Anderson, Mojdeh Delshad, Chrissi Brown King, Hourshad Mohammadi, and Gary A. Pope Reservoir Engineering Research

More information

SPE/WPC/AAPG/SPEE Petroleum Resources Management System (PRMS)

SPE/WPC/AAPG/SPEE Petroleum Resources Management System (PRMS) SPE/WPC/AAPG/SPEE Petroleum Resources Management System (PRMS) PRMS Prepared by the SPE Oil & Gas Reserves Committee (OGRC) 1 Who is the OGRC? International representation (USA, Canada, Australia, UK,

More information

NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE. Provide a copy of the report to the Board concerning Newfoundland

NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE. Provide a copy of the report to the Board concerning Newfoundland NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE CA181 Provide a copy of the report to the Board concerning Newfoundland Power Company s Study of Innovative Approaches to

More information

Simplified CO 2 plume dynamics for a Certification Framework for geologic sequestration projects

Simplified CO 2 plume dynamics for a Certification Framework for geologic sequestration projects Available online at www.sciencedirect.com Physics Energy Procedia 00 1 (2009) (2008) 2549 2556 000 000 www.elsevier.com/locate/procedia www.elsevier.com/locate/xxx Simplified CO 2 plume dynamics for a

More information

Fully integrated simulation and design process for offshore wind turbines including support structures

Fully integrated simulation and design process for offshore wind turbines including support structures Fully integrated simulation and design process for offshore wind turbines including support structures Dr. Michael Hänler 1 Dr. Thomas Bauer 2 Dr. Michael Beyer 1 Prof. Dr. Uwe Ritschel 2 1 Windrad Engineering

More information

Information That Predicts

Information That Predicts Information That Predicts Crystal Ball s Solutions for Financial Forecasting and Analysis O R A C L E W H I T E P A P E R N O V E M B E R 2 0 1 7 Table of Contents Introduction 1 Make Superior Financial

More information

John Boreman, Chair, Mid-Atlantic Fisheries Management Council SSC

John Boreman, Chair, Mid-Atlantic Fisheries Management Council SSC Memo To: From: John Boreman, Chair, Mid-Atlantic Fisheries Management Council SSC Thomas Miller, Vice-Chair, Mid-Atlantic Fisheries Management Council SSC Date: September 12, 2015 Re: Review of McNamee

More information

Process Control and Optimization Theory

Process Control and Optimization Theory Process Control and Optimization Theory Application to Heat Treating Processes Jake Fotopoulos, Lead Process Controls Engineer Air Products and Chemicals, Inc. Process Control and Optimization Theory --

More information

Thermal Recovery of Bitumen

Thermal Recovery of Bitumen Thermal Recovery of Bitumen February 23, 2007 Presented by Neil Edmunds, VP EOR Thermal Recovery of Bitumen 2 1. SAGD as a mechanism (instead of a process) 2. How a Steam/Oil Ratio is Determined 3. Optimizing

More information

Discrete Fracture Embedding to Match Injection Returns in a Single Porosity Model

Discrete Fracture Embedding to Match Injection Returns in a Single Porosity Model Proceedings World Geothermal Congress 2015 Melbourne, Australia, 19-25 April 2015 Discrete Fracture Embedding to Match Injection Returns in a Single Porosity Model Julian M. McDowell Jacobs, Level 2, 12-16

More information

INVESTIGATION ON SURFACE AND SUBSURFACE FLUID MIGRATION: ENVIRONMENTAL IMPACT

INVESTIGATION ON SURFACE AND SUBSURFACE FLUID MIGRATION: ENVIRONMENTAL IMPACT Proceedings of the 13 th International Conference on Environmental Science and Technology Athens, Greece, 5-7 September 2013 INVESTIGATION ON SURFACE AND SUBSURFACE FLUID MIGRATION: ENVIRONMENTAL IMPACT

More information

MODIFICATIONS TO KOZENY-CARMAN MODEL To ENHANCE PETROPHYSICAL RELATIONSHIPS

MODIFICATIONS TO KOZENY-CARMAN MODEL To ENHANCE PETROPHYSICAL RELATIONSHIPS 1 2 3 4 5 6 MODIFICATIONS TO KOZENY-CARMAN MODEL To ENHANCE PETROPHYSICAL RELATIONSHIPS Amir Maher Sayed Lala Geophysics Department, Ain Shams University e-mail: amir77_lala@yahoo.com Affiliation: Geophysics

More information

A HYBRID MODERN AND CLASSICAL ALGORITHM FOR INDONESIAN ELECTRICITY DEMAND FORECASTING

A HYBRID MODERN AND CLASSICAL ALGORITHM FOR INDONESIAN ELECTRICITY DEMAND FORECASTING A HYBRID MODERN AND CLASSICAL ALGORITHM FOR INDONESIAN ELECTRICITY DEMAND FORECASTING Wahab Musa Department of Electrical Engineering, Universitas Negeri Gorontalo, Kota Gorontalo, Indonesia E-Mail: wmusa@ung.ac.id

More information

Approach Optimizes Frac Treatments

Approach Optimizes Frac Treatments JULY 2011 The Better Business Publication Serving the Exploration / Drilling / Production Industry Approach Optimizes Frac Treatments By Jamel Belhadi, Hariharan Ramakrishnan and Rioka Yuyan HOUSTON Geologic,

More information

Analyzing Performance of

Analyzing Performance of Analyzing Performance of North American Shale Gas Resources 2013 SPE - GCS - Reservoir Technology Forum Rakesh R. Rai NanoDarcy Rock Changes Everything G&G: Shale petrophysics, seismic, core analysis,

More information