The Most Common Errors that Delay Self- Generation Project Utility Interconnection and / or Operation

Size: px
Start display at page:

Download "The Most Common Errors that Delay Self- Generation Project Utility Interconnection and / or Operation"

Transcription

1 The Most Common Errors that Delay Self- Generation Project Utility Interconnection and / or Operation 2006 San Diego Gas & Electric Company. All copyright and trademark rights reserved.

2 Overview 1. Common mistakes - Letter of authorization - Rule 21 interconnection application issues - Natural gas project related issues 2. Interconnection Misc. Information - Interconnection submittal criteria - Self-Generation information package overview - SDG&E contact information

3 Letter of Authorization No Letter of Authorization on file - The utility requires a Letter of Authorization signed by the customer of record in order to discuss a customer account or provide information to a third party LOA

4 Rule 21 Interconnection Application Issues Missing or Incorrect information on the application - Application information, which includes certain documents such as one-line diagrams, site plans, etc., must be complete, consistent, and accurate (e.g., address, acct. #, meter #, equipment information, etc.)

5 Rule 21 Interconnection Application Issues Insufficient Copies, Missing One-Lines, Diagrams, Site Plans, Protection Information - Page 1, Part 1, Section C of the Interconnection Application specifies required documentation that must accompany the application

6 Rule 21 Interconnection Application Issues No Application Fee or Incorrect Amount - A complete application must also include a fee. - An applicant must request a CPR form and send the CPR with an $ check or money order payable to SDG&E separate from the application. DO NOT send the fee with the application!

7 Rule 21 Interconnection Application Issues Submitting Partial Applications - Incomplete applications (e.g. missing information) or partial submittals may be returned and may delay the review process

8 Rule 21 Interconnection Application Issues Project is altered; application information is not revised or updated - Changes in projects include, but are not limited to: change in contractor, contact person, phone #, addresses, change in design, equipment; project size etc. Significant project changes may require a new application and an additional $800 fee.

9 Rule 21 Interconnection Application Issues No Generator Output Meter (NGOM) - Generator output metering may be an option. If an NGOM is to be installed, drawings must show it. The NGOM should be grouped with the site s existing metering. Electrically, it must be placed between the generator and the electric load it serves.

10 Rule 21 Interconnection Application Issues No Accessible Disconnects - There must be a utility accessible disconnect on both the line and load sides of the NGOM. SDG&E requires a visible-open and lockable disconnect.

11 Rule 21 Interconnection Application Issues Failure to provide a Proof of Insurance certificate

12 Rule 21 Interconnection Application Issues Delay in providing information required to prepare final execution copies of the Interconnection Agreement (ICA) - The utility typically requires a completed draft ICA to be submitted, that includes all necessary customer information, before the utility can prepare two (2) final ICAs for execution.

13 Natural Gas Project Related Issues Missing or Inaccurate Gas Information - In order to meet the customer s timetable, gas information is required in a timely manner to properly size and or build the gas meter and complete necessary system upgrades

14 Natural Gas Project Related Issues No Non-Core Gas Service Request - If your generator requires natural gas to generate electricity, it qualifies for noncore gas services. - A Request for Noncore Gas Services must be completed electing core or noncore service before your meter set can be designed and built. - If noncore gas service is elected, a gas service provider must also be arranged. SDG&E no longer provides utility procurement services for new noncore gas accounts.

15 Natural Gas Project Related Issues SDGE Does Not Guarantee Gas Pressure - If your project requires high pressure gas, as with a turbine installation, a gas compressor is necessary!

16 Interconnection Misc. Information Typical Interconnection submittals must include: - Interconnection Application (6 copies) - Application Fee ($800.00, initial fee) - One-Line Diagram (6 copies) - Site Plans (6 copies) - Diagrams (6 copies) - Protection Information (6 copies)

17 Interconnection Misc. Information SDGE s Self-Generation Information Package Includes: Cover Letter G&E Data Sheet Interconnection Application Request for Non-Core Gas Service LOA Plaque Illustration One-Line Illustration Self-Generation Resource Guide

18 Interconnection Misc. Information Sample interconnection agreements are available at: An electronic copy of the Self Generation Information Package may be requested at

19 Contact Information Questions in San Diego: - Regarding General Self-Generation or Rule 21 Interconnection Contact Mike Iammarino MJIammarino@semprautilities.com Regarding: Tariffs and Rules (other than R21) Contact Jim Spurgeon JSpurgeon@semprautilities.com

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017 Net Energy Metering 2.0 Solar PV Interconnection Handbook Effective December 1, 2017 Important Information The NEM 1.0 solar PV rate is closed. The NEM 2.0 is the current PV rate option available for solar

More information

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017 Net Energy Metering 2.0 Solar PV Interconnection Handbook Effective January 1, 2017 Overview This Handbook illustrates the steps, processes, and requirements to apply for a Solar Photovoltaic (PV) interconnection

More information

Your guide to SDG&E services. Helping you save energy and money

Your guide to SDG&E services. Helping you save energy and money Your guide to SDG&E services Helping you save energy and money Whether you re interested in establishing service, an easier way to pay your bill, saving energy or learning about the variety of assistance

More information

APPLICATION FOR SOLAR PERMIT

APPLICATION FOR SOLAR PERMIT APPLICATION FOR SOLAR PERMIT Permit Application Application Checklist o New York State Unified Solar Permit Application for Roof Mounted Systems 12kW or less. (Includes Electrical Permit Application) o

More information

Generator Interconnection Process. Wholesale Distribution Overview

Generator Interconnection Process. Wholesale Distribution Overview 1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation

More information

Feed-in-Tariff (FIT) Connection Application Guidelines

Feed-in-Tariff (FIT) Connection Application Guidelines Generation Planning & Transmission Capacity Feed-in-Tariff (FIT) Connection Application Guidelines These guidelines help to ensure efficient processing and implementation of the FIT project. It is important

More information

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) This application, terms, and conditions, and Interconnection Agreement is for Xcel Energy customers requesting the installation of a small generation

More information

LEVEL 1 Application for Interconnection and Net Metering

LEVEL 1 Application for Interconnection and Net Metering LEVEL 1 Application for Interconnection and Net Metering Use this application form only for a generating facility that is inverter based and certified by a nationally recognized testing laboratory to meet

More information

Self-Generation Incentive Program

Self-Generation Incentive Program Self-Generation Incentive Program The Application Process June 25, 2002 Dean Heatherington Steve Knaebel Sara Birmingham General Program Information: Is sometimes confused with the CEC program Best place

More information

Union Power Cooperative

Union Power Cooperative Union Power Cooperative INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities of the local

More information

Welcome to Speeding Up Your California Solar Initiative Application Form

Welcome to Speeding Up Your California Solar Initiative Application Form 10.08.09 Welcome to Speeding Up Your California Solar Initiative Application Form We will be starting the webinar momentarily Thank you for your patience To download today s presentation, please visit

More information

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:

More information

PREPARED DIRECT TESTIMONY OF PAUL BORKOVICH ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY SAN DIEGO GAS & ELECTRIC COMPANY

PREPARED DIRECT TESTIMONY OF PAUL BORKOVICH ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.1-- Exhibit No.: Witness: Paul Borkovich Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) Regarding Feasibility of Incorporating Advanced

More information

Generator Interconnection Procedures Overview

Generator Interconnection Procedures Overview Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution

More information

LEVEL I PREQUALIFICATION DOCUMENTS

LEVEL I PREQUALIFICATION DOCUMENTS Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,

More information

A. Section includes administrative and procedural requirements for substitutions.

A. Section includes administrative and procedural requirements for substitutions. SPECIFICATIONS NO. XX-XX-XXX-XX SECTION 01 25 00 - SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

Self Generation Incentive Program (SGIP) Jason Legner Sr. Program Manager

Self Generation Incentive Program (SGIP) Jason Legner Sr. Program Manager 1 Self Generation Incentive Program (SGIP) Jason Legner Sr. Program Manager SGIP History Self Generation Incentive Program (SGIP) Statewide - California Public Utilities Commission (CPUC) incentive program

More information

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw)

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw) An applicant (Generator Owner) makes application to to install and operate a generating facility greater than 100 kw interconnected with the utility system. Section 1, Applicant Information Directly Interconnected

More information

E. Helm R. Mundy D. Bernaudo (U 338-E) Before the. Public Utilities Commission of the State of California

E. Helm R. Mundy D. Bernaudo (U 338-E) Before the. Public Utilities Commission of the State of California Application No.: Exhibit No.: Witnesses: A.0-01-0 SCE-1 G. Higashi E. Helm R. Mundy D. Bernaudo (U -E) Corrected Testimony of Southern California Edison Company in Support of Application for Authorization

More information

METER UPGRADE MANUAL

METER UPGRADE MANUAL CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 METER UPGRADE MANUAL Version 4 EFFECTIVE DATE 5/01/2016 Meter Upgrade Manual This manual describes the process and the rules

More information

Commercial Construction Reference Guide

Commercial Construction Reference Guide Commercial Construction Reference Guide City of Murphy Customer Service Department 206 N Murphy Road Murphy, TX 75094 Ph. 972 468 4100 * Fax 972 468 4104 customerservice@murphytx.org Prior to submittal

More information

4 Secrets to Pain-Free Payment Management

4 Secrets to Pain-Free Payment Management 4 Secrets to Pain-Free Payment Management Textura is the leading provider of collaboration and productivity tools for the construction industry. Our solutions serve all construction industry professionals

More information

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW

More information

CUSTOMER GUIDE FOR DISTRIBUTION SYSTEM INTERCONNECTION INVERTER-BASED DISTRIBUTED RESOURCES. < 50 kw

CUSTOMER GUIDE FOR DISTRIBUTION SYSTEM INTERCONNECTION INVERTER-BASED DISTRIBUTED RESOURCES. < 50 kw CUSTOMER GUIDE FOR DISTRIBUTION SYSTEM INTERCONNECTION OF INVERTER-BASED DISTRIBUTED RESOURCES < 50 kw October 10, 2011 1 Index Introduction 1 Process Overview 1 Minimum Requirements for Interconnection

More information

LEVEL 2 Application For Interconnection And Net Metering

LEVEL 2 Application For Interconnection And Net Metering LEVEL 2 Application For Interconnection And Net Metering Use this Application form when generating facility is not inverter-based or is not certified by a nationally recognized testing laboratory to meet

More information

Interconnection Application

Interconnection Application Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

Cluster Study Process

Cluster Study Process Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO

More information

New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric

New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric Requirements for Application Submittal Part A For use in all New

More information

LEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA

LEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA Project No. 4484/A4L-379/964840 LEVEL I PREQUALIFICATION DOCUMENTS for OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North

More information

INTERCONNECTION APPLICATION AND AGREEMENT

INTERCONNECTION APPLICATION AND AGREEMENT INTERCONNECTION APPLICATION AND AGREEMENT With Terms and Conditions for Interconnection For a Level 1 Review (Certified Inverter-based Units under 10kW) Mailing Address PSE&G Net Metering 750 Walnut Avenue

More information

FRANCHISING OF OPERATION AND MAINTENANCE OF PARKING AREA AT BOAT HOUSE, OOTY

FRANCHISING OF OPERATION AND MAINTENANCE OF PARKING AREA AT BOAT HOUSE, OOTY TAMILNADU TOURISM DEVELOPMENT CORPORATION LIMITED DOCUMENT NO: 275/RM(N)/OOTY/2018 TENDER DOCUMENT FRANCHISING OF OPERATION AND MAINTENANCE OF PARKING AREA AT BOAT HOUSE, OOTY CONTENTS 01 TENDER NOTICE

More information

TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR ENERGY CONVERSION SYSTEM S

TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR ENERGY CONVERSION SYSTEM S TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR ENERGY CONVERSION SYSTEM S 1) This will apply to the installation of solar photovoltaic systems. 2) All units to be installed according to the

More information

Welcome-Joseph Montoya- Chief Building Official Project Green Award Presented to Building Division

Welcome-Joseph Montoya- Chief Building Official Project Green Award Presented to Building Division Town of Castle Rock Development Services Building Division Contractors Luncheon Philip S Miller Park-Mill House 1375 W Plum Creek Parkway June 14, 2017 11:30 AM-1PM Sponsor Lokal Homes Welcome-Joseph Montoya-

More information

CYMA Accounting for Windows

CYMA Accounting for Windows CYMA Accounting for Windows Technical White Paper CYMA Accounting for Windows 2014 Payroll Update CYMA Systems, Inc. 2330 W. University Drive Suite 4 Tempe, AZ 85281 800-292-2962 Fax: 480-303-2969 www.cyma.com

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

REVISION NO.: 8 EFFECTIVE: 03/26/18

REVISION NO.: 8 EFFECTIVE: 03/26/18 Distributed Generation Interconnection Process for Residential and Small General Service OVERVIEW REVISION NO.: 8 EFFECTIVE: 03/26/18 Required Steps for ED3 s Distributed Generation Interconnection Process

More information

PARTICIPANT HANDBOOK

PARTICIPANT HANDBOOK 2017-2018 PARTICIPANT HANDBOOK POLICIES AND PROCEDURES FOR PARTICIPATION IN THE STATEWIDE SAVINGS BY DESIGN PROGRAM Last Revised: February 23, 2018 www.savingsbydesign.com This program is funded by California

More information

LEVEL I PREQUALIFICATION DOCUMENTS COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION

LEVEL I PREQUALIFICATION DOCUMENTS COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION Project No. 4863/A4L-396 LEVEL I PREQUALIFICATION DOCUMENTS for COMPUTER SCIENCE ENGINEERING (CSE) ADDITION AND RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North

More information

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS Program Guide TABLE OF CONTENTS Introduction... 2 Purpose... 2 About CHP... 2 Program Description... 2 Call for CHP Projects... 3 Participant Webinar...

More information

BUILDING/FIRE/ZONING PERMIT GUIDE

BUILDING/FIRE/ZONING PERMIT GUIDE BUILDING/FIRE/ZONING PERMIT GUIDE Summary Guidelines The following is an instructional guide that will serve to assist you in securing the various permits issued by the Bureau of Code Administration. In

More information

PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS

PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS Building Division 555 Santa Clara Street Vallejo CA 94590 707.648.4374 1. PERMIT INFORMATION: The installation of a photovoltaic solar electric system requires

More information

PONDICHERRY UNIVERSITY (A

PONDICHERRY UNIVERSITY (A PONDICHERRY UNIVERSITY (A Central University) Centre for Bioinformatics PUDUCHERRY 605 014 Website: www.pondiuni.edu.in TENDER NOTICE PU/DIC/2016/E- 07.11.2016 Procurement of GE Manufactured Biacore 3000

More information

Quick Guide to 2015 Fiscal Year Utility Requisitions and Purchase Orders plus Payment Processing

Quick Guide to 2015 Fiscal Year Utility Requisitions and Purchase Orders plus Payment Processing Quick Guide to 2015 Fiscal Year Utility Requisitions and Purchase Orders plus Payment Processing Table of Contents Overview:... 1 Department responsibility:... 1 Purchasing responsibility:... 2 Accounts

More information

NOTICE INVITING QUOTATIONS. File No. NITT/F.No. 020/PROJ/ /DAC Date:

NOTICE INVITING QUOTATIONS. File No. NITT/F.No. 020/PROJ/ /DAC Date: NATIONAL INSTITUTE OF TECHNOLOGY, TIRUCHIRAPPALLI - 620 015 DEPARTMENT OF ACADEMIC OFFICE NOTICE INVITING QUOTATIONS File No. NITT/F.No. 020/PROJ/2018-19/DAC Date: 10.10.2018 To Sealed quotations are invited

More information

Environmental Assessment Environmental Review Agreement Template September 2013

Environmental Assessment Environmental Review Agreement Template September 2013 Environmental Assessment Environmental Review Agreement Template September 2013 The following are general terms and conditions typically used by Western in an Environmental Review Agreement for an Environmental

More information

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business

More information

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section 19825 V 11-10-12 6p2s H:\2012 Permit Masters\v 11-10-12 e-inspection Residential PV Installation

More information

Lake County School District s. Construction Audit for. Eustis Heights Elementary School. Executive Summary & Detailed Audit Report

Lake County School District s. Construction Audit for. Eustis Heights Elementary School. Executive Summary & Detailed Audit Report 1 Lake County School District s Construction Audit for Eustis Heights Elementary School Executive Summary & Detailed Audit Report Fiscal Year 2014 2015 Completed By: Thomas A. Mock, CIA Date: August 27,

More information

SIDEWALK CONSTRUCTION PERMIT APPLICATION & INSTRUCTIONS

SIDEWALK CONSTRUCTION PERMIT APPLICATION & INSTRUCTIONS John M. Pete O Connor III Commissioner Thomas Simone Martin E. Davis, L.S. DEPARTMENT OF PUBLIC WORKS Stephanie A. Miner, Mayor SIDEWALK CONSTRUCTION PERMIT APPLICATION & INSTRUCTIONS REQUIRED FOR: Replacing

More information

Application for Commercial Plan Review and Building Permit. Address:

Application for Commercial Plan Review and Building Permit. Address: City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial

More information

atlantic cit~ elect,ic

atlantic cit~ elect,ic atlantic cit~ elect,ic A PHI Company NEW JERSEY LEVEL 1 INTERCONNECTION APPLICATION/AGREEMENT With Terms and Conditions for Interconnection For a Level 1 Review (Certified Inverter-Based Generators 10kW

More information

APPLICATION PACK FOR THE ECOLABEL

APPLICATION PACK FOR THE ECOLABEL APPLICATION PACK FOR THE ECOLABEL Application form for televisions (ecolabelling criteria 12 March 2009) Page 1 of 17 Insert name and contact details of the Member State Competent Body(s) You can see which

More information

AUDITING INVOICES 101

AUDITING INVOICES 101 AUDITING INVOICES 101 AUDITING CONSULTANT INVOICES Definitions MCA: Master Consulting Agreement parent agreement that contains general terms and conditions by which consultants provide services CSA: Consultant

More information

2017 PARTICIPANT HANDBOOK

2017 PARTICIPANT HANDBOOK 2017 PARTICIPANT HANDBOOK POLICIES AND PROCEDURES FOR PARTICIPATION IN THE STATEWIDE SAVINGS BY DESIGN PROGRAM Last Revised: January 20, 2017 www.savingsbydesign.com This program is funded by California

More information

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

LEVEL I PREQUALIFICATION DOCUMENTS GEISEL RESTROOM RENOVATIONS

LEVEL I PREQUALIFICATION DOCUMENTS GEISEL RESTROOM RENOVATIONS Project No. 5005/A4L-424/ 962520 LEVEL I PREQUALIFICATION DOCUMENTS for GEISEL RESTROOM RENOVATIONS University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La

More information

Capacity Market. Understanding your 2016 Prequalification Assessment Results - September 2016

Capacity Market. Understanding your 2016 Prequalification Assessment Results - September 2016 Capacity Market Understanding your 2016 Prequalification Assessment Results - September 2016 Whilst you wait. PLEASE ENSURE YOUR PHONE IS ON MUTE SO AS NOT TO DISTURB OTHERS ON THE CALL WITH EXTERNAL NOISE

More information

Bidding Conditions Attachment C

Bidding Conditions Attachment C Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION Town of Warwick Building Department (845) 986-1127 NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal

More information

SKILLED MIGRATION ASSESSMENT APPLICATION FORM 2016

SKILLED MIGRATION ASSESSMENT APPLICATION FORM 2016 The Australian Institute of Quantity Surveyors (ABN 97 008 485 809) SKILLED MIGRATION ASSESSMENT APPLICATION FORM 2016 APPLICATION GUIDELINES The Australian Institute of Quantity Surveyors (AIQS) is specified

More information

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE ANNEXURE A T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 SCOPE OF WORK FOR

More information

Implementing MDM System at SDG&E. Itron Users Conference September, 2009 Ron Amundson Smart Meter Operations Project Manager SDG&E

Implementing MDM System at SDG&E. Itron Users Conference September, 2009 Ron Amundson Smart Meter Operations Project Manager SDG&E Implementing MDM System at SDG&E 2008 San Diego Gas & Electric Company. All copyright and trademark rights reserved Itron Users Conference September, 2009 Ron Amundson Smart Operations Project Manager

More information

Warren State Hospital, Statement of Work Electrical Distribution Infrared Inspection ANTICIPATED PERIOD OF CONTRACT

Warren State Hospital, Statement of Work Electrical Distribution Infrared Inspection ANTICIPATED PERIOD OF CONTRACT ANTICIPATED PERIOD OF CONTRACT The anticipated term of contract: October 1, 2016 (or upon full execution of contract; whichever is later) through June 30, 2021. The Inspection Service and Reports will

More information

Professional Qualifications Supplement (PQS) Instructions. GENERAL INSTRUCTIONS UF-368, Reitz Union Expansion and Renovation

Professional Qualifications Supplement (PQS) Instructions. GENERAL INSTRUCTIONS UF-368, Reitz Union Expansion and Renovation BUSINESS AFFAIRS www.facilities.ufl.edu FACILITIES PLANNING AND CONSTRUCTION DIVISION Professional Qualifications Supplement (PQS) Instructions GENERAL INSTRUCTIONS UF-368, Reitz Union Expansion and Renovation

More information

Lone Star Decorating (LDS) is the official service contractor for the ASMC Spring Conference 2018.

Lone Star Decorating (LDS) is the official service contractor for the ASMC Spring Conference 2018. January 22 nd, 2018 Austin Renaissance Austin, TX March 5 th and March 7 th, 2018 Dear Exhibitor: Lone Star Decorating (LDS) is the official service contractor for the. Enclosed you will find a freight

More information

Address of Installation Building Permit #

Address of Installation Building Permit # TOWN OF NISKAYUNA NY State Unified Solar Permit Application One Niskayuna Circle, Niskayuna NY 12309 Phone: 518-386-4522 Fax: 518-386-4592 Email: buiding@niskayuna.org The Town of Niskayuna has adopted

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: Longfellow ES Exit Balcony Addition DATE: March 4, 2019 755 Morse Street, SF, CA 94112 SFUSD Project No.12059

More information

Experimental Advanced Renewable Program (EARP) Anaerobic Digester. David Ronk

Experimental Advanced Renewable Program (EARP) Anaerobic Digester. David Ronk 1 Experimental Advanced Renewable Program () Anaerobic Digester David Ronk -AD Agenda 2 Overview David Ronk How to Participate Keith Troyer -AD Process Keith Troyer & Matt Good Overview 3 What is? Why

More information

Description. Need Statement

Description. Need Statement Description Brief description of the proposed project: Create an online Certificate of Financial Responsibility (COFR) Database and Web front end to make it more self-service and to free up DFG technical

More information

Feed-In Tariff (FIT) MUNICIPAL COUNCIL SUPPORT RESOLUTION GUIDE & APPLICATION

Feed-In Tariff (FIT) MUNICIPAL COUNCIL SUPPORT RESOLUTION GUIDE & APPLICATION This document contains both information and form fields. To read information, use the Down Arrow from a form field. Feed-In Tariff (FIT) MUNICIPAL COUNCIL SUPPORT RESOLUTION GUIDE & APPLICATION MATERIALS

More information

10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS

10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS 10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS Engineering, Procurement and Construction Management (EPCM) costs for Balance of Plant (BOP) installations seriously

More information

GoouN, MRcBRror, Sounru & Dny llp. Çrandfatherine Proviçign shoul4 be lpplemented Çonsistent with D March 21,2016

GoouN, MRcBRror, Sounru & Dny llp. Çrandfatherine Proviçign shoul4 be lpplemented Çonsistent with D March 21,2016 GoouN, MRcBRror, Sounru & Dny llp Jeanne B. Armstrong, Attorney at Law Edward Randolph, Director California Public Utilities Commission 505 Van Ness Avenue, Room 4004 San Francisco, CA 94102 Re: San Diego

More information

1/24/2014. Schedules Schedule of Values Submittals Payment Applications Requests for Information Change Order Requests Change Orders

1/24/2014. Schedules Schedule of Values Submittals Payment Applications Requests for Information Change Order Requests Change Orders 1 1 Construction Management Schedules Schedule of Values Submittals Payment Applications Requests for Information Change Order Requests Change Orders Budget Forecasting Substantial Completion Close out

More information

SAP CERTIFIED APPLICATION ASSOCIATE - SAP ARIBA SUPPLIER MANAGEMENT

SAP CERTIFIED APPLICATION ASSOCIATE - SAP ARIBA SUPPLIER MANAGEMENT SAP EDUCATION SAMPLE QUESTIONS: C_ARSUM_17Q4 SAP CERTIFIED APPLICATION ASSOCIATE - SAP ARIBA SUPPLIER MANAGEMENT Disclaimer: These sample questions are for self-evaluation purposes only and do not appear

More information

1) The products are labeled with an on-product label that was placed there by an FSCcertified

1) The products are labeled with an on-product label that was placed there by an FSCcertified Forest Stewardship Council United States Trademark License Application for Product Promotion This application form is for non-chain of Custody (CoC) certified companies seeking to use the FSC trademarks

More information

Delivery Delivery Obstacles Deviations from the Specified Quantity of Goods Consignment Note...

Delivery Delivery Obstacles Deviations from the Specified Quantity of Goods Consignment Note... 23.6 Incorrect Shipment Information... 5 23.9 Multi Parcel surcharge... 5 2.1 Definitions... 2 2.2 Headings... 2 11.2 Foodstuffs... 2 12.1 Ordering and Booking... 3 12.1.1 Delivery to Consumer... 3 12.1.2

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF FARMINGDALE NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

Consultant/Independent Contractor Training Guide

Consultant/Independent Contractor Training Guide Training Guide What is it? Consultant/Independent Contractor Employee/Employer Relationships vs. Independent Contractors will govern the decision to determine whether or not an individual may be engaged

More information

SAN ANTONIO WATER SYSTEM PRE-CONSTRUCTION MINUTES

SAN ANTONIO WATER SYSTEM PRE-CONSTRUCTION MINUTES JOB #: SAN ANTONIO WATER SYSTEM PRE-CONSTRUCTION MINUTES TITLE: DATE: TIME: PROJECT ENGINEER: DESIGNER / CONSULTANT: INSPECTOR: _ 704-7110 704-7199 AWARD DATE: BASIC BID AWARD AMOUNT: $ ADDENDUMS: Addendum

More information

Terms & Conditions: Kogan nbn Plans

Terms & Conditions: Kogan nbn Plans 1. What Terms and Conditions Apply to my Kogan nbn Product? (g) (h) This document sets out terms and conditions that apply to Kogan nbn contracts and products (collectively, the Products ). The terms and

More information

CHAPTER 14 VENDOR RETURNS & EXPENSE OFFSET TABLE OF CONTENTS

CHAPTER 14 VENDOR RETURNS & EXPENSE OFFSET TABLE OF CONTENTS CHAPTER 14 VENDOR RETURNS & EXPENSE OFFSET TABLE OF CONTENTS GENERAL OFFSET POLICY 14-2 DAMAGE ALLOWANCE 14-2 RETURN TO VENDOR 14-3 REPAIR AND RETURN 14-4 VENDOR CHARGEBACK POLICY 14-5 CHARGEBACK DISPUTES

More information

Residential Sewer Backup Prevention Program

Residential Sewer Backup Prevention Program City of Wheaton Residential Sewer Backup Prevention Program Please Note: The City reserves the right to modify the policies, procedures and rules of this program or discontinue the program in its entirety

More information

Entry means the photo submitted adhering to all requirements as set out in clause 6.10;

Entry means the photo submitted adhering to all requirements as set out in clause 6.10; Virgin Holidays #PackMoreMojo Competition terms and conditions By entering the Competition, Entrants agree to be bound by these Terms & Conditions. Please read these Terms and Conditions carefully prior

More information

SAME JETC May 22-25, 2012 America s Center St. Louis, Missouri

SAME JETC May 22-25, 2012 America s Center St. Louis, Missouri 5931 West Campus Circle Drive, Irving, Texas 75063 Phone: (972) 580-9000 Fax: (972) 465-1117 Log onto cyberservices @ www.theexpogroup.com 1 2 Choice of Destination Why Ship To The Warehouse? SAME JETC

More information

15 th Annual Farmers Market on Broadway May 30 September 26, 2018 Broadway District, Downtown Green Bay

15 th Annual Farmers Market on Broadway May 30 September 26, 2018 Broadway District, Downtown Green Bay Thank you for your interest in the 2018 Farmers Market on Broadway (FMOB). Please read carefully for all information regarding becoming a vendor. We are looking forward to another successful season! General

More information

DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY

DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY Dominica Electricity Services 2016 Version 2.00 DOCUMENT TITLE AND APPROVAL PAGE DOCUMENT NUMBER: 2016/002/D DOCUMENT TITLE: DISTRIBUTED RENEWABLE ENERGY

More information

2010 PAY FOR PERFORMANCE PROGRAM COMBINED HEAT & POWER APPLICATION PACKAGE

2010 PAY FOR PERFORMANCE PROGRAM COMBINED HEAT & POWER APPLICATION PACKAGE 2010 PAY FOR PERFORMANCE PROGRAM COMBINED HEAT & POWER APPLICATION PACKAGE This Pre-Installation Application Form includes the Requirements, Instructions and Terms and Conditions for Combined Heat & Power

More information

Hurricane Mitigation Supplement This form must be filled out and included with all Single Family re-roofing applications.

Hurricane Mitigation Supplement This form must be filled out and included with all Single Family re-roofing applications. Hurricane Mitigation Supplement This form must be filled out and included with all Single Family re-roofing applications Address: Permit For the purpose of this document sections cited are from the manual

More information

SOLAR ENERGY SYSTEMS APPLICATION

SOLAR ENERGY SYSTEMS APPLICATION For reasonable accommodations or alternative formats please contact 311 at 612-673-3000. People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000. TTY users call 612-673-2157

More information

Certification Application Form

Certification Application Form Certification Application Form 1. Application Sought Construction Certificate S.96 Construction Certificate Office Use Only Complying Development Certificate (CDC) Amended CDC If ticked, please select

More information

PARTICIPANT HANDBOOK

PARTICIPANT HANDBOOK 2013-2014 PARTICIPANT HANDBOOK POLICIES AND PROCEDURES FOR PARTICIPATION IN THE STATEWIDE SAVINGS BY DESIGN PROGRAM Last Revised: January 15, 2014 www.savingsbydesign.com This program is funded by California

More information

Business Practice Manual for Metering. Version 1415

Business Practice Manual for Metering. Version 1415 Business Practice Manual for Metering Version 1415 Revised: May 25August 1October 1, 2016 Approval History Approval Date : March 13, 2009 Effective Date : March 13, 2009 BPM Owner BPM Owner s Title : Benik

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF UPPER BROOKVILLE PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that

More information

Commercial & Industrial Custom Incentive Program

Commercial & Industrial Custom Incentive Program About This Application UGI Electric offers incentives for cost-effective custom energy efficiency improvements to help businesses reduce energy use by improving the efficiency of their equipment and facility.

More information

Accounts Payable-Vendor Partnership

Accounts Payable-Vendor Partnership Accounts Payable-Vendor Partnership Can we work together to pay you more quickly? The City of Miami values its relationship with you, our supplier. Our Purchasing Department and Accounts Payable have designed

More information

Smart Pricing Program

Smart Pricing Program Smart Pricing Program Customer Outreach and Education Quarterly Briefing - Monday, March 4, 2013 2011San Diego Gas & Electric Company. All copyright and trademark rights reserved. SDG&E Business Overview

More information

Understanding Your TIERED Bill

Understanding Your TIERED Bill Understanding Your TIERED Bill 1. Your amount due Shows your current monthly amount due and the due date. 2. Your SCE account information If you ever need customer service or want to enroll in SCE programs

More information

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY APPLICATION FOR AUTHORITY TO REVISE THEIR CURTAILMENT PROCEDURES

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY APPLICATION FOR AUTHORITY TO REVISE THEIR CURTAILMENT PROCEDURES QUESTION 16.1: 16.1. With respect to the SDG&E advanced meter infrastructure ( AMI ) system, which was described by Paul Borkovich in his rebuttal testimony in A.15-07-014: SDG&E has completed installation

More information

LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP

LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PMO-RALG ENHANCEMENT OF PROCUREMENT CAPACITY OF LOCAL GOVERNMENT AUTHORITIES PROJECT (EPC LGAP) LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PROCUREMENT COMPLIANCE & PERFORMANCE AS PER

More information