1 TOTORAL WIND FARM PROJECT Document Prepared By Knut Vrålstad Project Title Totoral Wind Farm Project Version 2.0 Date of Issue Prepared By Knut Vrålstad, SN Power Invest AS Contact Lilleakervn. 8 PO Box 200, Lilleaker 0216 Oslo Norway 1

2 Table of Contents 1 Project Details Summary Description of the Project Sectoral Scope and Project Type Project Proponent Other Entities Involved in the Project Project Start Date Project Crediting Period Project Scale and Estimated GHG Emission Reductions or Removals Description of the Project Activity Project Location Conditions Prior to Project Initiation Compliance with Laws, Statutes and Other Regulatory Frameworks Ownership and Other Programs Proof of Title Emissions Trading Programs and Other Binding Limits Participation under Other GHG Programs Other Forms of Environmental Credit Projects Rejected by Other GHG Programs Additional Information Relevant to the Project Application of Methodology Title and Reference of Methodology Applicability of Methodology Project Boundary Baseline Scenario Additionality Methodology Deviations Quantification of GHG Emission Reductions and Removals Baseline Emissions Project Emissions Leakage Summary of GHG Emission Reductions and Removals Monitoring Data and Parameters Available at Validation Data and Parameters Monitored Description of the Monitoring Plan Environmental Impact Stakeholder Comments

3 1 PROJECT DETAILS 1.1 Summary Description of the Project 1.2 Sectoral Scope and Project Type Sectoral scope: Project type: Grouping: 01 Energy Industries (Renewable / non-renewable) Wind Power The project is not a grouped project 1.3 Project Proponent Project proponent Contact information Role / responsibilities Norvind S.A Mr. Roberto Leiva roberto.leiva@snpower.com Vitacura 2939, office 2801 CP Las Condes, Santiago Chile Project owner, responsible for monitoring SN Power Chile Inversiones Eléctricas Ltda. Mrs. Vinka Hildebrandt vinka.hildebrandt@snpower.com Vitacura 2939, office 2801 CP Las Condes, Santiago Chile Shareholder of Norvind, VERPA off taker 1.4 Other Entities Involved in the Project 1.5 Project Start Date The Project start date is

4 1.6 Project Crediting Period Project start date: on which the project activity began reducing or removing GHG emission. The Project has been registered successfully as a CDM project on December 7th, That is, the period from to (including both days) is considered as the Project crediting period for VCUs. 1.7 Project Scale and Estimated GHG Emission Reductions or Removals Project Mega-project X Years Estimated GHG emission reductions or removals (tco2e) , ,011 Total estimated ERs 56,740 Total number of crediting years 1 Average annual ERs 56, Description of the Project Activity 1.9 Project Location The wind farm is located in the Canela community, Choapa Province, Coquimbo region, Chile. The project activity is located 294 km north from Santiago de Chile and 79 km north from Los Vilos, between the Pan-American Highway and the Pacific Ocean. The coordinates of the project are the following: 4

5 Table 1: Coordinates 1 of the Project Area Wind Turbine Generator East (m) North (m) (WTG) M M M M M M M M M M M M M M M M M M M M M M M The following figures show the location of the project activity: 1 UTM 19 WGS 84 5

6 Figure 1: Map of Chile and Location of the Totoral Wind Farm Project 1.10 Conditions Prior to Project Initiation The project activity consists of the installation of a new wind power plant at a site which was not inhabited or developed in any way, and where no renewable power plant was operated prior to the implementation of the project activity. It does not result in the creation of any GHG emissions. The purpose of the project activity was to generate and supply clean energy to the electricity grid Compliance with Laws, Statutes and Other Regulatory Frameworks 1.12 Ownership and Other Programs Proof of Title The title of the project activity is Totoral Wind Farm Project. The CDM Host Country Letter of Approval from the Ministry of Environment of Chile, dated 2nd December 2011, endorses the project under this title and authorises the participation of the project proponents. This documentary evidence is furnished to the DOE. 6

7 Emissions Trading Programs and Other Binding Limits The Project has been registered as a CDM project on 07/12/2010, for which a renewable crediting period of 3 7 years will be used under the CDM GHG Program. Therefore, CO2 emission reductions generated by the Project during the CDM crediting period will be verified as unique CERs but not VCUs to avoid double counting. As to the project under VCS (Version 3), only emission reductions achieved before CDM registration - from 08/12/2009 to 06/12/ will be considered as VCUs, which will be sold only once. The net GHG emission reductions generated by the project will not be used for compliance of any emission trading program or to meet binding limits on GHG emissions. No program of this kind has been implemented in the country during the monitoring period Participation under Other GHG Programs The Project has been registered as a CDM project with registration number Other Forms of Environmental Credit The Project has not created, nor will it create any other form of GHG-related environmental credits based on the production during the VCS crediting period Projects Rejected by Other GHG Programs 1.13 Additional Information Relevant to the Project Eligibility Criteria The project is not a grouped project, so no eligibility criteria are specified. Leakage Management No fossil fuel will be consumed by the Project activity, so no leakage need to be considered in the Project. Commercially Sensitive Information No commercially sensitive information has been excluded from the public version of the project description. Further Information Not applicable 7

8 2 APPLICATION OF METHODOLOGY 2.1 Title and Reference of Methodology PROJECT DESCRIPTION: VCS Version Applicability of Methodology 2.3 Project Boundary 2.4 Baseline Scenario 2.5 Additionality 2.6 Methodology Deviations 3 QUANTIFICATION OF GHG EMISSION REDUCTIONS AND REMOVALS 3.1 Baseline Emissions 8

9 3.2 Project Emissions 3.3 Leakage 3.4 Summary of GHG Emission Reductions and Removals 4 MONITORING 4.1 Data and Parameters Available at Validation 4.2 Data and Parameters Monitored 4.3 Description of the Monitoring Plan 5 ENVIRONMENTAL IMPACT 9

10 6 STAKEHOLDER COMMENTS 10

DAK PSI 3 AND 4 HYDROPOWER PROJECT

DAK PSI 3 AND 4 HYDROPOWER PROJECT DAK PSI 3 AND 4 HYDROPOWER PROJECT Document Prepared By Kyoto Energy Pte. Ltd. Project Title Dak Psi 3 and 4 Hydropower Project Version 2.3 Date of Issue Prepared By Contact 27-February-2013 Kyoto Energy

More information

Sarbari II hydro power project by DSL Hydrowatt Limited in Kullu, Himachal Pradesh

Sarbari II hydro power project by DSL Hydrowatt Limited in Kullu, Himachal Pradesh Sarbari II hydro power project by DSL Hydrowatt Limited in Kullu, Himachal Pradesh Document Prepared By (DSL Hydrowatt Limited) Project Title Sarbari II hydro power project by DSL Hydrowatt Limited in

More information

INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT

INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT Document Prepared By Inner Mongolia Xinjin Wind Power Co., Ltd. Project Title Inner Mongolia Hangjin Yihewusu Wind Power Project Version 2.0 Date of Issue

More information

AMAYO PHASE II WIND POWER PROJECT

AMAYO PHASE II WIND POWER PROJECT AMAYO PHASE II WIND POWER PROJECT Report No: 8000402033-11/558 Date: 2012-03-21 TÜV NORD CERT GmbH JI/CDM Certification Program Langemarckstraße, 20 45141 Essen, Germany Phone: +49-201-825-3335 Fax: +49-201-825-3290

More information

PROJECT DESCRIPTION: VCS Version 3

PROJECT DESCRIPTION: VCS Version 3 VCS Project Description Template This template is for the development of VCS projects. Instructions for completing the project description: TITLE PAGE: All items in the box at the bottom of the title page

More information

Background information on existing PoA regulations

Background information on existing PoA regulations Agenda item 5(a) Review of the modalities and procedures of the clean development mechanism Background information on existing PoA regulations SBI 42 Bonn, Germany, 1 11 June 2015 Definition of PoA A voluntary

More information

Validation and Verification: VCS

Validation and Verification: VCS Validation and Verification: VCS Mr N.VASASMITH GHG Assessor Scope 13.1 Meeting room 3, Zone B, Queen Sirikit National Convention Center 2012 January 24 Prepare by Ms S.THONGSONG 1 Introduction VCS is

More information

Overview of CDM Documentation and Procedures

Overview of CDM Documentation and Procedures Overview of CDM Documentation and Procedures 19-20 April 2006 London, England John Kessels CDM Documentation Project Design Document CDM Institutions CDM New Methodology Baseline (CDM NMB) CDM New Monitoring

More information

Waste management - Hydro, Wind, Solar Energy. - Capturing of landfill methane emission - Biomass power. to generate power - Geothermal, Tidel Energy

Waste management - Hydro, Wind, Solar Energy. - Capturing of landfill methane emission - Biomass power. to generate power - Geothermal, Tidel Energy Workshop on Improving the Regional Distribution of CDM s in Asia and the Pacific Technical Session 1 : Overview of CDM Key Elements of CDM Cycle Hemant Nandanpawar International CDM Specialist Technical

More information

VALIDATION AND VERIFICATION REPORT FOR SOLAR GROUPED PROJECT BY ACME GROUP (EKIESL-VCS-AUG-16-01)

VALIDATION AND VERIFICATION REPORT FOR SOLAR GROUPED PROJECT BY ACME GROUP (EKIESL-VCS-AUG-16-01) VALIDATION AND VERIFICATION REPORT FOR SOLAR GROUPED PROJECT BY ACME GROUP (EKIESL-VCS-AUG-16-01) Document Prepared by: Carbon Check (India) Private Ltd. Project Title Report Title Solar Grouped project

More information

UNFCCC/CCNUCC DRAFT STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA. I.

UNFCCC/CCNUCC DRAFT STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA. I. Page 1 STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA I. Background 1. In decision 3/CMP.1 paragraph 4, Parties requested the clean

More information

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD)

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD) CDM Executive Board Page 1 PROGRAMME DESIGN DOCUMENT FORM FOR CDM PROGRAMMES OF ACTIVITIES (F-CDM-PoA-DD) Version 02.0 PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD) PART I. Programme of activities (PoA)

More information

Lesson 1: Introduction to GHG Projects and Project Level Accounting. Page 1 Learning Objectives

Lesson 1: Introduction to GHG Projects and Project Level Accounting. Page 1 Learning Objectives Lesson 1: Introduction to GHG s and Level Accounting Page 1 Learning Objectives Upon completion of this lesson, you will be able to understand: Rationale for undertaking GHG projects Difference between

More information

500kW Photovoltaic Plant on Vava u Island in the Kingdom of Tonga

500kW Photovoltaic Plant on Vava u Island in the Kingdom of Tonga 500kW Photovoltaic Plant on Vava u Island in the Kingdom of Tonga Document Prepared By Easy Carbon Consultancy Co., Ltd. Project Title 500kW Photovoltaic Plant on Vava u Island in the Kingdom of Tonga

More information

VERIFICATION REPORT YUNNAN MANGLI HYDROPOWER PROJECT

VERIFICATION REPORT YUNNAN MANGLI HYDROPOWER PROJECT VERIFICATION REPORT YUNNAN MANGLI HYDROPOWER PROJECT Document Prepared By: Bureau Veritas Certification Holding SAS Report No.BVC/China-VR/7066/2012 Project Title Version Report ID Yunnan Mangli Hydropower

More information

Gold Standard Validation Report

Gold Standard Validation Report Gold Standard Validation Report CARBON ASSET MANAGEMENT SWEDEN AB Gold Standard Validation of the Ningxia Yinyi 49.50 MW Wind-farm Project, China Report No. 1053561 04 April 2008 TÜV SÜD Industrie Service

More information

CLEAN DEVELOPMENT MECHANISM PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-CPA-DD) Version 01 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-CPA-DD) Version 01 CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-CPA-DD) Version 01 CONTENTS A. General description of CDM programme activity (CPA) B. Eligibility of CPA

More information

CDM VALIDATION AND VERIFICATION EXPERIENCE FOR SALKHIT WIND FARM PROJECT

CDM VALIDATION AND VERIFICATION EXPERIENCE FOR SALKHIT WIND FARM PROJECT CDM VALIDATION AND VERIFICATION EXPERIENCE FOR SALKHIT WIND FARM PROJECT B AYA R M A A A M A R J A R G A L SENIOR CARBON FINANCE SPECIALIST, CLEAN ENERGY LLC, NEWCOM GROUP HEAD OF ENVIRONMENTAL WORKING

More information

The World Bank 1818 H Street, NW, Washington, DC 20433, USA

The World Bank 1818 H Street, NW, Washington, DC 20433, USA Mr. Jose Domingos Miguez Chairperson CDM Executive Board Mr. Hans Jurgen Stehr Vice Chair CDM Executive Board The World Bank 1818 H Street, NW, Washington, DC 20433, USA Members of the CDM Executive Board

More information

REPORT OF THE SEVENTH MEETING OF THE EXECUTIVE BOARD Annex 5

REPORT OF THE SEVENTH MEETING OF THE EXECUTIVE BOARD Annex 5 - 1 - Annex 5 Appendix A 1 to the simplified modalities and procedures for small-scale CDM project activities CLEAN DEVELOPMENT MECHANISM SIMPLIFIED PROJECT DESIGN DOCUMENT FOR SMALL SCALE PROJECT ACTIVITIES

More information

CDM project review - technology and regulation aspects

CDM project review - technology and regulation aspects Pacific Regional CDM Capacity Building Workshop CDM project review - technology and regulation aspects Xianli Zhu 24-28, Jan 2011, Suva, Fiji Outline DNA Approval Expert support as part of the host country

More information

VER MONITORING REPORT

VER MONITORING REPORT VER MONITORING REPORT RIALMA COMPANHIA ENERGÉTICA S/A. SANTA EDWIGES II SMALL HYDRO POWER PLANT SMALL SCALE CDM PROJECT Monitoring Period: From 3 December, 2005 to 31 March, 2007 Version 2 April 14th,

More information

VALIDATION OPINION FOR REVISION OF REGISTERED MONITORING PLAN

VALIDATION OPINION FOR REVISION OF REGISTERED MONITORING PLAN VALIDATION OPINION FOR REVISION OF REGISTERED MONITORING PLAN Rio Taquesi Hydroelectric Power Project UNFCCC Ref. No. 1031 SGS Climate Change Programme SGS United Kingdom Ltd SGS House 217-221 London Road

More information

LA FERME BAMBOUS SOLAR PHOTOVOLTAIC POWER PLANT

LA FERME BAMBOUS SOLAR PHOTOVOLTAIC POWER PLANT LA FERME BAMBOUS SOLAR PHOTOVOLTAIC POWER PLANT Document Prepared By on behalf of Project Title La Ferme Bambous solar photovoltaic power plant Version Version 1.1 Report ID Date of Issue Project ID Bambous_VCS_MR2

More information

Annex 27 GENERAL GUIDELINES FOR SSC CDM METHODOLOGIES. (Version 19.0) CONTENTS

Annex 27 GENERAL GUIDELINES FOR SSC CDM METHODOLOGIES. (Version 19.0) CONTENTS Page 1 GENERAL GUIDELINES FOR SSC CDM METHODOLOGIES (Version 19.0) CONTENTS Paragraphs I. Introduction... 1 3 2 A. Background... 1 2 2 B. Objectives... 3 2 II. Scope and applicability... 4 5 2 III. Terms

More information

GOLD STANDARD PASSPORT

GOLD STANDARD PASSPORT GOLD STANDARD PASSPORT CONTENTS A. Project title B. Project description C. Proof of project eligibility D. Unique Project Identification E. Outcome stakeholder consultation process F. Outcome sustainability

More information

Clean Development Mechanism

Clean Development Mechanism Clean Development Mechanism Srikanth Subbarao Regional CDM Expert for the Pacific Islands (Consultant) Technical Support Facility (TSF) /Carbon Market Initiative Energy, Transport and Water Division Why

More information

Procedures and Criteria for Screening, Evaluating and Approving CDM Projects: A Case Study in Kazakhstan

Procedures and Criteria for Screening, Evaluating and Approving CDM Projects: A Case Study in Kazakhstan Procedures and Criteria for Screening, Evaluating and Approving CDM Projects: A Case Study in Kazakhstan Matthew S. Mendis Alternative Energy Development Division (AED) International Resources Group, Ltd.

More information

INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT

INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT Document Prepared By Inner Mongolia Xinjin Wind Power Co., Ltd. Project Title Inner Mongolia Hangjin Yihewusu Wind Power Project Version 2.0 Report ID

More information

Concepts of Clean Development Mechanism. Confederation of Indian Industry

Concepts of Clean Development Mechanism. Confederation of Indian Industry Concepts of Clean Development Mechanism Kyoto Protocol UNFCCC & Kyoto Protocol Kyoto Treaty was drawn up in Kyoto, Japan, on 11 th December, 1997 to implement United Nations Framework Convention for Climate

More information

Climate Financing CDM and NAMA in Rwanda

Climate Financing CDM and NAMA in Rwanda Climate Financing CDM and NAMA in Rwanda Kigali, 7th October 2014 Faustin MUNYAZIKWIYE Director of Climate Change and International Obligations Dpt / REMA Outlines Introduction to Climate Change Mapping

More information

CDM Module 1. Introduction to Programmatic CDM (PoA) Lesson 2. How does the Programmatic CDM Work? Select Next to begin. Menu November 2011.

CDM Module 1. Introduction to Programmatic CDM (PoA) Lesson 2. How does the Programmatic CDM Work? Select Next to begin. Menu November 2011. CDM Module 1 Introduction to Programmatic CDM (PoA) Lesson 2 How does the Programmatic CDM Work? November 2011 Select Next to begin Next> Lesson Partners and Collaborators How does the Programmatic CDM

More information

An Introduction to Offsets

An Introduction to Offsets An Introduction to Offsets Janet Peace PMR Technical Workshop on Domestic Emission Trading (ETS) Shenzhen, China March 13, 2012 Outline Brief introduction to GHG offsets Offsets what are they? Quality

More information

REDD Methodology Module. Estimation of emissions from activity shifting for avoided unplanned deforestation

REDD Methodology Module. Estimation of emissions from activity shifting for avoided unplanned deforestation REDD Methodology Module Estimation of emissions from activity shifting for avoided unplanned deforestation Version 1.0 April 2009 I. SCOPE, APPLICABILITY, DATA REQUIREMENT AND OUTPUT PARAMETERS Scope This

More information

CARBON OFFSETS WWF-AUSTRALIA POSITION

CARBON OFFSETS WWF-AUSTRALIA POSITION CARBON OFFSETS WWF-AUSTRALIA POSITION Properly designed and implemented carbon offsets reduce carbon pollution. Conversely, poorly designed and/or implemented carbon offsets can contribute to carbon pollution

More information

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM (CDM-SSC-PoA-DD) Version 01 CONTENTS

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM (CDM-SSC-PoA-DD) Version 01 CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM (CDM-SSC-PoA-DD) Version 01 CONTENTS A. General description of small-scale programme of activities

More information

Monitoring and Verification Plan Graneros Plant Fuel Switching Project June Prepared by

Monitoring and Verification Plan Graneros Plant Fuel Switching Project June Prepared by Monitoring and Verification Plan Graneros Plant Fuel Switching Project June 2003 Prepared by MGM International, Inc. Ayacucho 1435, 9 B C1111AAM Buenos Aires Argentina Table of Contents 1. Introduction

More information

Voluntary Carbon Standard

Voluntary Carbon Standard Voluntary Carbon Standard Voluntary Carbon Standard 2007.1 18 November 2008 Voluntary Carbon Standard - Specification for the project-level quantification, monitoring and reporting as well as validation

More information

Experience of the Clean Development Mechanism as a result based mechanism for methane abatement

Experience of the Clean Development Mechanism as a result based mechanism for methane abatement Experience of the Clean Development Mechanism as a result based mechanism for methane abatement Methane finance study group meeting Washington, DC December 19, 2012 Today s main focus Clean Development

More information

Voluntary Carbon Standard Version 2007 Verification Report

Voluntary Carbon Standard Version 2007 Verification Report Voluntary Carbon Standard Version 2007 Verification Report 19 November 2007 Verification Report: 1313671 Name of Verification Date of the issue: company: TÜV SÜD Industrie 30-11-2010 Service GmbH Report

More information

CDM AND VER VALIDATION PROTOCOL

CDM AND VER VALIDATION PROTOCOL APPENDIX A CDM AND VER VALIDATION PROTOCOL SAYALAR 30.4 MW WIND FARM PROJECT TURKEY FINAL REPORT NO. 2007-44003 REVISION NO. 01 Table 1 Mandatory Requirements for High Standard Voluntary Emission Reduction

More information

CDM Carbon Finance Workshop. Session 9: Discussion of project risks and mitigation strategies. Accra, June

CDM Carbon Finance Workshop. Session 9: Discussion of project risks and mitigation strategies. Accra, June CDM Carbon Finance Workshop Session 9: Discussion of project risks and mitigation strategies Accra, June 24-26 2009 Contents Introductory quiz CDM and project risk explained Key concepts covered Case study

More information

Voluntary Carbon Standard VALIDATION REPORT BUNDLED WIND POWER PROJECT

Voluntary Carbon Standard VALIDATION REPORT BUNDLED WIND POWER PROJECT VALIDATION REPORT BUNDLED WIND POWER PROJECT Positive Climate Care 9.75 MW Bundled Wind Power Project Activity by Savita Oil Technologies Ltd. & its group companies in the state of Maharashtra, India.

More information

PROGRAMME OF ACTIVITIES (POA) REQUEST FOR REGISTRATION - INFORMATION AND REPORTING CHECK CHECKLIST

PROGRAMME OF ACTIVITIES (POA) REQUEST FOR REGISTRATION - INFORMATION AND REPORTING CHECK CHECKLIST PROGRAMME OF ACTIVITIES (POA) REQUEST FOR REGISTRATION - INFORMATION AND REPORTING CHECK CHECKLIST PCP : Clean development mechanism project cycle procedure (version 02.0), EB 66, annex 64, 2 March 2012.

More information

Tres Valles Cogeneration Project. Frederik Staun, UNEP Risoe Centre, Carbon finance Belize City August, 2010

Tres Valles Cogeneration Project. Frederik Staun, UNEP Risoe Centre, Carbon finance Belize City August, 2010 Tres Valles Cogeneration Project Frederik Staun, fsta@risoe.dtu.dk UNEP Risoe Centre, Carbon finance Belize City 24 26 August, 2010 Description of the project Tres Valles Cogeneration Project consists

More information

How to develop a Carbon Finance project?

How to develop a Carbon Finance project? How to develop a Carbon Finance project? Assessment of tool - Is this landfill project feasible? Source: www.unescap.org/esd Minimum Project Requirements 1 2 3 4 5 7 8 9 10 11 12 Type of Project CER Volume

More information

Zafarana Wind Power Plants AS CDM Projects. Eng. Rafik Youssef Georgy Consultant, NREA

Zafarana Wind Power Plants AS CDM Projects. Eng. Rafik Youssef Georgy Consultant, NREA Zafarana Wind Power Plants AS CDM Projects Eng. Rafik Youssef Georgy Consultant, NREA ا ORGANIZATION CHART OF MINISTRY OF ELECTRICITY & ENERGY Egyptian Electricity Holding Company Nuclear Materials Authority

More information

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG)

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG) Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG) The RE CDM PoA in PNG Programme of Activities (PoA) for Sustainable RE Power in Papua New Guinea (PNG) envisages

More information

Financing Programmes for CDM Projects

Financing Programmes for CDM Projects Financing Programmes for CDM Projects November 2003 European Commission (Directorate-General for Energy and Transport) Contract no. NNE5/2002/52: OPET CHP/DH Cluster TITLE: Financing Programmes for CDM

More information

From: Climate Focus Subject: Response to the Call for Public Inputs on PoA Date: 03 September 2008

From: Climate Focus Subject: Response to the Call for Public Inputs on PoA Date: 03 September 2008 Memo To: CDM Executive Board and the Small Scale Working Group From: Climate Focus Subject: Response to the Call for Public Inputs on PoA Date: 03 September 2008 Introduction Climate Focus appreciates

More information

Policies and Strategies Credibility, efficiency & integrity of the CDM

Policies and Strategies Credibility, efficiency & integrity of the CDM Policies and Strategies Credibility, efficiency & integrity of the CDM Grant A. Kirkman Team Leader CDM Methodologies 2nd Latin American Carbon Forum Thurs 6 September 12:00-13:00 Lima, Peru United Nations

More information

The Clean Development Mechanism (CDM)

The Clean Development Mechanism (CDM) Jan. 28, 2005 The Clean Development Mechanism (CDM) Converting emission reductions to Certified Emission Reductions (CERs) under the rules governing the Kyoto Protocol Presentation s Outline Jan. 28, 2005

More information

Bulgarian JI Guidelines. 2006, September

Bulgarian JI Guidelines. 2006, September Bulgarian JI Guidelines 2006, September Table of Contents BULGARIAN JI GUIDELINES... 1 1. International Requirements... 1 2. JI Process in Bulgaria... 3 3. Participants... 4 Step 6: Request for Letter

More information

Basics of Carbon Finance. Klaus Oppermann, World Bank Carbon Finance Unit Tenth Annual Financial Agent Workshop Washington DC, June 28, 2006

Basics of Carbon Finance. Klaus Oppermann, World Bank Carbon Finance Unit Tenth Annual Financial Agent Workshop Washington DC, June 28, 2006 Basics of Carbon Finance Klaus Oppermann, World Bank Carbon Finance Unit Tenth Annual Financial Agent Workshop Washington DC, June 28, 2006 Overview Kyoto Protocol. Clean Development mechanism CDM. World

More information

2007 CDM/JI Feasibility Study Biogas Electricity Generation through Anaerobic Digestion of Waste Executive Summary Report

2007 CDM/JI Feasibility Study Biogas Electricity Generation through Anaerobic Digestion of Waste Executive Summary Report 2007 CDM/JI Feasibility Study Biogas Electricity Generation through Anaerobic Digestion of Waste Executive Summary Report 1. Outline of The Host Country 1.1. Background of The Project The main objective

More information

Gangwon Wind Park Project

Gangwon Wind Park Project Report No. TA201-200501, Revision 03 Final Validation Report Gangwon Wind Park Project December 9, 2005 KOREA ENERGY MANAGEMENT CORPORATION Contents 1. Summary of the Project Activity 2 2. Principles 3

More information

Criteria Catalogue: VER+

Criteria Catalogue: VER+ Criteria Catalogue: VER+ Prepared / changed: IS-CMS-MUC approved: IS-CMS-MUC page 1 of 10 CONTENTS Acronyms...3 Definitions...3 A. CRITERIA CATALOGUE... 4 1. Eligibility Criteria...4 2. Additionality...4

More information

KAMIRANGA CERAMIC FUEL SWITCHING PROJET VERIFICATION REPORT

KAMIRANGA CERAMIC FUEL SWITCHING PROJET VERIFICATION REPORT KAMIRANGA CERAMIC FUEL SWITCHING PROJET VERIFICATION REPORT Document Prepared By IBOPE Instituto Brasileiro de Opinião Pública e Estatística Ltda. Project Title Kamiranga Ceramic Fuel Switching Project

More information

COMPONENT PROJECT ACTIVITIES DESIGN DOCUMENT (CPA-DD)

COMPONENT PROJECT ACTIVITIES DESIGN DOCUMENT (CPA-DD) CDM Executive Board Page 1 COMPONENT PROJECT ACTIVITY DESIGN DOCUMENT FORM FOR AFFORESTATION AND REFORESTATION COMPONENT PROJECT ACTIVITIES (F-CDM-AR-CPA-DD) Version 02.1 COMPONENT PROJECT ACTIVITIES DESIGN

More information

Carbon Trading an overview of financial instruments designed to combat climate change

Carbon Trading an overview of financial instruments designed to combat climate change Carbon Trading an overview of financial instruments designed to combat climate change Mark van Soestbergen International Carbon Bank & Exchange www.icbe.com UF Bioenergy and Sustainability School Soil

More information

Introduction to Climate Change & CDM

Introduction to Climate Change & CDM African Development Bank African Carbon Support Programme ONEC3 Introduction to Climate Change & CDM AfDB Tunis 21 st September 2011 0 The African Carbon Support Programme ACSP: Two year programme funded

More information

Capacity Building Workshop on Development of CDM Activities and NAMA for Public And Private Sector In Zimbabwe

Capacity Building Workshop on Development of CDM Activities and NAMA for Public And Private Sector In Zimbabwe CDM Project Cycle Capacity Building Workshop on Development of CDM Activities and NAMA for Public And Private Sector In Zimbabwe Nyanga, Zimbabwe 24 25 August 2016 UNFCCC Secretariat UNFCCC RCC UNFCCC

More information

Introduction to the Project Cycle

Introduction to the Project Cycle Introduction to the Project Cycle Jane Ebinger Senior Energy Specialist Sustainable Development Department The World Bank February 2007 Outline Introduction to the project cycle Illustrate concepts through

More information

Introduction to the Project Cycle

Introduction to the Project Cycle Introduction to the Project Cycle Jane Ebinger Senior Energy Specialist Sustainable Development Department The World Bank Outline Introduction to the project cycle Illustrate concepts through the preparation

More information

VERIFICATION REPORT FOR SATARA WIND POWER PROJECT IN MAHARASHTRA, INDIA

VERIFICATION REPORT FOR SATARA WIND POWER PROJECT IN MAHARASHTRA, INDIA VERIFICATION REPORT FOR SATARA WIND POWER PROJECT IN MAHARASHTRA, INDIA Document Prepared By: LGAI Technological Center, S.A. (Applus) Project Title Satara Wind Power Project in Maharashtra, India Version

More information

4. The Clean Development Mechanism for Biomass projects in Asia

4. The Clean Development Mechanism for Biomass projects in Asia 4. The Clean Development Mechanism for Biomass projects in Asia 4.1 Introduction Up to mid- 2006 more then 800 CDM projects are in the pipeline, globally 1. Registered projects are more than 200, average

More information

Registration - Information and reporting checklist (Version 2.0) The main changes between version 1.0 and version 2.0 are the following:

Registration - Information and reporting checklist (Version 2.0) The main changes between version 1.0 and version 2.0 are the following: Registration - Information and reporting checklist (Version 2.0) Version 1.0 of the information and reporting checklist was published in June 2010. The enclosed version 2.0 of this checklist represents

More information

Study on Programmatic CDM for. Promotion of Energy Saving measures. at TEDA, Tianjin, China. Summary

Study on Programmatic CDM for. Promotion of Energy Saving measures. at TEDA, Tianjin, China. Summary FY2007 CDM/ JI Study Study on Programmatic CDM for Promotion of Energy Saving measures at TEDA, Tianjin, China Summary January 2008 E&E Solutions Inc. Summary 1. Fundamental elements of the project 1.1

More information

Becoming Green and Gold: Applying the CDM to Wind Energy

Becoming Green and Gold: Applying the CDM to Wind Energy Becoming Green and Gold: Applying the CDM to Wind Energy Introductory document Renewable Energy City Summit 13 14 May 2008 This report is solely for the use of client personnel. No part of it may be circulated,

More information

Outline. Hydro potential in CDM Issues in new hydro projects Case studies Next step? Short brief on EcoSecurities

Outline. Hydro potential in CDM Issues in new hydro projects Case studies Next step? Short brief on EcoSecurities The Clean Development Mechanism: Emission down, profit up Paul Butarbutar Senior Project Manager EcoSecurities Indonesia EcoSecurities Group plc Outline Hydro potential in CDM Issues in new hydro projects

More information

CER Monitoring Report

CER Monitoring Report CER Monitoring Report Waste gases utilisation for Combined Cycle Power Plant in Handan Iron & Steel Group Co., Ltd (Registration Reference No. 1262) Monitoring period 15/10/2007 ~ 29/02/2008 (first periodic

More information

VCS & CCB Program Updates. Sam Hoffer, VCS & CCB Program Manager Christopher Chapman, Program Officer

VCS & CCB Program Updates. Sam Hoffer, VCS & CCB Program Manager Christopher Chapman, Program Officer VCS & CCB Program Updates Sam Hoffer, VCS & CCB Program Manager Christopher Chapman, Program Officer What we ll cover today 1) VCS Program update 2) CCB Program update 3) Q/A Please type in your questions

More information

PROJECT TITLE: 86 MW HYDRO PROJECT IN HIMACHAL PRADESH

PROJECT TITLE: 86 MW HYDRO PROJECT IN HIMACHAL PRADESH PROJECT TITLE: 86 MW HYDRO PROJECT IN HIMACHAL PRADESH Document Prepared By Malana Power Company Limited Contact Information Bhilwara Towers, A-12, Sector -1 Noida-201301 Uttar Pradesh India Contact Number

More information

Gold Standard Passport CONTENTS

Gold Standard Passport CONTENTS Gold Standard Passport CONTENTS A. Project title B. Project description C. Proof of project eligibility D. Unique Project Identification E. Outcome stakeholder consultation process F. Outcome sustainability

More information

MRV IN THE CONTEXT OF INDCS

MRV IN THE CONTEXT OF INDCS MRV IN THE CONTEXT OF INDCS TYPES OF MRV MRV takes on a different meanings depending on the user and context: MRV of GHG emissions MRV of GHG emissions reductions of mitigation efforts MRV of non-ghg effects

More information

The Project Design Document

The Project Design Document Downloaded from orbit.dtu.dk on: Feb 11, 2018 The Project Design Document Olsen, Karen Holm Publication date: 2012 Link back to DTU Orbit Citation (APA): Olsen, K. H. (2012). The Project Design Document

More information

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD)

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD) CDM Executive Board Page 1 PROGRAMME DESIGN DOCUMENT FORM FOR SMALL-SCALE CDM PROGRAMMES OF ACTIVITIES (F-CDM-SSC-PoA-DD) Version 02.0 PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD) PART I. Programme

More information

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD)

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD) CDM Executive Board Page 1 PROGRAMME DESIGN DOCUMENT FORM FOR SMALL-SCALE CDM PROGRAMMES OF ACTIVITIES (F-CDM-SSC-PoA-DD) Version 02.0 PROGRAMME OF ACTIVITIES DESIGN DOCUMENT (PoA-DD) PART I. Programme

More information

Validation Report. Datang Zhangzhou Wind Power Co., Ltd. VALIDATION OF THE CDM-PROJECT: Fujian Zhangpu Liuao 45MW Wind Power Project.

Validation Report. Datang Zhangzhou Wind Power Co., Ltd. VALIDATION OF THE CDM-PROJECT: Fujian Zhangpu Liuao 45MW Wind Power Project. Validation Report Datang Zhangzhou Wind Power Co., Ltd VALIDATION OF THE CDM-PROJECT: Fujian Zhangpu Liuao 45MW Wind Power Project REPORT NO. 948571 2007, August 30 TÜV SÜD Industrie Service GmbH Carbon

More information

YUNNAN TENGZHONG NEW ENERGY TECHNOLOGY Co. Ltd. BIOMASS HEATING SYSTEM RETROFITTING AND BIOMASS COLLECTION STATION PROJECT

YUNNAN TENGZHONG NEW ENERGY TECHNOLOGY Co. Ltd. BIOMASS HEATING SYSTEM RETROFITTING AND BIOMASS COLLECTION STATION PROJECT YUNNAN TENGZHONG NEW ENERGY TECHNOLOGY Co. Ltd. BIOMASS HEATING SYSTEM RETROFITTING AND BIOMASS COLLECTION STATION PROJECT Document Prepared By Beijing Karbon Energy Consulting Co., Ltd. Project Title

More information

Linking Renewable Energy Promotion Policies with International Carbon Trade. Gareth Phillips Chief Climate Change Officer

Linking Renewable Energy Promotion Policies with International Carbon Trade. Gareth Phillips Chief Climate Change Officer Linking Renewable Energy Promotion Policies with International Carbon Trade Gareth Phillips Chief Climate Change Officer 16 June 2011 Development - Finance - Technology Overview RE / energy technology

More information

Validation Report. Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited

Validation Report. Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited Validation Report Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited Report No. 806970, Revision 01 2006, April 12 TÜV ndustrie Service

More information

Renewable Energy Projects and potentials in Mauritius

Renewable Energy Projects and potentials in Mauritius Renewable Energy Projects and potentials in Mauritius Sanjay Sookhraz Environmental Affairs Officer Central Electricity Board 22 September 2008 Energy Mix for the year 2007 Energy Mix for 2007 Bagasse

More information

Clean development mechanism and joint implementation

Clean development mechanism and joint implementation Clean development mechanism and joint implementation Andrew Howard Climate Change Secretariat www.unfccc.int ahoward@unfccc.int 18-19 June 2008 Montreal, Canada ICAO workshop Aviation and carbon markets

More information

SOLAR POWER PROJECT BY MYTRAH ENERGY INDIA PRIVATE LIMITED

SOLAR POWER PROJECT BY MYTRAH ENERGY INDIA PRIVATE LIMITED SOLAR POWER PROJECT BY MYTRAH ENERGY INDIA PRIVATE LIMITED Document Prepared by Mytrah Energy India Private Limited Project Title Solar Power Project by Mytrah Energy India Private Limited Version 01 Date

More information

MONITORING REPORT. Bundled wind power project in Tamil Nadu, India. Voluntary Carbon Units (VCUs):

MONITORING REPORT. Bundled wind power project in Tamil Nadu, India. Voluntary Carbon Units (VCUs): MONITORING REPORT Bundled wind power project in Tamil Nadu, India Voluntary Carbon Units (VCUs): 10 th April 2006 15 th November 2008 (Both days included) Monitoring Report Version: Version 1.2 Date: 11

More information

Santangou First and Second Grade Hydropower Stations Project MONITORING REPORT

Santangou First and Second Grade Hydropower Stations Project MONITORING REPORT Santangou First and Second Grade Hydropower Stations Project MONITORING REPORT Document Prepared By (Zhijie Duan, South Pole Carbon Asset Management Ltd.) Contact Information (j.duan@southpolecarbon.com)

More information

Clean Development Mechanism (CDM)

Clean Development Mechanism (CDM) 566 S 8QLW Clean Development Mechanism (CDM) 1 st Arab CP Workshop, Amman - Jordan 4-6 / 4 / 2006 www.cp.org.jo The Greenhouse Gases (GHGs) The atmospheric gases responsible for causing global warming

More information

Al-Shaheen CDM Project Experience

Al-Shaheen CDM Project Experience ١ LESSONS LEARNED FROM AL-SHAHEEN (ALS) OIL FIELD, GAS RECOVERY AND UTILIZATION PROJECT By Adnan Fahad Al-Ramzani Manager, Clean Development Mechanism HSE Regulation & Enforcement Directorate Contents

More information

Gia Schneider, Partner, EKO Asset Management. Carbon Sequestration on Farms & Forests Clayton Hall Newark, DE

Gia Schneider, Partner, EKO Asset Management. Carbon Sequestration on Farms & Forests Clayton Hall Newark, DE Carbon Offset Markets Gia Schneider, Partner, EKO Asset Management Carbon Sequestration on Farms & Forests Clayton Hall Newark, DE October 21, 2008 1 Agenda Current Carbon Market Role of Offsets Current

More information

Agriculture and the carbon market

Agriculture and the carbon market Agriculture and the carbon market Carbon Credits for Sustainable Land Use Systems (CaLas) Presented by Patrick Horka, head of PoAs, South Pole Carbon Asset Management Ltd. 15 December, 2012 Contents Basic

More information

Validation of CDM Projects Real life examples of what a DOE looks for

Validation of CDM Projects Real life examples of what a DOE looks for Validation of CDM Projects Real life examples of what a DOE looks for Jonathan Avis, CDM Business Manager ERM Certification and Verification Services 2nd Floor, Exchequer Court 33 St Mary Axe London EC3A

More information

Report on Project Consultations. Wei Zhou. Technical Support Facility Carbon Market Program Asian Development Bank

Report on Project Consultations. Wei Zhou. Technical Support Facility Carbon Market Program Asian Development Bank Report on Project Consultations Wei Zhou Technical Support Facility Carbon Market Program Asian Development Bank Objective of Project Consultations To assist PPs in assessing concept notes of proposed

More information

This document replaces Annex F dated 23 November 2009 in the rule updates section.

This document replaces Annex F dated 23 November 2009 in the rule updates section. PoA Rules and Guidance Annex F (revised on 23 December, 2010) This document replaces Annex F dated 23 November 2009 in the rule updates section. 1 PoA eligibility Where a group of project activities is

More information

Ontario and Quebec Forest & Reforestation/ Afforestation Offset Protocol Adaptation

Ontario and Quebec Forest & Reforestation/ Afforestation Offset Protocol Adaptation Ontario and Quebec Forest & Reforestation/ Afforestation Offset Protocol Adaptation Stakeholder Meeting March 30, 2017 11am-12pm PST 2 Agenda Introductions Protocol Adaptation Process & Expectations for

More information

Small-Scale CDM & Bundling: Criteria, Advantages & Status

Small-Scale CDM & Bundling: Criteria, Advantages & Status Small-Scale CDM & Bundling: Criteria, Advantages & Status Need for Small-Scale CDM introduced by CDM EB to encourage the development of smaller CDM projects typically would have been less attractive in

More information

GOVERNMENT OF PAKISTAN MINISTRY OF ENVIRONMENT

GOVERNMENT OF PAKISTAN MINISTRY OF ENVIRONMENT Clean Development Mechanism (CDM) National Operational Strategy GOVERNMENT OF PAKISTAN MINISTRY OF ENVIRONMENT (January, 2006) CONTENTS 1.0 INTRODUCTION 1 2.0 DESIGNATED NATIONAL AUTHORITY FOR CLEAN DEVELOPMENT

More information

Risk Based Verification Cambodia cook stove project

Risk Based Verification Cambodia cook stove project Risk Based Verification Cambodia cook stove project Chee.Keong.Lai@dnv.com www.dnv.com/certification/climatechange Contents 1. Introduction of Det Norske Veritas AS 2. Risk Based Validation/Verification

More information

YAPRAK WEIR AND HEPP

YAPRAK WEIR AND HEPP YAPRAK WEIR AND HEPP Document Prepared By: KBS Certification Services Pvt. Ltd. Project Title Yaprak Weir and HEPP Version 01.1 Report ID VCS.15.VER.005 Report Title Client Pages 19 Date of Issue Prepared

More information

PART I. Programme of activities (PoA)

PART I. Programme of activities (PoA) F-CDM-PoA-DD Programme design document form for CDM programmes of activities (Version 03.0) PART I. Programme of activities (PoA) SECTION A. General description of PoA A.1. Title of the PoA A.2. Purpose

More information