ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION

Size: px
Start display at page:

Download "ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION"

Transcription

1 INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document that the specified components and systems have been designed, installed, properly started up, and functionally tested to assure proper operation of equipment through all modes and conditions, including seasonal systems tests. The process begins as a part of the construction phase and extends through project completion, closeout, and warranty reviews. Documentation of Cx activities is provided to the building owner as a Final Report that outlines the events and findings of the project, including a comprehensive review of all findings, recommendations, and resolutions of identified problems. Cx is not intended to replace or eliminate any requirements or responsibilities for reviews, inspections, or other quality control measures by any other firm, organization, or party. Designers, contractors, and project managers maintain their obligations as a function of their roles and responsibilities. DEFINITIONS AND ROLE CLARIFICATION Definitions: District (School District or Owner) Architect/Engineering Firm (A/E) Contractor Commissioning (Cx) Commissioning Authority (CxA) Test and Balance (TAB) Owner s Project Requirements (OPR) Basis of Design (BOD) Project Team (A/E, Contractor, Owners) The CxA serves as the Owner s contractual representative and will act in the Owner s best interest by following accepted industry and professional standards. The CxA may not be an employee of or in contract with the A/E or GC on the project and will work independently from both; however, the CxA will collaborate with the A/E and GC throughout the construction process to meet deadlines and provide feedback to the Owner and the A/E as the process moves forward. The CxA will provide a final review and confirmation as the contractor makes corrections previously identified by the CxA and logged into a Commissioning Log Report. Page 1 of 8 Limited Commissioning Guidelines 3/23/2015

2 The Contractor is the primary facilitator and scheduler of all project-related activities. The Contractor is responsible for all project scheduling, documents, and communications. The Contractor has primary responsibility for ensuring that the project construction team makes all necessary corrections identified by the CxA. The Contractor will incorporate the CxA s scheduled Cx activities and milestones into the project master schedule. The School District (Owner) is expected to be fully engaged and active in the Cx process. The Owner will work with the A/E to define the Owner s Project Requirements (OPR). The Project Architect/Engineer of Record (A/E) is responsible for development of the Design Intent. The Design Intent includes the OPR, the Basis of Design (BOD), and the related documents for the project. It is the specific responsibility of the CxA to customize the Cx process outlined below to meet the OPR. QUALIFICATIONS AND RESPONSIBILITIES OF THE CxA Experience requirements: The CxA to have documented CxA experience in at least 2 building projects and 3 years of recent direct Cx project experience; The CxA shall meet with the Owner to clearly understand the Owner s Expectations as outlined in the OPR document; The CxA shall keep the Owner apprised of and involved in decision-making regarding system optimization, corrections, and issues as they arise; The CxA shall collaborate with the Contractor and the Project Team regarding scheduling of all Cx activities; The CxA shall inform the Project Team of system corrections and/or optimizations that should be addressed in a timely fashion; The CxA shall have access to an appropriate inventory of tools, equipment, instruments, and software necessary to perform Cx tasks. All CxA-provided equipment and instrumentation shall be current on all applicable certifications. CxA-provided equipment and instrumentation shall remain the property of the CxA; The CxA is expected to have an expert level proficient understanding of the trades and related technology for Cx; Page 2 of 8 Limited Commissioning Guidelines 3/23/2015

3 Should specialty or proprietary software, equipment, or tools be required for Cx activities; the CxA shall work with the Contractor or vendor to obtain training and access in the use of such tools. COMMISSIONING OUTCOMES FOR DISTRICT BUILDING PROGRAM PROJECTS The following are quality assurance outcomes for the Round Lake High School building project: 1. Develop Cx plan (set objectives, schedule reviews, verify performance, create reports and summaries of findings) based on the OPR and the BOD; 2. Participate in critical tasks of the Project Team; 3. Document successful completion of all elements of the OPR; 4. Ensure functioning system interfaces and effective controls operation; 5. Confirm corrections have been made by the Contractor as denoted in the Commissioning Report; 6. Provide the Owner with a complete Final Commissioning Report, documenting the findings, recommendations and resolutions of the Cx process. SCOPE OF COMMISSIONING WORK PERFORMED BY THE CxA 1. Mechanical and Heating, Ventilating, and Air Conditioning (HVAC) systems. 2. Building Automation and Environmental Controls Systems. 3. Participation in Contractor-provided Facility Staff Training. SCOPE OF WORK (Process Requirements) 1. Organize and Lead the Cx process. 2. Cx Plan for Functional Testing of Systems. 3. Cx Logs and Reports to support Functional Testing. 4. Sample testing following TAB efforts. 5. Final review to confirm corrections have been made by the Contractor as denoted in the Commissioning Report. 6. Provide Final Commissioning Report. 7. As an Alternate Cost, provide seasonal reviews, one for cooling and one for heating. DATA AND DOCUMENT COLLECTION AND VERIFICATION The CxA is expected to collect all data, documents, and information necessary to complete its task. The CxA will work with the Contractor and the Project Team to define the timing and schedule for document collection, review and reporting for the Cx effort. The GC is the central source for project-related documents and correspondences. The Contractor is to Page 3 of 8 Limited Commissioning Guidelines 3/23/2015

4 collect and distribute the documents and other necessary information for the CxA and the Project Team. As necessary for commissioned systems, the following are included: 1. Review of Construction Drawings, specifications, and documents. 2. Review records that are appropriate to understand design intent, as detailed in the BOD. 3. Construction Phase investigation, verification, and review. MEETINGS GUIDELINE The CxA will meet with members of the Project Team as often as needed and as reasonably requested by the Owner or other members of the Project Team. The meetings must be Cx relevant and include an agenda for discussion. The agenda is to be provided by the meeting organizer and in advance of the scheduled meeting. The CxA will work with the Contractor to minimize the number of on-site meetings in the effort to reduce travel for all parties. Use of technology is encouraged to reduce travel requirements. Use of technology is also encouraged in conjunction with necessary site visits and personnel meetings. The meeting expectations shall be clearly defined in the CxA s Cx plan. 1. As a function of the initial Cx plan developed by the CxA, the CxA will plan and coordinate with the GC the schedule for Cx-related and required meetings. 2. Multiple Cx scope topics as defined in these guidelines may be combined into a single meeting as quality and efficiency allow. 3. The CxA will regularly communicate with all members of the Project Team as required by project status, activity, and need. 4. Coordinate with the project Contractor to blend or schedule Cx meetings with other regular project related meetings whenever possible. COMMISSIONING SERVICES (Basic Services Performed by the CxA) CONSTRUCTION PHASE: 1. Conduct periodic site visits and inspections (as identified by the Cx plan and at appropriate intervals as determined by the CxA and in coordination with the Contractor) throughout the construction phase to verify that systems and equipment are installed in a manner that will allow the Cx process to proceed smoothly and in accordance with the Cx plan and construction milestones, and will be documented via a submitted written report noting all pertinent observations and deficiencies. 2. The Cx process shall not void or violate any manufacturer s or contractor warranties or guarantees. 3. Coordinate the Cx planning and work with the Contractor to ensure that Cx activities are being incorporated into the project schedule. Confirm that the Contractor has included updated Cx milestones in the critical path. 4. Notify the Contractor as to when CxA personnel are on-site. Page 4 of 8 Limited Commissioning Guidelines 3/23/2015

5 5. Coordinate all Cx meetings and activities in accordance with the preliminary and/ or modified Cx plan; (The CxA will record and distribute meeting minutes). 6. Coordinate and direct the Cx activities in a logical, sequential, and efficient manner using consistent protocols and forms, centralized documentation, and clear and regular communications; update the construction phase Cx plan as necessary. 7. Request and review additional information required to perform Cx tasks, including O&M materials, contractor start-up, and checkout procedures. 8. Document construction checklist completion by reviewing completed construction checklists and CxA selected site observations. 9. Verify air and water systems balancing by reviewing completed reports, by spot testing, and by selected on-site observations. Provide a report of observations. 10. Write the functional performance test procedures customized to the exact equipment and systems approved by the A/E during the submittal process. Include any necessary assistance with installing contractors; no related warrantees are to be violated. 11. Coordinate witness and document functional performance tests performed by installing contractor(s). Coordinate retesting as necessary. Coordinate retesting with the Contractor until satisfactory performance is achieved. 12. Tests on respective HVAC equipment shall be executed to reflect both the heating and cooling season operations. Overriding of control values to simulate conditions shall be allowed. 13. Maintain a master issues log and separate record of functional testing. Report all issues as they occur directly to the Contractor with duplicate copies to the Owner. Report all issues to the Owner at regularly scheduled meetings or as necessary or otherwise directed. Provide written progress reports and test results observations and recommended actions to the Contractor. 14. Reconfirm items on the master issues log have been completed after Contractor reports items are complete. 15. Attend the contractor-provided training of the School District s operations personnel as related to the facility new equipment and systems to add input to the staff on the operation of the systems. 16. Compile a Final Commissioning Report that consists of the following: a. OPR (by Owner and A/E); b. BOD (by A/E); c. CxA narrative of the above Items a. and b.; d. Functional Testing procedure and final Functional Testing results; e. Confirmation that the Master Issues Log items have been addressed and completed by the Contractor; Page 5 of 8 Limited Commissioning Guidelines 3/23/2015

6 f. Testing and Balancing review procedure and final evaluation of TAB report; g. System startup procedures and results. WARRANTY PERIOD: 1. Provide required opposite season or deferred testing and deficiency corrections if required and provide the final testing documentations for the Cx Record and O&M manuals as an Alternate Cost to the project. 2. Verify controls sequence and operation remain functionally consistent with design and operational intent and that drift has not occurred; 3. Return to site for the eleven-month walk-through and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal Cx as an Alternate Cost to the project. REPORTING GUIDELINES The CxA is expected to report all progress and events in an efficient and timely manner. Reporting frequency may vary according to the project status and Cx work performed. The reporting must be (but is not limited to) to the Contractor. The Contractor is responsible for the proper and timely distribution of documents, reports, and other correspondences to the Project Team, including: 1. Owner s Project Requirements; 2. A/E Project Basis of Design; 3. Commissioning Plan by the CxA; 4. Construction Phase Cx Reports at appropriate intervals per Cx plan and 100% completion; 5. Monthly Cx Status Report starting at the functional testing phase; 6. Periodic Issues Database Report; 7. Functional Testing Phase Reports for each System; 8. Seasonal Testing and Eleven Month Period Report (Alternate Cost); 9. Final Cx Report (Closeout). FUNCTIONAL TEST AND SAMPLING The CxA will identify the testing process and what is to be tested (i.e., critical, primary, noncritical). 1. CxA will complete functional tests of system components as previously described; 2. All critical and primary HVAC systems (new install only) shall be tested. Page 6 of 8 Limited Commissioning Guidelines 3/23/2015

7 3. Functional testing of all equipment and systems to be Cx will include but not be limited to verifying proper operation of systems, checking for calibration of all sensors and controls, commanding damper and valve actuators fully opened and closed, observing responses, verify that all systems and devices go to a fail-safe position upon shutdown, verify that standby equipment properly operate upon loss of primary devises or power, and verify that the various control loops have been tuned and operate according to the sequence of operation and the Engineers design intent. 4. The functional testing of automatic control systems will also include but not be limited to a checkout of required graphics programming, review of the programming for compliance with the sequence of operation, and analysis of trend data for proper systems response and loop stability. 5. Randomly test at least ten percent (10%) of estimated worst-case final TAB report data for each group of identical equipment. 1. The sample set must not be smaller than three. 2. If ten percent (10%) of the sample group fails a second group of ten percent (10%) is selected and tested. If the second test fails then the whole group fails. The TAB agency shall be liable for retesting a part or all of the specific HVAC systems before undergoing further performance verification. 6. Verify contractor control input/output (I/O) point-to-point (PTP) termination. Use random statistical sampling; by testing at least ten percent of the estimated worstcase or most critical points. 7. All controls will be randomly tested for correct I/O PTP terminations. All invalid PTP terminations shall be corrected. Any specific control system having more then fivepercent (5%) invalid PTP terminations shall be completely rechecked by the controls contractor. 8. If at any point, frequent failures are occurring or necessary work remains incomplete or unattended and testing is becoming more troublesome and more then verification, the CxA will stop and immediately inform the Contractor. The responsible subcontractor will be required to perform and document a checkout of all the remaining units, prior to continuing with the functional testing. The Contractor must be informed of the Cx progress and will coordinate any initial work and remediation. Excessive retesting and verification may be considered additional service of the CxA. Page 7 of 8 Limited Commissioning Guidelines 3/23/2015

8 DOCUMENTS TO BE PROVIDED Reference list of Cx process, systems and equipment related documents to be provided to the CxA by the Owner, A/E, and/or Contractor: 1. Owner s Project Requirements 2. Basis of Design 3. Project Schedule 4. Request for Information 5. Change Orders 6. Red Line Drawings 7. Operations & Maintenance Manuals 8. Other as defined by the GC and CxA Page 8 of 8 Limited Commissioning Guidelines 3/23/2015

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems

More information

B. OPR and BoD documentation may be included by reference for information only.

B. OPR and BoD documentation may be included by reference for information only. SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/05/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/05/2018 SECTION 01 9113 - GENERAL COMMISSIONING REQUIREMENTS GENERAL 1.1 SUMMARY The Owner has retained an independent Commissioning Authority (CxA) to coordinate commissioning activities for this project. The

More information

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process.

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process. SECTION 23 99 50 - (ADD#4) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Absolute Energy Raters Commissioning Plan Outline Template

Absolute Energy Raters Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither

More information

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section. SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

DESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS

DESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS SECTION 01 91 13 GENERAL COMMISSIONING REQUIREMENTS GENERAL The University of South Alabama is officially and formally committed to the concept of Commissioning all new buildings and major renovations.

More information

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions. SECTION 23 0800 COMMISSIONING HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED 1.2 RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 25 0800 - COMMISSIONING OF INTEGRATED AUTOMATION GENERAL 1.1 SUMMARY This section defines responsibilities of the Integrated Automation Contractor to facilitate the Commissioning process for the

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply

More information

2. Representatives of the facility user and operation and maintenance personnel.

2. Representatives of the facility user and operation and maintenance personnel. PART I 1 GENERAL COMMISSIONING REQUIREMENTS 1.1 Description of Work a) The purpose of the commissioning process is to provide the owner/operator with assurance that the systems have been installed according

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction November 26, 2014 Re: Request for Qualifications - Commissioning Services Bowen Science Building Modernize Building Systems University of Iowa The

More information

H59-N944-PD ATTACHMENT C: SECTION GENERAL COMMISSIONING REQUIREMENTS

H59-N944-PD ATTACHMENT C: SECTION GENERAL COMMISSIONING REQUIREMENTS ATTACHMENT C: SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SCOPE A. This section provides for commissioning of the project equipment and systems as specified herein. The commissioning

More information

~fied1tr: SLONE . I. Submittal #39. Title - Commissioning of HV AC Systems Plan Specification Section ,00 10 SD# 02,03,07.

~fied1tr: SLONE . I. Submittal #39. Title - Commissioning of HV AC Systems Plan Specification Section ,00 10 SD# 02,03,07. I SLONE ASSOCIATES, INC. Repair FRC Building 1553 Naval Station, Mayport, Florida Submittal #39 Title - Commissioning of HV AC Systems Plan Specification Section - 23 0800,00 10 Index SD# 02,03,07 Item

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction February 17, 2015 Re: Request for Proposals- Commissioning Services Madison Street Residence Hall Construct Facility University of Iowa The University

More information

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA 02210 (T) 617-423-7423 (F) 617-423-7401 mwalsh@vanderweil.com Module

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction February 26, 2015 Re: Request for Proposals- Commissioning Services College of Public Health Building - Fit Out Fifth Floor University of Iowa The

More information

SECTION COMMISSIONING

SECTION COMMISSIONING SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery

More information

SECTION COMMISSIONING

SECTION COMMISSIONING SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery

More information

City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408).

City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408). City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408). The application of the Commissioning Process starts at the beginning of the project

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction March 7, 2013 Re: Request for Proposals- Commissioning Services Mayflower Hall Permanent Flood Recovery & Mitigation (UI# 0200201) University of Iowa

More information

Commissioning Guidelines for the Arkansas Energy Performance Contracting Program

Commissioning Guidelines for the Arkansas Energy Performance Contracting Program Commissioning Guidelines for the Arkansas Energy Performance Contracting Program Version 1.1 March 2014 Arkansas Economic Development Commission Energy Office 900 West Capitol Avenue Little Rock, Arkansas

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING PART I GENERAL 1.01 SECTION INCLUDES A. Commissioning objectives. B. Roles and responsibilities. C. Test Equipment. D. Systems to be commissioned. E. Construction Checklist requirements. SECTION 01 91

More information

Capital Projects Group Mechanical Work Commissioning Specification

Capital Projects Group Mechanical Work Commissioning Specification Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa

More information

Higher Value Commissioning

Higher Value Commissioning Higher Value Commissioning Presented by: Erik Jeannette, PE May 2011 Commissioning What is it? Commissioning (Cx) is a comprehensive and systematic process to verify and document the systems of a facility

More information

Request for Proposal. for. Building Commissioning Services

Request for Proposal. for. Building Commissioning Services Page 1 of 11 Request for Proposal for Building Commissioning Services State College Area School District High School Project December 15, 2014 Page 2 of 11 Request for Proposal for Building Commissioning

More information

REQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I

REQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I Dover School District (Owner) requests written proposals to secure commissioning authority (CxA) services for the renovations project at the Garrison Elementary School in Dover, New Hampshire. The Owner

More information

THE COTTAGE at THORNAPPLE Hastings, Michigan

THE COTTAGE at THORNAPPLE Hastings, Michigan THE COTTAGE at THORNAPPLE ADDENDUM NO. 2 March 07, 2012 The Cottage at Thornapple 2580 Nashville Road Hastings, MI 49058 Owner: Barry County / Thornapple Manor 2700 Nashville Road Hastings, MI 49058 Architect:

More information

CxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP

CxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP CxA Gap Session April 25, 2017 2:00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP AIA Provider Number 50111116 Course Description This session and short quiz,

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Commissioning & Retro-Commissioning Helping You Get the Most of Your Facilities

Commissioning & Retro-Commissioning Helping You Get the Most of Your Facilities Commissioning & Retro-Commissioning Helping You Get the Most of Your Facilities John Rimer, CFM Introduction John Rimer, CFM 16+ Years Facility Management Numerous Industries & Various Roles Owner, FM360

More information

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program

More information

Commissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan

Commissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan Commissioning National Training for Commissioning, 2006 Presented By Paul Sra and Mike Cavan 1 Scope of Presentation Commissioning overview Commissioning requirements for LEED Standard Roles and responsibilities

More information

E mail:

E mail: April 12, 2017 Mr. Michael Otavka William S. Hart Union High School District 21380 Centre Pointe Parkway Santa Clarita, CA 91350 Re: Castaic High School HVAC Systems and Controls Commissioning (Cx) Dear

More information

REQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa #

REQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # REQUEST FOR PROPOSAL Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # Addendum #1 Issued Wednesday, February 10, 2016 Changes: Item #01: Item #02: Section

More information

Preparing a Cx Plan. Technical vs. Process Commissioning TECHNICAL FEATURE

Preparing a Cx Plan. Technical vs. Process Commissioning TECHNICAL FEATURE ASHRAE www.ashrae.org. Used with permission from ASHRAE Journal, December 2013 at www.atkinsglobal.com. This article may not be copied nor distributed in either paper or digital form without ASHRAE s permission.

More information

Pay for Performance - NC Technical Topic

Pay for Performance - NC Technical Topic Commissioning Resources and Clarifications Executive Summary Pay for Performance - NC Technical Topic This Technical Topic provides resources and clarifications for commissioning requirements of the Pay

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information

Building Commissioning

Building Commissioning Building Commissioning Roles, Responsibilities, and Benefits 2010 ASHRAE Annual Meeting CxA WORKSHOP Saturday, June 26, 2010 Jim Magee, CxA, LEED-AP Facility Commissioning Group Overview Cx Advocacy, Economics,

More information

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 QUALITY MANAGEMENT SYSTEM... 2 2.1 Quality Management

More information

Fact Sheet. Commissioning WHAT IS THE PURPOSE OF THIS REQUIREMENT? WHAT VALUE DOES IT PROVIDE TO THE OWNER? HOW DOES IT SAVE ENERGY?

Fact Sheet. Commissioning WHAT IS THE PURPOSE OF THIS REQUIREMENT? WHAT VALUE DOES IT PROVIDE TO THE OWNER? HOW DOES IT SAVE ENERGY? Commissioning Fact Sheet Funding for this publication is provided by the Northwest Energy Efficiency Alliance. OCTOBER 2017 VOLUME 1, ISSUE 2 WHAT IS THE PURPOSE OF THIS REQUIREMENT? There is a saying

More information

NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014

NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014 NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings March 5, 2014 0 Moderator Jim Huber, NEBB President-Elect and President of Complete Commissioning Jim Huber

More information

Contract No DFW Fire Station #5 HVAC System Replacement. Document Title: TABLE OF CONTENTS Section:

Contract No DFW Fire Station #5 HVAC System Replacement. Document Title: TABLE OF CONTENTS Section: Document Title: TABLE OF CONTENTS Section: 00 01 10 Incorporated into the contract documents will be the Dallas Fort Worth International Airport Standard Technical Specification Book: Published June 01,

More information

MSBA OWNERS PROJECT MANAGER ROUNDTABLE

MSBA OWNERS PROJECT MANAGER ROUNDTABLE MSBA OWNERS PROJECT MANAGER ROUNDTABLE September 12, 2018 Winchester High School Winchester, MA AGENDA 9:00 A.M. Welcome and Introduction 9:05 A.M. Presentation Commissioning Experiences on MSBA Projects

More information

Introduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D.

Introduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D. New and xisting Facilities D. ric Gregory, CCP Commissioning Manager Sustainable Performance Program Manager mory University eric.gregory@emory.edu (404) 727-1388 Introduction Cx Manager at mory University

More information

Acceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance

Acceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance Acceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance PAUL M. RASCHILLA, PARTNER M B A, E P M, C H C, C B C P, L E E D A P, C M V P, C S D P AKF GROUP LLC AKF Group LLC is....

More information

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014 1 Commissioning at NYP Joseph Lorino, PE, LEED Corporate Director April 1, 2014 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program NYP Commissioning Process

More information

ICC 1000 APPLICATION OF THE COMMISSIONING PROCESS. March 27, Proposed Revision: GJKettler May 11, 2014

ICC 1000 APPLICATION OF THE COMMISSIONING PROCESS. March 27, Proposed Revision: GJKettler May 11, 2014 ICC 1000 APPLICATION OF THE COMMISSIONING PROCESS March 27, 2014 Updated April 2, 2014 By Formatting and Style Committee Committee Update April 17, 2014 Proposed Revision: GJKettler May 11, 2014 - = indicates

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No March 2017

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No March 2017 DEPARTMENT OF THE ARMY ER 1110-345-723 U.S. Army Corps of Engineers CECW-CE Washington, DC 20314-1000 Regulation No. 1110-345-723 31 March 2017 Engineering and Design TOTAL BUILDING COMMISSIONING PROCEDURES

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Design & Construction December 8, 2017 Re: Request for Proposals- Commissioning Services 0691801 Chilled Water Plant 2 (West) Increase Cooling Tower Capacity University of Iowa The

More information

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT)

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) 1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) The use of an existing elevator during construction shall be strictly prohibited. Any deviation

More information

Executive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX:

Executive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX: Executive Summary Sample Company BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA 17070 PHONE: 717-697-6300 FAX: 717-697-1699 Executive Summary Sample Company has constructed a 80,000 sf. addition

More information

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL 1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and

More information

(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet

(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet (To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:

More information

Request for Commissioning Services Proposal [Review and edit to suit project]

Request for Commissioning Services Proposal [Review and edit to suit project] Request for Commissioning Services Proposal [Review and edit to suit project] Issuance Date: Closing Date: [ Insert Owner s Name ] (Owner) requests written proposals to secure commissioning authority (CxA)

More information

Building Commissioning Association NEW CONSTRUCTION BUILDING COMMISSIONING BEST PRACTICES

Building Commissioning Association NEW CONSTRUCTION BUILDING COMMISSIONING BEST PRACTICES Building Commissioning Association NEW CONSTRUCTION BUILDING COMMISSIONING BEST PRACTICES Including BCxA Essential Attributes updated May 2018 Contents 1. Introduction... 1 2. Pre-Design Phase... 6 2.1

More information

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap

More information

Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS

Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute

More information

PROFESSIONAL SERVICES DESCRIPTION FOR THE POSITION OF: Building Commissioning Services

PROFESSIONAL SERVICES DESCRIPTION FOR THE POSITION OF: Building Commissioning Services PROFESSIONAL SERVICES DESCRIPTION FOR THE POSITION OF: Building Commissioning Services SUBMISSION DEADLINE: October 23, 2009 11:00am FAIR AND OPEN PUBLIC SOLICITATION PROCESS FOR PROFESSIONAL SERVICES

More information

The Nuts and Bolts of the Commissioning Process

The Nuts and Bolts of the Commissioning Process The Nuts and Bolts of the Process May 2, 2007 10:30 Noon 15 th National Conference on Building Where the Industry Meets Agenda Introduction Getting started When is commissioning required? Choosing a commissioning

More information

ADDENDUM NO. 1 to the Contract Documents for Taylor Elementary School at Sea Lab New Bedford, Massachusetts

ADDENDUM NO. 1 to the Contract Documents for Taylor Elementary School at Sea Lab New Bedford, Massachusetts ADDENDUM NO. 1 to the Contract Documents for Taylor Elementary School at Sea Lab Mount Vernon Group Inc. 200 Harvard Mill Square Wakefield, MA 01880 Addendum Date: TO ALL BIDDERS AND SUB-BIDDERS This Addendum

More information

NAPA SANITATION DISTRICT

NAPA SANITATION DISTRICT NAPA SANITATION DISTRICT PSOMAS COMPANY - TASK ORDER No. 25 HEADWORKS EQUIPMENT REHAB-REPLACE PROJECT (CIP 17726) Date: July 25, 2018 Issued under Professional Services Agreement dated ---------, 2018.

More information

Elgin/Lake Huron SCADA Upgrades SCADA Standards Section 300 Detailed Design and Construction

Elgin/Lake Huron SCADA Upgrades SCADA Standards Section 300 Detailed Design and Construction Elgin/Lake Huron SCADA Upgrades Version Date Description of Revision v1 March 7, 2006 Preliminary Draft v2 March 22, 2006 Second Draft v3 May 2009 Third Draft v4 August 2010 Final Draft v5 January 2011

More information

Building Systems Commissioning: Ensuring Quality. Michael P. Della Barba Director of Commissioning Services Environmental Health & Engineering, Inc.

Building Systems Commissioning: Ensuring Quality. Michael P. Della Barba Director of Commissioning Services Environmental Health & Engineering, Inc. Building Systems Commissioning: Ensuring Quality Michael P. Della Barba Director of Commissioning Services Environmental Health & Engineering, Inc. EH&E Company Profile Established in 1988 Headquarters

More information

I. Development, Submittal, and Acceptance of a Quality Management System

I. Development, Submittal, and Acceptance of a Quality Management System I. Development, Submittal, and Acceptance of a Quality Management System 1. Scope Under the Contract, quality assurance and quality control management are the responsibility of the Contractor. The Contractor

More information

Commissioning In Energy Savings Performance Contracts

Commissioning In Energy Savings Performance Contracts Commissioning In Energy Savings Performance Contracts Karl Stum, P.E., Portland Energy Conservation Inc. (PECI) ABSTRACT Energy savings performance contracts (PCs) using the international measurement and

More information

Patrick Malloy Communities Quality Assurance System

Patrick Malloy Communities Quality Assurance System Patrick Malloy Communities Quality Assurance System Page 1 of 83 Log of Quality Manual Revisions Version Number Revision Date Type of Revision 1 April 9, 2007 1 st release 1 April 13, 2007 Sec 1.10 removed

More information

Best Practices in Commissioning Existing Buildings Building Commissioning Association

Best Practices in Commissioning Existing Buildings Building Commissioning Association Best Practices in Commissioning Existing Buildings Building Commissioning Association Presented at the 16 th National Conference on Building Commissioning by: Mark Miller, PE, CCP, CEM, LEED AP Principal,

More information

CSU Office of the Chancellor Commissioning Guideline for CSU Capital Projects. Commissioning Guideline for CSU Capital Projects.

CSU Office of the Chancellor Commissioning Guideline for CSU Capital Projects. Commissioning Guideline for CSU Capital Projects. Commissioning Guideline for CSU Capital Projects Rev: 11/28/18 ACKNOWLEDGEMENT The California State University (CSU) gratefully acknowledges the effort and work of Jai Agaram, John Andary, Douglas Effenberger,

More information

COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202

COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning

More information

USD 497. Request for Qualifications Commissioning Engineers Building Commissioning Services. August 11, 2017

USD 497. Request for Qualifications Commissioning Engineers Building Commissioning Services. August 11, 2017 USD 497 Request for Qualifications Commissioning Engineers Building Commissioning Services August 11, 2017 1 INTRODUCTION Lawrence Public Schools, in accordance with the policies of the Board of Education,

More information

P-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07

P-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 PART 1 GENERAL 1.1 REFERENCES SECTION 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 The publications listed below form a part of this specification to the extent referenced. The publications

More information

Rider A-1 Monitoring Based Commissioning (MBCx) for CSU Projects

Rider A-1 Monitoring Based Commissioning (MBCx) for CSU Projects Page 1 of 13 Rider A-1 Monitoring Based Commissioning (MBCx) for CSU Projects Monitoring Based Commissioning (MBCx) Objectives 1. The purpose of an MBCx effort is to realize improved building performance.

More information

Commissioning From the Agent s Perspective: Commissioning Buildings in the Code

Commissioning From the Agent s Perspective: Commissioning Buildings in the Code Commissioning From the Agent s Perspective: Commissioning Buildings in the Code Adoption In Arizona most all municipalities have adopted IECC 2012 in the last 3 years. Some have also adopted IECC 2015.

More information

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning A Building Commissioning Overview Presented by: Goetting & Associates Commissioning www.goettingcx.com What is the Definition of Commissioning? Building Commissioning is a Quality Assurance Process of

More information

CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017

CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017 CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017 OVERVIEW The recent adoption by the Centers for Medicaid and Medicare Services

More information

POSITION DESCRIPTION

POSITION DESCRIPTION POSITION DESCRIPTION Construction Manager Job Description Page 1 of 5 JOB TITLE: Construction Manager FLSA STATUS: Exempt DEPARTMENT: K-12 WORKER S COMP CODE: 8601 REPORTS TO: Program Manager EEO-1 JOB

More information

COMMISSIONING for LEED New and Existing Buildings

COMMISSIONING for LEED New and Existing Buildings Better Buildings By Design Conference Burlington, Vermont February 11-12. COMMISSIONING for LEED New and Existing Buildings Ron Wilkinson, P.E., LEED AP rwilkinson@akf-eng.com AKF Group, LLC What is Commissioning?

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc. How LEED & The Retro-Commissioning Credits Produce Energy Savings James Vallort Vice President Environmental Systems Design, Inc. Retro-Commissioning Today s session will focus on the following items:

More information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes

More information

MANUAL QUALITY CONTROL & QUALITY ASSURANCE

MANUAL QUALITY CONTROL & QUALITY ASSURANCE MANUAL QUALITY CONTROL & QUALITY ASSURANCE METROTEC ENGINEERING LLC P.O. BOX: 26045, DUBAI U.A.E TEL : 043889771 FAX:043889772 E Mail: metrotecengg@yahoo.com info@metrotec.ae Web: www.metrotec.ae 2 TABLE

More information

Volume II- Project Development Processes

Volume II- Project Development Processes Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required

More information

Commissioning Toolkit for In-House Commissioning of Small Buildings

Commissioning Toolkit for In-House Commissioning of Small Buildings 1 Commissioning Toolkit for In-House Commissioning of Small Buildings Dan Burgoyne Sustainability Manager California Department of General Services California Commissioning Collaborative April 12, 2007

More information

Manage Deliverables - Construction Step 6 February 2015

Manage Deliverables - Construction Step 6 February 2015 Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection

More information

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

SECTION COMMUNICATIONS SYSTEMS QUALITY ASSURANCE & TESTING

SECTION COMMUNICATIONS SYSTEMS QUALITY ASSURANCE & TESTING SECTION 16707 COMMUNICATIONS SYSTEMS QUALITY ASSURANCE & TESTING PART 1 - GENERAL 1.01 SECTION INCLUDES A. These quality control (QC) system requirements define characteristics, in addition to those in

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (November 2016) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 00.00 10 (February 2010) UNIFIED FACILITIES GUIDE

More information

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.

More information

Guideline HVAC&R Technical Requirements for The Commissioning Process

Guideline HVAC&R Technical Requirements for The Commissioning Process Guideline 1-2007 HVAC&R Technical Requirements for The Commissioning Process Charles E Dorgan, PE, PhD University of Wisconsin - Madison Synopsis The commissioning process for delivering quality new construction

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

ADDENDUM NO. 3. This addendum consists of 67 pages. Invitation to Bid ITB CPH Radiology Remodel Phases III, IV, and V

ADDENDUM NO. 3. This addendum consists of 67 pages. Invitation to Bid ITB CPH Radiology Remodel Phases III, IV, and V KENAI PENINSULA BOROUGH Purchasing & Contracting 47140 E Poppy Lane Soldotna, Alaska 99669-7520 Phone: (907) 714-2260 Fax: (907) 714-2373 www.kpb.us/purchasing ADDENDUM NO. 3 MIKE NAVARRE BOROUGH MAYOR

More information

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017 Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program

More information