1 Project Management for geothermal drilling projects 6th African Rift Geothermal Conference ARGeo-C6 Short Course 1 Project Management for Geothermal Development Anthony Ng ang a Ngigi

2 Content 1. What is project management 2. Drilling project set up 3. Objectives of the drilling project 4. The triple constraints-time, cost, quality, safety 5. Managing constraints 6. Drilling project management plan

3 Definition What is project management???? application of processes, methods, knowledge, skills and experience to achieve the project objectives ICB IPMA Competence baseline Ver. 3.0 outlines required attributes/approach to project management

4 Drilling project set up Set up What is the organization of carrying out the drilling project e.g. is it a contractor or a gov t org. carrying out the drilling Gov t org Laws, statutes, ordinances, directives, regulations, budgets, and policies Contractor independent in operations e.g. procurement

5 Drilling project set up cont d

6 Drilling project set up cont d

7 Objectives of the drilling project Drilling project aims at drilling the wells within:- Cost Time Quality Set safety standards When the above is achieved Success is realized

8 The triple constraint Typical Project Drilling Project Quality Quality/Safety

9 Managing the triple constraints A balance between the constraints has to be established Proper time management may control cost in most cases Aim to drill a quality well safely,timely and within set cost Does slow or fast drilling compromise the other constraints +vely or vely????

10 Managing the triple constraints cont d Time can be managed by breaking down all the drilling activities from start to finish ---> Scheduling

11 Drilling project management plan Integration of the following plans:- Interested parties management plan Project communication plan Procurement plan Contract plan Quality plan

12 Drilling project management plan cont d Interested parties management plan Identify interested parties e.g. external and internal External gov t, donors, IPPs, community etc. Internal top management, drilling crews, geoscientists etc. What are their expectations?? How do we get them involved into the project??? Participatory approach

13 Drilling project management plan cont d Project communication plan Who is to receive information on the project What information is to be passed level of detail When is the information going to be relayed Confidentiality of information Management of meetings:- Preparation for the meeting The conduct of the meeting Reporting the meeting Follow up of meeting deliberations

14 Drilling project management plan cont d Procurement plan Gov t organizations have to follow set regulations - lengthy process Elaborate plans need to be in place to deal with breakdowns - emergency procurement. Break downs are not planned Proper inventory to be kept to plan ahead from rig spares, rig tools and equipment to drilling materials, PPEs Identify in advance suppliers of specialized tools and equipment have a running contract if possible

15 Drilling project management plan cont d Contract plan Some of the works and services contracted in a drilling project include running of casings, casing cementing, wireline operations (logging), directional drilling, supply of fuel and cement etc. Legal department involved in drafting the contracts The contracts should be closely monitored for their expiry and if need be renewed in good time to maintain continuity Proper communication during contract execution written form preferred

16 Drilling project management plan cont d Quality plan Quality degree to which inherent characteristics fulfil the project requirements (ICB 3.0) All the four (4) phases (surface, anchor csg, production csg and liner section) in drilling of wells must fulfil set quality standards set SOPs must be followed e.g. maintain right torque for casings The project team should participate in management of the project quality create awareness Permanent organization sets the quality management practices If quality is overlooked project objectives may not be achieved

17 6th African Rift Geothermal Conference ARGeo-C6 Short Course 1 Project Management for Geothermal Development Organized by: Financed by: Coordinator: Lecturers: United Nations University Geothermal Training Programme (UNU-GTP) Icelandic Ministry for Foreign Affairs ICEIDA and Nordic Development Fund Ingimar G. Haraldsson, UNU-GTP Anthony Ng ang a Ngigi, Geothermal Development Company, Kenya Carine Chatenay, Verkís Consulting Engineers, Iceland Peketsa Mwaro Mangi, Kenya Electricity Generating Company, Kenya Yngvi Gudmundsson, Verkís Consulting Engineers, Iceland

DEVELOPMENT OF A GEOTHERMAL TRAINING CENTRE IN KENYA

DEVELOPMENT OF A GEOTHERMAL TRAINING CENTRE IN KENYA Paper to be presented at Workshop for Decision Makers on Geothermal Projects and Management, organized by UNU-GTP and KengGen in Naivasha, Kenya, 14-18 November, 2005 DEVELOPMENT OF A GEOTHERMAL TRAINING

More information

COST AND REVENUES OF DIRECT USE APPLICATIONS

COST AND REVENUES OF DIRECT USE APPLICATIONS Presented at Short Course VI on Utilization of Low- and Medium-Enthalpy Geothermal Resources and Financial Aspects of Utilization, organized by UNU-GTP and LaGeo, in Santa Tecla, El Salvador, March 23-29,

More information

GEOTHERMAL PROJECT TIMELINES

GEOTHERMAL PROJECT TIMELINES Proceedings, 6 th African Rift Geothermal Conference Addis Ababa, Ethiopia, 2 nd 4 th November 2016 GEOTHERMAL PROJECT TIMELINES Yngvi Gudmundsson Verkis Ofanleiti 2, 103 Reykjavik ICELAND yg@verkis.is

More information

KENYA S PLANS FOR GEOTHERMAL DEVELOPMENT A GIANT STEP FORWARD FOR GEOTHERMAL

KENYA S PLANS FOR GEOTHERMAL DEVELOPMENT A GIANT STEP FORWARD FOR GEOTHERMAL Presented at Short Course on Geothermal Development and Geothermal Wells, organized by UNU-GTP and LaGeo, in Santa Tecla, El Salvador, March 11-17, 2012. GEOTHERMAL TRAINING PROGRAMME LaGeo S.A.de C.V.

More information

SREP Ethiopia Project Approval Request Public Document International Finance Corporation (IFC)

SREP Ethiopia Project Approval Request Public Document International Finance Corporation (IFC) SREP Ethiopia Project Approval Request Public Document International Finance Corporation (IFC) 1. Country/Region: Ethiopia 2. CIF Project ID#: (Trustee will assign ID) 3. Source of Funding: FIP PPCR SREP

More information

GEOTHERMAL EXPLORATION IN RWANDA: A COUNTRY UPDATE

GEOTHERMAL EXPLORATION IN RWANDA: A COUNTRY UPDATE Presented at Short Course IX on Exploration for Geothermal Resources, organized by UNU-GTP, GDC and KenGen, at Lake Bogoria and Lake Naivasha, Kenya, Nov. 2-24, 2014. Kenya Electricity Generating Co.,

More information

WELLHEAD POWER PLANTS

WELLHEAD POWER PLANTS Installed power [GWe] Proceedings, 6 th African Rift Geothermal Conference Addis Ababa, Ethiopia, 2 nd 4 th November 2016 WELLHEAD POWER PLANTS Yngvi Gudmundsson, Elin Hallgrimsdottir Verkís, Mannvit,

More information

German-African Energy Forum 2012

German-African Energy Forum 2012 German-African Energy Forum 2012 Kirsten Offermanns Senior Project Manager Subdevision Energy and Environment KfW Entwicklungsbank Dr. Fritjof Börstler Senior Project Manager Bundesanstalt für Geowissenschaften

More information

GEOTHERMAL ENERGY IN THE WORLD FROM AN ENERGY PERSPECTIVE

GEOTHERMAL ENERGY IN THE WORLD FROM AN ENERGY PERSPECTIVE Presented at Short Course IX on Exploration for Geothermal Resources, organized by UNU-GTP, GDC and KenGen, at Lake Bogoria and Lake Naivasha, Kenya, Nov. 2-23, 2014. Kenya Electricity Generating Co.,

More information

OSD SUPPLY CHAIN ENTERPRISE METRICS STRATEGY. Evolving DoD Supply Enterprise Metrics The Maintenance Customer Perspective

OSD SUPPLY CHAIN ENTERPRISE METRICS STRATEGY. Evolving DoD Supply Enterprise Metrics The Maintenance Customer Perspective OSD SUPPLY CHAIN ENTERPRISE METRICS STRATEGY Evolving DoD Supply Enterprise Metrics The Maintenance Customer Perspective Mr. Paul Blackwell, ODASD(SCI) November 13, 2012 0 Introduction OSD SUPPLY CHAIN

More information

OVERVIEW OF GEOTHERMAL RESOURCE EXPLORATION AND DEVELOPMENT IN THE EAST AFRICAN RIFT SYSTEM

OVERVIEW OF GEOTHERMAL RESOURCE EXPLORATION AND DEVELOPMENT IN THE EAST AFRICAN RIFT SYSTEM Presented at Short Course VII on Exploration for Geothermal Resources, organized by UNU-GTP, GDC and KenGen, at Lake Bogoria and Lake Naivasha, Kenya, Oct. 27 Nov. 18, 2012. GEOTHERMAL TRAINING PROGRAMME

More information

PROJECTS MANAGEMENT AT KENGEN, KENYA

PROJECTS MANAGEMENT AT KENGEN, KENYA Presented at Short Course on Geothermal Project Management and Development, organized by UNU-GTP, KenGen and MEMD-DGSM, at the Imperial Botanical Beach Hotel, Entebbe, Uganda, November 20-22, 2008. GEOTHERMAL

More information

SASKATCHEWAN WAGE SURVEY 2013: FORESTRY, FISHING, MINING, QUARRYING, OIL AND GAS INDUSTRY SUMMARY

SASKATCHEWAN WAGE SURVEY 2013: FORESTRY, FISHING, MINING, QUARRYING, OIL AND GAS INDUSTRY SUMMARY SASKATCHEWAN MINISTRY OF THE ECONOMY JUNE 2014 SASKATCHEWAN WAGE SURVEY 2013 SASKATCHEWAN WAGE SURVEY 2013: Insightrix Research Inc. 1-3223 Millar Ave Saskatoon, SK S7K 5Y3 P: (306) 657-5640 E: info@insightrix.com

More information

06.0 Data and Access Classification

06.0 Data and Access Classification Number 6.0 Policy Owner Information Security and Technology Policy Data and Asset Classification Effective 01/01/2014 Last Revision 12/30/2013 Department of Innovation and Technology 6. Data and Asset

More information

CONTRACTING OF GEOTHERMAL PROJECTS

CONTRACTING OF GEOTHERMAL PROJECTS Presented at Short Course on Geothermal Project Management and Development, organized by UNU-GTP, KenGen and MEMD-DGSM, at the Imperial Botanical Beach Hotel, Entebbe, Uganda, November 20-22, 2008. GEOTHERMAL

More information

GEOTHERMAL EXPLORATION IN RWANDA

GEOTHERMAL EXPLORATION IN RWANDA Presented at SDG Short Course I on Exploration and Development of Geothermal Resources, organized by UNU-GTP, GDC and KenGen, at Lake Bogoria and Lake Naivasha, Kenya, Nov. 10-31, 2016. Kenya Electricity

More information

SCALING-UP RENEWABLE ENERGY PROGRAM IN ETHIOPIA. Final Draft External Independent Review

SCALING-UP RENEWABLE ENERGY PROGRAM IN ETHIOPIA. Final Draft External Independent Review SCALING-UP RENEWABLE ENERGY PROGRAM IN ETHIOPIA Final Draft External Independent Review 26 th January 2012 TABLE OF CONTENTS TABLE OF CONTENTS... 2 I. TITLE OF THE INVESTMENT PLAN... 3 II. PROGRAM UNDER

More information

OECD DAC Peer Review of Iceland Memorandum

OECD DAC Peer Review of Iceland Memorandum OECD DAC Peer Review of Iceland Memorandum Submitted: July 22, 2016 Table of Contents Acronyms and Terms Used...ii List of Boxes, Figures, Tables and Annexes...iv Executive Summary...v Chapter 1: Towards

More information

Now, click on the word Oil (Petroleum) 2.) How is oil formed? 3.) What does the word petroleum mean? 4.) Describe crude oil and where it is found.

Now, click on the word Oil (Petroleum) 2.) How is oil formed? 3.) What does the word petroleum mean? 4.) Describe crude oil and where it is found. Energy Kids Page WebQuest You must follow the instructions step by step. Do not jump ahead. You will be using the website below to answer questions about energy resources. Log in to the computer. Open

More information

GEOTHERMAL EXPLORATION AND DEVELOPMENT IN RWANDA

GEOTHERMAL EXPLORATION AND DEVELOPMENT IN RWANDA Presented at Short Course VIII on Exploration for Geothermal Resources, organized by UNU-GTP, GDC and KenGen, at Lake Bogoria and Lake Naivasha, Kenya, Oct. 31 Nov. 22, 2013. GEOTHERMAL TRAINING PROGRAMME

More information

Power Africa Geothermal Road Show. Presented by David Kagiri

Power Africa Geothermal Road Show. Presented by David Kagiri Power Africa Geothermal Road Show Presented by David Kagiri September 2014 Outline of Presentation JOH-KGN001-20070825-JvW-P1 1.Summary of power sector and country investment environment 2. Detailed summary

More information

Global Alliance for Improved Nutrition

Global Alliance for Improved Nutrition Job Title: Finance and Administration Manager, Nigeria Classification: Senior Manager, R5 Direct Reports: 1-5 Work Location Nigeria Office Travel Required: Limited GAIN s purpose is to advance nutrition

More information

Rules on Initiation of Power Procurement and Review of Power Purchase Agreements. Eng. Anastas Mbawala, EWURA

Rules on Initiation of Power Procurement and Review of Power Purchase Agreements. Eng. Anastas Mbawala, EWURA Rules on Initiation of Power Procurement and Review of Power Purchase Agreements Eng. Anastas Mbawala, EWURA 1 Overview of this Presentation Background on statutory powers and purpose of the Rules Description

More information

RECOMMENDED PRACTICE 9.0 FOR LAND- BASED DRILLING RIGS AND SERVICE RIGS

RECOMMENDED PRACTICE 9.0 FOR LAND- BASED DRILLING RIGS AND SERVICE RIGS RECOMMENDED PRACTICE 9.0 FOR LAND- BASED DRILLING RIGS AND SERVICE RIGS MINIMUM STANDARDS FOR DERRICK EGRESS Version 1.0 August 1, 2006 CANADIAN ASSOCIATION OF OILWELL DRILLING CONTRACTORS Introduction

More information

Course outline Introduction to project management The project management process groups Project initiation

Course outline Introduction to project management The project management process groups Project initiation Course outline Introduction to project management The project management process groups Project initiation Total Quality Project Management 2 Many organizations today have a new or renewed interest in

More information

W I N D A N D S O L A R R F Q / R F P P R O C E S S

W I N D A N D S O L A R R F Q / R F P P R O C E S S W I N D A N D S O L A R R F Q / R F P P R O C E S S S a s k a t c h e w a n R e n e w a b l e s I P P and Supplier I n f o r m a t i o n S e s s i o n S a s k a t o o n, S a s k a t c h e w a n N o v e

More information

NEW DEVELOPMENTS IN GEOTHERMAL DRILLING

NEW DEVELOPMENTS IN GEOTHERMAL DRILLING Presented at Workshop for Decision Makers on Geothermal Projects in Central America, organized by UNU-GTP and LaGeo in San Salvador, El Salvador, 26 November to 2 December 2006 NEW DEVELOPMENTS IN GEOTHERMAL

More information

European Economic Area Financial Mechanism GR03 Programme «Renewable Energy» Energy profile: Norway

European Economic Area Financial Mechanism GR03 Programme «Renewable Energy» Energy profile: Norway Programme Operator European Economic Area Financial Mechanism 2009-2014 GR03 Programme «Renewable Energy» Energy profile: Norway Athens, 11 th September 2014 Dr. Paraskevas N. Georgiou, Research Associate

More information

Comparison of ISO Draft Version and PMBOK Guide 4 th Edition 1

Comparison of ISO Draft Version and PMBOK Guide 4 th Edition 1 Comparison of Draft Version and PMBOK Guide 4 th Edition 1 Stanisław Gasik, Ph. D.; sgasik@sybena.pl; www.sybena.pl Table of Contents HISTORY OF... 2 BASIC CONCEPTS... 2 PROJECT DEFINITION... 2 TYPES OF

More information

Use of Locally Fabricated or Modified Equipment. DROPS Forum July

Use of Locally Fabricated or Modified Equipment. DROPS Forum July Use of Locally Fabricated or Modified Equipment DROPS Forum July 02 2009 Incident 1: Welder Electrocution A rig subcontractor suffered fatal injuries from electrical shock while performing a welding operation.

More information

Isolating Potential Flow Zones During Well Construction

Isolating Potential Flow Zones During Well Construction Isolating Potential Flow Zones During Well Construction API Standard 65 Part 2 Glen Benge http://publications.api.org/ API Standard 65-2 Document highlights industry recommended cementing and well construction

More information

iktva Program Framework & Business Opportunities Saudi Aramco: Public

iktva Program Framework & Business Opportunities Saudi Aramco: Public iktva Program Framework & Business Opportunities Agenda iktva Program Framework Business Opportunities 1 2 3 1 2 iktva Baseline 5 Year iktva Action Plan iktva integration in Procurement Historical and

More information

Africa EU Action Programme to support improved transboundary basins management

Africa EU Action Programme to support improved transboundary basins management Africa EU Action Programme to support improved transboundary basins management Animated by: French Ministry for Foreign Affairs. Dakar, November 2004 Alain BERNARD a.bernard@oieau.fr AMCOW has selected

More information

SURVEY ON PRACTICES FOLLOWED IN SPARE PARTS INVENTORY MANAGEMENT IN MINING INDUSTRY.

SURVEY ON PRACTICES FOLLOWED IN SPARE PARTS INVENTORY MANAGEMENT IN MINING INDUSTRY. CHAPTER 3 SURVEY ON PRACTICES FOLLOWED IN SPARE PARTS INVENTORY MANAGEMENT IN MINING INDUSTRY. 3.1: Introduction: A survey was carried out to understand the present practices followed by the various Mining

More information

Analysis of the final version of Cameroon s R-PP

Analysis of the final version of Cameroon s R-PP Analysis of the final version of Cameroon s R-PP CAMEROON presented its Readiness Preparation Proposal (R-PP) for assessment by the FCPF Participants Committee (PC) at its 13 th meeting held in October

More information

INFRASTRUCTURE DEVELOPMENT IN GEOTHERMAL FIELDS: A CASE STUDY FOR MENENGAI GEOTHERMAL PROSPECT, KENYA

INFRASTRUCTURE DEVELOPMENT IN GEOTHERMAL FIELDS: A CASE STUDY FOR MENENGAI GEOTHERMAL PROSPECT, KENYA INFRASTRUCTURE DEVELOPMENT IN GEOTHERMAL FIELDS: A CASE STUDY FOR MENENGAI GEOTHERMAL PROSPECT, KENYA Wilson Rutinu Geothermal Development Company, P.O Box 100746-00101 - Nairobi, Kenya rougo@gdc.co.ke,

More information

Project Management Manual Prepared by: Project Support Office, Major Projects Department

Project Management Manual Prepared by: Project Support Office, Major Projects Department Project Management Manual Prepared by: Project Support Office, Major Projects Department Version: 2015 Project Support Office Project Management Manual Version: November 2015 This manual is a living document

More information

Purpose of the evaluation

Purpose of the evaluation Individual Contract Terms of Reference RECOMMENDED MINIMUM CONTENTS OF TOR FOR AN IC 1. BACKGROUND Since signing a Memorandum of Agreement with UNDP in 2012, the State of Kuwait has supported the UNDP

More information

Water Dependency of Geothermal Power Generation Systems

Water Dependency of Geothermal Power Generation Systems Proceedings 5 th African Rift geothermal Conference Arusha, Tanzania, 29-31 October 2014 Water Dependency of Geothermal Power Generation Systems (Esther Sironka. ) Kenya Electricity Generating Company

More information

Public Private Partnerships (PPP) CPA Mumo

Public Private Partnerships (PPP) CPA Mumo Public Private Partnerships (PPP) CPA Mumo What is a PPP? PPP involves a contract between a public sector authority and a private party in which the private party provides and/or produces a public service,

More information

KenGen's Wellhead Technology Experience and Business Insight

KenGen's Wellhead Technology Experience and Business Insight Proceedings World Geothermal Congress 2015 Melbourne, Australia, 19-25 April 2015 KenGen's Wellhead Technology Experience and Business Insight Ronoh Kibet and Roy Bwoma OLKARIA rkibet@kengen.co.ke Keywords:

More information

Indonesia's Energy Transit: Struggle to Realize Renewable Potential

Indonesia's Energy Transit: Struggle to Realize Renewable Potential Indonesia's Energy Transit: Struggle to Realize Renewable Potential By Jeremy Wilcox, Contributor September 14, 2012 LONDON -- Indonesia's electricity market is moving from a monopoly fossil-fuel generation

More information

University Document Hierarchy

University Document Hierarchy University Document Hierarchy Purpose The purpose of this document is to outline the hierarchy of instruments and documents, hereinafter collectively referred to as documents, which are in use within the

More information

Government Services ACCOUNTABILITY STATEMENT

Government Services ACCOUNTABILITY STATEMENT BUSINESS PLAN 2001-04 Government Services ACCOUNTABILITY STATEMENT This Business Plan for the three years commencing April 1, 2001 was prepared under my direction in accordance with the Government Accountability

More information

Sales & Operations Planning: An Introduction

Sales & Operations Planning: An Introduction Sales & Operations Planning: Sales An & Operations Introduction Planning: An Introduction S&OP Overview The S&OP process was first developed in the1980 s. Today, S&OP is used across the Global 1000 1980

More information

Presentation Overview

Presentation Overview How to Reasonably & Effectively Implement Compliance Programs for Small Group Physician Practices Andrea Merritt, Director of Compliance & Audit Services Ashlie Heald, Compliance Specialist Nova Compliance

More information

August 17, DCN Number: ALB07WP001 Revision: 0. Prepared By: 8300 Jefferson NE Suite B Albuquerque, New Mexico 87113

August 17, DCN Number: ALB07WP001 Revision: 0. Prepared By: 8300 Jefferson NE Suite B Albuquerque, New Mexico 87113 WORK PLAN ENERGY FUELS RESOURCE CORPORATION URANIUM MILL LICENSING SUPPORT PHASE 1 GEOTECHNICAL INVESTIGATION KLEINFELDER PROJECT NO. 83088 August 17, 2007 DCN Number: 83088.1.4.2-ALB07WP001 Revision:

More information

Holistic Drilling Fluid and Drilling Waste Management in the Fayetteville Shale SPE

Holistic Drilling Fluid and Drilling Waste Management in the Fayetteville Shale SPE Holistic Drilling Fluid and Drilling Waste Management in the Fayetteville Shale SPE - 144036 1 Key Components Holistic Fluid Management (HFM) Considerations Roles of the Project Team Project Phases and

More information

GEOTHERMAL DEVELOPMENT IN KENYA COUNTRY UPDATE. Cornel Ofwona Geothermal Development Company

GEOTHERMAL DEVELOPMENT IN KENYA COUNTRY UPDATE. Cornel Ofwona Geothermal Development Company GEOTHERMAL DEVELOPMENT IN KENYA COUNTRY UPDATE Cornel Ofwona Geothermal Development Company Electricity situation in Kenya Source Installed MW Hydro 761 Thermal 419.6 Geothermal 209 Co-gen 26 Wind 5.45

More information

2017 Archaeology Audit Program Procedure Manual. April 2017

2017 Archaeology Audit Program Procedure Manual. April 2017 2017 Archaeology Audit Program Procedure Manual April 2017 Table of Contents Contents Table of Contents... 2 1.0 Introduction and Scope... 3 2.0 Audit Objectives... 3 3.0 Audit Procedures... 4 3.1 Audit

More information

Summer 2014/2015. Grzegorz Karpiuk University of Information Technology and Management

Summer 2014/2015. Grzegorz Karpiuk University of Information Technology and Management Summer 2014/2015 Grzegorz Karpiuk University of Information Technology and Management gkarpiuk@wsiz.rzeszow.pl Project Management A project is a temporary endeavour undertaken to create a unique product,

More information

CH2404 Process Economics Unit I Inventory Control. Dr. M. Subramanian

CH2404 Process Economics Unit I  Inventory Control.  Dr. M. Subramanian CH2404 Process Economics Unit I Inventory Control Dr. M. Subramanian Associate Professor Department of Chemical Engineering Sri Sivasubramaniya Nadar College of Engineering Kalavakkam 603 110, Kanchipuram(Dist)

More information

Systematic Project Management

Systematic Project Management Systematic Project Management Karlos A. Artto at HUT S-72.124 Product Development of Telecommunication Systems Lecture on March 16, 2001 Systematic Project Management CONTENTS 1 What are the capabilities

More information

Africa Sustainable Transport Forum. Summary of the Outcomes of the Inaugural Forum, held in Nairobi, Kenya, from 28 to 30 October 2014

Africa Sustainable Transport Forum. Summary of the Outcomes of the Inaugural Forum, held in Nairobi, Kenya, from 28 to 30 October 2014 Africa Sustainable Transport Forum Summary of the Outcomes of the Inaugural Forum, held in Nairobi, Kenya, from 28 to 30 October 2014 1 The Africa Sustainable Transport Forum (ASTF) held its 1 st Ministerial

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized UGANDA POLICY NOTE ON SOCIAL ACCOUNTABILITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Team: Mary Bitekerezo (TTL), Joanna De Berry,

More information

Aveng Ground Engineering Profile

Aveng Ground Engineering Profile Aveng Ground Engineering Profile Contents Overview 1 2 Piling 2 Renewable Energy 6 Lateral Support 8 Grouting 10 Geotechnical investigations 12 Flagship projects 12 Contact us 12 Visit our website for

More information

2011 IRF Summit Conference Summary. Lars Herbst GOM Regional Director BSEE

2011 IRF Summit Conference Summary. Lars Herbst GOM Regional Director BSEE 2011 IRF Summit Conference Summary Lars Herbst GOM Regional Director BSEE As Attendees: Obtain an understanding of regulatory impacts from Montara and Macondo. Obtain an understanding of the avalanche

More information

University Document Hierarchy

University Document Hierarchy University Document Hierarchy Purpose The purpose of this document is to outline the hierarchy of instruments and documents, hereinafter collectively referred to as documents, which are in use within the

More information

Construction Simulation An Introduction

Construction Simulation An Introduction Construction Simulation An Introduction Tim O Leary Construction Solutions Europe & Africa Solutions BRIDGES BUILDINGS CADASTRE AND LAND DEVELOPMENT CAMPUSES COMMUNICATION S ELECTRIC AND GAS UTILITIES

More information

Mr. Herkko Lehdonvirta

Mr. Herkko Lehdonvirta Mr. Herkko Lehdonvirta Date and place of birth: Nationality: Marital status: 19.11.1952 Karuna, Finland Finnish Married, three children EDUCATION 1971-1976 Helsinki University of Technology Master of Science,

More information

Presentation by Hon. John Kiyonga Munyes, EGH, MP Minister for Labour Government of the Republic of Kenya

Presentation by Hon. John Kiyonga Munyes, EGH, MP Minister for Labour Government of the Republic of Kenya NATIONAL VOLUNTARY PRESENTATION TO THE ECOSOC 2012 ANNUAL MINISTERIAL REVIEW Promoting productive capacity, employment and decent work to eradicate poverty in the context of inclusive, sustainable and

More information

Lecture Series: Consumer Electronics Supply Chain Management

Lecture Series: Consumer Electronics Supply Chain Management Lecture Series: Consumer Electronics Supply Chain Management Mohit Juneja i2 Technologies Divakar Rajamani, Ph.D. University of Texas at Dallas Center for Intelligent Supply Networks () 2003 Mohit Juneja

More information

(20-MW Geothermal Power Generation)

(20-MW Geothermal Power Generation) MOEJ/GEC JCM Project Feasibility Study (FS) 2014 Summary of the Final Report (20-MW Geothermal Power Generation) (Implementing Entity: Mizuho Information and Research Institute, Inc.) 1.Overview of the

More information

Injection Wells for Liquid-Waste Disposal. Long-term reliability and environmental protection

Injection Wells for Liquid-Waste Disposal. Long-term reliability and environmental protection Injection Wells for Liquid-Waste Disposal Long-term reliability and environmental protection ACHIEVE MULTIPLE GOALS FOR LIQUID-WASTE DISPOSAL INJECTION WELLS Expertly located, designed, constructed, and

More information

INTERGRATION BETWEEN GEOGRAPHICAL INFORMATION SYSTEM AND SERVICE, APPLICATION AND PRODUCTS CONTRIBUTION TO GEOTHERMAL DEVELOPMENT

INTERGRATION BETWEEN GEOGRAPHICAL INFORMATION SYSTEM AND SERVICE, APPLICATION AND PRODUCTS CONTRIBUTION TO GEOTHERMAL DEVELOPMENT INTERGRATION BETWEEN GEOGRAPHICAL INFORMATION SYSTEM AND SERVICE, APPLICATION AND PRODUCTS CONTRIBUTION TO GEOTHERMAL DEVELOPMENT James Kimutai Geothermal Development Company Taj Towers, 8th Floor, Box

More information

Engaging Top Management in Projects Governance, Decision Making & Support Reinhard Wagner

Engaging Top Management in Projects Governance, Decision Making & Support Reinhard Wagner Engaging Top Management in Projects Governance, Decision Making & Support Reinhard Wagner We are IPMA 1 About the presenter > 30 years of experience in project-based leadership, in such different sectors

More information

Employment study: solutions on lack of skilled workers in the geothermalsector & results of the questionnaires

Employment study: solutions on lack of skilled workers in the geothermalsector & results of the questionnaires Deliverable n 5.1 Date: November 2013 Authors: Spyros Karytsas (Center for Renewable Energy Sources and Saving) Employment study: solutions on lack of skilled workers in the geothermalsector & results

More information

Opportunities And Challenges Of Developing Geothermal In Developing Countries: A Case Of Malawi

Opportunities And Challenges Of Developing Geothermal In Developing Countries: A Case Of Malawi Proceedings World Geothermal Congress 2015 Melbourne, Australia, 19-25 April 2015 Opportunities And Challenges Of Developing Geothermal In Developing Countries: A Case Of Malawi Tufwane Mwagomba Malawi

More information

A SMARTER AND GREENER DEFENCE NORDIC DEFENCE INDUSTRY SEMINAR CHAIRMAN S CONCLUSIONS

A SMARTER AND GREENER DEFENCE NORDIC DEFENCE INDUSTRY SEMINAR CHAIRMAN S CONCLUSIONS 2012 A SMARTER AND GREENER DEFENCE NORDIC DEFENCE INDUSTRY SEMINAR COPENHAGEN, 2-3 MAY 2012 CHAIRMAN S CONCLUSIONS A SMARTER AND GREENER DEFENCE On 2-3 May 2012 the 4th Nordic Defence Industry Seminar

More information

Open-Web Truss Long Span Installation Guidelines

Open-Web Truss Long Span Installation Guidelines TECHNICAL BULLETIN #301 Open-Web Truss Long Span Installation Guidelines RedBuilt has maintained a policy of manufacturing and marketing products of the highest quality to our customers. We guarantee the

More information

OPPORTUNITIES FOR DIRECT UTILIZATION OF GEOTHERMAL ENERGY IN EBURRU AREA, KENYA

OPPORTUNITIES FOR DIRECT UTILIZATION OF GEOTHERMAL ENERGY IN EBURRU AREA, KENYA OPPORTUNITIES FOR DIRECT UTILIZATION OF GEOTHERMAL ENERGY IN EBURRU AREA, KENYA Cornelius Ndetei Environmental Scientist Kenya Electricity Generating Co. Ltd 6 th African Rift Geothermal Conference (ARGEO-C6)

More information

CONSULTANT FOR ASSESSMENT OF TECHNICAL ASPECTS OF THE NSP INVESTING IN GRID-CONNECTED SOLAR PV IN THE GAMBIA GENERAL INFORMATION

CONSULTANT FOR ASSESSMENT OF TECHNICAL ASPECTS OF THE NSP INVESTING IN GRID-CONNECTED SOLAR PV IN THE GAMBIA GENERAL INFORMATION TERMS OF REFERENCE (ToR) NATIONAL CONSULTANT FOR ASSESSMENT OF TECHNICAL ASPECTS OF THE NSP INVESTING IN GRID-CONNECTED SOLAR PV IN THE GAMBIA GENERAL INFORMATION Services/Work Description: Execution of

More information

Well Abandonment & Intervention Services, Gulf Coast Region. Plug into a New Approach

Well Abandonment & Intervention Services, Gulf Coast Region. Plug into a New Approach Well Abandonment & Intervention Services, Gulf Coast Region Plug into a New Approach Get it Right the First Time Permanent Solutions to Your Well Abandonment Challenge Thousands of wells await safe and

More information

Terms of Reference For Project Evaluation REDD for reducing poverty in Nepal Phase I and II

Terms of Reference For Project Evaluation REDD for reducing poverty in Nepal Phase I and II Terms of Reference For Project Evaluation REDD for reducing poverty in Nepal Phase I and II Background REDD phase I (2009-2010) and REDD phase II project (2011-2013) are projects supported by Ministry

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

Leveraging the Scaled Agile Framework (SAFe ) in Federal Government Agile Transformations

Leveraging the Scaled Agile Framework (SAFe ) in Federal Government Agile Transformations Leveraging the Scaled Agile Framework (SAFe ) in Federal Government Agile Transformations An exploration of the intended benefits of SAFe, along with the antipatterns and resulting challenges that degrade

More information

Unit 11: Stakeholder Management (PMBOK Guide, Chapter 13)

Unit 11: Stakeholder Management (PMBOK Guide, Chapter 13) (PMBOK Guide, Chapter 13) Stakeholder management identifies people, groups, and organizations that could impact or be impacted by the project. The topic has increased in importance with each new edition

More information

HELIOS - WV Somalia Experience. Presented by George Fenton (WVI) and George Wachiuri (WVS)

HELIOS - WV Somalia Experience. Presented by George Fenton (WVI) and George Wachiuri (WVS) HELIOS - WV Somalia Experience Presented by George Fenton (WVI) and George Wachiuri (WVS) Where we Work in Africa 2 wvs wvs wvs 3 WV Operations WV International operates in remote areas of Kenya,Somalia,

More information

Sample Company. Risk Assessment and Mitigation Plan

Sample Company. Risk Assessment and Mitigation Plan Sample Company Revision History DATE VERSION DESCRIPTION AUTHOR 08-07-04 0.01 Initial Version F. Jack Anderson 09-07-04 0.02 Revised with changes from team reviews Michael Bennett 09-08-04 2.00 Initial

More information

From surface to the reservoir, solving your geothermal challenges for over 50 years

From surface to the reservoir, solving your geothermal challenges for over 50 years GEOTHERMAL From surface to the reservoir, solving your geothermal challenges for over 50 years Solving challenges. 1 Geothermal Clean, renewable and plentiful, geothermal energy holds huge promise worldwide

More information

Crisis Communications Preparedness Checklist

Crisis Communications Preparedness Checklist Crisis Communications Preparedness Checklist jonathan@bernsteincrisismanagement.com (626) 825-3838 Crisis Communications Preparedness Checklist, Page 1 Situation Self-examination Questions Actions Necessary

More information

HOW TO WRITE A WINNING PROPOSAL

HOW TO WRITE A WINNING PROPOSAL HOW TO WRITE A WINNING PROPOSAL WHAT IS A PROPOSAL? A proposal is a picture of a project, it is NOT the project. In that sense, it is based on your project plan but may be quite different from the Project

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

CUSTOMER AND SUPPLIER ROLES AND RESPONSIBILITIES FOR 21 CFR 11 COMPLIANCE ASSESSMENT. 21 CFR Part 11 FAQ. (Frequently Asked Questions)

CUSTOMER AND SUPPLIER ROLES AND RESPONSIBILITIES FOR 21 CFR 11 COMPLIANCE ASSESSMENT. 21 CFR Part 11 FAQ. (Frequently Asked Questions) 21 CFR Part 11 FAQ (Frequently Asked Questions) Customer and Supplier Roles and Responsibilities for Assessment of METTLER TOLEDO STARe Software Version 16.00, including: - 21 CFR 11 Compliance software

More information

The principal Law for Geothermal Resource Development in Kenya. Florah Mwawughanga

The principal Law for Geothermal Resource Development in Kenya. Florah Mwawughanga The principal Law for Geothermal Resource Development in Kenya By Florah Mwawughanga Purpose Highlight the role of Geothermal Resources Act in geothermal development in Kenya. Give brief on role of supplementary

More information

Incoterms ICC Rules for the use of Domestic and International Trade Terms. Kenya Maritime Authority

Incoterms ICC Rules for the use of Domestic and International Trade Terms. Kenya Maritime Authority Incoterms 2010 By the International Chamber of Commerce (ICC) ICC Rules for the use of Domestic and International Trade Terms O b l i g a t i o n s Costs & Risks Kenya Maritime Authority WHO WE ARE Kenya

More information

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: June 19, 2012 FILE CODE: A02-30/PW SUBJECT: STAGE

More information

H.R.6. Energy Independence and Security Act of 2007 (Enrolled as Agreed to or Passed by Both House and Senate) Subtitle B--Geothermal Energy

H.R.6. Energy Independence and Security Act of 2007 (Enrolled as Agreed to or Passed by Both House and Senate) Subtitle B--Geothermal Energy H.R.6 Energy Independence and Security Act of 2007 (Enrolled as Agreed to or Passed by Both House and Senate) SEC. 611. SHORT TITLE. Subtitle B--Geothermal Energy This subtitle may be cited as the `Advanced

More information

Barriers to the use of geothermal energy. Robert Kutschick Gaßner, Groth, Siederer & Coll. Pisa, 10th October 2013

Barriers to the use of geothermal energy. Robert Kutschick Gaßner, Groth, Siederer & Coll. Pisa, 10th October 2013 Barriers to the use of geothermal energy Robert Kutschick Gaßner, Groth, Siederer & Coll. Pisa, 10th October 2013 The Topics Part 1 Approval process for exploration, drilling and mining I. Federal Mining

More information

Saudi Energy Efficiency Center

Saudi Energy Efficiency Center Saudi Energy Efficiency Center Dr. Naif M. Alabbadi SEEC, Director General nabbadi@seec.gov.sa www.seec.gov.sa AFED 6th Annual Conference Sustainable Energy: Prospects, Challenges, Opportunities Sharjah

More information

Structural Lining of Water Mains. City of St. John s, Water and Wastewater Division

Structural Lining of Water Mains. City of St. John s, Water and Wastewater Division Structural Lining of Water Mains Overview Applications Pre-lining process Installation (Aqua-Pipe Product) Post-lining process Challenges Applications Alternative to water main reconstruction. Limited

More information

World Small Hydropower Development Report 2013

World Small Hydropower Development Report 2013 World Small Hydropower Development Report 2013 www.smallhydroworld.org MALAWI Disclaimer Published in 2013 by United Nations Industrial Development Organization (UNIDO) and International Center on Small

More information

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability

More information

EEA/Norway Grants. Energy efficiency and renewable energy

EEA/Norway Grants. Energy efficiency and renewable energy EEA/Norway Grants Energy efficiency and renewable energy Conference in Oslo November 7 2012 Bjørn Aulie, International Section, NVE Norwegian Water Resources and Energy Directorate (NVE) Reports to the

More information

Maersk Line: Future Operations Execution

Maersk Line: Future Operations Execution CASE Maersk Line: Future Operations Execution DEVELOPING A UNIQUE COMPETITIVE ADVANTAGE. END-2-END STANDARDISATION OF GLOBAL PROCESSES TO CONTINUOUSLY REDUCE LEAD TIME AND COST. Maersk Line Operations

More information

Global Geothermal Development Plan Roundtable

Global Geothermal Development Plan Roundtable Global Geothermal Development Plan Roundtable Dominica Geothermal Resource Development Programme Presented by: Lucien Blackmoore Permanent Secretary Ministry of Public Works, Energy and Ports Commonwealth

More information

SAMOA NATIONAL VOLUNTARY REVIEW

SAMOA NATIONAL VOLUNTARY REVIEW SAMOA NATIONAL VOLUNTARY REVIEW OPENING STATEMENT Country commitment to implementation SDGs Importance of contextualization of SDGs and localization indicators Agenda 2030 delivers for SIDS building on

More information

PHASES OF GEOTHERMAL DEVELOPMENT IN ICELAND

PHASES OF GEOTHERMAL DEVELOPMENT IN ICELAND Paper to be presented at Workshop for Decision Makers on Geothermal Projects and Management, organized by UNU-GTP and KengGen in Naivasha, Kenya, 14-18 November, 2005 PHASES OF GEOTHERMAL DEVELOPMENT IN

More information