Project Forecast Survey Results Good Scheduling Practices June 2016

Size: px
Start display at page:

Download "Project Forecast Survey Results Good Scheduling Practices June 2016"

Transcription

1 Good Scheduling Practices 5 June 6

2 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of project plans is an integral part of the project planning process and the practices adopted by project planners and schedulers can often determine whether or not it is a good plan or not-so-good plan. In 5, Project Forecast called for responses for a survey on Good Scheduling Practices. The survey sought the views on what are good practices when creating new time schedules (also known as plans and programmes) using predominately the Critical Path Method (CPM). Invitations to participate in the survey were sent to planners and schedulers known by Project Forecast. This survey has found: Half of the survey respondents start preparing schedules by creating the WBS structure, and the other half start with identification of critical milestones. Two-thirds of respondents indicated they would like to have a scope statement and understanding of project objectives and purpose prior to starting to prepare a schedule. Not all respondents include a start milestone, although all respondents include a finish milestone. A majority of respondents rarely, if at all, use Start-to-Finish (SF) activity relationships. More than half of respondents seek a third party or peer review of the schedule, compare or benchmark the schedule against other similar project schedules. When preparing schedules, a lack of or poorly designed work breakdown structures (WBS) and review of the scope of work is one of the top things planners and schedulers get wrong, closely followed by poor sequencing. When statusing or updating schedules, only two thirds of respondents indicated they checked that all activities in progress show some percentage (%) complete. More than two thirds of respondents indicated that the percentage complete should rarely be based on cost complete, and it should, mostly, be based on the quantity of material installed. More than two thirds of respondents indicated that for activities in progress the completion date should mostly or always be based on the performance (productivity) of the activity, and only sometimes be based on experience. When updating or statusing a schedule, relying on activity owners progress updates, and not validating the progress with measurable objective facts is one of the top things that planners and schedulers get wrong, closely followed by not updating the forecast to reflect reality. All respondents indicated that the completion date should only sometimes, if not then rarely, be based on their experience. It is recommended: The findings of this survey are used to prepare a good scheduling practices checklist; and The survey is release again in the near to solicit a greater response and to identify any change trends in good scheduling practices.

3 Good Scheduling Practices 5 June 6 Contents Executive Summary... Introduction... Abbreviations... Survey Questions Asked... 5 Who Responded to the Survey... 7 The Survey Responses... 8 Key Findings and Recommendation

4 Good Scheduling Practices 5 June 6 Introduction There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of project plans is an integral part of the project planning process and the practices adopted by project planners and schedulers can often determine whether or not it is a good plan or not-so-good plan. In 5, Project Forecast called for responses for a survey on Good Scheduling Practices. The survey sought the views on what are good practices when creating new time schedules (also known as plans and programmes) using predominately the Critical Path Method (CPM). Invitations to participate in the survey were sent to planners and schedulers known by Project Forecast. This report summarises the responses from the survey. Abbreviations The following abbreviations and acronyms have been used in this report. Abbreviation CBS CPM FF FS MS SF SS WBS Definition Cost Breakdown Structure Critical Path Method Finish-to-Finish (an activity relationship type) Finish-to-Start (an activity relationship type) Microsoft Start-to-Finish (an activity relationship type) Start-to-Start (an activity relationship type) Work Breakdown Structure For other planning and scheduling terms and definitions please view Project Forecast s Glossary of planning and scheduling terms at

5 Good Scheduling Practices 5 June 6 Survey Questions Asked The survey sought the responses to nine (9) questions. The questions were designed to identify the steps that the respondents take and the information they like to have available when preparing project time schedules, the steps taken when reviewing schedules and the top things that they consider planners and schedulers get wrong. The questions were: Q. Generally the steps I take when creating a new schedule are... (rank each step from to 7, with being the first step) [rank the order from to 7, with being the first step]. create working calendars establish the Work Breakdown Structure (WBS) identify the project critical milestones create the list of activities or tasks estimate the duration(s) for activities or tasks establish the dependencies between activities, tasks and milestones assign resources Q. Before starting a schedule I like to have... [rank either Always, Mostly, Sometimes, Rarely or Never] a scope statement a drawing or layout plan an execution strategy a contract and/or procurement strategy a cost estimate a cost estimate with man hours an agreed corporate/project Work Breakdown Structure (WBS) and Cost Breakdown Structure (CBS) a list of target and/or contract milestone dates an understanding of the project objectives and purpose Q. When preparing a schedule I... [rank either Always, Mostly, Sometimes, Rarely or Never] include a start milestone include a finish milestone avoid using constraints use a structure activity numbering system, based on either the WBS or activity coding use activity coding agree the general project execution methodology with the project manager agree the contracting and procurement strategy with the project manager establish durations using productivity rates and material or man hour estimates establish durations using the knowledge and experience of the team like to keep the duration for the majority of activities less than work days for design activities include allowances for peer reviews for design activities include allowances for discipline coordination reviews include allowances for client and owner approvals 5

6 Good Scheduling Practices 5 June 6 include allowances for government and authority approvals include allowances for inclement weather delays keep a record of all the assumptions and base information I have relied upon to prepare the schedule compare or benchmark the schedule against other similar project schedules establish unique resource calendars name activities using a verb and noun use leads and lags use finish to start (FS) relationships use start to start (SS) relationships use finish to finish (FF) relationships use start to finish (SF) relationships name activities so that the activity is easily identifiable if the schedule is filtered structure the schedule so that it can be easily rolled up into a Level, Level or Level schedule Q. Before I issue a schedule I... [rank either Always, Mostly, Sometimes, Rarely or Never] make sure that all activities, other than the start milestone, has a predecessor make sure that all activities, other than the finish milestone, has a successor check working calendar assignments for all activities review the longest path review the critical path review activities with excessive total float review activities with excessive free float review all activities with constraints seek a third party or peer review of the schedule compare or benchmark the schedule against other similar project schedules check the key project milestone dates review the resource profile check there is no dangling logic Q5. I believe the top things planners and schedulers get wrong the most when preparing schedules are... Q6. When updating or statusing a schedule I... [rank either Always, Mostly, Sometimes, Rarely or Never] check that the data date has been updated check that all activities in progress show some percentage (%) complete check to make sure there are no activities with actual dates later than the data date or status date check that we have a saved baseline 6

7 Good Scheduling Practices 5 June 6 Q7. The percentage (%) complete for activities should be... [rank either Always, Mostly, Sometimes, Rarely or Never] based on man hours complete based on material quantities installed agreed progress gates / milestone gates what I am told by the activity owner what I estimate (or guestimate) based on my experience based on the number of days complete / planned number of days based on cost complete Q8. For activities in progress, the completion date should be... [rank either Always, Mostly, Sometimes, Rarely or Never] based on the percentage (%) complete based on what the activity owner tells me based on my experience based on the performance (productivity) on the activity to date Q9. I believe the top things planners and schedulers get wrong the most when statusing/updating schedules are... Who Responded to the Survey The survey had six (6) respondents. One respondent did not answer Q6, Q7 and Q8. Two respondents did not answer Q9. 7

8 Good Scheduling Practices 5 June 6 The Survey Responses The following is a summary of the responses from the survey. Q. Generally the steps I take when creating a new schedule are... (rank each step from to 7, with being the first step) [rank the order from to 7, with being the first step]. create working calendars establish the Work Breakdown Structure (WBS) identify the project critical milestones create the list of activities or tasks estimate the duration(s) for activities or tasks establish the dependencies between activities, tasks and milestones assign resources Total Score % % 6.67% 6.67% 6.67% 6.67% % 8.% % The table above shows the that half of the respondents start with establishing the work breakdown structure, and the other half of the respondents start with identification of critical milestones. Assigning resources is the last step undertaken by all respondents. 8

9 Good Scheduling Practices 5 June 6 Q. Before starting a schedule I like to have... a scope statement a drawing or layout plan an execution strategy a contract and/or procurement strategy a cost estimate a cost estimate with man hours an agreed corporate/project Work Breakdown Structure (WBS) and Cost Breakdown Structure (CBS) a list of target and/or contract milestone dates an understanding of the project objectives and purpose Always Mostly Sometimes Rarely Never Total 6.67% 6.67% 6.67% 6.67% 8.% % % 6.67% 6.67% 6.67% Two thirds of respondents indicated they would like to have a scope statement and an understanding of the project objectives and purpose before starting preparation of the project time plan or schedule. Two thirds of respondents indicated that a cost plan with man hours was rarely required before starting preparation of the project time plan or schedule. One respondent also made the comment that they like to have a list of constraints and assumptions. 9

10 Good Scheduling Practices 5 June 6 Q. When preparing a schedule I... include a start milestone include a finish milestone avoid using constraints use a structure activity numbering system, based on either the WBS or activity coding use activity coding agree the general project execution methodology with the project manager agree the contracting and procurement strategy with the project manager establish durations using productivity rates and material or man hour estimates establish durations using the knowledge and experience of the team like to keep the duration for the majority of activities less than work days for design activities include allowances for peer reviews Always % 6.67% % 6.67% Mostly % 5 8.% % 6.67% Sometim es 6.67% 6.67% 6.67% 5 5 Rarely Never Don t Total Know

11 Good Scheduling Practices 5 June 6 for design activities include allowances for discipline coordination reviews include allowances for client and owner approvals include allowances for government and authority approvals include allowances for inclement weather delays keep a record of all the assumptions and base information I have relied upon to prepare the schedule compare or benchmark the schedule against other similar project schedules establish unique resource calendars name activities using a verb and noun use leads and lags use finish to start (FS) relationships use start to start (SS) relationships use finish to finish (FF) relationships use start to finish (SF) relationships Always 6.67% 6.67% 6.67% 5 Mostly 6.67% % 5 5 Sometim es 6.67% 6.67% % 5 8.% % Rarely 6.67% 6.67% % 6.67% 6.67% Never 5 Don t Know Total

12 Good Scheduling Practices 5 June 6 name activities so that the activity is easily identifiable if the schedule is filtered structure the schedule so that it can be easily rolled up into a Level, Level or Level schedule Always Mostly Sometim es Rarely Never Don t Know Total 6 6 All respondents include a finish milestone in their project time plans or schedules. Half of the respondents do not use Start-to-Finish (SF) relationships, with only one respondent using the SF relationship sometimes. Q. Before I issue a schedule I... make sure that all activities, other than the start milestone, has a predecessor make sure that all activities, other than the finish milestone, has a successor check working calendar assignments for all activities Always 8.% Mostly Sometim es 6.67% Rarely 6.67% Never Don t Know Total review the longest path 6 review the critical path 6 6

13 Good Scheduling Practices 5 June 6 Always Mostly Sometim es Rarely Never Don t Know Total review activities with excessive total float 6.67% 6.67% 6 review activities with excessive free float 6.67% 6.67% 6 review all activities with constraints 8.% % 6 seek a third party or peer review of the schedule % 6 compare or benchmark the schedule against other similar project schedules % 6 check the key project milestone dates 8.% % 6 review the resource profile 6 check there is no dangling logic 6 All respondents indicated that they make sure that all activities, other than the finish milestone, has a successor. More than half of the respondents seek a third party or peer review of the schedule, compare or benchmark the schedule against other similar project schedules or review the resource profile before they issue a schedule.

14 Good Scheduling Practices 5 June 6 Q5. I believe the top things planners and schedulers get wrong the most when preparing schedules are... Maintain schedule quality Unrealistic durations Do not plan the project in major chunks first then expand in detail to get the critical path right first Using incorrect calendars for activities Excessive dangling logic Hiding allowances in activities should be itemised in schedule Project Sequencing Do not build the project in their head logically first Excessive use of constraints Persuaded to use unrealistic durations or logic by management Understanding Scope Using hard constraints within the schedule Check the validity of assumptions and logic path with the construction team Starting the schedule without an integrated WBS and CBS Do not review the scope and WBS of the project Don't allow for reviews Poorly designed WBS A quantitative analysis of the responses is summarised below. Lack of or poorly designed WBS, CBS and review of scope. Poor sequencing. Poor duration estimation. Lack of big picture planning first. Excessive use of constraints. Poor maintenance of schedule quality. Lack of reviews. Incorrect working calendars. Hiding schedule allowances.

15 Good Scheduling Practices 5 June 6 Q6. When updating or statusing a schedule I... Always Mostly Sometimes Rarely Never Total check that the data date has been updated 8 5 check that all activities in progress show some percentage (%) complete 6 5 check to make sure there are no activities with actual dates later than the data date or status date 5 5 check that we have a saved baseline 5 5 All respondents indicated they check to make sure there are no activities with actual dates later than the data date or status date and check that a baseline has been saved. Only two thirds of respondents indicated they checked that all activities in progress show some percentage (%) complete when statusing or updating a schedule. 5

16 Good Scheduling Practices 5 June 6 Q7. The percentage (%) complete for activities should be... Always Mostly Sometimes Rarely Don t Know Total based on man hours complete 8 5 based on material quantities installed 5 agreed progress gates / milestone gates 5 what I am told by the activity owner 6 5 what I estimate (or guestimate) based on my experience 8 5 based on the number of days complete / planned number of days 8 5 based on cost complete 8 5 Almost two thirds of the respondents indicated that the percentage complete should, either always or mostly, be based on the quantity of material installed. More than two thirds of respondents indicated that the percentage complete should rarely be based on cost complete. 6

17 Good Scheduling Practices 5 June 6 Q8. For activities in progress, the completion date should be... based on the percentage (%) complete based on what the activity owner tells me based on my experience based on the performance (productivity) on the activity to date Always Mostly Sometimes Rarely Don t Know Total Almost two thirds of respondents indicated that for activities in progress the completion date should mostly or always be based on the performance (productivity) of the activity. All respondents indicated that the completion date should only sometimes, if not then rarely, be based on their experience. Q9. I believe the top things planners and schedulers get wrong the most when statusing/updating schedules are... Not amending data dates Not updating duration remaining to reflect reality Do not challenge the information coming from the activity owners Not being brave enough to status the work correctly even if it's bad news Believing what the owner tells rather than what they see Not moving incomplete works ahead of status date (MS project) Reviewing progress for outofsequence activities Lack of use of "objective and measurable" facts Not checking/auditing the accuracy of the dates Over valuing the work completed to date Physical % vs Duration % Baselining the previous update prior to statusing the schedule A quantitative analysis of the responses is summarised below. Not validating the progress and relying on what they have been told. Not updating the forecast to reflect reality (duration and sequencing). Not keeping a copy of the previous update as a baseline. Not using the appropriate percent complete. Over valuing the work complete to date. No adjustment to the data date. 7

18 Good Scheduling Practices 5 June 6 Key Findings and Recommendation The survey has found: Half of the survey respondents start preparing schedules by creating the WBS structure, and the other half start with identification of critical milestones. Two-thirds of respondents indicated they would like to have a scope statement and understanding of project objectives and purpose prior to starting to prepare a schedule. Not all respondents include a start milestone, although all respondents include a finish milestone. A majority of respondents rarely, if at all, use Start-to-Finish (SF) activity relationships. More than half of respondents seek a third party or peer review of the schedule, compare or benchmark the schedule against other similar project schedules. When preparing schedules, a lack of or poorly designed work breakdown structures (WBS) and review of the scope of work is one of the top things planners and schedulers get wrong, closely followed by poor sequencing. When statusing or updating schedules, only two thirds of respondents indicated they checked that all activities in progress show some percentage (%) complete. More than two thirds of respondents indicated that the percentage complete should rarely be based on cost complete, and it should, mostly, be based on the quantity of material installed. More than two thirds of respondents indicated that for activities in progress the completion date should mostly or always be based on the performance (productivity) of the activity, and only sometimes be based on experience. When updating or statusing a schedule, relying on activity owners progress updates, and not validating the progress with measurable objective facts is one of the top things that planners and schedulers get wrong, closely followed by not updating the forecast to reflect reality. All respondents indicated that the completion date should only sometimes, if not then rarely, be based on their experience. It is recommended: The findings of this survey are used to prepare a good scheduling practices checklist; and The survey is release again in the near to solicit a greater response and to identify any change trends in good scheduling practices. 8

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT PMP Exam Prep PROJECT SCHEDULE MANAGEMENT Page 223 Schedule Management Process : Contains 6 of the 49 total processes Plan Schedule Management Define

More information

Global Project Management, LLC

Global Project Management, LLC Global Project Management, LLC 2250 Gause Boulevard, Suite 310 Slidell, Louisiana 70461 Tel: 985-781-9190 A Projectis a temporary endeavor undertaken to create a unique product, service, or result. Initiation

More information

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove Improved Project Control Through Scheduling January 24, 2014 The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference

More information

Principles of Planning for IT Projects

Principles of Planning for IT Projects Principles of Planning for IT Projects Introduction Building Timings Exercises Meals & refreshments Mobile Phones Part 1 Setting the Scene 1. Course Objectives 2. Where projects come from 3. What is a

More information

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS) /11/16 Network Diagram 11//16 1 WORK BREAKDOWN STRUCTURE (WBS) A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body

More information

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management.

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management. 55205 Mastering Microsoft Project 2016 The course begins with the basic concepts and leads students through all the functions they ll need to plan and manage a small to medium-size project, including how

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

6 PROJECT TIME MANAGEMENT

6 PROJECT TIME MANAGEMENT CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

Scheduling. Adapted from John Musser

Scheduling. Adapted from John Musser Scheduling Adapted from John Musser Today Network Fundamentals Gantt Charts PERT/CPM Techniques WBS Review Types: Process, product, hybrid Formats: Outline or graphical organization chart High-level WBS

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI SP, LEED AP Hill International Charlie Jackson, PSP Project Life Span Construction CPM Conference - 2017 Author Biography

More information

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Impact Schedules Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference Project Planning & CPM Scheduling using MS Project APWA NorCal 2018 Annual Conference What is Planning? Planning: A determination of the what, how, where and by whom ; the tasks that need to be completed

More information

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 Project Scope -Definition A documented description of the project in terms of

More information

Time Management PLANNING

Time Management PLANNING Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

Scheduling Challenges in the Industrial Construction Sector

Scheduling Challenges in the Industrial Construction Sector Scheduling Challenges in the Industrial Construction Sector Carol Bolstad, President, Senior Planner Scheduling & Information Services, Inc. carol.bolstad@1sis.com www.1sis.com Agenda Scheduling Practices

More information

Project Time Management

Project Time Management Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis

More information

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional Session ID: 10686 Prepared by: Raquel Shohet, PSP Vice President Hill International, Inc. How to Develop, Manage

More information

MAINTAINING & UTILIZING AN INTEGRATED MASTER SCHEDULE FOR A FEDERAL CONTRACT

MAINTAINING & UTILIZING AN INTEGRATED MASTER SCHEDULE FOR A FEDERAL CONTRACT Wednesday, November 2, 2017, 2:00 2:50 a.m. MAINTAINING & UTILIZING AN INTEGRATED MASTER SCHEDULE FOR A FEDERAL CONTRACT SHERI SCHNEIDER, GMG MANAGEMENT, INC 1 SESSION OVERVIEW 01 Integrated Master Schedule

More information

MSP How to guide session 3 (Updating)

MSP How to guide session 3 (Updating) MSP How to guide session 3 (Updating) 1. Introduction Some people think planning ends once they gain agreement and pin up the schedule on the wall. On larger projects the schedule follows a defined update

More information

Information Technology Project Management, Seventh Edition

Information Technology Project Management, Seventh Edition Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning

More information

Project Management PSGLE 122. Time and Resources

Project Management PSGLE 122. Time and Resources Project Management PSGLE 122 Time and Resources Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation

More information

Team Member Application

Team Member Application MnDOT Project Management Office Presents: Team Member Application Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Risk Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Chapter 3 Managing Systems Projects

Chapter 3 Managing Systems Projects Chapter 3 Managing Systems Projects Harry J. Rosenblatt. (2014). Systems Analysis and Design, 10 th Edition, International Edition. Course Technology, Cengage Learning. Modified by Nichnan K., 2013 Systems

More information

Forecast Scheduling Microsoft Project Online 2018

Forecast Scheduling Microsoft Project Online 2018 Forecast Scheduling Microsoft Project Online 2018 Best Practices for Real-World Projects Eric Uyttewaal, PMP President ProjectPro Corporation Published by ProjectPro Corporation Preface Publishing Notice

More information

Time has the least. amount of flexibility; Schedule issues are the main reason for

Time has the least. amount of flexibility; Schedule issues are the main reason for PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely

More information

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1. Massport Capital Programs Enterprise Schedule Management Document 11 A Primavera Schedule Toolkit Vertical Projects July 2017 Version 1.5 Contents 1.0 INTRODUCTION 2 1.1 DISCLAIMER 2 2.0 TOOLKIT SCHEDULE

More information

Project Scope Management

Project Scope Management Project Scope Management Work Breakdown Structure (WBS) Created in Planning Process -> Scope Area Benefits of Work Breakdown Structure Organizes and defines the total scope of the project Helps prevent

More information

STO Navigator Canada Best-Practices Manual

STO Navigator Canada Best-Practices Manual Page 1 / 5 24.1- SCHEDULING METHODOLOGY 24.1.1. PURPOSE The following best-practice guideline provides the STO Project Controls Team with a defined methodology for scheduling, to accurately identify the

More information

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 8.4 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation

More information

LONG INTERNATIONAL. Robin K. Long, PMP

LONG INTERNATIONAL. Robin K. Long, PMP Robin K. Long, PMP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Robin K. Long, PMP

More information

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1 MGT/437 Project Management Session #2 University of Phoenix 02/12/2004 Brian Smithson 02/12/2004 MGT/437 #2 -- Brian Smithson 1 Agenda Review/Questions Session content PMI project framework Project Knowledge

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard Your easy, colorful, SEE-HOW guide! Plain&Simple Microsoft Project 03 Ben Howard Published with the authorization of Microsoft Corporation by O Reilly Media, Inc. 005 Gravenstein Highway North Sebastopol,

More information

Scheduling 2 Day Structure

Scheduling 2 Day Structure Day 1 Session 1: Design and Structure your Schedule 1. The need for planning and scheduling a. Purpose = communication not control b. Understand audience 2. Simple -v- complex projects 3. Planning -v-

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

James M. Bolin and Andrew Avalon, P.E., PSP

James M. Bolin and Andrew Avalon, P.E., PSP James M. Bolin and Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Plan Your Work, Work Your Plan Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Agenda Understand what a project is Understand the basics of

More information

Geog 469 GIS Workshop. Project Management

Geog 469 GIS Workshop. Project Management Geog 469 GIS Workshop Project Management Outline Basic principles of project management 6.1 What is a project versus an application? 6.2 What is a scoping statement for your project? 6.3 Why are critical

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Course 50413B: Mastering Microsoft Project 2010 Page 1 of 10 Mastering Microsoft Project 2010 Course 50413B: 2 days; Instructor-Led About this Course This two-day instructor-led course provides students

More information

Microsoft Project 2013 Core Essentials

Microsoft Project 2013 Core Essentials Microsoft Project 2013 Core Essentials 2092; 3 days; Instructor-led Course Description This in-depth training course presents the skills that students need to get the most out of Microsoft Project 2013.

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information

// Improving Project Plans using a Schedule Maturity Framework

// Improving Project Plans using a Schedule Maturity Framework // Improving Project Plans using a Schedule Maturity Framework An Introduction to the S1 > S5 Schedule Maturity Framework Dr. Dan Patterson, PMP CEO & President, Acumen August 2010 www.projectacumen.com

More information

BASELINE SCHEDULING BASICS Part 2: May 3, 2007

BASELINE SCHEDULING BASICS Part 2: May 3, 2007 BASELINE SCHEDULING BASICS Part 2: May 3, 2007 Mark Boe, P.E., PSP Vice President Capital Project Management, Inc. mboe@cpmiteam.com Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com

More information

EXHIBIT 2-2-C SCHEDULES

EXHIBIT 2-2-C SCHEDULES EXHIBIT 2-2-C SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The Work specified in this section consists of furnishing transportation, labor, materials, equipment, and incidentals necessary for preparation,

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

(Really) Understanding Microsoft Project

(Really) Understanding Microsoft Project 2019 (Really) Understanding Microsoft Project Ron Winter, PSP, FAACE Schedule Analyzer Software 1 Ron Winter, PSP, FAACE Bachelor of Science in Engineering Construction Scheduler US Air Force Navigator

More information

Project Management Framework

Project Management Framework Project Management Framework What s Project? - Why Project? What s Project Management? - Why Project Management? What s Project Management Professionals? - Why Project Management Professionals? Project

More information

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Administration Evacuation Timings, meals and facilities Mobile phones and emails Introductions

More information

Project Management. Time and Resources DPLE 157

Project Management. Time and Resources DPLE 157 Project Management Time and Resources DPLE 157 RLI Design Professionals is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this

More information

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM Using your EAC as a GPS 6 Characteristics of a Good EAC Kim Koster, Senior Director IPM Top Ten Reasons Projects Fail BAD plans and inadequate planning processes Proposal not adequate Lack of scope comprehension

More information

PROJECT TIME MANAGEMENT Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1212 Powered by POeT Solvers Limited PLANNING DEFINE ACTIVITIES MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities

More information

Demystifying Microsoft Project

Demystifying Microsoft Project Demystifying Microsoft Project With Melissa Esquibel, MCT Copyright 2015 Melissa P Esquibel LLC. All rights reserved. Unauthorized duplication prohibited. Microsoft, Project, Excel, SharePoint, PowerPoint,

More information

Microsoft Project 2013 Training

Microsoft Project 2013 Training Microsoft Project 2013 Training Project Tasks Tables Charts Forms Resources Tables Charts Forms Task Ribbon > Properties Grouping > Display Task Details * This allows you to view the Task Form pane so

More information

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc. What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc. Schedule? A PLAN Schedule? Schedule? A PLAN With Respect to Time Schedule? A

More information

Project Scheduling with GanttProject. EGR 386w

Project Scheduling with GanttProject. EGR 386w Project Scheduling with GanttProject EGR 386w 1 GanttProject http://www.ganttproject.biz/ Download version 2.6.x Has numbered tasks option The video (access from ganttproject.biz) http://www.youtube.com/watch?v=5rhcsa5ad34&feature=youtu.be

More information

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification JEE4980 Sr Design Project Lecture Wilcox Chapter 1 discussion Assignment Team Progress Report due BL Team Meeting Agenda due BL Team Charter 1 ST draft due EL Product Brainstorm due EL Baseline design

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

2017 Construction CPM Conference Ron Winter, PSP, FAACE Schedule Analyzer Software CPM ACTIVITY STATUS

2017 Construction CPM Conference Ron Winter, PSP, FAACE Schedule Analyzer Software CPM ACTIVITY STATUS 2017 Ron Winter, PSP, FAACE Schedule Analyzer Software CPM ACTIVITY STATUS Ron Winter, PSP, FAACE Bachelor of Science in Engineering Construction Scheduler US Air Force Navigator Construction Scheduler

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Managing Projects with Microsoft Project Server 2010

Managing Projects with Microsoft Project Server 2010 Managing Projects with Microsoft Project Server 2010 Duration: 4 Days Course Code: GK2597 Delivery Method: Company Event Overview: Learn to take project management to the next level using Microsoft Project

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

PROJECT SCHEDULING & CONTROL

PROJECT SCHEDULING & CONTROL PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012 5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes

More information

PROJECT PLANNING AND SCHEDULING

PROJECT PLANNING AND SCHEDULING PROJECT PLANNING AND SCHEDULING AFTAB HAMEED MEMON Office: E6-003A, Makmal Kej. Bangunan Jab. Kej. Bangunan & Peminaan, FKAAS Contact No. 014-2527620 E-mail: ah78memon@hotmail.com Introduction to Project

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

Retained Logic and Progress Override in Primavera P6

Retained Logic and Progress Override in Primavera P6 By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding

More information

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management Project Management Professional (PMP) Exam Prep Course 6 - Project Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Project Controls for Optimal Execution

Project Controls for Optimal Execution Project Controls for Optimal Execution Scheduling Techniques to Optimize Execution Tony Bolstad, Senior Project Controls Manager, Scheduling & Information Services, Inc. www.1sis.com Agenda Scheduling

More information

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms GLOSSARY 1. Inclusions and Exclusions This glossary includes terms that are: Unique or nearly unique to project management (e.g., project scope statement, work package, work breakdown structure, critical

More information

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix INDEX: 1. Course Description 2. Course Development 3. Certifications offered by

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

Andrew Avalon, P.E., PSP

Andrew Avalon, P.E., PSP Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,

More information

The Planning Process Group

The Planning Process Group Assalam-o-alaikum Project Management Process Groups Project Integration Management Knowledge Areas Initiating Planning Executing Scope Time Cost Quality Human Resources Communications Monitoring & Controlling

More information

Document No: SB002-P3 Revision No: Last Updated: April

Document No: SB002-P3 Revision No: Last Updated: April BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

Abbreviations Foreword Author s Note. PART I Key Principles, Processes and Methodologies 1. 1 Introduction to Project Management Techniques 3

Abbreviations Foreword Author s Note. PART I Key Principles, Processes and Methodologies 1. 1 Introduction to Project Management Techniques 3 Contents Abbreviations Foreword Author s Note PART I Key Principles, Processes and Methodologies 1 1 Introduction to Project Management Techniques 3 1. What is a Project? 5 2. Types of Projects 6 3. What

More information

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder

More information

The Scheduling Maturity Model. ched

The Scheduling Maturity Model. ched at The Scheduling Maturity Model ched Table of contents Preface 4 Foreword 5 Acknowledgements 6 Applicability 7 Introduction 8 Fundamental Concepts 9 How is the Maturity Model used for Assessment? 10 What

More information

Project Management Basics

Project Management Basics IIA Beach Cities Chapter September 20, 2017 Project Management Basics Michael Haas PMP Dina Keirouz PMP Overview Introductions What is Project Management What is the role of the Project Manager Questions

More information

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek Schedule Margin Contingency for Schedulers John Owen, Product Manager Schedule and Risk, Deltek Contingency / Management Reserve Let s start with a question Have you ever seen a project without any Contingency

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 7-1 Project Resources

More information

RiskyProject Lite 7. Getting Started Guide. Intaver Institute Inc. Project Risk Management Software.

RiskyProject Lite 7. Getting Started Guide. Intaver Institute Inc. Project Risk Management Software. RiskyProject Lite 7 Project Risk Management Software Getting Started Guide Intaver Institute Inc. www.intaver.com email: info@intaver.com Chapter 1: Introduction to RiskyProject 3 What is RiskyProject?

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

EVALUATION COPY. Unauthorized Reproduction or Distribution Prohibited THE OCCASIONAL PROJECT MANAGER

EVALUATION COPY. Unauthorized Reproduction or Distribution Prohibited THE OCCASIONAL PROJECT MANAGER THE OCCASIONAL PROJECT MANAGER 2016 by Systemation. ALL RIGHTS RESERVED. No part of this book may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying

More information