Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Size: px
Start display at page:

Download "Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management"

Transcription

1 Project Management Professional (PMP) Exam Prep Course 6 - Project

2 Slide 1 Looking Glass Development, LLC (303) / (888) S. Ulster St. #150 Denver, CO information@lookingglassdev.com

3 Slide 2 All the processes required to ensure timely completion of the project. The major output of these processes is the project schedule. Planning Process Group

4 Slide Plan Defines the rules for developing & managing the schedule. The benefit of this process is that it provides guidance & direction on how the schedule will be managed. Planning Process Group

5 Slide Plan Inputs.1 Project charter.2 Project management plan.3 Enterprise environmental factors.4 Organizational process assets Tools & Techniques.1 Expert judgment.2 Data analysis.3 Meetings Outputs.1 plan

6 Slide Define Activities Creating a list of all the work that needs to be done to produce the project deliverables. Work packages are decomposed into schedule activities. These schedule activities provide a basis for estimating, scheduling, executing, and monitoring and controlling. Planning Process Group

7 Slide 6 Less Details Project Initiation Rolling Wave Planning Analyze Existing Situation Define New System Requirements Purchase And Install Package Construct & Test System Components Test & Implement System Planning Details More Details Project Start Time

8 Slide 7 Inputs.1 Project management plan.2 Enterprise environmental factors.3 Organizational process assets 6.2 Define Activities Tools & Techniques.1 Expert judgment.2 Decomposition.3 Rolling wave planning.4 Meetings Outputs.1 Activity list.2 Activity attributes.3 Milestone list.4 Change requests.5 Project management plan updates

9 Slide Sequence Activities Ordering the activities that have been defined and assigning logical dependencies. Planning Process Group

10 Slide 9 PDM Finish to Start Start to Start Finish to Finish Start to Finish A S - S B C F - S D E S F is not common F G H F - F

11 Slide 10 Conditional Diagramming GERT is most common. Allows for probability. Allows for looping. 20% Eyeball Diagram 80% A B C

12 Slide 11 Dependencies Mandatory (hard logic) Mandatory dependencies are defined as situations where the ordering of task, activities or deliverables is locked into place by the work itself and there is no other alternative path. Discretionary (soft logic) Discretionary dependencies are situations where there is more than one possible path to complete the project work, but someone has chosen a specific path for some reason. External External dependencies refer to situations where dependencies are placed on the project team by some outside force, regardless of logic or preference. Regulations and laws are the most common form of external dependencies.

13 Slide 12 Leads & Lag Lead time occurs whenever a finish-to-start relationship allows the successor task to start prior to the completion of the predecessor. Lag time represents a relationship that requires a delay between the two tasks.

14 Slide Sequence Activities Inputs.1 Project management plan.2 Project documents.3 Enterprise environmental factors.4 Organizational process assets Tools & Techniques.1 Precedence diagramming method (PDM).2 Dependency determination and integration.3 Leads and lags.4 Project management information system Outputs.1 Project schedule network diagrams.2 Project document updates

15 Slide 14 Dependency Determination Mandatory External Dependency Mandatory Internal Dependency Discretionary External Dependency Discretionary Internal Dependency

16 Slide 15 Leads & Lag

17 Slide Estimate Activity Durations Compilation (not the sum) of activity duration estimates results in the project duration. All supporting data is documented. Uses identified risks and cost estimates. Accuracy improves over time. Ranges, e.g. 280 days -5% to +10%. Planning Process Group

18 Slide Estimate Activity Duration Inputs.1 Project management plan.2 Project documents.3 Enterprise environmental factors.4 Organizational process assets Tools & Techniques.1 Expert judgment.2 Analogous estimating.3 Parametric estimating.4 Three point estimating.5 Bottom-up estimating.6 Data analysis.7 Decision making.8 meetings Outputs.1 Duration estimates.2 Basis of estimates.3 Project document updates

19 Slide 18 Project Evaluation & Review Technique (PERT)

20 Slide 19 Project Evaluation & Review Technique (PERT) PERT Weighted = Average PERT Standard = Deviation Optimistic + 4X Most Likely 6 Pessimistic - Optimistic 6 + Pessimistic

21 Slide 20 Distributions A binomial distribution is used whenever there are only two possible outcomes. A uniform distribution represents a scenario where each value of a random variable has an equal probability of occurrence. A triangular distribution is a continuous probability distribution that begins with a minimum value, ends with a maximum value, and makes use of a mode, or most likely value somewhere along the continuum. A beta distribution represents a distribution of probabilities when we don t know what the probability is. The central limit theorem (CLT) states that the mean of a large population of independent and random variables, each having a finite mean and variance will be normally distributed.

22 Slide 21 Reserves Contingency Reserves These represent reserves controlled by the project manager and they are to be used for know unknowns. This means the project manager and team can plan for an event that they see as possible. Management Reserves These represent reserves controlled by the project sponsor or the senior management. They cannot be accessed without their permission. Management reserves are used to respond to unknown unknowns. These are events that cannot be planned for.

23 Slide 22 Agile Estimation Ideal Time - Assumes resources 100% dedicated Relative Sizing Often called T-Shirt sizing. Points Aggregates complexity & time. Fibonacci Sequence Another comparison technique. Affinity Estimating Process of grouping requirements into categories or collections. Used to group similarly sized user stories together.

24 Slide 23 Iterative. 6.5 Develop Schedule Determines planned start and end dates for activities and the whole project. Baseline for measuring progress. Planning Process Group

25 Slide 24 CPM The Critical Path is the project path which will be the longest duration or where all activities have zero float. The Critical Path does not necessarily have the greatest risk. The Critical Path determines the earliest completion of the project.

26 Slide 25 CPM ES - Early Start is the earliest the task can begin. Dur Duration is the amount of calendar time the task will take. EF - The Early Finish is the earliest the task can end. LS The Late Start is the latest the task can begin. LF The Late Finish is the latest the task can end. Float - The Slack, slip or float is amount of time the task can delay without impacting the project end date. Also called Total Float. Near Critical Path A network path close in length to the critical path. Free Float The amount of time a task can delay without delaying the early start date Project Float The amount of time the project can be delayed without impacting an externally imposed completion date. ES DUR EF Deliverable LS Float LF

27 Slide 26 The Critical Path Method EF = ES + DUR = Forward Pass LS = LF DUR = Backward Pass Float = LF EF or LS ES ES DUR EF Deliverable LS Float LF Deliverable C Deliverable D Deliverable A Deliverable B Deliverable E Deliverable F

28 Slide 27 After CPM. Resource Optimization Redistribute resource assignments where a resource is needed on more than one task in the same time period. Can change the critical path.

29 Slide 28 Critical Chain Method Critical Chain = Longest chain PDM/CPM of dependent tasks with zero slack taking into consideration resource constraints Progress equal burn rate of the buffers vs. work complete Measurement is done against the Project Buffer. OR 10 BL PR 10 FB R 15 OR 30 FB GR Y 20 PB 27 FB 5 BL 30 Y 10 Using CPM would take an estimated 75 units. Which is then missed by 100%. CCPM allows for more accurate estimates with smaller misses.

30 Optionality Slide 29 A Sample Map The Backbone Sequence Walking Skeleton Less Optional More Optional

31 Slide Develop Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project documents.3 Agreements.4 Enterprise environmental factors.5 Organizational process assets.1 Schedule network analysis.2 Critical path method.3 Resource optimization.4 Data analysis.5 Change requests.6 Schedule compression.7 Project management information system.8 Agile release planning.1 Schedule baseline.2 Project schedule.3 Schedule data.4 Project calendars.5 Change requests.6 Project management plan updates.7 Project document updates

32 Slide 31 Leveling vs. Smoothing Resource leveling involves adjusting the start and finish dates of tasks to prevent resources from becoming over allocated. Resource smoothing adjust the project activities so they do not exceed predefined resource limits. This is different from leveling in that smoothing does not allow the project s critical path to change and the project s completion date cannot be delayed.

33 Slide 32 Leveling vs. Smoothing Similarities Resource Leveling Resource Smoothing A schedule network analysis technique. A resource optimization technique. Improves resource utilization. A schedule network analysis technique. A resource optimization technique. Improves resource utilization.

34 Slide 33 Resource Leveling Leveling vs. Smoothing Aim is to adjust start and end dates of a project with resource constraints while balancing resource requirements and resource availability Used in resource-constrained scheduling. Critical path of the project will be affected, and usually the length of critical path will increase. Can be applied to resources on critical path. Free and total float (or slack) may be used. Will optimize all the resources and may change the duration of the project. Risk: May change the critical path and hence the duration. Differences Resource Smoothing Aim is to achieve optimal resource usage by avoiding peaks and valleys in the resource usage profile. Hence the name smoothing. Used in time-constrained scheduling. Critical path of the project won't change. Doesn't apply to resources on critical path. Free and total float (or slack) are used. May not be able to optimize all the resources if sufficient slack (or float) isn't available, but does not change the duration of the project. Risk: Loss of flexibility due to reduction in slack. Hence chances of increase in number of near-critical activities.

35 Slide 34 Other Terms One-Point Estimate A single value estimate. Regression Analysis A graphic analysis to track if two variables are related. Heuristic A rule of thumb. Learning Curve The improvement achieved by doing an activity more than once. Monte Carlo Simulation A computer model which allows the analyst to simulate an activity 1,000 or more times to achieve a probability of a result. Looking Glass Development, LLC.

36 Slide 35 Crashing vs. Fast Tracking Fast Tracking Fast Tracking is doing dependent items in parallel. It amounts to changing a finishto-start relationship to a start-to-start or a finishto-finish relationship. For the exam it is important that you remember that the negative impact of Fast Tracking is the potential for rework. Crashing Crashing is increasing the number of hours worked. This can be done by adding resources assigned to a task, activity or deliverable or by simply working overtime. The negative impact of Crashing that must be remembered is a likely increase in costs.

37 Slide 36 Gantt Charts

38 Slide 37 Milestone Chart

39 Slide Control Schedule Part of Integrated Change Control. Determine the current status of the project schedule. Influence the factors that create schedule changes. Determine that the project schedule has changed. Manage the changes as they occur.

40 Slide 39 Inputs.1 Project management plan.2 Project documents.3 Work performance data.4 Organizational process assets 6.6 Control Schedule Tools & Techniques.1 Data analysis.2 Critical path method.3 Project management information system.4 Resource optimization.5 Leads and lags.6 Schedule compression Outputs.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan updates.5 Project documents updates

41 Slide 40 Project Time Management Summary Six (6) processes. PERT, GERT, PDM, CPM, CCPM. Crashing, fast tracking. Decomposition, baseline, float or slack. Schedule development is iterative.

42

43 Review Questions Part 1: 1. A resource gives you a pessimistic estimate of 10 days and an optimistic estimate of 6 days. What is the standard deviation? A B. 4 C D A resource gives you a pessimistic estimate of 9 days and an optimistic estimate of 4 days. What is the standard deviation? A B C D A resource gives you a pessimistic estimate of 5 days and an optimistic estimate of 2 days. What is the standard deviation? A B. 0.5 C D A resource gives you a pessimistic estimate of 15 days and an optimistic estimate of 6 days. What is the standard deviation? A. 8.0 B C. 9.5 D A resource gives you a pessimistic estimate of 17 days and an optimistic estimate of 8 days. What is the standard deviation? A B C. 1.5 D. 1.83

44 6. A resource gives you a pessimistic estimate of 25 days and an optimistic estimate of 15 days. What is the standard deviation? A B C D A resource gives you a pessimistic estimate of 28 days and an optimistic estimate of 17 days. What is the standard deviation? A B C D A resource gives you a pessimistic estimate of 21 days and an optimistic estimate of 12 days. What is the standard deviation? A B C. 14 D Completion of the project scope is measured against all of the following A. The product requirements B. The project management plan C. The scope statement D. The WBS and the WBS dictionary 10. All of the following are inputs to the define scope process except: A. Project charter B. WBS dictionary C. Project documents D. Organizational process assets

45 Review Questions Part 2: 1. When comparing the Critical Chain to the Critical Path which of the following is true? A. The Critical Path accounts for resource limitations B. The Critical Chain accounts for resource limitations C. The Critical Path uses aggressive estimates D. The Critical Chain uses pessimistic estimates 2. The Critical Chain Methodology schedules each activity to: A. Occur as late as possible B. Occur as soon as possible C. Occur with the middle schedule D. Any of the above 3. The Critical Chain Method focuses on managing what? A. Total project float B. The Critical Path C. Buffers D. Specific network paths 4. What is the major difference between the Critical Path and the Critical Chain? A. The Critical Path takes into account resources B. The Critical Path is always longer C. The Critical Chain is always longer D. The Critical Chain takes into account resources 5. Which of the following statements about the Critical Chain is true? A. Critical Path management does not allow multi-tasking B. Critical Chain management uses bar charts C. Critical Chain management does not allow multi-tasking D. All of the above are true

46 6. Which of the following statements about Critical Chain Management is true? A. It is a methodology that creates an optimized project schedule that considers resource limitations B. It is a methodology that works best when resources are unlimited but schedule milestones are restricted C. It makes extensive use of PERT D. It is used primarily with Agile Methodologies in information technology projects. 7. Which of the following is not a step in the Theory of Constraints (TOC)? A. Identify the constraint B. Identify the next systems constraint C. Exploit the constraint D. Subordinate everything to the constraint 8. According to the TOC most current management philosophies focus on what? A. Throughput management B. Schedule management C. Cost management D. Balancing all of the above 9. According to the TOC, what is the only way to achieve good cost performance? A. Achieve good local performance everywhere B. Manage costs throughout the system C. Have visibility to all costs D. Have all project team members know the project costs

47 Review Questions Part 3: 1. What is the variance of a project that has a best case estimate of 6, a most likely case estimate of 7, and a worst case estimate of 10? A B C D Your project is significantly over budget and behind schedule. It is critical that you determine your projected duration. To gain a better understanding of the project you analyze the sequence of deliverables, activities or tasks to findthe ones with the least amount of schedule flexibility. What technique are you using? A. GERT B. CPM C. PERT D. PDM 3. A project manager is discussing her project with her boss. They are concerned that the project might be falling behind schedule and decide they must determine the project s likely completion date and find out where any flexibility exists. Which of the following tools would best provide this information? A. AOA B. PDM C. CPM D. Network Diagramming 4. You are the project manager for a new product. You are in the planning phase of your project and have just been told by one of your senior resources that they require the completed schematics before they can begin to build the product prototype. This is an example of what kind of dependency? A. Mandatory B. Discretionary C. Internal D. External

48 5. You are the project manager at a major pharmaceuticals company. You are planning the release of a new drug and must wait for regulatory approval before you can begin manufacture of the drug. This is an example of what kind of dependency? A. Discretionary B. External C. Internal D. Mandatory 6. Which of the following is a type of bar chart? A. Gaussian distribution B. Scatter plot C. Gantt chart D. Logit model 7. As a general rule, which of the following is better illustrated by network diagrams than by bar charts? A. Project progress B. Logical relationships between activities C. The project s critical chain D. Resource needs 8. Which of the following is not correct about PDM? A. The critical path always has dummy tasks B. Every network has at least one critical path C. The network displays all task interdependencies D. Tasks not on the critical path have slack or float 9. Which of the following terms represents a method of problem solving that relies on inductive reasoning from past experience or expert judgment when there is no relevant mathematical algorithm available? A. A heuristic B. A logit C. GERT D. Analogous estimating

49 10. Which of the following best describe the amount of time that one activity can be delayed without impacting the early start of its succeeding task or activity? A. Lead time B. Float C. Lag time D. None of the above 11. Which of the following terms best represents the amount of time one activity can begin prior to the completion of its preceding dependent task? A. Lag time B. Lead time C. Float D. None of the above 12. Which of the following statements is correct? A. A network diagram allows you to determine the amount of time the project will take. B. A WBS allows you to determine the longest chain of dependent tasks. C. Changing the end date of the project will cause the network diagram to change. D. The critical path will always contain dummy tasks. 13. Which of the follow statements about a milestone is true? A. A milestone can have any duration B. A milestone has the same duration as the task, activity or deliverable it represents C. A milestone always has zero duration D. None of the above 14. Which of the following statements best describes the relationship between standard deviation and risk? A. Standard deviation provides the level of uncertainty about the estimate B. Standard deviation defines whether or not safety is in the estimate C. Standard deviation defines the accuracy of the estimate D. There is no relationship between risk and standard deviation

50 15. Your boss asks you to use Monte Carlo analysis to evaluate your project. For what purpose was this request most likely made? A. To create an activity s estimated length B. To gain an indication of the risk in the project C. To define the order in which activities occur D. Define project resource requirement 16. On Monday morning your boss comes into your office and asks about the amount of slack you have on a specific activity in your project. This is determined by which of the following: A. Performing a PERT analysis. B. Estimating the task or activity length. C. Creating a PDM diagram. D. Determining the total amount of time that a schedule activity may be delayed without impacting the project delivery. 17. Your boss enters your office and is concerned that a particular activity will delay the delivery of the project. What is the best thing to do? A. Determine if the activity is on the critical path. B. Explain why your boss should not worry. C. Perform a GERT analysis. D. Examine the activity s risk triggers. 18. You and your project team have obtained estimates for your project, assigned resources, and developed a precedence diagram of the project. Several of your resources are very concerned that two of the activities are not being focused on enough and will end up delaying the project because they are critical components of the project s end product. What is the best thing to do? A. Sit down with the resources to discuss the project Gantt chart. B. Determine if the activities in question are on the critical path. C. Examine the project s risk register. D. Evaluate alternative project execution paths. 19. Which of the following best describes the impact of multiple critical paths on a project? A. The project takes longer to complete. B. The project is more expensive. C. The project takes more resources to manage. D. The project risk increases.

51 20. You and your project team have just completed the development of your PDM diagram. The current diagram shows there are three critical paths in your project. What is the best thing to do next? A. Re-evaluate the network for errors. B. Develop the project schedule. C. Examine the project risk register. D. Discuss alternative networks with your team. 21. In discussing your project with management you determine that the project schedule is the most flexible and the project scope is the least flexible. If the allowable monthly project expenditures are fixed, then what is the best thing to do? A. Level the resources. B. Examine the project s critical path. C. Analyze the project s life cycle costs. D. Crash the project. 22. Your manager asks you to produce a report on your project for management. Which of the following would best meet the request? A. Bar chart B. PERT chart C. Milestone chart D. Gantt chart 23. You and your project team have just completed the development of your project schedule. Based on the constraints provided by the project sponsor, the project is scheduled to be completed after the project deadline. Assuming that costs are the least important constraint and scope is the most important constraint, which of the following is the best thing to do? A. Fast track the project. B. Crash the project. C. Reassess the critical path. D. Develop a critical chain model for the project.

52 24. You and your project team have just completed the development of your project schedule. Based on constraints provided by the project sponsor, the project is scheduled to be completed after the project deadline. Assuming that costs are the most important constraint and scope is the least important constraint, which of the following is the best thing to do? A. Crash the project. B. Reassess the critical path. C. Develop a new project schedule. D. Fast track the project. 25. Your manager comes to you and demands that you complete your project three weeks early. What is the best thing to do? A. Meet with your project team to examine alternatives for crashing and fast tracking. B. Tell your boss the project critical path does not allow for a three week early completion. C. Ask the project to work overtime. D. Ask your manager if you can reduce the scope of the project. 26. When evaluating the impact that crashing will have on your project, which of the following should be included in the evaluation? A. The project sponsor s interest. B. Risks associated with the schedule changes. C. The amount of overtime to be worked. D. The impact of a reduction in project scope. 27. Which of the following PM processes requires the project manager to reach an agreement with the activity resources on the calendar date for each activity? A. Sequence activities. B. Estimate activity durations. C. Estimate resources. D. Develop schedule. 28. It is late Friday afternoon when your project sponsor informs you that the project schedule has been reduced by two weeks. What is the best thing to do? A. Meet with your project team to determine options for schedule compression. B. Cut the project scope. C. Crash the project. D. Inform management that the date cannot be met.

53 29. As the project manager, you estimate the time that is needed for each activity, assign tasks to specific resources and then add the estimates to create the project estimate. You then use this value to establish the project delivery date which you provide to the project sponsor. What is incorrect with this process? A. The project manager created the estimates without the team. Additionally, summing the tasks will lead to a significantly longer project duration. B. Project duration estimates should be developed by the project sponsor. C. The project manager created the estimates without the project resources and did not use a network diagram to define the critical path. D. The project completion date should be derived from an evaluation of the triple constraints. 30. You are the project manager for a large construction project. It is early in the project lifecycle and you have completed the activity definition. In analyzing the activities you see a number of activities that are dependent on each other but can start at the same time. Which methodology is the best one to properly evaluate this project? A. CPM B. PDM C. AOA D. GERT 31. You are the project manager for a $250,000 software development project. You are working with your project team and you determine that the project has a number of project tasks that are dependent on each other. However, one of your team members also points out that the tasks can finish at the same time. Which of the following is the best technique to understand this situation? A. Critical path method B. Activity on arrow method C. Precedence diagramming method D. Program evaluation and review technique

54 32. You are the project manager for a large consulting company leading a process improvement project for your organization s largest client. The project currently has a CPI of 1.04 and SPI of.98. Your customer has just asked if you can produce a diagram that shows the probabilistic project path. Which of the following tools would be best in this situation? A. Graphical evaluation and review technique B. Program evaluation and review technique C. Critical path method D. Precedence diagramming method 33. Which of the following is best suited to define a project network that has potential looping of the activities, deliverables or tasks? A. PERT B. CPM C. GERT D. PDM 34. You are the project manager for a software development project with an estimated budget of $650,000. You have just completed the duration estimates, and activity sequencing for your project. Which of the following do you still need to complete the initial project schedule? A. Performance measurement baseline B. Contingency reserves C. Schedule data D. Schedule management plan 35. You are just taking over for a project manager who was forced to take a medical leave of absence. Your project has a CPI of.93 and an SPI of.89. To gain a better understanding of how the previous project manager was managing schedule changes, to which of the following would you turn? A. The project plan B. The project schedule C. The schedule management plan D. The project Gantt chart

55 36. You are taking over for a project manager who was terminated. The previous project manager was using weighted average duration estimates to develop the schedule network. What type of modeling are you using? A. Monte Carlo analysis B. Project evaluation and review technique analysis C. Critical chain analysis D. Critical path analysis 37. You are the project manager for a large mechanical engineering project. You have completed your scope statement, the WBS, the resource estimate, duration estimates, and the network diagram. Which of the following is the thing you should do next? A. Create the schedule B. Complete the cost estimates C. Define the project budget D. Solicit purchase 38. You work as a project manager and have completed the scope statement, resource estimates, and the WBS. You ve just received the activity duration estimates. Which of the following is your best course of action? A. Finalize the schedule B. Compress the schedule C. Complete the risk register D. Develop RFPs 39. One of your resources comes into your office to discuss their task. The project has a CPI of.89 and an SPI of.92. The resource s task has an early start of week 14 and a late start of week 17. What do you know about this activity? A. It is ahead of schedule B. It is behind schedule C. It is on the critical path D. It is not on the critical path 40. You have an activity that has an ES of 12 weeks, an LS of 15 weeks, an EF of 21 weeks, and an LF of 24 weeks. What do you know about this activity? A. It is not on the critical path B. It is ahead of schedule C. It is behind schedule D. It is on the critical path

56 41. You are leading a project that you have just learned is 3 weeks behind schedule. The dependencies are discretionary. The project has an SPI of.81 and a CPI of.83. Due to cost overruns you cannot add more resources. What is the best thing to do? A. Move resources from tasks with discretionary dependencies B. Complete activities in parallel where possible C. Reduce resources D. Reduce project scope 42. You ve been brought into the organization because senior management is struggling to get a strong understanding of the state of their projects. You only have a week to prepare a 30 minute presentation on the status of all the projects. Which of the following would best help senior management understand the current portfolio status? A. Project management plan executive summaries B. Detailed cost and schedule analysis C. Milestone charts D. Gantt charts 43. Sally is a brand new project manager within a company that manufactures household products. She s just taken over a project that is seriously over budget and behind schedule. Originally, the project was slated to have spent $135,000 and they have already spent $170,000. It appears that most of the overage is because of flawed original estimates. This project is critical to the organization s success. Who has primary responsibility to solve these issues? A. The project sponsor B. The project manager C. The project team D. Senior management 44. You are the project manager for a project that you have just learned is 30 days behind schedule. You do not have any additional resources that may be engaged. The project has a CPI of.84 and an SPI of.79. The BCR is 1.45 and only a few of the project tasks have mandatory dependencies. What is the best thing to do? A. Meet with the project sponsor to inform them of the delay. B. Reduce the project scope to meet the deadline. C. Crash the project. D. Make more activities concurrent.

57 45. Rearranging dependent tasks or activities so they are done in parallel is called what? A. Fast tracking B. Leveling C. Paralleling D. Crashing 46. Rearranging resources and resource workloads so that the amount of work done in each month or specified time period is constant is called what? A. Fast tracking B. Paralleling C. Leveling D. Crashing 47. Adding additional resources to reduce the schedule time of a task or activity is called what? A. Fast tracking B. Crashing C. Paralleling D. Leveling 48. Which of the following is a benefit of a three point project estimate? A. It shows a better understanding of the task. B. It allows the project manager to better manage stakeholder expectations. C. It helps determine if the project will meet the schedule. D. It provides a probabilistic estimate. 49. Which of the following is a benefit of analogous project estimates? A. It helps to raise questions about expectations. B. The estimates will more accurately reflect actuals C. It helps the project resources understand their obligations. D. It helps senior management feel better about the estimates. 50. Which of the following is an advantage of parametric estimating? A. It accounts for estimating uncertainty. B. It provides for improved communication. C. It provides a quantifiable deterministic estimate. D. It provides estimates at the lowest possible level.

58 51. You are the project manager for a very large and important project within your organization. Your project has been progressing very well until the last couple of weeks when you began to experience a large number of scope changes. Your current CPI is 1.02 and your SPI is.98. As the project manager, what should you do? A. Maintain the baseline and make approved changes. B. Maintain the baseline and resist all changes. C. Make only the changes approved by the project sponsor. D. Initiate a discussion with management about the level of changes. 52. Your boss asks you to change a presentation slide showing a network diagram to one showing a bar chart. Which of the following best explain this request? A. Bar charts show logical relationships more effectively than network diagrams. B. Bar charts better display resource trade-offs than network diagrams. C. Bar charts better show the critical path than network diagrams. D. Bar charts better display progress or status. 53. You are leading a large project for your organization. Early in the project the sponsor informs you that neither time nor costs are as important as the number of resources used each month. Which of the following is the best thing for you to do? A. Level the project resources B. Crash the project C. Fast track the project D. Apply a heuristic 54. Upon presenting your plan to your sponsor you are informed that the schedule exceeds the target completion date the sponsor desired. If the project network diagram cannot change, but the sponsor offers extra resources what is the best thing to do? A. Crash the project B. Fast track the project C. Level the resources D. Perform a Monte Carlo analysis

59 55. You ve determined that crashing your project is the best option for reducing your project schedule. The best approach to crashing would also include looking at the: A. Sponsor s opinion of which activities to crash. B. Risk impacts of crashing each activity. C. Customer or end user s opinion of which activities to crash. D. When in the project timeline the activities occur. 56. You are assigned as the project manager for a manufacturing project within your organization. During the planning phase of the project, you estimate the time needed for each activity and then add the estimates to create the project estimate. You then commit to delivering the project by the defined date. What is wrong with this scenario? A. The team did not create the estimate, and compilation was not used. B. The estimate is too short and should be created by management. C. The team did not create the estimate and a network diagram was not used. D. The estimate should be matched to the customer s required completion date. 57. You have a project with the following activities: Activity A takes 40 hours and is the first task. Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and takes 35 hours. Activity D must happen after activities B and C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is true if activity B actually takes 37 hours? A. The critical path is 67 hours. B. The critical path changes to Start, B, D, End. C. The critical path is Start, A, C, E, F, End. D. The critical path increases by 12 hours. 58. The WBS, activity duration estimates, and the precedence diagram are completed. Which of the following should you do next? A. Validate project scope. B. Identify project risks. C. Sequence the activities. D. Create a preliminary schedule and get the team s approval.

60 59. You are leading an engineering project for your organization and have developed a six level WBS that has been sequenced using PDM. The activity duration estimates have been received. What should you do next? A. Create an activity list. B. Begin the work breakdown structure. C. Finalize the schedule. D. Compress the schedule. 60. You are the project manager for an information technology project within your organization. A five-level work breakdown structure has been developed for the project. The network diagram and duration estimates have been created and the schedule has been developed and compressed. Which of the following time management activities should you do next? A. Gain approval. B. Estimate activity resources. C. Use parametric estimating. D. Control the schedule. 61. The project is calculated to be completed two weeks after your sponsor s deadline. You have been told there are no additional resources. The project is low risk, the benefit cost ratio is expected to be 1.71, and the project dependencies are preferential. What is the best thing to do? A. Remove non-critical activities from the project. B. Make more activities concurrent. C. Cut resources from non-critical activities. D. Move resources from preferential dependencies to external dependencies.

61 Answer Key Part 1: 1. A Answer A. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 10-6 = 4 and then 4/6 = C Answer C. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 9-4 = 5 and then 5/6 = B Answer B. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 5-2 = 3 and then 3/6 =.5 4. D Answer D. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 15-6 = 9 and then 9/6 = C Answer C. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 17-8 = 9 and then 9/6 = A Answer A. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 10 and then 10/6 = C Answer C. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 11 and then 11/6 = 1.83

62 8. D Answer D. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 9 and then 9/6 = A Answer A. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 18 and then 18/6 = B Answer B. The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 12 and then 12/6 = 2.0

63 Answer Key Part 2: 1. B Answer B. The Critical Chain is the longest chain of dependent tasks with zero slack or float taking into consideration resource constraints. The difference between the Critical Path and the Critical Chain is the resource considerations. When using the Critical Chain Methodology it is important that you use true, most likely case estimates without safety. 2. A Answer A. The Critical Chain Method requires the creation of a PDM Diagram and then scheduling from the late finish date for each activity asks the project manager to add in resource, feeder and project buffers. 3. C Answer C. Critical Chain Management focuses on managing the three different types of project buffers: Project, feeder, and resource. 4. D Answer D. While in most cases the Critical Chain will be longer, there is no set rule guaranteeing it. However, it is true that the Critical Chain does take into account resource limitations while the Critical Path does not. 5. C Answer C. Because CCPM focuses on the longest chain of dependent tasks that takes into account resource constraints, it specifically excludes multi-tasking. 6. A Answer A. The core argument of Critical Chain Management is that most projects fail because they do not consider the limitations of the resources. This means that one resource cannot be doing two tasks at the same time. When this happens, the resource in question becomes the bottleneck and will delay the project.

64 7. B Answer B. The Theory of Constraints has five major steps: A - Identify the system constraint B - Exploit the constraint C - Subordinate everything to the constraint D - Elevate the systems constraints E - Repeat the process 8. C Answer C. According to the Theory of Constraints, most current management philosophies focus on either cost or throughput management. In reality, most are simply focused on cost management. 9. A Answer A. According to the Theory of Constraints, the only way to achieve good cost performance is to achieve it at each local or independent stage of the process. This localizing factor becomes a major problem for overall project performance because this can be very different from good overall project cost performance. Sometimes a local step needs to be sacrificed to ensure good overall performance.

65 Answer Key Part 3: 1. B Answer B. PMBOK Guide p The correct answer is The PERT variance is calculated by first calculating the PERT standard deviation for the case using the formula of (pessimistic optimistic) / 6. Once you have the PERT standard deviation you must square that result to obtain the PERT variance. 2. B Answer B. Each of these methods provides an evaluation of the project in some way. However, only the critical path method or CPM, focuses in on the amount of slack or float contained by a task. 3. C Answer C. Each of these methods provides an evaluation of the project in some way. However, only the critical path method or CPM, focuses in on the amount of slack or float contained by a task. 4. B Answer B. PMBOK Guide p Internal dependencies are not a type defined by PMI. This is an example of a discretionary dependency because the question clearly states that the schematics are required to go the next step. 5. D Answer D. PMBOK Guide p Internal dependencies are not a type defined by PMI. This is an example of a mandatory dependency. Neither the manufacturing nor the project management processes require the regulatory approval. However, governmental approval is required in order to sell the completed product. 6. C Answer C. PMBOK Guide p A Gantt chart is a type of bar chart laid on its side that also shows a project calendar. The lengths of the bars reflect the length of time the task, deliverable, or activity take. 7. B Answer B. PMBOK Guide p Network diagrams are modeling methods that display the relationships between task, deliverable and activities. Since the bars in a bar chart are independent of each other, they cannot provide this information.

66 8. A Answer A. PMBOK Guide p PDM or the precedence diagramming method is a method of network diagram designed to display task dependencies and relationships. One of its most valuable outputs is the critical path which is the longest chain of dependent tasks where there is no slack or float. 9. A Answer A. A heuristic is a method of problem solving that relies on inductive reasoning from past (expert) judgment when there is no relevant mathematical algorithm. It is also sometimes referred to as a rule of thumb. 10. C Answer C. PMBOK Guide p Lag time represents the amount of time a task or activity can be delayed without impacting the early start of the next task or activity. Often lag is added to a chain to produce a gap between tasks or activities. 11. B Answer B. PMBOK Guide p Lead time represents the amount of time one activity can begin prior to the completion of its preceding dependent task. Lead time is used to compress a schedule and can run the risk of rework. 12. A Answer A. PMBOK Guide p The network diagram is specifically designed to allow you to determine all the potential project paths and the longest time the project can take. A work breakdown structure is used to show the project deliverables. Changing the end date of a project does not necessarily change a network diagram and the critical path never contains dummy tasks. 13. C Answer C. PMBOK Guide p.157. A milestone is a marker representing the completion of a task, activity or deliverable. It never has duration of any length. 14. A Answer A. Standard deviation allows you to determine the amount of dispersion from the mean that your estimates have. The more dispersed the estimates, the more variance exists between the estimates and therefore the greater the risk is.

67 15. B Answer B. PMBOK Guide p Several of these answers are close, but the correct answer is to gain an indication of the risk in the project. Monte Carlo simulations will not tell you about specific risk. They reveal the probabilistic nature of risk. A Monte Carlo simulation enables the user to determine the probability that a result will occur within a given range. The wider the range, the greater the uncertainty or risk. 16. D Answer D. PMBOK Guide p.210. Slack or float represents the amount of time a specified activity may be delayed without impacting the project s critical path. Only items not on the Critical Path have slack or float. It is the difference between the early finish and late finish or the early and late start. 17. A Answer A. PMBOK Guide p.210. Slack or float represents the amount of time a specified activity may be delayed without impacting the project s Critical Path. Only items not on the Critical Path have slack or float. It is the difference between the early finish and late finish or the early and late start. In this case the best answer is to first determine if the task is on the Critical Path and find out how much slack or float it has. 18. B Answer B. PMBOK Guide p.210. Slack or float represents the amount of time a specified activity may be delayed without impacting the project s Critical Path. Only items not on the critical path have slack or float. It is the difference between the early finish and late finish or the early and late start. In this case the best answer is to first determine if the tasks are on the Critical Path and find out how much slack or float it has. 19. D Answer D. PMBOK Guide p.210. Multiple critical paths are not unusual in the real world. This simply means that if any of the activities on any of the Critical Paths are delayed, the entire project will be delayed. This sometimes causes an increase in project resources or cost and it might cause the project to take longer. However, it is a guarantee that the project has an increase in risk because the project now has more chance for an activity delay to impact the delivery of the project.

68 20. B Answer B. PMBOK Guide p.210. Multiple critical paths are not unusual in the real world. This simply means that if any of the activities on any of the critical paths are delayed the entire project will be delayed. Therefore, the existence of multiple critical paths does not represent an error in your process. The development of the PDM Diagram is part of activity sequencing. The next step in the process is developing the project schedule. 21. A Answer A. PMBOK Guide p.211. This is a triple constraints question. If the project schedule is the most flexible, this means the project could continue for several months past the original forecast. This is especially true because the project has an inflexible scope. Because the project cost is fixed on a monthly basis but not on a total basis the best thing to do is level the resources to ensure the monthly project costs do not exceed the allowable amount. 22. C Answer C. PMBOK Guide p.218. The best tool for reporting to management is a milestone chart. This provides the correct level of information for management. 23. B Answer B. PMBOK Guide p.215. The best thing to do in this case is crash the project. This usually entails adding resources to the project to get project work done more quickly. This will cause a likely increase in project costs. Fast tracking is doing tasks in parallel which decreases the schedule, but this often causes rework which in this case is unacceptable. 24. D Answer D. PMBOK Guide p.215. The best thing to do in this case is fast track the project. This is because you do not have the ability to increase the cost by adding resources (crashing). Reassessing the critical path and developing a new schedule are not preferred alternatives. 25. A Answer A. PMBOK Guide p.215. Whenever your due date is reduced, the first thing to do evaluate the two alternatives you have. You can either crash or fast track the project.

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012 5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes

More information

Project Management CSC 310 Spring 2017 Howard Rosenthal

Project Management CSC 310 Spring 2017 Howard Rosenthal Project Management CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project Management - Traditional, Agile, Extreme 7TH Edition Authors:

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2 Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and

More information

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M. Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction

More information

Definition. Name of the tool or technique Project mission statement

Definition. Name of the tool or technique Project mission statement Tools and Techniques Definitions (or by alphabetic order ; see below) A definition of each of the tools and techniques is provided below. The primary sources of definitions were the PMBOK Guide and Max

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

Operations Management

Operations Management 17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

Project Management Professional (PMP) Exam Prep Course 2 - Types of Exam Questions

Project Management Professional (PMP) Exam Prep Course 2 - Types of Exam Questions Project Management Professional (PMP) Exam Prep Course 2 - Types of Exam Questions Slide 1 Types of Exam Questions Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150

More information

Content Break-up & Methodology for awarding Contact Hours / PDUs

Content Break-up & Methodology for awarding Contact Hours / PDUs N.I.T.E - Project Management Professional (PMP) Exam Prep Course Content Break-up & Methodology for awarding Contact Hours / PDUs This course is based on Project Management Book of Knowledge PMBOK Guide

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

IST 302 : Project Time Management

IST 302 : Project Time Management IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.

More information

Program Evaluation and Review Technique (PERT)

Program Evaluation and Review Technique (PERT) Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because

More information

Developing a Project Plan

Developing a Project Plan Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Chapter 3 Managing the Information Systems Project

Chapter 3 Managing the Information Systems Project Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to

More information

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management PMP Exam Preparation Workshop Chapter # 5 Copyright PMI SOC 2013 1 Learning Objectives By the end of this session you will understand: How scope management processes relate to the process groups Project

More information

The PMP CRAM. The Guide to Pass the PMP

The PMP CRAM. The Guide to Pass the PMP 1 The Bellwether Partners www.thebellwetherpartners.com The PMP CRAM The Guide to Pass the PMP PMP CRAM: This guide provides key themes and knowledge areas for preparation the PMP Exam. It is meant to

More information

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition? 1. Which of the following is true regarding the project charter? A. The project charter is a document that formally authorize a project or phase.. B. The project charter represent a high level planning

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business Case Contract Enterprise environmental factors Project charter Expert judgement 26/02/2013 18:22:56 1 2

More information

Project Management Professional (PMP) Exam Prep Chapter 09 - Project Human Resource Management

Project Management Professional (PMP) Exam Prep Chapter 09 - Project Human Resource Management Project Management Professional (PMP) Exam Prep Chapter 09 - Project Human Resource Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO

More information

PMI-001 Questions & Answers

PMI-001 Questions & Answers PMI-001 Questions & Answers Number: PMI-001 Passing Score: 700 Time Limit: 137 min File Version: 21.2 http://www.gratisexam.com/ PMI-001 Questions & Answers Exam Name: Project Management Professional v5

More information

Initiation Group Process. Planning Group Process

Initiation Group Process. Planning Group Process Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani PRINCESS NOURA UNIVESRSITY Project BUS 302 Reem Al-Qahtani This is only for helping reading the PMBOK it has our notes for focusing on the book Project Framework What is PMBOK? o PMBOK= Project Body of

More information

Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam

Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam Slide 1 Application & Exam Types of Questions PM Basics Ten Knowledge Areas Professional Responsibility Practice Exams Slide

More information

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set4.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside

More information

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises Scheduling Delivering On Your Promises Why Schedule? Don t need to, I ve done this before. I have the schedule in my head. Nobody will pay attention to it. Why bother, it just changes. I m on the line

More information

Project Scope Management

Project Scope Management Assalam-o-alaikum Project Management Process Groups Project Integration Management Knowledge Areas Initiating Planning Executing Scope Time Cost Quality Human Resources Communications Monitoring & Controlling

More information

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and

More information

PMP043 Project Scheduling and Budgeting

PMP043 Project Scheduling and Budgeting PMP043 Project Scheduling and Budgeting H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae ictd@ictd.ae Course Introduction: Through an increasingly challenging multimedia-simulated

More information

Project Forecast Survey Results Good Scheduling Practices June 2016

Project Forecast Survey Results Good Scheduling Practices June 2016 Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well

More information

// How Traditional Risk Reporting Has Let Us Down

// How Traditional Risk Reporting Has Let Us Down // How Traditional Risk Reporting Has Let Us Down Dr. Dan Patterson, PMP CEO & President, Acumen November 2012 www.projectacumen.com Table of Contents Introduction... 3 What is Project Risk Analysis?...

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500 Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500 Thierry Labriet, STS STS SA, Lausanne, Switzerland +41 21 510 11 50 office@sts.ch www.sts.ch 1 Contents 1 Foreword... 3 2 Executive

More information

Artificial Intelligence

Artificial Intelligence Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which

More information

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management PMP Training Training Topics Chapter 1 Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus Chapter 2 Objectives of Project Management Framework What is Project

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT ESTIMATE ACTIVITY DURATION PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources

More information

Errata 1 st Printing. Errata 2 nd Printing

Errata 1 st Printing. Errata 2 nd Printing Errata 1 st Printing NOTE: The following errata only pertain to the first printing of the PMBOK Guide Fifth Edition. In order to verify the print run of your book (or PDF), refer to the bottom of the copyright

More information

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Plan Your Work, Work Your Plan Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Agenda Understand what a project is Understand the basics of

More information

PMI EXAM PgMP Program Management Professional (PgMP)

PMI EXAM PgMP Program Management Professional (PgMP) PMI EXAM PgMP Program Management Professional (PgMP) Total Questions: 342 Practice exams also include self assessment and reporting features! 1 Question: 1 Your program has 121 stakeholders that you'll

More information

Software Engineering II - Exercise

Software Engineering II - Exercise Software Engineering II - Exercise April 29 th 2009 Software Project Management Plan Bernd Bruegge Helmut Naughton Applied Software Engineering Technische Universitaet Muenchen http://wwwbrugge.in.tum.de

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Testkings PMP 705q. PMI PMP. Project Management Professional v5

Testkings PMP 705q.  PMI PMP. Project Management Professional v5 Testkings PMP 705q Number: PMP Passing Score: 800 Time Limit: 120 min File Version: 14.5 PMI PMP Project Management Professional v5 This is my first share of braindumps questions. Very helpful study center

More information

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard Your easy, colorful, SEE-HOW guide! Plain&Simple Microsoft Project 03 Ben Howard Published with the authorization of Microsoft Corporation by O Reilly Media, Inc. 005 Gravenstein Highway North Sebastopol,

More information

Planning and Scheduling Training Program Course Brochure and Competency Matrix

Planning and Scheduling Training Program Course Brochure and Competency Matrix Planning and Scheduling Training Program Course Brochure and Competency Matrix INDEX: 1. Company Introduction 2. Training Programme Description 3. Training Delivery Options 4. Course Syllabus 5. Programme

More information

Effective Project Coordination and Management

Effective Project Coordination and Management Effective Project Coordination and Management PROGRAMME SUMMARY Projects frequently fail, not because of a lack of technical skills on the part of those executing the project, but because of inadequate

More information

03/23/2016. Presented for Boston College Employee Development Office March 23, 2016 by Denise M. Guérin, JD, MS-PPM, PMP. Q&A from Session #1

03/23/2016. Presented for Boston College Employee Development Office March 23, 2016 by Denise M. Guérin, JD, MS-PPM, PMP. Q&A from Session #1 2016 Denise M. Guérin Presented for Boston College Employee Development Office March 23, 2016 by Denise M. Guérin, JD, MS-PPM, PMP 1 Q&A from Session #1 Group Meeting Sequencing Activities Building a Network

More information

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Version: 2.0, 18 JAN 2012 Configuration Management Log & Draft Version Status Document Configuration Management

More information

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Version: 2.0, 18 JAN 2012 Configuration Management Log & Draft Version Status Document Configuration Management

More information

Project Management Professional (PMP) Boot Camp

Project Management Professional (PMP) Boot Camp Project Management Professional (PMP) Boot Camp According to the Project Management Institute, the world's leading association for the project management profession: "PMP Certification is the profession's

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information

A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing

A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing A Guide to the Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing NOTE: The following errata only pertain to the first and second printing of the PMBOK Guide Sixth Edition. In order to

More information

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - 3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - PREPARED BY: Jessica Summers Virtual Training Coordinator PPM Global Services, Inc. P: 1-800-746-4029 x 310 F: 1-800-746-4029 E:

More information

Implement. Control. Integrate. Knowledge Leverage. Course Overview

Implement. Control. Integrate. Knowledge Leverage. Course Overview Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Course Overview The Certificate In Project Management (CIPM) exam is administered

More information

Effective PMP Exam Coaching. Effective Project Management Consultancy. PMP Exam Study Material

Effective PMP Exam Coaching. Effective Project Management Consultancy. PMP Exam Study Material Integration Effective Project Management Consultancy Stakeholders Scope Time Cost PMP Exam Study Material Based on PMBOK Guide Fifth Edition Quality Communication Procurement Effective PMC Private Limited

More information

Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA. Introductions 8/31/2017

Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA. Introductions 8/31/2017 Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA 8:00 8:50 Goals, key concepts, five process groups, nine knowledge areas 8:50 9:00 Break/questions 9:00 9:50 Initiating & Planning the project

More information

Project Stakeholder Management

Project Stakeholder Management Jambo (Swahili) Project Management Process Groups Project 4. Integration Management Initiating Planning Executing 5. Scope Monitoring & Controlling Closing Knowledge Areas 6. Time 7. Cost 8. Quality 9.

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),

More information

CPET 545 SOA and Enterprise Applications

CPET 545 SOA and Enterprise Applications SOA Project Planning & Management CPET 545 SOA and Enterprise Applications SOA Project Planning & Management 11-18-2008 SOA Project Phases [1] Requirement engineering Business domain analysis Solution

More information

Project Management Basics

Project Management Basics IIA Beach Cities Chapter September 20, 2017 Project Management Basics Michael Haas PMP Dina Keirouz PMP Overview Introductions What is Project Management What is the role of the Project Manager Questions

More information

ABSTRACT A Remarkably Concise Summary of the PMBOK 5th Edition. John P. Muldoon PMBOK. Summarized

ABSTRACT A Remarkably Concise Summary of the PMBOK 5th Edition. John P. Muldoon PMBOK. Summarized ABSTRACT A Remarkably Concise Summary of the PMBOK 5th Edition PMBOK John P. Muldoon Summarized Introduction to PMBOK Summarized Aug. 15, 2014 This ebook is my attempt to summarize the Project Management

More information

Project Management Techniques

Project Management Techniques Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

Glossary bglos.indd 10/28/2015 Page 1

Glossary bglos.indd 10/28/2015 Page 1 Glossary 2 Glossary Numbers 360 degree review A form of project performance appraisal (a tool and technique of the Manage Project Team process) that solicits feedback from everyone with whom the team member

More information

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Administration Evacuation Timings, meals and facilities Mobile phones and emails Introductions

More information

PMP Exam Preparation Course Project Scope Management

PMP Exam Preparation Course Project Scope Management Project Scope Management 1 Product Scope Product scope The features and functions that are to be included in your products or service or result of the project. Completion is measured against the product

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

PMP Certification Course Outline

PMP Certification Course Outline PMP Certification Course Outline (I) Becoming a PMP (II) Project Management Framework o Project Management Processes for a Project o Project Management Context (III) Project Management Environment o Project

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Examsoon QUESTION

More information

RiskyProject Professional 7

RiskyProject Professional 7 RiskyProject Professional 7 Project Risk Management Software Getting Started Guide Intaver Institute 2 Chapter 1: Introduction to RiskyProject Intaver Institute What is RiskyProject? RiskyProject is advanced

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek Schedule Margin Contingency for Schedulers John Owen, Product Manager Schedule and Risk, Deltek Contingency / Management Reserve Let s start with a question Have you ever seen a project without any Contingency

More information

Schedule Module Exploration Systems Engineering, version 1.0

Schedule Module Exploration Systems Engineering, version 1.0 Schedule Module Exploration Systems Engineering, version.0 Exploration Systems Engineering: Schedule Module Module Purpose: Schedule To understand the different types of schedules: Gantt chart, milestone

More information

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick CPM in Construction Management transition from 7 th to 8 th Edition James J. O Brien Fredric L. Plotnick Introduction to CPM is Still Required Chapter 1. Introduction to CPM Planning and Scheduling 3 1.1

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH.

INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH. INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH. Dec 2014 DATE: 20.12.2014 Max. Marks: 100 TIME: 2.00 p.m to 5.00 p.m. Duration: 03

More information

Lesson Three: Business Analysis Planning and Monitoring BANA 110 Analyzing Business Needs and Requirements Planning Gary Mesick and Shelly Lawrence,

Lesson Three: Business Analysis Planning and Monitoring BANA 110 Analyzing Business Needs and Requirements Planning Gary Mesick and Shelly Lawrence, Lesson Three: Business Analysis Planning and Monitoring BANA 110 Analyzing Business Needs and Requirements Planning Gary Mesick and Shelly Lawrence, Instructors YOU ARE HERE Analysis and the Decision to

More information

CSU Project Management Certificate Program. Project Scope Management

CSU Project Management Certificate Program. Project Scope Management CSU Project Management Certificate Program Project Scope Management Instructor: George Angel eaglebusiness@hotmail.com 303-678-9466 1 Scope gone wild! client wants what? 2 Project Scope Management Agenda

More information

Agenda. PMBOK Guide Third Edition. PMI Standards Background. PMI Life Cycle Plan for Standards. Presented by Kevin Chui, PMP. How Did We Get Here?

Agenda. PMBOK Guide Third Edition. PMI Standards Background. PMI Life Cycle Plan for Standards. Presented by Kevin Chui, PMP. How Did We Get Here? Agenda PMBOK Guide Third Edition Presented by Kevin Chui, PMP Vice President, PMI Hong Kong Chapter Background PMBOK Guide 2004 Update Project Structural Changes to the Standard Process Group Changes Knowledge

More information

Scheduling for Success with Critical Chain. Abstract

Scheduling for Success with Critical Chain. Abstract by Rob Newbold, September 2010 Abstract The Critical Chain scheduling approach described in this paper can be used to create good schedules that have provided substantial benefits in speed, predictability,

More information

LECTURE 8: Planning & Control Functions & Tools (Part II) Project Management BACA

LECTURE 8: Planning & Control Functions & Tools (Part II) Project Management BACA LECTURE 8: Planning & Control Functions & Tools (Part II) Project Management BACA 4132 1 PM PROCESSES INITIATION PLANNING CONTROL PROJECT MANAGEMENT PROCESSES EXECUTION ANALYSIS CLOSING Project Management

More information