Market Trials Structured/Unstructured Test Scenario Detail: 16.2 RUC Offer Curve Subject to Mitigation

Size: px
Start display at page:

Download "Market Trials Structured/Unstructured Test Scenario Detail: 16.2 RUC Offer Curve Subject to Mitigation"

Transcription

1 Market Trials Structured/Unstructured Test Scenario Detail: 16.2 RUC Offer Curve Subject to Mitigation

2 Revision History Date or Version Number 1.0 July 1, July 24, 2013 Author Change Description Comments SPP Operations Temper Williams Initial Version Update Expected Results 1.2 September 12, September 13, 2013 Temper Williams Temper Williams Update Market Participant Activities. Update MP Activities with Markets UI verification information Market Trials Structured/Unstructured Test Scenario Detail 2

3 Table of Contents Revision History Scenario Details Scenario Description Expected Result Market Participant Activities SPP Activities and Procedures Production Like Activities Scenario Specific Activities Additional Requirements & Considerations Additional Considerations Market Trials Structured/Unstructured Test Scenario Detail 3

4 1.0 Scenario Details 1.1 Scenario Description RTBM Mitigated offers for Energy, Start up, and No Load product shall be submitted on a daily basis by the Market Participant in accordance with the Mitigated Offer Development Guidelines. These offers may be submitted up to 1700 hours or one hour following the posting of the DA Market results. For this scenario, MPs should submit RTBM Offers for Energy, Start up, and No Load such that each offer type is subject to mitigation by SPP. 1.2 Expected Result SPP will apply mitigation measures by replacing the Energy, Start up, and/or No Load Offers with the offer if: The Resource s Energy, Start up, or No Load Offer exceeds the applicable threshold as determined in Section of the Integrated Marketplace Protocols; and The Resource is subject to mitigation measures as determined in Section of the Integrated Marketplace Protocols; and The Resource fails the Market Impact Test as described in Section of the Integrated Marketplace Protocols. The START/STOP notification in the Market User Interface will indicate the Resource has been. An Energy Offer below $25/MWh will not be subject to mitigation measures. 2.0 Market Participant Activities Market Participants are to submit Energy, Start up, and No Load offers on a resource with a DAMKT Commit Status of Not Participating such that the difference between the Normal Offer and the Mitigated Offer exceeds the thresholds as described below: The Energy Offer Curve threshold is a 25% increase above the Mitigated Energy Offer for all Resources The offer threshold for the Start up Offer is a 25% increase above the Mitigated Offer for the applicable Start up Offer. The offer threshold for the No Load Offer is a 25% increase above the Mitigated Offer for the applicable Start up and No Load Offer. MPs are to Submit a RMS ticket titled Scenario 16.2 indicating the resource chosen for the scenario. Following execution of the Day Ahead RUC, MPs who submitted offers subject to mitigation and received a DARUC commitment for that Resource should confirm that their Resource received a mitigation START/STOP. This can be performed by checking the Mitigation flag in the START/STOP notifications in the Market User Interface (MUI) b.etween CPT. The START/STOP notifications are located on the Resource Offers tab under Date >Market Results > Commitments >View. Markets User Interface: Mitigation Identification 1) A Mitigated column will be present and true/false will be displayed Market Trials Structured/Unstructured Test Scenario Detail 4

5 Market Results: Commitments Resource: Commitment API and XML Notifications: The following operations allow participants to determine if a resource has been in the Markets system. In order to identify which offers have been, participants should reference the element available in all of the following operations (excluding Mitigated MWP). If this element is set to true, the offer associated with the specified resource has been. Known Issue #550 Mitigation flag not set correctly on commitments that are. This is an issue in the Markets API and Notifications. Market Trials Structured/Unstructured Test Scenario Detail 5

6 Market Results XML Notification API Operation Mitigated flag Day Ahead Energy Cleared Offers n/a GetEnergyClearedOfferSet GetEnergyClearedOfferSetByDay not Day Ahead OR Cleared Offers Mitigated Make Whole Payments Real Time Energy Dispatch n/a GetReserveClearedOfferSet GetReserveClearedOfferSetByDay PostEnergyMitigatedMWPSet GetEnergyMitigatedMWPSetByDay n/a PostEnergyDispatchSet GetEnergyDispatchSet GetEnergyDispatchSetByDay Real Time OR Cleared PostReserveDispatchSet GetReserveDispatchSet GetReserveDispatchSetByDay Resource Commitments PostEnergyCommitmentSet GetEnergyCommitmentSet GetEnergyCommitmentSetByDay not not not not 3.0 SPP Activities and Procedures 3.1 Production Like Activities RUC Operators perform validations and steps necessary to complete Day Ahead RUC execution as documented in the Production like Activities of the Base Day Ahead RUC Market scenario. RUC Operators review results of Day Ahead RUC clearing and ensures appropriate steps for determining and enforcing Mitigation were taken as defined within Section 8 of the Integrated Marketplace Protocols. 3.2 Scenario Specific Activities SPP will manipulate data to ensure that the MPs Resource(s) fail the Market Power Test therefore becoming a mitigation candidate. SPP will also alter the LMP Impact threshold the ensure Resources fail the Impact Test. SPP will validate results of Day Ahead RUC solution and ensure Mitigation was applied within accordance to Section 8 of the Integrated Marketplace Protocols. This includes accurate application of the following: Behavior Test These are tests on a per offer type basis that evaluate the offers associated with a Resource against their offers. Failing a behavior test means that the offer may need to be. Market Power Test This refers to tests that are done to determine if a Resource has the potential to significantly influence price due to congestion across a flowgate. How close an activated flowgate was to binding in the un solve and a Resource s Resource to load distribution factor (RLDF) determines if the Resource is pivotal to the flowgate. Market Trials Structured/Unstructured Test Scenario Detail 6

7 Mitigation Candidate Test These are a set of tests which consider the results of the behavior tests, market power test, and the results of the un solve to come up with a list of offers that should be replaced by their offers in the solves. Impact Test Impact tests involve comparing the results of an un solution with a solution in order to identify Resources that would otherwise enjoy excessive income due to their influence on a constraint. Failing an impact test means that the Resource should be. 3.3 SPP Procedures None 4.0 Additional Requirements & Considerations 4.1 Additional Considerations SPP staff will document the results of the scenario. This documentation should include, but is not limited to, the following: What was the status of MP participation? Did MPs submit all data as requested? What was the quality of the data? How much manual intervention was required by SPP for the input data due to lack of MP participation, quality of data, etc? What were the results of the scenario? Did the results reflect the expected outcome? How much manual intervention was required by SPP to execute the market and achieve a solution? Were the results posted to the MPs by the pre determined deadline? Market Trials Structured/Unstructured Test Scenario Detail 7

2016 ANNUAL VRL ANALYSIS

2016 ANNUAL VRL ANALYSIS 2016 ANNUAL VRL ANALYSIS Published on 08/01/2016 By Ops Market Support/Forensics Chris Davis Ricky Finkbeiner REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 7/11/2016 Ricky

More information

3. Overview of Market Instruments

3. Overview of Market Instruments 3. Overview of Market Instruments 3.2 Ancillary Services Bids Four types of Ancillary Services are used by CAISO in its markets Regulation Up, Regulation Down, Spinning Reserve, and Non-Spinning Reserve.

More information

Agenda. Bilateral Settlement Schedules Overview Bilateral Settlement Schedules Online GUI

Agenda. Bilateral Settlement Schedules Overview Bilateral Settlement Schedules Online GUI Agenda Bilateral Settlement Schedules Overview Bilateral Settlement Schedules Online GUI 2 BILATERAL SETTLEMENT SCHEDULES OVERVIEW 3 Common Acronyms AO Asset Owner API Application Programming Interface

More information

Opportunity Cost Calculator Member Impacting Project Overview

Opportunity Cost Calculator Member Impacting Project Overview Opportunity Cost Calculator Member Impacting Project Overview 5/20/2014 Page 1 Table of Contents Version Control... 2 Document Purpose... 2 Executive Summary... 4 Business Impact... 4 Users Impacted...

More information

Release Notes OASIS April 18, Version 1.1

Release Notes OASIS April 18, Version 1.1 Release Notes OASIS 6.3.0 Version 1.1 April 18, 2013 REVISION HISTORY VERSION NO. DATE DESCRIPTION 1.0 01/09/2012 Initial version 1.1 04/18/2013 Updates on the Report Summary & API Specifications document

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

Relationship-Based Member-Driven Independence Through Diversity Evolutionary vs. Revolutionary Reliability & Economics Inseparable

Relationship-Based Member-Driven Independence Through Diversity Evolutionary vs. Revolutionary Reliability & Economics Inseparable Southwest Power Pool PRICE FORMATION TASK FORCE MEETING October 18, 2016 AEP Offices Dallas, TX SUMMARY OF MOTIONS Motions: Agenda Item 2 Minutes Approval Valerie Weigel (Basin) motioned, and Jim Flucke

More information

SPP Emergency Operations: 2016 Summer Preparedness Workshop

SPP Emergency Operations: 2016 Summer Preparedness Workshop SPP Emergency Operations: 2016 Summer Preparedness Workshop AGENDA 9:00 9:15 Welcome.. CJ Brown 9:20 9:30 EOP Update Process... Kim Gorter 1. Review 2. Posting Red-line Version 3. Stakeholder Interaction

More information

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria MISO-PJM Interface Pricing Post Implementation Metrics and Criteria Contents 1 Introduction... 2 2 Real-Time Market Interchange Price Signal Effectiveness Metrics... 2 2.1 Post Implementation Pricing Monitoring

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. PJM Update 4. MISO Update 5. Congestion Overlap Solution 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM

More information

ERCOT ISO: Current Market and Trends in Future Market Design

ERCOT ISO: Current Market and Trends in Future Market Design ERCOT ISO: Current Market and Trends in Future Market Design Reza Alaghehband, P.E. Control Engineering, Austin Energy, Austin, TX EMS Users Group Meeting September 12-13, 2005 Providence, RI Outline:

More information

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff ConOp Internal NYISO HVDC Controllable Line Scheduling Concept of Operation Author: Scott Harvey, LECG Reviewers: ISO Staff LECG Staff Project Sponsor: Point of Contact: C. King B. Kranz Document Locator:

More information

Local Market Power Mitigation Enhancements

Local Market Power Mitigation Enhancements Local Market Power Mitigation Enhancements Draft Final Proposal May 6, 2011 CAISO/M&ID/CRH May 6, 2011 page 1 Draft Final Proposal Local Market Power Mitigation Enhancements Table of Contents 1. Introduction...

More information

Applying PROBE for Congestion Analysis and Grid Planning

Applying PROBE for Congestion Analysis and Grid Planning Applying PROBE for Congestion Analysis and Grid Planning August 1, 2003 Jim Mitsche JMitsche@power-gem.com 518 393 3834 1 Topics Analysis Objectives Nature of Congestion Cost & Cost Calculation What is

More information

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources Market Issues Bulletin Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources March 10, 2015 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400

More information

Pseudo-Tie Congestion Overlap

Pseudo-Tie Congestion Overlap Pseudo-Tie Congestion Overlap Tim Horger Director, Energy Market Operations Markets & Reliability Committee March 22, 2018 Congestion Overlap Background Pseudo-Tie Market-to-Market congestion overlap between

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

More information

Commitment Cost Default Energy Bids Enhancements (CCDEBE) Business Rules

Commitment Cost Default Energy Bids Enhancements (CCDEBE) Business Rules CAISO proposes to allow market-based offers for each component of the supply offer subject to mitigation and to allow greater flexibility to negotiate or adjust each component. The purpose of this section

More information

LMP Calculation and Uplift

LMP Calculation and Uplift LMP Calculation and Uplift Anthony Giacomoni January 29, 2018 PJM 2017 Session Objectives Review fundamentals of locational marginal pricing (LMP) and uplift Review simple locational marginal pricing and

More information

2014 State of the Market

2014 State of the Market 2014 State of the Market 24 August 2015 SPP Market Monitoring Unit Disclaimer The data and analysis in this report are provided for informational purposes only and shall not be considered or relied upon

More information

6.1.9 IFM Initial Conditions

6.1.9 IFM Initial Conditions 6.1.9 IFM Initial Conditions A Generating Unit that was committed in the previous day s Day-Ahead Market (IFM or RUC) run (TD-2 for TD-1) but was de-committed before HE24 would normally be considered initially

More information

2. Market Operations Overview

2. Market Operations Overview 2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static

More information

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator: ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

Regional Flexibility Markets

Regional Flexibility Markets CAISO Contingency Modeling Alternative: Regional Flexibility Markets March 2014 Southern California Edison Outline Concerns with the CAISO s N-1-1 proposal Alternative approach: Regional Flexibility Markets

More information

BROCHURE. e7 PROMOD Generation and transmission modeling system with nodal and zonal price forecasting

BROCHURE. e7 PROMOD Generation and transmission modeling system with nodal and zonal price forecasting BROCHURE e7 PROMOD Generation and transmission modeling system with nodal and zonal price forecasting 2 B R O C H U R E e7 P R O M O D PROMOD is the premier integrated electric generation and transmission

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

FERC Order 764 Settlements

FERC Order 764 Settlements FERC Order 764 Settlements Spring Release 2014 The information contained in these materials is provided for general information only and does not constitute legal or regulatory advice. The ultimate responsibility

More information

Two Settlement PJM /06/2016

Two Settlement PJM /06/2016 Two Settlement PJM 2016 Objectives Describe Two-Settlement process Day-Ahead Market Balancing Market Explain Virtual Transactions and their settlement Inc Offers Dec Bids Up-to Congestion Transactions

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Initial Trial Report VERSION: 1.0 STATUS: Final for Publication DATE: 29 th SEPTEMBER 2017 Contents Introduction... 3 Objectives

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...

More information

Day-ahead ahead Scheduling Reserve (DASR) Market

Day-ahead ahead Scheduling Reserve (DASR) Market Day-ahead ahead Scheduling Reserve (DASR) Market Agenda Implementation Overview of the DASR Market Market Clearing Process Market Clearing Example Performance Compliance Market Settlements Appendix: emkt

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

Local Market Power Mitigation Options Under Convergence Bidding

Local Market Power Mitigation Options Under Convergence Bidding California Independent System Operator Corporation I. Background Local Market Power Mitigation Options Under Convergence Bidding Department of Market Monitoring October 2, 2009 The introduction of convergence

More information

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect Parameter Tuning for Uneconomic Adjustments Lorenzo Kristov, Principal Market Architect Stakeholder Meeting May 13, 2008 Topics for Discussion Objectives of Current Parameter Tuning Effort Parameter Tuning

More information

Overview of Three Pivotal Supplier Test

Overview of Three Pivotal Supplier Test Overview of Three Pivotal Supplier Test MMUAC December 4, 2015 Howard Haas TPS Background The three pivotal supplier test is a reasonable application of the Commission s delivered price test Tests for

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at any bus is made up of three components:

More information

ISO Course Outline. Market Transactions Class

ISO Course Outline. Market Transactions Class ISO Course Outline Purpose Market Transactions Class This two-day training class is intended to be one of the cornerstones of the market training program and is designed to review the market concepts and

More information

Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois

Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois 1 Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois Zhi Zhou*, Audun Botterud Computational Engineer Argonne National Laboratory

More information

Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition

Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition Chris Mensah-Bonsu, Ph.D., Principal Consulting Advisor GRIDCo Bernard Modey, Director, System Operations - GRIDCo

More information

Generator Contingency & RAS Modeling

Generator Contingency & RAS Modeling Generator Contingency & RAS Modeling Revised Straw Proposal March 22, 2017 Perry Servedio Sr. Market Design & Regulatory Policy Developer Agenda Time Topic Presenter 2:00-2:05 Introduction James Bishara

More information

Reserve Market. PJM State & Member Training Dept. PJM /06/2016

Reserve Market. PJM State & Member Training Dept. PJM /06/2016 Reserve Market PJM State & Member Training Dept. PJM 2016 Objectives Define Reserve products Explain the Reserve requirements Calculate Reserve offers PJM 2016 2 Reserves Reserves are additional generation

More information

Generator Contingency & RAS Modeling

Generator Contingency & RAS Modeling Generator Contingency & RAS Modeling Revised Issue Paper & Straw Proposal November 15, 2016 Perry Servedio Sr. Market Design & Regulatory Policy Developer Agenda Time Topic Presenter 9:00-9:05 Introduction

More information

Congestion Cost Metrics

Congestion Cost Metrics Congestion Cost Metrics DRAFT One of the features of a locational marginal price (LMP) based market is the ability to identify grid locations that are difficult to serve with economic generation due to

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) COMMENTS OF SOUTHWEST POWER POOL, INC.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) COMMENTS OF SOUTHWEST POWER POOL, INC. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Fast-Start Pricing in Markets Operated by Regional Transmission Organizations and Independent System Operators Docket No. RM17-3-000

More information

PJM M2M Market Flow Proposal. October 2014

PJM M2M Market Flow Proposal. October 2014 PJM M2M Market Flow Proposal October 2014 Table of Contents 1. Introduction... 1 2. M2M Market Flow... 1 3. Real-Time Balancing Congestion and M2M payments... 3 4. Firm Flow Entitlement Impact of Market

More information

Contingency Modeling Enhancements Issue Paper

Contingency Modeling Enhancements Issue Paper Contingency Modeling Enhancements Issue Paper March 11, 2013 California ISO Contingency Modeling Enhancements Issue Paper Table of Contents I. Executive Summary... 3 II. Plan for Stakeholder Engagement...

More information

Locational Marginal Pricing II: Unlocking the Mystery

Locational Marginal Pricing II: Unlocking the Mystery Locational Marginal Pricing II: Unlocking the Mystery Thomas D. Veselka Argonne National Laboratory Decision and Information Sciences Division Center for Energy, Environmental, and Economic Systems Analysis

More information

Business Requirements Specification

Business Requirements Specification Business s Specification Convergence Bidding on the Intertie Disclaimer All information contained in this draft Business s Specification (BRS) as provided by the California Independent System Operator

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

Updated Operating Parameter Definitions

Updated Operating Parameter Definitions Updated Operating Parameter Definitions Tom Hauske Senior Lead Engineer, Performance Compliance Market Implementation Committee February 10, 2016 Why are we discussing? A number of operating parameters

More information

Data Miner 2 11/20/ PJM 2017

Data Miner 2 11/20/ PJM 2017 Data Miner 2 11/20/2017 Data Miner 2 Data Miner 2 will become the central data repository and interface for PJM public data. Key Product Features - Unified / highly available interface for all PJM public

More information

EIM Winter Reliability notes and processes for EIM entities. Craig Williams Training and Readiness

EIM Winter Reliability notes and processes for EIM entities. Craig Williams Training and Readiness EIM Winter 2017 Reliability notes and processes for EIM entities Craig Williams Training and Readiness The information contained in these materials is provided for general information only and does not

More information

Bid cost recovery and variable energy resource settlement Straw proposal

Bid cost recovery and variable energy resource settlement Straw proposal Bid cost recovery and variable energy resource settlement Straw proposal April 9, 2015 Table of Contents 1. Background... 3 2. Schedule for policy stakeholder engagement... 3 3. Initiative scope... 3 4.

More information

Power System Economics and Market Modeling

Power System Economics and Market Modeling Power System Economics and Market Modeling 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com PowerWorld Simulator OPF and Locational Marginal

More information

Alternatives for Addressing the Interface Pricing Flaw

Alternatives for Addressing the Interface Pricing Flaw Alternatives for Addressing the Interface Pricing Flaw Presented to: Joint and Common Market Meeting David Patton President, Potomac Economics March 21, 2014 Introduction MISO and PJM s interface prices

More information

Market Monitoring Unit. State of the Market Summer 2017

Market Monitoring Unit. State of the Market Summer 2017 State of the ket 20 published ober 20, 20 TABLE OF CONTENTS List of figures... i 1. ket performance highlights... 1 2. Prices, mitigation, and market costs... 4 3. Demand, generation and unit commitment...

More information

The Virtues of A Virtual RTO

The Virtues of A Virtual RTO The Virtues of A Virtual RTO Jim Mayhew Mirant September 26, 2003 Harvard Electricity Policy Group 1 A Virtual RTO? An Organization That is a RTO in All but Name? Minimum Attributes? Regional Security

More information

MISO Hourly Scheduling Rules. PJM Interconnection - Generator Offer Flexibility Senior Task Force June 19, 2015

MISO Hourly Scheduling Rules. PJM Interconnection - Generator Offer Flexibility Senior Task Force June 19, 2015 MISO Hourly Scheduling Rules PJM Interconnection - Generator Offer Flexibility Senior Task Force June 19, 2015 Purpose Overview Discuss MISO hourly Generation Offer structure/capability Reference: Energy

More information

June 21, Southwest Power Pool, Inc., Docket No. ER Order No. 755 Compliance Filing

June 21, Southwest Power Pool, Inc., Docket No. ER Order No. 755 Compliance Filing June 21, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No. ER13- -000 Order No.

More information

Vacation Approval for SharePoint 2003 or SharePoint 2007 solution End User Guide

Vacation Approval for SharePoint 2003 or SharePoint 2007 solution End User Guide Vacation Approval for SharePoint 2003 or SharePoint 2007 solution End User Guide Solution Description For a department s employees to request vacation or other time off, with secure approval, tracking

More information

Demand Response and Scarcity Pricing

Demand Response and Scarcity Pricing Item #/ Check When Complete Demand and Scarcity Pricing Begin End Category Sub-Category Order 719 Summary Draft Status SPP Notes References Assignment 41 47 63 Demand Allow DR to provide ancillary services

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

PJM ExSchedule User Guide

PJM ExSchedule User Guide PJM ExSchedule User Guide Revision: 07 Effective Date: July 13, 2017 Prepared by Transmission Service Department PJM 2017 i Approval and Revision History PJM User Guide: ExSchedule Table of Contents Table

More information

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation MRTU Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation CRR Educational Class #2 CAISO Market Operations Why are LMPs important to the CRR Allocation & Settlement Process The CRR revenue

More information

SPP EIS Market Overview. Western Visitors

SPP EIS Market Overview. Western Visitors SPP EIS Market Overview Western Visitors SPP.org 1 June 9, 2010 Contents Market Concepts Energy Imbalance Defined Market Benefits Locational Imbalance Pricing Scheduling Native Load Scheduling Market Systems

More information

NYISO/PJM Market-to-Market Coordination

NYISO/PJM Market-to-Market Coordination NYISO/PJM Market-to-Market Coordination Joint Stakeholders Meeting July 21, 2011 / Rensselaer, NY Agenda Joint Operating Agreement (JOA) Overview Project Timeline & Progress Report Key Concepts Real-Time

More information

Order 831 Offer Validation for Demand Response: Enhancements to DR Hub and Markets Gateway

Order 831 Offer Validation for Demand Response: Enhancements to DR Hub and Markets Gateway Order 831 Offer Validation for Demand Response: Enhancements to DR Hub and Markets Gateway DRS September 22, 2017 Demand Response Offer Cap Validation Process Demand Response (Economic and Load Management):

More information

Innovative PI System Displays that Optimize Power Trading in US Markets. Copyr i g h t 2013 O S Is o f t, L L C.

Innovative PI System Displays that Optimize Power Trading in US Markets. Copyr i g h t 2013 O S Is o f t, L L C. Innovative PI System Displays that Optimize Power Trading in US Markets Presented by Jay Moore Agenda Introduction Products used by EDF Trading NA, LLC Business Challenge Solved This presentation will

More information

SPP EIS Market Training. Markets 301

SPP EIS Market Training. Markets 301 SPP EIS Market Training Markets 301 SPP.org 1 Revised 02/26/2010 Contents Market Concepts Energy Imbalance Defined Market Benefits Locational Imbalance Pricing Scheduling Native Load Scheduling Market

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

Demand Response. Overview. Recommendations

Demand Response. Overview. Recommendations Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power

More information

Market Simulation Presentation Spring 2014 Release

Market Simulation Presentation Spring 2014 Release Market Simulation Presentation Spring 2014 Release Christopher McIntosh Lead Market Simulation Coordinator Spring 2014 Release February 20 th, 2014 Agenda Spring 2014 Market Simulation Initiatives and

More information

Solutions for Power Generation

Solutions for Power Generation EM SG SOLutions Solutions for Power Generation Energy Management Smart Grid Solutions Solutions for Power Generation Overview Power Applications Generation Planning and Trading Summary Page 2 Solutions

More information

Interface specification for Columna Service Logistics - Track Services

Interface specification for Columna Service Logistics - Track Services Interface Specification POSLOGISTICS-10697 Interface specification for Columna Service Logistics - Track Services Version 1.12, reduced for tracking purposes Prepared for: Integrators SSE/10697/IFS/0002$Revision:

More information

Draft Final Proposal. Bid Cost Recovery Mitigation Measures

Draft Final Proposal. Bid Cost Recovery Mitigation Measures Draft Final Proposal April 6, 2012 Draft Final Proposal Table of Contents 1 Introduction and background... 3 2 Schedule... 3 3 Overview of the draft final proposal... 4 3.1 Modified day ahead metered energy

More information

LMP s and Congestion Relief

LMP s and Congestion Relief LMP s and Congestion Relief Lens, Crystal Ball, or Alice s Looking Glass? Jim Mitsche jmitsche@power-gem.com www.power-gem.com 1 Opinions, Based on What? Analysis of NY State Congestion Cost and Causes

More information

IMM Quarterly Report: Fall 2017

IMM Quarterly Report: Fall 2017 IMM Quarterly Report: Fall 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics December 5, 2017 Highlights and Findings: Fall 2017 The MISO markets performed competitively this fall,

More information

Interface Pricing Approach Whitepaper May 2015

Interface Pricing Approach Whitepaper May 2015 Interface Pricing Approach Whitepaper May 2015 This white paper represents MISO's current progress and assessment on the Interface Pricing issue. Additional analysis is underway and will be shared with

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Indirect Taxation and Tax Administration Value Added Tax VEG N O 067

EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Indirect Taxation and Tax Administration Value Added Tax VEG N O 067 EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Indirect Taxation and Tax Administration Value Added Tax VAT Expert Group 18 th meeting 5 February 2018 taxud.c.1(2018)588112 EN Brussels,

More information

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3

More information

FINAL REPORT PHASE IV MARKET TRIALS

FINAL REPORT PHASE IV MARKET TRIALS October 26, 1999 FINAL REPORT PHASE IV MARKET TRIALS Scott M. Harvey, William W. Hogan, Susan L. Pope, Andrew Hartshorn and Kurt Zala EXECUTIVE SUMMARY On behalf of the Member Systems of the New York Power

More information

Managing Flexibility in MISO Markets

Managing Flexibility in MISO Markets Managing Flexibility in MISO Markets Clean Energy Regulatory Forum November 9, 2012 Outline Impacts of Variable Generation on Ancillary Services Dispatchable Intermittent Resources Introduction to Proposed

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

Shortage Pricing Penalty Factors and the Offer Cap (Corrected September 9, 2015)

Shortage Pricing Penalty Factors and the Offer Cap (Corrected September 9, 2015) Shortage Pricing Penalty Factors and the Cap (Corrected September 9, 2015) Adam Keech Senior Director, Market Operations Market Implementation Committee September 9, 2015 Background Information Operating

More information

Maintaining good Seller performance on Amazon for successful Christmas sales

Maintaining good Seller performance on Amazon for successful Christmas sales Maintaining good Seller performance on Amazon for successful Christmas sales Why a good Seller performance matters Good customer experience: - Positive feedback - Loyalty - Positive word-of mouth (more

More information

Analysis of the 2019/2020 RPM Base Residual Auction

Analysis of the 2019/2020 RPM Base Residual Auction Analysis of the 2019/2020 RPM Base Residual Auction The Independent Market Monitor for PJM August 31, 2016 Monitoring Analytics 2016 www.monitoringanalytics.com Introduction This report, prepared by the

More information

PJM/MISO Day Ahead M2M Exchange BENEFIT ANALYSIS

PJM/MISO Day Ahead M2M Exchange BENEFIT ANALYSIS PJM/MISO Day Ahead M2M Exchange BENEFIT ANALYSIS Benefit Analysis Objectives Evaluate the benefit of exchanging MW utilization on M2M flowgates in DA markets between MISO and PJM, where benefits are realized

More information

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Last Revised: May 25, 26 Disclaimer: "MIDWEST ISO MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND, EXPRESS

More information

S o u t h w e s t P o w e r P o o l F r e q u e n t l y C o n s t r a i n e d A r e a s S t u d y

S o u t h w e s t P o w e r P o o l F r e q u e n t l y C o n s t r a i n e d A r e a s S t u d y S o u t h w e s t P o w e r P o o l F r e q u e n t l y C o n s t r a i n e d A r e a s - 2 0 1 4 S t u d y February 2015 John Hyatt, PhD Principal Market Monitor Market Monitoring & Analysis Southwest

More information

Dual Pricing Constraint

Dual Pricing Constraint Dual Pricing Constraint Dual Pricing Constraint Physical + Virtual Net CAISO intertie awards

More information

2750 Monroe Blvd Audubon, PA

2750 Monroe Blvd Audubon, PA 2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report

More information

Hourly values for at least the next 48 hours. Daily values for at least the next 31 calendar days.

Hourly values for at least the next 48 hours. Daily values for at least the next 31 calendar days. A. Introduction 1. Title: Available Transmission System Capability 2. Number: MOD-001-1a 3. Purpose: To ensure that calculations are performed by Transmission Service Providers to maintain awareness of

More information

BPM Change Management Meeting

BPM Change Management Meeting BPM Change Management Meeting September 26, 2017 Julia Payton BPM Change Management Process BPM_CM@caiso.com Agenda BPM Change Management Meeting, September 26, 2017 Topic Introduction/meeting overview

More information

Data Viewer, Member Voting, Account Manager, DR Hub, Power Meter, and Data Miner Roadmaps

Data Viewer, Member Voting, Account Manager, DR Hub, Power Meter, and Data Miner Roadmaps Data Viewer, Member Voting, Account Manager, DR Hub, Power Meter, and Data Miner Roadmaps As of March 20, 2018 www.pjm.com 2018 Roadmap Data Viewer, Voting, Account Manager, DR Hub and Power Meter, Data

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Congestion and Marginal Losses The locational marginal price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components: the system marginal price (SMP) or energy

More information

Release User Group Agenda 10:00 a.m. 10:55 a.m. (Pacific Time)

Release User Group Agenda 10:00 a.m. 10:55 a.m. (Pacific Time) Release User Group Agenda August 7, 2012 10:00 a.m. 10:55 a.m. (Pacific Time) Web Conference Information URL: https://www.connectmeeting.att.com Meeting Number: 8665282256 Access Code: 5251941 Conference

More information

Introduction to the Demand Response Auction. IESO Training

Introduction to the Demand Response Auction. IESO Training Introduction to the Demand Response Auction IESO Training May 2017 Introduction to the Demand Response Auction AN IESO TRAINING PUBLICATION This guide has been prepared to assist in the IESO training of

More information

Release User Group Agenda

Release User Group Agenda Release User Group Agenda November 29, 2011 10:00 a.m. 10:55 a.m. (Pacific Time) Web Conference Information URL: https://www.connectmeeting.att.com Meeting Number: 8665282256 Access Code: 5251941 Conference

More information