Extending the New Plant Design 3D Model Into an Operations and Maintenance Tool. Ken Barry Senior Project Manager
|
|
- Bruno Whitehead
- 6 years ago
- Views:
Transcription
1 Extending the New Plant Design 3D Model Into an Operations and Maintenance Tool Ken Barry Senior Project Manager
2 Objectives Extending the New Plant Design 3D Model Into an Operations and Maintenance Tool Ensuring that the necessary data is available Virtual plant configuration management Data Quality Assurance (QA) and Software Validation & Verification (V&V) 2
3 What is the Problem? Theorem 1 50% of the problems in the world result from people using the same words with different meanings Theorem 2 The other 50% of the problems result from people using different words with the same meaning Stan Kaplan, Risk Analysis, Vol 17,
4 What is the Solution? We need a common data language and standards that will be used by the nuclear plant sub-tier suppliers through the suppliers through the EPC and reactor vendors and finally through to the operator 4
5 Why? Pre-startup Information management throughout the asset lifecycle is a key means to increasing the return on assets in modern process plants. Better information management can benefit new plants by: Providing contractual definition of information deliverables for a planned plant Reducing costs by bringing a new plant up to full operating capacity faster Reducing the substantial costs of collating handover data against the installed asset base 5
6 Why? Post-startup And can also benefit existing plants by: Increasing plant productivity towards the inherent asset maximums Finding new efficiencies in maintenance and operations Streamlining the supply chain 6
7 Why? The Numbers The National Institute of Standards and Technology s (NIST) study, Cost Analysis of Inadequate Interoperability in the U.S. Capital Facilities Industry identified and quantified the efficiency losses in the U.S. capital facilities industry attributable to inadequate interoperability. The researchers very conservatively estimated those U.S. losses to be $15.8 billion in
8 What is Configuration Management (CM)? EDB Engineering Design Basis per 10CFR50.2 What needs to be there Conform Conform Physical Plant What is actually there PP Conform PD Plant Documentation What we say is there Work Processes must assure that: Elements conform all the time All changes are authorized Conformance is auditable 8
9 Issues with the old way Existing plant CM is based upon paper (P&IDs) does not take advantage of computer technology and can be at odds with existing technology SSC Data from suppliers has to be captured with human intervention Adoption of formal change management processes demands a great deal of linkage between manual processes and separate databases Existing change management is reliant upon tribal knowledge 9
10 How is the CM process impacted by use of 3-D Model Software Suite? Current Generation Nuclear Plants Physical Plant Plant Documentation Must Conform As-built information must be accurately reflected on plant documentation. Next Generation Nuclear Plants Physical Plant Must Conform 3-D Model Software Suite Must Conform Plant Documentation As-built information must be accurately entered into the 3-D Model Software Suite which then produces plant documentation. 10
11 What is a 3D Model? A 3-dimensional engineering tool for designing a plant 11
12 The configuration data is much more than a 3-D Model Sample Valve Attributes Tag number System Room number Data Sheet Assignment Body type Actuator type Pressure rating Material type Safety Class Size Actuator fail position Locking requirements Actuator electrical safety class Number and type of position indicators I&C system(s) that monitors valve position I&C system(s) that control valve position 12
13 Equipment Life Cycle Work Process Phase I: Equipment Data Development Phase II: Budget Estimate Phase III: Equipment Specs & RFQ Phase IV: Purchase Order / Vendor Drawings & Models Phase V: Fabricate /Deliver/Install Owner Operator Application Exchanges EPC Supplier / Distributor Conceptual Conceptual Design Design PerformanceReq Preliminary Preliminary Design Design BudgetRFQ Design Design Review Review Budget Budget Quote Quote Authorize Authorize Project Project Budget Estimate Authorization Authorization Estimate Estimate BudgetQuote Application Exchanges ProjectAuth Production Production Design Design BidRFQ BidDesign Bid Bid Package Package Design Review Design Review Bid Quote Bid Quote Phase Phase VI: VI: Operations Operations and and Maintenance Maintenance access access engineering engineering information information BidQuote Bid Bid Approval Approval BidReview Fab Fab Approval Approval Fab Fab Bid Eval & Review Review & Bid Eval & & Award Approval Award Approval Tagged List FabAuth Purchase Order Receive Receive PO PO POSpec Approval Approval Drawings Drawings FabDwg FabReview Fabricate Fabricate Ship Ship Invoice Invoice transaction As Installed Pay Pay PayRequest Receipt, Receipt, Inspection, Inspection, Installation Installation & & Commission Commission Care, Install + Spares AsShipped VendorDocs = AEX usage scenarios 13
14 Nuclear Information Handover 14
15 Business Strategy NEI / INPO Performance Model EPRI Programs Documents Data Flow INPO Programs Documents Data Flow DATA GOALS Timely Accurate Consistent Retrievability Re-usable Single Source STANDARDS - GOALS Open Standards Open Formats Open Architecture Primary Information/Data Categories 15
16 What Pieces Do We Have Now? IT tool availability is not the issue 16
17 What Pieces are Missing? An accepted and tested standard that defines: Use of reference data defining standard terms with precise meanings Accurate expression of relationships between data Retention and query of the full lifecycle history of the data Exchange of structured data in a standard format with a standard protocol Automatic collation from multiple external sources on demand Freedom from the need to identify, map and transform between applications 17
18 What is EPRI s Role? Provide and assemble the industry expertise to establish data interoperability standards for nuclear plant lifecycle management Provide the driving force to establish the nuclear industry standards Work with other organization (i.e. Fiatech) to capture and adapt existing expertise and standards Monitor adoption and provide support as needed 18
19 What are the Next Steps? Establish nuclear XML Schemas for critical components (Fiatech AEX) Harmonization of EPRI Initiative Actions/Results with ISO is Essential to the Effective Utilization of ISO for Achieving New Nuclear Virtual Power Plant Configuration Management in support of New Nuclear Power Plant Life Cycle Design, Operations, Maintenance and Engineering Quality Assurance Program for 2D and 3D Design and Modeling Software and V&V for Quality Software Develop XML Templates for Configuration Management Business Rules. 19
20 The Journey to Data Interoperability Join Us! 20
SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018
SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 1.0 SCOPE This document establishes the quality program requirements for an organization providing engineering
More informationSmartPlant Enterprise for Owner Operators. Leveraging the Engineering Design Basis Across the Plant Life Cycle
Enterprise for Owner Operators Leveraging the Engineering Design Basis Across the Plant Life Cycle Business Case Owner operators currently face unprecedented demands to: Deliver multiple new plants and
More informationSolutions for Nuclear Generation New Build and Refurbishment related to Supply Chain and Procurement. September 2014
Solutions for Nuclear Generation New Build and Refurbishment related to Supply Chain and Procurement September 2014 Ventyx, an ABB Company The world s most complete industrial enterprise software and solution
More informationfor Owner Operators Leveraging the engineering Design SmartPlant Leveraging the Engineering Design Basis Across the Plant Life Cycle
Enterprise FOR owner Operators Leveraging the engineering Design Basis Across the Plant Life Cycle Enterprise for Owner Operators Leveraging the Engineering Design Basis Across the Plant Life Cycle 2 BUSINESS
More informationAutomating the Facility Supply Chain
Texas Industries of the Future #1 2003-03-18 Automating the Facility Supply Chain Charles Wood, FIATECH Tom Teague, eplantdata Texas Technology Showcase March 18, 2003 Texas Industries of the Future #2
More informationDAVID J. HOLLER DETAILED EXPERIENCE
DAVID J. HOLLER EXPERIENCE SUMMARY QA Professional and Technical Specialist with 33 years of nuclear power-related experience. Experience and capabilities include quality program assessment, management
More information"NPP Design Basis Handover and Knowledge Preservation from Subcontractors, Vendors and EPC"
"NPP Design Basis Handover and Knowledge Preservation from Subcontractors, Vendors and EPC" Interregional Knowledge Management Workshop on Life Cycle Management of Design Basis Information Issues, Challenges,
More informationDesign Knowledge Management for the Power Industry. Opportunities, Challenges and Lessons Learnt
Design Knowledge Management for the Power Industry. Opportunities, Challenges and Lessons Learnt Kevin Gribbin November 2014. Topics Intergraph - Who we are - What we do DKM and CMIS Current State Integration
More informationEngineering Data Lifecycle Management 18/08/2011
Lifecycle 18/08/2011 Handover Overview What is Lifecycle? The Handover Dilemma The Case for Smarter Handover Smarter Attributes Best Practice From Other Industries Lifecycle Processes by MCP Phase EPCs
More informationEngineering & Schematics
SmartPlant Enterprise Engineering & Schematics 2 Industry Challenges Engineering, Procurement, and Construction Companies (EPCs) During engineering, there is increasing pressure on margins and intense
More informationSPI Interfaces & Integration
SPI Interfaces & Integration the future is not what it used to be John Dressel SmartPlant Instrumentation Application Specialist Sunday, June 5. 2011 Orlando Fl. The Beginning In the beginning there was
More informationCapturing Equipment Data Requirements Using ISO & Assessing Conformance (EDRC) and OGI Pilot
Capturing Equipment Data Requirements Using ISO 15926 & Assessing Conformance (EDRC) and OGI Pilot Manoj Dharwadkar, Bentley Systems; Alan Johnston, MIMOSA; Mark Palmer, NIST EDRC and OGI Pilot Outline
More informationEPRI QUALITY PROGRAM MANUAL
Controlled Copy No. : If no Controlled Copy No. is assigned; this copy is uncontrolled EPRI QUALITY PROGRAM MANUAL REVISION 13 Effective TOC: TABLE OF CONTENTS Sec. Title Page SUMMARY OF CHANGES... 2 Mapping
More informationSoftware Global Customer Conference
Intergraph Process, Power & Marine Smart Engineering from Concept to Operations Software Global Customer Conference Presenter: Paras Trivedi - Frank Joop Product Owner SPP&ID/SPPE Executive Director Global
More informationQuality Management Manual Revision 19
Quality Management Manual Revision 19 959 Concord Street Framingham, MA 01701 508-875-2121 www.epm-inc.com with offices in Knoxville, TN and Raleigh, NC Rev. 19 PROPRIETARY INFORMATION NOTICE Page ii
More informationSMARTPLANT ENTERPRISE
SOLUTION SMARTPLANT ENTERPRISE Engineering & Schematics Industry Challenges ENGINEERING, PROCUREMENT, AND CONSTRUCTION COMPANIES (EPCs) Projects are growing more complex. They are larger, workshared with
More informationSargent & Lundy LLC April 8, 2014
Farid M. Berry Vice President & Project Director Sargent & Lundy LLC April 8, 2014 Role of the OWNER S ENGINEER Technical Meeting on Becoming a Knowledgeable Customer Obninsk and Novovoronezh, Russian
More informationINS QA Programme Requirements
Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued
More informationTrade and Logistics II in Microsoft Dynamics AX 2009 Course 80025A: 3 Days; Instructor-Led
Trade and Logistics II in Microsoft Dynamics AX 2009 Course 80025A: 3 Days; Instructor-Led About this Course The two-day Microsoft Dynamics AX 2009 Trade & Logistics II, course introduces advanced Trade
More informationDefinitions contained in the above mentioned document and industry regulations are applicable herein.
Quality Specification TEC-1021 21May12 Rev E Global Quality Management System Supplement for Various International Nuclear Quality Assurance Criteria, Regulations, and Requirements 1. SCOPE 1.1. Content
More informationThe Role of ISO in Strategic Asset Lifecycle Information Management
The Role of ISO 15926 in Strategic Asset Lifecycle Information Management Summary Utilizing IS0 15926 enables organizations to meet their asset information requirements while reducing the costs associated
More informationSmartPlant 3D Materials Handling. Taylor D. Cole Vice President, Intergraph Global Metals & Mining Industry
SmartPlant 3D Materials Handling Taylor D. Cole Vice President, Intergraph Global Metals & Mining Industry Global Outlook - Commodities Global Seaborne Iron Ore Global Copper 1136 844 2 X 2 X 1421 1624
More informationAccepting Supplier ISO 9000 Quality Programs
Accepting Supplier ISO 9000 Quality Programs IEEE Subcommittee on Qualification October 7-8, 2004 Leigh A. Aparicio PSE Technical Leader aparicio@epri.com Project Overview ISO 9000 Phase I Initiated in
More informationProduct Realization. Ameritube LLC 1000 N. Hwy 77, Hillsboro TX Revision Level: Procedure No. A
5/8/2012 Page No. 1 of 32 Date Description Of Change Signature Rev. Level 5/8/2012 New Document Jeremy Wilson Procedure pproval: Company Title: Date: Quality Manager 5/8/2012 5/8/2012 Page No. 2 of 32
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS
More informationQuality Assurance Policy and Procedures
650 Montana Ave, Suite A Las Cruces, NM 88001 (575) 522-0430 www.rmgovernmentservices.com Quality Assurance Policy and Procedures PURPOSE. The purpose of this policy is to outline the quality assurance
More informationIAEA Procurement Engineering and Supply Chain Activities John Moore Division of Nuclear Power
IAEA Procurement Engineering and Supply Chain Activities John Moore Division of Nuclear Power j.h.moore@iaea.org Vienna, September 8-10, 2014 (Technical Meeting TM-47114) Topics IAEA documents related
More informationDOE Graded Approach. IAEA January 23-27, 2012 Meeting
DOE Graded Approach IAEA January 23-27, 2012 Meeting Duli C. Agarwal (301) 903-3919 Office of Quality Assurance (HS-33) Office of Nuclear Safety U.S. Department of Energy Driver of Graded Approach 10 C.F.R.
More informationSource to consumer. Using GS1 standards in retail
Source to consumer Using GS1 standards in retail GS1 makes it possible for apparel and general merchandise companies to follow their products from the source to the consumer ensuring that the right product
More informationCompany Overview. Safety Quality Reliable Service
Company Overview Safety Quality Reliable Service Our Company MRC Global is the largest, global distributor of pipe, valve and fitting (PVF) products and services to the energy and industrial markets. Our
More informationPage 1 / 11. Version 0 June 2014
Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning
More informationBusiness Case Our Challenge. Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects
Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects Business Case Our Challenge How to move from the current position of; Intelligent schematics (P&ID s)
More informationDocument Number: QSP-06-01
Page 1 of 1 Introduction to the Fluke Biomedical Supplier Handbook Dear Fluke Supplier, The Fluke Biomedical Supplier Handbook was written for you to better understand Fluke and Fluke s engagement with
More informationeschoolmall.com uses the Internet to make it easier to
eschoolmall.com uses the Internet to make it easier to do business with schools. Imagine error-free purchase orders... faster payment through Electronic Funds Transfer (EFT)... turning inventory faster...
More informationOsprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -
February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February
More informationIndustry 4.0 What does it Mean for CAPIEL Manufacturers?
Industry 4.0 What does it Mean for CAPIEL Manufacturers? 1 INTRODUCTION Manufacturing industry has entered in a new phase of changes, which foresee digital technologies to be integrated within the heart
More informationImplementing Compliant Medical Device Best Practice Business Processes Using Oracle E-Business Suite
Implementing Compliant Medical Device Best Practice Business Processes Using Oracle E-Business Suite A white paper discussing the compliant use of the Oracle Electronic Record, Electronic Signature (E-Records)
More informationBentley Distributed Enterprises
Bentley Distributed Enterprises Bentley s Mission Users of our software design, build, map, and operate the world s infrastructure. Our mission is to help them do it better and faster. A Strong Global
More informationQUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES
Your Company Name QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 QMS Policies and Procedures Latest Revision Date Abstract:
More informationV&V Best Practices. CASSS, CMC Strategy Forum Steven W. Badelt, PhD Managing Partner Suttons Creek, Inc. SUTTONSCREEK.COM
V&V Best Practices CASSS, CMC Strategy Forum Steven W. Badelt, PhD Managing Partner Suttons Creek, Inc. Solving the problem of Complexity. 21CFR820.30 & FDA Guidance INCOSE System Engineering Handbook
More informationVendor Quality. Requirements Manual
ate Released 05/07/10 Last Review ate 03/14/16 Page 1 of 7 Vendor Quality Requirements Manual Nasco Aircraft Brake, Inc. 13300 Estrella Ave. Gardena California 90248 Telephone No. 310-532-4430 Fax. No.
More informationQUALITY CLAUSE CODES
14201 Myerlake Circle 5307 Luce Avenue, Bldg 243E Clearwater, FL 33760 McClellan, CA 95652 P (727) 539-8585 F (727) 539-0316 THESE ARE IN ADDITION TO THOSE SET FORTH IN ANY DOCUMENT THAT IS PART OF THE
More informationTRIOLE - IT industrialization is here, and it works -
TRIOLE - IT industrialization is here, and it works - May, 2006 Fujitsu Limited What Business Needs Efficiency Continuity Agility Industrialized IT Infrastructure Consistency of manufactured goods Standardized
More informationISO 9001:2008 and AS9100 Rev. C. Supplier Quality Manual
ISO 9001:2008 and AS9100 Rev. C Supplier Quality Manual ffective Date: Section I Supplier (same as xternal Provider) xpectations 1.0 Introduction 2 of 7 This Supplier Quality Manual (SQM) has been created
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL QD-SUPPLIER-QUALITYMANUAL 1 of 13 02.20.15 TABLE OF CONTENTS Page A. Goal 3 B. Purpose 3 C. Approach 3 D. Applicability 3 E. Implementation 3 F. Zero Defects Policy 3 Section 1:
More informationSEMS and Supplier Management- An Operator s Perspective
SEMS and Supplier Management- An Operator s Perspective Petroleum Equipment Suppliers Association Legal Seminar Mar 26, 2013 Karl Van Scyoc Anadarko Petroleum Corporation Supplier? Organization or individual
More informationProject Management Information System
Project Management Information System a UNIFIER TM deployment The Project Controls Group Mission Analyze the organization structure and information needs and configure UNIFIER TM to suit that organization
More informationEnsuring Process Safety & Asset Integrity Leveraging Plant Asset Information
Ensuring Process Safety & Asset Integrity Leveraging Plant Asset Information Adrian Park Vice President, SmartPlant Enterprise Solutions, Intergraph Process, Power & Marine Progressive Safety and Asset
More informationSmartPlant Materials Handling
SmartPlant Materials Handling Intergraph Australia 2008 15-19 September 2008 Global Outlook - Commodities Iron Ore Aluminium & Alumina Metallurgical Nickel Coal Thermal Coal Copper Source: Deutsche Bank,Research,
More informationASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1
ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 Karte: Wikipedia CIS GmbH Experts in ASME Code Consulting CIS GmbH Consulting Inspection Services 3 rd Party Inspection Training
More informationŁańcuch dostaw i procedury zapewnienia jakości w realizacji elektrowni jądrowej budowanej w oparciu o technologię amerykańską.
Łańcuch dostaw i procedury zapewnienia jakości w realizacji elektrowni jądrowej budowanej w oparciu o technologię amerykańską. Supply chain and quality assurance procedures in execution of nuclear power
More informationIntegrated Product Development for Process and Discrete Industries: an Overview and Outlook. Product Management PLM October 2011
Integrated Product Development for Process and Discrete Industries: an Overview and Outlook Product PLM October 2011 Legal Disclaimer The information in this presentation is confidential and proprietary
More informationAudit Report. Audit of Contracting and Procurement Activities
Audit Report August 2012 Recommended for Approval to the Deputy Minister by the Departmental Audit Committee on October 12, 2012 Approved by the Deputy Minister on October 18, 2012 Table of Contents Table
More informationFrom Integrated Engineering to Integrated Operations...
Comos - Changing the way you manage your assets From Integrated Engineering to Integrated Operations... Geoff Turner A Siemens Business It s all about risk... Supporting business strategies for Engineering
More informationPAYIQ METHODOLOGY RELEASE INTRODUCTION TO QA & SOFTWARE TESTING GUIDE. iq Payments Oy
PAYIQ METHODOLOGY RELEASE 1.0.0.0 INTRODUCTION TO QA & SOFTWARE TESTING GUIDE D O C U M E N T A T I O N L I C E N S E This documentation, as well as the software described in it, is furnished under license
More informationExperience at Hinkley Point C: building Information Modelling (bim) and Enterprise Lifecycle Management Solutions Presented By: Sue Hewish & Jason
Experience at Hinkley Point C: building Information Modelling (bim) and Enterprise Lifecycle Management Solutions Presented By: Sue Hewish & Jason Walker Agenda: Introductions Section 1: Introduction to
More informationSHELTON INDUSTRIAL PATTERN INC.
Defintions: Seller : Supplier of materials, parts and or services that support production Supplies : materials, parts that support production FOD : Foreign Object Debri / Damage 1. Quality Management System
More informationEPRI Update. Marc H. Tannenbaum Technical Leader, EPRI. RAPID Clearwater Beach, Florida May16, 2016
EPRI Update Marc H Tannenbaum Technical Leader, EPRI RAPID Clearwater Beach, Florida May16, 2016 Critical Spares Project is building on 1019162 Some sites have implemented critical spares programs A few
More informationQUALITY ADMINISTRATIVE PROCEDURE
NYE COUNTY NUCLEAR WASTE REPOSITORY PROJECT OFFICE QUALITY ADMINISTRATIVE PROCEDURE TITLE: Procurement of Items and Services REVISION: 1 DATE: PAGE: 1 of 8 PROCEDURE NUMBER: QAP-7.1 SUPERSEDES: Revision
More informationTITLE: Quality Assurance Sub-Contract Quality Clauses DATE: 12/4/2017 OWNER: Operations Manager
Scope: This process outlines the Exotic Tool Welding (ETW) quality control terms and conditions levied to suppliers providing product or service for ETW. The QA codes identified on the purchase order correlate
More information0. 0 TABLE OF CONTENTS
QUALITY MANUAL Conforming to ISO 9001:2008 0. 0 TABLE OF CONTENTS Section Description ISO 9001 Clause Page 0 TABLE OF CONTENTS n/a 2 1 PIMA VALVE, INC. DESCRIPTION n/a 3 2 QUALITY MANUAL DESCRIPTION 4.2.2
More informationManagement System Requirements
Management System Requirements Identification, Recognition, Application IAEA Technical Meeting Grading of the Application of Management System Requirements Vienna, 23 27 January 2012 RWE Technology GmbH
More informationBechtel PCA Instrument SIG Workshop 2010
Bechtel PCA Instrument SIG Workshop 2010 Robin Benjamins Bechtel Central Engineering & Technology 1 Bechtel s Information Landscape Legend Cost Data Quantity Data Owner Operator Suppliers Corporate Systems
More informationUnlocking the value of Engineering Information in Facilities Engineering Operations based on ISO 55000
Unlocking the value of Engineering Information in Facilities Engineering Operations based on ISO 55000 Sloane Whiteley, Senior Consultant AVEVA Enterprise Solutions Lessons Learned from the Past Incident
More informationAriba Network Enabling Business Commerce in a Digital Economy
SAP Brief SAP Ariba s Ariba Network Ariba Network Enabling Business Commerce in a Digital Economy SAP Brief Automate commerce to connect In a digital economy, moving from paper to electronic processing
More informationQuality Management System Plan
Quality Management System Plan Rev. 2 February, 2004 Shaw Environmental & Infrastructure, Inc. 4171 Essen Lane Baton Rouge, LA 70809 Page iii Rev. 2 Table of Contents PAGE Approvals Quality Policy &
More informationASME NQA-1 Certification. Matthew Vazquez September 4, 2017
ASME NQA-1 Certification Matthew Vazquez September 4, 2017 NQA-1 Certification The ASME NQA-1 Certification Program seeks to meet the needs of the nuclear industry by expanding the supply chain with organizations
More informationMaterial available on web at
Material available on web at http://gtumcain.wordpress.com Major topics Modules of ERP Human Resources Management Financial Management Inventory Management Quality Management Sales and Distribution (Murlidhar
More informationQT9 ERP Job Management Software. Compliance. Paperless. User Friendly. Powerful.
Compliance. Paperless. User Friendly. Powerful. SOFTWARE FEATURES Email Alerting Configure email alerts for inventory level of both your raw materials and your finished goods Outlook Integration Create
More informationAuditing Association of Canada Onshore Pipeline Regulations Management Systems and Audits
Auditing Association of Canada Onshore Pipeline Regulations Management Systems and Audits Ken Colosimo Technical Leader Audits Operations National Energy Board Presentation Overview NEB - Who We Are &
More informationASA-100 QUALITY MANUAL
Your Company Name ASA-100 QUALITY MANUAL Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 Quality Manual Latest Revision Date Abstract: This quality manual describes (your Company's)
More informationRFID for Manufacturing: Critical Success Factors.
RFID for Manufacturing: 7 Critical Success Factors. Transforming RFID Data into Value RFID for Manufacturing: 7 Critical Success Factors. Innovative manufacturers are leveraging the real-time visibility
More informationLenovo Services for the Data Center
Lenovo Services for the Data Center September 28, 2016 Mission Our mission is to be your trusted partner in the data center. #1 Thousands of customers trust Lenovo Services to run their businesses and
More informationHM Dunn AeroSystems Purchase Order Quality Clauses
HM Dunn AeroSystems Purchase Order Quality Clauses applies to all divisions of HM Dunn AeroSystems, which include Apex Engineering International (AEI) and HM Dunn Companies. Approved Processing Sources
More informationSiemens PLM Software. SIMATIC IT Unilab. Your next generation LIMS. siemens.com/lims
Siemens PLM Software SIMATIC IT Unilab Your next generation LIMS siemens.com/lims 2 Laboratories are under enormous pressure to do an ever-increasing amount of work with fewer employees and at lower cost.
More informationCURTISS WRIGHT Actuation Systems 201 Old Boiling Springs Rd Shelby, NC SUPPLIER QUALITY REQUIREMENTS SQR-100. Rev. L.
CURTISS WRIGHT Actuation Systems 201 Old Boiling Springs Rd Shelby, NC 28152-8008 SUPPLIER QUALITY REQUIREMENTS SQR-100 Rev. L Approved by: PREFACE This document is to be used to define the quality requirements
More informationA Strategic Guide to Visibility & Cost Reduction
A Strategic Guide to Visibility & Cost Reduction Table of Contents I. Executive Summary... 2 II. Auditing... 3 III. Complexity Reduction... 4 IV. Network Design... 4 V. Outsourcing... 5 VI. Operations
More informationOracle Sourcing. Cut Costs with Online Collaboration and Negotiation
Oracle Sourcing Oracle Sourcing and Oracle Sourcing Optimization are the enterprise applications that improve the effectiveness and efficiency of strategic sourcing. They are key components of Oracle Advanced
More informationQUALITY DEPT request to have FORM 1135 for REVIEW/APPROVAL Cycle everytime form will be updated/revised.
REF ONLY-DATA MANAGEMENT: 1 ST (2) PAGES IS NOT PART OF FORM 1135. QUALITY DEPT request to have FORM 1135 for REVIEW/APPROVAL Cycle everytime form will be updated/revised. FORM 1135 QUALITY ASSURANCE CLAUSES
More informationEnabling Asset Integrity Management for the Oil & Gas Industry
Enabling Asset Integrity Management for the Oil & Gas Industry THE CHALLENGE Ensuring operational integrity of critical assets and installations is of paramount importance to oil field operators and the
More informationPA Group USA. Master Complexity with Apparel and Textile for Microsoft Dynamics AX Microsoft Dynamics AX. White Paper
PA Group USA Microsoft Dynamics AX Master Complexity with Apparel and Textile for Microsoft Dynamics AX 2012 White Paper This paper discusses how the makers and distributors of apparel and textiles can
More informationSUPPLIER QUALITY SYSTEM SURVEY
SUPPLIER QUALITY SYSTEM SURVEY DATE (M/d/yy): 55 Dragon Court Woburn, MA 01801 Tel: (781) 933-7300 Fax: (781) 935-4529 GENERAL INFORMATION Supplier Name: Physical Address: City: State: Zip: Sr. Company
More informationD.P.E.LTD QUALITY CONTROL PROCEDURE NO 9 QUALITY CONTROL REQUIREMENTS FOR SUPPLIERS MASTER COPY
Page 1 of 8 D.P.E.LTD QUALITY CONTROL PROCEDURE NO 9 QUALITY CONTROL REQUIREMENTS FOR SUPPLIERS MASTER COPY REF: DPE/Q.C.P.9 Dated: 19/10/2010 Approved By: P Knight Title: Quality Manager Signed: Page
More information4. RELATED DOCUMENTS AND FORMS 4.1. AS ISO Cambridge Valley Machining, Inc. QMS procedures, including, but not limited to:
Approved By: Purchasing Manager Candice Lane (signature on file) Date: 5/26/17 Approved By: Process Owner James D. Moore (signature on file) Date: 5/26/17 1. PURPOSE 1.1. To define Cambridge Valley Machining,
More informationFixed Scope Offering for Oracle Fusion Procurement. Slide 1
Fixed Scope Offering for Oracle Fusion Procurement Slide 1 Today s Business Challenges Adopt leading Global SCM practices & strategies across the entire enterprise value chain to move into the future.
More informationORACLE UPK PRE-BUILT CONTENT FOR: E-BUSINESS SUITE R12.1
ORACLE UPK PRE-BUILT CONTENT FOR: E-BUSINESS SUITE R12.1 Oracle s User Productivity Kit (UPK) is a collaborative content development platform that drives end-user and project team productivity throughout
More informationCDM Note 002: Principal Designer Appointment
Introduction The part of Network Rail discharging the Client duties, will have to take a key decision when and who to appoint as the Principal Designer, for a change to the infrastructure. This note provides
More informationThis part of the Works Information sets out the obligations of the Contractor with regards to:
Works Information Volume 2B Part 13 Assurance, Records and Certification Part 13 Assurance, Records and Certification 13.1 Introduction The Contractor self-certifies the quality of the works. This part
More informationQuality Assurance Manual
Quality Assurance Manual Current Electrical is committed to leading the market in satisfying customer needs by providing versatile and innovative electrical and control solutions We take pride in the ability
More informationWorking Party DEXPI ISO of ProcessNet* Section Process, Apparatus and Plant Technology. DEXPI - Data EXchange Process Industry
Working Party DEXPI ISO 15926 of ProcessNet* Section Process, Apparatus and Plant Technology DEXPI - Data EXchange Process Industry * ProcessNet an Initiative of DECHEMA and VDI-GVC Working party DEXPI
More informationJoerg Wiederspohn, Senior Development Architect, Financial Services, SAP AG Karin Fischenbeck (BIAN)
BIAN Business Partner / Party Adoption of BIAN Thinking and Deliverables as part of the SAP for Banking Solution Portfolio in the Business Partner Domain Joerg Wiederspohn, Senior Development Architect,
More informationMICROSOFT DYNAMICS GP. Product Capabilities and Business Ready Licensing Module Guide. Solutions
MICROSOFT DYNAMICS GP Product Capabilities and Business Ready Licensing Module Guide Solutions Become a Dynamic Business with Microsoft Dynamics GP For more than 25 years, Microsoft Dynamics GP has delivered
More informationINTEGRATING ISO 9000 METHODOLOGIES WITH PROJECT QUALITY MANAGEMENT
INTEGRATING ISO 9000 METHODOLOGIES WITH PROJECT QUALITY MANAGEMENT M a r ch 2015 OBJECTIVE ISO and Project Quality Management Process Are they different or the same? ISO 9000 QMS FAMILY ISO 9000:2005 Vocabulary
More informationBusiness Requirements Definitions
Business Requirements s Department of Financial Services Date: 01/19/2017 Revision: Version 2.0 Table of Contents Overview... 3 Priority Field Values s... 4 Functional Requirements Categories... 5 Accounts
More informationNIRMA Glossary of Terms and Definitions NIRMA Technical Guidelines
NIRMA Glossary of Terms and Definitions NIRMA Technical Guidelines Both the 1998 and 2011 (R2013) editions are available for TG 11, 15, 16, and 21. The 1998 editions of these four TGs form the basis for
More informationSUPPLIER QUALITY CODES
Supplier Quality s D07-00125 Rev A APPROVALS NAME AND TITLE SIGNATURE DATE M.G. Blankenship Senior Director, Operations I. Jimenez Materials Manager D07-00125-02 Page 1 of 5 SQC 1 SQC 2 SQC 3 SQC 4 SQC
More informationWORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B
1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework
More informationComos Industry Solutions
Comos Industry Solutions Delivering Customer Value from Integrated Engineering to Integrated Operations SPACe 2012 Siemens Process Automation Conference Comos Industry Solutions Organization Excellence
More informationRisk assessment checklist - Purchasing cycle
Check Yes or No or N/A (where not applicable). Where a No is indicated, some action may be required to rectify the situation. Cross-references (e.g., See FN 1.01) point to the relevant policy in the First
More informationNRC INSPECTION MANUAL INSPECTION PROCEDURE 35065
NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications
More information