1 Government Procurement: challenges and need for new approach Sheffield Hallam FM Conference Deborah Rowland, Government Property Unit Paddy Howlin, Government Procurement Service 12 th September 2012 UNCLASSIFIED 13/09/2012

2 Introductions Deborah Rowland Head of Facilities Management Category Government Property Unit Provide overview of FM procurement challenge and proposed way forward Paddy Howlin Head of Sourcing and Category Management Property Government Procurement Service Provide overview LEAN Sourcing Supporting procurement reform in Central Government

3 FM Procurement Issue Central Government Departments (CGD s) and their Arm Length Bodies (ALB s) currently procure Facilities Management (FM) contracts in isolation, with no standardisation of terms, key performance indicators (KPIs) or pricing, which limits government s ability to act as an intelligent customer and which suppliers exploit to their advantage. GPU and GPS are proposing a central Contracting Model for FM, with broad departmental and market support to address these shortcomings, maximise savings from FM and fully supports the SME agenda. GPU has already identified contracts totalling 502m per annum that could be re-procured through the FM Contract Model by 2020 with estimated annual savings of 158 million. The proposed model could also have wider applicability to the public sector.

4 Background Statistics on FM Second highest spend category - c 1.9bn* reflects assumed 30% element of unitary charge as FM cost (includes MOD and PFIs, excludes NHS) No transparency of actual costs for FM services within PFIs Limited transparency of FM spend and contract data Over 5,000* identified FM contracts procured, delivered and managed in silos by CGD s, ALB s and NDPBs. No consistency of service standards, KPI s, commercial terms, pricing, procurement Cost of procurement/management by each CGD s and ALB s and heavy reliance on consultancy At least 1,877* FTEs within CGD FM (operational delivery & contract management) at a cost of 56m* Skills and capability in contract management is variable Technical skills/knowledge are not shared or lessons learned disseminated FM spend and contract data inconsistent Lack of transparency by building and service type which leads to an inability to benchmark per m2 by service and location Inability to extract data from existing systems within each departmental FM contract CGD s paying consultants separately to benchmark their FM costs Gaps and inconsistency in FM data supplied from ALB s * Note all figures FY10/11 annual FM data return from CGDs/ALB s

5 Central Contracting Model GPU FM recommends the procurement of a central contracting model which could meet all of the challenges outlined above. The intention is to outsource to a central contracting team to manage all FM contracts with suppliers on behalf of government departments and their ALBs. The model will take over the provision of services from existing FM contracts on their expiry and will provide the following benefits: Savings achieved from; contracts negotiated to consistent standards, economies of scale and robust monitoring of FM costs. Significantly reduced FTE requirement to fulfil FM functions allowing staff to be deployed more efficiently. Increased data transparency due to central management of contracts to allow genuine comparison and further scope for savings. Inclusivity for SME s (able to bid at first tier through FM Supplier portal) encouraging growth in the FM sector. FM costs are currently expected to reduce in line with the national average reduction in occupied area as governed by National Property Controls (NPCs). Opportunity analysis predicts that this model provides savings of 15% over and above the savings trend (Appendix A).

6 Data Data Data Data Data DEPARTMENTS Business Demand Quality Control Compliance DEMAND Departments Wider Public Sector STRATEGIC Strategy/Direction Policy Property Alignment Innovation Reporting/analysis Market Trends TACTICAL Contract Management Procurement Supplier Evaluation MI/Data Performance Consistency/ Standards Audit Analysis CR Commercial Relationships GPU Strategy & Policy (Category Lead) FM Board Intelligent Client GPS Lead Procurement activity(s), Contracting Authority, Develop/Deliver/ Implement/Management of FM Supplier Framework Portal*, Spot Buying capability and support Performance & Data Management (Integrator) (Outsourced Contract/Lead Dept/GPS) Performance Management, MI, Supply Management, Audit, Standards, Technical Expertise, Sourcing Intelligence, FM Data Warehouse, Self- Service Helpdesk (CAFM), Mobilisation/Implementation, Framework Procurement & Supplier Portal (optional) (Fee tbc) Invoices & Contracts Project Bank Account OPERATIONAL FM Delivery Local relationships Helpdesks TFM Hard FM FM Supplier Framework Portal Soft FM UNCLASSIFIED Catering Specialist *0.5% GPS Management Fee recovered from suppliers based on spend directed through F/W

7 LEAN Sourcing Supporting procurement reform in Central Government Paddy Howlin Head of Sourcing & Category Management Property Government Procurement Service CFMD Conference: September 2012 UNCLASSIFIED

8 Setting the context Mandated across use of Central Government however key principals and benefits will apply to procurement undertaken by Health, Education, Local Government, Housing sectors etc. MCO announced publication of the LEAN Review at SME event on 11 February 2011: Management Summary & Diagnostics are published on Cabinet Office website: Headlines were significant saving to be made in time and cost by working in a more efficient and effective way. The output of the study was a proposed new way of managing competitive dialogue within the existing legal framework that eliminates waste and unnecessary sequential activity. The Cabinet Office has developed a standard solution - a suite of tools to enable the execution of the LEAN sourcing process for all three procedures: restricted, open and competitive dialogue.

9 The new policy requirements The new approach comprises the following new government policy requirements: Adoption of a LEAN sourcing approach designed to strip out waste and reduce costs. A requirement to carry out significant levels of pre-procurement market engagement with diverse range of prospective suppliers, including SMEs in order to warm-up the market, test our thinking and generate ideas for innovation as part of the development of outcome-based specifications. The default starting point for all Government procurements will be the use of the Open Procedure. There is an expectation that all but the most complex procurements are completed with 120 working days (publication of the advert to the award of contract). Complex defined as procurements in construction, infrastructure and defence etc that typically require a detailed design proposal developed, planning permission, private finance etc. The policy requirements will be adopted in the proposed future procurement for Facilities Management.

10 A simple illustration & challenge of as-is practice Source: Tenders Electronic Daily (Central Government) Jan 11 to Aug 11 No. of contracts awarded No. of PINs published relating to those contracts Average No. of Working Days from Contract Notice Publication to Contract Award Decision Date Competitive Dialogue 10 4 (40%) 439 Restricted (11%) 202 Open 10 2 (20%) 111 Are the right choices being made on selection of procurement route? Are opportunities being missed in warming up the market and using the PIN to reduce timescales? Benefit opportunities are being missed... Reduced turnaround times = 1) Decreased costs to suppliers 2) Better utilisation of scarce procurement resources 3) Potentially reduced procurement resource costs

11 Procurement routes the choice has become limited! Route Key Features Use Open All interested suppliers may respond to the advertisement in the OJEU by tendering for the contract. Well defined, outcome-based requirements will help ensure a manageable number of bid responses from good quality and capable suppliers. There is a government commitment towards greater use of the Open procedure and procurers should use this procedure as their default option. Restricted A two stage process where a selection of suppliers who respond to the advert is made and only they are invited to submit a tender for the contract. The selection (pre-qualification) questionnaire (PQQ) must only contain proportionate and relevant criteria. Use in limited circumstances where pre qualification is essential. The use of a standardised, stripped back core PQQ is mandatory across central Government, and not used at all for sub 100k work. Competitive Dialogue Following an advert and a selection process potential suppliers are invited to enter into dialogue to develop one or more suitable solutions before chosen suppliers are invited to tender. The Government has set a presumption against the use of competitive dialogue. Negotiated One or more potential suppliers are selected to negotiate the terms of the contract. An advert is usually required. Only to be used in extremely limited circumstances Described in the Regulations, for example, where a previous procurement was discontinued because of unacceptable/irregular tenders.

12 7 Key principles of the new approach Key principles 1. Establish a clear understanding of required business outcomes 2. Engage with the market in order to shape and confirm that the business requirement is attractive to a diverse range of suppliers 3. Use LEAN thinking and visual tools to set up and run a well planned and efficient process 4. Do not commence formal procurement until thorough engagement with suppliers has taken place. The Open procedure should be the default route 5. Streamline any engagement with suppliers and stakeholders by using a boot camp (or Industry Sounding) approach to make best use of limited time 6. Use e-sourcing tools to support the procurement and follow the LEAN Standard Operating Procedures (SOPs) 7. Measure and manage performance through continued focus on turnaround times and costs. Advert to award should be completed within120 working days Strong focus on preparing to go to market This is a key activity that takes time and careful planning Strong focus on running a fast procurement process This is a key activity that requires collective effort and is dependant on effective preparation Procurement perspective - The must do minimum Focus on the voice of the customer ensuring a sound understanding of required business outcomes Establish a planning and management discipline using visual management tools to drive progress Advertise your potential requirement to the market (preferably by using a project specific PIN) and undertake pre-procurement market engagement with industry prior to going to OJEU to inform sourcing strategy Ensure readiness for OJEU by developing your bidders pack (outcome / output based specification, draft Ts&Cs and project plan) ready for publication of OJEU Utilise OJEU compliant e-sourcing tools to underpin the sourcing process Confirm application of the LEAN sourcing standard operating procedures and challenge deviation from them to assure that best practice and efficiency has been built into all sourcing projects Drive continuous improvement and reductions in procurement turnaround times (from Contract Notice to Award of Contract) by measuring performance.

13 The new LEAN sourcing approach the 5 Stage Process Pre-Procurement Market Engagement Sourcing and Contracting 1. Business need & baselining 2. Market analysis & sourcing strategy 3. Supplier identification 4. Execution of sourcing strategy 5. Finalise contract Talk to potential suppliers, publicise requirement (preferably by using a project specific PIN) to warm the market up and advertise the industry engagement event Industry Sounding Events to capture the suppliers views on your requirement, on the viability, and on possible delivery options and where appropriate to facilitate meetings between suppliers to explore the potential for the establishing consortia, partnering arrangements and / or subcontracting opportunities. Mobilisation Pre-OJEU readiness - the preparation and subsequent publication of a bidders pack at OJEU including requirements, draft terms and conditions, selection criteria, evaluation strategy and criteria and procurement timescales. This transparency allows suppliers to make informed decisions as to whether they wish to bid. Driven by visual management tools Establish a project planning and performance hub in the mobilisation phase and use visual management and e- sourcing tools to drive the process and to measure and manage performance including turnaround times in line with the 120 day target. Execution of sourcing strategy through structured workshops, Industry Briefing Events and tightly managed project plans Use standstill period to prepare for publication of the contract documentation and to finalise delivery and contract management plans KEY TO SUCCESS: The new approach requires more work to be carried out before going to market

14 LEAN Sourcing Process General Overview Business need, baselining & market analysis Sourcing strategy Supplier identification Execution of sourcing strategy Finalise contract Mobilisation 1. Business Need Identification, Baselining & Market Analysis Ensure identification & clear articulation of the business need Talk to business stakeholders 2. Mobilisation 3. Sourcing Strategy Establish the procurement & identify sourcing strategy Talk to suppliers 4. Supplier Identification (OJEU) Publish requirements through a contract notice in the supplement to the Official Journal of the European Union Ensure that you are ready to go to market 22 to 66 calendar days from issue of OJEU 5. Supplier clarification Respond to all questions & clarifications simultaneously 6. Evaluation of Tenders The best solution is established through evaluation of tenders Use e- sourcing tools 7. Contract Award Notify the supplier and finalise the contract 10 days Drive continuous improvement in turnaround times by measuring performance 8. Contract Signature Formal signature of contract The sourcing team is set up for success, all associated stakeholders are clear on requirements of the business need Establish a strong PPM discipline approach and deploy visual management techniques Within 120 working days Indicative Timeline Ranges Subject to requirement at least months 7 10 Working Days Working Days Working Days 2 10 Working Days

15 In summary... Pre-OJEU Setting up for success - readiness 1.Developing a clear understanding of requirement business outcomes 2.Engaging with suppliers in the market and identifying opportunities for innovation and/ or breaking requirements into more attractive lots 3.Developing a detailed understanding of the business requirement and constructing it in a way that will be clear and attractive to the market 4.Getting a team in place with the right capabilities and a clear delivery plan (that takes into account approval and assurance points) Risk Execution Key points Procurement: OJEU to Award 1.Operating a highly efficient process in line with the plan, which focuses on reducing turnaround times and costs to both the client and the suppliers within the competition but maintains quality 1. The more quality time that is spent on pre-ojeu activities the more efficient the procurement is likely to be. 2. Reduced turnaround times (OJEU to award) = reduced costs and improved resource utilisation 3. LEAN sourcing is not about cutting corners it is about improving efficiency, and quality as part of a repeatable approach that is subject to continuous improvement 1. Failure to complete the pre-ojeu activities is likely to result in three things occurring: 1. A protracted procurement incurring significant costs 2. A business outcome that is sub-optimal 3. Dissatisfaction of key business stakeholders

16 Next Steps for FM Upon ministerial approval to the proposed recommendations for FM, GPU & GPS will commence with finalising the business case in coordination with central government departments through implementation working groups. Procurement will then follow a Lean process with a plan to be operational by mid 2014 Questions

Procurement of FM Services

Procurement of FM Services Next Generation FM Services Procurement of FM Services 22nd June 2017 Presented by Mark French Procurement of FM Services Introducing Crown Commercial Service (CCS) We re one of the biggest public procurement

More information

Estates, Facilities & Professional Services. Transactional Finance, Accountancy & Transactional Procurement Services Framework User Guide

Estates, Facilities & Professional Services. Transactional Finance, Accountancy & Transactional Procurement Services Framework User Guide . Estates, Facilities & Professional Services Transactional Finance, Accountancy & Transactional Procurement Services Framework Framework Reference Number: LPP/2013/00002 April 2015 2 Version Control Contributor(s)

More information

Project: Replacement provision for the Highway Term Service Contract (HTSC)

Project: Replacement provision for the Highway Term Service Contract (HTSC) BUSINESS JUSTIFICATION CASE (BJC) Project: Replacement provision for the Highway Term Service Contract (HTSC) Purpose: To support the Councils Highways Service in the management of highways infrastructure,

More information

Procurement Strategy and Action Plan. Financial Year

Procurement Strategy and Action Plan. Financial Year Procurement Strategy and Action Plan Financial Year 2018-2019 Status Final Owner Procurement Source location Procurement website Consultation APUC Endorsed Audit Committee 11 June 2018 Publication 1 August

More information

The impact and progress achieved against each of the principles of the 2015 WPPS is summarised below:

The impact and progress achieved against each of the principles of the 2015 WPPS is summarised below: Y Pwyllgor Cyfrifon Cyhoeddus / Public Accounts Committee PAC(5)-07-18 P2 National Assembly for Wales Public Accounts Committee: Public Procurement Evidence from Welsh Government Welsh Government Leadership

More information

What the new EU Public Procurement Directive means for SMEs: A DCO Overview

What the new EU Public Procurement Directive means for SMEs: A DCO Overview What the new EU Public Procurement Directive means for SMEs: A DCO Overview What the new EU Procurement Directive means for SMEs: A DCO Overview By Michael Crosby Communications Officer Connect on LinkedIn

More information

A simple Procurement Process Flow diagram is shown in Appendix 1 and should be considered when carrying out spend.

A simple Procurement Process Flow diagram is shown in Appendix 1 and should be considered when carrying out spend. Scottish Canals Procurement Policy Introduction The Scottish Canals Procurement Policy supports the Scottish Canals Procurement Strategy and sets out the method of delivery of the day-to-day procurement

More information

GP Out of Hours/111 Service Re-commissioning. Graham Clark, Lead Clinician, Out of Hospital Care Chris Coath, AD, Commissioning, Out of Hospital Care

GP Out of Hours/111 Service Re-commissioning. Graham Clark, Lead Clinician, Out of Hospital Care Chris Coath, AD, Commissioning, Out of Hospital Care Agenda item: 9.2 Subject: Presented by: Submitted to: GP Out of Hours/111 Service Re-commissioning Graham Clark, Lead Clinician, Out of Hospital Care Chris Coath, AD, Commissioning, Out of Hospital Care

More information

E 4 ISSUE/REVISION LAST MODIFIED 26 November 2012 DATE PRINTED

E 4 ISSUE/REVISION LAST MODIFIED 26 November 2012 DATE PRINTED THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT E 4 ISSUE/REVISION LAST MODIFIED 26 November 2012 DATE PRINTED RIBA stage E E4 PREPARE PQQ FOR CONTRACT WORKS (OJEU & NON OJEU) 1. DEFINITION

More information

Market Engagement/Soft Market Event

Market Engagement/Soft Market Event Market Engagement/Soft Market Event Lifestyle Services Procurement September 28 th 2016 Public Health Procurement Leads Steve Curtis, Senior Procurement Officer Jayne Smith, Procurement Officer Aims Robust

More information

How to improve commercial performance. Deliver more for less David Shields, Director Apsiz Services Ltd

How to improve commercial performance. Deliver more for less David Shields, Director Apsiz Services Ltd How to improve commercial performance Deliver more for less David Shields, Director May 2014 Transforming Government Procurement Service The Initial Major Steps Clear set of organisational targets established

More information

Public Contracts Regulations A Constructionline guide

Public Contracts Regulations A Constructionline guide Public Contracts Regulations 2015 A Constructionline guide Introduction The construction industry has a high risk and complicated procurement process. This has been recognised in a Cabinet Office guidance

More information

NHS Highland. Procurement Strategy

NHS Highland. Procurement Strategy NHS Highland Procurement Strategy 2016-21 NHS Highland Procurement Strategy 2016-21 1 Introduction Recognising that effective and efficient procurement will positively support the Board in achieving its

More information

Medical Category Tower Providers Contract Awards. Questions and Answers

Medical Category Tower Providers Contract Awards. Questions and Answers Medical Category Tower Providers Contract Awards Questions and Answers 1. What is the Future Operating Model (FOM)? The National Health Service (NHS) has the potential, through greater collaboration, to

More information

NHS GREENWICH Clinical Commissioning Group. Procurement Framework Document. Version 1.4

NHS GREENWICH Clinical Commissioning Group. Procurement Framework Document. Version 1.4 NHS GREENWICH Clinical Commissioning Group Procurement Framework Document Version 1.4 Date Version Status Comments 28/03/2013 1.3 Draft Draft submitted to Governing Body on 3/04/13 and Market Management

More information

RE-PROCUREMENT OF THE COLLABORATIVE SOUTH EAST WALES HIGHWAYS AND CIVILS CONSTRUCTION FRAMEWORK (SEWHIGHWAYS2)

RE-PROCUREMENT OF THE COLLABORATIVE SOUTH EAST WALES HIGHWAYS AND CIVILS CONSTRUCTION FRAMEWORK (SEWHIGHWAYS2) CARDIFF COUNCIL CYNGOR CAERDYDD CABINET MEETING: 27 JULY 2017 RE-PROCUREMENT OF THE COLLABORATIVE SOUTH EAST WALES HIGHWAYS AND CIVILS CONSTRUCTION FRAMEWORK (SEWHIGHWAYS2) REPORT OF CORPORATE DIRECTOR

More information

BIS Research & Evaluation Framework. Guide for Buyers

BIS Research & Evaluation Framework. Guide for Buyers BIS Research & Evaluation Framework Guide for Buyers Framework reference: CR150025BIS BIS Research & Evaluation Framework: Guide for Buyers Update 22 June 2016 1 P age Research & Evaluation Framework Contract

More information

ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 16 th October 2017

ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 16 th October 2017 ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 16 th October 2017 Title Leisure Management Contract Award Report of Wards Status Strategic Director (Adults, Communities and Health) All Public (with separate

More information

Procurement Strategy Version 08 October Reference Version 08

Procurement Strategy Version 08 October Reference Version 08 Strategy 2016-2020 Version 08 October 2016 Reference Version 08 Issue date October 2016 Review date October 2018 Introduction At Red Kite, achieving value for money in delivering our corporate vision is

More information

GLOSSARY C O N T E N T S PAGE. Group Procurement Strategy

GLOSSARY C O N T E N T S PAGE. Group Procurement Strategy C O N T E N T S PAGE 1 Executive Summary 3 2 Scope of this Strategy 3 3 Procurement Principles 4 4 Route To Market 6 5 Procurement Governance 8 6 Procurement Plan 2018/19 8 GLOSSARY EU European Union ICT

More information

CAN DO the. toolkit 2. RESOURCE 1: Can Do Toolkit 2. Funded by. MerthyrValleys. Quality Living Striving for Excellence Working Together

CAN DO the. toolkit 2. RESOURCE 1: Can Do Toolkit 2. Funded by. MerthyrValleys. Quality Living Striving for Excellence Working Together SMEfriendly procurement CAN DO the toolkit 2 Funded by MerthyrValleys H O M E S Quality Living Striving for Excellence Working Together RESOURCE 1: Can Do Toolkit 2 IMPORTANT: All three resources that

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY PROCUREMENT STRATEGY 2017-2022 1. Introduction 1.1 Vision for Procurement University College Cork, National University of Ireland, Cork (UCC) was established in 1845. Its vision is to be a leading University

More information

NHSScotland Procurement Review

NHSScotland Procurement Review NHSScotland Procurement Review Project Initiation Document QuEST Portfolio Office Contents 1. Document Control 3 1.1 Programme Details 3 1.2 Version Control 3 2. Purpose of the Document 4 3. Context and

More information

provide the key responsibilities of UK SBS in delivering quality and effective Strategic Procurement services to the Client

provide the key responsibilities of UK SBS in delivering quality and effective Strategic Procurement services to the Client The purpose of this Procurement Service Schedule is to: provide detail on the current scope of UK SBS Strategic Procurement services to BIS show service areas that have been determined as in scope for

More information

Resource Efficiency Framework Agreement Advice, Support and Delivery Service for Energy Efficiency Advice and Environmental Consultancy

Resource Efficiency Framework Agreement Advice, Support and Delivery Service for Energy Efficiency Advice and Environmental Consultancy Y Pwyllgor Cyfrifon Cyhoeddus / Public Accounts Committee PAC(4)-24-15 P3B Resource Efficiency Framework Agreement Advice, Support and Delivery Service for Energy Efficiency Advice and Environmental Consultancy

More information

Procurement Strategy period September 2012 September 2014

Procurement Strategy period September 2012 September 2014 National Library of Scotland Procurement Strategy period September 2012 September 2014 Aims This document aims to identify NLS strategy for the development and continued improvement of procurement systems,

More information

BCS, The Chartered Institute for IT. Consultation Response: HM Government Making Public Sector Procurement More Accessible to SMEs

BCS, The Chartered Institute for IT. Consultation Response: HM Government Making Public Sector Procurement More Accessible to SMEs BCS, The Chartered Institute for IT Consultation Response: HM Government Making Public Sector Procurement More Accessible to SMEs Dated: 17 October 2013 BCS The Chartered Institute for IT First Floor,

More information

Public Procurement in Laboratory Medicine How to Obtain the Best Solution

Public Procurement in Laboratory Medicine How to Obtain the Best Solution Public Procurement in Laboratory Medicine How to Obtain the Best Solution Introduction Who am I and where do I work Background Pre-Tender Preparation During the Tender Post Tender Award Summary Who am

More information

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference:

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference: Inland Revenue Transformation Programme Sourcing Workstream PROCUREMENT PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 28/06/2013 v1.0 FINAL Reference: 2013050 Document Control File

More information

GLASGOW WEST HOUSING ASSOCIATION PROCUREMENT STRATEGY

GLASGOW WEST HOUSING ASSOCIATION PROCUREMENT STRATEGY GLASGOW WEST HOUSING ASSOCIATION PROCUREMENT STRATEGY 2016-2020 Glasgow West Housing Association Limited Registered with The Scottish Housing Regulator HEP126 Registered under the Co-operative and Community

More information

FRAMEWORK OVERVIEW. Standardisation and rationalisation. Reduction of effort and resources. Cost avoidance/strategic cost allocation

FRAMEWORK OVERVIEW. Standardisation and rationalisation. Reduction of effort and resources. Cost avoidance/strategic cost allocation FRAMEWORK OVERVIEW HealthTrust Europe s (HTE) Document Storage, Scanning and Related Services framework agreement offers a simple and compliant route to market for the procurement of a range of documents

More information

Audit services outline procurement strategy

Audit services outline procurement strategy Audit services outline procurement strategy November 2016 High quality independent audit is one of the cornerstones of public accountability. It gives assurance that taxpayers money has been well managed

More information

Provision of ICT Managed Service for Aspirations Academies Trust

Provision of ICT Managed Service for Aspirations Academies Trust Provision of ICT Managed Service for Aspirations Academies Trust This document should be read in conjunction with the Pre-Qualification Questionnaire. 1 Contents 1. Glossary and Definitions... 4 2. Introduction...

More information

Brief Guide to Public Sector EU Procurement Legislation. Despatch PIN not a call for competition (optional) allowing shortened timescale

Brief Guide to Public Sector EU Procurement Legislation. Despatch PIN not a call for competition (optional) allowing shortened timescale A summary of the Open Procedure: Brief Guide to Public Sector EU Procurement Legislation Despatch PIN not a call for competition (optional) allowing shortened timescale before the contract notice was dispatched,

More information

ISLE OF MAN GOVERNMENT PROCUREMENT POLICY GD 2017/0026

ISLE OF MAN GOVERNMENT PROCUREMENT POLICY GD 2017/0026 ISLE OF MAN GOVERNMENT PROCUREMENT POLICY GD 2017/0026 INCLUSIVE TOLERANT SUSTAINABLE INTRODUCTION This Document sets out the Council of Ministers Procurement Policy for Government Ministerial Forward

More information

Procurement Policy. Education is for improving lives and for leaving your community and world better than you found it.

Procurement Policy. Education is for improving lives and for leaving your community and world better than you found it. Procurement Policy Education is for improving lives and for leaving your community and world better than you found it. Review date: April 2020 Page 1 of 13 Contents 1. Introduction... 3 2. Principles...

More information

Brooke Weston Trust. Trust Handbook: Policies and Procedures. Procurement Policy. Associated Policies Charging and Remissions

Brooke Weston Trust. Trust Handbook: Policies and Procedures. Procurement Policy. Associated Policies Charging and Remissions Title Procurement Policy Associated Policies Charging and Remissions REVIEWED: NEXT REVIEW: 1. Policy statement 1.1 This policy (Policy) sets out the rules by which The Brooke Weston Trust (the Trust)

More information

LANCASHIRE COMBINED FIRE AUTHORITY PROCUREMENT STRATEGY

LANCASHIRE COMBINED FIRE AUTHORITY PROCUREMENT STRATEGY LANCASHIRE COMBINED FIRE AUTHORITY PROCUREMENT STRATEGY 2018-21 CONTENTS 1. INTRODUCTION... 3 2. BACKGROUND... 3 3. WHAT IS PROCUREMENT... 3 4. APPLICABILITY... 4 5. PROCUREMENT PRINCIPLES... 4 6. CONTROLS,

More information

Parliamentary Procurement Rules

Parliamentary Procurement Rules Parliamentary Procurement Rules Document Revision History and Key Facts Version Issue date Policy owner Date of next review Comments/ brief description of main changes in this revision 001 01/01/15 PPCS

More information

Keep up-to-date. Invest in your future.

Keep up-to-date. Invest in your future. Keep up-to-date. Invest in your future. Services for professional procurement. Be better informed, make better decisions. Procurement Training for Regulated Procurement Professionals in Ireland Training

More information

BUYER S GUIDANCE FOR USE OF THE FRAMEWORK AGREEMENT FOR: POISE Framework agreement

BUYER S GUIDANCE FOR USE OF THE FRAMEWORK AGREEMENT FOR: POISE Framework agreement BUYER S GUIDANCE FOR USE OF THE FRAMEWORK AGREEMENT FOR: POISE Framework agreement 19 th October 2016 18th October 2020 OJEU Contract Notice Number: 2016/S 153-277888 OJEU Award Number: 2016/S 203-367806

More information

Guidance to support delivery of the Living Wage Commitment to Care at Home and Housing Support

Guidance to support delivery of the Living Wage Commitment to Care at Home and Housing Support Guidance to support delivery of the Living Wage Commitment to Care at Home and Housing Support 1. Introduction This guidance is a tripartite document informed and agreed by Scottish Government, COSLA,

More information

Procurement Strategy and Action Plan

Procurement Strategy and Action Plan Strategy and Action Plan 2016-2021 1. Context The University of Aberdeen s Strategic Plan contains a vision to transform the world with greater knowledge and learning and to be one of the world s top seats

More information

Issues for commissioners and Third Sector Organisations.

Issues for commissioners and Third Sector Organisations. Developing a voluntary sector provider market Issues for commissioners and Third Sector Organisations. Kevin Pritchard CBS Director Page -1- Third Sector Provider Development National Aims Aims of the

More information

A quick guide to equality and procurement for housing

A quick guide to equality and procurement for housing A quick guide to equality and procurement for housing A quick guide to equality and procurement What s in this guide? This guide is intended to provide important information about key legal requirements

More information

Collaborative Purchasing The UK Experience

Collaborative Purchasing The UK Experience Collaborative Purchasing The UK Experience Richard Peasgood MBA, MCIPS Ex Workstream Director Major Projects Firebuy (UK) Drivers Bain Review Industrial Action Gershon Review Public Sector Efficiency Local

More information

Procurement Evaluation Report. For The Provision of CCTV Services

Procurement Evaluation Report. For The Provision of CCTV Services Procurement Evaluation Report For The Provision of CCTV Services Ref: 5000004944 Document Status: FINAL Date: 29/11/13 Author: Vanessa Amissah Owner: Kevin Bates Document Location Version Control Description/Reason

More information

Estimated total value: c. 25m per annum (based on/subject to confirmation of West Midlands Combined Authority s (WMCA) annual AEB allocation)

Estimated total value: c. 25m per annum (based on/subject to confirmation of West Midlands Combined Authority s (WMCA) annual AEB allocation) Information notice This notice is for prior information only Main activity General public services Scope of the procurement Title: Adult Education Budget (AEB) Procurement Type of contract Service Estimated

More information

Procurement framework for managing Commissioning changes

Procurement framework for managing Commissioning changes Procurement framework for managing Commissioning changes 1. Introduction This framework sets out NHS Kernow s management of major changes to the commissioning of services. Applying a consist approach for

More information

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Purpose The Business Case describes and seeks approval to award the contract for the replacement of the existing Pathology

More information

Audit services procurement strategy

Audit services procurement strategy Audit services procurement strategy December 2016 High quality independent audit is one of the cornerstones of public accountability. It gives assurance that taxpayers money has been well managed and properly

More information

Parliamentary Procurement Rules

Parliamentary Procurement Rules Parliamentary Procurement Rules Document Revision History and Key Facts Version Issue date Policy owner Date of next review Comments/ brief description of main changes in this revision 001 01/01/15 PPCS

More information

Streamlining processes and increasing value for the oil and gas supply chain

Streamlining processes and increasing value for the oil and gas supply chain Streamlining processes and increasing value for the oil and gas supply chain 1 What is the Supply Chain Code of Practice? The Supply Chain Code of Practice outlines a set of best practice guidelines and

More information

Scotland Excel. Report by Director Scotland Excel

Scotland Excel. Report by Director Scotland Excel Scotland Excel To: Executive Sub Committee On: 10 February 2017 Report by Director Scotland Excel Tender: Engineering & Technical Consultancy Schedule: 06/16 Period: 18 March 2017 until 17 March 2021 1.

More information

Census Transformation Programme. Market Engagement Exercise. Supplier Information Document

Census Transformation Programme. Market Engagement Exercise. Supplier Information Document Census Transformation Programme Market Engagement Exercise Supplier Information Document September 2016 Table of contents Introduction 2 About this document 2 1. About the census 2 2. Statistics in the

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

Glasgow Life Procurement Annual Report

Glasgow Life Procurement Annual Report 1 Glasgow Life Procurement Annual Report 2016-2017 1. Introduction This Annual Report provides an account of Glasgow Life s procurement activity for 2016/17. 2. Background and key statistics The Scottish

More information

Commercial Profession Skills and Competency

Commercial Profession Skills and Competency Commercial Profession Skills and Competency Framework Document Title Author Commercial Profession Skills and Competency Framework Ian Mackie Approver Sign Off Commercial Capability Group Version V1 13/02/15

More information

Deliverability Testing

Deliverability Testing Invitation to Negotiation Stage 1 (ITN1) for the provision of a Prime Provider for the delivery of Integrated Community Services to NHS Bath and North East Somerset CCG and Bath & North East Somerset Council

More information

Final Business and Regulatory Impact Assessment

Final Business and Regulatory Impact Assessment Final Business and Regulatory Impact Assessment Title of Proposal Final Business and Regulatory Impact Assessment (BRIA) associated with proposed changes to the public procurement rules in Scotland. 1.

More information

National Civil Engineering & Infrastructure Framework. London 8 th December 2017

National Civil Engineering & Infrastructure Framework. London 8 th December 2017 National Civil Engineering & Infrastructure Framework London 8 th December 2017 Matt Carrington-Moore Chief Marketing Officer Adrian Hill Head of Frameworks John Simons Head of Procurement & Audit Agenda

More information

Higher Education Procurement Association. Procurement Benefits Reporting Guidance 2016/17 Onwards

Higher Education Procurement Association. Procurement Benefits Reporting Guidance 2016/17 Onwards Higher Education Procurement Association Procurement Benefits Reporting Guidance 2016/17 Onwards January 2017 1 Contents Section Subject Page Section 1 Background & Introduction 3 Section 2 Reporting 4

More information

In total, nine bidders submitted a PQQ response and five were successfully taken forward to the Invitation to Tender stage.

In total, nine bidders submitted a PQQ response and five were successfully taken forward to the Invitation to Tender stage. Report to Cabinet 12 th January 2017 By the Cabinet Member for Leisure and Culture & By the Cabinet Member for Finance and Assets DECISION REQUIRED Main report not exempt Appendix 1 Exempt under Paragraph

More information

Supporting Families Service

Supporting Families Service Supporting Families Service Commissioning Plan November 2017 1. Introduction 1.1. This plan outlines the commissioning model for a future family support service. It is part of a wider move towards greater

More information

Role of contracts & procurement

Role of contracts & procurement Role of contracts & procurement Many bring sites and/or containers are provided and serviced without any formal arrangement between the different parties (i.e. the local authority and the service provider)

More information

Date: 18 July Report title: Gateway 1: Procurement Strategy Approval - Southwark External Solicitors Framework

Date: 18 July Report title: Gateway 1: Procurement Strategy Approval - Southwark External Solicitors Framework Item No. 15. Classification: Open Date: 18 July 2017 Meeting Name: Cabinet Report title: Gateway 1: Procurement Strategy Approval - Southwark External Solicitors Framework Ward(s) or groups affected: Cabinet

More information

Case Study: Developing a Comprehensive Procurement Strategy to Ensure Financial Stability for the NHS

Case Study: Developing a Comprehensive Procurement Strategy to Ensure Financial Stability for the NHS Case Study: Developing a Comprehensive Procurement Strategy to Ensure Financial Stability for the NHS Warren Simms Associate Director Clinical Procurement and Market Management Context. NHS Procurement

More information

Category Manager: Compliance. Recruitment Pack. Category Manager: Compliance 1 of 16 January Recruitment Pack

Category Manager: Compliance. Recruitment Pack. Category Manager: Compliance 1 of 16 January Recruitment Pack Category Manager: Compliance Category Manager: Compliance 1 of 16 January 2018 Contents 1. Your Application... 3 2. Welcome from Dave Neilson, Chief Executive... 4 3. About Fusion21... 5 4. Job Description

More information

Procurement Policy & Procedures

Procurement Policy & Procedures Procurement Policy & Procedures 1 Introduction 2 Objectives 3 Organisation 4 Authority 5 Procurement Procedures 6 EU Procurement Regulations 7 General Principles of Procurement 8 Reporting & Information

More information

Corporate Strategy for Commissioning and Procurement

Corporate Strategy for Commissioning and Procurement Corporate Strategy for Commissioning and Procurement 2012-2015 Page 1 of 19 C ontents 1 I n t r o d u c t i o n... 3 Introduction to Durham County Council... 3 Introduction to the Corporate Strategy for

More information

An Introduction to Milton Keynes Council Procurement

An Introduction to Milton Keynes Council Procurement An Introduction to Milton Keynes Council Procurement An Introduction to Milton Keynes Council Procurement v1 October 2014 1 Milton Keynes Council Procurement Introduction Milton Keynes Council (the Council)

More information

Jo Walker, Director: Environment ( ;

Jo Walker, Director: Environment ( ; Residual Waste Contract Competitive Dialogue Evaluation Framework AGENDA NO: Cabinet Date 19 th November 2008 INSERT PORTFOLIO NAME HERE Key Decision Background Documents Location/Contact for inspection

More information

DORSET PROCUREMENT. Procurement Strategy

DORSET PROCUREMENT. Procurement Strategy DORSET PROCUREMENT Procurement Strategy 2018 2020 To provide procurement and commercial expertise that supports contracts and purchasing activity to deliver value for money, social value and added value

More information

Health and Care Professions Council 04 July Proposed Approach to a revised threshold policy for the acceptance of Fitness to Practise concerns

Health and Care Professions Council 04 July Proposed Approach to a revised threshold policy for the acceptance of Fitness to Practise concerns Agenda Item 10 Enclosure 7 Health and Care Professions Council 04 July 2018 Proposed Approach to a revised threshold policy for the acceptance of Fitness to Practise concerns For discussion From John Barwick,

More information

HOW TO DO BUSINESS WITH BANGOR UNIVERSITY A GUIDE FOR SUPPLIERS

HOW TO DO BUSINESS WITH BANGOR UNIVERSITY A GUIDE FOR SUPPLIERS HOW TO DO BUSINESS WITH BANGOR UNIVERSITY A GUIDE FOR SUPPLIERS Produced by Bangor University s Corporate Procurement Team July 2016 Version 1.0 CONTENT About this Guide.. 3 Background.. 4 The Procurement

More information

NHS DORSET CCG CLINICAL SERVICES REVIEW SPECIFICATION

NHS DORSET CCG CLINICAL SERVICES REVIEW SPECIFICATION NHS DORSET CCG CLINICAL SERVICES REVIEW SPECIFICATION 1. REQUIREMENTS OVERVIEW 1.1 NHS Dorset Clinical Commissioning Group (CCG) is seeking a provider partner to better understand the enduring care needs

More information

UNIVERSITY PROCUREMENT STRATEGY

UNIVERSITY PROCUREMENT STRATEGY UNIVERSITY PROCUREMENT STRATEGY 1. Introduction 1.1 The Procurement Strategy supports the delivery of the University s Strategic Plan, in which one of the Strategic Aims is to: Be environmentally sustainable

More information

National Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide

National Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide National Commissioning Board Leading Integrated and Collaborative Commissioning A Practice Guide March 2017 Introduction The short practical guide is intended to stimulate commissioners and other senior

More information

Scotland Excel Executive Sub Committee

Scotland Excel Executive Sub Committee Scotland Excel Executive Sub Committee To: Executive Sub Committee On: 17 June 2016 Report by Director Tender: Street lighting bulk renewal of luminaires Schedule: 10/13 Period: 1 July 2016 until 30 June

More information

Contract Management arrangements - Procurement Policy update

Contract Management arrangements - Procurement Policy update Agenda item: 13 Report title: Report by: Action: Contract Management arrangements - Procurement Policy update Gordon Duffus, Head of Procurement, Resources and Quality Assurance, gordon.duffus@gmc-uk.org,

More information

Government Services Division. eservices High Level Implementation Plan

Government Services Division. eservices High Level Implementation Plan Government Services Division eservices High Level Implementation Plan The Secretary Department of Treasury and Finance 1 Treasury Place Melbourne Victoria 3002 Australia Telephone: +61 3 9651 5111 Facsimile:

More information

Ensuring full compliance with policy & practice by staff and suppliers. Equality Analysis Report Template (2014)

Ensuring full compliance with policy & practice by staff and suppliers. Equality Analysis Report Template (2014) Equality Analysis Procurement Ensuring full compliance with policy & practice by staff and suppliers 1 Title of policy Procurement Policy Equality Analysis Report Template (2014) 2 Who does the policy,

More information

02/03/17 Appendix A Reqts Traceability Matrix v3.0 DCC Public. requirements.

02/03/17 Appendix A Reqts Traceability Matrix v3.0 DCC Public. requirements. esource W1 W2 W3 W4 W5 Appendix 2, 2.5 Outcome and ways of working description Ensure all activities and outputs are delivered in accordance with the objectives and design principles Timely and valuable

More information

Officer Recommendations

Officer Recommendations Policy and Resources Committee 19 July 2018 Title Report of Wards Status Award of Contract to Community Sector Development Partner Leader of the Council All Public (with separate exempt report) Enclosures

More information

Audit report Written statement of response to the audit report from the health service CEO

Audit report Written statement of response to the audit report from the health service CEO 1.1 Background From 26 June 2016, hospitals and health services mandated under Schedule 1 and 5 of the Health Services Act 1988 (Vic) must comply with the new Health Purchasing Victoria (HPV) Health Purchasing

More information

Options Appraisal for Repairs and Maintenance Services for Babergh and Mid Suffolk District Councils (MSDC)

Options Appraisal for Repairs and Maintenance Services for Babergh and Mid Suffolk District Councils (MSDC) Appendix 1 Options Appraisal for Repairs and Maintenance Services for Babergh and Mid Suffolk District Councils (MSDC) Executive Summary This report presents the options available for providing repairs

More information

SOUTH WEST POLICE PROCUREMENT DEPARTMENT (SWPPD) PROCUREMENT STRATEGY 2014/15

SOUTH WEST POLICE PROCUREMENT DEPARTMENT (SWPPD) PROCUREMENT STRATEGY 2014/15 Appendix A SOUTH WEST POLICE PROCUREMENT DEPARTMENT (SWPPD) PROCUREMENT STRATEGY 2014/15 V1 April 2014 1 Foreword 1.1 The overall vision of the PCCs and the Chief Constables of the Forces they maintain

More information

Procurement Policy. Version: 001 NHS Southend CCG Governing Body Date ratified: 5 th January Name of originator/author: Narinder Singh - Attain

Procurement Policy. Version: 001 NHS Southend CCG Governing Body Date ratified: 5 th January Name of originator/author: Narinder Singh - Attain Procurement Policy Version: 001 Ratified by: NHS Southend CCG Governing Body Date ratified: 5 th January 2017 Name of Director Sponsor Margaret Hathaway Name of originator/author: Narinder Singh - Attain

More information

European Maritime and Fisheries Fund Competitive Tendering and Public Procurement. Technical Guidance Notes

European Maritime and Fisheries Fund Competitive Tendering and Public Procurement. Technical Guidance Notes Welsh Government Rural Communities Rural Development Programme 2014-2020 European Maritime and Fisheries Fund 2014-2020 Competitive Tendering and Public Procurement Technical Guidance Notes Crown Copyright

More information

Trends in NHS Procurement and their impact

Trends in NHS Procurement and their impact Trends in NHS Procurement and their impact HFMA Procurement Forum 24 th May 2018 Beth Loudon Head of Sourcing and Procurement NHS Shared Business Services What are we going to talk about? Explore the concept

More information

Commissioning for the NHS Health Check: Preparation to Procure. 5 November 2009

Commissioning for the NHS Health Check: Preparation to Procure. 5 November 2009 : Preparation to Procure 5 November 2009 Agenda Market engagement and management When should you procure? What are the procurement options? Developing a procurement strategy Market Management Should be

More information

Customer Support Group (CSG) Invoicing and Monitoring Arrangements. April 2016

Customer Support Group (CSG) Invoicing and Monitoring Arrangements. April 2016 Internal Audit Customer Support Group (CSG) Invoicing and Monitoring Arrangements April 2016 Distributed to: Chief Operating Officer Commercial Director Director of Resources Head of Finance Partnership

More information

Brief Guide to Public Sector EU Procurement Legislation. Services for professional procurement. Be better informed, make better decisions.

Brief Guide to Public Sector EU Procurement Legislation. Services for professional procurement. Be better informed, make better decisions. Services for professional procurement. Be better informed, make better decisions. Brief Guide to Public Sector EU Procurement Legislation www.achilles.com Public procurement in the European Union (EU)

More information

ANALYST & INVESTOR PRESENTATION

ANALYST & INVESTOR PRESENTATION ANALYST & INVESTOR PRESENTATION 15 NOVEMBER 2010 HSBC, Canary Wharf Agenda Interim Management Statement Support Services Presentations Business overview Internal initiatives delivering value Public sector

More information

Supporting Families Service

Supporting Families Service Supporting Families Service Draft Commissioning Plan September 2017 1. Introduction 1.1. This draft plan outlines the proposed commissioning model for future family support services. It is part of a wider

More information

Delivering Procurement Savings for the Public Sector

Delivering Procurement Savings for the Public Sector Delivering Procurement Savings for the Public Sector David Shields, Managing Director, Government Procurement Service 21/09/2011 1 Strategic Review Commissioned February 2011 by Francis Maude, MCO, and

More information

Procurement Strategy Approved: 7 December 2016 Review Date: March 2018

Procurement Strategy Approved: 7 December 2016 Review Date: March 2018 Procurement Strategy Approved: 7 December 2016 Review Date: March 2018 If you have difficulty with sight, or if you require a translated copy of this policy, we would be pleased to provide the information

More information

This five year strategy sets out how the council intends to purchase goods, works or services from third parties that:

This five year strategy sets out how the council intends to purchase goods, works or services from third parties that: Contents 1. Introduction... 3 2. Achievement of outcome of next five years... 4 2.1 Monitoring arrangements... 6 Appendix 1 Council strategic priorities 2015... 7 Appendix 2 Commissioning led council and

More information

Contents Contact details

Contents Contact details Procurement Strategy - Period December 2016 December 2018 Contents 1.0 Introduction / Executive Summary... 2 2.0 Procurement Vision and Mission Statement... 2 3.0 Strategic rationale / context... 2 3.1

More information

Better Procurement. A Response to the Government s Consultation on the Development of an Industrial Strategy. scapegroup.co.uk

Better Procurement. A Response to the Government s Consultation on the Development of an Industrial Strategy. scapegroup.co.uk Better Procurement A Response to the Government s Consultation on the Development of an Industrial Strategy scapegroup.co.uk Executive Summary This document has been prepared in response to the Government