Procurement Management Processes
|
|
- Joel West
- 5 years ago
- Views:
Transcription
1 Procurement Management Processes Olga Botero PM A-01 Contracting and procurement in project management Dr. Tony Prensa October 8 th 2010
2 Project Procurement Management includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team (PMBOK, 2008, p.313) Processes Plan procurement, document requirements and identify potential vendors Conduct procurement, choose vendor, award contract Administer contract performance, monitor progress and administer change management Close procurement, document outcome, close contract and Procurement Management Definitions adjust finances Products ADC project-scheduling tool for the entire company eliminating duplicate software and obtaining quality suppliers, quantity discounts, lower paperwork cost and standardized practices (Kerzner, 2004, p. 840)
3 Executive Summary Project Integration Procurement Management Processes SOW - Statement of Work SOO - Statement of Objectives Plan Procurement Conduct Procurement Administer Procurement Close Procurement Contract Types Fix price Lump sum Cost plus fixed fee Guarantee Max. Share Savings Project management knowledge area part of process groups From the Project Plan
4 Procurement Process and Project Success Cost effectiveness Keep project budget under control Buyer expertise eliminates mistakes Quantity discounts Streamline Work force One expert buyer according to product Eliminate duplicate effort Shared responsibilities PM will share responsibilities with Procurement Managers Seller choice could be more fair Risk mitigation The expertise of the buyer will result in a more reliable product or service Procurement administration in the product lifecycle of each phase will reduce the risk of the following phases (Kerzner, 2009, p. 841)
5 Project Procurement Processes To be used at ADC Planning procurement Procurement Specifications Find vendors Perform product analysis Develop SOO (Statement of Objectives) Develop plan Analyze SOWs and select best candidate Obtain approval Conduct Procurement Review winning bid specifications Check references Develop contract agreement Compare methodologies Execute software acquisition contract Or Service acquisition contract Execute Hardware acquisition contract
6 Project Procurement Processes To be used at ADC (Cont.) Administer procurement Procurement change management Review performance Analyze audit reports Administer claims Update procurement plan Integrate changes in project plan Close procurement Review end result according to SOO Project sign off by stakeholders and sponsors Close financial transactions Resolve inconsistencies Negotiate and mediate if possible Litigate if necessary
7 Contract Selection Criteria Cost of buying versus a SaaS Guarantee maximum share Fix cost plus subscription fee per user Technical requirements of each List from project managers 90 Day project time line Eliminates several contract types Contractor responsibilities Contractor SOW Contractor internal expertise
8 Fix price or lump sum contract Advantages Buyer has control on price Buyer will have advance notice on changes Buyer involvement is limited Seller will try to finish contract the earliest possible to maximize profit The vendor expertise will eliminate expensive training and time Disadvantages Too much time to develop specifications Requires exact knowledge of requirements Seller may inflate prices to cover contingencies Buyer may not get a quality product if seller cuts corners to finish earlier ADC will not have expertise in-house unless they are trained by the vendor A well-written contract offers three benefits. One, it prevents miscommunication between the major parties. Two, it prevents rework that results from misunderstandings. Three, it reduces the cost impact of fixes since the opportunity for rework has lessened. (Kliem, 1999)
9 Guarantee maximum share savings contract Advantages Firm cost at earliest possible completion Buyer and seller share same risk Advance notice for changes Incentive for project completion Buyer and seller form a team producing trained personnel Disadvantages Complete requirements before contract start date Buyer is permanently involved Buyer will provide auditing Buyer will use more resources The Owner who awards the contract should ask the contractor: "How much fee (or profit) do you want in this project? (Gogulski, 2002)
10 Summary We will use all the procurement processes: plan, execute, administer and close We will use a Request for Quotation (RFP) and require SOW from each vendor The Guarantee maximum share savings is our contract of choice The project success depends on the contract detail, clarity and fairness.
11 References Gogulski, P, (2002, December), Avoiding Construction Claims through Guaranteed Maximum Contracts, Retrieved October 7 th 2010 from entransit/gmax.pdf Kerzner, H. (2009). Project Management: A systems approach to planning, scheduling, and controlling. Hoboken, New Jersey: John Wiley & Sons Inc. Kliem, R, Ludin, R, (1999), Tools and Tips for Today s Project Manager, Colorado Technical University, Safari Books Online Project Management Institute, Inc. 2008, A Guide to the Project Management Body of Knowledge Fourth Edition Procurement Management, (2010) Retrieved October 7 th 2010 from Procurement-Management.htm
Contract Finalization
Contract Finalization Olga Botero PM630-1004A-01 Contracting and procurement in project management Dr. Tony Prensa Where do you want to be? Procurement Management Be part of the team Bidding Techniques
More informationProject Management for the Supply Professional
Project Management for the Supply Professional Dr. Rene G. Rendon, CPSM, C.P.M., CPCM, PMP U. S. Naval Postgraduate School (831) 656-3464 rgrendon@nps.edu 95 th Annual International Supply Management Conference,
More informationConnoisseur Solutions Project Procurement Management
Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes
More informationUpgrade to Legacy Billing System
Group Project, Alpha Group Bob Young, Group Leader Olga Botero Mike Lamb Cynthia Thompson Tim Watkins Professor Gigi Smith Project Planning, Execution, and Closure PM610-1001B-01-Group A-P5 T1 March 19,
More informationIntroduction to Project Management
Introduction to Project Management Chapter 10 Managing Project Procurement Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 10-1 Two Perspectives
More informationProject Management Professional (PMP) Exam Review
Project Management Professional (PMP) Exam Review Unauthorized distribution is strictly prohibited. These resources are for 3FOLD Education Centre students. PMI, PMP, PMBOK and the PMI Registered Education
More informationALTERNATIVE CONTRACTING METHODS
ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional
More informationAPDC Standard Customer Relationship Management Processes Project
APDC Standard Customer Relationship Management Processes Project Janele Boyles, Derrick Douglas and Olga Botero PM600-1001A-01 Project Management Processes in Organizations Professor Terry Northcraft January
More informationConstruction Contracts
Construction Contracts By Dr. Ibrahim Assakkaf Construction Contracts By Dr. Ibrahim Assakkaf 1 The Need Web-based Contracts Supporting scheduling Controlling Regulating Analyzing Auditing the procurement
More informationReport on Effectiveness of the Construction Manager at Risk Project Delivery Method
Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to
More informationTime to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO
Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from
More informationCHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS
CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical
More informationUnit 10: Procurement Management (PMBOK Guide, Chapter 12)
(PMBOK Guide, Chapter 12) This knowledge area addresses the processes for purchasing or acquiring products and services from outside the project team or organization. See course slide #10-1 for an overview
More informationFederal Acquisition Service
U.S. General Services Administration Federal Acquisition Service Frank Parker Contracting Officer General Services Administration February 26, 2008 Who are we? GSA Federal Acquisition Service A New Service
More informationPROCUREMENT AND CONTRACT MANAGEMENT TRAINING COURSES. Managing Contracts Managing Service Level Agreements Writing Statements of Work
PROCUREMENT AND CONTRACT MANAGEMENT TRAINING COURSES Managing Contracts Managing Service Level Agreements Writing Statements of Work MANAGING CONTRACTS 3 DAYS COURSE OVERVIEW Project managers, contract
More informationCORPORATE FINANCE WORKBOOK
CORPORATE FINANCE WORKBOOK CFA Institute is the premier association for investment professionals around the world, with over 101,000 members in 134 countries. Since 1963 the organization has developed
More informationGuten Tag. (good day)
Guten Tag (good day) What is the #1 problem many people have on a project? What is the #1 problem many people have on a project? Communication Project Management Process Groups Project 4. Integration Management
More information45. Feedlot construction delivery
Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction
More informationPMP MOCK EXAMS BASED ON PMBOK 5TH EDITION
PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set4.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationProject Management Professional Training
Training Course Course Language Course Duration Project Management Professional Training PMP Project Management Professional Exam Preparation based on PMBOK 6 th Edition ( 40 PDUs) English Total Number
More informationPMP TRAINING COURSE CONTENT
PMP TRAINING COURSE CONTENT SECTION1: INTRODUCTION PMI, PMP AND PMBOK What is PMI, PMP, and PMBOK? What do I get out of PMP? How do I get certified? Exam qualifications and PM experience Guidelines to
More informationOutsourcing: Managing Interorganizational Relations
CHAPTER TWELVE Outsourcing: Managing Interorganizational Relations Copyright 2014 McGraw-Hill Education. All Rights Reserved. PowerPoint Presentation by Charlie Cook Where We Are Now 12 2 Partnering Introduction
More informationProject Management Framework
Project Management Framework What s Project? - Why Project? What s Project Management? - Why Project Management? What s Project Management Professionals? - Why Project Management Professionals? Project
More informationECI: Two-Stage Contracts
ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /
More informationA Contracting Officer s Guide To Getting Stronger Contractors
A Contracting Officer s Guide To Getting Stronger Contractors Breakout Session # B12 Jeff Shen, VP & GM, Red Team Consulting Date: Monday, July 28, 2014 Time: 2:30pm-3:45pm Introductions Red Team Federal
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationAudio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program
Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications
More informationStart a successful pricing project
Start a successful pricing project Beginning a new pricing project can be difficult, risky and stressful. Pricing is a sensitive subject in almost every organization, but it doesn t have to be. For organizations
More informationLCS International, Inc. PMP Review. Chapter 9 Conducting Procurements and Sharing Information. Presented by David J.
PMP Review Chapter 9 Conducting Procurements and Sharing Information Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy
More informationManaging Information Technology 6 th Edition
Managing Information Technology 6 th Edition CHAPTER 11 METHODOLOGIES FOR PURCHASED SOFTWARE PACKAGES Copyright 2009 Pearson Education, Inc. Publishing as Prentice Hall 1 METHODOLOGIES FOR PURCHASED SOFTWARE
More informationProject Management Proposal
Project Management Proposal INTRODUCTION Managing Government Projects can often be challenging. You typically need to manage internal staff, external suppliers, contractors, equipment and materials - while
More informationThe 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th
The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not
More informationSummary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)
Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder
More informationRole of Procurement / Purchasing Within the Authority
Role of Procurement / Purchasing Within the Authority What is Purchasing s Role / Why Is Purchasing Important? The Authorized entity within the Water Authority that procures the goods / services required.
More informationProject Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP
Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction
More informationClick to edit Master title style
Click to edit Master title style Click Category to edit Management: Master title style Transformational Change in Federal Procurement Breakout Third Session level #G13 Eric Heffernan, Principal, Grant
More informationLB 889 The Political Subdivisions Construction Alternatives Act
1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.
More informationAdvance Collaborate Enrich
Job Order Contracting 101 A Facilities Management Tool Sponsored by the Center for Job Order Contracting Excellence and The National Association of State Facilities Administrators Job Order Contracting
More informationContent Break-up & Methodology for awarding Contact Hours / PDUs
N.I.T.E - Project Management Professional (PMP) Exam Prep Course Content Break-up & Methodology for awarding Contact Hours / PDUs This course is based on Project Management Book of Knowledge PMBOK Guide
More informationFlexible IT: Contracting Strategies for Infrastructure as-a-service White Paper
Flexible IT: Contracting Strategies for Infrastructure as-a-service White Paper About this Paper: ViON Corporation has provided technology Infrastructure as a Service (IaaS) to government agencies since
More informationOverview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Changes
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Changes PMI -- Project Management Institute» Leading global association for the project management profession»
More informationKirk W Buffington, CPFIM, CPPO, C.P.M.,
Kirk W Buffington, CPFIM, CPPO, C.P.M., An Overview We will be talking about: The elements of the RFP process Factors determining the selection of the procurement method The elements of risk and how they
More informationConstruction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017
Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 OPENING REMARKS Kinney Poynter Moderator Executive Director NASACT Alan Pennington Speaker Vice
More informationJOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference
JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation
More informationKnowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration
Knowledge Areas According to the PMBOK edition 5 Chapter 4 - Integration 4.1 - Develop Project Charter Process Project statement of work Expert Judgment Project charter Business case Facilitation techniques
More informationREPORT 2015/086 INTERNAL AUDIT DIVISION. Audit of the Kuwait Joint Support Office
INTERNAL AUDIT DIVISION REPORT 2015/086 Audit of the Kuwait Joint Support Office Overall results relating to the effective management of support functions performed by the Kuwait Joint Support Office were
More informationThe Meaning of Price Analysis
The Meaning of in not so FAR off terms Robert M. Hardison, CPPO Richland County School District One Director, Procurement and Warehouse Services 1 Government policy is to contract for its goods and services
More informationProcurement Presentation to the Financial Management Institute of Canada
Procurement Presentation to the Financial Management Institute of Canada Bid Evaluation Methodologies By: James Steedman Senior Procurement and Contracting Officer, Treasury Board Secretariat November
More informationIIA San Diego Chapter Government Auditing Seminar
IIA San Diego Chapter Government Auditing Seminar Capital Project Performance Auditing November 2013 Introduction In today s contracting environment, it is important to understand the risks when embarking
More informationComparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013
Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should
More informationMTNT An Alaska Native Corporation McGrath Takotna Nikolai Telida
Alpha Contracting with an Alaska Native Corporation MTNT An Alaska Native Corporation McGrath Takotna Nikolai Telida Effective Alpha Contracting. By working hand-in-hand with a contractor, the Alpha Contracting
More informationUnit 3: The Traditional Procurement Route
Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining
More informationProject Management Process Groups. Monitoring & Controlling. Initiating Planning Executing. Closing. Check & Act. Rita: A project ends here!
(Semaphore) Project Management Process Groups Initiating Planning Executing Monitoring & Controlling Closing Rita: Start Plan Do Check End & Act A project ends here! Project Management Process Groups Initiating
More informationTrinity Well Field and Production Facilities Project Management Using CMAR
Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,
More informationUniform Guidance Purchasing Updates. What University Administrators and PIs Need to Know
Uniform Guidance Purchasing Updates What University Administrators and PIs Need to Know Executive Summary The Uniform Guidance (UG) governs the management of federally funded sponsored projects across
More informationProcurement Services Overview
Procurement Services Overview Agenda Procurement Services @ UConn What is Procurement Terminology What we do How we help Things you need to know Projects & Initiatives Success stories Upcoming initiatives
More informationFlexible IT: Contracting Strategies for Infrastructure as-a-service White Paper
Flexible IT: Contracting Strategies for Infrastructure as-a-service White Paper About this Paper: ViON Corporation has provided technology Infrastructure as a Service (IaaS) to government agencies since
More informationWUPRPM Regulations and Procedures Effective: November 11, 2005 R. Purchasing and Financial Obligations Revision Date: July 1, 2015.
Table of Contents 1. Purpose... 3 2. Definitions... 3 3. Limits and Thresholds... 4 4. Competitive Bidding... 4 5. Request for Quotation/Request for Proposal... 5 6. Bid Information... 5 7. Bid Bonds...
More information2016 National Tribal Transportation Conference
Alaska Tribal Technical Assistance Program Center 2016 National Tribal Transportation Conference Construction Management Darrel Williams Introductions Introduction to Construction Administration Construction
More informationSelecting good vendors is as easy as: 1 Identify
Selecting good vendors is as easy as: 1 Identify 2 Prioritize 3 Integrate Note: Slides do not contain complete content and are intended for delivery with accompanying verbal presentation. SBC Project Management
More informationEnterprise Software License Agreements - Best Practices - Lessons Learned 9/8/2009 1
ELA Best Practices Enterprise Software License Agreements - Best Practices - Lessons Learned 9/8/2009 1 Buying Software Software has been commoditized in order to simplify small repeatable transactions
More informationCHAPTER 4 INTEGRATION OF CONSTRUCTION PROJECT MANAGEMENT AND SUSTAINABILITY
CHAPTER 4 INTEGRATION OF CONSTRUCTION PROJECT MANAGEMENT AND SUSTAINABILITY CONTENTS 4.1: THE IDEA 4.2: MANAGEMENT FUNCTIONS 4.3: ORGANIZATIONAL STRUCTURES 4.4: TYPICAL PROJECT DELIVERIES 4.5: ICT IN CONSTRUCTION
More informationINFRASTRUCTURE ADVISORY SERVICES
INFRASTRUCTURE ADVISORY SERVICES Circle of Commitment mitment Com Op po rtu n Sp irit ity d it io n s Prosperity Trust m un T ra Co m it y Re s p e c t In today s increasingly cost-conscious environment,
More informationLM032: Advanced Tendering Procedures & Bid Evaluation
LM032: Advanced Tendering Procedures & Bid Evaluation LM032 Rev.001 CMCT COURSE OUTLINE Page 1 of 6 Training Description: The engagement and management of contractors and suppliers is a vital part of the
More informationAppendix. Process Inputs and Outputs
3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the
More informationSection 8 Procurement Procedures
Section 8 Procurement Procedures Section 8 Defining Procurement Procurement is the orderly process of acquiring, by lease or purchase, goods or services such as food, meals, equipment, bookkeeping and
More informationADDENDUM NO. 1 Kansas City Area Transportation Authority 1350 E. 17 th Street Kansas City, Missouri 64108
ADDENDUM NO. 1 Kansas City Area Transportation Authority 1350 E. 17 th Street Kansas City, Missouri 64108 REQUEST FOR PROPOSAL (RFP) 18-4016-28A TEMPORARY STAFFING AGENCY SERVICES Issue Date: December
More informationUNDP Procurement. UNDP Angola Procurement
UNDP Procurement The term procurement refers to the process of acquiring goods, works and services. The process spans the whole cycle from identification of needs, choosing the adequate procurement methods,
More informationProgressive Design Build
Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract
More informationPURCHASING AGENT 1 GENERAL
PURCHASING AGENT 1 GENERAL This is the recruitment and training level as well as the junior working level for Purchasing Agents and involves routine administrative work in purchasing of limited varieties
More informationAdvanced Tendering Procedures & Bid Evaluation
An Intensive 5 Day Training Course Advanced Tendering Procedures & Bid Evaluation Effective Tendering, Bidding Strategies & Evaluation 10-14 Sep 2017, Dubai 21-MAY-17 This course is Designed, Developed,
More informationConstruction Auditing: Where To Start And How to make It Work For Your Organization. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Auditing: Where To Start And How to make It Work For Your Organization Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International.
More informationMEMORANDUM FOR CHIEF ACQUISITION OFFICERS SENIOR PROCUREMENT EXECUTIVES. Improving the Management and Use of Interagency Acquisitions
EXECUTIVE OFFICE OF THE PRESIDENT OFFICE OF MANAGEMENT AND BUDGET WASHINGTON, D.C. 20503 OFFICE OF FEDERAL PROCUREMENT POLICY June 6, 2008 MEMORANDUM FOR CHIEF ACQUISITION OFFICERS SENIOR PROCUREMENT EXECUTIVES
More informationIntegration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business Case Contract Enterprise environmental factors Project charter Expert judgement 26/02/2013 18:22:56 1 2
More informationPREPARE, CREATE & GO!
CRITICAL SUCCESS FACTORS IN eprocurement SOFTWARE ADOPTION PREPARE, CREATE & GO! BY ANTHONY FLYNN 3 Steps to an Effective RFQ Request for Quotation Whitepaper Series CONTENTS Request For Quotation Getting
More informationALTERNATE FORMS OF PROJECT DELIVERY
ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors
More informationTerms and Definitions Commonly Used in Technical Proposals
Terms and Definitions Commonly Used in Technical Proposals Note: Terms and definitions provided reflect commonly used terminology for software procurement and may not reflect the terminology utilized by
More informationManaging Contingent Labour
Managing Contingent Labour Presentation Title Nicole Morton HCM Practice Lead, Plaut SPEAKER NAME Mark Job Title, Dyson Organisation HCM Solution Architect, MMG 2 Main Message. Managing contingent labour
More informationChapter 30 Central Services Processes to Use Consultants 1.0 MAIN POINTS
Chapter 30 Central Services Processes to Use Consultants 1.0 MAIN POINTS The Ministry of Central Services (Ministry) uses the services of consultants to help achieve its goals. For the 16-month period
More informationOFFICE OF BUSINESS AND SUPPORT SERVICES Summary of State Board of Education Agenda Items November 13-14, 2007
OFFICE OF BUSINESS AND SUPPORT SERVICES Summary of State Board of Education Agenda Items November 3-4, 2007 OFFICE OF HEALTHY SCHOOLS Office of Child Nutrition D. to accept procurement authorization from
More informationPMP MOCK EXAMS BASED ON PMBOK 5TH EDITION
PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are
More informationWhat is PMP Certification exam? PMP stands for Project Management Professional certification exam. PMP, is one of the most respected and globally recognized certification is offered by the Project Management
More informationDefinitions. Group Purchasing Services Private for-profit or not-for-profit organizations that purchase goods and services on behalf of members.
Definitions Competitive Proposal* - i.e., a Request for Proposal (RFP), means a method of procurement whereby a technical proposal is solicited that explains how the prospective contractor will meet the
More informationBusiness Opportunities. and Insurance Board. with the Workplace Safety. Becoming a WSIB Supplier
Business Opportunities with the Workplace Safety and Insurance Board Becoming a WSIB Supplier Business Opportunities with the Workplace Safety and Insurance Board If you are interested in becoming a WSIB
More informationProject Management CSC 310 Spring 2018 Howard Rosenthal
Project Management CSC 310 Spring 2018 Howard Rosenthal 1 Notice This course is based on and includes material from the text: A User s Manual To the PMBOK Guide Authors: Cynthia Stackpole Snyder Publisher:
More informationIBM Emptoris Strategic Supply Management on Cloud
Service Description IBM Emptoris Strategic Supply Management on Cloud This Service Description describes the Cloud Service IBM provides to Client. Client means the company and its authorized users and
More informationBest Practices in Public Procurement
Best Practices in Public Procurement 1 Learning Objectives Overview of Procurement Facts Understanding Procurement Chain Procurement Planning Risk Management Ethics, Probity and Accountability The new
More informationINCORPORATING SERVICES PROCUREMENT INTO A TECHNOLOGY SOLUTION AN SAP FIELDGLASS WHITEPAPER
INCORPORATING SERVICES PROCUREMENT INTO A TECHNOLOGY SOLUTION AN SAP FIELDGLASS WHITEPAPER Services procurement is a large, growing area of spend at many organizations and encompasses a variety of engagement
More informationThe Procurement and Supply Manager s Desk Reference
The Procurement and Supply Manager s Desk Reference The Procurement and Supply Manager s Desk Reference Second Edition FRED SOLLISH, MS JOHN SEMANIK, MBA John Wiley & Sons, Inc. Copyright 2012 by John
More informationWEST VIRGINIA PURCHASING DIVISION 2017 In-House Training Program
WEST VIRGINIA PURCHASING DIVISION 2017 In-House Training Program REGISTRATION FORM & Name of Participant: Job Title: Agency / Organization: Address / City: E-mail Address: Telephone: All In-House Training
More informationTEXAS BOARD OF NURSING CONTRACT PROCUREMENT AND MANAGEMENT HANDBOOK JULY 2018
TEXAS BOARD OF NURSING CONTRACT PROCUREMENT AND MANAGEMENT HANDBOOK JULY 2018 I. Introduction a. Purpose i. All staff involved with procuring goods and services for the agency must comply with proper purchasing
More informationHow to Order Software Using DoD ESI Contract Vehicles
DoD ESI White Paper How to Order Software Using DoD ESI Contract Vehicles Practical guidance for the most common ordering scenarios in DoD May 2015 About DoD ESI The DoD ESI was formed in 1998 by Chief
More informationThe PM's Role in Capturing, Bidding, and Winning Performance-Based Contracts
The PM's Role in Capturing, Bidding, and Winning Performance-Based Contracts P R E S E N T E D BY: D R. J O H N G. P I C A R E L L I, P R E S I D E N T B U S I N E S S D E V E LO P M E N T A S S O C I
More informationCompiled by Rajan Humagai
Compiled by Rajan Humagai www.pavementengineering.com.au Project Processes Inputs, Tools & Techniques and Outputs. (Based on PMBOK 5 th Edition) 1. Project Integration 1. Develop 1. Project Statement Of
More informationPURCHASING AND PROCUREMENT OVERVIEW
Purchasing and Procurement Overview AASBO Certificate Program September 2018 David Smith Executive Director david@aasbo.com 256 585 1511 PURCHASING AND PROCUREMENT OVERVIEW Contract Procurement Law Understanding
More informationClick to edit Master title style
Click to edit Master title style Click to edit Master text styles Second level Third level Fourth level» Fifth level Contractor Performance Information: Key to the DoD s Superior Supplier Program Click
More informationProcurement Documents for Progressive Design-Build Projects
Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model
More informationACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY
ACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY Academy of Natural Sciences Purchasing Policy Overview This policy framework is intended to provide for the procurement of goods and services
More informationThe Role of the IGCE in Source Selection. Cobec Consulting Annette Barlia, Senior Consultant
The Role of the IGCE in Source Selection Cobec Consulting Annette Barlia, Senior Consultant Table of Contents Objective Background Defining the Independent Government Cost Estimate (IGCE) Acquisition Process
More information