ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY

Size: px
Start display at page:

Download "ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY"

Transcription

1 THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 5 LAST MODIFIED 2 December 2010 DATE PRINTED RIBA stages JK JK 5 ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY 1. DEFINITION 1.1 PRACTICAL COMPLETION Practical Completion is considered to be the point at which a building contract is considered practically complete by the Architect or Contract Administrator. This would normally occur when there are few, if any, significant defects or snagging items remaining and all critical test and completion certificates have been received. 1.2 HANDOVER Handover of the building from the main contractor to the University can take place only when the Practical Completion Certificate has been issued. This does not however mean that the building is necessarily ready for occupation as this will be dependant on the extent of any fit out works still to be undertaken e.g. furniture supply, audio-visual etc. 2. PURPOSE The issue of the Certificate of Practical Completion is a key stage in a building contract. At this point, the University will take possession of and adopt responsibility for the all the areas of the building works as detailed on the Certificate of Practical Completion. 3. PROCEDURE The Certificate of Practical Completion is issued only when, in the opinion of the Architect as Contract Administrator, the works (or part of the works in a phased or sectional completion) have reached a state of Practical Completion as defined in 1.1 above. For the works to be considered practically complete, all of the construction work that has to be undertaken must be complete. However, the Certificate of Practical Completion may still be issued where: There are a only few very minor items of work left incomplete There may be latent defects (the defects liability period allows previously undiscovered defects to be remedied) It should not be issued if there are significant patent defects outstanding or any key completion and / or test certificates are not concluded. If the University takes possession of the site prior to issue of the Certificate of Practical Completion, this action will automatically trigger practical completion contractually even though it may not have been formally certified. Page 1 of 6

2 3.1 ISSUE OF THE CERTIFICATE OF PRACTICAL COMPLETION Issuing the Certificate of Practical Completion is a process that requires careful planning and procedures and can determine whether or not the project is regarded as successful or not by its stakeholders. It gives rise to a number of events within a construction contract, which are as follows: The Contractor s liability ends for the following: o Insurance o Damage to the completed works o Damage to the building by frost o Any further liquidated damages o Conclusion (depending on terms) of guarantees and performance bonds End of sub-contractors protection: o Issue of the Certificate of Practical Completion may bring to an end subcontractor s protection under the Main Contract all risks insurance policy The University takes possession of the building and is required to: o Insure the building (risk of damage to the works and third party liability, see para. 3.3 below) o Release retention money to the Contractor (normally half) No further instruction may be issued o No variations / rectifications to the works other than those appearing during the defects liability period unless with the agreement of the main contractor. Defects liability period commences o The Certificate stands as the latest date from which the limitation period for claims will start to run. 3.2 FAILURE TO COMPLETE THE WORKS BY COMPLETION DATE Where the Contractor fails to complete the Works by the due date, this may give rise to a claim for liquidated damages. In this case, the Contract Administrator will issue a Certificate of Non-completion as well as ensuring that he has addressed any requests from the Contractor for an extension of time. If the University wishes to deduct liquidated damages from any sums due to the Contractor, the University must give notice to the Contractor of its intention to do so, no later than the issue of the Final Certificate. 3.3 UNIVERSITY PREPARATION FOR TAKING OVER THE BUILDING There are various agreements and procedures that the University of Edinburgh must undertake associated with practical completion and handover. The Project Management Team should ensure that the following are actioned early to avoid delay to the project programme. Template T59a should be filled in and signed off. Refer to template T59a End of Stage K Checklist Page 2 of 6

3 These are: Set up insurances: o On issue of the Certificate of Practical Completion, the Contractor s insurances cease (except with a partial or sectional completion). o The Project Management Team should liaise with University s Insurance office to ensure that the appropriate user / tenant insurances are set up in plenty of time to ensure that no period is uninsured. Refer to procedure FGH 6 Consider Insurances Arrange University Fit-out: o Make arrangements for the fit out of all University provided equipment, e.g. AV equipment, soft services o Make arrangement for the delivery and installation of any equipment not included within the Main Contract. Refer to procedure L1 Manage University fit-out Arrange access for completion of minor construction works: o Agree arrangements for access for the Contractor; this might include for rectifying defects, testing of services etc. Arrange for inspection by relevant funding and/or licensing bodies: o Parts of the building may require to be inspected to gain a special license to function or for grant money to be paid o Either may be dependent on the completion of a particular aspect of the works. 3.4 PRE-HANDOVER MEETING A minimum of two formal meetings will be required to achieve Sign-off and the issue of the Certificate of Practical Completion and Building Handover. The first of these is the Pre-handover meeting. Pre-handover meeting: Two to three weeks before the Certificate of Practical Completion is issued, the Project Management Team should arrange a pre-handover meeting to discuss and hopefully agree acceptance of the building by the University and its occupation by the Users. Refer to template T62 for pre-handover meeting Agenda Part of the purpose of arranging this meeting is to ensure that the Architect, Design Team and other consultants, client (represented by the Project Administrator), Project Management Team and Clerk of Works undertake pre-completion checks (as far as is possible by visual inspection) that the work complies with the contract requirements. They will report on these at the meeting. The following parties should be invited: Project Administrator Contractor s representative Architect and Design Team representatives Premises Manager Representatives from University Services Departments as appropriate, e.g. Security, phones, fire, AV controls, health and safety, support services, grounds maintenance Page 3 of 6

4 Clerk of Works Any other relevant parties, e.g. specialist advisors Meeting arrangements: The meeting should be arranged two to three weeks before the programmed date for Practical Completion and will be held on site. The Project Management Team should give at least two weeks notice of the date of the meeting to all parties to allow them to review the project beforehand, and undertake the necessary checks The meeting will be chaired by the Project Management Team and minuted by the Architect The Architect will circulate minutes of the meeting to all those who were invited. 3.5 INFORMATION TO BE PROVIDED BY THE MAIN CONTRACTOR Prior to the Pre-handover meeting, the Contractor must first of all confirm completion of the building by the programmed completion date. The Contractor should then provide the following information, with the aim of handing over a fully functioning and commissioned building: O and M manuals, CDM Health and Safety File containing: As-built drawings Equipment manuals Specifications Test certificates for lifts, fire alarms, security alarms and all M & E systems: Completed installations must be in full working order for proving and test certificates provided where appropriate. Although installations must be commissioned before handover, it may not be possible to complete this work until these installations have been in use for a period of time. Commissioning reports for mechanical systems, fume cupboards, safety cabinets and the like: Depending on the complexity of the installation, commissioning and witnessing may need to be undertaken by specialists and effectively managed to a commissioning specification and system Generally on a major project, all systems, equipment, plant and parts of systems should be witnessed. On a minor project, 10% of tests should be witnessed Even when specialist consultants need to be involved, the Contractor still has responsibility for overall programming and ensuring that the works are complete and functioning by the contract completion date. Master keys and specified numbers of copy keys, key schedules: These should be clearly labelled - and all similar items for the handover of the building also provided. Refer to procedure L2 Manage Key Suiting Strategy Page 4 of 6

5 3.6 DEMONSTRATIONS Following commissioning of the various installations / items of equipment, separate demonstrations need to be arranged by the Architect for the following groups: Design Team and specialist consultants Estates and Buildings Building users The Architect should liaise with the Project Management Team to ensure that all the appropriate people are invited to each demonstration. The following templates should be filled in and signed off: Template T59b end of Stage K Checklist Main Contractor demonstration to Design Team & Certificate Confirmation Schedule Template T59c End of Stage K Checklist - Estates & Buildings Demonstration Schedule 3.7 DEFECTS LIST Any defects noted by the Clerk of Works and/or the Users or anyone involved in the project should be passed to the Design Team (Architect) and copied to the Project Management Team. The Architect as Contract Administrator is responsible for preparing the definitive defects list and issuing it to the Main Contractor. Note: there must be only one definitive defects list. Prior to the final handover meeting, the Architect will review the defects list to ascertain how many remain unresolved. It is the Architect s responsibility as Contract Administrator to decide whether it is appropriate to issue the Certificate of Practical Completion or not. 3.8 FINAL HANDOVER MEETING All outstanding matters identified in the Pre-handover meeting (see paragraph 3.4 above) should have been attended to before the Final Handover meeting. If there are still a number of outstanding matters to be resolved, Practical Completion and Handover may not be possible and in this case, the handover meeting will require to be reconvened. It should be noted that the final handover meeting is a formal meeting whereby the University Department of Estates and Buildings formally accepts the building on behalf of the Project Sponsor. Note: The Users do not accept the building. Refer to template T63 for Handover Meeting Agenda Prior to Final Handover Meeting and issue of Certificate of Practical Completion: The Architect should write to the University s Project Management Team, confirming that, in his/her opinion, the Certificate of Practical Completion (or sectional completion) can be issued and that so doing will have the following implications: The defects liability period will now commence The University should now set up the necessary insurances and reach agreement on responsibility for insurance in the case of a partial / phased practical completion. The Project Management Team will convene the Final Handover meeting with the following arrangements: Page 5 of 6

6 Same invitees as for the pre-meeting (see paragraph 3.4 above) The meeting arranged for the date of the issue of the certificate of Practical Completion Liaison between all parties as necessary before the meeting to ensure that all outstanding matters are cleared The meeting to be held on site chaired by the Project Management Team and minuted by the Architect. Date for the defects liability inspection to be agreed. The Architect to issue the draft schedule of defect to the Contractor A programme for undertaking the remedial work to be agreed with the Project Management Team and Users. 4. OUTPUT Following the Final Handover meeting, the output will be as follows: 4.1 CERTIFICATE OF PRACTICAL COMPLETION There are several types of Completion Certificate that the Contract Administrator is obliged to issue, all of which must be signed and dated. These are: Practical completion of the Works Statement of partial possession (where applicable) Practical completion for sectional completion (where applicable) 4.2 FORMAL HANDOVER Formal handover will be achieved in nearly all cases, including where there is sectional completion or partial possession. The outcome is: Certificate of Practical Completion, filed in project file ref. L.18.9 Completed and signed templates T59a, T59b and T59c Handover and Demonstration checklists, filed with the completion certificate Acceptance by the University of the building following the issue of the Practical Completion Certificate. Keys handed over Building maintenance information handed over Meters to be read and other use of fuel(s) noted and quantified. A date to be arranged for the defects liability inspection and a programme agreed for rectifying defects. Page 6 of 6

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main

More information

STRUCTURAL ENGINEER S SERVICES SCOPE

STRUCTURAL ENGINEER S SERVICES SCOPE ROYAL BOROUGH OF GREENWICH STRUCTURAL ENGINEER S SERVICES SCOPE WOOLWICH CREATIVE DISTRICT PROJECT status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: Nick

More information

AB 14 ISSUE/REVISION LAST MODIFIED 15 November 2012 DATE PRINTED

AB 14 ISSUE/REVISION LAST MODIFIED 15 November 2012 DATE PRINTED THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT 14 ISSUE/REVISION LAST MODIFIED 15 November 2012 DATE PRINTED RIBA stage 14 ESTLISH HEALTH AND SAFETY STRATEGY 1. DEFINITION The Construction

More information

MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE

MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE ROYAL BOROUGH OF GREENWICH MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE PROJECT xxx status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: role: signed:

More information

The purpose of the fit-out is to equip the facility as required to enable occupation by the users.

The purpose of the fit-out is to equip the facility as required to enable occupation by the users. THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION L 1 LAST MODIFIED 02 March 2011 DATE PRINTED RIBA stage L 1 MANAGE UNIVERSITY FIT-OUT 1. DEFINITION The issue of the Certificate

More information

JOB DESCRIPTION. To provide technical expertise and project support across the full range of Hanover s asset management projects.

JOB DESCRIPTION. To provide technical expertise and project support across the full range of Hanover s asset management projects. Hanover (Scotland) Housing Association Ltd Position: Clerk of Works Department: Asset Management Reports to: Contracts Supervisor Band: F Date: May 2016 Purpose of Job JOB DESCRIPTION To provide technical

More information

Project monitor services

Project monitor services Corporate Professional Local Project monitor services For use with the RICS Short form of consultant s appointment The mark of property professionalism worldwide www.rics.org Project Monitor Services For

More information

AB 14. RIBA stage AB AB 14 ESTABLISH HEALTH AND SAFETY STRATEGY 1. DEFINITION 2. PURPOSE

AB 14. RIBA stage AB AB 14 ESTABLISH HEALTH AND SAFETY STRATEGY 1. DEFINITION 2. PURPOSE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION 14 LAST MODIFIED 19 November 2010 DATE PRINTED 14 ESTLISH HEALTH AND SAFETY STRATEGY 1. DEFINITION The Construction (Design

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM20 Construction Project Completion & Procedure Document originated: July 2016 By: PSU Issue number: 1 No of pages: 18 Approved

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM20 Construction Project Completion & Procedure Document originated: July 2016 By: CSU Issue number: 1 No of pages: 19 Approved

More information

Table of Contents. Project Agreement Schedule 14

Table of Contents. Project Agreement Schedule 14 Table of Contents PART 1 DEFINITIONS... 3 PART 2 INTEGRATED MANAGEMENT SYSTEM REQUIREMENTS... 6 2.1. Introduction... 6 2.2. Overview... 6 2.2.1 Management System Requirements... 7 2.2.2 Certification...

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

ANNEXURE A SCOPE OF WORK FOR PROFESSIONAL SERVICES: RESTORATION OF NON PAREILLE BUILDINGS. Principal Agent and Professional Architectural Services

ANNEXURE A SCOPE OF WORK FOR PROFESSIONAL SERVICES: RESTORATION OF NON PAREILLE BUILDINGS. Principal Agent and Professional Architectural Services T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 ANNEXURE A SCOPE OF WORK FOR

More information

ESTATES SERVICES. Soft Landings An Introduction

ESTATES SERVICES. Soft Landings An Introduction ESTATES SERVICES Soft Landings An Introduction 2013 Capital Projects - Context Capital projects have responsibility for all new major build and refurbishment projects A major project is a project with

More information

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management Manage project completion and handover in built environment design Overview This unit applies to designers who are engaged in projects at site level at the handover stage and who are responsible for completing

More information

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1.

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1. PROBUILD SUBCONTRACTOR QUALITY MANAGEMENT GUIDE Section Two Project Specific Quality Management Plans Version No 1. PREFACE This document has been developed to assist subcontractors to meet Probuild s

More information

Webinar Project Close Out. December 14, 2017 / 10:00 - Noon

Webinar Project Close Out. December 14, 2017 / 10:00 - Noon Welcome to Project Close Out We will begin shortly. (for higher quality, dial a number based on your current location) To listen to this webinar: 1.669.900.6833 or + 1.408.638.0968 Access Code: 393.375.631

More information

Capability health procedure for academic support staff

Capability health procedure for academic support staff Capability health procedure for academic support staff Policy The School's policy in relation to sickness absence is to support employees by paying sick pay and investigating absence in conjunction with

More information

HANDOVER TAKEOVER REQUIREMENTS

HANDOVER TAKEOVER REQUIREMENTS THE AUSTRALIAN NATIONAL UNIVERSITY FACILITIES & SERVICES HANDOVER TAKEOVER REQUIREMENTS 2 FACILITIES INSPECTION CHECKLIST Project Number: Project Name: Project Location: Description: Building Number(s):

More information

The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings:

The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: GRAVESEND CAMPUS 1.0 LEARNING & SKILLS COUNCIL 1.1 Application In Principle The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: Gravesend Campus;

More information

CONSTRUCTION MANAGER

CONSTRUCTION MANAGER The South African Council for the Project and Construction Management Professions CONSTRUCTION MANAGER IDENTIFICATION OF WORK AND SCOPE OF SERVICES FOR CONSTRUCTION MANAGERS REGISTERED IN TERMS OF THE

More information

BAFE SP203-1 Assessment Check List

BAFE SP203-1 Assessment Check List BAFE SP203-1 Assessment Check List To be Read in conjunction with BAFE SP203-1 Version 5 May 2011 General A minimum of 2 projects, with all relevant documentation and certification are available for review.

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions

APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions The South African Council for the Project and Construction Management Professions (SACPCMP) Registration

More information

Architectural Design and Build Process. A Client Guide

Architectural Design and Build Process. A Client Guide Architectural Design and Build Process A Client Guide This guide has been prepared to summarise the various stages of a new-build residential design & construction process. It identifies important tasks

More information

Phase 1. Snagging phase (pre-finish stage)

Phase 1. Snagging phase (pre-finish stage) There are three phases to completing a path construction project, which are: Phase 1. Snagging phase (pre-finish stage) A week or two before the projects due to finish hold a snagging meeting to inspect

More information

Building Terms & Construction Jargon Explained. CLPM Glossary of Terms

Building Terms & Construction Jargon Explained. CLPM Glossary of Terms Building Terms & Construction Jargon Explained Building terms and construction jargon can be bewildering! If you are busy carrying out research for your building project, you ve probably already been bombarded

More information

Urzgan Rural Access Program

Urzgan Rural Access Program 00083939 Urzgan Rural Access Program Rehabilitation of Gravel Road from Surkhliz to Chinartu, Ch. (18+000-27+000)km in Urzgan Province of Afghanistan Lot 3 United Nations Office for Project Services (

More information

Pos Service Holland (SA) Pty Limited

Pos Service Holland (SA) Pty Limited 1. Definitions 1.1 In these general conditions it is understood under: Supplier: Customer: Pos Service Holland (SA) Pty Ltd T/A PSH-SA Every natural or legal person with whom supplier negotiates concerning

More information

CONTENTS. Quality Policy Statement. Managing Invitations to Tender. Rev 9

CONTENTS. Quality Policy Statement. Managing Invitations to Tender. Rev 9 QUALITY PLAN CONTENTS Section 1 Section 2 Section 3 Section 4 Section 5 Quality Policy Statement Quality System Managing Invitations to Tender Design and Drawings Contract Management Section 1 Quality

More information

Code of Conduct for Members of The Federation of Master Builders Limited

Code of Conduct for Members of The Federation of Master Builders Limited Code of Conduct for Members of The Federation of Master Builders Limited Code of Conduct for Members Members of the Federation of Master Builders (FMB) agree to comply with the requirements of the Code

More information

MODEL TUPE POLICY AND PROCEDURE FOR SCHOOLS / ACADEMIES

MODEL TUPE POLICY AND PROCEDURE FOR SCHOOLS / ACADEMIES MODEL TUPE POLICY AND PROCEDURE FOR SCHOOLS / ACADEMIES This model policy will apply to both teaching and non-teaching staff and has been agreed with the following recognised unions: ATL, NUT, NAHT, NASUWT,

More information

Maintenance for Building Services

Maintenance for Building Services A BSRIA Guide www.bsria.co.uk Maintenance for Building Services How to acquire maintenance services contracts By Jo Harris BG 3/2008 BG 3-2008 (Maintenance contracts) cover 6.p653 06/06/2008, 09:26 ACKNOWLEDGEMENTS

More information

Position Description: Site Supervisor Reports to: Site Manager/Project Manager

Position Description: Site Supervisor Reports to: Site Manager/Project Manager Position Description: Site Supervisor Reports to: Site Manager/Project Manager Overall Responsibilities Direct onsite supervision of staff and subcontractors. Application of knowledge, skills, tools, and

More information

Building Standards Customer Journey

Building Standards Customer Journey Building Standards Customer Journey Are you doing building work or home improvements? If so, this guide is for you. Building Standards Customer Journey Contents 2 Contents Building Standards Customer Journey

More information

Contractor safety for schools and services. Guidance

Contractor safety for schools and services. Guidance Health and safety services Health and safety services Contractor safety for schools and services Guidance Updated September 2008 and amended March/May 2009 Contents 1.0 Planning the work 1.1 Minor alterations

More information

SCHOOL GRIEVANCE POLICY EVENLODE PRIMARY SCHOOL

SCHOOL GRIEVANCE POLICY EVENLODE PRIMARY SCHOOL SCHOOL GRIEVANCE POLICY EVENLODE PRIMARY SCHOOL December 2014 Review January 2016 School Grievance Policy December 2014 Page 1 EVENLODE PRIMARY SCHOOLGRIEVANCE PROCEDURE 1. PURPOSE 1.1 To establish a procedure

More information

RIBA Small Project Plan of Work

RIBA Small Project Plan of Work Small Project www.ribaplanofwork.com www.ribaplanofwork.com Small Project 1 Foreword In 2013 the published a major overhaul to the to help our members respond to the technical and procedural developments

More information

Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015)

Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015) Alcester Academy To be the best that we can be Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015) ALCESTER ACADEMY MANAGING CONTRACTORS POLICY REVIEW PROCEDURES The Managing Contractors

More information

Implementing EC Regulation 1071/2009 Rules Concerning the Occupation of Road Transport Operator

Implementing EC Regulation 1071/2009 Rules Concerning the Occupation of Road Transport Operator Implementing EC Regulation 1071/2009 Rules Concerning the Occupation of Road Transport Operator This is the response of the Royal Society for the Prevention of Accidents (RoSPA) to the Department for Transport

More information

QSS 0 Products and Services without Bespoke Contracts.

QSS 0 Products and Services without Bespoke Contracts. QSS 0 Products and Services without Bespoke Contracts. Use: Typically Sub 50k processes without a bespoke contract. Amendment History Version Date Status V3 June 2018 Updated for 2018 deployment Contents

More information

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE ANNEXURE A T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 SCOPE OF WORK FOR

More information

EYNSFORD PARISH COUNCIL

EYNSFORD PARISH COUNCIL EYNSFORD PARISH COUNCIL FINANCIAL REGULATIONS These Financial Regulations were adopted by the Council at its Meeting held on 20 September 2007, last amended on 20 th July 2017. 1. GENERAL 1.1 These financial

More information

Building Regulations and Fire Safety Procedural Guidance

Building Regulations and Fire Safety Procedural Guidance Building Regulations and Fire Safety Procedural Guidance General Introduction This guide has been prepared for any person with influence over the building s fire safety arrangements, which includes but

More information

JOB DESCRIPTION. Surveyor Stockbridge Village. CESP (Community Energy Saving Programme) Delivery Team Villages Housing

JOB DESCRIPTION. Surveyor Stockbridge Village. CESP (Community Energy Saving Programme) Delivery Team Villages Housing JOB DESCRIPTION POST: SECTION: RESPONSIBLE TO: Surveyor Stockbridge Village CESP (Community Energy Saving Programme) Delivery Team Villages Housing CESP Project Manager / Head of Asset Management Objectives

More information

REVIEW OF SCOTTISH PUBLIC SECTOR PROCUREMENT IN CONSTRUCTION

REVIEW OF SCOTTISH PUBLIC SECTOR PROCUREMENT IN CONSTRUCTION REVIEW OF SCOTTISH PUBLIC SECTOR PROCUREMENT IN CONSTRUCTION Guidance on the use of a baseline skillset for construction procurement 11 October 2017 Page 1 of 21 1. Introduction... 3 2. Extract from the

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

Job Title Quantity Surveyor/Estimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports

Job Title Quantity Surveyor/Estimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports Job Description and Person Specification Job Title Quantity Surveyor/stimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports Other Resources

More information

THE WHARF TERRACES RENOVATIONS POLICY

THE WHARF TERRACES RENOVATIONS POLICY THE WHARF TERRACES RENOVATIONS POLICY Introduction This document has been approved by the Owners Corporation and sets out the policy and procedures owners must follow when they are proposing repairs, refurbishing

More information

The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings:

The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: GRAVESENDCAMPUS 1.0 LEARNING & SKILLS COUNCIL 1.1 Application In Principle The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: Gravesend Campus;

More information

International Standard on Auditing (UK) 220 (Revised June 2016)

International Standard on Auditing (UK) 220 (Revised June 2016) Standard Audit and Assurance Financial Reporting Council June 2016 International Standard on Auditing (UK) 220 (Revised June 2016) Quality Control for an Audit of Financial Statements The FRC is responsible

More information

University of Edinburgh. Engineering Services. Guidelines

University of Edinburgh. Engineering Services. Guidelines University of Edinburgh Engineering Services Guidelines Section 1: General Introduction and Application. Estates and Buildings Works Division Issue: 3 Date: January 2008 Engineering Services Guidelines

More information

Service Level Agreement (SLA) for COMPANY by. Integrity Property Services

Service Level Agreement (SLA) for COMPANY by. Integrity Property Services (SLA) for COMPANY by Effective Date: DATE Document Owner: Version Version Date Description Author 1.0 DATE Natalie Scanlon Approval (By signing below, all Approvers agree to all terms and conditions outlined

More information

Registered as a Scottish Charity - No. SC Job Description

Registered as a Scottish Charity - No. SC Job Description Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Salary: Reports To: Neighbourhood Maintenance Surveyor Assets and Investment Selkirk Grade 8, salary

More information

Design-Build Terminology

Design-Build Terminology Design-Build Terminology This glossary is representative of the terminology used in the design-build community and advocated by the Canadian Design-Build Institute (CDBI). For definitions of contractual

More information

CONSULTANTS FRAMEWORK AGREEMENTS: WALES AND MIDLANDS MAINTENANCE WORKS; EXISTING PROPERTIES. Essential Function Job Summary

CONSULTANTS FRAMEWORK AGREEMENTS: WALES AND MIDLANDS MAINTENANCE WORKS; EXISTING PROPERTIES. Essential Function Job Summary CONSULTANTS FRAMEWORK AGREEMENTS: WALES AND MIDLANDS MAINTENANCE WORKS; EXISTING PROPERTIES. Essential Function Job Summary The Landmark Trust have nearly 200 buildings across the country all maintained

More information

Shaping and sharing best practice in construction health and safety risk management

Shaping and sharing best practice in construction health and safety risk management Shaping and sharing best practice in construction health and safety risk management LEGAL ISSUES: THE CLIENT; COMPETENCE; WELFARE; COLLATERAL WARRANTIES; STATUTORY UNDERTAKERS; TERMINATION; ARCHIVING PROJECT

More information

BUILDING CONTROL (AMENDMENT) REGULATIONS 2013

BUILDING CONTROL (AMENDMENT) REGULATIONS 2013 BUILDING CONTROL (AMENDMENT) REGULATIONS 2013 MIND THE GAP ARCHITECT PRACTITIONER PERSPECTIVE IEI SEMNAR January 2014 Orla Fitz.Gerald MRIAI FCIArb Member COP WG & Architect in Practice Code of Practice

More information

Pre-Construction Conference Discussion Guide

Pre-Construction Conference Discussion Guide Pre-Construction Conference Discussion Guide This guide is a summary of the topics normally required at the Pre-Construction Conference based upon the Tennessee Board of Regents Designers Manual standard

More information

Appendix 3. POLICY & PROCEDURE No

Appendix 3. POLICY & PROCEDURE No DEPARTMENT OF PUBLIC WORKS DIVISION: ENGINEERING SERVICES SECTION: ADMINISTRATIVE PAGE NO: 1 OF 10 REVISION NO: 3 DATE: 1995 05 01 ESTABLISHED: 1986 03 03 Appendix 3 POLICY & PROCEDURE No. 2.3.1-020 TITLE:

More information

CIC Guidelines Preliminary Design

CIC Guidelines Preliminary Design Version 1.0 / August 2016 Stage 3 of 8 Approval: Of previous stage, design documentation, updated programme and cost plan. List matters from previous stage to be addressed in current stage. Documentation:

More information

MGD 001. Guidance Document for MCS 001. Version 1.0

MGD 001. Guidance Document for MCS 001. Version 1.0 MGD 001 Guidance Document for MCS 001 Version 1.0 This Microgeneration Installation Standard is the property of Department of Energy and Climate Change (DECC), 3 Whitehall Place, London,SW1A 2HH. DECC

More information

Company QESH Management Representative

Company QESH Management Representative PROJECT MANAGEMENT Page: 1 of 8 PROJECT MANAGEMENT ISSUE STATUS Issue Date: 11-04-2016 Issued for Use Revision Date: 05-06-2017 Revision No.: 1 Action Position Issued By: Reviewed By: Reviewed By: Approved

More information

Solihull Metropolitan Borough Council. Corporate Health and Safety Policy For Core Council Staff. September 2015

Solihull Metropolitan Borough Council. Corporate Health and Safety Policy For Core Council Staff. September 2015 Solihull Metropolitan Borough Council Corporate Health and Safety Policy For Core Council Staff Version Control: September 2015 Version Date Author Sent to Reason 1.1 June 2015 Steve Dean ( Health and

More information

CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016)

CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016) Document title ICE Health & Safety Expert Panel: CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016) Introduction The following questions and answers have been put together

More information

MINUTES OF PRE-BID CONFERENCE. INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No:

MINUTES OF PRE-BID CONFERENCE. INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No: I. Background MINUTES OF PRE-BID CONFERENCE INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No: 35-46214 The United Nations Development Programme (UNDP) would

More information

Building Control (Amendment) Regulations MBCA Guidance Document

Building Control (Amendment) Regulations MBCA Guidance Document Building Control (Amendment) Regulations 2014 Contents 1. Introduction 4 2. Legislative Background 5 3. Definitions 6 4. Process 7 5. Documents at tender stage 8 6. Building Control Management System 9

More information

ABSENCE MANAGEMENT POLICY: ABSENCE THROUGH ILLNESS

ABSENCE MANAGEMENT POLICY: ABSENCE THROUGH ILLNESS 18. ABSENCE MANAGEMENT POLICY: ABSENCE THROUGH ILLNESS This section is for information only and does not form part of your contract of employment with the College. The procedures and rules however must

More information

CIC Guidelines Procurement

CIC Guidelines Procurement Version 1.0 / August 2016 Stage 6 of 8 Approval: Of previous stage design documentation, updated programme and cost plan. List matters from previous stage to be addressed in current stage. Documentation:

More information

Local Rule: Engaging External Service Providers

Local Rule: Engaging External Service Providers Local Rule: Engaging External Service Providers 1. Significant Hazards Engaging incompetent Service Providers, failing to exchange appropriate health and safety information with them failing to adequately

More information

BRITISH COLUMBIA CERTIFIED PROFESSIONAL PROGRAM PRACTICE AND PROCEDURE MANUAL

BRITISH COLUMBIA CERTIFIED PROFESSIONAL PROGRAM PRACTICE AND PROCEDURE MANUAL BRITISH COLUMBIA CERTIFIED PROFESSIONAL PROGRAM PRACTICE AND PROCEDURE MANUAL Edition #1 August 3, 2015 Table of Contents List of Tables and Figures... 4 List of Attachments... 4 List of Abbreviations...

More information

Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16

Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16 Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16 Yorkshire Water Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16 2 Contents

More information

Robert Smyth Academy

Robert Smyth Academy Robert Smyth Academy Grievance Procedure for Employees 1. Purpose 2. Scope This procedure is designed to: a) assist the Principal and Governors with their responsibility to ensure consistent and fair treatment

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

This part of the Works Information sets out the obligations of the Contractor with regards to:

This part of the Works Information sets out the obligations of the Contractor with regards to: Works Information Volume 2B Part 13 Assurance, Records and Certification Part 13 Assurance, Records and Certification 13.1 Introduction The Contractor self-certifies the quality of the works. This part

More information

Submission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit

Submission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit Building Code The Florida State University Building Code Administration Program (BCA) was established in 2001 and is responsible for ensuring that all construction activities on FSU owned facilities are

More information

Ealing Schools. Medical Capability Procedure

Ealing Schools. Medical Capability Procedure Ealing Schools Medical Capability Procedure April 2009 Summary Medical Capability Procedure The aim of this procedure is to provide fair and effective arrangements to support schools in managing sickness

More information

List of Financial Regulations

List of Financial Regulations HEPTONSTALL PARISH COUNCIL FINANCIAL REGULATIONS List of Financial Regulations 1. General 25 2. Annual Estimates 25 3. Budgetary Controls 25 4. Accounting and Audit 26 5. Banking Arrangements and Cheques

More information

Invitation to Tender. External Audit Services. July 2015

Invitation to Tender. External Audit Services. July 2015 External Audit Services July Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 4 1.5. Copyright...

More information

Legionella Procedure. Document Control. Date of next Review. Revision No. Publication on Web Site. Date Document Reviewed. Summary of main changes

Legionella Procedure. Document Control. Date of next Review. Revision No. Publication on Web Site. Date Document Reviewed. Summary of main changes Document Control Revision No. Date Document Reviewed Publication on Web Site Date of next Review Summary of main changes Draft May 2017 New version of document 1 May 2017 May 2017 May 2018 Update of document

More information

Quality Assurance Manual

Quality Assurance Manual Quality Assurance Manual Current Electrical is committed to leading the market in satisfying customer needs by providing versatile and innovative electrical and control solutions We take pride in the ability

More information

Management of Contractors Procedure

Management of Contractors Procedure Management of Contractors Procedure Version Control Sheet Version Date Reviewed By Revision Details 1.0 28/08/2015 Louise Newsham Changes to job titles and roles. Reviewed to include recent legislative

More information

Structural Engineering & Civils Scope of Services

Structural Engineering & Civils Scope of Services Structural Engineering & Civils Scope of Services 1.0 General The scope of services set out below is indicative and are not intended to be exhaustive. This scope of service should be read in conjunction

More information

LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP

LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PMO-RALG ENHANCEMENT OF PROCUREMENT CAPACITY OF LOCAL GOVERNMENT AUTHORITIES PROJECT (EPC LGAP) LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PROCUREMENT COMPLIANCE & PERFORMANCE AS PER

More information

C2.15 Completion, Testing, Commissioning and Taking Over including Release of payment thereon

C2.15 Completion, Testing, Commissioning and Taking Over including Release of payment thereon C2.15 Completion, Testing, Commissioning and Taking Over including Release of payment thereon C2.15.1 Responsibility Centre : Execution Site in association with Commissioning Team (wherever commissioning

More information

JOB DESCRIPTION. 1. JOB TITLE: Estates Manager 2. HRMS REFERENCE NUMBER: HRMS/ ROLE CODE: 4. DEPARTMENT: Facilities Management

JOB DESCRIPTION. 1. JOB TITLE: Estates Manager 2. HRMS REFERENCE NUMBER: HRMS/ ROLE CODE: 4. DEPARTMENT: Facilities Management JOB DESCRIPTION 1. JOB TITLE: Estates Manager 2. HRMS REFERENCE NUMBER: HRMS/11065 3. ROLE CODE: 4. DEPARTMENT: Facilities Management 5. ORGANISATION CHART: 6. JOB PURPOSE: The University of Chester wishes

More information

Contract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services

Contract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services Contract Administration: Tips for Improving your Contract Administration Process Jennifer Adling Director of Procurement Services Contract Administration Following the award of a contract, the management

More information

CIC Guidelines Construction Administration and Observation

CIC Guidelines Construction Administration and Observation Version 1.0 / August 2016 Construction Administration Stage 7 of 8 Approval: To commence post-contract award activities. Documentation: From previous stage that forms the basis of the ongoing design. Approval:

More information

Superseded. JCLI Practice Note No 8. May 2008

Superseded. JCLI Practice Note No 8. May 2008 JCLI Practice Note No 8 JCLI Practice Note No 8 May 2008 Notes This JCLI Practice Note No 8 supersedes No 1 issued April 1978, No 2 issued April 1982, No 3 issued April 1985 (and all subsequent revisions),

More information

Privacy Policy of Townsville Motor Boat & Yacht Club Limited - Liquor Licence Number 84145

Privacy Policy of Townsville Motor Boat & Yacht Club Limited - Liquor Licence Number 84145 Privacy Policy of Townsville Motor Boat & Yacht Club Limited - Liquor Licence Number 84145 Application The Privacy Policy applies to personal information collected by the club, as the club is an applicable

More information

Privacy Policy of Brothers Leagues Club Ipswich Inc. Community Club Licence No

Privacy Policy of Brothers Leagues Club Ipswich Inc. Community Club Licence No Privacy Policy of Brothers Leagues Club Ipswich Inc. Community Club Licence No. 80331. Application The Privacy Policy applies to personal information collected by the club, as the club is an applicable

More information

should include the allocation of responsibilities and not appoint or instruct an independent surveyor to

should include the allocation of responsibilities and not appoint or instruct an independent surveyor to 01 Introduction The asbestos survey guide, HSG 264, provides guidance on asbestos surveys and sampling for asbestos in non domestic premises including the common parts of domestic premises. The key areas

More information

TECHNICAL SERVICES HANDOVER OF WORKS (FOR TSD INTERNAL PROJECT)

TECHNICAL SERVICES HANDOVER OF WORKS (FOR TSD INTERNAL PROJECT) Page 1 of 8 CHECK LIST FOR: Stage 1 Handover for Operation Stage 2 Completion of Defects Liability Period Stage 1 Sign off Completion Certificate * Overall Recommendation to GM, TS Stage 2 Sign off Defects

More information

FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC

FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC Form of Appointment Shaping and sharing best practice in construction health and safety risk management FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC 2011) Under the Construction (Design and

More information

Attachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #

Attachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone # UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial

More information

A62 PRE-CONSTRUCTION MEETING AGENDA

A62 PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

As a state agency, the College administration is required to develop procedures for Construction Manager selection.

As a state agency, the College administration is required to develop procedures for Construction Manager selection. COLLEGE of CENTRAL FLORIDA ADMINISTRATIVE PROCEDURE Title: Construction Management Selection Process Page 1 of 2 Implementing Procedure For F.S. 1013.45 Date Approved: 09/11/02 Division: Administration

More information

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015 1.0 Summary of Changes 1.1 This is a new joint procedure/sop for Essex Police and Kent Police. 2.0 What this Procedure is about 2.1 This document identifies how Essex Police and Kent Police shall manage

More information

Job Description Clerk of Works

Job Description Clerk of Works Job Description Clerk of Works Job Grade: SO2 Date Last Evaluated: Directorate: Department/Section: Reports to: Responsible for: Asset Management Employers Agent Project Manager - Employer s Agent None

More information

Job Description. Major Works Planning and Delivery Manager Salary SCP Staffing responsibilities

Job Description. Major Works Planning and Delivery Manager Salary SCP Staffing responsibilities Job Description Position Adaptations Project Manager Department/ Location Housing Options Reports to Major Works Planning and Delivery Manager Salary SCP 38-41 Staffing responsibilities (1 x Administrator;

More information