Facilities Study. For. XXXXXXXXXXXX Wind Park Interconnection Switching Station
|
|
- Judith Burke
- 6 years ago
- Views:
Transcription
1 Facilities Study For XXXXXXXXXXXX Wind Park Interconnection Switching Station Prepared For: Randy Harlas, Substation Manager El Paso Electric Company El Paso, TX September 2010
2 Table of Contents CERTIFICATION GENERAL FOREWORD DISCLAIMER SCOPE OF WORK... 3 Transmission Springerville to Luna 345 kv Line Tap... 3 Station XXXXXXXXXXXX 345kV Switching Station... 3 Table 1 Network Upgrade Material Costs 1, Table 2 EPE Interconnection Facilities Material Costs 1, COST SUMMARIES... 8 Table 3 Network Upgrade - Installation Costs 1, Table 4 EPE Interconnection Facilities Installation Costs CONCLUSIONS... 9 Project Schedule Transmission... 9 Project Schedule Switching Station... 9 Overall Project Cost LIST OF ATTACHMENTS Documents Substation Preliminary Design Drawings... 10
3 Certification Texas State - Certification I hereby certify, as a Professional Engineer in the state of Texas, that the information in this document was assembled under my direct personal charge. This report is not intended or represented to be suitable for re-use by El Paso Electric Company or others without specific verification or adaptation by the Engineer (Burns & McDonnell). This certification is made in accordance with the provisions of the laws and rules of the Texas State Board of Engineers Administrative Code. Electrical Engineer Approved P.E. Seal (Electrical) Kirk Saint Alwyn Powell, P.E. TX License No Date: August 26, 2010 Civil/Structural Engineer Kristie J Green, P.E. TX License No Date: August 26, 2010 Approved P.E. Seal (Civil/Structural) 1 P age
4 1. GENERAL El Paso Electric Company (Transmission Provider) has requested Burns & McDonnell Engineering (Engineer) to provide a total cost estimate for the Transmission Provider s substation addition for the connection of the proposed Interconnection Customer s XXXXXXXXXXXX Wind Project to Transmission Provider s Electric Transmission System. The Interconnection Customer proposes to connect an ultimate 99.8 MW of electric power to Transmission Provider s electric transmission system. The Point of Interconnection (POI) will be located at the Transmission Provider s new XXXXXXXXXXXX 345 kv Switching Station located along the Springerville-Luna 345 kv Transmission Line. Per the attached preliminary one line diagram (XX_OOL), the POI has been designated to be the point at which the Interconnection Customer s Electrical Facilities connects to the Transmission Provider s 345 kv bus. The following tasks and associated costs are not included in this Facility Study and shall be the responsibility of the Interconnection Customer: Land Acquisition and Surveying. Design and installation of the new kv substation to be located immediately adjacent to XXXXXXXXXXXX Switching Station as well as the transmission line from the Interconnection Customer s Generation Station to the line terminal at the POI. 2. FOREWORD This estimate has been prepared with +/- 15% accuracy as requested by the Transmission Provider. A 10% contingency has been added to the estimate which is to be applied before any adder is considered. All assumptions are clearly defined within this document and should be duly noted. Due to market conditions, costs (material and labor) have been increasing. The equipment and labor costs included in this document reflect budgetary quotes received from prospective construction contractors. These are the most up-to-date costs to the Engineer s knowledge, but are subject to change based on market conditions. Due to market conditions, prices of both copper and construction labor have been fluctuating. 3. DISCLAIMER Estimates, forecasts, projections, and schedules relating to costs, quantities, demand pricing (including but not limited to, property costs, construction, operation or maintenance costs, and/or energy or commodity demand and pricing), are opinions based on the Engineer s experience, qualifications and judgment. The Engineer has no control over the weather, cost and availability of labor, materials and equipment, labor productivity, energy or commodity pricing, demand or usage, population demographics, market conditions, change in technology, and other economic or political factors effecting such estimates or projections. The Transmission Provider acknowledges that actual results may vary significantly from the representations and opinions herein. Nothing herein will be construed as a guarantee or warranty (actual or implied) that rates, demand, pricing, costs, performance schedules, quantities, technology, or any other related items will not vary from the opinions contained in the report prepared by the Engineer. 2 P age
5 All costs included in this estimate are subject to change if the final design of the switching station changes from that shown on the preliminary prints. In using the term Network Upgrades in this report, it is assumed that all facilities at or beyond the Point of Interconnection are Network Upgrades. The Engineer has not evaluated and has formed no opinion on whether the facilities described as Network Upgrades are integrated with and support EPE s overall transmission system for the general benefit of all users. 4. SCOPE OF WORK Install a new 345 kv Switching Station by tapping the existing Springerville-Luna 345 kv transmission line in the Luna County XXXXXXXXXXX Area just west of Hwy 26 in New Mexico. Transmission Springerville to Luna 345 kv Line Tap The new substation will require the 345 kv Springerville-Luna Line to turn into the new substation in an in-and-out configuration. The proposed transmission towers shall be self supporting structures. The structures shall be capable of supporting 3 phases of 2-bundled 954 kcmil ACSR Cardinal conductor. The foundations for the dead-end structures shall be drilled shaft concrete foundations with steel reinforcement. Replace one (1) of the existing transmission shield wires (static position), between Luna and the new XXXX station, with OPGW. Geotechnical information is not available, so foundation sizes and costs were estimated based on data from other projects previously performed in the area. Transmission Engineering Assumptions The location of the new XXXXXXXXXXXX Switching Station shall be underneath the existing 345 kv Springerville-Luna transmission line ROW. Two (2) dead-end structures will be required to terminate the line adjacent to the new XXXXXXXXXXXX Switching Station and no existing structure modifications are required. The conductors shall be in a horizontal bundle configuration and will require spacers and dampers. All hardware assemblies shall use polymer insulators. The dead-end assemblies shall use compression fittings. The static wire replacement on the XXXX to Luna line will be performed while the transmission line remains in service (hot). o The existing structures can accommodate the OPGW. o No structural changes are required for the existing transmission structures. Station XXXXXXXXXXXX 345kV Switching Station The new XXXXXXXXXXXX Switching Station will consist of the following: One (1) three-position ring bus. 3 P age
6 o o o One (1) position is used for the transmission line to Tucson Electric s existing Springerville Substation. This position is also equipped with one (1) new 345 kv, 54 MVAR shunt reactor. - One of the two existing reactors located at Luna Substation may also be relocated to this position if necessary. One (1) position is used for the transmission line to the Transmission Provider s existing Luna Substation. One (1) position is designated for the connection of Interconnection Customer s Wind Generation Collection Station. Control building with the necessary power, relaying and communication equipment. One (1) lot of 345 kv Revenue Metering equipment to installed on the 345 kv line to the Interconnection Customer s adjacent Collector Substation. Metering equipment includes PT/CT combo units, foundations and support structures for the PT/CT units, Metering Panel, cables, etc. Costs for these and other materials are covered in Table 2 below. Site Survey The engineer will secure the services from a Transmission Provider-approved Survey company to perform a site and access road survey. Survey data will be used in grading design, soil cut-and-fill calculations and transmission structure positioning. Geotechnical Field Investigations and Engineering The Engineer will secure services from a Transmission Provider-approved Geotechnical Firm to perform field investigations. Geotechnical investigations and engineering calculations will be performed to establish the design basis for foundation and electrical grounding design. Site Preparation, Grading and Drainage Design The proposed XXXXXXXXXXXX Switching Station location will require the installation of an approximately 3500 foot gravel driveway to provide all weather access from Hwy 26 to the site. No costs associated with right of way or land purchases for the access road have been included. The proposed 20 foot wide access drive will consist of 8 inch thick well-graded crushed stone. The estimated 18,330 square yard substation will require a gravel surface assumed to consist of 3 inch thick gap-graded aggregate with a base of 4 inch thick well-graded crushed gravel ¾ inch in size. The station site is assumed to be crowned in the center to drain across the surface of the site outward. Because of the remote location of the station site, a detention pond is not envisaged. Drainage structures may include driveway culverts, rip-rap rocks, or grate inlets with outlet pipes if necessary. A three (3) strand barbed-wire fence will be constructed around the perimeter of the property with an 8-foot chain link fence constructed around the perimeter of the station site. 4 P age
7 Civil/Structural Design Engineer shall design the required foundations as shown on the layout drawing and according to Transmission Provider s or Engineer s specifications. Refer to the substation major materials list and preliminary design drawings for the various foundations to be installed on this project. Engineer shall perform the studies necessary to assure that the bus system is adequately supported by the structures, fittings, and insulators selected when placed under the site specific environmental and short circuit fault forces. Note. Custom structures will be designed by the Engineer as required however the Engineer assumes that all structures installed will be per Transmission Provider s Standards and current practices. The requirement of customized structures will translate to additional project costs which are not covered herein. Electrical Design Engineer shall design the station per Transmission Provider s Standards. The following are general tasks required to complete the electrical design: Install the electrical facility and equipment as indicated on the preliminary design drawings. Install the required insulation, conductors and fittings to inter-connect new equipment in the substation. Install a new station ground grid to adequately protect personnel and also the Transmission Provider s electrical infrastructure. Engineer will perform grounding calculations to verify that the new grid layout provides adequate personnel and equipment protection. Grounding installation shall be per Transmission Provider s standard practices. The station ground grid shall extend to the substation fence and exceed it by five feet. Install lightning protection (shielding) to adequately protect the new equipment. Perform the necessary calculations to design and verify the adequacy of the lightning protection. Install lightning masts as required. Install static wire between structures as needed. Lightning masts and line terminals will be fitted with 15 lightning spires on top (of each leg). Protection and Control Design The protection and control design shall follow Transmission Provider s Standards. The design is intended to provide a means of local and remote control of the equipment and electrical system (by means of switching) by the Transmission Provider. It is also intended to fulfill the purposes of protecting human life, protect electrical infrastructure under abnormal system conditions and minimize system outages and disturbances. The following are general tasks required to complete the protection and control design: Install a new control house which will be used to store all control and communication equipment, batteries and associated DC system equipment (located in a separated area of the house), and personnel safety equipment, etc. Install two (2) new Transmission Provider s Standard Line Protection Racks for the 345 kv transmission positions at this new station. Relay communication for the transmission lines to Springerville and Luna Substation shall be over fiber-optic conductors. A direct fiber-optic link between XXXX and Luna substation shall be 5 P age
8 installed. Communication between XXXX and Springerville shall be accomplished via the Transmission Provider s communication network. Communication between the XXXX station and the Interconnection Customer s adjacent substation will be by means of buried fiber optic conductors. Install one (1) new Transformer High-side Bus Protection Rack to protect the 345 kv position reserved for XXXX step-up transformer. Install revenue metering panel for the 345 kv line position designated for Interconnection Customer s Wind Generation Facilities. This panel will be connected to the PT/CT units installed at the XXXX line position in the yard. Install a Digital Fault Recorder (DFR). Install a new Communication Rack. Install relay serial communications as needed to connect the new relays to the communication rack. Install one (1) new shunt reactor rack for protection and control of the new shunt reactor and breaker. Provide relay settings for all new relays. Install SCADA control, monitoring and indication per Transmission Provider s standard practice. Install a new AC/DC Station Power system. Primary (normal) station power shall be provided by the Transmission Provider s 12 kv local distribution line located close to the proposed POI location. This will require extension of the existing distribution line. Costs associated with this work are included in the estimate. Backup (emergency) station service power shall be sourced from the low voltage side of the Interconnection Customer s step-up transformer in the adjacent Interconnection Customer substation. The backup SSVT will be located in EPE s yard (along with the primary SSVT) and will be connected to Interconnection Customer s transformer 34.5 kv bus via underground 34.5 kv power cable. An automatic transfer switch shall be installed between the two station service power sources. Connect the new equipment, racks and yard lights to the new AC/DC station service systems as needed. Install a raceway system from the control house to the field equipment. The raceway system will be comprised of cable trench (as specified) and 3 PVC conduit installed per Transmission Provider s current practices. Install the necessary shielded control and power cable to connect the field equipment to the control house equipment. Install floodlight assemblies in order to provide adequate lighting for the substation equipment. Lights will be installed at lightning masts and line terminal structures. 6 P age
9 Table 1 Network Upgrade Material Costs 1,2 Equipment Description XXXXXXXXXXXX Switching Station Unit Est. Qty. Lead Time (Weeks ARO) Unit Cost ($) Total Cost ($) 345kV, 54 MVAR, 3-P, Reactor EA ,500,000 1,500, kV, 2000 A, GCB EA , , kV, 2000 A, Disc Sw. EA , , kV Surge Arresters EA ,100 36, kV CCVT EA ,000 78,000 Structural Steel LOT , ,300 Other Elect/Site Materials 5 LOT 1-2,145,800 2,145,800 Station Materials (Sub-Total) 5,338,000 Springerville-Luna 345kV Transmission Line Tap Dead-end Structures EA , ,000 Dead-end Assemblies EA ,160 13, kcmil ACSR "Rail" FT 14, ,550 7-#8 Alumoweld FT 2, ,125 Luna-XXXX Fiber Installation 6 LOT 1-367, ,000 Other XMS Materials LOT 1-198, ,405 Transmission Materials (Sub-Total) 710,000 Total Major Costs - Network Upgrades 6,048,000 Table Notes 1. This table is included to show major substation equipment lead times and associated costs only. 2. No installation (labor) costs are included in this table. Labor costs are included in the cost summary unless otherwise noted. 3. Budgetary cost with +/- 25% accuracy. 4. Number of weeks after drawing approval. 5. Other Elect/Site Material cost include estimated pricing for site preparation, foundations, grounding, bus work, fittings and connectors, control house, raceway, station service minor equipment, DC system, protective relay racks, SCADA racks, communication equipment, etc associated with Network Upgrades. These materials generally have shorter procurement lead times. 6. Cost Data provided by Transmission Provider (EPE). Table 2 EPE Interconnection Facilities Material Costs 1,2 Equipment Description XXXXXXXXXXXX Switching Station Unit Est. Qty. Lead Time (Weeks ARO) Unit Cost ($) Total Cost ($) 345kV, 2000 A, Vertical Break Sw. EA ,000 30, kV Surge Arresters EA ,100 12, kV CT/PT Combo Unit EA , ,000 7 P age
10 Structural Steel LOT , ,000 Other Elect Materials 3 LOT 1-148, ,700 Total Material Costs - EPE Interconnection Upgrades 524,000 Table Notes 1. This table is included to show major substation equipment lead times and associated costs only. 2. No installation (labor) costs are included in this table. Labor costs are included in the cost summary unless otherwise noted. 3. Other Elect Material cost include estimated pricing for foundations, grounding, bus work, fittings and connectors, protective relay racks, revenue metering system (PT/CT units, Metering Panel and associated equipment), etc associated with EPE Interconnection Upgrades. These materials generally have shorter procurement lead times. Project Schedule See Attachment No COST SUMMARIES The estimated project transmission and station costs are outlined below. Station Costs are broken down into Network Upgrade Costs and EPE Interconnection Facilities Costs as shown below. Table 3 Network Upgrade - Installation Costs 1,2 Project Task Cost ($) Station Labor 2,205,000 Station Material 5,338,000 Station Construction Management 550,000 Station Engineering Costs 600,000 Station Installation Cost (Sub-Total) 8,693,000 Transmission Labor 10 1,548,400 Transmission Material 710,000 Transmission Construction Management 160,000 Transmission Engineering Costs 105,000 Transmission Installation Cost (Sub-Total) 2,523,400 Total Network Upgrade Costs 11,216,400 10% 1,121,640 Total Network Upgrade Costs w/contingency 12,338,040 Table Notes 1. Station Labor and material costs include Site Preparation costs. 2. Station Construction Management cost includes supervision and management of the construction process. 3. Station Engineering costs are budgetary. Final engineering costs will be provided when an RFP is issued to Engineer. 4. Total Transmission Material Cost includes all material required to construction transmission line including, steel, hardware, conductor, dampers, spacers and other miscellaneous material. 8 P age
11 5. Total Transmission Labor Cost includes all labor required to construction transmission line including erection, foundations, stringing, right-of-way preparation, construction incidentals and grounding. 6. The Transmission Engineering Line Item includes costs associated with transmission line design, owner s overhead engineering costs, survey, geotechnical investigations, construction support, environmental evaluations and permit applications. 7. Transmission Construction Management Costs include costs associated with procurement, bidding, construction supervision and management of the construction process. 8. Transmission Right-of-way acquisition and land management costs are not included in the Total Installed Cost. 9. The transmission line schedule shall follow the XXXX Switching Station schedule in Attachment Transmission Labor Cost include the costs to extend the local distribution to the XXXX substation site. Table 4 EPE Interconnection Facilities Installation Costs Project Task Cost ($) Total Labor 140,000 Total Material 524,000 Construction Management - Engineering Costs - Total Interconnection Facilities Cost 664,000 10% 66,400 Total Interconnection Facilities Cost w/contingency 730, CONCLUSIONS Project Schedule Transmission The required transmission line structural steel lead time (24-26 weeks) will have similar impact as power circuit breakers (26 weeks) on the project schedule. Since there are longer lead time items in the substation schedule, the transmission work is not expected to negatively impact the project schedule. Project Schedule Switching Station The project schedule shows that energizing the XXXX Interconnecting Switching station without the shunt reactor is estimated to be completed by August 24, Upon energization of the switchyard, back-feed to the Interconnection Customer s Facilities can occur. The Commercial Operation date of the Interconnection Customer s Generating Facility will depend on the timeframe required by the Interconnection Customer to synchronize, connect and run test operations once back-feed power is available. The energization (in-service) date for the new shunt reactor is estimated to be December 12, 2011 (see Attachment No. 1). The XXXX Interconnecting Switchyard Schedule is based on starting the activities no later than August 13, 2010 and the procurement of the long engineering 9 P age
12 lead time items no later than August 23, We recognize that at the time of this report, the procurement of long lead items has not yet occurred and is awaiting finalization of an agreement between EPE and the Interconnection Customer to govern such activities and the associated tender of letter(s) of credit. In addition we understand that issues associated with the land rights for the property upon which the XXXXXXXXXXXX Switching Station will sit are not completely resolved at this time. Based on the attached schedule, construction of the XXXXXXXXXXXX Switching Station would be completed and energized (in-service) by August 24, 2011 (without the shunt reactor) and the new line shunt reactor would be energized (in-service) by December 12, The energization (in-service) date for the relocated Luna line shunt reactor (if required) will be determined at a later date. The proposed schedule is contingent on EPE obtaining the required line clearances for the project as well as the Interconnection Customer and EPE resolving any remaining land rights issues. The Interconnection Customer shall provide to EPE (at no additional expense to EPE) any additional land rights required for construction and/or operation of the facilities, in the form of a lease or fee simple purchase for such parcel of land as EPE has identified for the purpose of constructing the interconnecting switchyard for the XXXXXXXXXXXX Wind Project, based upon final dimensions and location of the switchyard. EPE shall provide the location and specifications of the parcel as well as the form of real estate instrument, to the Interconnecting Customer, and the Interconnection Customer shall have ten (10) Business Days thereafter to provide the site in a form reasonably accepted by EPE: provided, however, that the ten (10) Business Day period shall not apply if additional land rights are required from the state as opposed to a private landowner, but the schedule may be adversely affected. The Transmission Provider will work on improving the shunt reactor delivery date (lead time) during the procurement phase. In order to meet the proposed energization (inservice) dates shown above, the Transmission Provider and Interconnection Customer must finalize the site location and provide right of entry for collecting soil samples and survey by August 30, 2010 to support the attached schedule. Overall Project Cost The overall estimated project cost for the installation of XXXXXXXXXXXX 345 kv Switching Station is $13,068,440 which includes 10% contingency. 7. LIST OF ATTACHMENTS Documents Attachment No. 1 XXWP Interconnecting Switchyard Schedule Substation Preliminary Design Drawings XXXXXXXXXXXX Switching Station Operation One-Line Diagram XXXXXXXXXXXX Switching Station General Location Plan XX_OOL XX_GLP 10 P age
Information Document Service Proposals and Cost Estimating ID # R
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationRequirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014
Requirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014 1040 O Street, P.O. Box 80869 p: 402.475.4211 Lincoln, NE 68501-0869 www.les.com
More informationFacility Interconnection Requirements
Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents
More informationTelecommunication Spaces
Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137
More informationMinimum Transmission Design Standards f or Competitive Upgrades Rev 2
Minimum Transmission Design Standards f or Competitive Upgrades Rev 2 December, 2016 Minimum Design Standards Task Force Revision History Date or Version Number 12/17/2014 Revision IR Author Change Description
More informationDOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES
Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating
More informationSECTION PACKAGE BOOSTER PUMP STATIONS
SECTION 331223 PACKAGE BOOSTER PUMP STATIONS Scope: The Contractor shall install a pump station at two locations to be determined by the Owner. These pump stations shall be designed to deliver flow to
More informationThe Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.
d/b/a National Grid and Clear River Energy LLC (Burrillville Interconnection Project) RIPUC Dkt. No. Testimony of David J. Beron, P.E., P.M.P. November, 0 0-v R.I.P.U.C. Dkt. No. 0 0 INTRODUCTION Q. Please
More informationTitle: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards
Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the
More informationV. Design, Application, Maintenance & Operation Technical Requirements
V. Design, Application, Maintenance & Operation Technical Requirements V.A PJM Design & Application of Overhead Transmission Lines 69 kv & Above These design criteria have been established to assure acceptable
More informationAudit Approach to FAC Transmission Vegetation Management FRCC Webinar
Audit Approach to FAC-003-2 Transmission Vegetation Management FRCC Webinar September 2013 Ground Rules All participants will be muted upon sign-on Please keep your phone on mute unless asking a question
More informationITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION
SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the
More information4301 Wilson Blvd. Arlington, VA tel:
To: SUNDA Project Cooperatives From: February 3, 2015 Re: Reference Block Design for Utility Scale PV Solar System Purpose: Provides a reference block design with simple, convenient features, which is
More informationContact Clark Public Utilities Construction Services department at (360) to initiate a request for service.
CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation
More informationBuilding Codes in Effect: 2010 California Building, Residential, Fire, Energy and Electrical Codes, including Article 690.
AGUA CALIENTE BAND OF CAHUILLA INDIANS A SOVEREIGN TRIBAL GOVERNMENT Planning & Development Department Building and Safety Division 5401 Dinah Shore Drive Palm Springs, CA 92264 (760) 669-6800 RESIDENTIAL
More informationMATERIAL ALLOWANCES AND UNIT PRICES
PART 1 - GENERAL 1.1 SECTION INCLUDES ADDITIONS AND RENOVATIONS TO WEST YORK AREA HIGH SCHOOL - #1231 SECTION 012200 MATERIAL ALLOWANCES AND UNIT PRICES A. Measurement and payment criteria applicable to
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationSubstation Grounding. Presented by: Bruce Kayser, PE Assisted by Danny Seele
Substation Grounding Presented by: Bruce Kayser, PE 785-633-5756 Assisted by Danny Seele Introduction Bruce Kayser, PE BSEE from KSU in 1989 Licensed Professional Engineer in KS Employed by ElectriComm,
More informationTechnical Requirements for Distributed Generation Connection
Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting
More informationACCR. More Amps. More Confidence. Glenmar E. Cambri, REE Senior Applications Engineer
TM ACCR More Amps More Confidence Glenmar E. Cambri, REE Senior Applications Engineer What is 3M ACCR? A high voltage, overhead transmission conductor designed as a drop-in replacement for ACSR and other
More informationUnderground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11
Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (URD) Index General Discussion... 1-2 Description... 3-7 Drawings (Available
More informationItem Name Description Unit of Measure Mobilization Per WSDOT Lump Sum
Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of
More informationA. Product Data shall be provided for each type of product indicated.
32 31 13 CHAIN LINK FENCES AND GATES SECTION 1 GENERAL 1.1 SUMMARY This Section includes the following: 1. Chain Link Fences 2. Gates for Chain Link Fences. See electrical specifications for electrical
More informationStandard TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationSECTION GROUNDING AND BONDING
SECTION 16060 PART 1 GENERAL 1.01 DESCRIPTION A. Section includes requirements for an electrical grounding system, including electrodes, grounding rods, connectors, insulators, equipment grounding and
More informationPenn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications
Penn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications 1. FENCE REQUIREMENTS Hazard Trees All hazard trees, which are within tree length of the fence, must be felled
More informationUNDERGROUND SERVICES SECONDARY
Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-
More informationPOTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More informationSpecification Lightning Protection Systems
Specification Lightning Protection Systems General: Summary A) This Section specifies the lightning protection system for the building(s) or structure(s). This system provides safety for the building and
More informationTYPICAL INSTALLATION INSTRUCTIONS
TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect
More informationInternational ejournals
ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER
More informationB. Accept materials on site in original factory packaging, labeled with manufacturer s identification.
SECTION 26 05 02 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Work Included: Furnish all labor, material, services and skilled supervision necessary for the construction, erection, installation,
More information02800 SHADE STRUCTURES
02800 SHADE STRUCTURES for PLAY AREAS ****************************************** SPECIFIER: The shade structure shall utilize a four point hypar system with four columns located a minimum of 10 feet from
More informationSection ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR
PART 1 - GENERAL Section 26 05 15 SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR 1.1 Cable shall be 15 kv, shielded, three conductor with ground, stranded copper, with continuously welded and corrugated
More informationDetailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content
Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Purpose The purpose of this Detailed Requirements Document (DRD) is to provide
More informationCommunications Page 1 of 9
Page 1 of 9 Last Update: April 23 rd, 2014 Introduction Design In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a
More informationXXXXX. Bremner Trio Small Hydro Project. Interconnection Facilities Study and Project Plan
XXXXX Bremner Trio Small Hydro Project Interconnection Facilities Study and Project Plan June 25, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights
More informationTABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...
TABLE OF CONTENTS 4 DESCRIPTION AND EVALUATION OF ALTERNATIVES... 4-1 4.1 INTRODUCTION... 4-1 4.2 METHODOLOGY... 4-1 4.3 DESCRIPTION OF ALTERNATIVES... 4-2 4.3.1 No Project Alternative... 4-2 4.3.2 Alternative
More informationThe Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999
CANADIAN ELECTRICAL CODE 1 The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 Repealed by Chapter E-6.3 Reg 8 (effective June 24, 2003). Formerly Chapter E-6.3 Reg 6 (effective March
More informationGainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)
Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA 20155 Phone (703) 754-6750 Work Request # UNDERGROUND DISTRIBUTION FACILITIES AGREEMENT (FOR COMMERCIAL CUSTOMER) Developer/Builder/Owner
More informationPHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS
1 Introduction 1.1 In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a utility. It should be assumed that all new
More informationPratt & Whitney. Power Systems MOBILEPAC. Gas Turbine Package. It s in our power.
Power Systems Pratt & Whitney Power Systems MOBILEPAC Gas Turbine Package TM It s in our power. Pratt & Whitney FT8 MOBILEPAC Gas Turbine Package The MOBILEPAC gas turbine package requires the smallest
More informationSection 2: Underground
Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,
More information(Condensed from National Electric Code)
WIRING, SPECIFICATIONS, INSPECTION, AND METER INSTALLATION PROCEDURES FOR RESIDENTIAL CUSTOMERS SERVED BY SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORPORATION Effective April 1, 1974 Revised February 3,
More informationINVITATION TO BID CITY OF HOPKINSVILLE
INVITATION TO BID CITY OF HOPKINSVILLE Office of the Procurement Specialist 715 South Virginia Street P. O. Box 707 Hopkinsville, Kentucky 42241-0707 TITLE: DESIGN BUILD BUIDLING FOR THE CITY OF HOPKINSVILLE,
More informationCITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application
CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY
More informationWelcome to Douglas County PUD
Welcome to Douglas County PUD We are committed to providing the best possible utility services at the lowest possible cost consistent with sound business principles. To better serve you, please fill out
More informationELECTRICAL SERVICE EXTENSION POLICY
I. OBJECTIVE A. To provide a fair and consistent method of extending, upgrading and downgrading power lines and other service facilities within the Mason County PUD No.1 (PUD 1) service area. B. To encourage
More informationPublic Utility District Number 1 of Snohomish County
Public Utility District Number 1 of Snohomish County Facility Connection Requirements September 29, 2011 1 Revision History: Number Date Description Original Sept. 29, 2011 Document Origination Compilation
More informationSubstation Bus Design: Current Methods Compared with Field Results
Electrical Transmission and Substation Structures Conference 2009 ASCE 143 Substation Bus Design: Current Methods Compared with Field Results Keith Malmedal Ph.D. P.E. P.Eng. 1 and John Wendelburg P.E.
More informationPublic Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018
Public Utility District Number 1 of Snohomish County Facility Connection Requirements February 9, 2018 1 Revision History: Number Date Description By Reviewed by Approved by: Original Sept. 29, 2011 Document
More informationPermit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:
Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,
More informationSECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES
SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable
More informationDistributed Generation. Technical Requirements and Interconnection Agreements
Distributed Generation Technical Requirements and Interconnection Agreements February 2005 Table of Contents Section 1: Interconnection Process for Distributed Generation Systems (17 pages) Section 2:
More informationPRIMARY LINE EXTENSION
PRIMARY LINE EXTENSION Installation of new electric service to an empty parcel/lot or extending a transformer to within 150' of proposed meter location. This includes installing a permanent branch, addition,
More informationSWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS
Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,
More informationUnit Substation Transformer Construction Checklist (under 500 kva)
Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationDECISION 1 SCOPE AND CONSIDERATIONS... 2
MEMORANDUM TO Windfarm developers FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed: Frank de Vries 19.09.2017
More informationLow Voltage Switchgear Construction Checklist (under 500 kva)
Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationElectric Service Standards
V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are
More informationSECTION CHAIN-LINK FENCES AND GATES 02821/1
SECTION 02821 - CHAIN-LINK FENCES AND GATES 02821/1 PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: 2. Gates: horizontal slide or swing. 3. Fences installed where
More informationEngineering Data for Copper and Aluminum Conductor Electrical Cables
2018 Edition Engineering Data for Copper and Aluminum Conductor Electrical Cables THE OKONITE COMPANY Okonite Cables...A higher Standard! The Okonite Company, 2018 Okonite Cables Table of Contents SECTION
More informationStandard PRC-002-NPCC-01 Disturbance Monitoring
A. Introduction 1. Title: Disturbance Monitoring 2. Number: PRC-002-NPCC-01 3. Purpose: Ensure that adequate disturbance data is available to facilitate Bulk Electric System event analyses. All references
More informationSECTION HIGHWAY GRADE CROSSING WARNING SYSTEMS
SECTION 18700 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for highway grade crossing warning systems. B. Where shown on the Contract Drawings or as required to accommodate associated
More informationTrico Electric Cooperative, Inc. Interconnection Requirements. For. Distributed Generation
Version Dated May 5, 2017 Trico Electric Cooperative, Inc. Interconnection Requirements For Distributed Generation TRICO ELECTRIC COOPERATIVE, INC. INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION
More informationPIP PCEPA003 Process Analyzer System Field Installation Guidelines
January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities,
More informationFAC Facility Interconnection Requirements
FAC-001-2 Interconnection Requirements A. Introduction 1. Title: Interconnection Requirements 2. Number: FAC-001-2 3. Purpose: To avoid adverse impacts on the reliability of the Bulk Electric System, Transmission
More informationLarge Basic Service. This Section applies to members requiring new. Introduction. Service Types
Large Basic Service Introduction This Section applies to members requiring new Large Basic electric service installations, greater than 400 amps single phase and greater than 50kW three phase. This Section
More informationIncremental Black Start RFP Response Template & General Information
Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section
More informationWolverine Power Supply Cooperative, Inc. Senior Transmission System Operator
I. OBJECTIVE Wolverine Power Supply Cooperative, Inc. Senior Transmission System Operator A. The Senior Transmission System Operator is responsible for the reliable and safe operation of Wolverine s transmission
More informationBenchmarking and Control Indicators for Electrical Substation Projects
Benchmarking and Control Indicators for Electrical Substation Projects Submitted by: Justin R. Nettesheim A thesis submitted in partial fulfillment of the requirements for the degree of Master of Civil
More informationDIVISION 1100 TRAFFIC
SECTION 1102 STREET LIGHTING GENERAL INFORMATION The Idaho State Electrical Board has determined that all street lights are to be provided with an external fuse disconnect, in a junction box between the
More informationSECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number
MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number PART 1 GENERAL 01 02 03 04 SCOPE Furnish and install Manual Transfer Switches (MTS) and
More informationWIND ENERGY CONVERSION SYSTEMS
CHAPTER 159 WIND ENERGY CONVERSION SYSTEMS 159.01 Purpose and Intent 159.05 Location 159.02 Definitions 159.06 Design and Technical Standards 159.03 General Regulations 159.07 Abandonment and Removal Procedure
More informationFence and Wall Requirements
Fence and Wall Requirements Definitions Decorative wall - A wall constructed of stone or other material erected for the sole purpose of providing a decorative and/or landscaped feature, and not to include
More informationFoundation Manual. Part Number: Version: Updated: July 5, S. Meadows Pkwy. A-9, #329 Reno, NV
Foundation Manual Part Number: 150002 Version: 1.22 Updated: July 5, 2009 748 S. Meadows Pkwy. A-9, #329 Reno, NV 89521 775-831-9463 www.mariahpower.com July 2009, Mariah Power, All Rights Reserved Dear
More informationELECTRICAL SERVICE UPGRADE RESIDENTIAL AND COMMERCIAL QUICK INFORMATION REFERENCE
ELECTRICAL SERVICE UPGRADE RESIDENTIAL AND COMMERCIAL QUICK INFORMATION REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2015 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION.
More information2015 Code Rollout Meeting Q & A
1 SECTION QUESTION SaskPower Inspections Dept. ANSWER 2 3 4 5 6 7 8 9 10 11 12 15-02-024 15-02-200 15-02-200 15-02-200 15-02-314 Are existing single or double 'weather proof when not in use' covers allowed
More informationTop Five Reasons to Implement Distributed Bus Protection
GE Grid Solutions Top Five Reasons to Implement Distributed Bus Protection White Paper Author: JC Theron g imagination at work 1. Abstract Power systems have evolved in the past few decades due to factors
More informationBasic Service. This Section provides information regarding a. Introduction
Basic Service Introduction This Section provides information regarding a new electric Basic Service for a single phase service less than or equal to 400 amps, and a three phase service less than 50kW.
More informationLesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System
Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators
More informationType FLX Freezer Floor Frost Heave Protection DESIGN GUIDE
Type FLX Freezer Floor Frost Heave Protection DESIGN GUIDE Commercial Products Type FLX TM Freezer Floor Frost Heave Protection DESIGN GUIDE Contents Introduction...2 Application Information... 2-3 Product
More informationCHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2
CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 7.1. GENERAL.... 2 7.1.1. Inspection Restriction Dates.... 2 7.1.2. Complete Improvements.... 2 7.1.3. Public Improvements.... 2 7.1.4. Warranty
More informationCustomer Requirements Customer-owned Transformer Vault Room
Scope This standard documents the requirements for customer-owned vault rooms containing transformers and switches that are owned, operated, and maintained by Tacoma Power. It does not address transformer
More informationCUSTOMER SERVICE POLICIES
Resolution U-10670 Effective December 18, 2013 Section Title Page No. 1.0 Statement of General Policy... 2 2.0 Electrical Service... 3 2.1 Electrical Service Availability and Characteristics... 3 2.2 Large-Load
More informationENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)
EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY
More information1.1 Related Work.1 Electrical Pathway Lighting Design Spec.: Section 16010
Subdivision Requirements Manual Page 1 of 7 PART I - GENERAL 1.1 Related Work.1 Electrical Pathway Lighting Design Spec.: Section 16010 1.2 Scope of Work.1 Work under this section, in coordination with
More informationNEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems
NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I
More informationAEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION
AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION PART I - GENERAL 1.01 Summary A. The erosion control blanket contains agricultural straw fibers for the purpose of erosion control
More informationSPECIAL SPECIFICATION 8826 Self Supporting Communications Tower (20 to 100 feet)
2004 Specifications CSJ 2103-01-030 SPECIAL SPECIFICATION 8826 Self Supporting Communications Tower (20 to 100 feet) 1. Description. Furnish and install 100 foot tall or less, self-supporting light duty
More informationSECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.
SECTION 02830 CHAIN LINK FENCES AND GATES (GALVANIZED) 1.0 GENERAL 1.1 Section Includes A. Fence framework, fabric, gates, and accessories. B. Excavation for post bases; concrete footing for posts. C.
More informationSECTION TRENCHING & BACKFILLING
SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications
More informationTECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT
TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT 1.1 General 1.1.1 These Special Conditions of Contract supplement the General Instructions.
More informationRoof & Gutter Ice/Snow Melting Design Guide
Roof & Gutter Ice/Snow Melting Design Guide Page 1 of 10 Roof & Gutter Ice/Snow Melting Design Guide CONTENTS Application Overview Page 2 STEP 1 Layout Page 4 STEP 2 Calculating Amount of Cable Page 5
More informationSECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:
SECTION 16130 (Master Template Final-05) ELECTRICAL BOXES PART 1 GENERAL 1.01 SECTION INCLUDES A. Provide boxes for electrical equipment and wiring devices as follows: 1. Wall and ceiling outlet boxes.
More informationCurlex High Velocity EROSION CONTROL BLANKET SPECIFICATION
Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION PART I - GENERAL 1.01 Summary A. The erosion control blanket contains excelsior wood fiber for the purpose of erosion control and revegetation
More informationElectric Service Handbook
Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated
More informationLyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual
Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This
More informationAll service lines shall conform to the following requirements:
505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the
More information