2006 PRELIMINARY ENGINEERING STUDY

Size: px
Start display at page:

Download "2006 PRELIMINARY ENGINEERING STUDY"

Transcription

1 2006 PRELIMINARY ENGINEERING STUDY KENNETH ROAD FROM 145TH STREET TO 151ST STREET PREPARED FOR: JULY 2011 PREPARED BY: 2400 PERSHING ROAD, SUITE 400 KANSAS CITY, MISSOURI TRANSYSTEMS PROJECT NO. P

2 Contents CONTENTS... I EXECUTIVE SUMMARY... 2 INTRODUCTION... 3 BASIC INFORMATION AND PROCEDURES... 3 EXISTING CONDITIONS... 4 Roadways... 4 Rights-of-Way... 4 Traffic Volumes... 4 Land Uses... 4 Vertical Profile... 4 Drainage... 4 Utilities... 5 Johnson County Wastewater... 5 Water District No. 1 of Johnson County... 5 Kansas City Power & Light... 5 Kansas Gas Service... 5 Time Warner Cable... 5 Magellan Pipeline Company... 5 Panhandle Eastern Pipeline Company... 5 MEDIAN BREAKS AND TURN LANE STORAGE REQUIREMENTS... 6 PRELIMINARY DESIGN... 6 Design Criteria - Roadway... 6 Design Criteria Drainage... 7 Typical Sections... 7 Right-of-way... 7 Proposed Horizontal Alignment... 7 Proposed Vertical Alignments... 7 Historical Considerations... 8 Threatened and Endangered Species... 8 Drainage... 8 Culverts... 8 Bridges... 9 Permitting... 9 Construction... 9 ESTIMATE OF COSTS APPENDIX A SUPPORTING DOCUMENTS APPENDIX C PRELIMINARY PLANS... SEPARATE VOLUME i

3 Executive Summary TranSystems Corporation completed this preliminary engineering study to establish a reasonable horizontal and vertical layout for Kenneth Road from near 145th Street to just south of 151st Street. The objective of this study was to complete a preliminary design that eliminated the at-grade crossing with the railroad, minimized impacts to existing development, to serve as a planning tool to guide future development, and to establish a right of way corridor to be preserved as development occurs over time. The findings of this study were determined in coordination with the City of Overland Park, Kansas. The major objectives of this study were as follows: Establish Design Criteria Establish design guidelines, typical roadway sections and right-of-way widths for Kenneth Road. Develop Preliminary Horizontal/Vertical Alignment Develop preliminary horizontal and vertical alignments for Kenneth Road. Determine Major Drainage Improvements Size facilities for major drainage crossings (bridges and culverts). Determine Total Project Cost Provide opinion of probable total project cost including construction, utility relocation, right-of-way, administration, legal and engineering costs based upon 2010 construction costs. The comprehensive solution to meet the objective identified is summarized in the subsequent sections of this report. Kenneth Road Overland Park s standard divided thoroughfare street section, centered on the section line, is used. 2

4 Introduction TranSystems entered into an agreement with the City of Overland Park, Kansas on December 4, Part of this agreement was to perform a Preliminary Engineering Study for Kenneth Road from approximately ¼ mile north of 151st Street to a point on 151st Street approximately ¼ mile west of Kenneth Road. The goal of the agreement was to establish a recommended horizontal and vertical layout for the free flow of Kenneth Road with 151st Street to the west. However, due to the recent annexation by the City of Overland Park, the project objective was altered to provide for a continuous north-south route on Kenneth Road separated from the existing railroad facilities. Additionally, rights-of-way will be established for preservation as development occurs along this corridor. The study also documents the following: Documentation of Existing Conditions Median Break Summary Preliminary Design Estimate of Construction Costs Each of these topics will be discussed in greater detail within this report. The Preliminary Plans are also included in Appendix C to graphically depict the proposed improvements. Basic Information and Procedures Topographic information was obtained from AIMS mapping, provided by the City of Overland Park. Property Ownerships were provided by the City of Overland Park. Utility companies were contacted via U.S. mail. Cross county gas line companies were contacted by . Development plans and existing platts along the corridor were provided by the City of Overland Park and the City of Leawood and included the following: Leabrooke, Third Plat Street Plan & Profile Mission Heights The Reserve at Ironhorse Blue River Main Wastewater Treatment Plant Copies of each are included in Appendix A Roadway plans prepared in 2005 by Phelps Engineering, Inc. for Kenneth Road from just north of the railroad to 144th Street were provided by the City of Leawood. Traffic volumes and median break information, including turn bay lengths were provided by the City of Overland Park. The Design Criteria was developed in accordance with the current City ordinance. Additionally, the criterion complies with the standards and practices of the Kansas Department of Transportation (KDOT) and the American Association of State Highway and Transportation Officials (AASHTO) publication entitled, A Policy on Geometric Design of Highways and Streets, dated The Blue Valley Watershed Study dated 2001, prepared by Camp, Dresser & McKee, Inc., including Addendum No. 1 from 2005, was provided by the City of Overland Park. Field Surveys were performed by TranSystems Corporation to verify type and size of culverts, and to ascertain stream flow line conditions upstream and downstream of the road crossing. Construction cost estimates were prepared in 2010 dollars. 3

5 Existing Conditions Roadways Kenneth Road is a north/south thoroughfare serving Overland Park and Leawood residents. It is a two-lane paved roadway with small graded shoulders and open ditches. Throughout the project area, Kenneth Road is located either fully in Overland Park, (primarily south of the UPRR) or jointly in Overland Park and Leawood (primarily north of the UPRR). Just north of 144th Street Kenneth Road is fully in Leawood. 151st Street is the only intersecting thoroughfare along Kenneth Road. However there are also tee-intersections on the west side of Kenneth at 144th, 145th and 148th Streets. Additionally, there are 3 driveways to houses on the west side of Kenneth, 4 field entrances (3 on the west and 1 on the east) and a driveway to the private softball fields located east of Kenneth just south of the railroad tracks. Rights-of-Way The existing right-of-way is generally 20 feet either side of the section line. North of 145th Street the right of way continues as 20 feet wide on the east side of the section line, but widens to 50 feet on the west side of the section line. The existing right-of-way is shown on the plan drawings in the Appendix. Traffic Volumes Traffic volumes were provided by the City of Overland Park and are Average Daily Traffic (ADT) for the year The following summarizes the traffic volumes: Kenneth Road 15,000 ADT Land Uses There are wide ranging land uses along the project corridor. The properties within Overland Park adjacent to Kenneth Road include primarily large tracts of land. The current zoning of the study corridor north of 151st Street is shown as IP-1 J, indicating Planned Light Industrial. The tracts adjacent to Kenneth Road and immediately south of 151st Street are zoned CP-3J, or Planned Commercial. However, the future land use maps published by the City of Overland Park indicate all of the land adjacent to the corridor is designated for Park use. Within the City of Leawood, lot sizes are significantly smaller and the land use becomes decidedly more suburban. This area includes AG, Agricultural zoning near the southern part of the city; SD-CR, Planned General Retail south of 148th Street; RP-3, Planned Cluster Attached (6,000 s.f. per dwelling) from 148th Street to 145th Street; and RP-4, Planned Apartment (4,000 s.f. per dwelling) north of 145th Street. Vertical Profile Nearly all of Kenneth Road achieves the 50 mph design speed when compared to AASHTO design criteria. The lone exception is near the north end of the project at 144th Street. In the AIMS mapping, there is a crest vertical curve at this location that does not meet AASHTO criteria. However, in 2004 the City of Leawood had plans developed that addressed this vertical curve. With those improvements the existing corridor fully meets the 50 mph design speed for vertical design. Drainage 151st and Kenneth is located very near the Blue River and is significantly impacted by the Blue River floodplain. Surface drainage is accomplished primarily via open ditches adjacent to Kenneth Road and 151st Street. Newer subdivisions north of the UPRR have enclosed storm sewer systems. However, these simply drain into the open ditch sections along Kenneth. There are four culvert crossings of Kenneth Road and 151st Street. Between 145th and 148th Streets, there is an existing 6 x 4 ft. Reinforced Concrete Box (RCB); just south of the UPRR there is a 25-ft single span bridge over Negro Creek; approximately 800 ft south, there is a six-feet wide concrete structure with no bottom spanning a tributary to Negro Creek. On 151st Street there is a triple 48-inch Corrugated Metal Pipe (CMP) structure along this same tributary to Negro Creek. Only one structure is usable for this project, and that is the existing bridge on Negro Creek. This could be utilized to provide access to the 4

6 Effertz ball fields on the east side of Kenneth. The remaining structures are not long enough to accommodate the proposed typical section with adequate clear zone. Utilities The major utilities in the study area are telephone, water, power, gas, sanitary sewers and fiber optic, along with natural gas transmission pipelines. These utility lines are shown on the plan drawings in the Appendix and are described as follows: Johnson County Wastewater Johnson County Wastewater has several facilities in the area. Along the west side of Kenneth just south of 145th Street there is approximately 240 ft. of 8-inch PVC sanitary sewer and approximately 140 ft. of 10- inch PVC sanitary sewer. These lines are parallel to Kenneth and just outside the right-of-way in the subdivision s utility easement. In addition, there is a 36-inch RCP trunk line on the north side of, and parallel to, the railroad tracks. This feeds to the Blue River Main Sewer District No. 1 treatment plant, and is located within its own easement, except where it crosses the existing right-of-way for Kenneth Road. Water District No. 1 of Johnson County WaterOne has several facilities in the project area. Along the west side of Kenneth Road, there is an 8-inch water main. This follows the roadway to the north side of the railroad tracks, where it veers southwesterly from the roadway, parallel to the tracks. After following the tracks for several hundred feet, the line makes a perpendicular crossing of the railroad and returns to the west side of Kenneth Road. This main goes throughout the project limits. An 8-inch main also branches off to the west at 148th Terrace to serve the local subdivision. On 151st Street there is an 8-inch main on the south side, west of Kenneth, and a 12-inch main on the south side east of Kenneth. All of these mains are outside the public right-of-way in their own easements. Kansas City Power & Light KCP&L has both overhead and underground facilities along throughout the corridor. Along the east side of Kenneth Road and the south side of 151st Street, KCP&L has a 3-phase, overhead, primary conductor. From this facility several local service lines feed residences, and subdivisions. These feed points are underground at 148th Terrace and 145th Street. The 3-phase, underground primary conductor, runs from the east side of Kenneth Road, into the developments on the west side, and continues generally parallel to the above noted streets. It appears that all of these facilities lie outside existing rights-of-way. Kansas Gas Service Kansas Gas Service has local service lines along 148th Terrace, and a 12-inch transmission line crossing 151st Street near the creek. However, neither of these facilities should be adversely impacted by the project. Time Warner Cable Time Warner Cable has various facilities within the project limits. These are primarily found on the KCP&L power poles that appear to be located outside existing public rights-of-way. Magellan Pipeline Company Magellan Pipeline Company confirmed that they have no facilities within this project area. Panhandle Eastern Pipeline Company Panhandle Eastern Pipeline Company has a 10-inch natural gas transmission line along the east side of Kenneth Road throughout the project limits. This pipeline is in its own easement and is approximately 80- years old. Should the gas line need to be relocated, work times would be limited to late spring or summer 5

7 when demand is low. Lead time is important as well. Panhandle Eastern indicated they would need about 1-year to plan for any relocation. In addition to these utilities, we contacted Conoco Phillips Pipeline, Enbridge Pipelines, AT&T and ATMOS Energy. Although multiple efforts were made, these entities did not respond. Median Breaks and Turn Lane Storage Requirements The City provided the following recommendations for proposed median break locations and full-width turn lane storage requirements (excluding tapers) on Kenneth Road: Location Northbound Southbound Eastbound Westbound 145th Street 150 N/A N/A N/A 148th Terrace N/A N/A 151st Street Preliminary Design The following design criteria, based on chapter of the Overland Park Municipal Code and on A Policy on the Geometric Deign of Highways and Streets, 2004 version, were used to develop the preliminary design. Design Criteria - Roadway Kenneth Road 151st Street Functional classification Thoroughfare Thoroughfare Design speed 50 mph 50 mph Posted speed 45mph 45mph Proposed right-of-way 80 Undivided/120 Divided 80 Undivided/120 Divided Proposed typical roadway section 12-2 Inside/13-0 Outside 12-2 Inside/13-0 Outside Proposed Median Width N/A Undivided/ 24-0 Divided N/A Undivided/ 24-0 Divided Proposed curb type Type D Inside/Type B Outside Type D Inside/Type B Outside Proposed sidewalk width 5 Both sides 5 both sides Proposed Normal Crown 2.08% (1/4 per Foot) 2.08% (1/4 per Foot) Minimum Radii 1200 Divided/600 Undivided* 1200 Divided/600 Undivided* Maximum grade 6% 6% Minimum grade 1% 1% Minimum stopping sight distance 400 ft 400ft Sag vertical curve (min. K) Crest vertical curve (min. K) Maximum Superelevation 4% 4% Superelevation Runoff 1:200 1:200 Side Slopes 4:1 4:1 6

8 Design Criteria Drainage The City of Overland Park Municipal has adopted APWA Section 5600, with amendments. The following design criteria is a summary of the applicable standards.. Method of estimating runoff Rational (less than 200 Acres) Computer modeling over 200 acres Storm sewer system design storm 10 year Cross-road culvert design storm 50 year Cross-road culvert design storm (low point) 100 year Ditches 25 year Allowable Spread 10.5 (6 intersections and crosswalks) Minimum pipe size 15 Type of pipe RCP Minimum pipe velocity 3 ft./sec. Maximum pipe velocity 20 ft./sec. Typical Sections The typical sections for the proposed roadways are shown in the Appendix. All thoroughfare sections have 12 thick asphaltic concrete pavement over a 6 aggregate base course. Page 2 of the plans in the Appendix shows the standard four-lane divided thoroughfare section recommended for Kenneth Road and 151st Street. The roadway width consists of a 13 outside lane and 12-2 inside lane. Five-foot sidewalks are located 1-foot inside the proposed right-of-way line on both sides of the street. Right-of-way Right-of-way requirements are indicated on the plan drawings in the Appendix and on the typical section on page 2 of the plans in the Appendix. All thoroughfare sections will include a 120 right-of-way corridor, lying 60 on either side of centerline. Permanent drainage easements will be necessary at the ends of the crossroad drainage structures. Temporary construction easements will be necessary along most properties adjacent to construction. Additional permanent utility easements will be necessary to accommodate utility relocations, particularly for the Panhandle Eastern Pipeline facility and the Johnson County Water District No. 1 facilities near the railroad tracks on Kenneth. The final locations of the proposed utility easements should be determined during the project design phase when more accurate utility information is available. Proposed Horizontal Alignment The roadway is proposed to be a standard thoroughfare centered on the existing section line from 145th Street to 151st Street. Proposed Vertical Alignments The minimum design criteria for thoroughfare type roadways is established in the City of Overland Park Municipal Code and the 2004 edition of A Policy on Geometric Design of Highways and Streets published by the American Association of State Highway and Transportation Officials. The two main design issues when developing the vertical alignments for these roadways are Stopping Sight Distance (S.S.D.) of a crest vertical curve and the K value of a sag vertical curve. The requirements for this project are shown in the Design Criteria section of this report. An exception to the Design Criteria has been incorporated for the bridges over the Union Pacific Railroad tracks. To achieve the desired 50 mph design speed, and limit the profile to 6% maximum grade, the project would have required substantial reconstruction of 148th Street and the planned commercial 7

9 development area. This would also have shifted the high point further to the south, and elevated the intersection with 151st Street significantly. Therefore, the design speed was reduced to 40 mph, which allows the clearance to be achieved over the railroad tracks, without significantly impacting 148th Street or 151st Street. Additionally, two profiles were established on 151st Street west of Kenneth. The primary profile shown on the plans would tie into the railroad tracks west of Kenneth with an at-grade crossing. The second profile, shown as a dashed line and labeled as Future Profile, would enable a grade-separated crossing of the railroad tracks. As shown on Kenneth Road, the crown of the roadway must be rotated to a two-percent reverse crown to help achieve the grade-separated crossing. This is accommodated with profiles on 151st Street. Historical Considerations The Kansas State Historical Society (KSHS) will have to be contacted to determine if there are known archaeological sites or historic structures within the project area and what impact, if any, the improvements would have on any properties listed on the National Register of Historic Places. Due to the close proximity of the project to several waterways, the likelihood of significant historic or cultural sites tends to be greater. Therefore, this should be explored further in the early stages of the design process. Threatened and Endangered Species The United States Department of the Interior, Fish and Wildlife Service should be contacted as well to ascertain the presence of any threatened or endangered species in or near the project area. Since the project is bridging a flood plain area, the likelihood of threatened or endangered species increases. This contact should be initiated early in the design process. Drainage New drainage structures beneath Kenneth Road and 151st Street will be reinforced concrete boxes. The major culvert crossings were sized for a 100-year storm. The analysis was performed using Bentley Pondpack (Version 10.1) incorporating the Soil Conservation Service (SCS) TR-55 methodology. A one foot freeboard elevation was utilized in the culvert design. Locations of structures are shown on the plan and profile sheets in the Appendix. The Blue River Watershed is immediately downstream of the culverts. However, the sizing of the culverts was done assuming low water conditions on the Blue River and a localized 100-year storm. Since the a large portion of the area is inundated in the 100-year Blue River event, the culverts would be serving as equalizers within the flood plain during that event, rather than conveying runoff through the project. During final design it may be necessary to design a storm system that utilizes area inlets to collect the water at the toes of slope where positive drainage cannot be achieved. Temporary interceptor ditches should be utilized in order to keep large areas of off-site drainage from entering the roadway. The temporary interceptor ditches will only be used where development has not yet occurred. Culverts There is one culvert crossing on 151st Street west of Kenneth Road, and two crossings on Kenneth Road. The data used in analyzing the storm drainage flowing from the adjacent drainage areas is shown in the table below: Structure Location Size Area (acres) CN Value Time of Conc. (min) i 100 (in/hr) Q 100 (cfs) Plugged WSE st Sta x 6 RCB Kenneth - Sta x 6 RCB Kenneth - Sta x 5 RCB It should be noted that the discharge reported through the culvert at Kenneth Road station (404 cfs) is less than the discharge through the upstream culvert at 151st Street station (431 cfs) due to attenuation 8

10 of the hydrograph. This is caused by the proposed roadway culverts operating similar to detention pond outlets. The plugged water surface elevations were determined by assuming each individual proposed culvert is completely blocked (one at a time) so the structure has no hydraulic capacity. Water storage areas and volumes were estimated from AIMS mapping data and project surveys. The proposed roadway profiles were used to simulate weir flow in the plugged culvert analysis. Pondpack output for each scenario is available in the appendix of this report. Bridges Two bridges are required on Kenneth Road to cross over the Union Pacific Railroad and Negro Creek. The bridge length was set based on spanning the Blue River floodway, but also placed the bridge piers in an arrangement that spans the railroad right-of-way. This allows the project to proceed with minimal impact to the railroad operation or the future expansion of their facilities. To achieve these objectives, the bridge needs to be 1,225-ft in length, with spans of The preliminary design was based on a parabolic haunch welded plate girder with the end of haunch set at the 30% point of the spans. The maximum web depth used was 120-inches (84-inches min.) and the maximum flange thickness was 3-inches based. These parameters were based on a conversation with a local steel fabricator. A deeper web could be used, but that would eliminate several fabricators from being able to supply materials for the project. During final design, consideration should also be given to the length of structural element that could be handled in the fabricator s shop which is generally around 150-ft. Because of this restriction, as well as the ability to transport long loads to the site, field splices will likely be required in higher stress zones than would normally be desirable. Additionally, the 400-ft span is near the maximum limit for deflection requirements, and is near the maximum web depth and flange plate thickness available from most fabricators. Another span arrangement of was evaluated and such an arrangement would give a more reasonable bridge design but would encroach into the Union Pacific Railroad right-of-way. This arrangement would still allow the piers to be located beyond the 25-ft clear zone required by the railroad. Locations of bridge structures are shown on the plan and profile sheets in the Appendix. Permitting Permits will be required before beginning construction activities on this project. Due to the continually changing nature of permitting requirements, it is recommended the engineer review permitting requirements during the project s preliminary design phase. The following permits may be required and should be investigated: 404 Permit DWR Permit National Pollution Discharge Elimination System (NPDES) Permit City Land Disturbance Permit City Flood Plain Permit FEMA Other Construction Construction phasing and maintenance of traffic during construction are not specifically addressed in this study. However, these items must be considered during the preliminary and final design. Construction of two separate bridges on Kenneth may allow for one bridge to be constructed while traffic is maintained on the existing roadway. However, temporary shoring needed for construction the approach embankment, may prove to be cost prohibitive. It will be vital to plan for constructability early in the design process. Estimated project costs are included in the following section. 9

11 Estimate of Costs Approximate quantities have been calculated to determine the approximate project construction cost, including potential utility relocations. The total project cost also includes anticipated costs for design engineering, City administration costs, right-of-way costs, and costs for construction phase services. SUMMARY OF PRELIMINARY COSTS 151ST STREET & KENNETH ROAD INTERSECTION City of Overland Park, Kansas G:\KC06\0429\CostEstimate\151st Street \[151st Street & Kenneth Road Cost Estimate.xls]RW 6/22/2011 Item Totals 1. Construction Costs $ 17,227, Engineering/Survey $ 861, % of Construction 3. Inspection $ 1,808, % of Construction 4. Material Testing $ 258, % of Construction 5. Project Administration $ 344, % of Construction 6. Legal Publications, Printing, Misc. $ 86, % of Construction 7. Ownership Certificates/ Title Report $ 8, R/W Acquisition $ 2,146, Utility Relocations $ 1,462, TOTAL PROJECT COST $ 24,204,

12 PRELIMINARY R/W ACQUISITION COSTS 151ST STREET & KENNETH ROAD INTERSECTION City of Overland Park, Kansas G:\KC06\0429\CostEstimate\151st Street \[151st Street & Kenneth Road Cost Estimate.xls]RW 6/22/2011 Tract Easement type Approx (S.F.) Approx. Cost Right of Way $ 101, Temporary Construction 7601 $ 7, Drainage $ - Right of Way $ 118, Temporary Construction $ 20, Drainage 2500 $ 2, Right of Way 331 $ 1, Temporary Construction $ - Drainage $ - Right of Way 3577 $ 14, Temporary Construction $ - Drainage $ - Right of Way $ 83, Temporary Construction 8953 $ 8, Drainage $ - Right of Way $ 117, Temporary Construction $ 13, Drainage $ - Right of Way 5911 $ 23, Temporary Construction 1082 $ 1, Drainage $ - Right of Way 3321 $ 13, Temporary Construction $ - Drainage $ - Right of Way 2071 $ 8, Temporary Construction 1329 $ 1, Drainage 1031 $ 1, Right of Way 1351 $ 5, Temporary Construction 1605 $ 1, Drainage 1243 $ 1, Right of Way 2118 $ 8, Temporary Construction 4337 $ 4, Drainage $ - Right of Way 2085 $ 8, Temporary Construction 4044 $ 4, Drainage $ - Right of Way 1949 $ 7, Temporary Construction 3800 $ 3, Drainage $ - 11

13 PRELIMINARY R/W ACQUISITION COSTS 151ST STREET & KENNETH ROAD INTERSECTION City of Overland Park, Kansas G:\KC06\0429\CostEstimate\151st Street \[151st Street & Kenneth Road Cost Estimate.xls]RW 6/22/2011 Tract Easement type Approx (S.F.) Approx. Cost Right of Way $ 52, Temporary Construction 8599 $ 8, Drainage $ - Right of Way $ 349, Temporary Construction $ 163, Drainage 7357 $ 7, Right of Way $ 40, Temporary Construction 8249 $ 8, Drainage 1188 $ 1, Right of Way $ 119, Temporary Construction $ 27, Drainage 2175 $ 2, Right of Way $ 42, Temporary Construction 3467 $ 3, Drainage $ - Right of Way $ 107, Temporary Construction $ 41, Drainage $ - Right of Way $ 328, Temporary Construction $ 66, Drainage 1384 $ 1, Right of Way 2017 $ 8, Temporary Construction $ - Drainage $ - Right of Way 9178 $ 36, Temporary Construction 2927 $ 2, Drainage $ - Right of Way $ 95, Temporary Construction $ 38, Drainage 956 $ Right of Way 1299 $ 5, Temporary Construction 3652 $ 3, Drainage $ - Right of Way 294 $ 1, Temporary Construction $ - Drainage $ - R/W Total $ 2,146,

14 PRELIMINARY UTILITY RELOCATION COSTS 151ST STREET & KENNETH ROAD INTERSECTION City of Overland Park, Kansas G:\KC06\0429\CostEstimate\151st Street\[151st Street & Kenneth Road Cost Estimate.xls]RW 6/22/2011 Item Quantity Units Unit Price Price 1. 8" Water Line Relocation 4550 L.F. $ $ 304, " Water Line Relocation 550 L.F. $ $ 55, " PVC Sanitary Sewer 450 L.F. $ $ 29, " RCP Sanitary Sewer 500 L.F. $ $ 112, " Gas Line (Panhandle Enastern) 4,100 L.S. $ $ 717, Subtotal $ 1,219, % Contingency $ 243, TOTAL $ 1,462,

15 PRELIMINARY CONSTRUCTION COSTS 151ST STREET & KENNETH ROAD INTERSECTION City of Overland Park, Kansas G:\KC06\0429\CostEstimate\151st Street\[151st Street & Kenneth Road Cost Estimate.xls]RW 6/22/2011 Item Quantity Units Unit Price Price 1. Mobilization 1 L.S. $ 782, $ 782, Clearing & Grubbing 1 L.S. $ 49, $ 49, Removal of Improvements 1 L.S. $ 61, $ 61, Contractor Construction Staking 1 L.S. $ 97, $ 97, Unclassified Excavation 11,367 C.Y. $ 5.00 $ 56, Compaction of Earthwork 169,894 C.Y. $ 2.00 $ 339, Erosion Control 1 L.S. $ 54, $ 54, Temporary Seeding 6.4 Acre $ 1, $ 6, " Fly Ash Treated Subgrade 43,215 S.Y. $ 5.00 $ 216, " Aggregate Base Course (OP Special) 43,215 S.Y. $ 7.00 $ 302, " Asphaltic Concrete Intermediate Course 18,082 Ton $ $ 1,446, " Asphaltic Concrete Surface Course 4,306 Ton $ $ 344, Concrete Approach Pavement 457 S.Y. $ $ 22, Curb and Gutter (Type B) 7,347 L.F. $ $ 146, Curb (Type D) 6,454 L.F. $ $ 116, Concrete Median Nose 10 Each $ 2, $ 20, Concrete Entrance Pavement 0 S.Y. $ $ " Concrete Sidewalk 3,781 S.Y. $ $ 151, Sidewalk Ramp 10 Each $ 1, $ 10, Underdrain 7,777 L.F. $ $ 139, Curb Inlet 36 Each $ 4, $ 162, Junction Box 2 Each $ 4, $ 9, Storm Sewer RCP 5,980 L.F. $ $ 418, RCP End Section 4 Each $ $ 2, RCB 6'x6' 200 L.F. $ $ 60, RCB 2-6'x6' 615 L.F. $ $ 319, Bridge 96,006 S.F. $ $ 10,560, Fence 5,107 L.F. $ 8.00 $ 40, Traffic Signal 1 Each $ 150, $ 150, Pavement Marking 1 L.S. $ 41, $ 41, Signing 1 L.S. $ 17, $ 17, Traffic Control 1 L.S. $ 61, $ 61, Street Lighting 1 L.S. $ 91, $ 91, Sodding 16,962 S.Y. $ 6.00 $ 101, Seeding 9.4 Acre $ 1, $ 9, Subtotal $ 16,407, % Contingency $ 820, TOTAL $ 17,227,

16 Appendix A Supporting Documents Leabrooke, Third Plat Mission Heights The Reserve at Ironhorse Blue River Main Wastewater Treatment Plant 15

17

18

19

20

21 Appendix B Hydrologic and Hydraulic Computations The analysis was performed using Bentley Pondpack (Version 10.1) 151 st Street and Kenneth Road Proposed Kenneth Road (Station 41+65) Proposed 151 st Street 100% Plugged Kenneth Road (Station 16+79) 100% Plugged Kenneth Road (Station 41+65) 100% Plugged 20

22 21

23 22

24 23

25 24

26 25

27 151 st and Kenneth Rd 151 st Plugged 26

28 27

29 28

30 29

31 30

32 31

33 32

34 33

35 Appendix C Preliminary Plans Preliminary plans are provided as a separately bound set of 11 x 17 plans. 34

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS

CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

Location Drainage Study

Location Drainage Study Location Drainage Study PROJECT ROUTE: LIMITS: MUNICIPALITY/COUNTY: JOB NUMBER: IL 47 at Burlington Road 750ft NW to 750ft SE of IL 47(Burlington), & 1000ft S to 1000ft N of Burlington (IL47) Kane County

More information

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:

More information

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01 Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

Appendix D - Evaluation of Interim Solutions

Appendix D - Evaluation of Interim Solutions Appendix D - Evaluation of Interim Solutions D.1 Introduction The implementation of long-term improvements is projected to take 5 to 8 years. To reduce the number of years of flooding impacts, the partner

More information

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows: UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed

More information

ENGINEERING DESIGN MANUAL

ENGINEERING DESIGN MANUAL CITY OF BRIDGEPORT, TEXAS ENGINEERING DESIGN MANUAL Updated September 2009 By: Baird, Hampton & Brown, Inc. Engineering and Surveying Grapevine, Texas Prepared by: Freeman Millican, Inc Consulting Engineers

More information

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number) EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY

More information

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: CONSTRUCTION SURVEY PART 1 - GENERAL 1.01 SECTION INCLUDES Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: A. Construction Survey: 1. Project

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

Chapter 9 - Storm Drains

Chapter 9 - Storm Drains Chapter 9 - Storm Drains TABLE OF CONTENTS CHAPTER 9 - STORM DRAINS... 9-1 9.1 Introduction... 9-1 9.1.1 Objective 9-1 9.2 Design Policy... 9-2 9.2.1 Definition 9-2 9.2.2 General Policies... 9-2 9.3 Design

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

SUBDIVISION SECTION STREET DESIGN MANUAL

SUBDIVISION SECTION STREET DESIGN MANUAL CITY OF ANAHEIM SUBDIVISION SECTION STREET DESIGN MANUAL A. INTRODUCTION : POLICY STATEMENT B. STREET CLASSIFICATION C. STREET STANDARDS REQUIREMENTS Requirements Approval of Street Improvement Plans Widening

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

TRANSPORTATION & PUBLIC WORKS DEPARTMENT TECHNICAL STANDARDS

TRANSPORTATION & PUBLIC WORKS DEPARTMENT TECHNICAL STANDARDS Athens-Clarke County Unified Government TRANSPORTATION & PUBLIC WORKS DEPARTMENT TECHNICAL STANDARDS JULY, 2009 PREFACE The technical standards presented herein reflect the current policies and practices

More information

City of Elgin SUBDIVISION FINAL ENGINEERING Engineering Submittal Checklist

City of Elgin SUBDIVISION FINAL ENGINEERING Engineering Submittal Checklist If this is a re-submittal, please provide a point-by-point response to previous review comments, identifying how each comment has been addressed, location in the plan set of the changes made to address

More information

SECTION CONSTRUCTION SERVICES

SECTION CONSTRUCTION SERVICES SECTION 01100 CONSTRUCTION SERVICES PART 1 GENERAL 1.01 - Section Includes A. Mobilization. B. Construction Surveys. C. Record Documents. 1.02 Description Of Work A. Mobilization: includes the preparatory

More information

LAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA

LAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA LAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA FEBRUARY 1996 CITY OF LAWRENCE, KANSAS STORMWATER MANAGEMENT CRITERIA TABLE OF CONTENTS Pg 1.0 GENERAL 1.1 Introduction... 1 1.2 Applicability... 1 1.3 General

More information

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification 7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street

More information

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE The Existing Roadway Condition Assessment Report (ERCAR) should include the evaluation of all elements against new construction criteria.

More information

THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN. 4. Drainage Plan. a. Drainage Plan Description

THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN. 4. Drainage Plan. a. Drainage Plan Description THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN 4. Drainage Plan a. Drainage Plan Description The Specific Plan area drains naturally into two separate watersheds: approximately 6 percent of the Specific

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

Keys Edge Community Development District. Engineer s Report Infrastructure Improvements

Keys Edge Community Development District. Engineer s Report Infrastructure Improvements Keys Edge Community Development District Engineer s Report Infrastructure Improvements Prepared for Keys Edge Community Development District Board of Supervisors Miami-Dade County, Florida Prepared by

More information

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater.

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater. Background The City of rth Las Vegas strives to provide the development community with adequate information to ensure the successful completion of any project in the City. To aid in the submittal of a

More information

Gwinnett County Stormwater System Assessment Program

Gwinnett County Stormwater System Assessment Program Gwinnett County Stormwater System Assessment Program Jonathan Semerjian, PE Dept. of Water Resources Stormwater Management Sam Fleming, PE Dewberry Presentation Overview Project Background Drivers Enhanced

More information

SECTION 11: REGULATORY FLOODWAYS

SECTION 11: REGULATORY FLOODWAYS SECTION 11: REGULATORY FLOODWAYS Contents 11.1. The Floodway... 11-2 11.1.1. The floodway concept... 11-2 11.1.2. Floodway map... 11-2 11.1.3. Floodway permitting... 11-3 11.1.4. Changing the floodway...

More information

All driveways shall have a separate site plan when the application is submitted.

All driveways shall have a separate site plan when the application is submitted. Driveway Submittal Requirements All driveways shall have a separate site plan when the application is submitted. Within 24 hours of application submittal, all proposed driveways shall: be addressed with

More information

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 7.1. GENERAL.... 2 7.1.1. Inspection Restriction Dates.... 2 7.1.2. Complete Improvements.... 2 7.1.3. Public Improvements.... 2 7.1.4. Warranty

More information

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects 2.0 ROADWAYS 2.1 Road Classification 2.1.1 Standard Drawing Classification All Road Widths and Road Allowances shall be designed in accordance with the most recent Town of New Tecumseth Standards: TNT.SD

More information

DIVISION 5 STORM DRAINAGE CRITERIA

DIVISION 5 STORM DRAINAGE CRITERIA DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the

More information

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) PROJECT DESCRIPTION: (Enter Type of Project Planning Cost Estimate as Title)

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations.

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations. COACHELLA VALLEY WATER DISTRICT DOMESTIC WATER CHECKLIST Tract/Parcel No: Project Common Name: Developer: Engineer: Engineer Signature: Date: Phone: Phone: Print: This is only a general checklist; please

More information

BOARD OF LAPEER COUNTY ROAD COMMISSIONERS

BOARD OF LAPEER COUNTY ROAD COMMISSIONERS BOARD OF LAPEER COUNTY ROAD COMMISSIONERS Policy On: CONSTRUCTION OF COMMERCIAL DRIVEWAYS, PRIVATE ROAD APPROACHES, AND PUBLIC ROADWAYS Adopted: December 19, 2005 Revised: October 21, 2009 INTRODUCTION

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

City of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development

City of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development City of Redwood City Stormwater Pollution Prevention Program Drainage Guidelines for Residential Development General Requirements A. Plot & Finished Grading Plan must be submitted with Building Permit

More information

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project.

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project. EXECUTIVE SUMMARY FINDINGS: Based on the results of this feasibility study, the Platte Republican Diversion Project would be cost-effective. With minimal improvements to the channel, and the existing bridge

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

HIGH SCHOOL #2 Severance, CO MANAGEMENT PLAN November,

HIGH SCHOOL #2 Severance, CO MANAGEMENT PLAN November, HIGH SCHOOL #2 Severance, CO MANAGEMENT PLAN November, 18 2016 1 VICINITY MAP Site Data Land Use Statistics o Proposed Developed Site 55 acres 22.8% o Flood Plain 6 acres 2.4% o Open Space 100.6 acres

More information

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17 S&L Gravel, Section B: Proposal Page 10701.0 - TRAFFIC CONTROL - LUMP SUM 1.00 $6,425.00 $6,425.00 $6,425.00 $10,000.00 10720.0 - TRAFFIC CONTROL SIGN - PORTABLE ARROW BOARD - DAYS 25.00 $25.00 $625.00

More information

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS APRIL 2011 APRIL 2011 Page 1 Chapter Table of Contents 12.1 Policy... 12-3 12.1.1 Table 1... 12-3

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN. SECTION 2D-1 PROJECT REVIEW General... 2D-1

TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN. SECTION 2D-1 PROJECT REVIEW General... 2D-1 TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN SECTION 2D-1 PROJECT REVIEW General... 2D-1 SECTION 2D-2 PREPARATION OF INFORMATIONAL BROCHURES Responsibility... 2D-2 Purpose of Brochure... 2D-2 Review of Draft

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

2A Stormwater Regulations and Permitting A. Iowa Drainage Law and Resources 1 B. Regulated Activities 1

2A Stormwater Regulations and Permitting A. Iowa Drainage Law and Resources 1 B. Regulated Activities 1 Design Manual Chapter 2 - Stormwater Table of Contents TOC Table of Contents Chapter 2 - Stormwater 2A General Information 2A-1--------------------------------General Information A. Concept... 1 B. Informing

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS CEE BS, Fulltime (3 positions) Posted 1/30/2017 COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS SUFFOLK COUNTY IS AN EQUAL OPPORTUNITY / AFFIRMATIVE ACTION EMPLOYER

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

Highway Engineering. 3 _ 2/2 Lecture/Laboratory Hours

Highway Engineering. 3 _ 2/2 Lecture/Laboratory Hours COURSE OUTLINE CIV216 Course Number Highway Engineering Course Title 3 _ 2/2 Credits Lecture/Laboratory Hours COURSE DESCRIPTION Explores the planning, design, construction, and characteristics of highways

More information

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

RESIDENTIAL CONSTRUCTION New Dwellings and Additions How to Obtain a Building Permit For RESIDENTIAL CONSTRUCTION New Dwellings and Additions MIAMI COUNTY, KANSAS CODE SERVICES DEPARTMENT 201 South Pearl Street, Suite 201 Paola, Kansas 66071-1777 Phone:

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

1400 SUBDIVISION ROADS CHAPTER

1400 SUBDIVISION ROADS CHAPTER BC MoT SUPPLEMENT TO TAC GEOMETRIC DESIGN GUIDE MoT Section 1400 TAC Section Not Applicable 1400 SUBDIVISION ROADS CHAPTER 1410 SUBDIVISION ROAD CONSTRUCTION SPECIFICATIONS 1410.01 GENERAL... 1410-1 1410.01.01

More information

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1300 CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1301 SECTION 13.01 STATEMENT OF PURPOSE To provide for manufactured home park development, of long-term duration of stay, in

More information

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

ENGINEERING DESIGN & IMPROVEMENT STANDARDS ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI PH. (517) FAX (517)

Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI PH. (517) FAX (517) Date Issued Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI 48854 PH. (517) 676-8395 FAX (517) 676-8364 APPLICATION FOR SOIL EROSION AND SEDIMENTATION POLLUTION

More information

3 PROJECT DESCRIPTION

3 PROJECT DESCRIPTION 3.1 PROJECT OVERVIEW 3 PROJECT DESCRIPTION The Rocklin 60 project (proposed project) includes the subdivision of 56.9 acres of land, construction of 179 single-family, detached dwelling units, and installation

More information

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects SEPTEMBER 1989 Arkansas State Highway and Transportation Department GEOMETRIC DESIGN CRITERIA for Non-freeway

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

Chapter 6 DOCUMENTATION OF HYDRAULIC STUDIES SOUTH DAKOTA DRAINAGE MANUAL

Chapter 6 DOCUMENTATION OF HYDRAULIC STUDIES SOUTH DAKOTA DRAINAGE MANUAL Chapter 6 DOCUMENTATION OF HYDRAULIC STUDIES SOUTH DAKOTA DRAINAGE MANUAL October 2011 Table of Contents Section Page 6.1 INTRODUCTION...6-1 6.1.1 General...6-1 6.1.2 Purpose...6-1 6.1.3 Objectives...6-2

More information

Carpinteria Avenue Bridge Replacement Project Description Introduction

Carpinteria Avenue Bridge Replacement Project Description Introduction Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with

More information

State Highway 10A Improvements (from the SH-10 junction extending 6.18 miles east to the SH-100 junction, Muskogee and Sequoyah Counties, Oklahoma)

State Highway 10A Improvements (from the SH-10 junction extending 6.18 miles east to the SH-100 junction, Muskogee and Sequoyah Counties, Oklahoma) (from the SH-10 junction extending 6.18 miles east to the SH-100 junction, Muskogee and Sequoyah Counties, Oklahoma) Open House January 31, 2017 Open House Purpose Explain purpose and need for SH-10A improvements

More information

Storm. Section. B. General Design and Drawing Standards Design

Storm. Section. B. General Design and Drawing Standards Design Section Storm 5 General Plans for the existing stormwater system are maintained in digital and printed form by the City. Copies may be obtained from the Utility Division of the Public Works Department.

More information

NOTICE OF PREPARATION

NOTICE OF PREPARATION NOTICE OF PREPARATION Date: June 12, 2014 To: From: Subject: Governor s Office of Planning and Research/State Clearinghouse Unit, Responsible Agencies, Trustee Agencies, and Interested Parties Announcement

More information

DRAINAGE DESIGN DOCUMENTATION

DRAINAGE DESIGN DOCUMENTATION June, 2017 DRAINAGE DESIGN DOCUMENTATION (An expansion of the Stormwater Management Design Report) Note: This report outline is not all-inclusive. There may be situations when information not included

More information

Project Drainage Report

Project Drainage Report Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable

More information

ARTICLE 5 DESIGN STANDARDS AND IMPROVEMENT AND CONSTRUCTION STANDARDS

ARTICLE 5 DESIGN STANDARDS AND IMPROVEMENT AND CONSTRUCTION STANDARDS ARTICLE 5 DESIGN STANDARDS AND IMPROVEMENT AND CONSTRUCTION STANDARDS SECTION 501. PURPOSE The purpose of this Article is to provide reasonable design and improvement standards for public improvements

More information

ADAMS COUNTY ROAD STANDARDS

ADAMS COUNTY ROAD STANDARDS ADAMS COUNTY ROAD STANDARDS June 19, ADAMS COUNTY PUBLIC WORKS 210 W. Alder Ritzville, WA 99169 (509) 659-3276 1.00 GENERAL CONSIDERATIONS 1.01 APPLICABILITY These Standards shall apply to all new construction

More information

APPENDIX G HYDRAULIC GRADE LINE

APPENDIX G HYDRAULIC GRADE LINE Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm

More information

A.3 Concrete Cross gutter 18

A.3 Concrete Cross gutter 18 TABLE OF CONTENTS SECTION NUMBER PAGE NO. SECTION 1 - General Requirements 1-3 SECTION 2 - Preparation of Plans 4-8 SECTION 3 - Inspection 9-10 SECTION 4 - Roads and Streets 11-15 STANDARD DRAWINGS A.1

More information

SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS

SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS Page 4-1 INTRODUCTION 4-3 4-1.01 Applicability of VMCs 14.24, 14.25, 14.26 4-4 4-1.02 Minimum Requirements - Projects Below Threshold

More information

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE BE IT ORDAINED by the Town Council of the Town of Plainville: SECTION 1. SUBDIVISIONS. All subdivisions hereinafter developed within

More information

4.1 Browns Canal Introduction Sub-basin Information

4.1 Browns Canal Introduction Sub-basin Information Section 4 Withlacoochee Basin 4.1 Browns Canal 4.1.1 Introduction The information presented in this sub-basin plan for Browns Canal is intended to provide the reader with information necessary to understand

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

Classifications of Improvements and Definitions

Classifications of Improvements and Definitions Design Manual Chapter 1 - General Provisions Table of Contents TOC Table of Contents Chapter 1 - General Provisions 1A General Conditions 1A-1---------------------------------General Conditions A. Purpose.....

More information

SECTION WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA

SECTION WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA SECTION 6900 - WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA 6901 DESIGN CRITERIA A. General 1. The design standards presented in the City of Lee's Summit Design Criteria are the minimum standards

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts 2.7 C Culverts 1. General Culverts are intended to safely pass flow under road crossings. Criteria are designed to protect, maintain, and enhance public health, safety, and the environment. Where culverts

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

Zoning Permits 11-1 ZONING PERMITS

Zoning Permits 11-1 ZONING PERMITS Zoning Permits 11-1 ZONING PERMITS (a) Building or structures shall be started, repaired, reconstructed, enlarged or altered only after a zoning permit has been obtained from the administrator and a building

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

10.0 Storm Sewer Systems

10.0 Storm Sewer Systems October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and

More information

Project Need and Evaluation

Project Need and Evaluation City of Brooklyn Center 2011 Palmer Lake East Street and Utility Reconstruction Project Public Hearings February 14, 2011 Public Improvement Hearing: Special Assessments Local public improvements to the

More information

PRELIMINARY DEVELOPMENT PLAN INFORMATION

PRELIMINARY DEVELOPMENT PLAN INFORMATION PRELIMINARY DEVELOPMENT PLAN INFORMATION SITE AREA =.0 AC. (,8,8 S.F.) BUILDING FOOTPRINT =,8 S.F. PAVEMENT/PARKING AREA = 0,98 S.F. BUILDING COVERAGE OF SITE = % SITE IMPROVEMENT PLAN NOTES. ALL UTILITY

More information

STREAM AND BUFFER AREA PROTECTION/RESTORATION

STREAM AND BUFFER AREA PROTECTION/RESTORATION STREAM AND BUFFER AREA PROTECTION/RESTORATION AMENDMENT OPTIONS TO STRENGTHEN POLICY IN HEADWATERS AREAS DRAFT SUBSEQUENT TO THE JANUARY 25, 2007 MEETING OF THE PLANNING COMMISSION ENVIRONMENT COMMITTEE

More information

Project Alignment Appendix A

Project Alignment Appendix A Project Alignment Appendix A Fargo Moorhead Metropolitan Area Flood Risk Management Project EA Document This page is intentionally left blank Project Alignment Appendix A Table of Contents 1 BACKGROUND...

More information

Engineering Construction Plan Design Standards

Engineering Construction Plan Design Standards Engineering Construction Plan Design Standards The following design standards are intended to provide a basis upon which all residential, commercial, industrial and multiple sites within the Charter Township

More information

ENGINEERING DESIGN STANDARDS

ENGINEERING DESIGN STANDARDS OCEOLA TOWNSHIP 1577 N. LATSON ROAD HOWELL, MICHIGAN ENGINEERING DESIGN STANDARDS Prepared by: TETRA TECH Brighton, Michigan February 2010 ODESIGN.DOC CONTENTS Page PART I. ENGINEERING DESIGN STANDARDS

More information